Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
PINS Ref: EN010061
The Proposed Ferrybridge Multifuel 2 (FM2) Order
Ferrybridge Power Station Site, Knottingley, West Yorkshire
Combined Heat and Power (CHP) Assessment
The Planning Act 2008
The Infrastructure Planning (Applications: Prescribed Forms and Procedure)
Regulations 2009
Regulation 5(2)(q)
Applicant: Multifuel Energy Limited
July 2014
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 (i)
Document History Document Number
Revision 6
Author Nigel Garrod ( Fichtner Consulting Engineers)
Signed Date 10/06/2014
Approved By Mark Shatwell (Fichtner Consulting Engineers)
Signed Date 10/06/20014
Document Owner Fichtner Consulting Engineers
Revision History
Revision No.
Date Reason for Revision Authorised By
1 20/12/2013 First draft for internal team review
Mark Shatwell (Fichtner Consulting Engineers)
2 03/04/2014 Updated following review Nigel Garrod (Fichtner Consulting Engineers)
3 15/05/14 Revised BAT justification Richard Lowe (URS)
4 28/05/2014 Revised following review Nigel Garrod (Fichtner Consulting Engineers)
5 04/06/2014 Revised following review Nigel Garrod (Fichtner Consulting Engineers)
6 10/06/14 Revised following review Nigel Garrod (Fichtner Consulting Engineers)
7 30/07/14 Final version Richard Lowe (URS)
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 (ii)
Glossary
ACC Air Cooled Condenser
BAT Best Available Technique
DCO Development Control Order
CCR Carbon Capture Ready
CCS Carbon Capture and Sequestration
CfD Contract for Difference
CHP Combined Heat and Power
CHPQA Combined Heat and Power Quality Assurance
CHPQI CHP Quality Index
CHP-R CHP-Ready
CO2 Carbon dioxide
DECC Department of Energy and Climate Change
DH District Heating
EA Environment Agency
EfW Energy from Waste
FM1 Ferrybridge Multifuel Power Station 1
FM2 Ferrybridge Multifuel Power Station 2
GCV Gross Calorific Value
IRR Internal Rate of Return
LEC Levy Exemption Certificate
MEL Multifuel Energy Limited
MWe Megawatt electrical
MWth Megawatt of thermal energy
MWhe Megawatt hour of electricity
MWhth Megawatt hour of thermal energy
NCV Net Calorific Value
NOx Nitrogen Oxides
NPS National Policy Statement
NPV Net Present Value
NRSWA New Roads and Street Works Act 1991
PES Primary Energy Savings
RHI Renewable Heat Incentive
ROC Renewable Obligations Certificate
RO Renewables Obligation
SSE SSE Generation Ltd
WDF Waste Derived Fuel
WMDC Wakefield Metropolitan District Council
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 (iii)
Contents
1. EXECUTIVE SUMMARY ......................................................................... 1
2. INTRODUCTION ..................................................................................... 4
3. COMBINED HEAT AND POWER (CHP) POLICY AND GUIDANCE ............................................................................................. 8
National Policy Statements for Energy ............................................................................. 8 DECC CHP Guidance ....................................................................................................... 9 EA CHP Ready Guidance - Combustion & Energy from Waste Plant ........................... 10 Local Planning Policy ...................................................................................................... 13 Policy and Guidance Summary ...................................................................................... 14
4. IDENTIFIED POTENTIAL HEAT USERS ............................................. 15
Introduction ..................................................................................................................... 15 Heat Load Estimation ..................................................................................................... 16 Heat Use Options ........................................................................................................... 16 Commercial Properties ................................................................................................... 16 Public Services Buildings................................................................................................ 18 Industrial Heat Users ...................................................................................................... 19 Residential Heat Users ................................................................................................... 20
5. HEAT EXPORT FEASIBILITY STUDY ................................................. 24
Heat Network Options ..................................................................................................... 24 Heat Network Demands and Profiles ............................................................................. 25 Heat Network Pipe Route ............................................................................................... 32 Design of Piping System................................................................................................. 33 Heat Capture Systems .................................................................................................... 36 Back-up heat source ....................................................................................................... 39 Thermodynamic Modelling Heat Balances ..................................................................... 40 EA CHP Ready Assessment Form ................................................................................. 41 CHP Envelope ................................................................................................................ 41 CHP Quality Index .......................................................................................................... 44 Sustainability ................................................................................................................... 46
6. FINANCIAL ASSESSMENT OF NETWORK OPTIONS ....................... 48
Financial Model Input Assumptions ................................................................................ 48 Capital Cost .................................................................................................................... 50 Operational and Maintenance Costs .............................................................................. 51 Results ........................................................................................................................... 52 Financial Study Sensitivity .............................................................................................. 53
7. BAT ASSESSMENT SUMMARY .......................................................... 54
First BAT test .................................................................................................................. 54 Second BAT test ............................................................................................................. 54 Third BAT test ................................................................................................................. 55
8. CONCLUSIONS .................................................................................... 56
9. REFERENCES ...................................................................................... 60
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 (iv)
Tables
TABLE 4.1 COMMERCIAL HEAT USERS .................................................... 18
TABLE 4.2 PUBLIC SERVICE HEAT USERS .............................................. 19
TABLE 4.3 INDUSTRIAL HEAT USERS ....................................................... 20
TABLE 5.1 SUMMARY OF HEAT NETWORK OPTIONS ............................. 25
TABLE 5.2 HEAT NETWORK PIPING .......................................................... 35
TABLE 5.3 ȠCHP AND PES FOR PIPE ROUTE CASES ............................. 44
TABLE 5.4 CHPQI CALCULATION .............................................................. 46
TABLE 5.5 CARBON DIOXIDE (CO2) AND NOX (AS NO2) SAVINGS WITH HEAT EXPORT (TONNES PER YEAR) ........................... 47
TABLE 6.1 CAPITAL COST .......................................................................... 51
TABLE 6.2 OPERATIONAL AND MAINTENANCE COST ........................... 52
Figures
FIGURE 5.1 – DAILY HEAT DEMAND PROFILE ........................................... 26
FIGURE 5.2 – SEASONAL HEAT DEMAND PROFILE .................................. 29
FIGURE 5.3 – HEAT EXTRACTION POINTS .................................................. 36
FIGURE 5.4 – CHP ENVELOPE ...................................................................... 43
Appendices
APPENDIX 1: PIPE ROUTE DRAWING .......................................................... 61
APPENDIX 2: HEAT USERS LIST .................................................................. 62
APPENDIX 3: THERMODYNAMIC MODELLING ........................................... 63
APPENDIX 4: SITE LAYOUT PLANT-CHP READY PLANT .......................... 66
APPENDIX 5: FM2 PLANT LOCATION AND SITE BOUNDARY ................... 68
APPENDIX 6: CHP-R GUIDANCE FORM ....................................................... 70
APPENDIX 7: ACTION PLAN .......................................................................... 78
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 1
1. EXECUTIVE SUMMARY
1.1. This CHP Assessment has been prepared in support of Multifuel Energy
Limited’s (the Applicant’s) application (the Application) for a Development
Consent Order (DCO) that has been made to the Planning Inspectorate
(PINS) under Section 37 of the Planning Act 2008 (the PA 2008).
1.2. The Application is for the construction and operation of a ‘multifuel’ power
station of up to 90 megawatts (MWe) gross output and associated
development (the Proposed Development) within the existing Ferrybridge
Power Station site. The Proposed Development is to be known as
‘Ferrybridge Multifuel 2 (FM2) Power Station’.
1.3. In line with the requirements of NPS EN-1, EN-3 and the Environment
Agency (EA) CHP Ready Guidance (2013), a CHP Assessment has been
prepared to support the application for Development Consent.
1.4. The CHP Assessment considered the supply of heat to potential users
within a 10 km radius of the Proposed Development and identified four
theoretically possible heat networks. Although it may be technically
feasible to supply up to 68 MWe of heat from the Proposed Development
on its own or from the combined capacity of both ‘Ferrybridge Multifuel 1
Power Station’ (FM1) and the Proposed Development, no economically
viable option was identified.
1.5. Based on the application of the Second BAT Test of the EA Guidance, the
amount of heat that could be extracted from the steam turbine without
reducing the efficiency below that of an equivalent non CHP-R plant, is
considered to be 20 MWth. This is based on the design of the FM1
development. In order to export more than 20MW th of heat, substantial
design changes would be required to the turbine which would compromise
the electrical efficiency of the Proposed Development, and is therefore not
considered to represent BAT for this installation.
1.6. FM1 is being built as ’CHP Ready‘ with a potential capacity to export up to
20 MWth of heat. The current design for the Proposed Development would
be able to supply a similar level of heat for export without affecting the
overall efficiency of the steam turbine. For this assessment, it has been
assumed that it would be more cost effective to supply the required heat
from the Proposed Development using FM1 as a back-up heat supply,
given it is part of the modified baseline scenario for the Proposed
Development. Using FM1 as a back-up heat source has a lower capital
cost than using dedicated gas boilers installed exclusively for that
purpose.
1.7. Having FM1 as a back-up only improves the IRR slightly over the base
case and it introduces additional operational complexities, as for example,
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 2
when the Proposed Development is offline for either programmed or
unprogrammed reasons, it is not possible to guarantee that FM1 will be
available, particularly as the two generating stations are being developed
by different commercial entities. This lack of certainty over the back-up
heat supply is considered likely to deter consumers from connecting to any
heat network associated with the Proposed Development. Also for several
of the potential scenarios considered, FM1 would not provide sufficient
back-up capacity, and additional boilers would still be likely to be required.
Therefore, it is considered necessary that at the detailed design stage for
the Proposed Development, any option for the use of FM1 heat export as
a back-up should be revisited. Depending on the outcome of the financial
and technical feasibility assessment undertaken at the detailed design
stage, dedicated gas boilers may be considered more suitable and reliable
to supply the back-up heat requirements.
1.8. Throughout this CHP assessment, it has been assumed that FM1 would
be used as a dedicated back-up where the heat demand is less than
20MWth. Where the heat requirement is more than 20 MWth, additional gas
boilers would be needed to supply the excess heat demand. It has been
assumed that where heat demand is less than 20 MWth FM1 would still be
configured to provide 20 MWth in order to ensure maximum benefit can be
obtained from FM1 in the future.
1.9. The costs and revenues associated with the construction and operation of
any CHP scheme, and the reduction in electrical revenue due to heat
export, have been assessed in this report. The estimated revenues from
heat sales were based on matching current gas heating costs. It was
found that none of the individual heat networks identified were
economically viable. Even when the scheme was scaled up to include the
three main potential networks together, to spread the cost of the heat
export plant and equipment across a wider base, the scheme was still not
determined to be economically viable.
1.10. Despite these initial findings, the Applicant will ensure that the Proposed
Development is designed to be ‘CHP Ready’ and sufficient space will be
preserved for CHP equipment in the future (Draft DCO Requirement 39).
This space will be confirmed at the detailed design stage but is estimated
to be approximately 450m2. The ability to extract steam from the turbine to
provide up to 20 MWth of heat will be maintained.
1.11. In addition, through Requirement 39, The Applicant will also carry out an
ongoing review of CHP potential, including:
Maintaining a dialogue with key heat users as set out in the
proposed action plan detailed in Appendix 7;
Instigate an action plan as outlined in Appendix 7 of this report;
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 3
Carrying out regular reviews to determine if there have been
sufficient changes in circumstances to warrant a new technical and
financial assessment; and
Re-visiting the technical and economic assessments at least every
5 years or when a change in circumstances warrants.
1.12. This CHP assessment demonstrates that the Proposed Development
meets the BAT tests outlined in the EA CHP Guidance and it therefore will
be designed and build as ‘CHP Ready’ to supply any identified viable heat
load of up to 20 MWth to allow for the future implementation of CHP should
the heat loads become economically viable.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 4
2. INTRODUCTION
2.1. This CHP Assessment has been prepared in support of Multifuel Energy
Limited’s (the Applicant’s) application (the Application) for a Development
Consent Order (DCO) that has been made to the Planning Inspectorate
(PINS) under Section 37 of the Planning Act 2008 (the PA 2008).
2.2. The Application seeks a DCO for the construction and operation and
maintenance of a new build ‘multifuel’ power station of up to 90 megawatts
(MWe) gross output and associated development (the Proposed
Development). The Proposed Development is known as Ferrybridge
Multifuel 2 (FM2) Power Station (hereafter referred to as FM2) and will be
located within the existing Ferrybridge Power Station site, Knottingley,
West Yorkshire.
2.3. The Proposed Development is a ‘Nationally Significant Infrastructure
Project’ (a NSIP), being for an onshore generating station with an average
gross electrical output in excess of 50MW (PA 2008 Section 15(2)(c)).
Where a NSIP is proposed, an application for Development Consent must
be made to PINS and approved by the relevant Secretary of State (SoS)
before the development can proceed.
2.4. The DCO, if granted, would be known as the ‘Ferrybridge Multifuel 2
(FM2) Power Station Order’.
The Background to the Proposed Development
2.5. The Proposed Development will be capable of producing low carbon
electricity through the use of waste derived fuels from various sources of
processed municipal solid waste, commercial and industrial waste and
waste wood. It will therefore make a positive contribution toward the UK
Government’s climate change commitments, in addition to increasing the
diversity and security of national electricity supply, while also reducing the
amount of waste that is sent to landfill.
2.6. A similar multifuel power station is already being constructed on land
within the Ferrybridge Power Station site. This project is known as
‘Ferrybridge Multifuel 1 Power Station’ (FM1) and was consented under
Section 36 of the Electricity Act 1989 in October 2011. It is anticipated
that FM1 will be fully operational from Q3 2015.
2.7. The level of interest received from potential fuel suppliers in relation to
FM1 has demonstrated that there is sufficient demand and fuel availability
for a second multifuel power station at Ferrybridge. This is one of the
reasons that has led to the Applicant’s decision to progress FM2.
The Applicant
2.8. The Applicant, Multifuel Energy Limited (MEL) is a 50:50 joint venture that
has been formed by SSE Generation Ltd (SSE) and WTI/EfW Holdings
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 5
Ltd, a subsidiary of Wheelabrator Technologies Inc. (WTI) to develop low
carbon electricity generating plant.
2.9. SSE is one of the UK’s leading energy companies and the largest non-
nuclear electricity generator, operating a diverse portfolio across the UK
and Ireland. A subsidiary of SSE owns and operates the Ferrybridge
Power Station site, which includes the operational Ferrybridge ‘C’ coal-
fired Power Station.
2.10. WTI is a leading developer, owner and operator of energy from waste
(EfW) facilities and has been established for over 37 years. WTI currently
owns and/or operates 21 energy facilities in the USA, 17 of which are EfW
facilities. It has also recently acquired part of a business in China that has
three operational plants and a further six under development.
2.11. The Applicant has an option agreement in place to enter into a lease for
the land within the Application Site (the proposed DCO ‘Order’ Limits) that
is within the control of SSE, while the draft DCO seeks the necessary
powers and authorisations in respect of the land that lies outside SSE’s
control.
2.12. Further information on the Applicant can be found by going to the FM2
project website: www.multifuelenergy.com/fm2.
The Application Site
2.13. The Application Site (the Order Limits) comprises almost entirely of land
inside the boundary of the Ferrybridge Power Station site and is entirely
within the administrative area of Wakefield Metropolitan District Council
(WMDC). The Ferrybridge Power Station site is situated between the
River Aire to the north and east and the A1(M) immediately to the west.
2.14. The Application Site itself extends to approximately 32 hectares (ha) and
consists primarily of land that originally formed part of the Power Station’s
former golf course, including land that is currently being used in
connection with the construction of FM1, in addition to other land (some of
which is outside the Power Station site) that may be required for electricity
grid and utilities connections.
2.15. A detailed description of all the Application Site and its location and
surroundings is provided in the ‘Application Site Description Document’
(Application Document Ref. No. 5.2), which forms part of the Application.
The Proposed Development
2.16. The Proposed Development comprises of the multifuel power station (the
generating station) and all of the elements that are integral to it, including
the fuel reception and storage facilities, combustion system, steam turbine
and emissions stack, amongst others, as well as associated and
supporting buildings, structures, plant and areas.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 6
2.17. In addition, it includes some ‘Associated Development’ connected with the
generating station as defined by Section 115(2) of the PA 2008. This
comprises of a new connection to the electricity grid network,
improvements to an existing access road and a new foul water connection.
2.18. The Proposed Development will also involve temporary works connected
with the construction phase such as contractors’ compounds and laydown
areas.
2.19. A detailed description of all the elements of the Proposed Development is
provided in the ‘Proposed Development Description Document’
(Application Document Ref. No. 5.3).
2.20. It is currently anticipated that (subject to a DCO being granted and a final
investment decision being made) work will commence on the Proposed
Development in Q4 of 2015, with construction expected to be completed
by Q2/Q3 of 2018. Subject to construction being completed within this
timescale, the multifuel power station would enter commercial operation in
Q4 2018.
The Purpose and Structure of this Document
2.21. This CHP Assessment has been prepared in order to comply with Section
4.6 of the ‘Overarching National Policy Statement for Energy (EN-1) (Ref.
1-2) and paragraphs 2.5.26 - 27 of the ‘National Policy Statement on
Renewable Energy (EN-3), which require developers advancing thermal
generating stations to consider the opportunities for CHP. The
Assessment will demonstrate that the Applicant has explored the potential
for the plant to operate in CHP mode, exporting heat to off-site users. It is
the Applicant’s ambition that the CHP potential for the Proposed
Development (as with FM1) is maximised. In order to maximise the CHP
potential the use of Best Available Techniques (BAT) for the Proposed
Development will be demonstrated by applying the three BAT tests as
outlined in the CHP Ready Guidance for Combustion and Energy
from Waste Power Plants (EA V1.0 February 2013) (Ref. 1-3).
2.22. The Proposed Development will be designed to be ‘CHP Ready’. The
combined capacity of both FM1 and the Proposed Development has been
considered jointly as part of the CHP study and identification of potential
users. FM1 is currently under construction and is due to be complete by
the end of 2014, when commissioning will commence. Full operation is
anticipated to commence from Q3 2015. FM1 is being built as ’CHP
Ready’ with a potential capacity to export up to 20 MWth of heat.
2.23. A further revision of this CHP assessment will take place following
completion of the detailed design of the Proposed Development, prior to
its construction. The revised assessment will be based on potential heat
loads agreed with the EA and the specific design of the plant.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 7
2.24. This CHP Ready Assessment comprises:
Section 1: Executive Summary of the CHP Assessment.
Section 2: This brief Introduction.
Section 3: The context and assessment methodology.
Section 4: The results of the search for CHP opportunities surrounding
the Proposed Development undertaken in line with the CHP Guidance.
Section 5: Investigations into heat network options. An evaluation of the
technical options available to the Applicant carried out based on estimated
identified heat demands.
Section 6: Financial assessment of the identified CHP network, an
evaluation of the financial options available to the Applicant carried out
based on the cost and revenues for the various heat network options
identified.
Section 7: Summary of the BAT Assessment process for CHP and CHP-R
in this CHP Assessment.
Section 8: Conclusions of the CHP Assessment.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 8
3. COMBINED HEAT AND POWER (CHP) POLICY AND GUIDANCE
3.1. The UK Government is committed to promoting the installation of CHP
wherever economical. This commitment to CHP is reflected in national
policy and guidance relating to energy infrastructure and also local
planning policy. This policy and guidance is outlined below.
National Policy Statements for Energy
3.2. The National Policy Statements (NPSs) for energy infrastructure form the
policy framework for applications for new generating stations of greater
than 50 MWe capacity in England and Wales. The NPS of most relevance
to the Proposed Development are the Overarching National Policy
Statement on Energy (EN-1) and the National Policy Statement on
Renewable Energy Infrastructure (EN-3).
3.3. Section 4.6 of EN-1 deals with the consideration of CHP. Paragraph 4.6.2
states that CHP is technically feasible for all types of thermal generating
stations, including nuclear, energy from waste and biomass.
Paragraph 4.6.3 goes on to state the use of CHP reduces emissions and
that the Government is therefore committed to promoting ‘Good Quality
CHP’, which denotes CHP that has been certified as highly efficient under
the CHP Quality Assurance programme.
3.4. Paragraph 4.6.5 recognises that to be economically viable as a CHP plant,
a generating station needs to be located close to industrial or domestic
customers with heat demands. The distance will though vary according to
the size of the generating station and the nature of the heat demand.
3.5. Paragraph 4.6.6 highlights that under guidelines issued by DECC in 2006,
any application to develop a thermal generating station under Section 36
of the Electricity Act 1989 must have either included CHP or contain
evidence that possibilities for CHP had been fully explored to inform the
Secretary of State’s (SoS) consideration of the application. The paragraph
goes on to confirm that the same principle now applies to any thermal
generating station that is the subject of an application for Development
Consent under the PA 2008 and that the SoS should have regard to
DECC’s guidance, or any successor to it, when considering the CHP
aspects of application for thermal generating stations.
3.6. Paragraph 4.6.7 states that:
“In developing proposals for new thermal generating stations,
developers should consider the opportunities for CHP from the very
earliest point and it should be adopted as a criterion when considering
potential locations for a project. Given how important liaison with
potential customers for heat is, applicants should not only consult
those potential customers they have identified themselves but also
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 9
bodies such as the Homes and Communities Agency (HCA), Local
Enterprise Partnerships (LEPs) and Local Authorities and obtain their
advice on opportunities for CHP. Further advice is contained in the
2006 DECC guidelines and applicants should also consider relevant
information in regional and local energy and heat demand mapping.”
3.7. Paragraph 4.6.8 goes on to state that to encourage proper consideration
of CHP, substantial additional weight should be given by the SoS to
applications incorporating CHP. If the proposal is for thermal generation
with CHP, the applicant should:
explain why CHP is not economically or practically feasible;
provide details of any future heat requirements in the area that the
station could meet; and
detail the provisions for ensuring any potential heat demand in the
future can be exploited.
3.8. Paragraph 4.6.10 states that if not satisfied with the evidence that has
been provided, the SoS may wish to investigate this with one or more
bodies such as the HCA, LEPs and Local Authorities. Furthermore,
(paragraph 4.6.11) should the SoS identify a potential heat customer that
has not been explored the applicant should be requested to pursue this. If
agreement cannot be reached with the potential customer, the applicant
should provide evidence demonstrating why this was not possible.
3.9. Paragraph 4.6.12 states that the SoS may wish to impose requirements
within any DCO to ensure that the generating station is ‘CHP Ready’ to
facilitate the potential future export of heat, should demand be identified.
3.10. NPS EN-3 reiterates the requirement of EN-1 to either include CHP or
present evidence in the application that the possibilities for CHP have
been fully explored (2.5.26 - 27).
DECC CHP Guidance
3.11. The requirements for the assessment of the feasibility of CHP in relation to
thermal generating stations are set out in the DECC (then DTI) Guidance
on Background Information to Accompany Notifications Under Section
14(1) of the Energy Act 1976 and Applications under Section 36 of the
Electricity Act 1989 (December 2006). Paragraph 8 states that the
Government expects developers to explore opportunities to use CHP fully,
including community heating, when developing proposals for new thermal
generating stations. However, it does recognise that in some cases CHP
will not always be an economic option.
3.12. Paragraph 9 goes on to state that the Government will expect developers
to submit information to demonstrate that they have seriously explored
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 10
opportunities for CHP, including community heating, and where this is
feasible that Good Quality CHP is provided. Paragraph 11 continues:
“Developers should therefore provide evidence to show the steps that
they have taken to assess the viability of CHP opportunities within the
vicinity of their proposed location for the plant. Their application
…should contain:
an explanation of their choice of location, including the potential
viability of the site for CHP;
a report on the exploration carried out to identify and consider the
economic feasibility of local heat opportunities and how to
maximise the benefits from CHP;
the results of that exploration; and
a list of organisations contacted.”
3.13. Paragraph 12 of the Guidance lists what must be included with
applications where CHP is not to be included. This includes:
the basis for the developer’s conclusion that it is not economically
feasible to exploit existing regional heat markets;
a description of potential future heat requirements in the area; and
the provisions in the proposed scheme for exploiting any potential
heat demand in the future.
3.14. Paragraphs 13 - 17 provide guidance on exploring opportunities for local
users to make use of heat. Developers should fully explore opportunities
for existing and likely local users of heat across a range of sectors,
including industry, housing and community users. They should also
engage with Government agencies, have regard to heat mapping and
contact regional and local bodies to identify potential heat users.
3.15. Paragraph 19 stresses that where heat opportunities have been identified,
developers should carry out detailed studies on the economic feasibility of
these. Paragraphs 20-22 provide further guidance on economic feasibility.
EA CHP Ready Guidance - Combustion & Energy from Waste Plant
3.16. The EA has recently published detailed guidance on CHP Readiness
Assessments as part of the Environmental Permitting regime.
3.17. The EA requires applications for Environmental Permits to demonstrate
Best Available Technology (BAT) for a number of criteria, including energy
efficiency. One of the principal ways of improving energy efficiency is
through the use of CHP. The EA therefore requires developers to satisfy
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 11
three BAT tests in relation to CHP. The first involves considering and
identifying opportunities for the use of heat off-site. Where this is not
technically or economically possible and there are no immediate
opportunities, the second test involves ensuring that the plant is built to be
‘CHP Ready’. The third test involves carrying out periodic reviews to see if
the situation has changed and there are opportunities for heat use off-site.
3.18. Where Development Consent is granted for a new plant without CHP, the
subsequent application for an Environmental Permit should build on the
conclusions of the CHP Assessment and contain sufficient information to
demonstrate the new plant will be built ‘CHP ready’ (for the chosen
location and design). The Environment Agency requires that:
“all applications for Environmental Permits for new installations
regulated under the Environmental Permitting (England and Wales)
Regulations 2010 demonstrate the use of Best Available Techniques
(BAT) for a number of criteria, including energy efficiency. One of the
principal ways in which energy efficiency can be improved is through
the use of Combined Heat and Power (CHP). With respect to the use
of CHP, there are three BAT tests which should be applied. These are
as follows:
First BAT Test:
The Environment Agency considers that BAT for energy efficiency for
new combustion power plant or Energy from Waste (EfW) plant is the
use of CHP in circumstances where there are technically and
economically viable opportunities for the supply of heat from the
outset.
The term CHP in this context represents a plant which also provides a
supply of heat from the electrical power generation process to either a
district heating network or to an industrial / commercial building or
process.
However, it is recognised that opportunities for the supply of heat do
not always exist from the outset (i.e. when a plant is first consented,
constructed and commissioned).
Second BAT Test:
In cases where there are no immediate opportunities for the supply of
heat from the outset, the Environment Agency considers that BAT is to
build the plant to be CHP-Ready (CHP-R) to a degree which is
dictated by the likely future opportunities which are technically viable
and which may, in time, also become economically viable.
The term ‘CHP-R’ in this context represents a plant which is initially
configured to generate electrical power only but which is designed to
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 12
be ready, with minimum modification, to supply heat in the future.
The term ‘minimum modification’ represents an ability to supply heat in
the future without significant modification of the original plant /
equipment. Given the uncertainty of future heat loads, the initial
electrical efficiency of a CHP-R plant (before any opportunities for the
supply of heat are realised) should be no less than that of the
equivalent non-CHP-R plant.
Third BAT Test:
Once an Environmental Permit has been issued for a new CHP-R
plant, the applicant/operator should carry out periodic reviews of
opportunities for the supply of heat to realise CHP. Such opportunities
may be created both by new heat loads being built in the vicinity of the
plant, and / or be due to changes in policy and financial incentives
which improve the economic viability of a heat distribution network for
the plant being CHP. “
3.19. The EA guidance reiterates the need for applications for Development
Consent involving generating stations to be supported by a CHP
Assessment in line with Section 4.6 of EN-1, which contains details on:
an explanation of their choice of location, including the potential
viability of the site for CHP;
a report on the exploration carried out to identify and consider the
economic feasibility of local heat opportunities and how to
maximise the benefits from CHP;
the results of that exploration; and
a list of organisations contacted.
3.20. and, if the proposal is for generation without CHP:
the basis for the developer’s conclusion that it is not economically
feasible to exploit existing regional heat markets;
a description of potential future heat requirements in the area; and
the provisions in the proposed scheme for exploiting any potential
heat demand in the future”.
3.21. The CHP-R Guidance states that:
“The primary focus of this CHP-R Guidance is on the demonstrations
required in an application for an Environmental Permit for new plants
under the Environmental Permitting (England and Wales) Regulations
2010. However, the principles contained within this CHP-R Guidance
may also have implications on consent applications (i.e. Planning
Permission (under the Town and Country Planning Act 1990) or a
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 13
DCO (under the Planning Act 2008)) for the new plant. Indeed, the
Environment Agency will be consulted on these applications, as well
as applications for extensions of / variations to existing plants.
The Environment Agency Document "Guidelines for Developments
requiring Planning Permission and Environmental Permits" sets out
the Environment Agency's role in the planning process and its
approach to responding to applications for developments which will
also require an Environmental Permit. In particular, these Guidelines
recognise that there may be some interdependencies between
planning and permitting requirements. In the case of such
interdependencies, the Guidelines recommend early engagement with
the Environment Agency via their planning pre- application service
and, in some cases, a "parallel- tracking" approach is recommended
whereby the preparation and submission of the planning and
permitting applications is carried out at the same time.
Therefore, it is recommended that this CHP-R Guidance (and the
requirements for CHP-R) is considered prior to making a consent
application for a new plant, in particular because the first and second
BAT tests may affect the layout, space requirements and building
design for the implementation of CHP. Accordingly, the Environment
Agency recommends that the requirement for new plants to be CHP or
CHP-R is discussed at the earliest possible stage, ideally during
planning pre-application. In any case, where a DCO is required the
applicant will have to make similar demonstrations under both the
planning and permitting applications in terms of suitability of the
location for CHP, potential opportunities for heat supply and CHP-R.
When consulted by the Planning Authorities on relevant consent
applications for new plants, the Environment Agency will highlight the
need for the plant to be CHP or CHP-R and will make reference to this
CHP-R Guidance. Where a DCO is required, the Environment Agency
will additionally comment on the results of the CHP Assessment.
The Environment Agency will not object to applications for new plants
where they are located in areas where there are no opportunities for
heat supply. However, where relevant, the Environment Agency will
highlight the lack of opportunities to the Planning Authorities and this
may influence the Planning Authority in its consideration of the
suitability of the proposed location.”
Local Planning Policy
3.22. The Application Site lies within the administrative area of Wakefield
Metropolitan District Council (WMDC).
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 14
3.23. Of relevance to this CHP Assessment is WMDC Core Strategy (2009)
Policy CS13 ‘Mitigating and Adapting to Climate Change and Efficient Use
of Resources’. Part 2b requires all development to incorporate energy
from decentralised and renewable, or low carbon sources.
3.24. WMDC Development Policies (2009) Policy D28 ‘Sustainable Construction
and Efficient Use of Resources’ encourages the use of CHP within the
district. The policy states:
“The Council will require that new development within the district shall
be energy and water efficient and incorporate built-in conservation
measures. Opportunities to conserve energy and water resources
through the layout and design of the development shall be maximised
[…] the Council will require where practical […] the use of solar
energy, passive solar gain and heat recycling (such as combined heat
and power)”
Policy and Guidance Summary
3.25. National policy clearly confirms the requirement for applications for
Development Consent involving thermal generating stations to consider
the scope to include CHP and for applications to be supported by an
assessment of this.
3.26. The above national and local policy and guidance have been taken into
account in undertaking this CHP Assessment for the Proposed
Development. Where relevant, this is referred to within the following
sections.
3.27. The EA CHP-R Guidance sets out a methodology for assessing the
technical and economic viability of CHP for a Proposed Development to
facilitate all new generating station developments being designed as CHP
Ready.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 15
4. IDENTIFIED POTENTIAL HEAT USERS
Introduction
4.1. A review of the potential heat demand within a 10 km radius of the
Proposed Development has been undertaken to assess potential known or
consented future developments that may require heat and to identify any
existing major heat consumers; i.e. to identify potential heat loads. This
enabled the initial design of proposed heat network options to be
developed. The potential heat loads have been identified using a review of
publicly available datasets on fuel use in the region - the UK CHP
Development Map1, DECC National Heat Map2, DECC Public CHP
Database, available OS data, satellite imagery and aerial photographs
from Google Maps and Microsoft Bing Mapping.
4.2. A number of potential heat users exist within a 10 km radius of the
Proposed Development, including private and public sector buildings.
Following granting of DCO consent and issue of the Environmental Permit,
the Applicant would be able to prepare Heads of Terms for agreement with
potential heat users, if economically viable to do so. No heat supply
agreements have yet been made by the Applicant, as without the
necessary planning consent and Environmental Permit, heat users are
unwilling to commit to commercial agreements for heat supply in our
experience, particularly when heat will not be available for several years.
4.3. A meeting was held with Wakefield Metropolitan District Council on 12th
March 2014 to discuss potential heat users which could theoretically
connect to a CHP scheme. Discussions have also been held in November
2013 with Wakefield Enterprise Partnership and potential heat users
during the development of the FM1 generating station. The outcomes of
these meetings have been taken into consideration when identifying
potential heat users within the study area. A copy of this report has been
sent to Wakefield Metropolitan District Council.
4.4. The technical suitability of connecting potential identified heat users to a
district heating system has been considered on the basis of maximising
carbon savings and delivering the highest Primary Energy Savings (PES).
Larger heat users and those closer to the Proposed Development have
been considered ahead of other users on the basis they are more likely to
produce an economically viable solution.
4.5. The EA CHP Ready Guidance for Combustion and Energy from Waste
Power Plants requires that the heat loads used in a CHP-R assessment
be agreed with the Environment Agency. At this stage, due to the number
1 http://chp.decc.gov.uk/developmentmap/
2 http://tools.decc.gov.uk/nationalheatmap/
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 16
of options under consideration and the potential scale of the number of
potential heat users, no consultation with the EA has taken place to date,
but discussions with the EA will take place as part of the Environmental
Permit application process. Once any preferred potential district heating
system configuration has been finalised the process of agreeing the heat
loads with the EA will be carried out.
Heat Load Estimation
4.6. The annual heat usage estimates have been based on the UK CHP
Development Map3, DECC National Heat Map4 and benchmark heat
usage values mainly derived from standardised figures from the Chartered
Institution of Building Service Engineers (CIBSE) Guide F (Energy
Efficiency in Buildings).
4.7. In the CIBSE Guide, commercial, educational, recreational and other loads
are expressed in terms of kWh (thermal) per square metre of floor space
per year of fossil fuel use (natural gas is typically assumed). Based on
estimates of floor areas and an assessment of the development type, it is
possible to estimate annual energy usage. Converting natural gas use to
actual heat loads (which might be provided by hot water distribution
systems) requires an assumption of gas-fired boiler efficiency. In this CHP
assessment, an efficiency of 85% is assumed, based on industry norms.
Floor areas for individual heat users have been estimated using
dimensioning tools on aerial photographs.
Heat Use Options
4.8. Industry, commerce, public services and residential developments are all
prospective users of heat from a CHP plant and these have been
considered in this assessment.
Commercial Properties
4.9. These can provide a wide range of CHP options. Typically, good targets
are office blocks, hospitals, hotels, leisure facilities and higher education
establishments. These tend to have reasonably high heat demands over
prolonged periods. Retail outlets and schools are typically not ideal targets
as their heat demands can be low, making economic returns difficult to
achieve unless they have large buildings. However, these facilities have
still been considered in conjunction with other heat users.
4.10. The Xscape Extreme Sport and Leisure Centre is adjacent to junction 32
of the M62 and could present a major heat load opportunity. This leisure
centre has a building covering 40,000 m2. The current compression
3 http://chp.decc.gov.uk/developmentmap/
4 http://tools.decc.gov.uk/nationalheatmap/
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 17
chillers use a relatively large amount of electricity, and the site
management are amenable to discussing installation of absorption chillers.
This is a relatively new development as it was opened in 2006 but by the
time district heating mains could be installed the equipment could be at
least 15 years old and it may be at a time when at least some of the
existing heating and cooling equipment is nearing the end of its service
life. There is also a water leisure facility proposed nearby, which would
require low grade heat.
4.11. For the purposes of this study, it is assumed that only 25% of the total
heat demand from this site could be provided by a district heating network.
This estimate is based on Fichtner’s previous knowledge and experience
on similar projects. It should be noted that much of the energy used by
Xscape is for refrigeration and it is not possible to replace this with district
heating.
4.12. Initial discussions were held between SSE and XScape site management
in 2012 about their interest in potential heat available from the FM1
development. However, the challenge of identifying a viable route across
the A1(M) motorway and through the conurbations between the site and
FM1, together with the state of the existing Xscape infrastructure, meant
that discussions have not progressed further.
4.13. There are a number of other commercial buildings near to the Proposed
Development which have high heat loads and are listed in Table 4.1
below. This table only includes existing buildings where heat loads can be
estimated. New or proposed developments will be considered as set out in
the proposed action plan given in Appendix 7.
4.14. The Carlton Lane shopping centre has been included as a potential heat
load but further investigation would be required. In multiple unit shopping
centres, the shop units are normally electrically heated and only the
common areas may be heated by a system that is compatible with a
district heating system. Retrofitting compatible systems to the shop units
would be prohibitively expensive.
4.15. Castleford Tigers are developing a new stadium in Glass Houghton. The
development, off M62 junction 32, would be on land between Stainburn
Avenue and Spittal Hardwick Lane on the opposite side of the junction
leading into Xscape. A public consultation, on dates yet to be confirmed,
will take place before a Planning application is submitted to Wakefield
Council. Subject to planning approval, construction could begin during
2015 and the new stadium would open for the 2017 season. This would be
a potential heat user for connection to the CHP scheme and further
discussions would be warranted following the granting of both the DCO for
the Proposed Development and the planning consent for the new stadium.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 18
Table 4.1 Commercial Heat users
Consumer
Number5
Name Post Code
Distance
to FM2
(km)
Estimated
Heat Demand
(MWhth/yr)
Estimated
Average
Annual Heat
Demand
(MWth)
1 Morrisons, Marine Villa Road WF11 8ER 2.8 218 0.02
2 Ferrybridge Business Park,
Ferrybridge Road
WF11 8NA 1.8 771 0.09
3 Caddick Construction WF11 8DA 5.0 63 0.01
4 Business park (10 units
considered off Common
Lane and Fernley Green
Road)
WF11 8DH 4.0 595 0.07
5 Carlton Lanes Shopping
Centre
WF10 1AL 4.3 1,208 0.14
6 Xscape Extreme Sport and
Leisure Centre
WF10 4TA 4.0 2,244 0.26
22 Green Lane Business Park WF7 6RA 7.3 34,252 3.91
25 Normanton Industrial Estate,
Pioneer Business Park,
Whitwood Entreprise Park,
Latitude Park, Whitwood
Freight Centre, Wakefield
Europort, Valencia Park
WF6 1RL 7.6 133,283 15.22
26 Savile Industrial Park,
Raglan Industrial Estate,
Acorn industrial Estate
WF10 1PB 5.1 19,360 2.21
Total 191,994 22
Public Services Buildings
4.16. WMDC has been consulted on the potential development of a heat
network with a positive response. Their estate could form a base load for a
district heating network, providing a good opportunity to extend the system
to both commercial and domestic users in the area, since many of the
public buildings are located along the main road routes within the area.
Like all local authorities, WMDC are looking at ways of reducing their
carbon footprint and connection to a district heating scheme offers the
opportunity for large carbon savings.
4.17. The buildings suitable for inclusion in this CHP assessment include:
5 See Appendix 1 and Appendix 2
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 19
primary schools (recognising schools are typically not ideal targets
as their heat demands can be low);
secondary schools (as above);
administrative buildings; and
leisure centres.
4.18. Table 4.2 below shows the public service buildings identified for inclusion
in this study.
4.19. The connection of any public sector building to a district heating network
would be subject to the appropriate procurement rules.
Table 4.2 Public Service Heat users
Consumer
Number6
Name Post Code
Distance to
FM2 Plant
(km)
Estimated
Heat
Demand
(MWhth/yr)
Estimated
Average Annual
Heat Demand
(MWth)
16 Knottingley Sport Centre/
Swimming Pool, Weeland
Road
WF11 8EE 2.6 3,054 0.35
17 Knottingley Social Club,
Weeland Road
WF11 8EE 2.6 155 0.02
18 Knottingley High School
and Sports College
WF11 0BZ 3.4 141 0.02
19 Castleford Schools WF10 3JU 1.8 3,709 0.42
20 Vale School, Ferrybridge
Road
WF11 8JF 2.2 161 0.02
21 Featherstone Technology
College
WF7 5AT 6.3 969 0.11
23 Purston Infant School WF7 5LF 7.0 107 0.01
24 North Featherstone
Junior and Infants School
WF7 6LW 5.9 229 0.03
Total 8,525 0.97
Industrial Heat Users
4.20. Table 4.3 shows the industrial heat users identified for inclusion in this
study. Many of the identified users are glassworks, which do not require
low grade heat or steam as they rely on natural gas-fired high temperature
furnaces, so while they are listed in Table 4.3, they are unlikely to provide
realistic heat loads.
6 See Appendix 1
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 20
4.21. Heat demand from Tradebe Solvent Recovery on Weeland Road was
estimated using the UK CHP Development Map. It is assumed that 25% of
the total heat demand from this site could be provided by a district heating
network as it is mostly a steam user which is currently produced by gas
boilers on site. This estimate is based on Fichtner’s previous knowledge
and experience on similar projects. During the project execution phase
contact will be made with Tradebe Solvent Recovery in order to determine
if they are a potential heat customer, and if so to confirm their heat
demand.
Table 4.3 Industrial Heat Users
Consumer
Number7
Name Post Code
Distance
to FM2
Plant
(km)
Estimated
Heat
Demand
(MWhth/yr)
Estimated
Average
Annual
Thermal Heat
Demand (MWth)
7 Tradebe Solvent
Recovery, Weeland
Road
WF11 8DZ 4.0 20,477 2.34
8 Allied Glass
Containers, Fernley
Green Road
WF11 8DH 3.8 149 0.02
9 Stolzle Flanconnage,
Weeland Road
WF11 8AP 3.4 253 0.03
10 Ardagh Glass, Spawn
Bone Lane
WF11 0HP 3.0 514 0.06
11 Siniat WF11 8UL 0.8 1,936 0.22
12 Tangerine
confectionery, Cott
Beverages and
Baileygate industrial
estate
WF8 2JS 2.5 22,338 2.55
13 Total Lubricants,
Ferrybridge Road
WF11 8JY 2.0 331 0.04
14 ADM Milling WF11 8HR 2.5 5,382 0.61
15 Plasmor Concrete WF11 0DL 4.0 22 0.00
Total 51,402 5.87
Residential Heat Users
4.22. Historically community heating in the UK has been difficult to implement.
This is mostly due to the existence of an extensive natural gas network
and a regulated energy supply market which allows customers the
7 See Appendix 1
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 21
freedom to change suppliers on a regular basis to obtain improved
commercial terms. The high cost of infrastructure is also a barrier to
community heating. Developers of private residential properties are
reluctant to utilise community heating as it often increases development
costs.
4.23. Community heating typically lends itself to situations where:
There is no alternative heating offered.
Scandinavian countries typically use community heating to great
success. This source of heat is accepted by the community, and
when new houses are built they are added to the existing networks.
This practice has not been used in the UK. The retrospective
installation of hot water mains and domestic heat exchangers is
expensive when compared to the continued use of gas, which is
reflected in the take-up rate. Clearly lower take-up rates increase
the costs for those included in a scheme.
There is a high heat density.
Areas of high population e.g. high rise flats are ideally suited to
communal heating as they provide a high heat load for a relatively
low number of connections, which improves the overall cost of a
scheme.
There is a high level of Local Authority / housing association
properties.
Single landlord arrangements can improve the take-up rate
significantly, improving the economics of a scheme.
4.24. Community heating schemes for housing are unlikely to be major heat
users. Typically they are less than 10 MWth with a very seasonal demand
and are therefore not normally considered independently for large scale
CHP schemes. Only new build developments of at least 2,000 dwellings
would be considered viable for a standalone system due to the capital
costs involved with the extensive heat distribution systems involved. This
is considered the minimum number of dwellings that would generate
sufficient revenue to justify the infrastructure costs required to supply heat
to multiple small heat users. New build residential properties are likely to
be constructed to high energy efficiency standards and will therefore
require low volumes of input energy.
4.25. Existing low rise residential properties are likely to be expensive to retrofit
heat interface units and heat metering. They also normally require
extensive distribution pipe networks. Some difficult to insulate properties
may be eligible for grant support under the Energy Company Obligation for
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 22
connecting to heat networks but the level of this support is currently
uncertain.
4.26. Social landlords considering community heating or connection to a wider
district heating scheme seek to achieve low energy prices as well as a low
carbon footprint. Providing affordable warmth is a key objective for social
landlords and this can restrict the heat price charged by a district heating
network operator and lower the rate of return.
4.27. Domestic housing in the form of multi-storey flats, particularly if they are in
groups can provide good heat loads if they use a wet heating system.
There are no suitable existing developments of this type within the search
area.
4.28. A search has been undertaken for proposed or consented large scale
residential development plans in the area using WMDC’s website. A plan
is in place for the regeneration of Castleford - the Castleford Growth
Delivery Plan - which includes the development of 3,000 additional homes,
spread out over different locations in Castleford. The construction of these
new homes has already started and will be completed before the
Proposed Development is operational. They are therefore not at this time
considered suitable for connection.
4.29. Following a meeting with WMDC, contact was made with a planning officer
responsible for a proposed housing development at Pontefract Road,
Knottingley by Gleeson Development Ltd and Warmfield Ferrybridge Ltd.
Although, there is no detailed information on the heat demand
requirements of this development that can be considered at this stage, it
will still be assessed as a potential heat user in the future once more
information becomes available on heat load and timescales for the
development.
4.30. Attempts were made to engage with Selby District Council and North
Yorkshire County Council regarding the potential for exploiting heat
exported from the Proposed Development. Requests to meet with the
appropriate officers were declined at this stage due to their high
workloads. A copy of this report has been sent to both Selby District
Council and North Yorkshire County Council. Any comments received will
be managed through the proposed action plan, see Appendix 7.
4.31. A copy of this report has also been sent to the Homes and Communities
Agency, Leeds City Region Enterprise Partnership and Wakefield
Enterprise Partnership. All comments received will be managed through
the proposed action plan, see Appendix 7.
4.32. Residential users have therefore not been considered further at this stage
for the reasons outlined above. In addition, heat revenue from residential
users can be more erratic due to vacancy rates, higher management costs
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 23
per connection and allowing residential users the ability to opt out at any
time from a district heating supply, so as to avoid a monopoly supply
situation.
4.33. However, should any larger, mixed use district heating scheme be rolled
out by WMDC, the opportunities of connecting residential users can be re-
examined, as in these circumstances the economics should become more
favourable.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 24
5. HEAT EXPORT FEASIBILITY STUDY
Heat Network Options
5.1. The design of any the heat network is the critical component in defining
the technical and financial viability of a district heating scheme. This
section seeks to review the various potential network options and heat
supply considerations that feed into the financial modelling based on the
estimated heat demands and physical constraints. The capital and
operational cost estimates are set out in Section 6.13 and 6.14.
5.2. As the identified heat users are located in different areas, four potential
pipe routes have been identified for exporting heat from the Proposed
Development, and if appropriate, also from FM1. These routes are
described below and include various combinations of existing heat users.
A map of these routes is provided in Appendix 1.
Pipe Route 1 delivers heat to the east of the Proposed
Development to business parks, public buildings and light industrial
users.
Pipe Route 2 delivers heat to the south of the Proposed
Development to business parks and schools.
Pipe Route 2A delivers heat to the users on pipe route 2 but within
5km of the Proposed Development.
Pipe Route 3 delivers heat to the west of the Proposed
Development to business parks and public buildings.
5.3. Table 5.1 below provides a breakdown of the network options with
combination of the identified networks, including the estimated heat
demands and length of the primary pipelines.
5.4. For this study it has been assumed that each network option would be
installed in its entirety and that no phasing would occur. It is not
uncommon for district heating systems to be installed over long periods of
time with the heat load growing as more consumers become available/
interested. However, this effect is very difficult to predict and usually
makes achieving an economically acceptable solution more difficult as it
front loads the development costs with revenues having to grow over long
periods. For this reason, phasing has not been considered in this
assessment.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 25
Table 5.1 Summary of Heat Network Options
Option Heat Consumers
Included8
Total annual
heat consumed
at point of use
(MWhth/yr)
Average heat
demand at
point of use
(MWth)
Peak Heat
Export at
Proposed
Development
boundary9
(MWth)
Length of
main pipe
required
(m)
1 1, 2, 3, 4, 7, 8, 9, 10,
11, 13, 14, 15, 16,
17,18, 20
34,200 3.91 5.5 3,300
2 12, 21, 22, 23, 24 57,900 6.63 13.8 9,700
2A 12 22,300 2.55 2.8 3,600
3 5, 6, 19, 25, 26 159,800 18.36 48.6 4,400
Combined Network Options
1+2A 1, 2, 3, 4, 7, 8, 9, 10, 11, 13, 14, 15, 16, 17, 18, 20, 12
56,500 6.46 8.3 3,600
1+2 1, 2, 3, 4, 7, 8, 9, 10,
11, 13, 14, 15, 16, 17,
18, 20, 12, 21, 22, 23,
24
92,100 10.54 19.3 9,700
1+2+3 1,2,3,4, 7, 8, 9, 10,
11, 13, 14, 15, 16, 17,
18, 20, 12, 21, 22, 23,
24, 5, 6, 19, 25, 26
251,900 28.9 67.9 9,700
Heat Network Demands and Profiles
5.5. Generic heat demand profiles were developed for seasonal and daily
changes in heat demand for each of the individual heat loads identified
based on the annual average demand. A combined heat demand profile
for each network option was then derived from a sum of the individual heat
load profiles of the network users. The indicative profiles are provided
below and show the variation in required heat capacity during a typical day
in different seasons for each pipe route option.
8 From section 4
9 This is the actual peak heat extracted from the Proposed Development which is estimated by taking
into consideration the pressure drop and heat loses through the pipe network.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 26
Figure 5.1 – Daily Heat Demand Profile
3.00
3.50
4.00
4.50
5.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 1
Winter Peak
Average
Summer Minimum
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 2
Winter Peak
Average
Summer Minimum
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 27
3.00
13.00
23.00
33.00
43.00
53.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 3
Winter Peak
Average
Summer Minimum
6.00
7.00
8.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 1+2A
Winter Peak
Average
Summer Minimum
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 28
5.6. The following figures show how the daily maximum heat capacity
requirement changes throughout the year for each pipe route option.
5.00
10.00
15.00
20.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 1+2
Winter Peak
Average
Summer
Minimum
10.00
20.00
30.00
40.00
50.00
60.00
70.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
dai
ly
Time (hours)
Pipe Route 1+2+3
Winter Peak
Average
Summer
Minimum
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 29
Figure 5.2 – Seasonal Heat Demand Profile
3.0
3.5
4.0
4.5
5.0
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 1
3.0
5.0
7.0
9.0
11.0
13.0
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 2
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 30
2.50
2.55
2.60
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 2A
3.0
8.0
13.0
18.0
23.0
28.0
33.0
38.0
43.0
48.0
53.0
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 3
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 31
6.00
7.00
8.00
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 1+2A
3.0
8.0
13.0
18.0
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 1+2
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 32
5.7. From the heat load assessment and the heat the profiles outlined above,
the estimated heat loads for each network option are shown in Table 5.1.
Heat Network Pipe Route
5.8. An indicative layout of the heat networks required to deliver heat to the
identified potential heat users was produced and is provided in Appendix 1
and 2. It should be stressed that this routing is indicative; a detailed
engineering assessment would be required to determine the optimum
route, which is not appropriate for this initial feasibility study.
5.9. The predominant engineering issue associated with the supply of heat by
hot water relates to the installation of the heat supply pipeline. The pipe
line required to supply hot water is likely to be a pair of large diameter
pipes which must be installed in a trench. Determining a feasible route for
such a pipeline is complex as outlined below.
5.10. On the Ferrybridge ’C’ Power Station site, existing cables and pipes may
obstruct the most direct route to end consumers. River, railway, motorway
and high voltage cable crossings may also be required which can prove to
be technically challenging and expensive. The operational needs of the
whole site would also need to be taken into consideration so as to avoid
conflict resulting in lost generation from the existing power station.
5.11. Outside the site a pipeline would need to be routed along public highways
with the inevitable issues of traffic management and avoiding other buried
utilities. These issues have a direct bearing on the cost and installation
time for any pipeline.
5.12. To install heat supply infrastructure, such as pre-insulated district heating
pipes, in the public highway, the Applicant would need to comply with the
3.0
8.0
13.0
18.0
23.0
28.0
33.0
38.0
43.0
48.0
53.0
58.0
63.0
68.0
January February March April May June July August September October November December
MW
(dai
ly m
axim
um
)
Time (months)
Pipe Route 1+2+3
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 33
requirements of the New Roads and Street Works Act 1991 (NRSWA).
This lays out the legal obligations that apply to both statutory and non-
statutory undertakers wishing to install apparatus in the public highway.
Failure to comply can lead to fines and/or an order to remove the
apparatus.
5.13. The provisions of the NRSWA do not apply to works carried out on private
land. As a non statutory undertaker, the Applicant would be required to
negotiate the route of any pipe line with relevant land owners, allowing for
access for construction and future maintenance. This will inevitably involve
legal negotiations over the structure of any wayleaves or easements, as
well as protective provisions for the operators of existing utilities and
infrastructure potentially affected by any pipeline.
5.14. The time taken to put in place the necessary permissions can be extensive
and must be factored into any heat delivery project timescales. It is not
unknown for a landowner to prolong the process as part of the negotiation
strategy to obtain a better deal.
5.15. Wayleaves and easements often come with an annual fee. This can, in
some cases, be high. In others it starts low but due to regular reviews can
become expensive. The landowners often recognise that the Applicant has
few other viable options and therefore can seek to maximise their position.
5.16. A major consideration with any proposed street works is the presence of
other utilities. Whilst newer installations will be well mapped there will be
older installations whose location is less certain. There will also be
abandoned or other out of service apparatus whose location is unknown.
5.17. The effect of other utilities can be very disruptive and potentially very
expensive. Whilst all utility companies will provide details of their
apparatus and in some cases mark locations, this does not remove the
risk of finding something uncharted or of damaging a live utility. The
resultant delays and cost can be significant.
Design of Piping System
5.18. As the potential heat users identified are a mix of commercial and
industrial facilities, it is acknowledged that the heat supply
requirements will not be the same for all users. To confirm the actual
demand profiles and supply conditions for each user would require further
extensive assessment. Therefore, for the purposes of this assessment it
has been assumed that a medium pressure hot water heat network, with
maximum flow temperature of up to 115°C and return of typically 75°C
would be adequate to supply all users. These are typical hot water
conditions for a district heating scheme. This assumption has been used
to estimate pipe diameters and heat losses.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 34
5.19. There may be heat users that require steam and are currently connected
to a steam distribution system within a site; this may result in a necessity
to invest in more supply works and complex integration within their site.
5.20. The main process constituents of a district heating scheme are:
primary heat station equipment at the point of supply;
secondary heat station equipment at the point of delivery; and
a flow and return pipe system circulating hot water between the
point of supply and the points of use.
5.21. The primary heat station would recover energy from the turbine and
transfers this to the hot water via a primary heat exchanger. Circulation
pumps would deliver this hot water to the secondary heat stations at the
end users and then return cooled water. Condensate return pumps in the
primary heat station would return the condensate from the primary heat
exchanger to the main condensate tank. FM1 and the Proposed
Development would have separate primary heat stations. The primary
heat station would be likely to comprise:
primary shell and tube heat exchanger(s);
condensate return pumps;
district heating circulation pumps;
pressurisation system;
heat meters;
back up boilers (if required); and
all other associated equipment.
5.22. The secondary heat station at the consumer would be likely to comprise a
plate heat exchanger which enables the exchange of energy from the hot
water to the heat user’s heating system. This is normally located within the
heat users’ boiler house but can be in other locations. The interface
connections between the heat network and building heating system will
typically comprise:
plate heat exchanger;
local controls;
heat meter;
flow isolation valve;
return isolation valve;
drain down point; and
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 35
electrical and control connections.
5.23. The district heating pipe sizes have been estimated based on the peak
heat demand from the Proposed Development turbine and adjusted to
make an allowance for heat losses through the system. The estimated
main pipe sizes for the network options are detailed in Table 5.2 below.
5.24. There are a number of European Standards covering the manufacture and
installation of pre-insulated district heating pipes although there are a
limited number of pipe suppliers. There are no UK manufacturers of
pre-insulated district heating pipe. Few UK contractors have experience of
installing this type of pipe in public highways but there are contractors with
good experience of installing utilities infrastructure who could manage
such a project. District heating pipeline installation is covered by BS EN
13941 - Design and installation of pre-insulated bonded pipe systems for
direct heating.
5.25. As the system is designed as flow and return, a single trench can be used
for both the flow pipes to the consumer heat stations, and return
pipes back to the plant. The minimum trench sizes are given for the
main distribution pipelines in Table 5.2 below. It should be noted that
10 This is the actual peak heat extracted from the FM2 plant turbine which is estimated by taking into
consideration the pressure drop and heat loses through the pipe network.
Table 5.2 Heat Network Piping
Options
Length of main
pipe required
(m)
Peak Heat Export
at FM2 boundary
(MWth)10
Main Pipe
Size
Main Pipe Trench
Size (mm)
1 3,300 5.5 DN200 1050 mm wide
1000 mm deep
2 9,700 13.8 DN250 1150 mm wide
1050 mm deep
2A 3,600 2.8 DN150 950 mm wide
950 mm deep
3 4,400 48.6 DN450 1550 mm wide
1250 mm deep
Combined Network Options
1+2A 3,300 8.3 DN200 1050 mm wide
1000 mm deep
1+2 9,700 19.3 DN250 1150 mm wide
1050 mm deep
1+2+3 4,400 67.9 DN450 1550 mm wide
1250 mm deep
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 36
trench depths may vary considerably due to the presence of existing
utilities and the nature of road construction.
Heat Capture Systems
5.26. Heat is typically supplied in the form of steam and/or hot water.
5.27. The supply of steam is limited by distance and safety considerations.
Piping steam over a long distance is usually expensive as mains have to
be oversized and heavily insulated to avoid loss of pressure or
temperature. Process steam users require steam at particular
temperatures and pressures, and failure to meet these conditions can
result in the process working ineffectively or not at all. Transporting steam
through public areas or under the public highway has particular health and
safety issues which can be difficult to resolve. It is likely that only on-site
operations at Ferrybridge would be suitable for the supply of steam. There
are currently no suitable significant heat users on-site.
5.28. Adjacent to the Ferrybridge ‘C’ Power Station site is a plasterboard
manufacturer, Siniat Ltd. Initial discussions were held between SSE and
Siniat Ltd in 2012 about their interest in potential steam available from the
FM1 development. However, the existing Siniat Ltd infrastructure is not
compatible with the proposed steam conditions, therefore discussions
have not progressed further.
5.29. Process steam for heat export is usually extracted via a bleed on the
turbine and piped to the steam user. Where steam is captured from the
user’s process and condensed, the condensate can be returned to the
power plant. However, care has to be exercised to avoid any
contamination being carried in the returned condensate to the power plant
boiler.
5.30. More typically for a district heating scheme heat is transported using hot
water. Steam from the turbine is usually used to produce this hot water via
a shell and tube heat exchanger, although there are other options for
recovering heat from the energy from waste plant.
5.31. For the Proposed Development layout, heat may be recovered from three
points. These are shown in the diagram below:
Figure 5.3 – Heat Extraction Points
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 37
5.32. 1) Condenser. Wet steam emerges from the steam turbine typically at
around 40°C. This energy can be recovered in the form of low grade hot
water from the condenser depending on the type of cooling implemented.
5.33. An air-cooled condenser (ACC) will be installed for the Proposed
Development, which has been agreed to represent BAT for the installation.
Steam is condensed in finned tubes with heat rejected from the steam into
the air flow. Since heat is rejected to the air rather than cooling water, an
ACC cannot be used directly to provide hot water. To recover heat, an
additional water cooled condenser must be used.
5.34. 2) Steam turbine. Steam extracted from the steam turbine can be used to
generate hot water for district heating schemes. District heating schemes
typically operate with a flow temperature of 90oC to 120oC and return
water temperatures of 50oC to 80oC. Steam is extracted from the turbine at
low pressure to maximise the power generated from the steam. The steam
is passed through a condensing heat exchanger, with condensate
recovered back into the feedwater system. Extracting steam in this way
reduces the electrical generation capacity of the generating station.
5.35. This source of heat offers the most flexible design for the facility. The
steam bleeds can be sized to provide additional steam above the plant’s
parasitic steam loads. However the size of the heat load will need to be
clearly defined to allow the steam bleeds and associated pipework to be
adequately sized. Increasing the capacity of the bleeds once the turbine is
installed is difficult.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 38
5.36. In accordance with the second BAT Test of the EA CHP Ready guidance,
this assessment assumes that, given the uncertainty of future heat loads,
the initial electrical efficiency of the CHP Ready Proposed Development is
to be no less than that of the equivalent non-CHP-R plant. The amount of
heat that could be extracted from the steam turbine without reducing the
efficiency below that of an equivalent non CHP-R plant, is considered to
be 20 MWth. This is based on the design of the FM1 development. In order
to export more than 20MWth of heat substantial design changes would be
required to the turbine which would compromise the electrical efficiency of
the Proposed Development, and is therefore not considered to represent
BAT. Therefore, the concept design of the plant assumes steam will be
extracted from the two lowest pressure uncontrolled bleeds on the turbine.
5.37. 3) Flue gas. Flue gas from the outlet of the flue gas treatment plant will
contain water in vapour form. This flue gas is proposed to be discharged
at around 140°C. It can be cooled further using a flue gas condenser to
recover the latent heat from the moisture. This heat can be used to
produce hot water for district heating. Similarly to the heat available from
the condenser, this does not affect the power generation from the plant
(there will however be a small increase in parasitic electrical load).
5.38. Condensing the flue gas can be achieved in a wet scrubber. However the
scrubber temperature is typically no more than 80°C, which restricts the
hot water temperature available for the customer. Alternatively a heat
exchanger can be used. This can provide higher hot water temperatures
although corrosion of the tubes can be an issue unless specialist materials
are used (such as PTFE tube bundles).
5.39. Additional cooling of the flue gas is likely to result in the frequent
production of a visible plume from the stack; although this is only water
vapour it can be wrongly be misinterpreted as pollution by the public. The
water condensed from the flue gas could be recycled with other process
effluent. However, if this is not possible it would need to be treated and
then discharged. Effluent discharges could be achieved through a trade
effluent discharge consent although this would need to be agreed with the
relevant parties.
5.40. At the current time it is considered that for the heat users identified, there
is only likely to be demand for hot water for use in wet heating systems
(typically in the region of 75°C to 115°C). It is proposed that this hot water
would be raised from steam from at least one turbine bleed point to
provide sufficient temperature. This method for the supply of heat is
considered to be favourable for the following reasons:
There are no obvious users within the immediate vicinity of the
plant for 30oC to 40oC hot water;
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 39
The use of a flue gas condenser will increase the risk of a visible
plume for significant periods of the year. This is not desirable as it
will add to the visual impact of the plant and as such has not been
considered;
The use of steam from the turbine offers the most flexibility for
allowing heat to be supplied to future developments.
Back-up heat source
5.41. At times, the Proposed Development will not be operating, such as during
routine maintenance outages. During these times, heat consumers will still
need heat. There is therefore a need, somewhere within the heat
distribution system, to provide a back-up source of heat to meet the needs
of consumers.
5.42. Depending on the heat load provided by the district heating system, the
standby plant could comprise oil or gas fired hot water heaters (boilers)
with a separate dedicated chimney stack.
5.43. For this CHP assessment, it has been assumed that FM1 will act as back-
up to any heat provision from the Proposed Development, supplying up to
20MWth, and that back-up boilers will only be required when both the
Proposed Development and FM1 are unavailable. Boilers have not been
considered to meet any of the peak heat demand. Back-up facilities would
be designed to ensure the maximum peak heat export capacity can be
met (without heat from the Proposed Development) but also provide
sufficient turndown to supply smaller summer loads with reasonable
efficiency.
5.44. As noted in the network options descriptions, the cost estimate for back-up
facilities has been included in the assessment in order to show the full
costs of a network and auxiliary requirements.
5.45. The planning consent and necessary approvals for any heat network and
back-up boilers are outside the scope of this DCO application and would
be subject to new planning applications and approvals. The visual and air
quality impact of any back-up boilers would need to be assessed as part of
any subsequent planning application.
5.46. Although FM1 and the Proposed Development will be on the same site,
FM1 will have a different commercial ownership and operational
management to the Proposed Development. FM1 has been considered to
be available as a dedicated back-up heat supply due to lower capital costs
than providing dedicated gas boilers at this stage. However, having FM1
as a back-up heat source only improves the IRR slightly and it presents
operational complexities. When the Proposed Development is offline for
either programmed or unprogrammed reasons, it is not possible to
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 40
guarantee that FM1 will be available. This lack of certainty over the back-
up heat supply would almost certainly deter consumers from connecting to
the heat network. Therefore, at the project execution phase of the
Proposed Development, this option will be re-evaluated. Depending on the
outcome of the financial and technical feasibility, dedicated gas boilers
may be considered more suitable and reliable to supply the back-up heat
requirements than the use of FM1.
5.47. The reliance on back-up boilers can be slightly reduced by the use of heat
accumulators. These can also be used to manage peak heat demand to
avoid the use of fossil fuelled peak lopping boilers. Heat accumulators can
be used to store excess heat generated during off-peak periods for supply
at times of peak heat demand (reducing the total installed capacity of plant
required). This decouples heat production from heat demand, improving
the operational flexibility of a CHP plant. Heat accumulators are effectively
large water tanks; as heat is absorbed the temperature rises and as heat
is extracted the temperature decreases.
5.48. Heat accumulators can specifically be used with CHP plants to allow
maximum electricity generation at times when heat demand is not as high
(by storing any excess heat generated). This enables CHP plants to
operate at times when revenue from electricity sales are highest and
allows the heat generated to be made available at a later time when
electricity revenue is not as favourable. In the case of the Proposed
Development it is anticipated that there will be no diurnal variation in
electricity price and therefore the effectiveness of a heat accumulator will
be minimal.
Thermodynamic Modelling Heat Balances
5.49. In order to assess the impact of heat export on the electrical output of the
plant, an accurate representation of the Proposed Development had to be
developed using Fichtner’s KPRO thermodynamic modelling software. The
basis of this model was the heat balance for FM1 combined with additional
heat balances provided by turbine suppliers for a controlled extraction
turbine. The FM1 heat balance is based on the actual detailed design of
FM1. This model was used to produce the CHP envelope discussed in the
“CHP Envelope” section below.
5.50. In order to assess the maximum amount of heat that could be exported
from the plant, a steam turbine with a controlled pressure extraction at 2.1
bar(a) was modelled. This model was based on the optimum technical
configuration that would be used if DH was economically viable from the
outset. A controlled pressure extraction means that the pressure at the
extract remains constant for varying steam flow. This is particularly
important at high steam extraction volumes. This allows steam to be
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 41
extracted at the lowest pressure possible (limited by the required hot water
flow temperature) and means that extraction flow is not limited by the
increase in pressure ratio across the upstream blades. Provided the
extraction port and pipework are sized correctly, up to 80% of the inlet
steam flow can be extracted through a controlled extraction. The actual
allowable steam extraction quantities will need to be confirmed with
potential turbine suppliers at the detailed design stage.
5.51. However, installing a steam turbine with controlled extraction would
reduce power output by approximately 200 kWe when no heat is exported
compared to a non-CHP ready installation. It would also cost an additional
€500,000. In line with the second BAT test of the EA CHP Ready
Guidance, the initial electrical efficiency of a CHP-Ready plant has to be
no less than that of the equivalent non-CHP Ready plant. Therefore, at
this stage in the plant design, the use of controlled extraction has been
discounted. BAT is considered to be the use of a standard steam turbine
with uncontrolled extractions, as this maintains the electrical efficiency of
the Proposed Development. Based on experience from the FM1
development, this will limit the maximum heat export to 20MWth.
5.52. The Z ratio, which is the ratio of the reduction in power export for a given
increase in heat export, was calculated from the KPRO model to be 5.0.
This Z ratio could therefore be used to calculate the reduction in power
generated when assessing the economic viability of the different network
options presented in section 6. This ratio is dependent on the grade of
heat required. A high Z ratio will produce the highest primary energy
saving and lowest loss of electricity generation.
EA CHP Ready Assessment Form
5.53. This report undertakes a CHP-R Assessment which considers the
requirements of the EA’s CHP-R Guidance. The completed CHP-R
Assessment Form can be found in Appendix 6.
CHP Envelope
5.54. To allow any identified and additional future CHP opportunities to be
realised, the design (and final build) of the Proposed Development will
incorporate the required provisions to allow for the potential future
implementation of CHP. Accordingly, the Proposed Development will be
designed and built as CHP Ready and a space will be preserved for CHP
equipment. The size of this space will be dictated by the likely future
opportunities which are technically viable and which in time may become
economically viable. It is estimated that a minimum area of 450 m2 will be
required within the turbine hall and this will be confirmed through detailed
design. Space will be maintained for the duration of the Proposed
Development, which is sufficient for a 20 MWth heat station. This will be
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 42
secured through a DCO requirement and added to the technical
specification. It is considered that this is an appropriate solution given the
potential uncertainty surrounding the identified and future CHP
opportunities.
5.55. The “CHP Envelope” as outlined under requirement 2 of the CHP-R
guidance, which identifies the potential operational range of a new plant
where it could be technically feasible to operate electrical power
generation with heat generation, is provided in Figure 5.4.
5.56. The points defining the envelope are as follows:
A: Minimum Stable Load (with no Heat Extraction)
B: Minimum Stable Load (with maximum Heat Extraction)
Line A to B: The minimum electrical power output for any given
heat load (corresponds to the minimum stable plant load).
C: 100% Load (with maximum Heat Extraction)
D: 100% Load (with no Heat Extraction)
Line D to C: The maximum electrical power output for any given
heat load (corresponds to 100% plant load).
E: Proposed operational point of the plant
Unrestricted Operation: If a selected heat load is located in this
region, the plant will have the ability to operate at any load
between minimum stable plant load and 100% plant load whilst
maintaining the selected heat load.
Restricted Operation: If a selected heat load is located in this
region, the plant will not have the ability to operate over its full
operational range without a reduction in heat load.
5.57. The CHP efficiency (ƞCHP) can be defined as:
ƞCHP = (Net Process Heat Output + Net Power Output) / Fuel Heat
Input
5.58. It should be noted that the “CHP Envelope” should not be considered as
definitive, and the operational range for the Proposed Development will
ultimately be subject to the required hot water flow temperature and steam
turbine design.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 43
Figure 5.4 – CHP Envelope
5.59. Heat balance diagrams for each of the thermodynamic models at the
points in the above “CHP Envelope” are provided in Appendix 3.
5.60. Primary Energy Saving (PES) and CHP efficiency (ƞCHP) for operating
cases for each network option on line D to E and E to C in the CHP
Envelope are shown in the table below.
DCHPƞ=30%
PES=0%E
CHPƞ=37.2%PES=4.7%
CCHPƞ=70.2%PES=18.4%
ACHPƞ=26.4%
PES=0%
BCHPƞ=63.1%PES=10.4%
Unrestricted Operation Restricted Operation
-
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0
Ele
ctri
cal
Po
we
r O
utp
ut
(MW
)
Heat Load (MW)
100% Plant Load MSL 50% Plant Load Proposed Operational Point
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 44
Table 5.3 ƞCHP and PES for pipe route cases
Pipe Route
Average heat
demand at point
of use (MWth)
ƞCHP
(%)
(NCV basis)
PES11
(%)
No heat export 0.0 30.0%
1 3.91 31.3% 0.4%
2 6.63 32.2% 0.8%
2A 2.55 30.9% 0.1%
3 18.36 36.2% 2.9%
1+2 10.54 33.5% 1.4%
1+2A 6.46 32.2% 0.8%
1+2+3 28.9 39.7% 4.5%
CHP Quality Index
5.61. CHPQA (Combined Heat and Power Quality Assurance) is an Energy
Efficiency Best Practice Programme initiative by the UK Government.
CHPQA aims to monitor, assess and improve the quality of UK Combined
Heat and Power. In order to prove that a plant is a Good Quality CHP
plant, the Quality Index (QI) is calculated. The QI for CHP schemes is a
function of their heat efficiency and power efficiency according to the
following formula:
QI = X power + Y heat
where:
power = power efficiency
heat = heat efficiency
5.62. The power efficiency is calculated using the gross electrical output, and is
based on the gross calorific value of the input fuel. The heat efficiency is
also based on the gross calorific value (GCV) of the input fuel. The
coefficients X and Y are defined in the CHPQA Guidance Notes based on
the total gross electrical capacity of the scheme and the fuel/technology
type used.
11 Primary Energy Saving(PES) is calculated based on a formula taken from the EA’s CHP-R
Guidance
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 45
5.63. The CHP QI can be used to obtain a CHPQA Certificate for a facility,
which enables it to be eligible for a Government incentives for energy
exported. In order for a facility to obtain a Government incentive payment
on all of the electricity or heat exported from the plant (proportional to the
biogenic content of the fuel), the QI must be equal to or greater than 100
during operation and 105 during design stage. If the QI is less than 100,
then only a portion of the energy exported will be eligible for support. If the
QI is above 100 during the operational phase of the facility no additional
incentive payment will be received beyond that obtained for a QI of 100.
This can act as a disincentive to increase heat load above that required to
achieve a QI of 100.
5.64. On 21st December 2012, the Government released a consultation
document entitled “Renewable Combined Heat and Power Schemes –
Review of Qualification Criteria: Consultation on proposals to amend the
calculation of CHP Quality Index for renewable CHP schemes.” The
consultation closed on 8th March, 2013. The Government response to the
consultation was issued on July 2013. One of the amendments following
the consultation is to change the X and Y values used within the CHPQI
formulae. The consultation response states that this is to ensure schemes
which receive Government support are supplying significant quantities of
heat and delivering intended energy savings.
5.65. As a result of the consultation, a safeguard provision was also introduced
such that all CHP schemes that meet a specified minimum heat efficiency,
overall efficiency and primary energy saving criteria are guaranteed a
Quality Index of 100. For a scheme over 25 MWe electrical capacity, the
criteria are as follows:
heat efficiency ≥ 10%;
overall efficiency ≥ 35%; and
primary energy savings (PES12) ≥ 10%.
5.66. In addition to the introduction of the safeguard provision support for district
heating has been provided by reducing the qualifying CHPQI from 100 to
95 for the first five years of operation. This has been introduced to
recognise the fact that district heating schemes can often take a number of
years to become established.
5.67. The CHPQI values for the different heat network options assessed for the
Proposed Development were calculated and the results are shown in
Table 5.4.
12 Calculation method for PES in CHPQA is different to one in EA CHP-R Guidance. CHPQA follows
the method in Annex 3 of Directive 2004/8/EC of The European Parliament and of the Council.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 46
Table 5.4 CHPQI calculation
Cases
Average heat
demand at
point of use
(MWth)
Gross
Electrical
Efficiency
(GCV basis)
Heat Efficiency
(GCV basis) CHPQI
No heat export 0.0 29.3% 0.0% 102.6
1 3.91 29.0% 1.5% 103.3
2 6.63 28.8% 2.5% 103.9
2A 2.55 29.1% 0.9% 103.1
3 18.36 27.9% 6.8% 106.4
1+2 10.54 28.5% 3.9% 104.7
1+2A 6.46 28.8% 2.4% 103.8
1+2+3 28.9 27.0% 10.7% 108.5
5.68. The table above confirms that for all of the potential heat network options
a CHPQI score in excess of 100 would be achieved. It would therefore not
be necessary to rely on the safeguard provision to be classified as ‘Good
Quality’ CHP.
Sustainability
5.69. High-level calculations have been performed to estimate the potential
carbon dioxide (CO2) emissions saving predicted for the Proposed
Development when in CHP mode. These are the savings due only to the
displacement of individual heat generating plant at each heat consumer as
these emissions sources will cease to exist. A sustainability assessment
for the Proposed Development is presented in Chapter 17 of the
Environmental Statement (Application Document Ref. No. 6.2). Table 5.5
demonstrates the results for each pipe network option described above.
5.70. The Proposed Development will save carbon dioxide and NOx emissions
for every heat export scenario assessed, by displacing the equivalent
fossil fuel fired heat generating plant. It has been assumed that the
displaced heat generating plant is fuelled by natural gas.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 47
Table 5.5 Carbon Dioxide (CO2) and NOx (as NO2) Savings with heat
export (tonnes per year)
Cases
Base Case
with no heat
export
Pipe
Route 1
Pipe
Route 2
Pipe
Route 2A
Pipe Route
3
CO2 Saving from Heat
Generated (tonnes) 0 6,506 10,959 4,210 29,154
NOx saving from Heat
generated (tonnes) 0 3.2 5.3 2.0 14.2
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 48
6. FINANCIAL ASSESSMENT OF NETWORK OPTIONS
6.1. In order to assess the commercial feasibility of any potential CHP scheme
a financial model was developed. The financial model took into account:
capital costs;
operational and maintenance costs for the heat network;
revenues from the sale of heat; and
the reduction in electricity revenue due to the reduction in electricity
produced by the Proposed Development as a result of exporting heat.
It did not consider any other running costs or administrative costs
associated with operation of the Proposed Development. The purpose of
the model was to determine the Internal Rate of Return (IRR) for each
identified network option.
Financial Model Input Assumptions
6.2. Revenue from any CHP scheme would come from various sources. The
financial assessment considered revenue from heat sales and was not
inclusive of revenue from any Government incentives e.g. Renewable
Obligation Certificates (ROC), Contract for Difference (CfD) or Renewable
Heat Incentive (RHI) values. The timescale for construction of the
Proposed Development means it will not be completed before ROCs are
withdrawn in April 2017. The current uncertainty over the levels of support
available from CfD or RHI means it is not possible to make a reasonable
estimate of the long term income available from Government support. Any
incentive payment would be based on the biogenic proportion of the input
fuel, which for the Proposed Development is likely to be no more than
50%.
6.3. Typically, it is currently expected that waste derived fuel has a biogenic
content of 50%, although it is recognised that the UK market is changing
and the biogenic fraction could reduce over time due to the national
requirement to remove organic content from the front end of waste
processing. Therefore not all of the energy output from the Proposed
Development would necessarily attract any subsidy. The input fuel will be
subject to an OFGEM approved continuous testing regime. A reduction in
biogenic proportion would reduce revenues from any Government
incentives. To date no facility processing municipal solid waste or waste
derived fuel has secured approval to receive Government incentives.
6.4. The financial model only considered the commercial feasibility of the CHP
scheme, not of the Proposed Development as a whole, which is outside
the consideration of this report.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 49
6.5. For the purposes of this report it has been assumed that there will be no
benefits from potential Enhanced Capital Allowances or from a reduction
in Business Rates. For a facility of this magnitude determining any such
potential benefit is highly complex and is considered to be outside of the
scope of this study.
6.6. Payment due from renewable energy Levy Exemption Certificates (LECs)
has been separated from the electricity price and considered as lost
revenue. It has also been assumed that 90% of the LECs sale value would
be received by the applicant. This assumes that some of the market value
of a LEC is retained by the licensed electricity supplier, so only a
proportion of the value is received by the generator.
6.7. The financial parameters considered in the financial assessment are
detailed below.
Assumed lost power value: £52.40/MWhe (2014)
Value of Levy Exemption Certificate: £5.24/LEC (2013/14)
Proportion of LECs received: 90%
Assumed gas price: £28.28/MWhth (2014)
Assumed heat price: £33.27/MWhth (2014)
Assumed heat price from FM1: £11.42/MWh (2014)
6.8. The heat and lost power price has been derived from the current
commercial gas and electricity prices based on DECC’s data13. The gas
price has been converted to an output energy unit price, to provide a
benchmark competitive price for the energy supplied. The unit gas price
for district heating users has been estimated at £28.28/MWhth. If a
reasonable boiler efficiency of 85 % is applied, the output energy unit price
will be £33.27/MWhth.
6.9. FM1 heat price is derived by assuming that FM1 will be revenue neutral.
Therefore, the total lost power revenue per mega watt hour has been
divided by the Z ratio to determine a heat price.
6.10. All of the cost and revenue prices such as capital and operational costs,
power price, heat price and LEC price have been indexed at RPI which
has been estimated at 2.5% over the project life. The starting point for
indexation is 2014.
6.11. A 10 year project life in the financial model was assumed for this CHP
assessment. This is based on the premise that it will be difficult to secure
13 Data was taken from “https://www.gov.uk/government/publications/updated-energy-and-emissions-
projections-2013”and https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/254831/Annex-f-price-growth-assumptions-2013.xls
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 50
heat supply contacts in excess of 10 years and that the energy market
could change significantly over a long period. It is assumed that heat
supply contracts will either be renewed or replaced and that the heat load
will remain constant over a longer period, but that the commercial terms
would almost certainly change. There is no guarantee that the assumed
level of market penetration can be sustained over a term longer than 10
years.
Capital Cost
6.12. The capital cost of any heat network would depend on several factors, the
main ones being the type, length and size of the pipe work required and
physical barriers or constraints to be overcome in the network route.
These factors have been considered at a high level to estimate the capital
cost of the network, but it must be emphasised that this costing is
indicative at this stage and would need to be reviewed as more detailed
information becomes available. The market has not been approached at
this stage to validate any of the estimated costs, so there is a risk that the
actual prices may be higher than the estimated prices. Wherever possible,
capital costs have been based on information from similar projects or the
Fichtner internal database.
6.13. The network capital costs for the individual networks are summarised in
Table 6.1 below. For the other options, which include the combination of
the individual networks, capital costs would typically be scaled up to
include all four networks, to spread the cost of the heat export plant and
equipment across a wider base, and these scaled up costs have been
used in the financial model.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 51
Table 6.1 Capital Cost
Pipe Route
1
Pipe Route
2
Pipe Route
2A
Pipe Route
3
District Heating pipework equipment
& installation (inclusive of traffic
management and licensing costs)
£7,815,000 £14,015,000 £3,722,000 £22,797,000
Primary Heat station equipment &
installation £1,178,000 £1,778,000 £733,000 £2,904,000
Secondary heat stations equipment
& installation £1,014,000 £1,297,000 £446,000 £2,174,000
Back up system including
installation and commissioning £1,482,000 £1,871,000 £1,210,000 £5,106,000
Additional cost for steam turbine
controlled extraction option
£420,000 £420,000 £420,000 £420,000
Total £11,909,000 £19,381,000 £6,531,000 £33,401 ,000
Operational and Maintenance Costs
6.14. Operational and Maintenance costs for the entire district heating network
have been estimated based on Fichtner’s experience of similar CHP
projects. The market has not been approached for actual quotations and if
the scheme progresses more accurate figures would need to be obtained.
So, at this time, there is a risk that the actual prices may be higher or
lower than the estimated prices.
6.15. The annual Operational and Maintenance costs for the individual networks
are detailed in the table below.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 52
Table 6.2 Operational and Maintenance Cost
Pipe
Route 1
Pipe
Route 2
Pipe
Route 2A
Pipe
Route 3
Maintenance
Primary Heat Exchanger area inspection
and maintenance £8,000 £12,000 £5,000 £21,000
FM1 Heat station inspection and
maintenance £9,000 £9,000 £9,000 £57,000
DH pipe routine inspection £5,000 £5,000 £5,000 £5,000
DH pipe leak detect system £5,000 £5,000 £5,000 5,000
Secondary Heat Exchanger Inspect and
controls check £9,000 £9,000 £9,000 £9,000
Heat meter calibration check £9,000 £9,000 £9,000 £9,000
Maintenance Subtotal £45,000 £49,000 £42,000 £106,000
OPEX
Treatment Chemicals £6,000 £6,000 £6,000 £6,000
Pumping Cost £24,000 £40,000 £15,000 £105,000
Back up boiler running costs £34,000 £58,000 £22,000 £519,000
Total £109,000 £153,000 £85,000 £736,000
Results
6.16. The financial model has been run for each of the heat network options
presented in Section 5 (Table 5.1).
6.17. The financial model estimates are based on pre tax Internal Rate of
Return (IRR) over a 10 year period. The capital cost of the district heating
equipment has also been depreciated over a 10 year period.
6.18. From the financial modelling none of the route options or combinations of
routes provided a positive rate of return. Therefore none of the options
considered provides an economically viable solution.
6.19. It is important to recognise that some of the input assumptions for the
financial model such as gas prices and electricity prices can be quite
volatile; if gas prices fall, the IRR would reduce further. This issue could be
exacerbated if electricity prices also rose during such a period.
6.20. Based on the application of the Second BAT Test of the EA Guidance, the
amount of heat that could be extracted from steam turbine without
reducing the efficiency below that an equivalent non CHP-R plant is
considered to be 20 MWth. This configuration matches the peak heat
demand of pipe route 1 + 2. This heat export configuration, without the
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 53
built in controlled steam extraction, has been modelled to confirm it does
not produce a positive rate of return.
Financial Study Sensitivity
6.21. A sensitivity analysis on the CHP financial model has been carried out in
order to investigate the impact of varying the following input parameters;
Electricity price14: Low price (as defined in Annex F of the Updated
energy and emissions projections: 2013);
Capital Cost: decrease by -10%;
Heat Revenue: increase by +10%;
As the base case for each pipe route option considered was not
economically viable, only parameters that would improve the outcome
have been considered for the sensitivity analysis. As pipe route option 3
produced the best initial results, the sensitivity analysis has been confined
only to this option.
6.22. The Renewables Obligation has not been considered in the sensitivity
analysis as the timescale for construction of the Proposed Development
means it will not be completed before ROCs are withdrawn in April 2017.
6.23. CfD and RHI potentially could make a district heating scheme
commercially viable if the biogenic content of the WDF was in excess of
50%. However, there are high risks of changes to the currently proposed
tariff figures and eligibility criteria including the qualifying biogenic content
of the WDF. Therefore any potential income from government incentives
has been discounted at this time.
6.24. The sensitivity analysis concluded that neither a decrease in capital cost;
an increase in heat revenue; or a lower electricity price, sufficiently
improves the IRR to provide an economically viable CHP scheme for pipe
route option 3. In addition, when combining any two of the possible
improvement parameters, the IRR still does not reach an acceptable level.
Combining the effect of all three possible improvement parameters has not
been carried out as it is considered that it is highly unlikely that all three
could occur together. Although each sensitivity case produced a positive
IRR, none were high enough to justify an economic investment when
considering the technical and financial risks associated with a major CHP
scheme.
14 https://www.gov.uk/government/publications/updated-energy-and-emissions-projections-2013
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 54
7. BAT ASSESSMENT SUMMARY
7.1. The EA CHP Guidance states that the EA requires applications for
Environmental Permits to demonstrate Best Available Technology (BAT)
for a number of criteria, including energy efficiency. One of the principal
ways of improving energy efficiency is through the use of CHP. The EA
therefore requires developers to satisfy three BAT tests in relation to CHP.
The first involves considering and identifying opportunities for the use of
heat off-site. Where this is not technically or economically possible and
there are no immediate opportunities, the second test involves ensuring
that the plant is built to be ‘CHP Ready’. The third test involves carrying
out periodic reviews to see if the situation has changed and there are
opportunities for heat use off-site.
7.2. The EA CHP Guidance BAT Requirements have been fulfilled for the
Proposed Development as outlined in this section:
First BAT test
7.3. The Proposed Development will not be operated as a CHP plant at the
outset of commercial operation as no economically viable opportunities for
the supply of heat have been identified to date. A financial model has been
developed to assess the commercial feasibility of a potential CHP scheme
as presented in Section 6. The results of the financial assessment indicate
that none of the four identified individual heat networks identified in this
report are economically viable. Even when a potential CHP scheme was
scaled up to theoretically include all four networks together, to spread the
cost of the heat export plant and equipment across a wider base, the
scheme was still not economically viable.
Second BAT test
7.4. The Proposed Development will be built to be ’CHP Ready' for the
identified loads as there are no immediate economically viable
opportunities for the supply of heat from the outset. The final heat export
capacity provided will be determined at detailed design stage and will
reflect the load potential available at that time. This will ensure that the
Proposed Development is designed and built to allow for the future
implementation of CHP when the identified or potential future heat loads
become economically viable.
7.5. In accordance with the second BAT Test of the EA CHP Ready guidance,
this assessment assumes that, given the uncertainty of future heat loads,
the initial electrical efficiency of the CHP Ready Proposed Development is
no less than that of the equivalent non-CHP-R plant. Therefore, the
concept design of the plant assumes steam will be extracted from the two
lowest pressure bleeds on the turbine via an uncontrolled extraction. To
install a steam turbine with controlled steam extraction at higher pressure
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 55
would reduce the electrical efficiency of the Proposed Development and
would increase its capital cost and is therefore not considered to represent
BAT in the absence of immediate opportunities for the supply of heat.
This limits the available supply of heat from the Proposed Development to
around 20 MWth, which is consistent with that available from the FM1 plant
under construction.
7.6. The “CHP Envelope” for the Proposed Development has been identified to
demonstrate that it will meet the identified heat loads within its likely
operational profile. The CHP Envelope demonstrates that the annual
average heat loads of each identified heat network options are within the
operational ranges of the Proposed Development. Therefore, it is
technically feasible to operate Proposed Development to supply the
identified annual average heat loads.
7.7. Sufficient space will be allocated for a 20 MW heat station within the
turbine hall. Routes for district heating pipelines within the boundary of the
site will be maintained (DCO Draft Condition 39(2)). The Proposed
Development will not be brought into commercial use until the planning
authority has confirmed in writing that it is satisfied that sufficient space
has been provided and that there are suitable routes for the pipelines
(DCO Draft Condition 39(1)).
Third BAT test
7.8. Once the Proposed Development is operating as a CHP Ready plant, the
Applicant will also carry out an ongoing review of CHP potential, including:
Maintaining a dialogue with key heat users as set out in the proposed
action plan given in Appendix 7;
Instigate an action plan as outlined in Appendix 7of this report;
Carrying out regular reviews to determine if there have been sufficient
changes in circumstances to warrant a new technical and financial
assessment; and
Re-visiting the technical and economic assessments at least every 5
years or when a change in circumstances warrants.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 56
8. CONCLUSIONS
8.1. In line with the requirements of NPS EN-1 and EN-3 and the EA CHP
Ready Guidance, this CHP Assessment has been undertaken to support
the application for a DCO and meet the BAT requirements of the CHP
Ready Guidance.
8.2. In accordance with the second BAT Test of the EA CHP Ready guidance,
this assessment assumes that, given the uncertainty of future heat loads,
the initial electrical efficiency of the CHP Ready Proposed Development is
to be no less than that of the equivalent non-CHP-R plant. The amount of
heat that could be extracted from the steam turbine without reducing the
efficiency below that an equivalent non CHP-R plant, is considered to be
20 MWth. This is based on the design of the FM1 development.
8.3. This CHP assessment demonstrates that the Proposed Development
meets the BAT tests outlined in the EA CHP Ready Guidance. It therefore
will be designed and built as ‘CHP Ready’ to supply any identified viable
heat load up to 20 MWth. This will allow for the future implementation of
CHP as and when the identified heat loads become economically viable.
8.4. A meeting was held with WMDC on 12th March 2014 to discuss potential
heat users which could be suitable to connect to a CHP scheme.
Discussions have also been held in November 2013 with Wakefield
Enterprise Partnership and potential heat users during the development of
the FM1 generating station. The outcomes of these meetings have been
taken into consideration when identifying potential heat users within the
study area.
8.5. The CHP Assessment has indicated that there are a number of potential
heat users within a 10 km radius of the Proposed Development including
private and public sector buildings. These include:
A total commercial annual average heat load of approximately 22 MWth;
A total public services annual average heat load of approximately
1.0 MWth;
A total industrial annual average heat load of approximately 5.9 MWth.
8.6. Therefore, there is a range of potential CHP opportunities within a 10 km
radius of the Proposed Development. In addition, future CHP opportunities
could be identified in the event that the Proposed Development is
consented and moves towards construction and operation.
8.7. To allow any identified and additional future CHP opportunities to be
realised, the design (and final build) of the Proposed Development will
incorporate a number of defined features which will allow for the future
implementation of CHP. Accordingly, it will be designed and built to be
CHP Ready. This will be secured as per a Requirement in the DCO. It is
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 57
considered that this is an appropriate solution given the current uncertainty
(and thus absence of economic feasibility) surrounding the identified and
future CHP opportunities.
8.8. Within this CHP Assessment, four theoretical pipe routes have been
identified for exporting heat from the Proposed Development, and where
necessary from FM1. These routes include various combinations of
existing heat users. A map of these routes is provided in Appendix 1.
Pipe Route 1 with a peak heat demand of 5.1 MWth and an annual
average heat demand of 3.9 MWth;
Pipe Route 2 with a peak heat demand of 13.2 MWth and an annual
average heat demand of 6.6 MWth;
Pipe Route 2A with a peak heat demand of 2.6 MWth and an annual
average heat demand of 2.6 MWth;
Pipe Route 3 with a peak heat demand of 47.8 MWth and an annual
average heat demand of 18.4 MWth.
8.9. Based on the evaluation undertaken, at the current time it is considered
that there is only likely to be demand for hot water for use in wet heating
systems (typically in the region of 75oC to 115oC). It is proposed that this
hot water would be raised from steam from at least one turbine bleed point
to provide sufficient temperature, without requiring major design changes.
This will be confirmed during the detailed design stage.
8.10. The peak heat load demands at the point of supply have been calculated
by taking into consideration the heat losses through the system.
8.11. The main process constituents of a district heating scheme are:
primary heat station equipment at the point of supply;
secondary heat station equipment at the point of delivery; and
a flow and return pipe system circulating hot water between the point of
supply and the points of delivery.
8.12. Throughout this CHP Assessment, it is assumed that FM1 would be used
as a dedicated back-up where the heat demand is less than 20MWth, as it
is part of the modified baseline of the Proposed Development. Where the
heat requirement is more than 20 MW th, additional gas boilers would
supply any additional demand. It is assumed FM1 will always be
configured to provide 20 MWth of thermal output.
8.13. A thermodynamic model of the Proposed Development has been
developed in order to present an accurate representation of the
Development, assess the impact of heat export on the electrical output
and to produce the CHP envelope, which identifies the potential
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 58
operational range of a new plant where it could be technically feasible to
provide electrical power generation with heat generation for export.
8.14. The CHPQA QI values for the different heat network options assessed for
the Proposed Development were calculated. The results show that for all
of the potential heat network options a QI score in excess of 100 would be
achieved.
8.15. High-level calculations have been performed to estimate the carbon
dioxide (CO2) and the oxides of nitrogen (NOx) emissions savings
predicted for the Proposed Development when in CHP mode. The
Proposed Development would save carbon dioxide and nitrogen oxide
emissions for every heat export case assessed by displacing the
equivalent fossil fuel fired heat generating plant.
8.16. A financial model has been generated to assess the commercial feasibility
of a potential CHP scheme. The financial model took into account capital
cost, the operation and maintenance costs and revenues associated with
the heat network itself, and changes in electricity revenue due to the
reduction in electricity produced by the Proposed Development. It did not
consider any other running costs or administrative costs associated with
operation of the Proposed Development. The financial model therefore
only considered the commercial feasibility of the CHP scheme, not of the
Proposed Development as a whole, which is outside the consideration of
this report.
8.17. The financial assessment only considered revenue from heat sales and
was not inclusive of potential revenue from any Government incentives
e.g. Renewable Obligation Certificates (ROC), Contract for Difference
(CfD) or Renewable Heat Incentive (RHI) values. The timescale for
construction of the Proposed Development means it will not be completed
before ROCs are withdrawn in 2017. The current uncertainty over the
levels of support available from CfD or RHI and any associated
qualification criteria mean it is not possible to make a reasonable estimate
of the long term sustainable income available from Government support.
8.18. The financial model results show that none of the heat network options
provide an acceptable Internal Rate of Return (IRR). Even when the
scheme was scaled up to include all three main identified pipe routes, a
positive return was not achieved. It is important to recognise that some of
the input assumptions for the financial model such as gas prices and
electricity prices can be quite volatile; if gas prices fall, the IRR would
reduce further. This issue could be exacerbated if electricity prices also
rose during such a period.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 59
8.19. A number of sensitivities were examined which confirmed that the
economic viability is highly susceptible to the volatility of the input
assumptions.
8.20. Despite these initial findings that the CHP scheme is not financially
feasible, the Applicant will ensure that the Proposed Development is
designed to be ‘CHP Ready’ and a space will be preserved for CHP
equipment to be installed in the future. This space will be dictated by the
future opportunities which are technically viable and which in time may
become economically viable.
8.21. The Applicant will also carry out an ongoing review of CHP potential,
including:
Maintaining a dialogue with key heat users as set out in the proposed
action plan given in Appendix 7;
Instigate an action plan as outlined in Appendix 7of this report;
Carrying out regular reviews to determine if there have been sufficient
changes in circumstances to warrant a new technical and financial
assessment; and
8.22. Re-visiting the technical and economic assessments at least every 5 years
or when a change in circumstances warrants.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Fichtner Consulting Engineers July 2014 Page 60
9. REFERENCES
Ref. 1-1 Planning Act 2008
Ref. 1-2 Overarching Energy National Policy Statement EN-1
Renewable Energy Infrastructure National Policy Statement
EN-3
Ref. 1-3 CHP Ready Guidance for Combustion and Energy from
Waste Power Plants; Environment Agency, V1.0; February
2013
Ref. 1-4 Environmental Impact Assessment for a proposed Multifuel
Power Station; 2009; URS.
Ref. 1-5 Environmental Statement – 2011 Addendum for a proposed
Multifuel Power Station; 2011; URS
Ref. 1-6 CHPQA Guidance Notes
Ref. 1-7 Renewable Combined Heat and Power Schemes – Review of
Qualification Criteria: Consultation on proposals to amend the
calculation of CHP Quality Index for renewable CHP schemes
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited Date: July 2014 Page 61
APPENDIX 1: PIPE ROUTE DRAWING
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 62
APPENDIX 2: HEAT USERS LIST
Consumer
Number Name Post Code Distance to FM2 Plant
1 Morrisons, Marine Villa Road WF11 8ER 2.8km
2 Ferrybridge Business Park, Ferrybridge Road WF11 8NA 1.8km
3 Caddick Construction WF11 8DA 5km
4 Business park (10 units considered off Common Lane and Fernley Green Road) WF11 8DH 4km
5 Carlton Lanes Shopping Centre WF10 1AL 4.3km
6 Xscape Extreme Sport and Leisure Centre WF10 4TA 4km
7 Tradebe Solvent Recovery, Weeland Road WF11 8DZ 4km
8 Allied Glass Containers, Fernley Green Road WF11 8DH 3.8km
9 Stolzle Flanconnage, Weeland Road WF11 8AP 3.4 km
10 Ardagh Glass, Spawn Bone Lane WF11 0HP 3km
11 Siniat WF11 8UL 0.8km
12 Tangerine confectionery, Cott Beverages and Baileygate industrial estate WF8 2JS 2.5km
13 Total Lubricants, Ferrybridge Road WF11 8JY 2km
14 ADM Milling WF11 8HR 2.5km
15 Plasmor Concrete WF11 0DL 4km
16 Knottingley Sport Centre/ Swimming Pool, Weeland Road WF11 8EE 2.6km
17 Knottingley Social Club, Weeland Road WF11 8EE 2.6km
18 Knottingley High School and Sports College WF11 0BZ 3.4km
19 Castleford Schools WF10 3JU 1.8km
20 Vale School, Ferrybridge Road WF11 8JF 2.2km
21 Featherstone Technology College WF7 5AT 6.3km
22 Green Lane Business Park WF7 6RA 7.3km
23 Purston Infant School WF7 5LF 7km
24 North Featherstone Junior and Infants School WF7 6LW 5.9km
25 Normanton Industrial Estate, Pioneer Business Park, Whitwood Entreprise Park, Latitude
Park, Whitwood Freight Centre, Wakefield Europort, Valencia Park
WF6 1RL 7.6km
26 Savile Industrial Park, Raglan Industrial Estate, Acorn industrial Estate WF10 1PB 5.1km
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 63
APPENDIX 3: THERMODYNAMIC MODELLING
See separate attachment for a better resolution of the following models
A3.1 Base case – Two boilers in operation no heat export
A3.2 Two Boilers in operation – maximum heat export
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 64
A3.3 Two Boilers in operation – 20 MWth heat export
A3.4 One Boiler in operation – no heat export
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 65
A3.5 One Boiler in operation – maximum heat export
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 66
APPENDIX 4: SITE LAYOUT PLANT-CHP READY PLANT
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 67
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 68
APPENDIX 5: PROPOSED DEVELOPMENT LOCATION AND SITE BOUNDARY
A5.1 - Location Plan
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 69
A5.2 - Site Installation Boundary
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 70
APPENDIX 6: CHP-R GUIDANCE FORM
# Description Unit
s Notes / Instructions
Requirement 1: Plant, Plant Location and Potential Heat Loads
1.1 Plant Name Ferrybridge Multifuel 2 (FM2)
1.2 Plant Description
The Proposed Development is a Multifuel Power Station
with a capacity of up to 90 MWe gross output (circa 70 MWe
net output), capable of producing low carbon electricity and
heat through waste derived fuel (WDF) from various
sources of processed municipal solid waste (MSW),
commercial and industrial waste and waste wood. It is
expected that power will be exported to the distribution
network. The nominal capacity of the facility will not exceed
675,000 tonnes per annum (tpa) of fuel based on an
average calorific value (CV) of 12 MJ/kg. Fluctuations in the
fuel Net Calorific Value (NCV) may vary the annual waste
throughput, but this will not exceed 675,000 tpa of waste
derived fuel.
The plant will have two combustion lines, employing
reciprocating grate technology, with steam fed to a single
steam turbine. Steam from the turbine exhaust will be
condensed in an Air Cooled Condenser (ACC).
1.3 Plant Location
(Postcode / Grid Ref)
The Proposed Development Site consists of land owned
by SSE within the Ferrybridge Power Station complex,
located at Stranglands Lane, Knottingley, West
Yorkshire, WF11 8SQ. The development will be centred
on Grid Reference 447250, 425345 and is shown in Figures
1.1 and 1.2 of Appendix 5 of this CHP Assessment.
1.4
Factors Influencing
Selection of Plant
Location
The selection of the site for the Proposed Development is
directly related to the presence of the FM1 plant under
construction to the immediate south of the Site. The
reasons for the selection of Ferrybridge ‘C’ for the
Ferrybridge Multifuel Power Station 1 (FM1) included its
location in relation to the fuel sources available in
Yorkshire, availability of existing supporting infrastructure
including connection to the national grid and availability of
water supplies, excellent road links and availability of rail
links, access to a pool of skilled labour for operations and
maintenance, solid record of environmental compliance at
the Ferrybridge ‘C’ power station and site remediation
issues to be addressed at the other sites considered in the
region. These reasons (as set out in the Environmental
Statement for FM1 (Ref. 1-4 and Ref. 1-5) still apply for the
Proposed Development. And there have been no changes
to the alternative sites considered that would change the
conclusions reached during that process. The proximity to
FM1 allows shared use of key infrastructure (such as the
upgraded rail link and gantry crane), and greater leverage
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 71
for key contracts such as fuel supply.
The location within the Ferrybridge Power Station
complex adjacent to the FM1 facility has been selected
for a number of reasons, including:
allocation of the Site by the Local Planning Authority for development associated with power generation;
previously used land within the Ferrybridge Power Station site is available for development;
limited existing constraints and services crossing the available site that would require diversion, demolition or relocation; and
planned reduction in generating capacity at the Site through closure of part of Ferrybridge ‘C’ Power Station.
As such, sites outside of the Ferrybridge Power Station
complex have not been reconsidered as alternative
locations for the Proposed Development.
There are a number of options available in relation to
the specific location of plant within the DCO (Application
Site) boundary, and the layout of the plant. The EIA process
has informed decision making regarding the specific
location and layout of the plant and the decision making
process will be described in full in the Environmental
Statement.
More factors that have been used to select the location of
the plant is given below:
There are likely potential for CHP opportunities around the applicant site. For more details, please refer to Sections 4 and 5 of this report.
There is a sufficient land capacity for the Proposed Development as in shown in Figure 1.2 of Appendix 5 of this report.
The Application Site consists primarily of land that originally formed part of the Power Station’s former golf course, including land that is currently being used in connection with the construction of FM1, in addition to other land (some of which is outside the Power Station site) that may be required for utility connections.
A detailed description of the Application Site and its surroundings is provided within the Application Site Description Document (Application Document Ref. 5.2).
The application site is chosen by taking into consideration the policies of the relevant Local Plan(s) and the NPPF together with other relevant planning considerations. For more details, please see Section 3 of this report.
CHP provisions contained within the relevant Planning documents.
The application site is chosen by taking into consideration Environmental factors such as proximity to sensitive receptors including: Air Quality Management Areas (AQMAs); and
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 72
Statutory Designated Sites (and the likely presence of Protected Species). More details will be in the Environmental Statement.
There is an existing connection point to the national Grid Electricity Transmission System within the Ferrybridge ‘C’ Power Station, and it has an available capacity for export to the Electricity Transmission System.
Proximity to / availability of fuel source is described in the Environmental Statement.
There is no cooling water requirement for the Proposed Development.
CCS is not applicable.
1.5 Operation of Plant
a) Proposed Operational
Plant Load % 100
b)
Thermal Input at
Proposed Operational
Plant Load
MW 234.8
c)
Net Electrical Output
at Proposed
Operational Plant
Load
MW 70.5 (Best case assumed for maximum CHP benefit)
d)
Net Electrical
Efficiency at Proposed
Operational Plant
Load
% 30.0 (Best case assumed for maximum CHP benefit)
e) Maximum Plant Load % 100
f) Thermal Input at
Maximum Plant Load MW 234.8
g)
Net Electrical Output
at Maximum Plant
Load
MW 70.5
h)
Net Electrical
Efficiency at Maximum
Plant Load
% 30.0
i) Minimum Stable Plant
Load % 50 (one boiler in operation at 100%)
j)
Thermal Input at
Minimum Stable Plant
Load
MW 117.4
k)
Net Electrical Output
at Minimum Stable
Plant Load
MW 28.9
l)
Net Electrical
Efficiency at Minimum
Stable Plant Load
% 23.7
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 73
1.6 Identified Potential
Heat Loads
68 MW District Heating.
Details of identified heat loads can be found in section 5 of
this report.
1.7 Selected Heat Load(s)
a)
Category
(e.g. Industrial /
District Heating)
District Heating.
b) Maximum Heat Load
Extraction Required MW 20
1.8
Export and Return
Requirements of Heat
Load
a) Description of Heat
Load Extraction Hot water
b) Description of Heat
Load Profile
Variable load.
Detailed heat load profiles can be found in section 0 of this
report.
c) Export Pressure bar a 10
d) Export Temperature °C 115
e) Export Flow t/h 1449
f) Return Pressure bar a 6
g) Return Temperature °C 75
h) Return Flow t/h 1449
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 74
Requirement 5: Integration of CHP and Carbon Capture
5.1 Is the Plant required to be CCR? No
5.2 Export and Return Requirements
Identified for Carbon Capture
100% Plant Load
a) Heat Load Extraction for Carbon
Capture at 100% Plant Load MW N/A
b) Description of Heat Export (e.g.
Steam / Hot Water)
N/A
c) Export Pressure bar a N/A
d) Export Temperature °C N/A
e) Export Flow t/h N/A
f) Return Pressure bar a N/A
g) Return Temperature °C N/A
h) Return Flow t/h N/A
i) Likely Suitable Extraction Points N/A
Minimum Stable Plant Load
j)
Heat Load Extraction for Carbon
Capture at Minimum Stable Plant
Load
MW N/A
k) Description of Heat Export (e.g.
Steam / Hot Water)
N/A
l) Export Pressure bar a N/A
m) Export Temperature °C N/A
n) Export Flow t/h N/A
o) Return Pressure bar a N/A
p) Return Temperature °C N/A
q) Return Flow t/h N/A
r) Likely Suitable Extraction Points N/A
5.3 Operation of Plant with Carbon
Capture (without CHP)
a) Maximum Plant Load with Carbon
Capture %
N/A
b) Carbon Capture Mode Thermal
Input at Maximum Plant Load MW
N/A
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 75
c)
Carbon Capture Mode Net
Electrical Output at Maximum
Plant Load
MW
N/A
d)
Carbon Capture Mode Net
Electrical Efficiency at Maximum
Plant Load
%
N/A
e) Minimum Stable Plant Load with
CCS %
N/A
f)
Carbon Capture Mode CCS
Thermal Input at Minimum Stable
Plant Load
MW
N/A
g)
Carbon Capture Mode Net
Electrical Output at Minimum
Stable Plant Load
MW
N/A
h)
Carbon Capture Mode Net
Electrical Efficiency at Minimum
Stable Plant Load
%
N/A
5.4 Heat Extraction for CHP at 100%
Plant Load with Carbon Capture
a)
Maximum Heat Load Extraction at
100% Plant Load with Carbon
Capture
[H]
MW
N/A
b)
Maximum Heat Extraction Export
Flow at 100% Plant Load with
Carbon Capture
t/h
N/A
c)
Carbon Capture and CHP Mode
Net Electrical Output at 100%
Plant Load
MW
N/A
d)
Carbon Capture and CHP Mode
Net Electrical Efficiency at 100%
Plant Load
%
N/A
e)
Carbon Capture and CHP Mode
Net CHP Efficiency at 100% Plant
Load
%
N/A
f)
Reduction in Primary Energy
Usage for Carbon Capture and
CHP Mode at 100% Plant Load
%
N/A
5.5
Heat Extraction at Minimum
Stable Plant Load with Carbon
Capture
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 76
a)
Maximum Heat Load Extraction at
Minimum Stable Plant Load with
Carbon Capture
MW
N/A
b)
Maximum Heat Extraction Export
Flow at Minimum Stable Plant
Load with Carbon Capture
t/h
N/A
c)
Carbon Capture and CHP Mode
Net Electrical Output at Minimum
Stable Plant Load
MW
N/A
d)
Carbon Capture and CHP Mode
Net Electrical Efficiency at
Minimum Stable Plant Load
%
N/A
e)
Carbon Capture and CHP Mode
Net CHP Efficiency at Minimum
Stable Plant Load
%
N/A
f)
Reduction in Primary Energy
Usage for Carbon Capture and
CHP Mode at Minimum Stable
Plant Load
%
N/A
5.6
Can the Plant with Carbon
Capture supply the Selected
Identified Potential Heat Load
(i.e. is the Identified Potential
Heat Load within the ‘CHP and
Carbon Capture Envelope’)?
N/A
5.7
Description of Potential Options
which could be incorporated in the
Plant for useful integration of any
realised CHP System and Carbon
Capture System
N/A
Requirement 6: Economics of CHP-R
6.1 Economic Assessment of CHP-R
In order to assess the commercial feasibility of
the CHP scheme a financial model was
developed.
Details of the Economic assessment of CHP-R
is in section 6 of this CHP Assessment.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 77
BAT Assessment
Is the new plant a CHP plant at
the outset (i.e. are there
economically viable CHP
opportunities at the outset)?
No.
Details of Economic assessment of CHP-R is in
section 6 of this CHP Assessment.
If not, is the new plant a CHP-R
plant at the outset? Yes
Once the new plant is CHP-R, is it
BAT?
Yes
Periodic reviews of opportunities for heat supply
will be carried out once the plant becomes
operational.
An action plan will be implemented as outlined
in Appendix 7 of this CHP Assessment.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 78
APPENDIX 7: ACTION PLAN
Although it is technically feasible to deliver heat to the area surrounding the Proposed Development, the financial modelling has shown that it is currently not financially viable to do so. Therefore, in order to preserve the opportunity to realise the full energy export potential of the Proposed Development it is recommended that an action plan is put in place. The outcome of this action plan will be a regular updating of the potential to export heat with a view to ultimately making the Proposed Development a CHP facility.
The action plan should be structured and have well defined objectives. It should involve all the local stakeholders and be supported at the highest levels within MEL. The action plan should identify the strategic tasks required for the district heating scheme development.
The action plan should be tailored to ensure a focused approach is adopted that is best suited to achieving the desired outcome. The initial phase of the plan could include the following actions:
revalidation of the heat load survey and research;
engagement with Stakeholders;
building a data base of potential heat users;
technical viability assessment; and
economic viability assessment.
The initial phase actions should be repeated every five years from first commercial operation until a viable CHP scheme is developed. A joint working group could be established involving local stakeholders once a viable scheme has been identified.
Constructing a data base of potential heat users is a useful tool for developing a CHP scheme. This data base should be revisited and updated at least every five years. New and planned developments can be added. Change in building ownership and use can affect the potential to be a heat customer. Boiler age can be tracked so that the consumer can be targeted when they are already considering investing in a new heating system. The data base will become a powerful tool over the life of the project.
The Proposed Development will be CHP enabled to be able to deliver up to 20 MW. In order to achieve CHP status, the scope of any proposed DH scheme needs to be well defined and technically assessed to prove that it is deliverable. Potential consumers need to be identified and approached so that there is a high degree of certainty over heat sales. The economic viability then needs to be confirmed.
The key steps to successfully delivering a viable district heating scheme are considered as:
(1) Maintain dialogue with identified key heat users;
At the appropriate times meetings should be held with each key organization already contacted to ensure every heat sales opportunity is maintained.
(2) Make contact with other potential heat users;
Building up a data base of potential customers has been identified as a key action towards delivering district heating. A programme of canvassing and surveys should be developed. During the execution phase of the project this programme can be implemented to build up a picture of the potential for more heat consumers. This needs to be carried out with due care to avoid alienating potential customers with excessive cold calling.
Ferrybridge Multifuel 2 (FM2)
Document Ref No: 5.10
Combined Heat and Power (CHP) Assessment
Multifuel Energy Limited July 2014 Page 79
(3) Instigate the action plan outlined above;
It is essential that a proper plan and organized approach is adopted if a viable district heating scheme is to be progressed. A clear strategy is required with objectives and targets. This can then be developed into a commercial business plan. The action plan should include all necessary tasks to enable CHP Review reports to be produced at the appropriate times.
(4) Open negotiations with potential Energy Services Company (ESCO)’s;
The core business of MEL is not selling heat. It is unlikely that MEL will have the right level of experience or expertise to maximise the DH opportunities. Therefore, it would be prudent for MEL to seek a partner to act as the ‘heat shipper’ and the interface with the consumer. This type of organisation is normally termed an Energy Services Company (ESCO). Choosing the right ESCO will be an important step for this project. Not all potential ESCO’s have the same experience or capability. Contact needs to be made with suitable organizations at the appropriate time and discussions held over how they could help make this project a success.
(5) Set up a working group involving local stakeholders;
Involving local stakeholders will improve the chances of a positive outcome. Demonstrating to local businesses that there is widespread support for the project will encourage them to become involved. Giving out a positive impression will generate confidence that committing to the scheme will be a benefit. Consideration should be given to setting up a working group during the execution phase of the project.
(6) Carry out ongoing reviews of potential heat load and scheme costs;
By carrying out ongoing reviews it will be possible to measure progress and identify any barriers preventing the project from gaining real momentum. This will help inform the decision makers on what the next steps should be.
(7) Produce regular CHP Review reports.
A CHP Review report will help focus the stakeholders on those things that have been a success and those things that have not produced the desired results. This provides a learning opportunity which can then lead to a more informed decision making process. The reports can be used to demonstrate the success of the project and in turn it then becomes a powerful marketing tool. The first CHP Review report should be provided 12 months after the authorised development has been taken into commercial operation and should confirm that appropriate connection and space for the later provision of heat pass-out for off-site users of heat has been provided (DCO Draft Condition 39(3)).
The CHP review needs to consider the opportunities that reasonably exist for the export of heat from the authorised development at the time of submission of the CHP Review and should include a list of actions (if any) the undertaker can reasonably undertake (without material additional cost to the undertaker) to increase the potential for the export of heat from the authorised development. The undertaker can thereafter undertake such actions as are agreed within the timescales specified in the CHP Review. The CHP Review will be revised and re-submitted by the undertaker to the planning authority on the date that is five years after the date of its previous submission to the planning authority throughout the lifetime of the authorised development and any actions specified in the subsequent CHP Review will be carried out by the undertaker in accordance with the timescales specified in the re-submitted CHP Review (DCO Draft Condition 39(4)).