18
May 17, 2013 Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N. E. Mailcode PJ – 12.1 Washington, DC 20426 Subject: FFP Project 131, LLC Application for Preliminary Permit Dear Secretary Bose: On behalf of FFP Project 131, LLC, enclosed please find a completed application for a preliminary permit pursuant to Section 4.30 of the Commission's regulations for the Felsenthal Lock and Dam Hydroelectric Project. If you have any questions regarding this submittal, please do not hesitate to contact me. Sincerely, Daniel N. Lissner FFP Project 131, LLC 239 Causeway Street, Suite 300 Boston, Massachusetts 02114 Daniel Lissner General Counsel T 978.252.7111 F 617.367.3372 [email protected] www.free-flow-power.com Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

May 17, 2013

Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N. E. Mailcode PJ – 12.1 Washington, DC 20426

Subject: FFP Project 131, LLC Application for Preliminary Permit Dear Secretary Bose: On behalf of FFP Project 131, LLC, enclosed please find a completed application for a preliminary permit pursuant to Section 4.30 of the Commission's regulations for the Felsenthal Lock and Dam Hydroelectric Project. If you have any questions regarding this submittal, please do not hesitate to contact me. Sincerely,

Daniel N. Lissner FFP Project 131, LLC

239 Causeway Street, Suite 300 Boston, Massachusetts 02114

Daniel Lissner

General Counsel

T 978.252.7111 F 617.367.3372

[email protected]

www.free-flow-power.com

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 2: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

APPLICATION FOR PRELIMINARY PERMIT

FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT

FFP Project 131, LLC 239 Causeway Street, Suite 300

Boston, MA 02114

May 2013

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 3: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This
Page 4: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

BEFORE THE UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT

I. Statement of Application

FFP Project 131, LLC applies to the Federal Energy Regulatory Commission for a preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This application is made in order that the Applicant may secure and maintain priority of licensing for the project under Part 1 of the Federal Power Act while obtaining the data and performing the acts required to determine the feasibility of the project and to support an application for license.

2. The location of the proposed project is:

State: Arkansas County: Union County, Arkansas Nearby Town: Felsenthal, Arkansas Body of Water: Ouachita River

3. The exact name, business address, and telephone number of the Applicant is:

FFP Project 131, LLC 239 Causeway Street, Suite 300 Boston, MA 02114 978.283.2822

The exact name, address, and telephone number of persons authorized to act as agent for the Applicant in this application are:

Daniel Lissner Free Flow Power Corporation 239 Causeway Street, Suite 300 Boston, MA 02114 978.252.7111 [email protected]

4. Preference under Section 7(a) of the Federal Power Act

FFP Project 131, LLC is a domestic limited liability company and is not claiming preference under the section 7(a) of the Federal Power Act.

5. Term of Permit

The proposed term of the requested permit is 36 months.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 5: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

6. Existing Dams or Other Project Facilities

The project will use the existing Felsenthal Lock and Dam structure, located on the Ouachita River. The project facilities are owned and operated by the U.S. Army Corps of Engineers (USACE) Vicksburg District. The address for the district office is:

U.S. Army Corps of Engineers Vicksburg District 4155 East Clay Street Vicksburg, MS 39183

Section 4.32(a) Information 1. Identify every person, citizen, association of citizens, domestic corporation, municipality,

or state that has or intends to obtain and will maintain any proprietary right necessary to construct, operate, or maintain the project:

FFP Project 131, LLC is the only entity that has or intends to obtain and will maintain any proprietary rights necessary to construct, operate, or maintain the proposed project.

2. Identify:

(i) Every county in which any part of the project, and any Federal facilities that would be used by the project, would be located:

Union County, Arkansas Union County Clerk 101 North Washington Avenue, Suite 102 El Dorado, AR 71730-5661 870.864.1910

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 6: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

(ii) Every city, town, or similar local political subdivision:

(A) In which any part of the project, and any Federal facilities that would be used by the project, would be located:

Felsenthal, Arkansas 1000 South 3rd Street Felsenthal, AR 71747 870.943.2454

(B) That has a population of 5,000 or more people and is located within 15 miles of the project dam:

Crossett City, Arkansas 307 Main Street Crossett, AR 71635 870.364.4131

(iii) Every irrigation district, drainage district, or similar special purpose political subdivision:

There are no irrigation districts, drainage districts, or similar special purpose political subdivisions associated with this project.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 7: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

(iv) Every other political subdivision in the general area of the project that there is a reason to believe would likely be interested in, or affected by, the application:

Arkansas Senators Senator John Boozman 320 Hart Senate Office Building Washington, DC 20510 Senator Mark Pryor 255 Dirksen Senate Office Building Washington, DC 20510

(v) All Indian Tribes that may be affected by the project:

The applicant has identified no Indian Tribes that may potentially have an interest or be affected by the project using the National Park Service’s Native American Consultation Database.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 8: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

BEFORE THE UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT

EXHIBIT 1 – GENERAL DESCRIPTION

Section 4.81(b)

1. General Configuration and Information

The proposed project will be located at the Felsenthal Lock and Dam on the Ouachita River at river mile 226.9, which is located in Union County, Arkansas. The project will utilize the existing USACE lock and dam that was placed into service in 1984. The existing Felsenthal Lock and Dam is further described in the following table:

Felsenthal Lock and Dam Year Placed Into Operation 1984

Location Felsenthal, Arkansas Water Body Ouachita River

Latitude 33° 03'11.88"N Longitude 92° 07'05.88"W

Structural Height 105 feet Gates 1 tainter and 3 bascule

Lock Dimensions 84 feet by 600 feet Storage Capacity 76,700 acre-feet

The proposed development of the site involves the construction of a new 5-MW hydropower facility at the eastern end (left side) of the existing Felsenthal Lock and Dam. The project will consist of the following major elements:

Existing Dam – The existing USACE facility consists of an operational lock, and a reinforced concrete dam with four Gates.

Intake – A new intake will be located immediately upstream and on the east (left) bank and will convey flow to the powerhouse. The intake will measure approximately 150 feet wide by 300 feet long in plan will be constructed with riprap slopes and unlined floor.

Powerhouse – A new reinforced concrete powerhouse, 150 feet wide by 100 feet in plan, will be constructed downstream of the new intake along the left bank, facing downstream. The powerhouse will contain the turbine-generators, switchgear, controls, and ancillary systems, as well as shop and storage space.

Tailrace Area – The new tailrace will assist on conveying water exiting the powerhouse back into the river downstream. The 150 foot wide by 500 foot long tailrace area will be an unlined excavation with stone riprap placed in the areas of higher velocity to prevent scour and erosion where necessary. Where portions of the riverbank are excavated to accommodate the tailrace, the grades will be laid back and will be used to transition the channel the existing shoreline grades in such a way that prevents scour and does not interfere with adjacent site features.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 9: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Turbine-Generators – Two horizontal bulb turbine-generators, each rated at 2.5 MW, will be installed in the new powerhouse for a total project installed capacity of 5 MW.

Substation – A 50-MVA 4.16/ 69-kV three phase step-up transformer will be located in a new substation and adjacent to the powerhouse. The new substation will be 60 feet wide by 60 feet long. The substation will also contain high side and low side disconnects and will be surrounded by a containment dike and a security fence.

Access Roads – Powerhouse access will be provided by extending an existing road. No new access roads will be necessary for the proposed project.

2. Reservoirs The Felsenthal Lock and Dam form an impoundment pool (Lake Jack Lee) that a slack-water pool that stretches for roughly 100 miles. At a normal pool elevation of 65 feet msl, at maximum pool, the surface area of the impoundment is approximately 22,730 acres with a maximum storage capacity of 76,700 acre-feet. The project will be operated in a run-of river mode that maintains the navigation channel at all times. There is no available storage capacity to be used for hydro generation purposes with this operational regime.

3. Transmission Lines

The applicant has identified existing transmission infrastructure in the proposed project area. These existing transmission elements will be evaluated during the permit period through field investigations and discussions with the local utility. It is anticipated that the project will utilize a single overhead three phase, 69kV line which is approximately 1 mile in length, extending from the substation to an existing substation at a proposed interconnection point.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 10: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

4. Turbines and Generators

x Two vertical Kaplan turbines, each with an installed nameplate capacity of 2.5 MW will be used at the project for a total installed capacity of 5 MW.

x The estimated average annual energy production is 18 GWh. x The hydraulic head used for estimating capacity and energy output is 12 feet. x The turbines and generators will be newly manufactured for the project.

5. Lands Within The United States

The Felsenthal Hydroelectric Project will be located on Federal property owned by the USACE. The majority of the project will be located within the bounds of the Felsenthal Lock and Dam property. A portion of the transmission line and the transmission interconnection will be located nearby on non-Federal Lands.

6. Development, Conservation, and Utilization of Water Resource

Felsenthal Lock and Dam Hydroelectric Project involves the environmentally responsible, low impact development and utilization of a currently unused source of renewable energy which will provide a clean source of electrical energy to help meet the region’s energy and capacity needs.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 11: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

BEFORE THE UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION

APPLICATION FOR PRELIMINARY PERMIT EXHIBIT 2 – DESCRIPTION OF STUDIES

Upon issuance of a Preliminary Permit, applicant proposes to conduct detailed studies to determine the ultimate feasibility of the project and potentially support the preparation of an application for License, as detailed below.

1. General Description of Proposed Studies

The following studies are planned: (i) Description of proposed studies a) Information Review: Publicly available general information will be compiled and

reviewed. This will include engineering and “as built” records from the original construction of the existing dam, local survey data, utility distribution and transmission information, material previously submitted to FERC for earlier development initiatives, as well as any studies or surveys that have been done concerning the dam structure, the upstream pool, and the reach of the waterway near the project.

b) Hydrologic Studies: Publicly available USGS and USACE gaging station record data will

be used to develop detailed daily stream flow forecasts at the project site. USACE operational information for the gates will be incorporated to determine actual flows available for generation. Historic USACE data records for upper and lower pool elevations, as well as field data will be gathered and used to develop head data for the proposed turbine location. A combination of flow and stage data will be used to model hydraulics and support energy production calculations at the site.

c) Develop and Review Alternatives: Project layout and sizing alternatives will be

developed and evaluated in order to maximize the power generated, minimize environmental impact, and otherwise select the optimal project to ensure the best possible use of the resource.

d) Preliminary Engineering and Design: The information generated in the preceding

studies will be incorporated into an optimized design suitable for a definitive estimate of project cost and feasibility.

e) Energy Generation and Cost Estimates: The flow and head data created in Task (b)

coupled with the selected project design alternatives from Tasks (c) and (d) will allow energy generation to be modeled for the project. Daily forecast energy generation will be determined and typical, wet, and dry year generation estimated will be made. Initial budgetary development and construction costs will be developed. A tentative permitting and construction schedule will be defined.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 12: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

f) Feasibility Analysis: The previous work will be compiled into a final feasibility analysis

along with data gathered on then-current and forecast wholesale power prices, financing costs, and O&M costs to determine the economic feasibility of the project.

If the result of the feasibility analysis is positive, the following activities are envisioned to take place during the remaining preliminary permit term to support Licensing and development of the project:

g) Informal Stakeholder Consultation and Discussions

h) Develop Notice of Intent (NOI)

i) Develop Pre-Application Document (PAD)

j) Begin Scoping Activities

It is anticipated tasks (a) through (f) will be completed within 12 months of the permit issuance. Tasks (g) through (j), if undertaken, will be performed during the remaining permit term.

(ii) New Road Construction

Access for all field surveys will be via existing roads. No new roads are required for the proposed project.

2. New Dam Construction

The proposed project will not require construction of any type of dam as the facility will be located at the existing Felsenthal Lock and Dam.

3. Waiver

The Applicant requests that the Commission waive the field study requirement because no new dam under the Section 4.81(c)(2Xiii) is proposed.

4. Statement of Cost and Financing

(i) Estimated Costs: The total cost for completing tasks (a) through (f) as outlined above is estimated to be $100,000. If task (g) through (j) are undertaken the total costs is estimated to not exceed $500,000. (ii) Expected Sources of Financing: The studies will be financed by the Applicant.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 13: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

BEFORE THE UNITED STATES FEDERAL ENERGY REGULATORY COMMISSION APPLICATION FOR PRELIMINARY PERMIT

EXHIBIT 3 – MAPS 1. General Location of Proposed Project

Attached are maps showing the location, the project layout, and the project boundary for the proposed project. The project location is shown on Map 1-Vicinity and Map 2-Location.

2. Project Features

The probable locations of the primary project features are shown in Map 3-Layout. 3. Proposed Boundary

The proposed project boundary and townships are shown on Map 4-Boundary. 4. National Wild and Scenic Rivers Systems

No areas in the project vicinity are included (or are known to have been designated for study for inclusion) in the National Wild and Scenic Rivers System.

5. Designated Wilderness Areas

No areas within the project boundary have been designated as wilderness area. No areas within the project boundary are known to be recommended for designation as wilderness area or designated as wilderness study area.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 14: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 15: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 16: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 17: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved

Page 18: FELSENTHAL LOCK AND DAM HYDROELECTRIC PROJECT … · preliminary permit for the proposed Felsenthal Lock and Dam Hydroelectric Project, as described in the attached exhibits. This

Form FERC-587

OMB No. 1902-0145

LAND DESCRIPTION Public Land States

(Rectangular Survey System Lands)

1. STATE: Arkansas 2. FERC PROJECT No: ____________________

3. TOWNSHIP: T19S RANGE: R10W MERIDIAN: Fifth 4. Check one: Check one: License X Pending X Preliminary Permit Issued If preliminary permit is issued, give expiration date: (Not applicable)

5. Exhibit Sheet Number(s) or Letter(s) Section 6 5 4 3 2 1

7 8 9 10 11 12

18 17 16 15 See Map 4 - Boundary

14 13

19 20 21 22 23 24

30 29 28 27 26 25

31 32 33 34 35 36

6. Contact’s name: Daniel Lissner Telephone No.: 978-283-2822 Date Submitted: May 17, 2013 This information is necessary for the Federal Energy Regulatory Commission to discharge its responsibilities under section 24 of the Federal Power Act.

Copyright © 2013 Free Flow Power Corporation - All Rights Reserved