Upload
vivian-pitts
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
Federal Highway AdministrationEmergency Relief (ER) Program
Brian Hogge
Field Operations Team Leader
July 2013
2
Background
Authorized by Congress in 23 USC, Section 125.
Repair or reconstruction of federal-aid highways and roads on federal lands damaged by:
Natural disasters (floods, hurricanes,earthquakes, tornadoes, landslides,wildfires, severe storms)
Catastrophic failures from an external cause (barge striking abridge pier or truck crash and fire)
Disaster Declaration
Federal-aid highway or federal lands roadway
Minimum event threshold is $700,000
Minimum site threshold is $5,000
General Requirements
4
Funds Available
Annual Authorization of $100,000,000 Supplemental Appropriations provided by Congress Unneeded funds withdrawn from states
Federal-aid Highways
Federal-aid highways other than those functionally classified as:
a)Local Road
b)Rural Minor Collector
Local roads and rural minor collectors may be eligible for other federal aid, but they are not eligible for FHWA ER funds.
1. Emergency Repairs
Restore essential traffic, minimize the extent of damage, or protect the remaining facilities
Eligible at 100% within 180 days
Eligible at normal share beyond 180 days*
*The 180 day time period for 100% eligibility of emergency repairs will be extended if a State cannot access a site to evaluate damages and the cost of repair.
Two Categories of Repair
Two Categories of Repair
7
2a. Permanent Repairs concurrent with Emergency Repairs
NEPA not required Follow Emergency Repair contracting method Eligible at normal pro rata share (not 100%)
8
Two Categories of Repair
Resilience
9
Design and construction of repairs should consider the long-term resilience of the facility. Resilience as the capability to anticipate, prepare for, respond to, and recover from significant multi-hazard threats with minimum damage to social well-being, the economy, and the environment. A risk-based analysis should be used when designing and constructing repairs to ensure they are cost effective and to reduce the potential for future losses. The analysis should apply the best available scientific and economic information to forecast and assess future risk factors.
10
Betterments
Betterments are added protective features
Changes that modify highway function or character
Betterments are generally not eligible
May be eligible if economically justified as beneficial to the ER program
11
Eligible Items
Preliminary Engineering
Construction Engineering
Right-of-Way
Designated Detours
Traffic Damages (limited applicability)
Debris Removal
Traffic Control Devices
Roadside Appurtenances
12
Debris deposited as a direct result of the disaster
Other debris may be eligible for FEMA funding*
Some debris removal may be considered “emergency repair” Removal to outside edge of shoulder
Debris considered to be a safety hazard
Additional debris removal (within right-of-way) is eligible as permanent repair
*In certain instances, debris removal previously eligible for ER funding will only be eligible for FEMA funding. See the ER Manual for details.
Debris Removal
13
Contract Requirements
Emergency repairs do not require prior FHWA authorization
Permanent repairs require prior FHWA authorization
Generally, ER contract requirements are the same as regular federal-aid projects
Pre-established emergency repair contracts may be used
14
Davis-Bacon
Required for any construction work
Not required for debris removal only without any incidental construction
Davis-Bacon requirements may only be waived by a Presidential Executive Order
Environmental Documents
15
Emergency Repairs:
23 CFR 771.117(c): The following actions meet the criteria for CEs… and normally do not require any further NEPA approvals by the Administration.
Emergency repairs are classified as categorical exclusions under 23 CFR 771.117(c)(9)(i).
Other “c list” activities include landscaping, rideshare activities, bus and rail car rehabilitation, etc.
Environmental Documents
16
Permanent Repairs:
23 CFR 771.117(c): The following actions meet the criteria for CEs… and normally do not require any further NEPA approvals by the Administration.
Permanent repairs are classified as categorical exclusions under 23 CFR 771.117(c)(9)(ii).
Other laws still apply Threatened & Endangered Species Act Clean Water Act Etc.
17
ER Program ChangesThe State should submit to the FHWA Division Administrator a program of projects which defines the work needed to restore or replace the damaged facilities within 3 months of the receipt of the initial disaster notification.
States are required to submit an application for ER funding to FHWA within two calendar years of the date of the disaster. The application must include a comprehensive list of all eligible project sites and repair costs.
ER projects shall be promptly constructed. Projects that have not advanced to the construction obligation stage by the end of the second fiscal year following the disaster occurrence will not be advanced unless suitable justification is provided to warrant retention is furnished to the FHWA.
18
Programmatic Agreement Signed in March 2012 Allows programmatic approval instead of case-by-case
approvals Permanent repairs performed concurrently with emergency repairs Force account work and contracting methods
Sets a threshold for programmatic approvals of $150,000 per site
Allows MnDOT to sign DDIRs under $150,000 per site Outlines eligibility and guidance for each type of work Requires DDIR completion within 12 weeks of completion of
work for Emergency Repairs and within 180 days of date of disaster for Permanent Repairs
Questions?
19
Image from June 2012 flood in Duluth, MN