Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 1 of 12
Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to
km.104.700 (km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Feasibility Report A. INTRODUCTION
India has about 3.3 million kilometers of road network, which is the second largest road
network after United States of America. The roads in the country are either under
administrative control of the Union Government or the State Government concerned.
Roads in the country carry about 65 percent of freight traffic and 87 percent of
passenger traffic. National Highways, the primary road network of the country, are under
the Union Government. The aggregate length of National Highways is, at present, 70,
548km which is about 2 percent of the road network but carries about 40 percent of road
traffic.
Keeping in view of the importance of the National Highways for the economic
development, the Government of India has taken up an ambitious program of
development of the National Highways under different phases of National Highway
Development Program (NHDP). One of the phases of NHDP, namely, NHDP Phase- VI
is for development of 1000 km of expressways. The expressways carry large volumes of
traffic at high speed and are access controlled.
The National Highways Authority of India (NHAI) has been entrusted with the
implementation of, inter-alia, NHDP Phase-VI. The construction of about 400 km long
Mumbai- Vadodara Expressway is one of the expressways which have been identified
for implementation in this phase. This project has been proposed to be implemented
under Public Private Partnership mode and to be executed as Design, Build, Finance
and Operate (DBFO) contracts.
The NHAI, as the employer and the executing agency has commissioned the services of
Intercontinental Consultants and Technocrats Private limited (ICT) for carrying out
consultancy services for “Preparation of Feasibility cum Preliminary Design Report for
Vadodara – Mumbai Expressway under NHDP Phase- VI”.
The proposed Vadodra - Mumbai expressway has been divided into three phases for
implementation:
Phase I: From proposed chainage km 104+700 to chainage km 378+722 in the
State of Gujarat, Maharashtra and Union Territory of Dadra and Nagar Haveli.
Environmental Clearance has already obtained from MoEF&CC for Phase-I
development.
Phase II: This section starts from proposed chainage km 26+320 (near Vasai in the
state of Maharashtra) to chainage km 104+700 (km 390+864 of NH-8 near Talasari
in the state of Maharashtra). Total length is 78.38 km. This Feasibility Report deals
with Phase II development of Vadodara Mumbai Expressway (VME).
Phase III: From proposed chainage km 0+000 to km 26+320 (26.320 km) in Thane
District of Maharashtra.
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 2 of 12
B. NEED OF THE PROJECT
The Mumbai–Ahmedabad Corridor in the western part of the country is one of the
important transport corridors of the country. On one side of this corridor is Mumbai
which is the financial capital of the country and on the other side is Vadodara, an
important commercial and business city. There are many industrial centres on this route.
Industries like, textile industry, gems and jewelries, petrochemical & fertilizer and other
industrial complexes have been established along this corridor. This corridor also serves
SEZ areas and ports. Development works of these corridors like improvement of
National Highways, construction of expressways, construction of dedicated railway
freight corridors, modernization of airports located along this corridor have been taken
up. The project road lies within the proposed Delhi Mumbai Industrial corridor which is
being planned as hub of industrial and urban activity.
NH-8 is of great significance for transportation in this corridor starting from the country’s
administrative capital of Delhi to financial capital of Mumbai. Present condition and steps
taken to develop its speed and safety are as follows:
The Vehicle Damage Factor (VDF) as assessed on NH8 section for 2 axle vehicles
varies from 2.04 to 5.86 whereas VDF for 6 axle vehicles were in the range of 19.48
to 25.69.
The average journey speed on Mumbai-Vadodara section of NH 8 was found to be
in the range of 50-60 km/hr (major part of the section) to 80-90 km/hr. whereas a
National Highway is designed for the speed of 100km/hr.
NH8 is carrying traffic in the range of 50,000 to 80,000 PCU per day. It has been
developed as 6 lane recently but many of the sections have already reached nearly
the capacity volume (LOS E) of 6 lane NH (120,000 PCU) in the year 2015.
Even with six laning or further widening, segregation of long distance and local and / or
slow traffic is hard to achieve. Further since it’s a National Highway (not access
controlled) and passes through many settlements land availability and displacement of
people would be a major concern.
C. PROJECT LOCATION
The Phase II of Vadodara Mumbai Expressway (VME) is a greenfield alignment. The
expressway starts at proposed chainage km 26+320 (near Vasai in the state of
Maharashtra) and ends at proposed chainage km 104+700 (km 390+864 of NH-8) near
Talasari in the state of Maharashtra. Total length of the VME Phase-II alignment is
78.38 km. The proposed alignment is passing through 4 talukas (Vasai, Palghar,
Dahanu and Talasari) of Palghar district in the state of Maharashtra. The alignment is
passing through plain and rolling terrain with cultivated and barren areas. On its way, it
crosses Palghar-Manor road, Boisar road, Tarapur, Masvan and Pulachapada Roads
which connects these villages with NH-8 and the alignment ends with a partial cloverleaf
type interchange on NH-8 near Talasari. The project road crosses 51 villages in Palghar
district. The predominant land use along the alignment is agricultural followed by
vegetation cover. The proposed alignment runs parallel to and very near to Rivers
Vaitarna, Surya and Suseri.
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 3 of 12
Crossing of River Vaitarna at Ch. km 45+000
Crossing of Surya River
at Ch. km 68+400
Figure-1 Index Map showing the Project Location
D. DESCRIPTION OF THE ALIGNMENT
Section from start point (chainage km 26+320) to Dahanu-Kasa Khurd Road (Km
78+650): In this section the alignment is to the
west (left) of NH 8 and diverges from it. It starts
300 m away from NH 8 and moves away to
about 11.6 km at Km 66+0 before narrowing
the distance to 10.0 km along Dahanu – Kasa
Khurd Road (SH 30). The terrain is generally
plain/ rolling. This section initially runs through
Vaitarna River valley and then starts rising. The
Section is thinly populated, under developed
and where subsistence agriculture is common
occupation. The alignment crosses Vaitarna
River thrice - at Ch. Km 31+00, Ch. Km 35+700 and Ch. Km 45+000. The crossing at
Km 31+00 is 2.2 km upstream (east side) of the
existing railway bridge located near Vaitarna
Railway Station of Western Railway mainline.
The alignment from km 45+00 to km 68+420
runs parallel to Surya River on the eastern side
of the river. The alignment crosses River Surya
at Ch. Km 68+420 and River Suseri at Ch. Km
72+190.The section ends with a diamond
interchange on SH-30.
There are no railway crossings in this section.
The alignment crosses Palghar- Manor road,
Boisar road, Tarapur, Masvan and Pulachapada Roads which connects these villages
with NH8. The alignment passes through Reserved Forest in parts aggregating to a total
length of about 1.75 km. Some parts of this section lie in Coastal Regulation Zone
(CRZ). Total length of the alignment in CRZ is 3.575 km out of which in Vasai (from Km
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 4 of 12
29.900 to km 30.434 & km 30.462 to km 30.800) and Palghar Taluka (km 30.800 to km
32.100; km 35.430 to km 36.833).
Section from Dahanu – Kasa Khurd Road (Km 78+650) to NH 8 Crossing (Km
104+700): In this section the alignment moves close to NH 8 up to Ch. km 85+200 (2
km away) and then runs parallel to it before crossing at Ch. Km 104+700 near Talasari.
The alignment is in plain and rolling terrain and passes through very sparsely populated
area without any major obstructions. The alignment crosses River Jogani at Ch. Km
89+600 and River Vadavali at Ch. Km 96+ 200. Agriculture is the main occupations of
the people living along the alignment. At Ch. Km 99+840, the alignment crosses SH-29
to Umargoun and the crossing is 3.4 km west of NH-8 and at Km 91+756 the alignment
crosses SH-31. The sections ends with a partial cloverleaf type interchange on NH-8
near Talasari.
E. TRAFFIC ESTIMATE
For estimation of traffic for the proposed expressway, a regional transport demand
model (RTDM) considering entire study area was developed. The RTDM has been used
by considering a number of parameters during the process of transport demand
generation, distribution in the study area, and assignment on the road network of study
area. For the base year, the model has been calibrated and validated by considering
existing traffic volumes and travel demand pattern observed on major road network in
Gujarat and Maharashtra (running parallel to and feeding to the proposed expressway).
For future scenarios where the proposed expressway exists the traffic gets diverted on
the new facility based on savings in Vehicle Operating Cost (VOC) and Travel Time.
These factors have been inbuilt in to the model by considering generalized cost of travel
based on the VOC established by ‘Road User Cost Study’ conducted by CRRI. Thus
traffic which is likely to travel on the proposed expressway has been arrived at by
considering future growth / development scenario and the traffic diversion from existing
road network. The projected traffic in the proposed expressway and lane configuration
are given below:
Crossing with NH-8
at Ch. Km 104+700 (End Point)
Crossing with SH-29 at Ch. Km 99+840
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 5 of 12
Table-1 Estimated Traffic in the Proposed Expressway (Ch. Km 26+320 to 104+700)
Section No. Chainage from/to
Estimated AADT
(in PCU)
Expressway Lane Requirements
2017 2035 2017-2035 2035-2045
Section 2-1 Km 26+320 - Km 78+650 72165 144465 8-lanes 8-lanes
Section 3 Km 78+650 - Km 104+700 68653 137255
F. RIGHT OF WAY
The proposed right of way is 100 m / 120 m in general except at interchanges area.
Chainage wise details of proposed RoW are given in Table-2.
Figure-2 Proposed Cross-section – 8 Lane Divided Carriageway
VME Phase-II
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 6 of 12
Table-2 Chainage wise Details of Proposed RoW
Sl. No. Stretches Length
(in Km) PROW Remarks
From To
1 26+300 27+150 0.850 As per Design Interchange Area
2 27+150 31+000 3.850 100
3 31+000 33+850 2.850 100
4 33+850 34+300 0.450 120
5 34+300 35+200 0.900 100
6 35+200 41+700 6.500 120
7 41+700 43+500 1.800 100
8 43+500 46+500 3.000 120
9 46+500 47+400 0.900 100
10 47+400 50+900 3.500 120
11 50+900 53+500 2.600 100
12 53+500 61+500 8.000 120
13 61+500 62+800 1.300 100
14 62+800 64+200 1.400 120
15 64+200 64+900 0.700 100
16 64+900 65+300 0.400 120
17 65+300 67+200 1.900 100
18 67+200 67+700 0.500 120
19 67+700 70+800 3.100 100
20 70+800 77+000 6.200 120
21 77+000 77+900 0.900 100
22 77+900 79+400 1.500 As per Design Interchange Area
23 79+400 80+600 1.200 100
24 80+600 82+800 2.200 120
25 82+800 84+900 2.100 100
26 84+900 86+200 1.300 120
27 86+200 93+300 7.100 100
28 93+300 95+800 2.500 120
29 95+800 99+600 3.800 100
30 99+600 102+000 2.400 120
31 102+000 103+300 1.300 100
32 103+300 106+600 3.300 As per Design Interchange Area
G. LAND ACQUISITION
The tentative land acquisition for VME Phase II is 926.236 Ha. The Taluka wise
proposed land acquisition details in district Palghar are presented in Table-3.
Table-3 Taluka wise details of Land Acquisition
Sl. No. Taluka Land in (Ha.)
1. Talasari 85.093
2. Dahanu 343.558
3. Palghar 442.743
4. Vasai 54.841
Total 926.236
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 7 of 12
H. DETAILS OF PROPOSED DEVELOPMENT
The proposed Mumbai- Vadodara Expressway is to be built as an access controlled
expressway with access allowed only at the interchanges. It will be a eight lane divided
carriageway with 12m wide depressed median. The carriageway width is 15 m with 3.0
m wide paved and 3.0 m wide earthen shoulders. Further it is proposed to build service
roads along the expressway at some locations to facilitate movement of local traffic
across expressway. Initially it was proposed to adopt a ROW of 100 m for the
expressway. However during subsequent discussions with NHAI officials it has been
decided to adopt an ROW of 120 m to give adequate space for utilities, plantation of
trees and to avoid construction of retaining walls in high embankment areas.
1. Interchanges
Interchanges are required on expressways for transfer of traffic from the expressways to
other intersecting roads/expressways or vice versa avoiding any conflict. The objective
of provision of interchanges is to allow safe and uninterrupted travel for expressway
users. Interchange is proposed at 2 locations, crossing of Dahanu Kasa Khurd (SH-30)
and crossing of Surat-Dahisar Sect of NH-8. Details are given in Table-4.
Table-4 Details of Interchanges
Sl. No.
Name of Interchange Chainage Length (m)
1 Interchange at Crossing of Dahanu Kasa Khurd (SH-30) 78+638 121.650
2 Interchange at Crossing of Surat-Dahisar Section of NH-8 104+707 131.189
2. Fly-Over
The expressway is an access controlled facility and all other road crossings therefore
will be provided either with a flyover or with a vehicular underpass with no access to the
expressway. Flyovers are proposed at 4 locations. Details are given in Table-5.
Table-5 Details of Fly-overs
Sl. No. Description Chainage Length (m)
1 Flyover Over Boisal - NH-8 Road 60+240 27.250
2 Bridge + Flyover over Tarapur-Charoti Road 73+054 93.100
3 Flyover Over Dhanu-Talasari (SH-31) 91+756 74.662
4 Bridge + Flyover over Umargaun-Talasari (SH-29) 99+882 126.650
3. Vehicular Underpasses
Vehicular underpasses of size 12mx5m have been proposed on Major District Roads
(MDRs) and other minor roads. Vehicular underpasses have been proposed at 15
locations as given in Table-6.
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 8 of 12
Table-6 Details of Vehicular Underpass
Sl. No. Chainage (km) Type of Crossing
1. 27+910 Virar - Khardi
2. 29+202 Fanas Pada - Virar
3. 32+339 Safale - Navghar
4. 38+653 Safale - NH 8
5. 43+849 Sakhade - NH 8
6. 46+396 Dolpada - Vadoli
7. 50+594 Palghar - Manor
8. 55+135 Palghar - Nagazari
9. 61+191 Kirat - Boisar
10. 65+057 Kirat - Ravte
11. 67+471 Chincharet - Ravet
12. 70+859 Aina - Naikapada
13. 81+660 Rankol - Charoti
14. 95+635 Gajad - dhanivari
15. 96+983 Vadavali - NH 8
4. Vehicular Overpass
At some locations where cross roads have been proposed to cross as elevated sections
on the expressway. 3 such overpasses of size 2 x 41 m span have been proposed at
following locations.
Table-7 Details of Vehicular Underpass
Sl. No. Chainage (km) Type of Crossing
1. 89+308 Asgarh - Chanchol
2. 101+912 Jhari - Talasari
3. 102+365 Kawada - Babuapada
5. Pedestrian / Cattle Underpasses
The expressway is a greenfield alignment and is access controlled therefore it will be
bifurcating the communities on either side. Since it is passing mainly through rural belt
the farming communities on either side need to be provided with suitable connection. To
serve this purpose, 26 pedestrian underpasses and 47 cattle underpasses of size
6mx3.5m have been proposed.
6. Bridges
The expressway alignment is crossing major / minor rivers, drains and nala at number of
locations where major / minor bridges have been proposed as per hydraulic
considerations. 8 major bridges (Table-8) and 29 minor bridges (Table-9) have been
proposed.
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 9 of 12
Table-8 Details of Major Bridge
Sl. No. Description Chainage Length (m)
1 Major Bridge over Vaitrana River - 1 31+300 1968.05
2 Major Bridge over Vaitrana River - 2 35+725 576.05
3 Major Bridge over canal + road 42+858 68.334
4 Major Bridge over canal + road 43+725 67.213
5 Major Bridge over Vaitrana River - 3 45+040 672.05
6 Major Bridge over Surya River 68+420 236.05
7 Major Bridge over Suseri Nallah 72+190 111.65
8 Major Bridge over Vadvali Nadi 96+208 96.65
Total Length (m) 3796.047
Table-9 Details of Minor Bridges over Rivers / Streams / Nallas / Utility
Sl. No. Description Chainage Length (m)
1. Minor Bridge over Local Nallah 37+780 27.353
2. Minor Bridge over Local Channel 37+965 19.162
3. Minor Bridge over Guljari Nallah 48+393 32.250
4. Minor Bridge over Local Channel 50+208 15.900
5. Minor Bridge over Local Nallah 52+728 12.551
6. Minor Bridge over Stream 54+310 27.250
7. Minor Bridge over Stream 57+885 29.250
8. Minor Bridge over Stream 59+888 37.250
9. Minor Bridge over Canal 60+712 29.255
10. Minor Bridge over Local Stream 61+539 19.162
11. Minor Bridge over Canal 62+421 21.373
12. Minor Bridge over Stream 63+570 32.250
13. Minor Bridge over Stream 63+925 15.900
14. Minor Bridge over Canal 65+134 39.631
15. Minor Bridge over Stream 66+137 12.440
16. Minor Bridge over Nallah 66+735 15.900
17. Minor Bridge over Stream 70+000 27.250
18. Minor Bridge over Stream 74+493 20.900
19. Minor Bridge over Canal 76+037 29.255
20. Minor Bridge over Jagani Nadi 79+745 21.940
21. Minor Bridge over Stream 81+330 27.372
22. Minor Bridge over Jagani Nadi 83+620 21.940
23. Minor Bridge over Stream 85+420 20.900
24. Minor Bridge over Jagani Nadi 89+604 50.973
25. Minor Bridge over Stream 91+564 15.900
26. Minor Bridge over Canal 93+650 27.848
27. Minor Bridge over Canal 94+491 29.250
28. Minor Bridge over Nallah 103+430 20.900
29. Minor Bridge over Gas Pipe Line 103+998 46.549
Total Length (m) 747.854
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 10 of 12
7. Culverts
75 RCC box culverts (73 on main & 2 on the loop / ramps of interchanges) and 25 Hume
pipe culverts are proposed across the main alignment to prevent disturbance of the
natural and artificial drainage system.
8. Service Roads
The roads where underpasses have not been provided have been connected to the
nearest underpass by service roads so that the movement of local traffic across the
expressway is not hindered. Service roads have also been provided at in the urban
areas. Total length of service road is 9.390 km. Locations of service road are presented
in Table-10.
Table-10 Details of Service Road
Sl. No. Stretches
Length (Km) Width (m) From (km) To (km)
Main Expressway Phase II (Left Service Road)
1. 38+640 39+000 0.360 5.50
2. 47+650 47+970 0.320 5.50
3. 54+965 55+150 0.185 5.50
4. 56+960 57+400 0.440 5.50
5. 60+975 61+350 0.375 5.50
6. 63+140 63+230 0.090 5.50
7. 65+085 65+230 0.145 5.50
8. 67+450 67+675 0.225 5.50
9. 70+850 71+960 1.110 5.50
10. 72+370 72+660 0.290 5.50
11. 73+750 74+000 0.250 5.50
12. 80+640 80+980 0.340 5.50
13. 81+630 82+650 1.020 5.50
14. 85+050 85+300 0.250 5.50
Sub-Total (A) 5.40
Main Expressway Phase II (Right Service Road)
1. 47+700 48+000 0.300 5.50
2. 48+650 48+850 0.200 5.50
3. 50+600 50+850 0.250 5.50
4. 55+080 55+260 0.180 5.50
5. 55+840 55+970 0.130 5.50
6. 63+140 63+230 0.090 5.50
7. 75+600 76+065 0.465 5.50
8. 81+660 82+650 0.990 5.50
9. 85+130 85+390 0.260 5.50
10. 95+200 95+625 0.425 5.50
Sub-Total (B) 3.29
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 11 of 12
Sl. No. Stretches
Length (Km) Width (m) From (km) To (km)
At Interchange Area (Left Service Road)
Int.
Location
Stretches Length (Km) Width (m)
From (km) To (km)
26+320 0+000 0+450 0.450 5.50
78+650 0+000 0+250 0.250 5.50
Sub-Total (C) 0.700
TOTAL = (A+B+C) 9.390
9. Way Side Amenities and Truck Parking
Wayside amenities along the expressway are integral parts and these facilities provide
useful services to the traveling public. These facilities provide services to the users who
desire to stop for rest, refreshment, information and fuelling or for some emergency
requirement. To facilitate the road user, way side amenities and truck parking has been
proposed along the expressway. The locations are as follows
Table-11 Details of Way Side Amenities and Truck Parking
Sl. No. Location Side
Way side Amenities (Type-A)
1 90+100 Left
2 90+600 Right
Way side Amenities (Type-B)
1 42+000 Left
2 47+500 Right
3 67+900 Left
4 70+400 Right
Truck Parking
1 41+000 Right
2 49+300 Left
10. Toll Plaza
For each interchange a suitable type from the standard configuration or a modified one
has been adopted based on the land constraints and requirement of traffic. Accordingly,
a full clover leaf interchange is having four separate toll plazas or partial clover leaf with
less number of toll plazas, and appropriate trumpet interchange at the start and end with
single main line toll plaza. The toll lanes have been estimated for horizon year 2035 and
2045 considering that, in the opening year, toll plazas will be constructed to cater for the
requirements for next 20 years and by 2035 the toll plazas can be expanded for the
requirements of year 2045. Toll plaza has been proposed at 6 locations (on loop /
ramp).
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700
(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra
Document : Feasibility Report Month: Oct 2016
National Highways Authority of India Page 12 of 12
11. Road Safety
Road safety aspects have been well studied and several safety features like road
marking, traffic sign, safety barriers, boundary stones, kilometer stones and hectometer
stones, pavement marking and lighting has been proposed. The engineering design of
the road has also considered IRC codal provisions related to road safety such as:
IRC: SP: 32-1988 Road Safety for Children
IRC: SP: 44-1994 Highway Safety Code
IRC: SP: 55-2001 Guidelines for Safety in Construction Zones
IRC:119:2015 Guidelines for Traffic Safety Barriers
I. PROJECT COST
The tentative Civil Cost works out to be as under:
Table-12 Total Project Cost (in INR Cr.)
S No. Description Total Cost (INR)
1 Site Clearance and Dismantling 35,629,995.00
2 Earthwork 7,039,653,679.00
3 Granular Base Course and Sub - Base 4,002,969,139.00
4 Bituminous Course 4,235,397,295.00
5 Culverts 836,774,824.00
6(A) Major Bridges 8,428,068,519.00
6(B) Minor Bridges, Canal Bridges, Gas Pipe Lines 2,693,443,698.00
6(C) Interchanges, Flyovers and ROB's 1,136,713,373.00
6(D) Underpasses / Overpasses 2,648,478,423.00
7 Drainage Works and Protection Works 3,613,379,093.00
8 Traffic Signs, Markings and Other Appurtenances. 301,467,410.00
9 Miscellaneous 1,207,821,116.00
10 Horticulture 129,834,466.00
A Total Civil Cost (INR) 36,309,631,030.00
B
Additional Cost
Physical Contingencies @ 3% 1,089,288,931.00
Supervision Charges @ 1 % 363,096,310.00
Sub Total Cost (B) 1,452,385,241.00
C Environmental and Mitigation Cost 217,857,786.00
D Land Acquisition and R&R Costs 12,045,335,263.41
E Cost for Shifting of Utilities 1,089,288,931.00
Sub Total Cost (C+D+E) 13,352,481,980.41
TOTAL COST (A+B+C+D+E) 51,114,498,251.41
Total Cost in Crores 5,111.45
Total Cost per Km in Crores 65.21