12
Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700 (km.390.864 of NH-8) of Main Expressway in the state of Maharashtra Document : Feasibility Report Month: Oct 2016 National Highways Authority of India Page 1 of 12 Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700 (km.390.864 of NH-8) of Main Expressway in the state of Maharashtra Feasibility Report A. INTRODUCTION India has about 3.3 million kilometers of road network, which is the second largest road network after United States of America. The roads in the country are either under administrative control of the Union Government or the State Government concerned. Roads in the country carry about 65 percent of freight traffic and 87 percent of passenger traffic. National Highways, the primary road network of the country, are under the Union Government. The aggregate length of National Highways is, at present, 70, 548km which is about 2 percent of the road network but carries about 40 percent of road traffic. Keeping in view of the importance of the National Highways for the economic development, the Government of India has taken up an ambitious program of development of the National Highways under different phases of National Highway Development Program (NHDP). One of the phases of NHDP, namely, NHDP Phase- VI is for development of 1000 km of expressways. The expressways carry large volumes of traffic at high speed and are access controlled. The National Highways Authority of India (NHAI) has been entrusted with the implementation of, inter-alia, NHDP Phase-VI. The construction of about 400 km long Mumbai- Vadodara Expressway is one of the expressways which have been identified for implementation in this phase. This project has been proposed to be implemented under Public Private Partnership mode and to be executed as Design, Build, Finance and Operate (DBFO) contracts. The NHAI, as the employer and the executing agency has commissioned the services of Intercontinental Consultants and Technocrats Private limited (ICT) for carrying out consultancy services for “Preparation of Feasibility cum Preliminary Design Report for Vadodara – Mumbai Expressway under NHDP Phase- VI”. The proposed Vadodra - Mumbai expressway has been divided into three phases for implementation: Phase I: From proposed chainage km 104+700 to chainage km 378+722 in the State of Gujarat, Maharashtra and Union Territory of Dadra and Nagar Haveli. Environmental Clearance has already obtained from MoEF&CC for Phase-I development. Phase II: This section starts from proposed chainage km 26+320 (near Vasai in the state of Maharashtra) to chainage km 104+700 (km 390+864 of NH-8 near Talasari in the state of Maharashtra). Total length is 78.38 km. This Feasibility Report deals with Phase II development of Vadodara Mumbai Expressway (VME). Phase III: From proposed chainage km 0+000 to km 26+320 (26.320 km) in Thane District of Maharashtra.

Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 1 of 12

Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to

km.104.700 (km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Feasibility Report A. INTRODUCTION

India has about 3.3 million kilometers of road network, which is the second largest road

network after United States of America. The roads in the country are either under

administrative control of the Union Government or the State Government concerned.

Roads in the country carry about 65 percent of freight traffic and 87 percent of

passenger traffic. National Highways, the primary road network of the country, are under

the Union Government. The aggregate length of National Highways is, at present, 70,

548km which is about 2 percent of the road network but carries about 40 percent of road

traffic.

Keeping in view of the importance of the National Highways for the economic

development, the Government of India has taken up an ambitious program of

development of the National Highways under different phases of National Highway

Development Program (NHDP). One of the phases of NHDP, namely, NHDP Phase- VI

is for development of 1000 km of expressways. The expressways carry large volumes of

traffic at high speed and are access controlled.

The National Highways Authority of India (NHAI) has been entrusted with the

implementation of, inter-alia, NHDP Phase-VI. The construction of about 400 km long

Mumbai- Vadodara Expressway is one of the expressways which have been identified

for implementation in this phase. This project has been proposed to be implemented

under Public Private Partnership mode and to be executed as Design, Build, Finance

and Operate (DBFO) contracts.

The NHAI, as the employer and the executing agency has commissioned the services of

Intercontinental Consultants and Technocrats Private limited (ICT) for carrying out

consultancy services for “Preparation of Feasibility cum Preliminary Design Report for

Vadodara – Mumbai Expressway under NHDP Phase- VI”.

The proposed Vadodra - Mumbai expressway has been divided into three phases for

implementation:

Phase I: From proposed chainage km 104+700 to chainage km 378+722 in the

State of Gujarat, Maharashtra and Union Territory of Dadra and Nagar Haveli.

Environmental Clearance has already obtained from MoEF&CC for Phase-I

development.

Phase II: This section starts from proposed chainage km 26+320 (near Vasai in the

state of Maharashtra) to chainage km 104+700 (km 390+864 of NH-8 near Talasari

in the state of Maharashtra). Total length is 78.38 km. This Feasibility Report deals

with Phase II development of Vadodara Mumbai Expressway (VME).

Phase III: From proposed chainage km 0+000 to km 26+320 (26.320 km) in Thane

District of Maharashtra.

Page 2: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 2 of 12

B. NEED OF THE PROJECT

The Mumbai–Ahmedabad Corridor in the western part of the country is one of the

important transport corridors of the country. On one side of this corridor is Mumbai

which is the financial capital of the country and on the other side is Vadodara, an

important commercial and business city. There are many industrial centres on this route.

Industries like, textile industry, gems and jewelries, petrochemical & fertilizer and other

industrial complexes have been established along this corridor. This corridor also serves

SEZ areas and ports. Development works of these corridors like improvement of

National Highways, construction of expressways, construction of dedicated railway

freight corridors, modernization of airports located along this corridor have been taken

up. The project road lies within the proposed Delhi Mumbai Industrial corridor which is

being planned as hub of industrial and urban activity.

NH-8 is of great significance for transportation in this corridor starting from the country’s

administrative capital of Delhi to financial capital of Mumbai. Present condition and steps

taken to develop its speed and safety are as follows:

The Vehicle Damage Factor (VDF) as assessed on NH8 section for 2 axle vehicles

varies from 2.04 to 5.86 whereas VDF for 6 axle vehicles were in the range of 19.48

to 25.69.

The average journey speed on Mumbai-Vadodara section of NH 8 was found to be

in the range of 50-60 km/hr (major part of the section) to 80-90 km/hr. whereas a

National Highway is designed for the speed of 100km/hr.

NH8 is carrying traffic in the range of 50,000 to 80,000 PCU per day. It has been

developed as 6 lane recently but many of the sections have already reached nearly

the capacity volume (LOS E) of 6 lane NH (120,000 PCU) in the year 2015.

Even with six laning or further widening, segregation of long distance and local and / or

slow traffic is hard to achieve. Further since it’s a National Highway (not access

controlled) and passes through many settlements land availability and displacement of

people would be a major concern.

C. PROJECT LOCATION

The Phase II of Vadodara Mumbai Expressway (VME) is a greenfield alignment. The

expressway starts at proposed chainage km 26+320 (near Vasai in the state of

Maharashtra) and ends at proposed chainage km 104+700 (km 390+864 of NH-8) near

Talasari in the state of Maharashtra. Total length of the VME Phase-II alignment is

78.38 km. The proposed alignment is passing through 4 talukas (Vasai, Palghar,

Dahanu and Talasari) of Palghar district in the state of Maharashtra. The alignment is

passing through plain and rolling terrain with cultivated and barren areas. On its way, it

crosses Palghar-Manor road, Boisar road, Tarapur, Masvan and Pulachapada Roads

which connects these villages with NH-8 and the alignment ends with a partial cloverleaf

type interchange on NH-8 near Talasari. The project road crosses 51 villages in Palghar

district. The predominant land use along the alignment is agricultural followed by

vegetation cover. The proposed alignment runs parallel to and very near to Rivers

Vaitarna, Surya and Suseri.

Page 3: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 3 of 12

Crossing of River Vaitarna at Ch. km 45+000

Crossing of Surya River

at Ch. km 68+400

Figure-1 Index Map showing the Project Location

D. DESCRIPTION OF THE ALIGNMENT

Section from start point (chainage km 26+320) to Dahanu-Kasa Khurd Road (Km

78+650): In this section the alignment is to the

west (left) of NH 8 and diverges from it. It starts

300 m away from NH 8 and moves away to

about 11.6 km at Km 66+0 before narrowing

the distance to 10.0 km along Dahanu – Kasa

Khurd Road (SH 30). The terrain is generally

plain/ rolling. This section initially runs through

Vaitarna River valley and then starts rising. The

Section is thinly populated, under developed

and where subsistence agriculture is common

occupation. The alignment crosses Vaitarna

River thrice - at Ch. Km 31+00, Ch. Km 35+700 and Ch. Km 45+000. The crossing at

Km 31+00 is 2.2 km upstream (east side) of the

existing railway bridge located near Vaitarna

Railway Station of Western Railway mainline.

The alignment from km 45+00 to km 68+420

runs parallel to Surya River on the eastern side

of the river. The alignment crosses River Surya

at Ch. Km 68+420 and River Suseri at Ch. Km

72+190.The section ends with a diamond

interchange on SH-30.

There are no railway crossings in this section.

The alignment crosses Palghar- Manor road,

Boisar road, Tarapur, Masvan and Pulachapada Roads which connects these villages

with NH8. The alignment passes through Reserved Forest in parts aggregating to a total

length of about 1.75 km. Some parts of this section lie in Coastal Regulation Zone

(CRZ). Total length of the alignment in CRZ is 3.575 km out of which in Vasai (from Km

Page 4: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 4 of 12

29.900 to km 30.434 & km 30.462 to km 30.800) and Palghar Taluka (km 30.800 to km

32.100; km 35.430 to km 36.833).

Section from Dahanu – Kasa Khurd Road (Km 78+650) to NH 8 Crossing (Km

104+700): In this section the alignment moves close to NH 8 up to Ch. km 85+200 (2

km away) and then runs parallel to it before crossing at Ch. Km 104+700 near Talasari.

The alignment is in plain and rolling terrain and passes through very sparsely populated

area without any major obstructions. The alignment crosses River Jogani at Ch. Km

89+600 and River Vadavali at Ch. Km 96+ 200. Agriculture is the main occupations of

the people living along the alignment. At Ch. Km 99+840, the alignment crosses SH-29

to Umargoun and the crossing is 3.4 km west of NH-8 and at Km 91+756 the alignment

crosses SH-31. The sections ends with a partial cloverleaf type interchange on NH-8

near Talasari.

E. TRAFFIC ESTIMATE

For estimation of traffic for the proposed expressway, a regional transport demand

model (RTDM) considering entire study area was developed. The RTDM has been used

by considering a number of parameters during the process of transport demand

generation, distribution in the study area, and assignment on the road network of study

area. For the base year, the model has been calibrated and validated by considering

existing traffic volumes and travel demand pattern observed on major road network in

Gujarat and Maharashtra (running parallel to and feeding to the proposed expressway).

For future scenarios where the proposed expressway exists the traffic gets diverted on

the new facility based on savings in Vehicle Operating Cost (VOC) and Travel Time.

These factors have been inbuilt in to the model by considering generalized cost of travel

based on the VOC established by ‘Road User Cost Study’ conducted by CRRI. Thus

traffic which is likely to travel on the proposed expressway has been arrived at by

considering future growth / development scenario and the traffic diversion from existing

road network. The projected traffic in the proposed expressway and lane configuration

are given below:

Crossing with NH-8

at Ch. Km 104+700 (End Point)

Crossing with SH-29 at Ch. Km 99+840

Page 5: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 5 of 12

Table-1 Estimated Traffic in the Proposed Expressway (Ch. Km 26+320 to 104+700)

Section No. Chainage from/to

Estimated AADT

(in PCU)

Expressway Lane Requirements

2017 2035 2017-2035 2035-2045

Section 2-1 Km 26+320 - Km 78+650 72165 144465 8-lanes 8-lanes

Section 3 Km 78+650 - Km 104+700 68653 137255

F. RIGHT OF WAY

The proposed right of way is 100 m / 120 m in general except at interchanges area.

Chainage wise details of proposed RoW are given in Table-2.

Figure-2 Proposed Cross-section – 8 Lane Divided Carriageway

VME Phase-II

Page 6: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 6 of 12

Table-2 Chainage wise Details of Proposed RoW

Sl. No. Stretches Length

(in Km) PROW Remarks

From To

1 26+300 27+150 0.850 As per Design Interchange Area

2 27+150 31+000 3.850 100

3 31+000 33+850 2.850 100

4 33+850 34+300 0.450 120

5 34+300 35+200 0.900 100

6 35+200 41+700 6.500 120

7 41+700 43+500 1.800 100

8 43+500 46+500 3.000 120

9 46+500 47+400 0.900 100

10 47+400 50+900 3.500 120

11 50+900 53+500 2.600 100

12 53+500 61+500 8.000 120

13 61+500 62+800 1.300 100

14 62+800 64+200 1.400 120

15 64+200 64+900 0.700 100

16 64+900 65+300 0.400 120

17 65+300 67+200 1.900 100

18 67+200 67+700 0.500 120

19 67+700 70+800 3.100 100

20 70+800 77+000 6.200 120

21 77+000 77+900 0.900 100

22 77+900 79+400 1.500 As per Design Interchange Area

23 79+400 80+600 1.200 100

24 80+600 82+800 2.200 120

25 82+800 84+900 2.100 100

26 84+900 86+200 1.300 120

27 86+200 93+300 7.100 100

28 93+300 95+800 2.500 120

29 95+800 99+600 3.800 100

30 99+600 102+000 2.400 120

31 102+000 103+300 1.300 100

32 103+300 106+600 3.300 As per Design Interchange Area

G. LAND ACQUISITION

The tentative land acquisition for VME Phase II is 926.236 Ha. The Taluka wise

proposed land acquisition details in district Palghar are presented in Table-3.

Table-3 Taluka wise details of Land Acquisition

Sl. No. Taluka Land in (Ha.)

1. Talasari 85.093

2. Dahanu 343.558

3. Palghar 442.743

4. Vasai 54.841

Total 926.236

Page 7: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 7 of 12

H. DETAILS OF PROPOSED DEVELOPMENT

The proposed Mumbai- Vadodara Expressway is to be built as an access controlled

expressway with access allowed only at the interchanges. It will be a eight lane divided

carriageway with 12m wide depressed median. The carriageway width is 15 m with 3.0

m wide paved and 3.0 m wide earthen shoulders. Further it is proposed to build service

roads along the expressway at some locations to facilitate movement of local traffic

across expressway. Initially it was proposed to adopt a ROW of 100 m for the

expressway. However during subsequent discussions with NHAI officials it has been

decided to adopt an ROW of 120 m to give adequate space for utilities, plantation of

trees and to avoid construction of retaining walls in high embankment areas.

1. Interchanges

Interchanges are required on expressways for transfer of traffic from the expressways to

other intersecting roads/expressways or vice versa avoiding any conflict. The objective

of provision of interchanges is to allow safe and uninterrupted travel for expressway

users. Interchange is proposed at 2 locations, crossing of Dahanu Kasa Khurd (SH-30)

and crossing of Surat-Dahisar Sect of NH-8. Details are given in Table-4.

Table-4 Details of Interchanges

Sl. No.

Name of Interchange Chainage Length (m)

1 Interchange at Crossing of Dahanu Kasa Khurd (SH-30) 78+638 121.650

2 Interchange at Crossing of Surat-Dahisar Section of NH-8 104+707 131.189

2. Fly-Over

The expressway is an access controlled facility and all other road crossings therefore

will be provided either with a flyover or with a vehicular underpass with no access to the

expressway. Flyovers are proposed at 4 locations. Details are given in Table-5.

Table-5 Details of Fly-overs

Sl. No. Description Chainage Length (m)

1 Flyover Over Boisal - NH-8 Road 60+240 27.250

2 Bridge + Flyover over Tarapur-Charoti Road 73+054 93.100

3 Flyover Over Dhanu-Talasari (SH-31) 91+756 74.662

4 Bridge + Flyover over Umargaun-Talasari (SH-29) 99+882 126.650

3. Vehicular Underpasses

Vehicular underpasses of size 12mx5m have been proposed on Major District Roads

(MDRs) and other minor roads. Vehicular underpasses have been proposed at 15

locations as given in Table-6.

Page 8: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 8 of 12

Table-6 Details of Vehicular Underpass

Sl. No. Chainage (km) Type of Crossing

1. 27+910 Virar - Khardi

2. 29+202 Fanas Pada - Virar

3. 32+339 Safale - Navghar

4. 38+653 Safale - NH 8

5. 43+849 Sakhade - NH 8

6. 46+396 Dolpada - Vadoli

7. 50+594 Palghar - Manor

8. 55+135 Palghar - Nagazari

9. 61+191 Kirat - Boisar

10. 65+057 Kirat - Ravte

11. 67+471 Chincharet - Ravet

12. 70+859 Aina - Naikapada

13. 81+660 Rankol - Charoti

14. 95+635 Gajad - dhanivari

15. 96+983 Vadavali - NH 8

4. Vehicular Overpass

At some locations where cross roads have been proposed to cross as elevated sections

on the expressway. 3 such overpasses of size 2 x 41 m span have been proposed at

following locations.

Table-7 Details of Vehicular Underpass

Sl. No. Chainage (km) Type of Crossing

1. 89+308 Asgarh - Chanchol

2. 101+912 Jhari - Talasari

3. 102+365 Kawada - Babuapada

5. Pedestrian / Cattle Underpasses

The expressway is a greenfield alignment and is access controlled therefore it will be

bifurcating the communities on either side. Since it is passing mainly through rural belt

the farming communities on either side need to be provided with suitable connection. To

serve this purpose, 26 pedestrian underpasses and 47 cattle underpasses of size

6mx3.5m have been proposed.

6. Bridges

The expressway alignment is crossing major / minor rivers, drains and nala at number of

locations where major / minor bridges have been proposed as per hydraulic

considerations. 8 major bridges (Table-8) and 29 minor bridges (Table-9) have been

proposed.

Page 9: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 9 of 12

Table-8 Details of Major Bridge

Sl. No. Description Chainage Length (m)

1 Major Bridge over Vaitrana River - 1 31+300 1968.05

2 Major Bridge over Vaitrana River - 2 35+725 576.05

3 Major Bridge over canal + road 42+858 68.334

4 Major Bridge over canal + road 43+725 67.213

5 Major Bridge over Vaitrana River - 3 45+040 672.05

6 Major Bridge over Surya River 68+420 236.05

7 Major Bridge over Suseri Nallah 72+190 111.65

8 Major Bridge over Vadvali Nadi 96+208 96.65

Total Length (m) 3796.047

Table-9 Details of Minor Bridges over Rivers / Streams / Nallas / Utility

Sl. No. Description Chainage Length (m)

1. Minor Bridge over Local Nallah 37+780 27.353

2. Minor Bridge over Local Channel 37+965 19.162

3. Minor Bridge over Guljari Nallah 48+393 32.250

4. Minor Bridge over Local Channel 50+208 15.900

5. Minor Bridge over Local Nallah 52+728 12.551

6. Minor Bridge over Stream 54+310 27.250

7. Minor Bridge over Stream 57+885 29.250

8. Minor Bridge over Stream 59+888 37.250

9. Minor Bridge over Canal 60+712 29.255

10. Minor Bridge over Local Stream 61+539 19.162

11. Minor Bridge over Canal 62+421 21.373

12. Minor Bridge over Stream 63+570 32.250

13. Minor Bridge over Stream 63+925 15.900

14. Minor Bridge over Canal 65+134 39.631

15. Minor Bridge over Stream 66+137 12.440

16. Minor Bridge over Nallah 66+735 15.900

17. Minor Bridge over Stream 70+000 27.250

18. Minor Bridge over Stream 74+493 20.900

19. Minor Bridge over Canal 76+037 29.255

20. Minor Bridge over Jagani Nadi 79+745 21.940

21. Minor Bridge over Stream 81+330 27.372

22. Minor Bridge over Jagani Nadi 83+620 21.940

23. Minor Bridge over Stream 85+420 20.900

24. Minor Bridge over Jagani Nadi 89+604 50.973

25. Minor Bridge over Stream 91+564 15.900

26. Minor Bridge over Canal 93+650 27.848

27. Minor Bridge over Canal 94+491 29.250

28. Minor Bridge over Nallah 103+430 20.900

29. Minor Bridge over Gas Pipe Line 103+998 46.549

Total Length (m) 747.854

Page 10: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 10 of 12

7. Culverts

75 RCC box culverts (73 on main & 2 on the loop / ramps of interchanges) and 25 Hume

pipe culverts are proposed across the main alignment to prevent disturbance of the

natural and artificial drainage system.

8. Service Roads

The roads where underpasses have not been provided have been connected to the

nearest underpass by service roads so that the movement of local traffic across the

expressway is not hindered. Service roads have also been provided at in the urban

areas. Total length of service road is 9.390 km. Locations of service road are presented

in Table-10.

Table-10 Details of Service Road

Sl. No. Stretches

Length (Km) Width (m) From (km) To (km)

Main Expressway Phase II (Left Service Road)

1. 38+640 39+000 0.360 5.50

2. 47+650 47+970 0.320 5.50

3. 54+965 55+150 0.185 5.50

4. 56+960 57+400 0.440 5.50

5. 60+975 61+350 0.375 5.50

6. 63+140 63+230 0.090 5.50

7. 65+085 65+230 0.145 5.50

8. 67+450 67+675 0.225 5.50

9. 70+850 71+960 1.110 5.50

10. 72+370 72+660 0.290 5.50

11. 73+750 74+000 0.250 5.50

12. 80+640 80+980 0.340 5.50

13. 81+630 82+650 1.020 5.50

14. 85+050 85+300 0.250 5.50

Sub-Total (A) 5.40

Main Expressway Phase II (Right Service Road)

1. 47+700 48+000 0.300 5.50

2. 48+650 48+850 0.200 5.50

3. 50+600 50+850 0.250 5.50

4. 55+080 55+260 0.180 5.50

5. 55+840 55+970 0.130 5.50

6. 63+140 63+230 0.090 5.50

7. 75+600 76+065 0.465 5.50

8. 81+660 82+650 0.990 5.50

9. 85+130 85+390 0.260 5.50

10. 95+200 95+625 0.425 5.50

Sub-Total (B) 3.29

Page 11: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 11 of 12

Sl. No. Stretches

Length (Km) Width (m) From (km) To (km)

At Interchange Area (Left Service Road)

Int.

Location

Stretches Length (Km) Width (m)

From (km) To (km)

26+320 0+000 0+450 0.450 5.50

78+650 0+000 0+250 0.250 5.50

Sub-Total (C) 0.700

TOTAL = (A+B+C) 9.390

9. Way Side Amenities and Truck Parking

Wayside amenities along the expressway are integral parts and these facilities provide

useful services to the traveling public. These facilities provide services to the users who

desire to stop for rest, refreshment, information and fuelling or for some emergency

requirement. To facilitate the road user, way side amenities and truck parking has been

proposed along the expressway. The locations are as follows

Table-11 Details of Way Side Amenities and Truck Parking

Sl. No. Location Side

Way side Amenities (Type-A)

1 90+100 Left

2 90+600 Right

Way side Amenities (Type-B)

1 42+000 Left

2 47+500 Right

3 67+900 Left

4 70+400 Right

Truck Parking

1 41+000 Right

2 49+300 Left

10. Toll Plaza

For each interchange a suitable type from the standard configuration or a modified one

has been adopted based on the land constraints and requirement of traffic. Accordingly,

a full clover leaf interchange is having four separate toll plazas or partial clover leaf with

less number of toll plazas, and appropriate trumpet interchange at the start and end with

single main line toll plaza. The toll lanes have been estimated for horizon year 2035 and

2045 considering that, in the opening year, toll plazas will be constructed to cater for the

requirements for next 20 years and by 2035 the toll plazas can be expanded for the

requirements of year 2045. Toll plaza has been proposed at 6 locations (on loop /

ramp).

Page 12: Feasibility Report - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/Online/TOR/26...Document : Feasibility Report Month: Oct 2016 National Highways Authority of India

Project : Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700

(km.390.864 of NH-8) of Main Expressway in the state of Maharashtra

Document : Feasibility Report Month: Oct 2016

National Highways Authority of India Page 12 of 12

11. Road Safety

Road safety aspects have been well studied and several safety features like road

marking, traffic sign, safety barriers, boundary stones, kilometer stones and hectometer

stones, pavement marking and lighting has been proposed. The engineering design of

the road has also considered IRC codal provisions related to road safety such as:

IRC: SP: 32-1988 Road Safety for Children

IRC: SP: 44-1994 Highway Safety Code

IRC: SP: 55-2001 Guidelines for Safety in Construction Zones

IRC:119:2015 Guidelines for Traffic Safety Barriers

I. PROJECT COST

The tentative Civil Cost works out to be as under:

Table-12 Total Project Cost (in INR Cr.)

S No. Description Total Cost (INR)

1 Site Clearance and Dismantling 35,629,995.00

2 Earthwork 7,039,653,679.00

3 Granular Base Course and Sub - Base 4,002,969,139.00

4 Bituminous Course 4,235,397,295.00

5 Culverts 836,774,824.00

6(A) Major Bridges 8,428,068,519.00

6(B) Minor Bridges, Canal Bridges, Gas Pipe Lines 2,693,443,698.00

6(C) Interchanges, Flyovers and ROB's 1,136,713,373.00

6(D) Underpasses / Overpasses 2,648,478,423.00

7 Drainage Works and Protection Works 3,613,379,093.00

8 Traffic Signs, Markings and Other Appurtenances. 301,467,410.00

9 Miscellaneous 1,207,821,116.00

10 Horticulture 129,834,466.00

A Total Civil Cost (INR) 36,309,631,030.00

B

Additional Cost

Physical Contingencies @ 3% 1,089,288,931.00

Supervision Charges @ 1 % 363,096,310.00

Sub Total Cost (B) 1,452,385,241.00

C Environmental and Mitigation Cost 217,857,786.00

D Land Acquisition and R&R Costs 12,045,335,263.41

E Cost for Shifting of Utilities 1,089,288,931.00

Sub Total Cost (C+D+E) 13,352,481,980.41

TOTAL COST (A+B+C+D+E) 51,114,498,251.41

Total Cost in Crores 5,111.45

Total Cost per Km in Crores 65.21