Upload
vokhanh
View
225
Download
4
Embed Size (px)
Citation preview
FAUZAN RUMZI
PERSONAL DATA Name : Fauzan Rumzi, ST
Address : Jln. Nuh No.10
RT/RW.03/10
Kelurahan: Suka Bumi Utara
Kecamatan: Kebun Jeruk
Kotamadya: Jakarta Barat
DKI Jakarta 11540 - Indonesia
E-mail address : [email protected]
Mobile : Indonesia (+62) 081363335300 or 085215191619
Place, date of birth: Bukittinggi, January 13, 1975
Gender : Male
Marital status : Married
Nationality : Indonesia
Language : Indonesia and English
Qualifications and Certificate (Certified): API 653 (Tank Inspector)
Quality Management System Auditor/Lead Auditor (IRCA 17399)
Welding Inspector CSWIP 3.1
Welding Inspector CSWIP 3.0
Welding Inspector MIGAS - B4T
Radiographic Interpreter ASNT Level 2 (NDT- RI)
Penetrant ASNT Level 2 (NDT - PT)
Magnetic Particle ASNT Level 2 (NDT- MT)
General Paint School Generic Type of Points Pre-
BlastingPreparation, PreTreatment, Application, Calculationb Jotun Paint
Computer Course
English Extension Course
EDUCATION BACKGROUND: 1996 – 2001 : Graduated from Degree (S-1) University of Eka Sakti
In Padang – Indonesia, Majoring Mechanical Engineering
1991 – 1994 : Graduated from Senior High School of SMUN 01
In Bukittinggi – Indonesia
1989 – 1991 : Graduated from Junior High School of SMPN 05
In Bukittinggi - Indonesia
1984 – 1989 : Graduated from Elementary School of SDN 14
In Bukittinggi – Indonesia
Summary and Qualification: √. API 653 (Tank Inspector)
Conducted by The Welding Institute (TWI) UK, London and PT. Beyond
Training on PT. Chevron Pacific Indonesia to Chevron Center Rumbai – Pekan
Baru/Riau.
√. Quality Management System
Quality Management System Auditor / Lead Auditor (IRCA Certification
A17399).
PT Neville Clarke Indonesia, Graha Indramas 4th Floor, J1.AIPDA KS Tubun
Raya No.77 Jakarta 11410 Email: [email protected]
√. Welding Inspector CSWIP 3.1(Welding Inspector International)
Welding Inspector International Certification of CSWIP 3.1 Training,
Conducted by The Welding Institute (TWI) UK, London and PT. Beyond
Training on
Jl. Kaliurang KM. 5, Ladrang no.4A, CT III, Utara Hotel Vidi 1
Sleman – YOGYAKARTA (55281) Email: [email protected]
Period December 7, 2009 to December 11, 2009. CSWIP 3.1 Certificate no :(
48856)
Welding lecturer & Executive is Mr Mohd Sulaiman Abbas
√. Visual Welding Inspector CSWIP 3.0(Visual Welding Inspector
International)
Visual Welding Inspector International Certification of CSWIP 3.0 Training,
conducted by The Welding Institute (TWI) UK, London .Presented by PT. Dua
Utama Jaya. Jl. Yos Sudarso, Complex Green Town Warehouse No. 2, Bengkong –
Batam. Email: [email protected]
Period November 22, 2007 to November 30, 2007.CSWIP 3.0 Certificate No:
(31758)
Welding lecturer & Executive is Mr Mohd Darus Bin Taib
√. Welding Inspector MIGAS (IWS/International Welding
Specialist) WELDING INSPECTOR ( IWS )
Presented by Balai Besar Bahan and Barang Teknik (B4T- Bandung) supported by
MIGAS
(Oil and Gas Department) and DEPNAKER (Labor Department)
Period November 10, 2002 until February 10, 2003.Certificate no. (0203.12.61)
B4T-Bandung.Jln.Sangkuriang no.14 Bandung – Indonesia
√. ASNT Radiographic Interpreter (RI) Level II
Training & Qualification. Certificate no. (116/RI/N/10)
SNT-TC-1A,2006 edition.
August 10, 2010 toAugust 25, 2010 Duri/Riau – Indonesia.
Edi Padmo, ST. (ASNT/NDT LEVEL III)
√. ASNT Magnetic Particle Test (MT) Level II
Participant ASNT MAGNETIC PARTICLE TESTING LEVEL.II Training &
Qualification. Certificate no.(SMS-MT-08068)
August 10, 2008 toAugust 25, 2008 Jakarta – Indonesia.
Sainal Rapi. (ASNT/NDT LEVEL III)
√. ASNT Penetrant Test (PT) Level II
Training & Qualification. Certificate no.(SMS-PT-08027)
August 10, 2008 toAugust 25, 2008 Jakarta – Indonesia.
√. General Paint School
Generic Type of Points Pre-Blasting
Preparation, Pre- Treatment, Application, Calculationb
Jotun Paint School Certification of Attendance.
√. COMPUTER COURSE
Windows, Microsoft word, Microsoft Excel and Microsoft Power point, Intro
to Multi Media, Intro to Internet.
Certificate no.2282 C.LPKP-Q.IV.2002. Period November 12, 2001 until April 12,
2002 Presented by Quantum Computer.
Padang – Sumatra Barat. West Sumatra Indonesia
√. English Extension Course
Speaking, Reading, Listening, Writing
Certificate no.1326.E.LPKP-Q.V .2002 Period November 12, 2001 until April
12, 2002 Presented by Quantum Computer.
Padang – Sumatra Barat. West Sumatra Indonesia
MEMBERSHIP: Fellow Member, the International Association of Quality Practitioners. (IAQP)
Member Associate Member, the Welding Institute. (TWI) Member, the
Indonesia Welding Society. (IWS - API)
Graduate Member, the American Institute of Non-Destructive Testing. (ASNT)
Associate Member, the Chartered Quality Institute. (CQI)
EXPERIENCE 11 YEAR. Having more than 11 years in Oil & Gas and Petrochemical Project at EPC and
Flexible Program Management Service and Fabrication Company as Field
Engineer, QC Inspector, QC Tank Inspector, Senior Tank Inspector, QC Piping
Inspector, Welding Inspector, Senior Welding Inspector and QA/QC
Coordinator, Asst QA/QC Manager. Scope of work in piping gas station likes
inspection line check of piping system, review P&ID, prepare test package for
pre-commissioning-commissioning, facilities acceptance line check inspection.
Inspection for mechanical equipment and static equipment fabrication (Pressure
Vessel, Column, Heat Exchanger, Air Cooler, Pig receiver/Launcher, Package
equipment and storage Tank). Other scope as supervision develops and reviewed
procedure for quality management system (QMS), Fabrication Procedure, NDE
procedure, painting-coating procedure, materials inspection and review mill
certificate, WPS/PQR. Familiar with QA/QC document system and traceability
record, ability with computer literate, familiar with standard related with oil &
gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,
Petrochemical, Pawer Plan, Oil&LPG Tank Terminal Project,Flexible Program
Management Service.
Skills:
- Capable to conduct onshore/offshore pre-commissioning, Testing and commissioning activities of piping and
Mechanical systems.
- Capable in fabrication, installation, periodic/annual
Inspection & quality control/assurance of non-destructive
Test for oil & gas production, off shore platform, pressure vessels, heat
Exchanger, boiler, pipeline, all Tank, piping welding inspection,
Tank welding inspection.
- Capable for technical review of document, WPS, drawing and field
Inspection of pressure vessels, storage tank, process piping, pipeline,
Flow line, Prodection line and off shore platform.
- Familiar with international standard and codes such as: AWS, ASME,
API, ANSI, British Standard, NACE and other codes.
- Capable to operate non-destructive test non-radiation and interpreting
Film of Radiographic test.
- I have experience in various welding process and various codes like
ASMEB31.1, ASMEB31.3, ASMEB31.4. ASMEB31.8, ASMESec-IX,
ASMESecVIII, API-1104, API-650, API-653, API-570, API-510.
DUTIES:
Having the aptitude and experience in communicating with personnel and
management of multi disciplined
nationalities, and delegation thereof.
Continued project progression occurs, when one is able to liaise between client,
contractor or third parties,
efficiently and effectively.
GENERAL: (Experienced with the under mentioned welding material and
processes.)
Welding processes: SMAW, GTAW, MIG, SAW, FCAW, CRC, STT.
Materials: Low temperature carbon steel, medium carbon steel,
ferritic/austentic stainless steel,
Titanium metals et cetera, Duplex stainless steel, Inconel, Incoalloy and copper
nickel.
Knowledgeable of quality assurance functions, such as compilation of:
Quality Assurance Manuals Procedures Inspection and Test Plans
Project Completion Dossiers Isometric mark up and line checks
PROFESSIONAL WORKING EXPERIENCE,
Company : PT. Tripatra Fluor Consortium (Client/Owner Representative)
Project and Maintenance: Chevron Pacific Indonesia -
Flexible Program Management Service
Discipline of Work: CGS, GS, POP, Onnflot, offlot and all piping: Stem Line,
Gas Line, Product Line, Flow Line, Pipe Line (Oil and Gas)
Position : QA/QC Senior Piping Inspector
Year : 27 March 2011 to Present
Location : SLN – REM – CMT and IM - LIBO (Duri – Riau)
Client/Owner : Chevron Pacific Indonesia
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED
Reviewing all the procedure WPS, PQR , NDE Procedure and NDE
Technician Certificate , Equipment calibration Certificate., HYDROTEST
Procedure, and Equipment Calibration Certificate & Pigging Procedure.
Witness of Welding Qualification Test by Contractor
Reviewing Material Certificate & Check Quality Material
Reviewing ITP & SOP
Reviewing Drawing & P&ID
Visual Inspection of the pipe to be used (measurement, cutting, beveling,
alignment & Fit-up
Monitoring of Welding Consumable, Handling & Storage
Conduct welding Inspection during Construction, Installation & Tie-in.
Monitoring & Inspecting that the Contractor doing all required, satisfied
and meet to the Requirement of the Standard, Specification as API 5L,
API 1104, ANSI B 31.8 ASME IX, API 650, API 653, API 510, API 2201,
API 570 & Engineering Design.
To take up the spot of Radiography Test & other NDE.
Reviewing & Aproval Welding Records Traceability at QC document
Constractor
Reviewing the Completed document Package for Hydrostatic Test
Line Check/Puch List Check as Per Test Packet
Witness Hydrostatic Test , Pigging & Flushing, Review & Aproved Report
Monitoring & Inspection Aplication Procedure & Standard at Field
Prepared Procedure For Repair Tank According API 653 Standard,
Review Welder Qualification According ASME IX Standard, Witness &
Review Result Wall Thickness measurement According Guid Line for
Repair Tank & Aproved Report Wall Thickness.
Prepared Procedure Pressure Vessel According ASME VIII Standard,
Witness & Review Result Wall thickness Measurement According Guide
Line for Repair Vessel & Aproved Report Wall Thickness.
Prepared Hot Tap Permite for Install Spool MPFM Header Flow Line
Prepared Surveiilance Report send to QA/QC ManagerTF & CPI.
Final Review Completed package Document Constractor Before Approved
CPI.
Conduct Montly Meeting with CPI CMT REM C
- Libo pipe Repalacement : Well Location LIBO # 03, # 20, # 53, # 48 & 6’
Mandar Gas Line
- LIBO GP. Improvement Flare Stack
- Petani pipe Replacement, well Location PETANI # 17, # 25
- Hiu Cucut Pipe Repalcement, well location HIU # 03, CUCUt # 01
- Pematang Pipe Replacement,well location PMTG #16, # 41, # 61,#32
- Pematang 10’ pipe Replacement
- Rangau Gs , Repair Test Tank
- Bekasap GS , Wash Tank Repair III
- Petani GP Improve piping system Corroded
- Petani GP Improve Install VRU
- Pematang GP Improve pematang Dehydration
Company : PT.Toyo Kanetshu Indonesia
Discipline of Work: Storage TANK / LNG, LPG – Spherical Tank, Water Tank
Position : QA/QC Asst Manager
Year : 30 December 2010 – 21 March 30, 2011
Location : LNG Tangguh WWT/BP - Papua
Client : PT. BP Indonesia
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test
Incoming material Inspection and check thickness material inspection
Dimensional control of fabrication
(Cutting and rolling Plate) pipe and all Accessories of storage tank
Dimensional check and visual inspection of steel structure
Control all visual inspection report fabrication
Training of new welder test before WQT.
Welder performance Qualification
Test per approved WPS.
Responsible to weld product and weld sequence
WQT for storage tank and prepare Welder ID and welder list.
Dimensional check: Plamb,Roundness, Levelness, Peking Banding and
Accessories orientation
Checking welding consumable prior to Welding and during welding
Visual inspection completed weld
Perform welding inspection works before, during, and after welding in
accordance with ITP, Project specification, Codes & Standard.
Coordinate the performance the performance of NDT & PWHT works
in accordance with ITP, Project specification, Codes & Standard.
Verify that approved WPS is available; welder is qualified with the
process and AFC drawing.
Ensure full coverage of all Fit-Up, welding works, & NDT/PWHT
activities.
Ensure that QC inspection program is being implemented accordingly.
Perform and or/coordination welder qualification test.
Notification to client of the inspection schedule.
Liaise with client field inspection.
Perform & Supervise performance of material receiving inspection.
Dimensional check storage tank before welding (Plumb, Roundness,
Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior
to welding.
Inspection checks Dimensional orientation shell nozzle and Roof
nozzle and Shell, Roof manhole.
Perform joint Fit-Up inspection & ensure dimensional check.
Check weld end preparation, tacking method, electrode used, pre-heat
requirement, inter-pass temperature & cleaning in accordance with
WPS.
Check welding parameter & welding consumables.
Perform final welding visual inspection in accordance with acceptance
criteria.
Identify weld requiring NDT & coordinate for NDT performance
Coordinate weld repair work in accordance with the repair procedure.
Review report & ensure that reports are prepared whenever required.
Responsible and Supervision of the Fit up and Erection (check
dimensional, orientation as per drawing) on the shell plate, Bottom
Plate, Bottom Annular, Suspended deck, Roof Plate, Compressor Ring,
Roof Structure, Stiffener Ring.
Responsible and Supervision of the Air Rissing work of Roof included
suspended
deck for Nh 20 Tank
Monitoring of weld rejection rate & NDT performance status.
Prepared Welding MAP
Prepared RT MAP
Prepared thickness MAP
Interpreted RT films & review PWHT charts.
Preparing document test package for Hydro test / Pneumatic test
Witness hydro testing, air leak testing & flushing.
Witness after hydro testing , solution film testing (SFT)
Line check and re-instatement of piping system, punch list and final
acceptance.
Preparing daily inspection report and manufacture data report (MDR.)
Company : PT. URAWA REKAYASA MANDIRI
Engineering –Contractor –Supplier
http://www.urawa.co.id
Discipline of Work: NEW 16’’ & 20’’PROD.LINE FROM TILAN BOOSTER TO
PAGER G.S. AT PAGER FIELD. (Pipe Line, Rood Crossing,
EXP. LOOP)
& NEW 16’’ & 12’’ PIPE PROD.LINE UPGRADE KOTA BATAK
OPERATION. (Pipe Line, Rood Crossing, EXP. LOOP)
Position : QA/QC Coordinator
Year : December 23, 2009 – December 24, 2010
Location : SLS/Duri-TILAN BOSTER # 9 (RIAU) &
SLN/MINAS – Kota Batak /SLS AREA KOPET (RIAU)
Client : PT. CHEVRON
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test
Responsibilities Carryout Inspection in accordance with ITP
Inspection of incoming Equipments and Bulk materials
Regular Inspection Construction activities
Inspection of Local fabricators work related to the Project
Verify the agreed corrective actions to Non-conformance Reports
Witness selected NDT activities
Inspection Flange faces serration
Witness of Flanges Bolt tightening
Witness of Hydrostatic and Pneumatic test
Review the Sub contractors documents
Final review on Test Packs
Inspection of 8",12",16",20",24" dia 32 km Pipe line for SLN or
SLS/Duri-TILAN BOSTER # 9 (RIAU) & SLN/MINAS – Kota Batak
/SLS AREA KOPET (RIAU) cHEVRON Project
Incoming material Inspection and check thickness material inspection
Dimensional control of fabrication
(Cutting pipe and all Accessories of Pipe line.
Dimensional check and visual inspection of steel structure
Control all visual inspection report fabrication
Training of new welder test before WQT.
Welder performance Qualification
Test per approved WPS.
Responsible to weld product and weld sequence
WQT for storage tank and prepare Welder ID and welder list.
Witness welding procedure qualification test piping system
Witness welding procedure qualification test for pipe line
Witness mechanical test for qualification procedure
Monitoring Fabrication Pig Receiver and pig Launcher and review all
document and NDT Report.
Monitoring Fabrication steel structure pipe rack and operation
building.
Visual check, Dimensional face to face, and to end Hydrostatic of
valves.
Monitoring fabrication storage tanks.
Witness PWHT Clean out door for storage tanks.
Witness Various Inspection piping welding activities for various
material verification such as fit-up visual inspection, preheating and
post weld heat treatment, dye leak test line check and Hydrostatic
test.
Witness Calibration pump
Inspection of all incoming material
Witness and dimensional check cold bending pipe
Responsible and supervising of insulation hot & cold in the boiler,
vessel, exchanger, tank, piping, and etc.
Responsible and supervision of painting the tank, vessel, exchanger,
pump & motor, piping, structure and etc.
Review and Record Inspection Report as per Job Specification
Counduct line check and punch list with engineering and owner.
Visual inspection of welding work and verification quality welded by
destructive and non-destructive.
Witness with owner of vacum test, pad Leak Test, penetrant Test and
Hydro Test.
Inspection Coating pipe with holiday detector.
Interpretation RT film
Prepared history sheet for control all report: Material, welding,
trencing, coating, Backlfilling.
Prepared history sheet for complete test Package well flow line and
weld head piping.
Witness Gauging, pigging, flashing, Hydrostatic and pressure test.
Company : PT.Bangun Bejana Baja
Engineering & Construction (BBB)
Discipline of Work: Storage TANK (MOGAS and DIESEL)
Position : Senior Welding Inspection (WI) /ALL NDT & NDE
Year : July 12, 2008 to 23 October 2009)
Location : Tanjung Priok (PROJECT JAKARTA TANK TERMINAL)
(JAKARTA UTARA)(20 TANK Doom Roof)
Client : PT. VOPAK/JTT (BELANDA)
DUTIES AND RESPONSIBILITIES:
E OF DUTY & ACTIVITIES INVOLVEDSCOP Witness welding procedure qualification test
Incoming material Inspection and check thickness material inspection
Dimensional control of fabrication
(Cutting and rolling Plate) pipe and all Accessories of storage tank
Dimensional check and visual inspection of steel structure
Control all visual inspection report fabrication
Training of new welder test before WQT.
Welder performance Qualification
Test per approved WPS.
Responsible to weld product and weld sequence
WQT for storage tank and prepare Welder ID and welder list.
Dimensional check: Plamb,Roundness, Levelness, Peking Banding and
Accessories orientation
Checking welding consumable prior to Welding and during welding
Visual inspection completed weld
Perform welding inspection works before, during, and after welding in
accordance with ITP, Project specification, Codes & Standard.
Coordinate the performance the performance of NDT & PWHT works
in accordance with ITP, Project specification, Codes & Standard.
Verify that approved WPS is available; welder is qualified with the
process and AFC drawing.
Ensure full coverage of all Fit-Up, welding works, & NDT/PWHT
activities.
Ensure that QC inspection program is being implemented accordingly.
Perform and or/coordination welder qualification test.
Notification to client of the inspection schedule.
Liaise with client field inspection.
Perform & Supervise performance of material receiving inspection.
Dimensional check storage tank before welding (Plumb, Roundness,
Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior
to welding.
Inspection checks Dimensional orientation shell nozzle and Roof
nozzle and Shell, Roof manhole.
Perform joint Fit-Up inspection & ensure dimensional check.
Check weld end preparation, tacking method, electrode used, pre-heat
requirement, inter-pass temperature & cleaning in accordance with
WPS.
Check welding parameter & welding consumables.
Perform final welding visual inspection in accordance with acceptance
criteria.
Identify weld requiring NDT & coordinate for NDT performance
Coordinate weld repair work in accordance with the repair procedure.
Review report & ensure that reports are prepared whenever required.
Responsible and Supervision of the Fit up and Erection (check
dimensional, orientation as per drawing) on the shell plate, Bottom
Plate, Bottom Annular, Suspended deck, Roof Plate, Compressor Ring,
Roof Structure, Stiffener Ring.
Responsible and Supervision of the Air Rissing work of Roof included
suspended
deck for Nh 20 Tank
Monitoring of weld rejection rate & NDT performance status.
Prepared Welding MAP
Prepared RT MAP
Prepared thickness MAP
Interpreted RT films & review PWHT charts.
Preparing document test package for Hydro test / Pneumatic test
Witness hydro testing, air leak testing & flushing.
Witness after hydro testing , solution film testing (SFT)
Line check and re-instatement of piping system, punch list and final
acceptance.
Preparing daily inspection report and manufacture data report (MDR.)
Company : PT.TIMAS SUPLINDO
Engineering & Construction
Discipline of Work: Mechanical & Piping, Storage TANK
Position : Senior Piping Inspector
Year : Desember, 20, 2007 to Mart, 27, 2008
Location : Project PM#8 & MB#23 Indah Kiat – Perawang
(RIAU).
PROJECT:
Project PM#8 & MB#23 Indah Kiat Process Pabrik / Storage Tank (Construct
and erect, Storage Tank (Double-Tank / Shell Inside Nickel 9%,Paiping
TITANIUM Reactor,Dabel Defuser Tank Pixel,Stinlis Tank ( 13 Tank ),Sat Down
Piping,Tae In Piping ( 7500/Isometrit-Drawing)
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test piping system
Witness welding procedure qualification test for pipe line
Witness mechanical test for qualification procedure
Monitoring Fabrication Pig Receiver and pig Launcher and review all
document and NDT Report.
Monitoring Fabrication steel structure pipe rack and operation
building.
Visual check, Dimensional face to face, and to end Hydrostatic of
valves.
Monitoring fabrication storage tanks.
Witness PWHT Clean out door for storage tanks.
Witness Various Inspection piping welding activities for various
material verification such as fit-up visual inspection, preheating and
post weld heat treatment, dye leak test line check and Hydrostatic
test.
Witness Calibration pump
Inspection of all incoming material
Witness and dimensional check cold bending pipe
Responsible and supervising of insulation hot & cold in the boiler,
vessel, exchanger, tank, piping, and etc.
Responsible and supervision of painting the tank, vessel, exchanger,
pump & motor, piping, structure and etc.
Review and Record Inspection Report as per Job Specification
Counduct line check and punch list with engineering and owner.
Visual inspection of welding work and verification quality welded by
destructive and non-destructive.
Witness with owner of vacum test, pad Leak Test, penetrant Test and
Hydro Test.
Inspection Coating pipe with holiday detector.
Interpretation RT film
Prepared history sheet for control all report: Material, welding,
trencing, coating, Backlfilling.
Prepared history sheet for complete test Package well flow line and
weld head piping.
Witness Gauging, pigging, flashing, Hydrostatic and pressure test.
Company : TKK/TKI (TOYO KANETSHU INDONESIA)
Position : Senior Tank Inspector (All NDT)
Year : April, 04, 2007 to November, 17, 2007
Location : PAPUA – INDONESIA/ PROJECT TANGGUH LNG
BP PROJECT TANGGUH LNG
Client : PT. BP (British Petroleum)
PROJECT:
Tangguh LNG Onshore Project LNG Storage Facilies E P C of LNG Storage Tank
(Construction and erect 11, Storage Tank (Double-Tank / Shell outside plate and
Shell inside Nickel 9%, Double Dome Roof. Roof outside Congrete and Roof
inside Plat Carbons, Deck Floating Roof Almunium. (ALL 11 Tanks/ 2 LNG TANK)
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED
Incoming material Inspection
Dimensional control of fabrication
(Cutting and rolling Plate) pipe and all Accessories of storage tank
Control all report fabrication.
Training of new welder test before WQT.
Welder performance Qualification
Test per approved WPS.
Checking welding consumable prior to Welding and during welding.
WQT for storage tank and prepare Welder ID and welder list.
Inspection of welding sequence, Distortion control prior to welding.
Witness and Prepared all Leak test,Vacum box test report
Witness and Prepared all PENETRANT TESTING (PT) report
Monitoring welding activities and prepared joint number system.
Final visual inspection of welding joint.
Dimensional check storage tank before welding (Plumb, Roundness, Levelness,
Responsible and Supervision of the Fit up and Erection (check dimensional,
orientation as per drawing) on the shell plate, Bottom Plate, Bottom Annular,
Suspended deck, Roof Plate, Compressor Ring, Roof Structure, Stiffener Ring.
Responsible and Supervision of the Air Rissing work of Roof included suspended
deck for Nh 3 Tank.
Paking and Banding) and fit – up Manhole and Nozzle prior to welding.
Prepared Material traceability MAP
Prepared Welding MAP
Prepared RT MAP
Prepared thickness MAP
Prepared PMI MAP
Prepared joint number system/RT film marking system
Coordinate the performance the performance of NDT & PWHT works in
accordance with ITP, Project specification, Codes & Standard.
Verify that approved WPS is available; welder is qualified with the process and
AFC drawing.
Ensure that QC inspection program is being implemented accordingly.
Notification to client of the inspection schedule.
Liaise with client field inspection.
Perform & Supervise performance of material receiving inspection.
Perform joint Fit-Up inspection & ensure dimensional check.
Check weld end preparation, tacking method, electrode used, pre-heat
requirement, inter-pass temperature & cleaning in accordance with WPS.
Check welding parameter & welding consumables.
Perform final welding visual inspection in accordance with acceptance criteria.
Identify weld requiring NDT & coordinate for NDT performance
Coordinate weld repair work in accordance with the repair procedure.
Review report & ensure that reports are prepared whenever required.
Monitoring of weld rejection rate & NDT performance status.
Interpreted RT films & review PWHT charts.
Preparing document test package for Hydro test / Pneumatic test
Witness hydro testing, air leak testing & flushing.
Witness after hydro testing , solution film testing (SFT)
Line check and re-instatement of piping system, punch list and final acceptance.
Preparing daily inspection report and manufacture data report (MDR.)
Company : IHI (Ishikawa jima-Harima Heavy Industries
Co., Ltd.) SHI – QATAR CO.W.L.L.
(Qatar Branch)
Position : QC Tank Inspector
Year : February 12, 2006 to April 01, 2007.
Location : RAS LAFFAN INDUSTRI CITY. (QATAR LIQUEFIED
GAS COMPANY LIMITED (II) / Project Qatar Gas II
Client : PT. QATAR GAS (QATAR.)
PROJECT:
QG II Onshore Project LNG Storage Facilies E P C of LNG Storage Tank
(Construct and erect 05, Storage Tank (Double-Tank / Shell outside Concrete
and Shell inside Nickel 9%, Double Dome Roof. Roof outside Congrete and Roof
inside Plat Carbons, Deck Floating Roof Almunium.
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED
Supervises field engineering lay-out.
Assisting the Project Superintendent for the daily schedule of work.
Assisting the Project Superintendent for the proper distribution of manpower
in different areas.
Coordinate / discuss with the Project Engineer / Project Superintendent the
job priorities, progress of work, materials and equipment needed for the
execution of work.
Maintain an up to date drawing file on each job.
Continually check drawings, specifications, etc., on each job for discrepancies
and deficiencies and report the same to the Project Engineer or Project
Superintendent.
Engineer-in-charge in inspection of tank foundation.
Engineer-in-charge in tank identification mark.
Engineer-in-charge in hydrostatic testing.
Conduct material inspection to assure that they are free from visual defects
with mill certificates and heat numbers prior to fabrication and erection.
Inspect lay-out and edge preparation together with heat number transfer and
assure that the required dimensions are met as per approved drawings.
Assisting the QA/QC Inspector to conduct fit-up and dimensional inspection
both on fabricated and erected structural members.
Assisting the QA/QC Inspector to ensure quality control implementation before
inspection with client and class.
Assisting the QA/QC Inspector for the final documentation of all inspection
reports and certification.
Assisting the QA/QC Inspector in preparation of as-built drawing.
Company : TKK/SHI – QATAR CO, W.L.L.
(Qatar Branch)
Position : QC Tank Inspector
Year : January 05, 2005 – January 21, 2006
Location : Upstream and Compression Facilities
Ras Laffan, Qatar / Dolphin Project Onshore
Energy, Ras Gas (Qatar
Client : PT. DOLPHIN ENERGY (UK)
PROJECT:
Construct and erect 36 Storage Tanks (Cone Roof, Double-Deck Floating Roof
and Dome Roof) for Condensate / Fire Water / Naphtha, Cracker Bottom and
LPG / LNG
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Supervises field engineering lay-out.
Assisting the Project Superintendent for the daily schedule of work.
Assisting the Project Superintendent for the proper distribution of
manpower in different areas.
Coordinate / discuss with the Project Engineer / Project
Superintendent the job priorities, progress of work, materials and
equipment needed for the execution of work.
Check / monitor the daily progress report from different areas and
discuss with the Project Superintendent to set a schedule according
to priority.
Maintain an up to date drawing file on each job.
Continually check drawings, specifications, etc., on each job for
discrepancies and deficiencies and report the same to the Project
Engineer or Project Superintendent.
Conduct material inspection to assure that they are free from visual
defects with mill certificates and heat numbers prior to fabrication
and erection.
Inspect lay-out and edge preparation together with heat number
transfer and assure that the required dimensions are met as per
approved drawings.
Assisting the QA/QC Inspector to conduct fit-up and dimensional
inspection both on fabricated and erected structural members.
Do visual inspection of welds.
Assisting the QA/QC Inspector to ensure quality control
implementation before inspection with client and class.
Assisting the QA/QC Inspector for requesting and carry out
inspection with client and class.
Assisting the QA/QC Inspector for the implementation of NDT
program.
Assisting the QA/QC Inspector for the final documentation of all
inspection reports and certification.
Company : SHI – QATAR CO., W.L.L.
(Qatar Branch)
Position : Field Tank Engineer
Year : September 15, 2004 - October 25, 2005
Location : Qatar Petroleum Lab Project (QATAR)
Mesaieed State of Qatar.
Client : PT. QATAR PETROLEUM (QATAR)
PROJECT:
Construct and erect 19 Storage Tanks (Cone Roof, Deck Floating Roof and Dome
Roof) for Condensate / Fire Water / Naphtha, Cracker Bottom.
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Engineer-in-charge in field engineering lay-out, preparation of tank
foundation and erection.
Assisting the QA/QC Personnel in conducting material inspection to
assure that they are free from visual defects with mill certificates
and heat number issued.
Assisting the Project Engineer both in field and office work especially
in documentation.
Assisting the Project Superintendent in planning to execute the job.
Maintain an up to date drawing file on each job.
Assisting the Project Engineer in hydrostatic testing.
Supervises field engineering lay-out, preparation of tank foundation
and erection.
Assisting the Project Superintendent for the daily schedule of work
and for proper distribution of manpower in different areas.
Coordinate / discuss with the Project Engineer / Project
Superintendent the job priorities, progress of work, materials and
equipment required for the execution of work.
Check / monitor the daily progress report from different areas and
discuss with the Project Superintendent to set a schedule according
to priority.
Maintain an up to date drawing.
Continually check drawings, specifications, etc., on each for
discrepancies and deficiencies and report the same to the Project
Engineer or Project Superintendent.
Conduct material inspection to assure that they are free from visual
defects with mill certificates and heat numbers prior to fabrication
and erection.
In-charge in fabrication lay-out of 12 miscellaneous flat bottom tanks.
Assisting the Project Engineer in hydrostatic testing to check if the
foundation settled.
Company: Samsung Corporation Engineering and Construction Group
Position: Field Tank Engineer
Years : August 15, 2003 – August 29, 2004
Location: Additional 3-LPG Tank Project of Qatar Petroleum in
Mesaieed State of Qatar.
Client : PT. QATAR PETROLEUM (QATAR)
PROJECT:
Construct and erect 03 Storage Tank (Construct and erect 03Storage Tank
(Double-Tank / Shell outside Concrete and Shell inside Nickel 15%, DoubleDum-
Roof. Roof outside Congrete and Roof inside Plate Carbons, Deck Floating Roof
Aluminum.
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Incoming material Inspection
Dimensional control of fabrication
(Cutting and rolling Plate) pipe and all Accessories of storage tank
Control all report fabrication.
Training of new welder test before WQT.
Welder performance Qualification
Test per approved WPS.
WQT for storage tank and prepare Welder ID and welder list.
Inspection of welding sequence, Distortion control prior to welding.
Witness and Prepared all Leak test,Vacum box test report
Monitoring welding activities and prepared joint number system.
Dimensional check storage tank before welding (Plumb, Roundness,
Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior
to welding.
Prepared Material traceability MAP
Prepared Welding MAP
Prepared RT MAP
Prepared thickness MAP
Prepared PMI MAP
Coordinate the performance the performance of NDT & PWHT works
in accordance with ITP, Project specification, Codes & Standard.
Verify that approved WPS is available; welder is qualified with the
process and AFC drawing.
Perform & Supervise performance of material receiving inspection.
Perform joint Fit-Up inspection & ensure dimensional check.
Check weld end preparation, tacking method, electrode used, pre-heat
requirement, inter-pass temperature & cleaning in accordance with
WPS.
Check welding parameter & welding consumables.
Perform final welding visual inspection in accordance with acceptance
criteria.
Coordinate weld repair work in accordance with the repair procedure.
Monitoring of weld rejection rate & NDT performance status.
Interpreted RT films & review PWHT charts.
Preparing document test package for Hydro test / Pneumatic test
Witness hydro testing, air leak testing & flushing.
Line check and re-instatement of piping system, punch list and final
acceptance.
Preparing daily inspection report and manufacture data report (MDR.
Company : PT. TIMAS SUPLINDO
Position : QC INSPECTOR (ALL NDT)
Year : December 10, 2002 to August 10, 2003
Project : Offshore Oil Field of Cnoocses BV. (Ypf Maxuses
Project.
Location : Offshore JAVA
Client : PT. CNOOCSES
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Responsible and supervising plate form / adjacent weld head platform
fabrication and installed.
Responsible and supervising piping work and assuring done according
to drawing with test package limited.
Prepared test package after completion of piping installation and nde
piping.
Visual inspection of welding work and verification quality welded by
distructive and non-destructive.
Visual check of space, beveling and cleaning pipe (blowing).
Ensuring the correct welding electrode was used.
Marking RT point shall be shoot with owner.
Line check / punh list with engineering and owner. Check welding
traceability record piping.
Check of piping / fitting material with mill certificate before issue to
fabrication and erection.
Prepared test package after completion of piping installation and NDE
work. Make daily welding record and report & marking RT point shall
be shoot.
Check of piping / fitting material with mill certificate before issue to
fabrication and erection.
Review and record inspection report as per job specification.
Visual check of space, beveling & cleaning before weld.
Ensuring the correct welding electrode was used.
Company : PT. ELNUSA PETRO TEKNIK
Position : QC INSPECTOR (ALL NDT)
Year : April 07, 2002 to September 28, 2002
Project/Location: Tambunan Bekasi
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED Oversee subcontractor piping activities including fabrication, erection
and review report document.
Controlling the correct welding electrodes was used.
Marking RT point shall be shoot.
Review and record inspection report as per job.
Conduct line check and punc list of piping test package with
engineering and owner.
Counduct line check and punch list wit owner.
Check pipe spools and pipe support shop fabrication.
Supervising Pipe spools and pipe support field installation.
Punch clear execution comment item,
Witness, hydro test, pneumatic test, flushing, blowing and post test
Monitoring pipe spools and pipe support field installation. Coating and
wrapping underground piping.
Punch list execution comment item,
Witness, hydro test, pneumatic test, flushing and blowing, post test,
reinstatement.
PT. Petra minas Engineering Pratama
Period of Service from : October 03, 2001 to April 03, 2002
Project & Location : on Maxus Southeast Sumatra Inc Main
Tenant Service
Classifying (Position) : QC INSPECTOR (ALL NDT)
DUTIES AND RESPONSIBILITIES:
SCOPE OF DUTY & ACTIVITIES INVOLVED
Responsible in internal and external punch list of piping test package
of following line with steam line, boiler feed water lines, cooling water
system, instrument air, process line and ECT.
Check of piping / fitting material with mill certificate before issue to
fabrication and erection.
Review and record inspection report as per job specification.
Visual check of space, beveling & cleaning before weld.
Ensuring the correct welding electrode was used.
Visual check of quality weld by destructive and non-destructive.
Responsible and supervision welder active.
Supervising of mechanical completion and reinstatement after
pressure test.
Monitoring spools fabrication and ensuring the sand blasting & primer
paint before pipe spools transfer to site.
Prepared test package after completion of piping installation and NDE
work.
Note: Original copy of certification and other supporting documents may be called for and
presented if and when require
I hereby certify that all statements in this data are true and correct to the best of my
knowledge and belief.
Best Regards,
Fauzan Rumzi, ST