Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

 

 

Page 2: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  2  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 • State  Seismic  Mitigation  Program  (SSMP)  The  District’s  application  for  SSMP  funds  for  Horace  Mann  Building  A  was  

updated   and   resubmitted   in   response   to   comments   and   questions   from   the   Office   of   Public   School   Construction  (OPSC).  OPSC  response  is  expected  around  the  end  of  the  year.  Altogether,  funding  for  5  of  the  13  eligible  buildings  is  considered  likely  and  up  to  $35  million  dollars  of  funds  could  be  approved  for  Phase  I.    

 • Furniture  Fixtures  and  Equipment  (FF&E)  Standards  No  new  developments  to  report.      • Department  of  Toxic  Substances  Control   (DTSC)  Due  to  receiving  State  Funding,  “No  Further  Action”  (NFA)  letters  

are  needed  from  DTSC  for  the  proposed  modernizations  at  El  Rodeo  and  BHHS:    o At  El  Rodeo  this  relates  to  leakage  from  the  previously  removed  underground  storage  tank.  Ongoing  monitoring  

of   the   Pilot   Test   Wells   will   continue   until   early   November;   and   then   a   Remedial   Action   Plan   (RAP)   will   be  prepared  and  submitted  to  DTSC  for  approval.  Once  formally  approved  by  DTSC  the  actual  remediation  will  start.  The  work   is  projected  to  take  through  2017.  An  application  for  the  reimbursement  of  all  costs   incurred  for  the  2014/2016  period  has  been  submitted  to  the  State  Water  Resources  Control  Board.    

o At   BHHS   the   NFA   is   due   to   possible   hazardous   materials   on   the   campus.   DTSC   has   approved   the   proposed  remediation  for  the  area  containing  Building  B.  A  RAP  for  the  remainder  of  the  campus  apart  from  the  Lacrosse  field  area  previously  cleared,  has  been  drafted,  and  will  be  submitted  to  DTSC  in  November.  Remediation  will  be  carried  out  primarily  through  the  construction  contracts.    

 • Safety  The  following  safety  violations  were  reported:  

o There   was   a   “near   miss”   safety   incident   at   the   BHHS   construction   project   involving   a   student   on  10/17/16.   A   full   investigation   of   the   incident   was   carried   out   and   a   “safety   stand   down”   by   the  contractor  team  was  conducted  to  ensure  similar  incidents  do  not  happen  again.      

 • Labor  Compliance  There  were  no  labor  compliance  issues  in  the  month  of  October.    

 • COC/Audits  The  remaining  5  items  of  the  22  recommendations  provided  by  the  2014/2015  Fiscal  Year  Audit  Report  

issued  by  Harvey  M.  Rose  Associates  are  still  to  be  completed.        

• Facilities   and   Planning   Procedures   Manual   Efforts   to   revise   and   update   the   Facilities   and   Planning   Procedures  Manual  are  temporarily  on  hold.    

 • Program  Management  Software  A  RFQ/RFP  to  procure  a  new  Program  Management  software  system  will  be  issued  

in  November.    

Page 3: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  3  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

      FINANCIAL  OVERVIEW  

 

 

Page 4: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  4  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   FINANCIAL  OVERVIEW  

Page 5: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  5  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

      MASTER  SCHEDULE  

 A  high  level  overview  of  the  current  master  schedule  is  shown  above.    Based  on  the  Board  direction  at  a  study  session  on  February  23,  2016;  the  overall  schedule  has  been  sequenced  into  2  Phases  with  Phase  I  in  the  grey  color  delineating  the  work  to  be  accomplished  within  the  current  Bond  funding.  All  Phase  II  related  work  will  be  dependent  on  Measure  Y.    

The  Horace  Mann  Building  A  Modernization  Project  is  in  progress  and  scheduled  for  completion  for  class  to  start  in  Fall  2017.  

Beverly  Hills  High  School  Construction  Documents  for  Buildings  A,  B1  &  B2  and  C  continue  in  the  DSA  approval  process.    Design   for   Buildings   B3   &   B4   is   in   progress   and   projected   to   be   submitted   to   DSA   in   early   2017.   Demolition   and  Abatement  of  B1,  B2  &  B3  is  ongoing  and  projected  completion  is  February  of  2017.  

The   El   Rodeo   modernization   plan   Construction   Documents   are   with   DSA   and   scheduled   for   approval   in   Spring,   2017.  Demolition  &  Abatement  on  Bldg.  A-­‐D  is  ongoing.  The  Make  Ready  projects  are  projected  for  completion  in  December,  2016.    

The  overall  Hawthorne  modernization  continues   in  Construction  Documents  design  phase.  The  Hawthorne  Auditorium  modernization  plans  will  be  submitted  to  DSA  in  November.  

The   Beverly   Vista   deck   waterproofing   project   is   in   redesign   and   expected   to   be   substanitally   completed   during   the  winterbreak  of  2016  with  the  exception  of  applying  the  waterproofing  membrane.    

Page 6: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  6  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   Beverly  Hills  High  School  Project  Status  

Phase 1 (Measure E Funded) Projects

INTERIM  HOUSING          Interim  Housing  has  been  completed  with  the  exception  of  some  remaining  close  out                                                                                  Items.  The  outstanding  punch  list  items  were  completed  in  October.  DSA         Close  out  items  are  pending  comments  for  wall  modifications  and  ADA  parking  lot  striping.    BUILDINGS  B1  &  B2   Construction  Documents  continue  in  DSA  back  check;  approval  is  expected  by  the  end  of  January,    (See  Photos  1-­‐4)   2017.  Abatement  and  Demolition  construction  work  is  ongoing.  Additional  hazardous  materials  

continue  to  be  discovered.  The  modernization  work  bid  process  will  start  in  late  2016,  with  work  to  begin  in  early  2017;  expected  completion  is  Summer  2018.  

 BUILDING  B3   Schematic   Design   completed   along   with   Building   B4;   The   final   Schematic   Design   package   was  

approved   by   the   Board   on   8/30/16.   Prior   to   proceeding   with   Design   Development,   the   budget  needs   to   be   approved   by   the   Board.   Building   B3   Abatement   and   Demolition   is   included   with  Buildings  B1  &  B2.  

 SITE  WORK   Site   Package   DSA   Approved;   does   not   include   final   design   development   for   the   South   Athletic  

Fields.   Partial   site   work   to   be   included   with   Buildings   B1-­‐B4   work;   majority   of   the   site   work  deferred  to  Phase  2.  

 

Phase 2 (Future Bond Funded) Projects

BUILDING  A   Currently  under  review  by  DSA;  approval  expected  in  Spring  2017.  Modernization  start  date  will  be  dependent  on  future  bonds.    

 BUILDING  B4   Design  is  concurrent  with  building  B3  referenced  above.  The  Board  agreed  to  move  B4  into  Phase  

1  if  there  are  sufficient  funds  available.  This  will  be  the  topic  of  an  upcoming  Board  study  session.  Work  tentatively  scheduled  to  begin  in  Summer  2018;  expected  completion  end  of  2019.  

 BUILDING  C   Currently  under  review  by  DSA;  approval  expected  in  Spring  2017.     Work  tentatively  scheduled  to  begin  in  Summer  2017;  expected  completion  in  Summer  2019.    BUILDING  E   To  be  demolished  after  completion  of  Building  C;  tentatively  scheduled  for  2019.    BUILDING  F   Minimal  repair  and  deferred  maintenance  work;  tentatively  scheduled  for  Summer  2019.    BUILDING  H   To  be  demolished  in  preparation  for  work  on  Building  C;  tentatively  scheduled  for  Summer  2017.    BUILDING  L   There   will   be   very   minimal   work   in   Building   L   associated   with   modernization   of   Building   A;  

tentatively  scheduled  for  Summer  2019-­‐Summer  2021.    SOUTH  SITE  WORK   Design  will  begin  in  2017     South  athletic  fields  tentatively  scheduled  for  construction  in  Summer  2019-­‐Summer  2021.     Final  portion  of  the  site  work  to  be  completed  after  removal  of  interim  housing  and  the  Venaco  oil  

wells,  tentatively  scheduled  for  Fall-­‐Winter  2021.  

Page 7: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  7  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

Construction Cost Summary

   

Page 8: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  8  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 

Page 9: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  9  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   El  Rodeo  School  Project  Status  

Phase 1 (Measure E Funded) Projects

INTERIM  HOUSING          The  close  out  process  is  in  progress  pending  DSA  approval  to  certify  project.      BUILDINGS  A  –  D   Construction  Documents  currently  under  review  by  DSA.  (See  Photo  5-­‐8)   Demolition   and   abatement   work   is   in   progress   (approximately   90%   complete)   with   scheduled  

completion  now  in  December.       DSA  Approval  for  Modernization  work  is  projected  in  May  2017.  The  construction  will    

begin  mid  2017  with  the  completion  scheduled  to  be  in  Summer,  2019.    MAKE  READY  PROJECTS  (See  Photo  9-­‐12)   Work  is  in  progress  and  scheduled  for  completion  in  late  November  2016.      PARTIAL  SITE  WORK   Construction  Documents  currently  under  review  by  DSA.     Work   to   be   completed   after   removal   of   interim   housing   and   in   coordination   with   the   proposed  

parking  structure.          

Phase 2 (Future Bond Funded) Projects

BUILDING  E   Construction  Documents  currently  under  review  by  DSA  along  with  Buildings  A  –  D.     Work  tentatively  scheduled  to  begin  in  2019;  expected  completion  in  the  summer  of  2020.      PARKING  GARAGE   Currently  in  design.    SITE  WORK   Site  development  work  will  be  completed  around  3rd  quarter  of  2020.      

 

 

 

 

 

 

 

 

 

Page 10: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  10  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

Construction Cost Summary

 

 

Page 11: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  11  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 

 

Page 12: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  12  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

Hawthorne  School  Project  Status  Phase 1 (Measure E Funded) Projects

AUDITORIUM   The  design  of  the  Auditorium  modernization  will  be  submitted  to  DSA  in  November.      

Phase 2 (Future Bond Funded) Projects

BUILDING  A   The  existing  Building  A  is  to  be  modernized.  The  A/E  is  working  on  the  construction  documents.    OTHER  BUILDINGS   All   other   existing   buildings   to   be   demolished   and   replaced   with   new   construction;   currently   in  

construction  document  phase  of  design.    PARKING  GARAGE   Currently  in  construction  document  phase  of  design  as  part  of  the  South  End  building.    SITE  WORK   Currently  in  construction  document  phase  of  design.    INTERIM  HOUSING   Solutions  for  interim  housing  are  still  being  determined.        

Page 13: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  13  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   Horace  Mann  School  Project  Status  

Phase 1 (Measure E Funded) Projects

BUILDING  B   The  final  punch  list  work  and  close  out  items  are  in  progress.  Critical  items  on  the       punch   list   are   being   executed   first   as   a   high   priority.   The   punch   list   is   set   to   be   completed   by  

November  25th.          

BUILDING  A     The  demolition  and  abatement  of  Building  A  is  in  progress  (approximately  98%  complete)  (See  Photo  13-­‐16                  and  the  modernization  is  in  progress  (approximately  26%  complete).    below)                      INTERIM  HOUSING   This  project  is  now  in  the  DSA  closeout  phase.    SITE  WORK   Currently  in  design;  Submittal  to  DSA  anticipated  in  November,  2016.            

           

 

 

 

 

 

 

 

         Construction Cost Summary

 

Page 14: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  14  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 

Page 15: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  15  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 

Page 16: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  16  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

Beverly  Vista  School  Project  Status  

SUMMER  2016     Repair  Major  Water  Intrusion:  NTP  was  issued  on  June  21,  2016  and  work  is  scheduled  for  (See  Photo  17-­‐20)          completion  in  November,  2016.    The  completion  date  has  been  extended  due  to  additional  work  

needed   to   reinforce   the  structural  deck  which  had  exposed   rebar.  The  specification  package   for  the  deck  waterproofing  is  being  determined  and  will  be  completed  late  December.  However,  due  to  the  mandatory  concrete  curing  duration,  the  waterproofing  product  cannot  be  applied  until  28  days   has   passed   from   the   time   the   concrete   deck   is   poured.   Correspondence   has   initiated   with  waterproofing  vendors  and  architect  to  discuss  options  of  possibly  expediting  this  process.  Due  to  this  fact,  the  expected  application  of  the  waterproofing  membrane  is  anticipated  for  late  January.  

      Courtyard  Grading  and  Site  Drainage  Improvements:  This  work  has  been  re-­‐scheduled  to  be  done  

during  winter  break  in  December,  2016.      SUMMER  2017   Security   fencing   improvements,  playground   lighting,  additional   repair  and  deferred  maintenance  

projects  currently  in  design  and  will  be  completed  in  the  summer  of  2017.      

           

Page 17: Facilities and Planning Department · 2016-12-05 · Facilities and Planning Department Measure E Update October 2016 Beverly Hills High School Project Status Phase 1 (Measure E Funded)

                                                 

 

www.bhusd.org   Page  17  

Facilities  and  Planning  Department  Measure  E  Update    October  2016  

   

 Construction Cost Summary