Expo Operations & Maintenance Facility Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility

Operations and Maintenance FacilityPre-Construction Meeting

July 10, 2013

Page 2: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility

Meeting Purpose and Format

Project Status Update

Introduction of Construction Contractor

Overview of Construction Process and Timeline

Next Steps

Meeting Agenda

Pre-Construction Meeting

Page 3: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

Project Milestones

Design Kick-Off

Summer 2011

Final Design CompletedFall 2012

ConstructionContract Awarded

Spring 2013

Start of ConstructionSummer 2013

Project Completion

Fall 2014

Status Update

Page 4: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility

Site Plan

Design

Page 5: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility Design

View from Exposition Boulevard

Page 6: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility

View from Stewart Street at Exposition Boulevard

Design

Page 7: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility

View from Stewart Street Crossing

Design

Page 8: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

KIEWIT BUILDING GROUP (Builder)

• Kiewit ranked 3rd largest contractor in the nation and one of the largest in the world (per Engineering News Record)

• In business since 1884…over 129 years of experience• A national leader in vertical building as well as heavy civil design-build

transportation projects• Builder of Gold Line Extension and other Metro projects, as well as the

Dorothy Chandler Pavilion and other significant LA County projects

MAINTENANCE DESIGN GROUP (Designer)• Maintenance Design Group (MDG), and its architectural partner RNL, have

assembled a multi-disciplined group of design and engineering professionals with expertise in transit maintenance facilities

Construction Contractor

Construction

Page 9: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

Construction Timeline

MAJOR CONSTRUCTION ELEMENTS

Summer 2013• Demolition• Site Excavation

Fall 2013• Continue Site Excavation• Site Utilities• Building Structural Foundations

Winter 2014• Steel Erection• Building Exterior• Building Interior Rough-in

Spring 2014• Rail Yard and Track Work• Building Finishes and Equipment

Summer 2014• Continue Rail Yard and Track Work• Continue Building Finishes and Equipment• Site Paving and Landscaping

Fall 2014• Continue Site Paving and Landscaping• Substantial Completion

Construction

Page 10: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

Limits of Activity: Majority of construction activities are contained onsite, with the exception of a

few utility tie-ins that will take place along Stewart Street and Centinela Avenue

Field Office:Contractor will utilize an existing building for an onsite field office

Site Access and Parking: Construction staff will access the site off of Stewart Street and exit onto

Centinela Avenue, and employees will park onsite

Haul Routes: Haul routes will use major thoroughfares (Centinela, Olympic, Stewart) as

opposed to residential streets

Construction Work Hours: 8 a.m. to 6 p.m., Monday to Friday9 a.m. to 5 p.m., Saturday (if necessary)

Construction Overview

Construction

Page 11: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility Mitigation Measures

Noise Mitigation –• Monitor existing ambient noise• Implement site specific noise control plans• Manage noise generating activities and minimize equipment noise• Implement mitigation measures if noise produced by construction activity exceeds allowable limits (i.e. sound blankets)• Respond to noise complaints or concerns

Temporary Construction Fencing – Installation of 8’ tall perimeter fencing that will securely delineate the construction work areas and provide noise attenuation

Construction Mitigation Plans

Perimeter Fencing with Noise Attenuation

Page 12: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility Mitigation Measures

Dust Control – Watering trucks will be used regularly to mitigate dust

Storm Water Protection – Filter fabric/controls will be installed around drain inlets to prevent runoff

Watering Truck for Dust Control

Construction Mitigation Plans (cont.)

Page 13: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

Distribute construction notices to project adjacent communities as the work progresses:

• Post on project website BuildExpo.org• Post on project social media sites Facebook and Twitter• Email to database of stakeholders and elected officials• Distribute door-to-door to within a ¼ mile radius of the construction

work zone• Provide to key project stakeholders as appropriate (i.e.

homeowners associations, etc.) for further dissemination

Construction Outreach

Construction Noticing

Page 14: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility Construction Outreach

Tom BeatyKiewit Building Group Community Relations ManagerTel: 310-694-6069Email: [email protected]

A 24-hour hotline is also available for all construction inquiries and emergencies: (213) 922-EXPO (3976)

• Team will respond to all construction inquiries as soon as possible and no later than 48 hours

• All emergencies will be addressed immediately

Community relations staff is available to respond to construction related issues:

Community Relations

Page 15: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility Opportunities

Local Jobs Program

Expo Board approved a Project Labor Agreement as part of the contract, which includes a Construction Careers component

30% of construction work hours to be performed by Community Residents who live in zip codes within a 5-mile radius of the Phase 2 alignment

10% of these hours will be performed by Disadvantaged Workers, such as those suffering from chronic unemployment and/or receiving public assistance

Page 16: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility

Secure the construction site with perimeter fencing

Begin building demolition and site prep work

Provide regular updates to stakeholder groups throughout construction

Next Steps

Next Steps

Page 17: Expo Operations & Maintenance Facility · 7/10/2013  · Expo Operations & Maintenance Facility Project Milestones Design Kick-Off Summer 2011 Final Design Completed Fall 2012 Construction

Expo Operations & Maintenance Facility Contacts

Project Website: www.BuildExpo.org

Sign-up on our homepage to be added to the project database and receive notices via email.

Project Hotline: 213-922-EXPO (3976)

www.Facebook.com/ExpoLine

www.Twitter.com/ExpoLine

Social Media:Email: [email protected]

Next Steps