Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry of Environment

Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Embed Size (px)

Citation preview

Page 1: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Experiences off the Netherlands with the the implementation of the Seveso Council-2

Directive : Learning lessons for Slovakia

Theo de GelderDutch Ministry of Environment

Page 2: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

2

Dutch experiences with the

implementation of the accident act

2003: a national evaluation four years after the implementation of the act Common need to improve the compliance of the

accident act Safety performances can only be achieved by

cooperation between authorities and cat. A & B operators

Page 3: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

3

Dutch experiences with the implementation of the accident act

Responsives:

95 operators category A & B 47 municipalities 7 provinces 28 labour inspectors 37 regional fire departments 9 environmental agencies 11 others

Page 4: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

4

Dutch experiences with the implementation of the accident act

Identified elements 1. Knowledge, information, tools, documentation 2 One counter desk thought (focal point) 3. Capacity / workload 4. Publicity 5. Time 6. Safety management system 7. Safety report 8. Inspections 9. Common conclusions 10. Recommendations for Slovakia

Page 5: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

5

Dutch experiences with the implementation of the accident act

1. knowledge, information, tools, documentation:

Lack of know-how mostly at the enterprises, municipalities and fire departments

Labour inspectors are more skilled No applicable instrument to determine domino-effects Authorities not always able to answer questions how

to do by enterprises. Report of information requirements, assistances,

national helpdesk and other guidelines much used

Page 6: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

6

Dutch experiences with the implementation of the accident act

2. One counter desk thought (focal point):

Start: great intention for cooperation Not always feasible Sometimes contrariety and conflicts in assessments Problem: planning coordination Different cultures/point of views between ministries National versus regional differences

Page 7: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

7

Dutch experiences with the implementation of the accident act

3. Capacity / workload:

90% enterprises supported by consultants Extra capacity needed for governmental offices and

enterprises Extra costs for 1/3 of all cat. A and B operators

5000-65000 euro’s 45%

100000-250.000 euro’s 40%

500.000-1.000.000 euro’s 15%

Page 8: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

8

Dutch experiences with the implementation of the accident act

4. Publicity:

Active information supply to the public Recommendable: two versions of the safety report

beceause of confidential information Doubts about the use and effectiveness of information

supply to the public “Sensitive” information for terrorism ?

Page 9: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

9

Dutch experiences with the implementation of the accident act

5. Time:

Complaints: all governmental work / actions takes too much time

Enterprises: we comply the legal time schedules

Page 10: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

10

Dutch experiences with the implementation of the accident act

6. Safety management system:

The interest of the introduction of a SMS is agreed Contribution to a greater awareness of risks Complaints enterprises: parts of a safety report does

not connect to existing management of quality systems

Page 11: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

11

Dutch experiences with the implementation of the accident act

7. Safety report:

The assessment by the authorities is too much theoretical in stead of practicable

Parts seems to be very useful Drawing up a safety report according to Seveso takes

more effort than the former internal and external safety reports

Too much details (avoid to create a paper tiger) Agreement about enforcing but no exaggeration ! ! Labour demands more than the Report Information

Requirements (own documentation) Interregional differences The term acceptable risk mentioned in the dutch act is

difficult to judge

Page 12: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

12

Dutch experiences with the implementation of the accident act

8. Inspections:

Very first inspections coordinated and cooperated Coordination and rejection are declining now Assessments by authorities are mostly fair and

reasonable The final notification to the management takes too

long Inspection frequency was too high. Nowadays

realistic

Page 13: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

13

Dutch experiences with the implementation of the accident act

9 Main conclusions

Improvement of awareness of risks, scenario’s, means to be taken, sms, observable reduction of risks

Improvement on emergency planning, plans, disaster and fire fighting, learning effect with cooperation was disappointing

Lack of capacity (time and know how) Lack of rejection for regulation, developing criteria

standards and policy Lack of willingness and responsibility to achieve a solid

cooperation and safety performance Lack of guidelines, assistances, standards, instruments The implementation needs time and money Focal point and coordinating body did not work proper but

is necessary !!

Page 14: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

14

Dutch experiences with the implementation of the accident act

RECOMMENDATIONS

Agreement about goal safety performance Achievement by common approach and cooperation

between operators and authorities Unification of common work-processes to improve

cooperation Development of standard specifications SR, SMS, skills etc Focal point / national helpdesk / centre of expertise Development of common training programmes Foundation of an “’Industrial University” (exchange

platform) Industry should make use of the line of business they

belong

Page 15: Experiences off the Netherlands with the the implementation of the Seveso Council-2 Directive : Learning lessons for Slovakia Theo de Gelder Dutch Ministry

Safety Management System (Theo)

15

Dutch experiences with the implementation of the accident act

RECOMMENDATIONS

Organise regional work conferences for all parties (operators and authorities)

Coordinating body is responsible for the assessment report

Avoid peak loading and inefficiencies by double work Parties involved: do give feed back on policymakers

in order to adjust the accident act and legislation and to develop or improve tools

As EU-member make use of the IMPEL-network !

Thank you good luck !