Upload
phunghanh
View
212
Download
0
Embed Size (px)
Citation preview
Experiences from First Top-Off Injection At The Stanford
Synchrotron Radiation Lightsource
Johannes Bauer, James Liu, Alyssa Prinz, Sayed Rokni
Radiation Protection Department
SLAC National Accelerator Laboratory
Menlo Park, CA 94025, U.S.A.
RADSYNCH’09
Trieste, Italy
May 22, 2009
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 2
Overview
• Introduction to SSRL
• Introduction to “Top-Off”
• Studies in Preparation for Top-Off
• Safety System
• First Tests
• SSRL Improvements
• New Tests
• Conclusions and Path Forward
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 3
Introduction to SSRL
“Stanford Synchrotron Radiation Lightsource”
• Evolved from high-energy physics synchrotron “SPEAR”
• Twice upgraded, now:
– Storage ring SPEAR3
– Fed by 10 Hz Linac (to 150 MeV), Booster (to 3 GeV)
– Connected with BTS line (Booster-To-SPEAR)
• 3 GeV, 100 mA with typically 1 W injectionusually three times a day fill from ~85 mA to 100 mA
• Going to 500 mA this year, later up to 5 W injection
• Currently 13 beamlines with 27 stations
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 4
Introduction to SSRL (cont.)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 5
Introduction to SSRL (cont.)
SPEAR3
BTS(Booster-to-SPEAR)
Linac &
BoosterBeamlines
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 6
So far: Injection stoppers (IS) closed while filling storage ring
no worries about electrons and Bremsstrahlung reaching BL
during injection
but temperature changes (alignment) affect optical components:
o.k. now, but not desired at higher currents
Top-Off: Filling storage ring while injection stoppers open
– “Infrequent injection”: 3+ times a day
– “Trickle injection”: up to once every minute
injector stays on, must stay tuned, high instantaneous charge
At other facilities “top-off” called “top-up”
Top-off, Top-Up, etc.
impractical unless IS stay open
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 7
Top-off, Top-Up, etc. (cont.)
Q = 5 A hr: Higher beam currents shorter lifetime higher losses
infrequent injection
trickle injection
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 8
SSRL Ray Trace Studies
Beam chamber apertures and magnets constrain
where beam can go
Studies by SSRL (with LBNL) to answer:
• How far towards beamline can injected beam travel with
which magnet settings?
• Which magnet settings prevent beam from going past safe
endpoints?
Safety Systems designed to keep beam within safe endpoints
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 9
QF QD BEND SDINSERTION DEVICE
A1 A2
Stored Beam on
design orbit
Ratchet
Wall
Fixed
Mask I
Fixed
Mask II
Comb
Mask
CM
Section of SPEAR BeamlineIncoming Beam
Assume all positions
and angles are
possible
No distinction between
stored beam, injected
beam on the 1st turn,
and injected on
subsequent turns
Energy error
No magnetic field
Straight line trajectories
Beamline Apertures
Vacuum Chamber
Radiation Masks
Magnetic field in all elements
ID – insertion device + trim coils
BEND – dipole magnet
QF – focusing quadrupole
QD – defocusing quadrupole
CM – horiz. corrector magnet
SD – defocusing sextupole
SPEAR Apertures
Vacuum Chamber
Radiation Masks
Safe
Endpoint
Start
Point
Region for trajectory simulations
Thanks to A.Terebilo, SSRL
SSRL Ray Trace Studies (cont.)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 10
Radiological Considerations
(1) Long-term dose from normal operation:Additional radiation from:
– forward-angle Bremsstrahlung from injected beam at apertures– higher beam currents
Based on estimated loss rates: within 1 mSv (100 mrem) per 1000 hr limit
(2) Radiation dose due to mis-steered beamWithin bounds of safety systems,
but such serious mis-steering expected only very rarely
Safety system defines “safety endpoint” that electrons cannot pass
Simulations up to 22 mSv/h (2.2 rem/h at 5 W) for dipole lines, ~20% less for ID lines – always radiation monitors in place
(3) Radiation due mis-steering with full safety system failureShould never happen; VERY UNLIKELY; requires several serious failures
Simulations dose rate high, up to 3.3 Sv/h (330 rem/h) at 5 W for dipole lines, up to 0.13 Sv/h (13 rem/h) for ID lines
but per event (<1 s) 0.74 mSv (74 mrem) with radiation monitors in place
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 11
Top-Off Safety Systems
Beam Containment System (BCS):
• Stored Current Interlock: top-off only for >50 mA
• Apertures: may not be modified without approval
• Magnet Power Supply Interlocks: monitoring both current and voltage
• Clearing Magnets: along dipole beamlines (no space for permanent magnets)
• Dose Rate Interlock: radiation monitors tripping at 0.02 mSv/h (2 mrem/h)
Non-BCS Systems:
• Daily Dose Interlock: rad. monitors allow max. 0.01 mSv (1 mrem) per day
• Charge Loss Interlock: allow only certain # e- lost each day
• Additional: Machine protection interlocks and software warnings (tight limits)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 12
• April to July 2008
• Interlocked BSOICs next to hutch
• Floor cleared, most data read out remotely:
– Beam Shut-Off Ion Chambers (BSOIC) SLAC-built
– Beamline Radiation Monitors HPI 6030/6012
• Access restricted:– No access during tuning
– Electronic “chirping” dosimeters
– Handheld dose meters
First Tests
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 13
• High-efficiency injection
(1 W injection, ~60-80% injection efficiency)
• Low-efficiency injection due to BTS mis-tuning
(1 W, ~30-50% injection efficiency)
Losses inside SPEAR ring at apertures
• Zero-efficiency injection
(1 W, 0% injection efficiency)
All of injected beam lost in ring due to “bump” at beamline
(orbit moved towards edge of aperture)
Beam Conditions for Tests
similar results
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 14
Measurements with Old Injection
BL55 microSv/h
(0.5 mrem/h)
already at
high-efficiency
injection
high-efficiency inj. < --- > low-efficiency inj.
BL11radiation only
at inefficient
injection
injection
current
throughout
0.16 0.04 nA
11 microSv/h
(1.1 mrem/h)
7 microSv/h
(0.7 mrem/h)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 15
Measurements with Old Inj. (cont.)
Three “types” of beamlines were found:
1. BL 4, 5:
Extra radiation seen during both
high-efficiency injection, up to 18.5 microSv/h (1.85 mrem/h)
and low-efficiency injection, up to 30 microSv/h (3 mrem/h)
2. BL 10, 11:
No extra radiation seen during high-efficiency injection,
but during low-efficiency injection, up to 16 microSv/h (1.6 mrem/h)
3. BL 1, 2, 6, 7, 9:
No or very little, < 1 microSv/h (< 0.1 mrem/h), extra radiation
seen during high- or low-efficiency injection
BL 8, 12, 13, 14: Ray trace studies not yet approved; BLs not tested
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 16
Dose Extrapolations - Old Injection
• No issues for any
BL at 100 mA
top-off operation
BL100 mA Infrequent Total dose
microSv/1000h mrem/1000h
BL 1 0 0
BL 2 4 0.4
BL 4 110 11
BL 5 190 19
BL 6 14 1.4
BL 7 10 1
BL 8 Ray trace study not yet approved, BL not tested
BL 9 3 0.3
BL 10 80 8
BL 11 80 8
BL 12 Ray trace study not yet approved, BL not tested
BL 13 Ray trace study not yet approved, BL not tested
Extrapolations
based on
measurements &
operation scenarios
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 17
Dose Components
Radiation from stored beam (s), injected beam (i),
traveling through wall (w), through beam pipe (b)
Dsb
Dib
DiwDswTerm unique for
top-off injection
Injection Stoppers
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 18
Dose Extrapolations - Old Injection
Dose components at 500 mA trickle injection
in mSv/1000h and mrem/1000h
BL Dib Diw Dsb Dsw Total
BL 1 0 0 0 0 0 0 0.01 1 0.01 1
BL 2 0 0 0 0 0 0 0.1 10 0.10 10
BL 4 0.93 93 0.02 2 1.32 132 0.06 6 2.33 233
BL 5 2.34 234 0.14 14 1.07 107 0.06 6 3.62 362
BL 6 0.05 5 0.05 5 0.18 18 0.02 2 0.30 30
BL 7 0.05 5 0 0 0 0 0.18 18 0.23 23
BL 8 Ray trace study not yet approved, BL not tested
BL 9 0 0 0 0 0.08 8 0 0 0.08 8
BL 10 0.94 94 0.01 1 0.32 32 0 0 1.27 127
BL 11 0.15 15 0.04 4 1.66 166 0.08 8 1.93 193
BL 12 Ray trace study not yet approved, BL not tested
BL 13 Ray trace study not yet approved, BL not tested
Dose components at
500 mA trickle injection
Dib high for BL 4, 5, 10
Dsb high for BL 4, 5, 11
lower with
new injection
Stored beam dose
measured with
GM/BF3 detector
Requires additional
shielding for higher
currents
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 19
SSRL Improvements to Injection
Injection system was adequate up to now;
top-off raised the bar, and SSRL responded
• Studied changes in x, y, x’, y’, energy, timing, optics
of injected beam
• New diagnostics added
• Better control of trajectory and optics
(computer monitoring, frequent checks)
• Removal of windows in BTS line:
Now one vacuum system from Linac to SPEAR
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 20
SSRL Improvements to Injection (cont.)
• Simulations show big improvement
very clear in y and y’ distributions of injected beam
injection efficiency83% 99% in simulation
• Similar simulation for optics
• Measured radiation doses went down
Thanks to J.Safranek, X.Huang, SSRL
with windows removed
windows present
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 21
• Repeat with improved injected beam (fall 2008)
• Measurements during high-efficiency injection
BL 4: 1.2 microSv/h 0.12 mrem/h
BL 5: 1.6 microSv/h 0.16 mrem/h
BL 10,11: 0 microSv/h 0 mrem/h
Dose rates about 10 times lower than before!
Worst 1.6 microSv/h (0.16 mrem/h) extrapolated to 1000 hour/year:
Dib = 5 microSv (0.5 mrem) for 100 mA infrequent injection56 microSv (5.6 mrem) for 500 mA infrequent injection92 microSv (9.2 mrem) for 500 mA trickle injection
(was 2.34 mSv or 234 mrem before)
Measurements with New Injection
The four worst BLs before!
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 22
Dose Extrapolations - New Injection
Dose components at 500 mA trickle injection
in mSv/1000h and mrem/1000h
BL Dib Diw Dsb Dsw Total
BL 1
BL 2
BL 4 0.07 7 0.02 2 1.32 132 0.06 6 1.47 147
BL 5 0.09 9 0.14 14 1.07 107 0.06 6 1.36 136
BL 6
BL 7
BL 8 Ray trace study not yet approved, BL not tested
BL 9
BL 10 0 0 0.01 1 0.32 32 0 0 0.33 33
BL 11 0 0 0.04 4 1.66 166 0.08 8 1.78 178
BL 12 Ray trace study not yet approved, BL not tested
BL 13 Ray trace study not yet approved, BL not tested
Dose components
at 500 mA trickle
injection
Dib now low!
No effects on Dsb
(to be improved by
shielding; reduction to
1/10 for higher current
operation)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 23
• Injection with low efficiency
BL4: 1.2 microSv/h 0.12 mrem/h
BL5: 4.8 microSv/h 0.48 mrem/h
BL10: 0.9 microSv/h 0.09 mrem/h
BL11: 0.6 microSv/h 0.06 mrem/h
Again lower dose rates than before
Worst 4.8 microSv/h extrapolated to 1000 hour/year
Dib = 2.8 mSv (280 mrem) at 500 mA trickle injection
(50 min to reach 100 mA)
Measurements with New Inj. (cont.)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 24
Summary of Test & Path Forward
• Tests taught us:– Improved injection well enough even for 500 mA trickle injection
– No long-term dose rate concerns for 100 mA (June 2009)
• More beamlines will be added over time
• For top-off up to 200 mA (July 2009)
– Warning system for injection beam lattice and optics
– Daily Dose Interlock
– Charge Loss Interlock
• For > 200 mA (stored beam issue) (Fall 2009)
– Additional shielding for BL4, 5 and 11
– Mitigation systems for BL thermal damage issues
• Review for trickle charge injection (beyond 2009)& injector upgrade (>1.5 W)
J.M.Bauer, “SSRL Top-Off Experiences”
RADSYNCH’09, May 22 2009, Page 25
Conclusions
• Tests very interesting: higher dose rates measured than expected
• SSRL was able to improve injection system
• With improvements top-off o.k. even for 500 mA trickle injection
• Stored-current dose needs to be addressed for >200 mA
• Top-off will start soon, later going to higher currents