14
EXPECTATION MEETS REALITY: SEISMIC PERFORMANCE OF POST- TENSIONED PRECAST CONCRETE SOUTHERN CROSS ENDOSCOPY BUILDING DURING THE 22 ND FEB 2011 CHRISTCHURCH EARTHQUAKE Stefano Pampanin (1), Weng Yuen Kam (1), Gary Haverland (2) and Sean Gardiner (3) (1) Dept. of Civil and Natural Resources Eng., Uni. of Canterbury, Christchurch, NZ (2) Structex Ltd, Christchurch, NZ (3) Formerly Structex Ltd, Christchurch, NZ Abstract The 22 nd Feb 2011 Christchurch earthquake highlighted the mismatch between the expectations of building occupants and owners over the reality of engineered buildings‟ seismic performance. Ductile plastic hinging behaviour of conventional reinforced concrete (RC) structures in large seismic event such as those of 22 nd Feb are expected by structural engineers. However, the reality of months of downtime and loss of occupancy of the building is not expected or desired by building users and owners. The innovative PRESSS-technology, utilising un-bonded post-tensioning precast concrete elements to achieve re-centering behaviour, is a new approach to achieve low damage seismic performance, in which building functional downtime and required structural repair are minimised. The Southern Cross Hospital Endoscopy building is the first application of the innovative PRESSS design technology in the South Island of New Zealand. The structure consists of four post-tensioned precast concrete frames in the North-South elevation and two sets of post-tensioned coupled precast concrete walls in the East-West elevation. Structex Ltd, in collaboration with the University of Canterbury and Fletcher Construction, delivers the five-storey Warren & Mahoney-designed building with a lower construction cost, reduced construction period and significantly improved seismic performance. The seismic performance of the Southern Cross Hospital Endoscopy building during the 22 nd Feb Christchurch earthquake suggests that the expectation of clients can be met by innovative structural solution. In addition to reporting on the details of the structural design and its performance during the 22 nd Feb event, the paper demonstrates the use of non-linear numerical model as a design verification and post-earthquake assessment tool.

EXPECTATION MEETS REALITY: SEISMIC PERFORMANCE OF …...frames running parallel to the structural walls served as drag ties as well as secondary resistance, especially at levels 3

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • EXPECTATION MEETS REALITY: SEISMIC PERFORMANCE OF POST-

    TENSIONED PRECAST CONCRETE SOUTHERN CROSS ENDOSCOPY

    BUILDING DURING THE 22ND

    FEB 2011 CHRISTCHURCH EARTHQUAKE

    Stefano Pampanin (1), Weng Yuen Kam (1), Gary Haverland (2) and Sean Gardiner (3)

    (1) Dept. of Civil and Natural Resources Eng., Uni. of Canterbury, Christchurch, NZ

    (2) Structex Ltd, Christchurch, NZ

    (3) Formerly Structex Ltd, Christchurch, NZ

    Abstract

    The 22nd

    Feb 2011 Christchurch earthquake highlighted the mismatch between the expectations of

    building occupants and owners over the reality of engineered buildings‟ seismic performance.

    Ductile plastic hinging behaviour of conventional reinforced concrete (RC) structures in large

    seismic event such as those of 22nd

    Feb are expected by structural engineers. However, the reality of

    months of downtime and loss of occupancy of the building is not expected or desired by building

    users and owners.

    The innovative PRESSS-technology, utilising un-bonded post-tensioning precast concrete elements

    to achieve re-centering behaviour, is a new approach to achieve low damage seismic performance,

    in which building functional downtime and required structural repair are minimised. The Southern

    Cross Hospital Endoscopy building is the first application of the innovative PRESSS design

    technology in the South Island of New Zealand. The structure consists of four post-tensioned

    precast concrete frames in the North-South elevation and two sets of post-tensioned coupled precast

    concrete walls in the East-West elevation. Structex Ltd, in collaboration with the University of

    Canterbury and Fletcher Construction, delivers the five-storey Warren & Mahoney-designed

    building with a lower construction cost, reduced construction period and significantly improved

    seismic performance.

    The seismic performance of the Southern Cross Hospital Endoscopy building during the 22nd

    Feb

    Christchurch earthquake suggests that the expectation of clients can be met by innovative structural

    solution. In addition to reporting on the details of the structural design and its performance during

    the 22nd

    Feb event, the paper demonstrates the use of non-linear numerical model as a design

    verification and post-earthquake assessment tool.

  • Page 2

    1 INTRODUCTION

    The 22nd

    Feb 2011 Christchurch earthquake highlighted the mismatch between the expectations of

    building occupants and owners over the reality of engineered buildings‟ seismic performance.

    Ductile plastic hinging behaviour of conventional reinforced concrete (RC) structure (Figure 1b) in

    large seismic event such as those of 22nd

    Feb are expected by structural engineers. The ultimate

    limit state (ULS) and maximum credible earthquake (MCE) design level specified in modern

    seismic codes, such as NZS1170:5, generally implies severe structural damage (to induce the

    required level of ductility) in large earthquakes (Figure 1a). However, the reality of months of

    downtime and loss of occupancy of the building is not expected and desired by building users and

    owners. Similar mismatch of expectation and reality after the Northridge earthquake in 1994 led to

    the concept of performance-based earthquake engineering [5].

    Figure 1: a) SEAOC (1999) Performance design and performance matrix [5], b) Ductile beam flexural hinging in a multi-storey RC buildings in Christchurch.

    The innovative PRESSS construction technology, utilising un-bonded post-tensioning precast

    concrete elements to achieve re-centering behaviour, is a new approach to achieve low damage

    seismic performance, in which building functional downtime and required structural repair are

    minimised. The Southern Cross Hospital Endoscopy (SCHE) building (Figure 2) is the first

    application of the innovative PRESSS design technology in the South Island of New Zealand. The

    architect is Warren and Mahoney with Structex acting as the structural engineer. Fletcher

    Construction is the principal contractor and Fulton Hogan is the post-tensioning sub-contractor.

    Figure 2: Architectural rendition of the Southern Cross Hospital Endoscopy building. (Architect: Warren and Mahoney)

    Modern seismic design for ULS and

    MCE: Ductile plastic hinges

    Longitudinal (East-West) Transverse

    (North-South)

    North

  • Page 3

    This paper will briefly describe the structural details, seismic design and construction of the SCHE

    building, highlighting the technology-transfer cooperation between research and industry. Then, in

    addition to reporting on its performance during the Canterbury earthquakes (4th

    Sept and 22nd

    Feb

    events), the paper demonstrates the use of non-linear numerical model as a design verification and

    post-earthquake assessment tool.

    2 DESCRIPTION OF STRUCTURAL SYSTEM

    The structure is a three-storey building with a carpark level on ground floor. The building includes

    several operation theatres at Level 2 and office space at Level 2 and 3. The roof level included an

    additional plant room. The building footprint is 19m x 28m. The building is founded piles

    foundation on 9m deep soft soil.

    The lateral-load resisting system consisted of four limited ductile post-tensioned precast concrete

    frames in the transverse (North-South) elevation and two sets of nominally ductile post-tensioned

    coupled precast concrete walls in the longitudinal (East-West) elevation. Two perimeter cast-in-situ

    frames running parallel to the structural walls served as drag ties as well as secondary resistance,

    especially at levels 3 and 4. The structural layout is shown in the plan view presented in Figure 3.

    Figure 3: Plan view of the building.

    The frames incorporated post-tensioned tendons and top mild-steel reinforcements (see Figure 9).

    The post-tensioned concrete walls had a combination of un-bonded mild steel reinforcements at the

    base and U-shaped flexural plates (UFPs) in between the walls for energy-dissipation and damping

    for the systems. Figure 4 shows the details of the North-side coupled walls with UFP elements. The

    lateral loads are transferred to the frames and walls by the 90mm thick concrete topping. The level 3

    and 4 are torsionally-sensitive in the longitudinal direction with the full-height walls acting only on

    the south side. The transverse post-tensioned frames are designed for the torsion-induced demand.

    The roof structure consists of large-span steel rafters (in the transverse direction) and purlins. The

    floors are typically 200mm prestressed hollowcore units with 90mm topping. The precast

    hollowcore, spanning in the longitudinal direction, were supported on the post-tensioned frames.

    Post-

    tensioned

    moment-

    resisting

    frames

    North

    Full height post-

    tensioned coupled

    walls (South)

    Half height post-

    tensioned coupled

    walls (North) Hollowcore

    span

    Cast-insitu

    RC gravity

    frame

    Cast-insitu

    RC gravity

    frame

  • Page 4

    The beam-elongation effect on the floor diaphragm from the post-tensioned frames was mitigated

    by the use of cast-in-situ band beam-slab at the single-hinging beam-column rocking interface

    (Figure 15d).

    Figure 4: top-left) Elevation of the north-face half-height coupled post-tensioned walls; top-right) Detail of the U-shaped flexural plates (UFP) coupling elements; bottom) Cross-section

    of south-face full-height walls (coupling detailed not shown).

    3 DESIGN AND CONSTRUCTION

    The PRESSS rocking systems relies on concentrated energy dissipation elements while the high-

    strength steel post-tensioning tendons and precast concrete units remain generally elastic (or

    confined crushing for concrete). The post-tensioning tendons also provide re-centering capacity to

    the system, minimising residual deformation post-earthquake. The design and sectional analysis of

    the PRESSS-technology have been thoroughly covered by the NZCS‟s PRESSS Design Handbook

    [2] and the Concrete Standard NZS3101:2006 Appendix B [4]. Herein, some interesting aspects of

    the design decision and construction phases in relation to the use of the PRESSS solution are

    described.

  • Page 5

    3.1 Decision process to use the PRESSS-system

    As the PRESSS-technology had not been used in any Christchurch or South Island construction,

    there was an augmented decision process to use the PRESSS-technology for this particular building.

    In general, several key aspects in a relative chronological order:

    1. Discussion with client, quantity surveyor and architect to outline the concept and the advantages, including possible price savings (in capital construction cost).

    2. Complete construction and costing analysis review with Fletcher Construction.

    3. Peer review and external consultation (with the University of Canterbury team) for design confidence and Building Consent application.

    Pricing analysis and post-construction review confirmed that construction savings were achieved

    (when compared to a monolithic precast concrete solution). Beam depth was reduced from 700mm

    to 600mm, allowing services to be accommodated without raising the building height (a critical

    issue in a built-up residential area).

    3.2 Construction process

    Precast elements and limited on-site casting can accelerate the construction process significantly.

    Construction process (in an approximate sequence with some overlapping):

    1. Sheet piling and excavation

    2. Screw piles foundation

    3. Foundation beams in-situ construction

    4. Installation and grouting of ground floor precast concrete columns

    5. Installation and propping of 1st floor beam and hollowcore floor.

    6. Installation of upper floor columns and beams (in sequence).

    Figure 5: The building under construction: a) Installation and erection of the precast columns and walls (North ends); b) Precast elements erection and propping from the North-East

    elevation view.

    7. Installation of shear walls

  • Page 6

    8. Casting of slab toppings

    9. Threading and post-tensioning of tendons in frames and walls.

    10. Complete in-situ end beams, gutters etc.

    11. Installation of prefabricated steel roof structure.

    3.3 Construction challenges and PRESSS-solution

    1. Limited cranage on site with basement limits the use of large precast concrete elements (e.g. full height frames). Therefore, post-tensioning of smaller precast elements (e.g PRESSS-

    technology) is a desirable solution to the cranage problem.

    2. Full height southern wall and partial height northern wall induced torsional demands onto the transverse direction frames. The post-tensioned frames, while supposedly „limited

    ductility‟ in design, possessed substantial lateral strength and ductility to account for the

    increased demand due to torsion amplification.

    3. Screw piles required to reduce noise during construction (building in an established neighbourhood).

    4. Need to keep all components simple and easy to be constructed, as well as “as conventional” as possible. There was also a need to avoid structural components that may be perceived as

    expensive.

    5. Post-tensioning anchorage blocks are large and required specific design to accommodate the steel work, spiral and transverse reinforcing. The 450mm wide column and 275mm thick

    walls dimensions were driven by the need for the anchorage blocks (see Figure 6).

    6. Design of construction sequence of the installation of the precast elements (beams, columns and floors) and post-tensioning work can accelerate the construction time significantly. As

    with any new building system, it may be worthwhile for engineers to specify/clarify the

    construction sequence with the contractors.

    Figure 6: Detailling of the post-tensioned frames: a) Anchorage block and spiral reinforcing within the precast column; b) Precast columns with ducts for post-tensioning tendons and

    mild-steel reinforcements; c) On-site post-tensioning.

  • Page 7

    3.4 Further advantages of the PRESSS systems

    1. Full length precast beam and columns – eliminating significant amount of insitu concreting. This led to more rapid construction time as full advantage of precast concrete was utilised.

    2. Limited „structural damage‟ in the rocking plastic hinge zone. Self-centering capacity limits residual lean and displacement following an earthquake.

    3. Analysis indicates lower level of floor acceleration compared to monolithic limited-ductility or nominally-ductile systems.

    4. The new PRESSS-technology uses conventional building components and elements (e.g. precast beams, walls, drossbach ducts etc).

    5. Reduced wall reinforcements (as post-tensioning tendons supplemented 40-50% of the required tension reinforcements.

    4 INELASTIC MODELLING AND VERIFICATION

    4.1 Inelastic 2D models

    As part of the original peer-review process, inelastic 2D models of the SCHE building were

    developed for non-linear push-over and time-history assessment. The modelling of the frame and

    wall systems has been carried out using a lumped plasticity approach, following the procedure

    described in NZCS‟s PRESSS Design Handbook [2]. Inelastic rotational springs are used in parallel

    at the rocking connections (beam-to-column, column-to-foundation and wall-to-foundation)

    connection to represent the self-centering contribution of the post-tensioned tendons (Non Linear

    Elastic Hysteresis loop) and the dissipative contribution from the mild steel (Elasto-Plastic with

    hardening, or bilinear). Frame, column and wall elements, away from the interface section are

    modelled as elastic elements. Lumped mass and plasticity 2D model is implemented in the finite

    element code Ruaumoko [1]. Figure 7 and Figure 8 illustrate the 2D models of the post-tensioned

    frames and post-tensioned coupled walls respectively.

    Figure 7: 2D elevation view of the post-tensioned frames model.

  • Page 8

    Figure 8: 2D elevation view of the post-tensioned coupled walls model: a) Full height south walls; b) Half height north walls.

    4.2 Section analysis of the rocking connections

    The moment rotation curves of the jointed ductile connections were derived using the procedures

    described in NZCS‟s PRESSS Design Handbook [2] while precast elements were analysed using

    typical moment-curvature. Figure 9 shows the typical moment-rotation analysis result for the beam-

    to-column rocking connections. Due to the discontinued bottom mild-steel reinforcements, the

    negative beam moment capacity is higher than the positive beam moment capacity.

    Figure 9: Moment-rotation evaluation of the rocking beam-column connections: a) Negative moment capacity i.e. tension at the bottom of the beam; b) Positive moment capacity.

    4.3 Inelastic push-over analysis versus design values

    Figure 10 shows the cyclic push-pull curves of the post-tensioned frames and the coupled walls

    (only south walls result is shown). Figure 11 plots the inelastic push-over curves of the frames and

    walls systems, superimposed with the seismicity demand (in terms of Acceleration-Displacement

    Response Spectrum (ADRS) curves). The demand curves are reduced using computed hysteresis

    damping curves from the actual system, and as higher energy dissipation is achieved at large

    rotation/displacement, the actualised damping reduction factor increases at higher displacements.

    Post-tensioning

    Mild-steel

    Total/Post-

    tensioning

    Total

  • Page 9

    Cyclic Push Pull

    -2000

    -1500

    -1000

    -500

    0

    500

    1000

    1500

    2000

    -4 -3 -2 -1 0 1 2 3 4 Drift (%)

    Bas

    e S

    hea

    r (k

    N)

    -544 -408 -272 -136 0 136 272 408 544Top Disp (mm)

    Cyclic Push Pull

    -2000

    -1500

    -1000

    -500

    0

    500

    1000

    1500

    2000

    -4 -3 -2 -1 0 1 2 3 4 Drift (%)

    Bas

    e S

    hea

    r (k

    N)

    -500 -375 -250 -125 0 125 250 375 500Top Disp (mm)

    Figure 10: Cyclic push-pull (displacement-controlled) analysis of a) Post-tensioned frames; b) South Coupled Walls.

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    0.45

    0.5

    0 0.5 1 1.5 2 2.5 3Top of Structure Drift (%)

    Sei

    smic

    co

    effi

    cien

    t (g

    )

    0

    860

    1720

    2580

    3440

    4300

    5160

    6020

    6880

    7740

    8600

    Ba

    se S

    hea

    r (k

    N)

    ULS Demand

    ULS Elastic

    SLS2 Demand

    PushOver Capacity

    Nominal Capacity (0.85)

    Elastic 5%

    1/1000 yrs

    Damped (x)

    1/1000 yrs

    NL Push-over

    Capacity

    ø = 1.0

    ø =0.85

    x = 8.2%

    Vb= 5455kN

    x = 13.2%

    Vb= 5892kN

    x = 10.5%

    Vb= 4766N

    2.0%

    x = 13.6%

    Vb= 5093kN

    Damped (x)

    1/500 yrs

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    0.45

    0.5

    0 0.5 1 1.5 2 2.5 3 3.5 4

    Drift at Effective Height (%)

    Sei

    smic

    coef

    fici

    ent

    (g)

    0

    800

    1600

    2400

    3200

    4000

    4800

    5600

    6400

    7200

    8000

    Base

    Sh

    ear

    (kN

    )

    Tall Walls

    Short Walls

    Combined Walls

    Combined Walls (phi=0.85)

    Elastic Demand

    1/1000 Damped Demand

    1/500 Damped demand

    Tall Walls

    Damped (x )

    1/1000 yrs

    x = 20.2%

    Vb= 4566kN

    x = 17.0%

    Vb= 5198kN

    Damped (x )

    1/500 yrs

    Short Walls

    x = 18.5%

    Vb= 5293kN

    1.8%

    5%-damped

    1/1000 yrsNominal

    Capacity,

    ø =0.85

    NL Push-over

    Capacity, ø = 1.0

    Figure 11: Inelastic push-over curves on a base-shear versus drift at effective height domain: a) PT frames in transverse direction; b) PT walls in longitudinal direction.

  • Page 10

    The SCHE building was designed as an Importance Level 3 building (R=1.3, design seismic hazard

    = 1/1000 years) according to NZS1170:5 [3]. A displacement-based design approach was adopted,

    as this approach was more suited for the PRESSS system. For design, 8% and 13% equivalent

    viscous damping (ξ) were assumed for the frames and walls respectively. The non-linear pushover

    analysis of the frames and walls (next section) indicates the ξ to be 13% and 18.5% for the frames

    and walls respectively. The design inter-storey drifts at the ULS (1/1000 years seismicity) were

    2.0% and 1.8% for the frames and walls respectively. The non-linear pushover analysis suggests the

    ULS inter-storey drift to be 1.67% and 1.75% for the frames and walls respectively. The push-over

    assessment base-shear values were also comparable to the DDBD design base shear (frames:

    5093kN versus 4286kN design; walls: 4656kN versus 3343kN design). The higher than expected

    base shear for the walls system can be attributed to the high post-yield stiffness of the coupled

    walls.

    4.4 Inelastic time-history analysis results

    Seven strong-ground motion records (listed in Table 1) were selected and scaled according to the

    NZS1170:5 guidelines. The records are selected as representatives of the site and seismicity

    conditions (Soil class D, 0.176g < PGA=0.22g < 0.33g, source magnitude, Mw of 5-7). Of the seven

    records, four records had no forward directivity (near-fault) effects while three records had

    distinctive directivity effects.

    Table 1: Selected and scaled strong ground motions for time-history analysis verification.

    Name Earthquake Event Year Mw StationRclosest

    (km)

    Soil Type

    (NEHRP)

    Unscaled

    PGA (g)

    Unscaled

    PGV

    (cm/s)

    Scaling

    Factor

    Scaled

    PGA (g)

    Ground Motion with No Directivity Effects

    EQ1 Superstition Hils 1987 6.7 Plaster City 21 D 0.155 20.6 2.44 0.379

    EQ2 Northridge 1994 6.7 LA – Hollywood Stor FF 25.5 D 0.231 18.3 2.02 0.467

    EQ3 Loma Prieta 1989 6.9 Gilroy Array #7 24.2 D 0.226 16.4 2.32 0.525

    EQ4 Landers 1992 7.3 Yemo Fire Station 24.9 D 0.2095 29.7 2.01 0.421

    Ground Motion with Directivity Effects ( Near Fault Earthquakes)

    EQ5 Northridge 1994 6.7 Newhall Fire st. 5.92 D 0.59 97.20 0.49 0.288

    EQ6 Imperial Valley 1979 6.6 El Centro Array #5 3.95 D 0.38 90.5 1.13 0.431

    EQ7 Tabas, Iran 1978 7.35 Tabas 2 D 0.852 121.4 0.96 0.816

    The inelastic time-history analysis results of the 2D models are shown in Figure 11 and Figure 14. The average inter-storey drift responses for the frames (in transverse direction) and the walls (in the

    longitudinal direction) are shown in Figure 11a and Figure 14a-b respectively. In general, the bottom two floors exhibited a stiffer response for both frames and walls with lower inter-storey

    drift. In fact, for the frames and the shorter north walls, the inter-storey drifts were significantly less

    than the design level drifts – indicative of a need for a inelastic dynamic model as the assumed

    damping might not be realised at all levels. For the whole building, the inter-storey drift responses

    in the 2D models were about 1.0% at levels three and four, and 0.3-0.5% at levels one and two.

    The floor acceleration was also checked as part of the design and verification. The floor

    acceleration time history responses of the frames and walls are presented Figure 11b-d. In general,

    the design intention is to limit the floor acceleration, particularly at level two and three to less than

    1g, in order to protect the medical equipment. The stronger lateral resistance and significant energy

    dissipation capacities (from having the north walls and more beam-column joints) at the lower two

    floors managed to achieve the target floor accelerations.

  • Page 11

    0

    1

    2

    3

    4

    0.0% 1.0% 2.0% 3.0%

    Interstorey Drift [%]

    Lev

    el

    Mean

    -/+ 1Std

    Design

    0

    1

    2

    3

    4

    0.0 0.5 1.0 1.5 2.0

    Floor acceleration [g]

    Lev

    elMean

    -/+ 1Std

    1

    2

    0.00 0.50 1.00 1.50 2.00

    Floor acceleration [g]

    Lev

    el

    Mean

    -/+ 1Std

    0

    1

    2

    3

    4

    0.00 0.25 0.50 0.75 1.00

    Floor acceleration [g]

    Lev

    el

    Mean

    -/+ 1Std

    Figure 12: Average response from the time-history analyses of the 7 earthquake records suite: a) Inter-storey drift response for the frames; b-d) Floor acceleration responses for the

    frames, south walls and north walls respectively.

    4.5 3D model results

    While not discussed thoroughly in this paper, the 3D model of the building (Figure 13) was

    developed to analyses the torsion-induced amplification on the frames (transverse and longitudinal).

    As time history analysis results of the 2D and 3D walls models presented in Figure 14 show, the torsional amplification in terms of inter-storey drift responses of the North (Tall) walls were

    approximately 30% and 80% at Level 3 and Level 4 respectively.

    Figure 13: 3D model of the Southern Cross Hospital Endoscope building.

    0

    1

    2

    3

    4

    0.00% 0.50% 1.00% 1.50% 2.00%

    Interstorey Drift

    Lev

    el

    Mean

    +/- 1 Stdev

    0

    1

    2

    0.0% 0.2% 0.4% 0.6% 0.8% 1.0%Interstorey Drift

    Lev

    el

    Mean

    +/- 1 Stdev

    0

    1

    2

    3

    4

    0 0.5 1 1.5 2Inter-storey Drift (%)

    Lev

    el

    Tall Walls

    Short Walls

    Figure 14: Average inter-storey drifts from the time-history: a) South walls 2D model; b) North walls 2D model; c) 3D model walls results.

  • Page 12

    5 PERFORMANCE OF THE BUILDING IN CANTERBURY 2010/2011 EARTHQUAKES

    5.1 Observed structural and non-structural damage

    No observable structural damage was detected in the building after the 4th

    Sept 2010 7.1 Mw

    Darfield earthquake. SCHE building was almost immediately re-occupiable (after an immediate

    structural assessment). In the 22nd

    Feb 2011 6.3 Mw Christchurch earthquake, the structure had

    signs of significant transient movements (Figure 15a-c), especially in the East-West longitudinal

    direction (consistent with the polarity of the Feb earthquake). On the top of the south walls, minor

    crushing damage was observed at the interface between the coupled walls. Most of the UFPs had

    Lueder yield lines, indicating the building‟s inter-storey drift of at least 0.5%-0.75% (corresponding

    to the yield drift of the UFPs).

    Figure 15: Observable damage (a-c) and non-damage (d) after the 22nd Feb 2011 earthquake.

    Non-structural damage was more significant when compared with the structural damage. A

    architectural glass panel on the staircase was cracked in both the earthquakes. In the Feb event, the

    non-structural façade‟s connection to the wall spalled (Figure 15c), possibly consequence of the

    fixity of the façade at the ground floor. Hospital staff reported one damaged water pipe and several

    internal lining cracks as other observed non-structural damage.

    In general, the seismic performance of the Southern Cross Hospital Endoscopy building during the

    22nd

    Feb Christchurch earthquake suggests that the expectation of clients can be met by innovative

    structural solution.

    5.2 Inelastic analysis using the 22nd

    February 2011 recorded strong ground motions

    The inelastic 2D model used in the peer review verification was used for a post-earthquake

    reassessment of the SCHE building performance. Resthaven (REHS) recording station is 250

    metres south-east of the SCHE building site. As both sites have significant soft soil layers (soil class

    D), it is reasonable to infer similar strong ground motions at the SCHE site using REHS records.

    Figure 16a shows the response spectra of several records from the 22nd February event, when compared to the NZS1170:5 design spectra. For brevity, only the analysis and results of post-

    tensioned walls in the principal direction of the REHS records (along the East-West direction -

    Figure 16b) will be discussed.

  • Page 13

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

    Sp

    ectr

    a A

    ccel

    erat

    ion

    / S

    a (g

    ms-

    2)

    .

    Period (sec)

    NZS1170:5 (2004)

    500-year motion

    Mean of 4

    CBD records

    EQ2:CHHC (S89W)

    EQ1:CBGS (NS64E)

    EQ3:REHS

    (S88E)

    EQ1:CBGS

    EQ4:CCCCEQ2:CHHC

    EQ3:REHSPrincipal direction

    NZS1170:5 (2004)

    2500-year motion

    N

    EQ4:CCCC (N89W)

    -0.6

    -0.5

    -0.4

    -0.3

    -0.2

    -0.1

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    10 15 20 25 30 35 40

    Acc

    eler

    atio

    n (

    g m

    s-2

    )

    Time (sec)

    Resthaven E-W

    Principal Direction

    Figure 16: a) 5%-damped response spectra of the records from Christchurch CBD in comparison with the NZS1170:5 design spectra; b) Resthaven station (REHS) recorded time-

    history.

    The inelastic time history analysis results is presented in Figure 17 for the south full height walls and the north half-height walls. The taller wall was significantly more flexible and attracted lesser

    base-shear when compared with the shorter walls. While this resulted in torsional-induced

    movement in the upper floors as well as in the transverse frames, the inelastic time-history results

    indicated that the existing capacity of the walls and frames were adequate for the event. The

    maximum inter-storey drift was approximately 2.5%, a good seismic performance considering the

    REHS event is approximately 40-60% above the 2500-years return period design ground motion.

    The immediate results suggested possible non-structural damage such as linings, façade and

    services as per observed after the earthquake. Such a „quick result‟ may assist structural engineers

    in assessing the structural health of the building rapidly with higher confidence than a visual

    inspection alone. Nevertheless, it should be noted that the simplistic analysis do not consider the

    secondary and redundant elements (e.g. gravity frames in the longitudinal direction and intrinsic

    soil-structural damping).

    -2.5

    -2.0

    -1.5

    -1.0

    -0.5

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    10 15 20 25

    Inte

    r-st

    ore

    y D

    rift

    (%

    )

    Time (second)

    3F-4F

    2F-3F

    1F-2F

    GF-1F

    -2.5

    -2.0

    -1.5

    -1.0

    -0.5

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    10 15 20 25 30

    Inte

    r-st

    ore

    y D

    rift

    (%

    )

    Time (second)

    1F-2F

    GF-1F

    Figure 17: Inter-storey drift time-history responses of the a) South full-height walls; b) North half-height walls.

  • Page 14

    6 CONCLUSIONS

    The 22nd

    Feb 2011 Christchurch earthquake is an unfortunate and tragic reminder of how far

    earthquake engineering has progressed in the past 50 years. It also provides an avenue and

    opportunity for the seismic engineering community to explore innovative construction technology

    in order to deliver higher seismic performance, which matches the expectation of building

    occupants and owners.

    The Southern Cross Hospital Endoscopy (SCHE) building is a successful demonstration of the

    PRESSS-technology for precast concrete multi-storey buildings with competitive cost, reduced

    construction period and significantly improved seismic performance. The seismic performance of

    the SCHE building during the 22nd

    Feb Christchurch earthquake suggests that the expectation of

    clients can be met by innovative structural solution.

    Non-linear time-history modelling was demonstrated as an useful design verification as well as a

    post-earthquake assessment tool.

    7 ACKNOWLEDGEMENTS

    Acknowledgement to Dr Dion Marriott for the assistance in the modelling phase of the study.

    Special thanks to the building owner, Southern Cross Hospital Trust, the architect, Warren and

    Mahoney, and the contractor, Fletcher Construction, for their willingness to be part of this

    innovative and challenging project.

    8 REFERENCES

    [1] Carr, A. (2008). "RUAUMOKO2D - The Maori God of Volcanoes and Earthquakes." Uni. of

    Canterbury, Christchurch, NZ, Inelastic Analysis Finite Element program.

    [2] NZCS (2010). PRESSS Design Handbook, New Zealand Concrete Society (NZCS), Auckland, New

    Zealand.

    [3] NZS1170 (2004). NZS 1170:2004 Structural design actions, Standards New Zealand, Wellington, NZ.

    [4] NZS3101:2006 (2006). "Appendix B: Special provisions for the seismic design of ductile jointed precast

    concrete structural systems." NZS3101: 2006, Concrete standards, Standards New Zealand, Wellington, NZ.

    [5] SEAOC (1999). Recommended lateral force requirements and commentary, Structural Engineers

    Association of California (SEAOC), Sacramento, CA.