Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Geotechnical Baseline Report Exhibit 21 Execution Version
Hampton Roads Bridge-Tunnel Expansion Commonwealth of Virginia Project No. 0064-M06-032 Virginia Department of Transportation
EXHIBIT 21
GEOTECHNICAL BASELINE REPORT
[See attached]
Virginia Department of Transportation
FINAL GEOTECHNICAL BASELINE REPORT
I‐64 HAMPTON ROADS BRIDGE‐TUNNEL
EXPANSION PROJECT
UNDER THE
VIRGINIA PUBLIC‐PRIVATE
TRANSPORTATION ACT OF 1995
(AS AMENDED)
STATE PROJECT NO. 0064‐M06‐032
FEDERAL PROJECT NO. [●]
ISSUANCE OF FINAL GBR:
NOVEMBER 28, 2018
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Commonwealth of Virginia Project No. 0064‐M06‐032 i Virginia Department of Transportation
Table of Contents
1.0 Introduction ...................................................................................................................................... 1
1.1 Purpose and Scope ........................................................................................................................ 1
1.2 Project Elements Covered by GBR ................................................................................................ 1
1.3 Sources of Geotechnical Information ........................................................................................... 2
1.4 Stationing and Datum ................................................................................................................... 2
2.0 Project Description ............................................................................................................................ 4
3.0 Previous Construction Experience .................................................................................................... 5
3.1 Hampton Roads Project ................................................................................................................ 5
3.2 Second Hampton Roads Bridge‐Tunnel Crossing .......................................................................... 6
3.3 Other Projects ............................................................................................................................... 6
4.0 Ground Characterization ................................................................................................................... 7
4.1 Island Artificial Fill (af) ................................................................................................................... 8
4.2 Alluvial Marine Sediments ............................................................................................................ 9
4.2.1 Alluvial Marine Sediments – Coarse‐Grained (Qc) .............................................................. 10
4.2.2 Alluvial Marine Sediments – Fine‐Grained (Qf) .................................................................. 11
4.2.3 Alluvial Marine Sediments – Organic/Fat Clay (Qo) ............................................................ 12
4.3 Yorktown Formation (Tys, Tyf) .................................................................................................... 15
4.3.1 Yorktown Formation – Coarse‐Grained (Tys) ...................................................................... 15
4.3.2 Yorktown Formation – Predominantly Fine‐grained (Tyf) .................................................. 16
4.4 Eastover Formation (Tye) ............................................................................................................ 17
4.5 Groundwater ............................................................................................................................... 18
5.0 Design and Construction Considerations ........................................................................................ 25
5.1 Tunnel Approach Structures ....................................................................................................... 25
5.1.1 Stratigraphy ......................................................................................................................... 25
5.1.2 Obstructions ........................................................................................................................ 26
5.1.2.1 Rock Containment Dikes and Scour Protection ............................................................... 26
5.1.2.2 Temporary Works from Previous Construction ............................................................... 27
5.1.3 Groundwater Control .......................................................................................................... 28
5.1.4 Gas Conditions .................................................................................................................... 28
5.1.5 Soil pH ................................................................................................................................. 29
5.2 Bored Tunnel .............................................................................................................................. 29
5.2.1 Stratigraphy ......................................................................................................................... 29
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Commonwealth of Virginia Project No. 0064‐M06‐032 ii Virginia Department of Transportation
5.2.2 Break‐in/out ........................................................................................................................ 30
5.2.3 Behavior of Soft Soils .......................................................................................................... 31
5.2.4 Obstructions ........................................................................................................................ 32
5.2.4.1 Rock Containment Dikes and Scour Protection ............................................................... 32
5.2.4.2 Temporary Works from Previous Construction ............................................................... 33
5.2.4.3 Unrecovered Equipment from Geotechnical Drilling Program ........................................ 34
5.2.4.4 Foundations for Survey Towers ....................................................................................... 35
5.2.5 Sticky Clay Behavior ............................................................................................................ 35
5.2.6 Cemented Sand and Shell Zones ......................................................................................... 36
5.2.7 Soil Abrasion Behavior ........................................................................................................ 36
5.2.8 Gas Conditions .................................................................................................................... 37
5.2.9 Soil pH ................................................................................................................................. 37
5.3.2 Obstructions ........................................................................................................................ 38
6.0 Instrumentation and Monitoring .................................................................................................... 39
7.0 Limitations ....................................................................................................................................... 40
8.0 References ...................................................................................................................................... 41
APPENDIX A ‐ Boring Location Plan and Baseline Subsurface Profile ......................................................... 43
APPENDIX B – Tunnelman’s Classification System ...................................................................................... 44
Tables Table 4.1 Baseline Values for Soil Index Properties and Shear Strength Table 4.2 Baseline Values for Soil Permeability and Compressibility Table 5.1 Location of Unrecovered Equipment from Geotechnical Drilling Program Table 5.2 Baseline Values for Soil Abrasivity Figures Figure 4.1 Baseline Subsurface Profile Figure 4.2 Range of Particle Size Distribution ‐ Island Artificial Fill Figure 4.3 Range of Particle Size Distribution‐Alluvial Marine Sediments–Coarse‐Grained Figure 4.4 Plasticity Chart for Alluvial Marine Sediments – Fine‐Grained
Figure 4.5 Undrained Shear Strength v. Elevation, Fine‐Grained Alluvial Marine Sediments Figure 4.6 Plasticity Chart for Alluvial Marine Sediments – Organic/Fat Clay Figure 4.7 Range of Particle Size Distribution ‐ Yorktown Formation – Coarse‐Grained Figure 4.8 Plasticity Chart for Yorktown Formation – Predominantly Fine‐Grained Figure 4.9 Range of Particle Size Distribution ‐Eastover Formation
Figure 5.1 Limits of Ground Improvement Required to Support TBM in Soft Soils Figure 5.2 Location of Unrecovered Equipment from Geotechnical Drilling Program Appendices Appendix A Appendix B
Boring Location Plan and Baseline Subsurface Profile Tunnelman’s Classification System
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 1 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
1.0 Introduction
The purpose of this Geotechnical Baseline Report (GBR) is to establish contractual baselines
describing the anticipated ground conditions to be encountered during construction of the
following elements of the I‐64 Hampton Roads Bridge‐Tunnel Expansion (HRBT) project: the
Tunnel Improvements.
Capitalized terms used in this GBR but not otherwise defined herein shall have the meanings
given to such terms in the Comprehensive Agreement.
1.1 Purpose and Scope
The baselines established in this report shall be used by the Design‐Builders in proposal
preparation and will also be used to evaluate potential Differing Tunnel Improvements Site
Conditions encountered during construction. To evaluate design alternatives and approaches,
construction means and methods, selecting equipment, and developing construction plans,
Design‐Builders are required to read and consider the GBR, the Geotechnical Data Report (GDR),
and all other Request for Proposal (RFP) Documents in their entirety.
The geotechnical baseline conditions described in this report reflect the Department’s judgment
of anticipated subsurface conditions and ground behavior based on construction means and
methods commonly employed to complete the work indicated by the RFP Documents. In
establishing these baselines, the Department considered available geologic and geotechnical
data and construction experience in similar ground conditions. Actual conditions encountered in
the field are expected to be within the range of conditions discussed herein for purposes of
determining whether such conditions constitute Differing Tunnel Improvements Site Conditions
pursuant to Section 4.3.2 of the General Conditions of Contract. However, the geotechnical
baseline conditions presented in this report are not a warranty that these conditions will, in fact,
be encountered. Ground behavior will be influenced by, among other factors, the construction
sequence and methods employed by the Design‐Builder, as well as the Design‐Builder’s
equipment, materials and workmanship. The issuance of the baselines shall not relieve the
Design‐Builder of its responsibility for the adequacy of the subsurface investigation program with
respect to the design and alignment of the permanent works, the design and implementation of
construction means and methods and safety precautions and programs.
1.2 Project Elements Covered by GBR
This baseline report pertains only to the tunnel, the boat section and cut‐and‐cover tunnel
approach structures on the portal islands, and island expansions. This baseline report does not
represent conditions for other project construction elements, including the Roadway and Bridge
Improvements. The Department will not issue a GBR covering other project construction
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 2 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
activities. The baseline report does not represent environmental baseline conditions such as
contaminated or hazardous soils or other materials.
1.3 Sources of Geotechnical Information
Geotechnical Investigations have been performed in phases for this project, and the applicable
data for the tunnel and tunnel approach structures is presented in the following two
Geotechnical Data Reports, which are included as part of the Contract:
“Preliminary Geotechnical Data Report – Hampton Roads Bridge Tunnel – North and
South Islands”, prepared by ECS Mid‐Atlantic LLC and dated June 15, 2018.
“Geotechnical Data Report – Marine”, prepared by Jacobs Engineering and dated July
2018.
Additional geotechnical information from within and near the HRBT location can be found in the
historic reports, records and published references listed in Section 8.0. The additional
geotechnical information includes boring logs from the original HRBT tunnel construction in the
1950s and the construction of the second HRBT crossing in the 1970s. In addition to the
geotechnical information, an archaeological survey report (AECOM, 2017) includes the results of
geophysical investigations performed along the tunnel alignment. These reports, records and
published references listed in Section 8.0 are provided as Disclosed Information to the Contract.
1.4 Stationing and Datum
All stations referred to in this report are based on the stationing established for the second bridge
tunnel crossing in the 1970s, with the end of the northernmost tube at Station 862+57, and the
end of the southernmost tube at Station 931+54, as shown on Drawing S‐1 of the original plans
for Contract T‐2 (Commonwealth of Virginia, 1975).
The project datum for horizontal control is NAD83, and all elevations referred to in this report
are based on NAVD88.
1.5 Disclosed Information and Scope Validation on Portal Islands
The Disclosed Information included in the Comprehensive Agreement provides supplemental
data on subsurface conditions beyond the baselines described in this report, such as but not
limited to, the presence of utilities, building foundations, and other site improvements. Should
the Disclosed Information within the perimeters of the existing North and South Islands have a
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 3 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
material impact on the Design‐Builder’s means and methods, Article 2.2 of Part 4, General
Conditions of Contract relating to scope validation and identification of scope issues shall apply.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 4 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
2.0 Project Description
The Project consists of improvements along approximately nine miles of the I‐64 corridor
between Settlers Landing Road in Hampton (Exit 267) and I‐564 in Norfolk (Exit 276). On land,
the Project will add a third lane to I‐64 in each direction, with a roadway section sufficient to
accommodate a part‐time median shoulder lane.
The Project will include a new bridge‐tunnel crossing of the Hampton Roads waterway,
approximately 3.5 miles long and generally parallel to the existing bridge‐tunnel crossings. The
new crossing will provide four additional lanes of traffic for a total of eight lanes of capacity across
the waterway.
The bridge‐tunnel section of the project includes the following main components:
A new approximate 3.5‐mile‐long bridge‐tunnel parallel to the existing bridge‐tunnels;
The tunnel may be constructed as either an immersed tube tunnel (ITT) or a bored tunnel,
designed to carry four lanes of eastbound traffic (the existing two‐lane eastbound tunnel
will be subsequently converted to carry westbound traffic, thereby providing four lanes
of westbound traffic);
Widening of the existing north and south portal islands to the west as required to
accommodate the new portals and approach structures for the parallel tunnel;
New trestle bridges connecting the mainland to each of the portal islands;
Repairs and improvements to the existing trestle bridges; and
Support systems, services and utilities for the new tunnel including but not limited to:
tunnel ventilation buildings; tunnel ventilation systems and equipment; tunnel and
approach lighting; power for lighting and other tunnel electrical needs; tunnel drainage;
fire detection and alarm; communications (phones and radio system); fire protection
systems; intrusion detection, supervisory control and data acquisition (SCADA) and
information technology systems (ITS).
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 5 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
3.0 Previous Construction Experience
The existing bridge‐tunnel was built in two separate projects: one in the 1950s and the second in
the 1970s. Both projects were built using ITT method of construction. In addition to the original
design and record drawings for both projects, several technical journal articles describe the
construction of the original and second crossings in some detail; these articles are included in the
list of references in Section 8.0 of this report. In addition, project documents included as
Supplemental Information to the contract contain several hundred photos taken during
construction of each project.
There are also several other similar transportation tunnel projects in the vicinity of the Hampton
Roads Bridge‐Tunnel Expansion with similar construction methodologies and subsurface
conditions. Section 3.3 provides a list of those projects.
3.1 Hampton Roads Project
The original Hampton Roads Project was completed in 1957 and included construction of a two‐
lane bridge and tunnel connecting Norfolk, Virginia with Hampton, Virginia across the Hampton
Roads waterway. The tunnel has a length of 7,479 feet between portals and consists of 23 steel
immersed tube tunnel sections, each approximately 300 feet long. The tunnel sections were
placed in a dredged trench between two man‐made portal islands, while the tunnel approach
structures on the islands were built by cut and cover methods. Trestle bridge connections from
the portal islands to the mainland on both the north and south sides provide a total water
crossing length of approximately 3.5 miles.
The North Island was founded on sands and silty sands which provided a suitable foundation.
However, at the South Island location, up to 80 feet of normally consolidated clay and organic
layers overlying sandy soils were present, which were expected to cause settlement or stability
issues during island construction. To mitigate these issues, the soft layers were dredged out over
the width of the tunnel approach structures and vent buildings on the South Island with 2H:1V
slopes, and the excavation was then hydraulically backfilled with soils dredged from nearby areas.
This hydraulic fill consisted of poorly graded, fine sand, which was densified by vibro‐flotation.
The perimeter slopes of the islands are protected by rip rap and armor stone.
The tunnel approach structures on the islands were built by cut and cover methods with steel
sheeting or soldier pile and lagging with cross‐lot struts used for temporary support of
excavation. Dewatering systems were employed to build the cut and cover structures “in‐the‐
dry.” Ventilation buildings and other support facilities were constructed on the islands.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 6 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
3.2 Second Hampton Roads Bridge‐Tunnel Crossing
The second Hampton Roads Bridge‐Tunnel Crossing was completed in 1975, and was built parallel
to, and 250 feet to the west of, the original tunnel. Similar to the original tunnel, it consists of a
6,900‐ft long two‐lane steel immersed tube tunnel between the two portal islands, which were
enlarged to accommodate the new tunnel and approach structures. Two additional trestle
bridges connect the islands with the mainland.
Design and construction of the South Island expansion faced similar issues to the original
construction. As opposed to over‐excavating the underlying normally consolidated clay and
organic layers, sand drains were installed through the clay and organics, and a surcharge was
placed to pre‐consolidate these layers prior to tunnel construction. An initial contract to build
the South Island expansion included placement of fill up to 25 feet higher than the finished island
elevation, as well as the installation of the sand drains and monitoring systems. The
consolidation of the clay layers achieved 90% consolidation approximately 15 months after
completion of the surcharge placement, with a maximum measured settlement under the
highest surcharge of approximately 13 feet.
A second contract included the removal of the South Island surcharge, the construction of the
North Island expansion, and the immersed tube tunnel. The tunnel approach structures were
again built by cut and cover methods using temporary support of excavation systems including
sheeting and soldier pile and lagging, however this time with tiebacks instead of cross‐lot struts.
Dewatering systems were again employed to build the cut and cover structures “in the dry”.
Follow‐on contracts included construction of the ventilation buildings and other facilities.
3.3 Other Projects
Other similar tunnel projects in the vicinity of the Hampton Roads Bridge‐Tunnel Expansion with
similar subsurface conditions include the following:
Midtown Tunnel;
Downtown Tunnel;
I‐664 Monitor‐Merrimack Memorial Bridge‐Tunnel; and
Chesapeake Bay Bridge and Tunnel (original Thimble Shoal Channel and
Chesapeake Channel tunnels constructed in the 1960s, as well as the Parallel
Thimble Shoal Tunnel, which is currently under construction).
Transportation tunnel projects completed in the vicinity to date were constructed exclusively
using the immersed tube tunneling method. The proposed Parallel Thimble Shoal Tunnel for the
Chesapeake Bay Bridge‐Tunnel crossing, which is expected to commence tunneling operations in
2019, will be constructed using the bored tunneling method.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 7 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
4.0 Ground Characterization
The project site is located within the Coastal Plain of Virginia where the James River meets the
Chesapeake Bay. The Coastal Plain comprises a thick wedge of sediments underlain by
Precambrian to early Mesozoic basement bedrock at depths greater than 2,000 feet. The
majority of the sediments consist of late Jurassic and Cretaceous clays, sands and gravels which
were transported from the Appalachian Mountains and deposited in the Atlantic Ocean basin.
The subsurface materials anticipated to be encountered within the tunnel alignment overlie
these sediments, and comprise younger Tertiary and Quaternary layers that can generally be
classified into the following four geological strata, from youngest to oldest:
Island Artificial Fill (af)
Alluvial Marine Sediments (Qc, Qf, Qo)
Yorktown Formation (Tys, Tyf)
Eastover Formation (Tye)
The Yorktown and Eastover formations are fossiliferous marine sands and clays that were
deposited during interglacial highstands of the sea under similar conditions to the current site
environment. The Eastover is thought to be late Miocene‐aged, while the Yorktown is considered
to be early Pliocene‐aged. The Alluvial Marine Sediments are Quaternary aged, geologically
unconsolidated layers that were likely deposited during the Holocene and late Pleistocene
epochs.
Each stratum is discussed in the following sections of the report, and the baseline properties of
these layers are presented in Tables 4.1 and 4.2. A baseline subsurface profile projected along
the alignment of the second tunnel built in the 1970s is shown in Figure 4.1. In addition, in
Appendix A, the baseline subsurface profile is shown on full size sheets with the boring location
plan. This baseline profile is applicable for new tunnel alignments between the existing tunnels,
and for alignments up to 500 feet to the west of the second 1970s tunnel alignment. Although
the subsurface profile is drawn along the 1970s tunnel alignment, for clarity, the existing tunnel
structure and associated backfill materials are not included in the profile. The limits of existing
structures, and the associated dredging limits and backfill and scour protection materials are
shown on the record drawings (Commonwealth of Virginia, 1956, 1975). Qualifying statements
related to interpretation of the subsurface profile for different elements of the proposed
construction are presented in Sections 5.1.1, 5.2.1 and 5.3.1 of this report.
In Appendix B, the Tunnelman’s Classification System (after Heuer, 1974) is presented. This
classification system was developed to describe soft ground behavior during tunnel excavation
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 8 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
and each stratum that could be encountered in the bored tunnel alignment will be classified in
accordance with this system. Although this classification system was created before the
widespread use of pressurized‐face TBMs and therefore assumes an open‐face excavation
method, it is nevertheless useful for conveying how soils are anticipated to behave if not properly
controlled during tunneling or other excavation.
4.1 Island Artificial Fill (af)
The North Island and the South Island were constructed using hydraulically placed fill to a finished
surface elevation of approximately Elevation +11 feet. The hydraulic fill is predominantly
composed of clean fine sands and typically classifies in the Unified Soil Classification System
(USCS) as poorly graded sand (SP), silty sand (SM) and poorly graded sand with silt (SP‐SM).
Based on the mudline elevation shown on the drawings for the original tunnel construction
contracts, at the North Island, the artificial fill thickness varies between 20 and 25 feet, with the
base of the layer between Elevation ‐9 and ‐14 feet. At the South Island, the artificial fill thickness
to the west of the existing tunnels appears to vary between 33 and 48 feet below ground surface
with the base of the layer encountered between Elevations ‐22 and ‐37 feet. Although not
reflected by the most recent site investigations as documented in the GDRs, the fill thickness is
greater at locations beneath the original tunnels and tunnel approach structures constructed in
the 1950s, with the over‐excavation and replacement of the soft clay layers employed at that
time resulting in the fill extending to the top of the Yorktown formation, up to Elevation ‐105, as
shown in the 1950s record drawings and documented by Steuerman and Murphy (1957).
Over 13 feet of settlement was measured during construction of the South Island expansion in
the 1970s so it is reasonable that the fill thickness would be greater than for the North Island.
Based on analysis of the N60 SPT test results, the hydraulic fill is very loose to medium dense.
Grain size analyses were performed on several samples, and the range of particle size distribution
observed in the test samples from the recent geotechnical investigations is shown in Figure 4.2.
Baseline index and shear strength properties for this layer are provided in Table 4.1 and the range
for the hydraulic conductivity is included in Table 4.2. When encountered above the
groundwater level, this layer when unsupported and unimproved would classify in the
Tunnelman’s Classification System as “Running”, while below groundwater would classify as
“Flowing”.
Armor stone, rip rap, and crushed rock filter layers were placed around the island perimeters to
contain the hydraulic fill placement, and to provide scour protection. When the islands were
expanded in the 1970s construction, it is understood that the existing scour protection placed in
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 9 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
the 1950s was not removed but rather was buried under the new hydraulic fill; for example, a
note on Sheet 7 (of 127) of the record drawing set for Contract T‐2 (Commonwealth of Virginia,
1975) states: ”Existing rip rap and bedding along the entire west side of North Island to be
removed to El +7.0.”
Figure 4.2 Range of Particle Size Distribution ‐ Island Artificial Fill (af)
4.2 Alluvial Marine Sediments
Below the island fill, and below the mudline outside of the island footprints, a layer of alluvial
marine sediments is present, and consists of interlayered sands, inorganic and organic silts and
clays, and peat. Based on the properties of the materials in this layer, it can be sub‐divided into
the following three sub‐layers:
Alluvial Marine Sediments – Coarse‐Grained (Qc)
Alluvial Marine Sediments – Fine‐Grained (Qf)
Alluvial Marine Sediments – Organic/Fat Clay (Qo)
The distribution of these three sub‐layers is quite variable, particularly below the South Island.
The sub‐layers may be individually present or present in any combination. Furthermore, the
relative order of appearance of the sub‐layers, vertically, is also variable.
Gravel SandSilt or Clay
Coarse Fine Coarse Medium Fine
0
10
20
30
40
50
60
70
80
90
100
0.0010.0100.1001.00010.000100.000
Percent Finer
Particle Size (mm)
Maximum25% QuartileMedian75% QuartileMinimum
Hydrometer AnalysisUS Standard Sieve NumberUS Standard Sieve Size (inches)
#200#4 #10 #40 #80 #100
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 10 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
4.2.1 Alluvial Marine Sediments – Coarse‐Grained (Qc)
The coarse‐grained alluvial marine sediments were encountered below the fill of both islands and
below the mudline over most of the tunnel alignment. Below the North Island and north of
Station 878+00, the fine‐grained and organic/fat clay marine sediments were not encountered,
and the coarse‐grained deposits extend to the top of the Yorktown formation, which was
encountered between Elevations ‐85 and ‐32 feet. South of Station 878+00, the coarse‐grained
sediments vary between 5 and 30 feet thick and are typically encountered above the fine‐grained
alluvial marine sediment layers, but in some locations granular layers and lenses are also
encountered within and below the cohesive alluvial deposits. The coarse‐grained alluvial marine
sediments are very loose to dense, and generally classify in the USCS as poorly graded sand (SP),
silty sand (SM), and clayey sand (SC). Grain size analyses were performed on several samples,
and the range of particle size distribution observed in the test samples is shown in Figure 4.3.
Figure 4.3 Range of Particle Size Distribution‐Alluvial Marine Sediments–Coarse‐Grained (Qc)
Baseline index and shear strength properties for the Qc layer are provided in Table 4.1 and the
baseline hydraulic conductivity range is listed in Table 4.2. If left unsupported or not modified
with ground improvement, depending on the fines content and water pressure, this layer would
classify as “Fast Raveling” or “Flowing” in the Tunnelman’s Classification System, as detailed in
Appendix B.
Sand
FineMediumCoarseSilt or Clay
Gravel
Coarse Fine
0
10
20
30
40
50
60
70
80
90
100
0.0010.0100.1001.00010.000100.000
Percent Finer
Particle Size (mm)
Maximum25% QuartileMedian75% QuartileMinimum
Hydrometer AnalysisUS Standard Sieve NumberUS Standard Sieve Size (inches)
#200#4 #10 #40 #80 #100
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 11 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
4.2.2 Alluvial Marine Sediments – Fine‐grained (Qf)
From approximately Station 878+00 to 945+00, the fine‐grained marine sediments were
encountered below the coarse‐grained marine sediments. The fine‐grained marine sediments
predominantly consist of lean clay (CL) and fat clay (CH). A plasticity chart showing the liquid
limit plotted versus the plasticity index for laboratory tests on this layer is shown in Figure 4.4.
The thickness of the Qf layer is quite variable, and it can be difficult to visually distinguish
between the underlying organic/fat clay sub‐layer (i.e. the Qo layer described below). However,
the distinction between the two sub‐layers is clear from laboratory test data.
Below the channel between Stations 878+00 and 928+00, the top of the fine‐grained Alluvial
Marine Sediment layer was encountered below the coarse‐grained marine sediments between
Elevations ‐45 and ‐90 feet and varied between a few feet to over 35 feet thick. Below the South
Island, between Stations 928+00 and 945+00, the top of the fine‐grained Alluvial Marine
Sediment layer was encountered between Elevation ‐25 and ‐50 feet, and was up to 30 feet thick.
Figure 4.4 Plasticity Chart for Alluvial Marine Sediments – Fine‐grained (Qf)
Extensive in situ shear strength testing was performed during the geotechnical investigation
programs, including CPT probes, field vane shear tests, and flat plate dilatometer tests. In
addition, an extensive laboratory testing program was performed. The results of these tests were
highly variable. Figure 4.5 shows the measured undrained shear strength from the various tests
versus elevation. The plot has been split between the results from the marine geotechnical
0
10
20
30
40
50
60
70
80
0 10 20 30 40 50 60 70 80 90 100
Plasticity Index
Liquid Limit
Alluvial Marine Sediments ‐ Fine grained (Qf)
CL‐ML ML or OLMH or OH
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 12 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
program performed by Jacobs Engineering (Figure 4.5a) and the South Island geotechnical
investigation by ECS Mid‐Atlantic LLC (Figure 4.5b). The data in Figure 4.5 includes results from
both the Qf sub‐layer and the Qo sub‐layer.
On the South Island, between Stations 928+00 and 944+00, the 1970s tunnel construction placed
a surcharge up to 26 feet over the current island elevation, which pre‐consolidated this layer and
increased the shear strength below the island. The increase in strength is apparent from a
comparison of the field and laboratory test results between the two GDRs. Figure 4.5 shows the
overall range of the test results from the marine and South Island investigations, which
demonstrates the increased shear strength below the South Island. Typical ranges of shear
strength are also highlighted, which shows an increase in strength with depth. Two baseline
ranges of undrained shear strength are provided in Table 4.1; one for locations outside the South
Island surcharge from the 1970s construction, and the second for pre‐consolidated layers below
the South Island surcharge.
The consolidation properties of the Qf sub‐layer were investigated by performing pore pressure
dissipation tests during the CPT probing, and by an extensive laboratory test program consisting
of one‐dimensional consolidations tests. In addition, the South Island pre‐consolidation works
from the 1970s were instrumented and well‐documented (Kuesel et al, 1973), which effectively
provides a field load test of in situ compressibility properties.
Baseline index and shear strength properties for the Qf sub‐layer are provided in Table 4.1, and
the baseline range for parameters relating to compressibility of the layer is presented in Table
4.2. This layer would classify as “Squeezing” in the Tunnelman’s Classification System.
4.2.3 Alluvial Marine Sediments – Organic/Fat Clay (Qo)
Below the channel between Stations 878+00 and 906+00, the Alluvial Marine Sediment‐
Organic/Fat Clay layer was encountered between Elevations ‐60 and ‐110 feet, and generally
varied between 10 and 20 feet thick. Between Stations 906+00 and 928+00 the thickness
increased to approximately 50 feet. Below the northern section of the South Island, between
Stations 928+00 and 932+00, the layer is as much as 60 feet thick and between Station 932+00
and 942+00 decreases to about 20 feet thick.
The index properties and classification of this layer were quite variable; it was variously classified
as fat clay (CH), organic clay (OL), fat organic clay (OH) and peat (PT). A plasticity chart showing
the liquid limit plotted versus the plasticity index for laboratory tests on this layer is shown in
Figure 4.6.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 13 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.5a Outside South Island Surcharge Area from 1970s Construction
Figure 4.5b: Below South Island Surcharge Area from 1970s Construction
Figure 4.5 Undrained Shear Strength v. Elevation, Fine‐Grained Alluvial Marine Sediments
(Note: The test results shown include both Qf and Qo sub‐layers )
‐160
‐140
‐120
‐100
‐80
‐60
‐40
‐20
0
0 500 1000 1500 2000 2500 3000 3500Eleva
tion (ft)
Su (psf) Marine
VST
UU Test
CU Test
DM Tests Marchetti
DM Tests Schmertman
Typical Range
‐160
‐140
‐120
‐100
‐80
‐60
‐40
‐20
0
0 500 1000 1500 2000 2500 3000 3500
Elev
ation (ft)
Su (psf) South Island
DM Tests Marchetti
DM Tests Schmertman
CU Tests
UU Tests
Typical Range
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 14 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.6 Plasticity Chart for Alluvial Marine Sediments – Organic/Fat Clay (Qo)
Extensive in situ and laboratory shear strength testing was also performed for this layer during
the geotechnical investigation programs, and the measured undrained shear strength versus
elevation from the various tests is shown in Figure 4.5. As discussed in the previous section of
the report, the plot has been split between the results from the marine geotechnical program
(Figure 4.5a) and the geotechnical investigation from the South Island (Figure 4.5b).
The consolidation properties of the Qo sub‐layer were also investigated by performing pore‐
pressure dissipation tests during the CPT probing, and by an extensive laboratory test program
consisting of one‐dimensional consolidations tests. As discussed in the previous section, the
South Island pre‐consolidation works from the 1970s were instrumented and well‐documented
(Kuesel et al, 1973), which effectively provides a field load test of in situ compressibility
properties.
Baseline index and shear strength properties for the Qo layer are provided in Table 4.1, and the
baseline range for parameters relating to compressibility of the layer is presented in Table 4.2.
This layer would classify as “Squeezing” in the Tunnelman’s Classification System, as detailed in
Appendix B.
0
10
20
30
40
50
60
70
80
90
0 10 20 30 40 50 60 70 80 90 100
Plasticity Index
Liquid Limit
Alluvial Marine Sediments ‐ Organic/Highly Plastic Clay (Qo)
CL‐ML ML or OLMH or OH
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 15 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
4.3 Yorktown Formation (Tys, Tyf)
The Yorktown Formation lies beneath the Alluvial Marine Sediments over the entire tunnel
alignment and can generally be distinguished by the change to a green to blue gray color. The
top of the formation was encountered between Elevations ‐32 and ‐52 feet below the North
Island, between Elevations ‐60 and ‐140 feet between the islands, and between Elevations ‐40
and ‐120 feet below the South Island. The Yorktown formation is predominantly a granular layer,
but throughout, there are numerous interbedded layers of fine‐grained deposits; it can therefore
be subdivided into the following two sub‐layers:
Yorktown Formation – Predominantly Coarse‐Grained (Tys)
Yorktown Formation – Predominantly Fine‐Grained (Tyf)
4.3.1 Yorktown Formation – Coarse‐Grained (Tys)
The coarse‐grained Yorktown formation layer generally consists of green to blue‐gray, over‐
consolidated, silty fine sand with varying amounts of fine‐grained fractions and marine shell
fragments, typically classified as silty sand (SM) or clayey sand (SC), and sometimes classified as
poorly‐graded sand (SP), well‐graded sand (SW), poorly‐graded gravel (GP) or well‐graded gravel
(GW). Based on analysis of the N60 SPT test results, the layer relative density varies from very
loose to very dense.
In several zones, the SPT test recorded “weight of rod” resistance at depths of over 100 feet
below the mudline, which was unexpected within this over‐consolidated layer; these SPT results
may not be truly representative of the in situ relative density and may have been caused by
sample disturbance in the difficult drilling conditions involving fine sand layers under high
hydrostatic pressures.
Grain size analyses were performed on several samples, and the range of particle size distribution
observed in the test samples is shown in Figure 4.7.
Baseline index and shear strength properties for the Tys layer are provided in Table 4.1 and the
baseline hydraulic conductivity range is listed in Table 4.2. When unsupported and unimproved,
and depending on the fines content and water pressure, this layer would classify as “Fast
Raveling” or “Flowing” in the Tunnelman’s Classification System, as detailed in Appendix B.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 16 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.7 Range of Particle Size Distribution ‐ Yorktown Formation – Coarse‐Grained (Tys)
4.3.2 Yorktown Formation – Predominantly Fine‐grained (Tyf)
Fine‐grained layers comprising very stiff to hard sandy, shelly clays, were encountered at various
elevations within the Yorktown formation. These layers are more prevalent towards the base of
the formation, between Elevations ‐150 and ‐170 feet, where a 5 to 20 feet thick layer was
observed along most of the tunnel alignment. This layer generally classifies as either fat or lean
clay (CH or CL) with sand. A plasticity chart showing the liquid limit plotted versus the plasticity
index for laboratory tests on this layer is shown in Figure 4.8.
Baseline index and shear strength properties for the Tyf layer are provided in Table 4.1. This
layer would classify as “Squeezing” in the Tunnelman’s Classification System, as detailed in
Appendix B.
Gravel SandSilt or Clay
Coarse Fine Coarse Medium Fine
0
10
20
30
40
50
60
70
80
90
100
0.0010.0100.1001.00010.000100.000
Percent Finer
Particle Size (mm)
Maximum25% QuartileMedian75% QuartileMinimum
Hydrometer AnalysisUS Standard Sieve NumberUS Standard Sieve Size (inches)
#200#4 #10 #40 #80 #100
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 17 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.8 Plasticity Chart for Yorktown Formation – Predominantly Fine‐Grained (Tyf)
4.4 Eastover Formation (Tye)
The Eastover formation underlies the Yorktown formation along the entire tunnel alignment and
was first encountered at elevations varying between Elevation ‐158 feet to Elevation ‐175. The
formation extended to Elevation ‐275 feet where the deeper borings were terminated. The
Eastover formation generally consists of green‐gray, over‐consolidated, fine to coarse sand with
varying amounts of fine‐grained material and marine shell fragments. The formation is
comprised of poorly graded sand (SP), silty sand (SM), clayey sand (SC) and poorly graded sand
with clay (SP‐SC). A dense marker bed consisting of cemented shell fragments and coarse sand
was encountered overlying the Eastover formation. Based on analysis of the N60 SPT test results,
the layer’s relative density varies from very loose to very dense.
In several zones, the SPT test recorded “weight of rod” resistance at depths of over 100 feet
below the mudline, which was unexpected within this over‐consolidated layer; these SPT results
may not be truly representative of the in situ relative density and may have been caused by
sample disturbance in the relatively difficult drilling conditions involving fine sand layers under
high hydrostatic pressures. Some SPT samples also encountered refusal within this layer which
is considered to be representative of denser, more cemented zones.
0
10
20
30
40
50
60
70
80
0 10 20 30 40 50 60 70 80 90 100
Plasticity In
dex
Liquid Limit
Yorktown Formation ‐ Fine grained (Tyf)
CL‐ML ML or OLMH or OH
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 18 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Grain size analyses were performed on several samples, and the range of particle size
distribution observed in the test samples is shown in Figure 4.9.
Figure 4.9 Range of Particle Size Distribution ‐ Eastover Formation (Tye)
Baseline index and shear strength properties for the Tye layer are provided in Table 4.1. This
layer when unsupported and unimproved would classify as “Flowing” in the Tunnelman’s
Classification System, as detailed in Appendix B.
4.5 Groundwater
Groundwater levels at the site are based on tidal fluctuations and are expected to vary from
Elevation +4 feet at high tide to Elevation ‐1 feet at low tide.
Artesian groundwater conditions were not observed during the project geotechnical
investigation but have been reported present in the Yorktown and Eastover formations in the
technical literature (e.g. Hamilton and Larson, 1988).
For baseline purposes, the Design‐Builder shall consider that the groundwater pressure in all
subsurface layers may vary by ±5 feet from the hydrostatic pressure due to the ambient sea level
in the shipping channel.
Gravel SandSilt or Clay
Coarse Fine Coarse Medium Fine
0
10
20
30
40
50
60
70
80
90
100
0.0010.0100.1001.00010.000100.000
Percent Finer
Particle Size (mm)
Maximum25% QuartileMedian75% QuartileMinimum
Hydrometer AnalysisUS Standard Sieve NumberUS Standard Sieve Size (inches)
#200#4 #10 #40 #80 #100
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 19 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Notes:
1. The baseline values shown represent the range of material properties that the Design‐Builder must consider when selecting construction equipment and materials, means and methods, and evaluating the potential impacts of construction on existing structures. Soil properties for design of the temporary and permanent project elements shall be derived by the Design‐Builder in accordance with Section 24, Geotechnical ‐ Islands and Tunnels of the Technical Requirements of the Contract.
2. Baselines for artificial fill consider the hydraulically placed sand only; the baselines do not consider the oversized material (i.e. containment dikes material, scour protection material, etc.).
3. The first range of undrained shear strength is for locations outside the 1970s South Island surcharge area, while the second range is for pre‐consolidated layers below the South Island surcharge. The extents of the South Island surcharge area shall be defined to be as shown on Drawing No S‐6 of Contract T‐2 of the 1970s construction record drawings (Commonwealth of Virginia, 1975).
4. Cemented sand and shell layers up to 5 feet thick within the Yorktown and Eastover Formations may have unconfined compressive strength up to 1000 psi. 5. For the granular layers (af, Qc, Tys, and Tye), the baseline range of the layer’s particle size distribution shall be between the maximum and minimum limits shown on
Figures 4.2, 4.3, 4.7 and 4.9. 6. For table entries designated as “N/A”, a baseline range is not provided.
Table 4.1 – Baseline Values for Soil Index Properties and Shear Strength
Stratum / Sub‐Layer Typical USCS
Classification
Total Unit Weight
Water Content
Liquid Limit
Plasticity Index
Effective Friction Angle (°)
Undrained Shear
Strength (psf)(pcf) (%) (%)
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Island Artificial Fill (af)(2) SP, SM, SP‐SM 105‐125 N/A Non‐Plastic
N/A 30‐34 N/A
Alluvial Marine Sediments – Coarse‐Grained (Qc)
SP, SM, SC 105‐125 N/A Non‐Plastic
N/A 30‐40 N/A
Alluvial Marine Sediments – Fine‐Grained (Qf) CL, CH 100‐120 20‐60 30‐60 15‐30 N/A 225‐750(3) 525‐1400
Alluvial Marine Sediments ‐ Organic/Fat Clay (Qo)
OL, OH, CH, PT 90‐110 35‐75 30‐110 25‐60 N/A 125‐650 (3) 250‐1500
Yorktown Formation – Coarse‐Grained (Tys) SM, SC 115‐130 N/A Non‐Plastic
N/A 30‐42 N/A(4)
Yorktown Formation – Fine‐Grained (Tyf) CL, CH 110‐130 25‐40 30‐55 15‐40 N/A 750‐6000(4)
Eastover Formation (Tye) SP, SM, SP‐SC 120‐130 N/A Non‐Plastic
N/A 30‐42 N/A(4)
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 20 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Notes: 1. The baseline values shown represent the range of material properties that the Design‐Builder must consider when selecting construction equipment and
materials, means and methods, and evaluating the potential impacts of construction on existing structures. Soil properties for design of the temporary and permanent project elements shall be derived by the Design‐Builder in accordance with Section 24, Geotechnical – Islands and Tunnels of the Technical Requirements of the Contract.
2. The first range of OCR is for locations outside the 1970s South Island surcharge area, while the second range is for pre‐consolidated layers below the South Island surcharge area. The extents of the South Island surcharge area shall be defined to be as shown on Drawing No S‐6 of Contract T‐2 of the 1970s construction record drawings (Commonwealth of Virginia, 1975).
3. Horizontal and vertical coefficient of consolidation shall be considered equal. The first range of Cv is representative for virgin compression, while the second range is for recompression.
4. For table entries designated as “N/A”, a baseline range is not provided.
Table 4.2 – Baseline Values for Soil Permeability and Compressibility
Stratum / Sub‐Layer Typical USCS
Classification
Hydraulic Conductivity
In Situ Void Ratio
Over Consolidation
Ratio (OCR)
Compression Index (Cc)
Recompress‐ ion Index
(Cr)
Coefficient of Secondary
Compression (Cα)
Coefficient of Consolidation(3)
(Cv)
(cm/sec) (cm2/sec)
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Baseline Range
Island Artificial Fill (af) SP, SM, SP‐SM 10‐3‐ 10‐1 N/A N/A N/A N/A N/A N/A
Alluvial Marine Sediments ‐ Coarse Grained (Qc)
SP, SM, SC 10‐3 – 10‐1 N/A N/A N/A N/A N/A N/A
Alluvial Marine Sediments – Fine‐ Grained (Qf)
CL, CH 10‐7 to 10‐5 0.6‐1.0 1.0 – 1.5(2)
1.0 – 2.0 0.30‐0.50 0.02‐0.05 0.001‐0.005 0.003‐0.030(3) 0.001‐0.020
Alluvial Marine Sediments ‐ Organic/Fat Clay (Qo)
OL, OH, CH, PT 10‐7 to 10‐5 1.3‐2.0 1.0 – 1.5(2)
1.0 – 2.0 0.60‐1.00 0.05‐0.16 0.001‐0.010 0.001‐0.015(3) 0.0005‐0.010
Yorktown Formation – Coarse‐ Grained (Tys)
SM, SC 10‐3 – 10‐1 N/A N/A N/A N/A N/A N/A
Yorktown Formation ‐ Fine‐Grained (Tyf)
CL, CH N/A N/A N/A N/A N/A N/A N/A
Eastover Formation (Tye) SP, SM, SP‐SC N/A N/A N/A N/A N/A N/A N/A
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 21 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.1 – Baseline Subsurface Profile 1/4
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 22 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.1 – Baseline Subsurface Profile 2/4
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 23 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.1 – Baseline Subsurface Profile 3/4
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 24 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 4.1 – Baseline Subsurface Profile 4/4
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 25 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
5.0 Design and Construction Considerations
This section will discuss design and construction considerations as well as anticipated ground
behavior during construction of the Tunnel Improvements, including:
Below‐grade tunnel approach structures
Bored tunnel
Island expansions 5.1 Tunnel Approach Structures
It is anticipated that the below‐grade approach structure to the bored tunnel on both portal
islands will be similar to the existing boat sections and cut and cover tunnels. This will involve
installation of support of excavation systems, excavation to the design subgrade level, and
construction of the reinforced concrete structures.
5.1.1 Stratigraphy Figure 4.1 shows the baseline stratigraphy along the tunnel approaches based on the recent and
historic geotechnical information. For design and construction of the tunnel approach structures,
the interfaces between adjacent geological strata shown in the baseline profile are qualified by
the following statements:
North Island (Station 850+00 to 867+00):
The boundary shown between the Artificial Fill (af) and the Alluvial Marine Sediments
Coarse‐grained (Qc) is not baselined. The geotechnical properties of both materials are
similar. Obstructions, that may be encountered more frequently in the fill layer, are
addressed in Section 5.1.2 of this GBR; and
The boundary between the Alluvial Marine Sediments (Qc) and the Yorktown formation
(Tys) is baselined and may vary by ±5 feet from the boundary shown in Figure 4.1.
South Island (Station 924+00 to 945+00):
The boundary shown between the Artificial Fill (af) and the Alluvial Marine Sediments‐
Coarse‐grained (Qc) is not baselined. The geotechnical properties of both materials are
similar. Obstructions that may be encountered more frequently in the fill layer are
addressed in Section 5.1.2 of this GBR;
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 26 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
The boundary between the Alluvial Marine Sediments‐Coarse‐grained sub‐layer (Qc) and
the underlying Alluvial Marine Sediments‐Fine‐grained sub‐layer (Qf) is baselined and
may vary by ±5 feet from the boundary shown in Figure 4.1;
The boundary between the Alluvial Marine Sediments‐Fine‐grained sub‐layer (Qf) and the
underlying Alluvial Marine Sediments‐Organic/Fat Clay sub‐layer (Qo) is baselined and
may vary by ±5 feet from the boundary shown in Figure 4.1; and
The boundary between the Alluvial Marine Sediments (Qc, Qf, Qo) and the Yorktown
formation is baselined and may vary by ±5 feet from the boundary shown in Figure 4.1.
5.1.2 Obstructions
There are numerous potential obstructions that may affect the construction of the tunnel
approach structures and must be accounted for by the Design‐Builder both in the design and
selection of means and methods of construction. These obstructions fall into the following
categories and are discussed in the subsequent paragraphs:
Rock Containment Dikes and Scour Protection; and
Temporary Works from Previous Construction.
5.1.2.1 Rock Containment Dikes and Scour Protection As shown on the record drawings (Commonwealth of Virginia, 1956, 1975), the existing portal
islands were constructed using a series of containment dikes, which contain armor stone with
individual stone size varying up to a maximum dimension of 5 feet. Additionally, the portal
islands, as well as the existing tunnels, are covered with various layers of scour protection
including heavy rip rap, quarry run rock and gravel sized crushed rock. The materials that
comprise the containment dikes and the scour protection were obtained from intact, crystalline,
igneous or metamorphic rock sources. They could potentially cause obstructions to installation
of support of excavations systems, and cause handling difficulties requiring special lifting
equipment during mass excavation of the approaches.
These rip rap and stone layers were installed in both the 1950s and 1970s construction, and it is
understood that the original stone layers from the 1950s were buried when the islands were
expanded in the 1970s. The general location of the armor stone dikes and heavy rip rap
placements are shown on the record drawings (Commonwealth of Virginia, 1956, 1975) and
construction photographs included as Supplemental Information to the Contract.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 27 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
It is also very likely that rip rap and stone layers were also placed, inadvertently or otherwise, in
areas not shown on the record drawings. In addition, numerous major storms have occurred
throughout the construction and operational history of the islands which have damaged the
stone protection of both islands. This has resulted in the deposition and possible burial of
random armor stone, construction materials and other miscellaneous debris within the limits of
the proposed temporary and permanent construction.
For baseline purposes, the Design‐Builder shall be prepared to encounter heavy rip rap and other
large stone layers as follows:
At the North Island, between Stations 850+00 and 867+00, the Design‐Builder may
encounter armor stone with individual stone size up to a maximum dimension of 5 feet
and weighing up to 10 tons anywhere above Elevation ‐25 feet. This applies over a width
of 500 feet to the east and 200 feet to the west of the second 1970s tunnel centerline.
At the South Island, between Stations 924+00 and 945+00, the Design‐Builder may
encounter armor stone with individual stone size up to a maximum dimension of 5 feet
and weighing up to 10 tons anywhere above Elevation ‐30 feet. This applies over a width
of 500 feet to the east and west of the second 1970s tunnel centerline.
The thickness of the various stone layers is shown on the record drawings
(Commonwealth of Virginia, 1956, 1975) and for baseline purposes may be encountered
in local areas up to twice the layer dimension shown on the drawings.
The Design‐Builder’s means and methods and bid price shall account for accommodating any rip
rap or stone layers encountered within the limits outlined in the previous three bulleted items.
Heavy rip rap or armor stone is not expected to be encountered outside of these limits.
5.1.2.2 Temporary Works from Previous Construction
Based on review of construction photographs, both the 1950s and 1970s construction employed
a combination of soldier pile and lagging and steel sheeting to support the tunnel approach
excavations. In the 1950s, cross lot struts were placed between the two walls, whereas tiebacks
were installed in the 1970s. To maintain a dry excavation, dewatering wells were also installed.
Dewatering wells were likely to be more numerous in the vicinity of where excavations were
deepest. Temporary piers supported on piles may also have been constructed around the
perimeter of the islands for off‐loading construction materials.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 28 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
The Design‐Builder’s means and methods and bid price for the tunnel approach structures shall
account for encountering any of the following temporary works from previous construction:
Steel soldier pile and lagging or steel sheeting encountered up to 10 feet behind the face
of the current finished walls of the tunnel approaches, and up to 20 feet below the base
of the original excavation.
Tieback tendons encountered up to 65 feet behind the face of the finished walls, and up
to 20 feet below the full depth of the original excavation. Tieback tendons are baselined
to have been de‐tensioned;
Steel dewatering well screens may be encountered to Elevation ‐140 feet and may be
present within 50 feet of the periphery of the current approach structures. Dewatering
wells may or may not have been grouted or backfilled when abandoned.
5.1.3 Groundwater Control
The Design‐Builder shall not rely on any untreated in situ soil strata (or combination of soil strata)
to provide stability and/or groundwater cutoff for any excavation required for the tunnel
approach structures. The Design‐Builder shall consider that dewatering or ground treatment,
along with provision of sufficient penetration below the base of excavation with support of
excavation walls, will be required to provide stability and limit groundwater inflows into the
excavations.
5.1.4 Gas Conditions The geotechnical investigations did not find any evidence of the presence of gas in the deposits
that will be encountered during construction of the approach structures. However, the
occurrence of methane due to decay of organic matter is expected. Historic records indicate that
the organic layers present from Station 878+00 to 945+00 have previously been a source of gas.
It is understood that during installation of the sand drains on the South Island during the 1970s
construction, methane gas was encountered. The escaping gas was lit which fueled a flare that
burned for months. In addition, in a 1970s era boring for I‐64 on the Willoughby Spit, to the south
of the South Island, methane gas was encountered in the organic layer, which led to relocation
of a proposed bridge following an unsuccessful attempt to burn off the gas that lasted for three
months without a significant drop in pressure.
Therefore, during construction of the below grade tunnel approach structures on the South
Island, gas may be encountered during any construction activity that penetrates layers with
organic content.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 29 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
5.1.5 Soil pH Soil pH testing was conducted on samples from all strata that will be encountered in the
tunneling. For baseline purposes, the Design‐Builder shall consider the soil pH value will range
between a minimum of 7.0 and a maximum of 11.0.
5.2 Bored Tunnel
This section describes anticipated subsurface conditions along the bored tunnel alignment
including soil stratigraphy, ground improvement required to stabilize very soft layers below the
TBM, potential obstructions, and various geotechnical‐related issues that could arise during
construction of the tunnel.
Section 23, Bored Tunnel of the Technical Requirements (TRs) of the Contract Documents
requires tunnel excavation methods that were established based on the need to control unstable
ground conditions. The minimum requirements include the use of a pressurized face Tunnel
Boring Machine (TBM) that can control groundwater and stabilize the tunnel face in the various
strata that will be encountered. This machine must be able to apply a positive pressure to the
tunnel face, resisting the earth and groundwater pressures to effectively control the ground and
groundwater inflows.
5.2.1 Stratigraphy Figure 4.1 shows the baseline stratigraphy along the tunnel alignment based on the recent and
historic geotechnical information. For design and construction of the bored tunnel by TBM, the
boundaries between adjacent geological strata shown in the baseline profile are qualified by the
following statements:
The boundary shown between the Artificial Island Fill (af) and the Alluvial Marine
Sediments‐Coarse‐grained (Qc) is not baselined. The geotechnical properties of both
materials are similar.
The boundary shown between the Alluvial Marine Sediments‐Coarse‐grained sub‐layer
(Qc) and the Alluvial Marine Sediments‐ Fine‐grained sub‐layer (Qf) is baselined and may
vary by ±5 feet.
The boundary shown between the Alluvial Marine Sediments‐Fine‐ grained sub‐layer (Qf)
and the Alluvial Marine Sediments‐ Organic/Fat Clay sub‐layer (Qo) is not baselined.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 30 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Except for the baseline for determining ground improvement limits provided in the next
bullet, the boundary shown between the Alluvial Marine Sediments (Qc, Qf, Qo) and the
Yorktown formation (Tys) is baselined and may vary by ±5 feet.
For determining ground improvement limits required by the contract, the boundary
shown between the Alluvial Marine Sediments (Qc, Qf, Qo) and the Yorktown formation
(Tys) is baselined and does not vary from the location shown in Figure 4.1.
The boundary shown between the two Yorktown formation sub‐layers (Tys, Tyf), and
between the Yorktown and the Eastover formations is not baselined. When tunneling in
the Yorktown (Tys, Tyf), or the Eastover (Tye) formations, the TBM excavation will include
very soft to hard cohesive deposits, very loose to very dense granular deposits, as well as
cemented sands and shell layers; the Design‐Builder shall be prepared to encounter the
full range of the materials defined in this GBR for the Yorktown and Eastover Formations
anywhere along the tunnel alignment below the Alluvial Marine Sediments stratum (Qc,
Qf, Qo).
The Design‐Builder shall anticipate unstable soil conditions (e.g., flowing soil as defined in
Appendix B) at any location along the tunnel alignment and accordingly must maintain a positive
face pressure at the heading at all times; therefore, methods to excavate the tunnel in a
controlled manner (i.e., match the muck removal rate from the excavation chamber to the
advance rate of the TBM while maintaining the desired pressure at the working face) will be
necessary to maintain stability and control of over‐excavation. Refer to TR Section 23, Bored
Tunnel for minimum TBM requirements and requirements for compressed air interventions. The
ground conditions along the entire alignment will not support free air interventions.
Although adjustments to TBM operating parameters (e.g., face pressures, type and volume of
soil conditioning) are to be expected with the mixed soil conditions to be encountered at the face
of the TBM, these adjustments will be more frequent within zones where soil groups with
distinctly different index or engineering characteristics are encountered. Changes in the behavior
of the excavated material (e.g. stickiness, abrasivity, strength, and hydraulic conductivity) will
also occur as the proportion of the different soil groups encountered at the face changes.
Therefore, continuous monitoring and adjustments of face pressures and conditioners will be
necessary when tunneling throughout.
5.2.2 Break‐in/out Ground improvement will be necessary to allow for a stable excavation during break‐out/break‐
in of the TBM from the tunnel approach structures at the portal islands (i.e. the soil at the break‐
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 31 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
out/break‐in locations will be neither stable nor impervious). TR Section 23, Bored Tunnel
specifies minimum requirements for the ground improvement.
5.2.3 Behavior of Soft Soils Between approximately Stations 877+50 and 945+50, and between approximately Elevations ‐50
and ‐130 feet, the Alluvial Marine Sediments‐Fine‐grained sub‐layer (Qf) and the underlying
Alluvial Marine Sediments‐Organic/Fat Clay sub‐layer (Qo) consist of very soft, inorganic and
organic silts and clays, and peat. Ground improvement will be required to strengthen these layers
to provide sufficient support to the TBM to maintain alignment and grade.
TR Section 23, Bored Tunnel requires that between Stations 877+50 and 945+50, whenever any
part of the tunnel below the springline is within the Alluvial Marine Sediments‐Fine‐grained sub‐
layer (Qf) or the Alluvial Marine Sediments‐Organic/Fat Clay sub‐layer (Qo), the Design‐Builder
shall provide ground improvement to the in situ soils in advance of tunneling. The horizontal and
vertical limits of the ground improvement required by Section 23 are shown in Figure 5.1.
Figure 5.1 ‐ Limits of Ground Improvement Required to Support TBM in Soft Soils
The Design‐Builder’s bid price for the required ground improvement should be based on the
baseline profile shown in Figures 4.1 as modified by the qualifying statements in Section 5.2.1.
Prior to performance of this ground improvement, TR Section 24, Geotechnical ‐ Islands and
Tunnels requires that a detailed geotechnical investigation be implemented to define the top and
bottom of the Qf and Qo sub‐layers.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 32 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
The ground improvement method shall be selected by the Design‐Builder to be compatible with
their tunneling operations from the alternatives listed in TR Section 24, Geotechnical ‐ Islands
and Tunnels. Other ground improvement techniques may be considered as an Alternative
Technical Concept (ATC). The design and performance requirements of the ground improvement
is the responsibility of the Design‐Builder. The improved ground limits and characteristics shall
be able to support the TBM to maintain the Design‐Builder’s proposed tunnel alignment within
reasonable driving tolerances.
5.2.4 Obstructions
The geologic strata present along the tunnel alignment are not known to contain naturally
occurring boulders that could impede the progress of the TBM, and the Design‐Builder may
consider that boulders will not be encountered outside the limits defined herein for man‐made
obstructions. Nevertheless, as a safeguard, and as required by TR Section 23, Bored Tunnel, the
TBM shall be equipped to accommodate boulders.
There are numerous “man‐made” obstructions that may impede the progress of the TBM and
must be accounted for by the Design‐Builder both in the design and selection of means and
methods of construction. These obstructions fall into the following categories and are discussed
in the following paragraphs:
Rock Containment Dikes and Scour Protection;
Temporary Works and Miscellaneous Debris from Previous Construction;
Unrecovered Equipment from Geotechnical Drilling Program; and
Foundations for Survey Towers.
5.2.4.1 Rock Containment Dikes and Scour Protection Rock containment dikes and scour protection constructed in the 1950s and 1970s were described
in Section 5.1.2.1. With respect to TBM tunneling, for baseline purposes, the Design‐ Builder
shall be prepared to encounter heavy rip rap and stone layers as follows:
At the North Island, between Stations 850+00 and 867+00, the Design‐Builder may
encounter armor stone the same as the size and limits detailed in Section 5.1.2.1;
At the South Island, between Stations 924+00 and 945+00, the Design‐Builder may
encounter armor stone the same as the size and limits detailed in Section 5.1.2.1;
Between the two islands, from Station 867+00 to 924+00, the Design‐Builder may
encounter armor stone with a maximum dimension up to 5 feet and weighing up to 10
tons anywhere within 10 feet below the mudline shown on Figure 4.1;
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 33 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Between the two islands, from Station 867+00 to 924+00, the Design‐Builder may
encounter scour protection, locking backfill, and other types of special fill materials within
the backfilled trenches of the existing tunnels, as shown on the record drawings
(Commonwealth of Virginia, 1956,1975). For baseline purposes, the backfilled trench
limits may vary up ±20 feet horizontally and ±5 feet vertically from the limits shown on
the record drawings; and
The thickness of the various stone layers is shown on the record drawings
(Commonwealth of Virginia, 1956, 1975) and for baseline purposes may be encountered
in local areas up to twice the layer dimension shown on the drawings.
The Design‐Builder’s means and methods, and bid price, for TBM tunneling shall account for
accommodating any rip rap or stone layers encountered within the limits outlined in the previous
four bulleted items. However, the Design‐Builder’s bid price may consider that heavy rip rap or
armor stone will not be encountered outside of these limits.
5.2.4.2 Temporary Works from Previous Construction Temporary works from previous construction in the 1950s and 1970s were described in Section
5.1.2.2.
The Design‐Builder’s means and methods and bid price for TBM tunneling shall account for
encountering any of the following temporary works:
Soldier pile and lagging or sheeting encountered up to 10 feet behind the face of the
current finished walls of the tunnel cut and cover approach structures, and up to 20 feet
below the base of the original excavation;
De‐tensioned tieback tendons may be encountered up to 65 feet behind the face of the
finished walls, and up to 20 feet below the full depth of the original excavation.
Steel dewatering well screens may be encountered to Elevation ‐140 feet and may be
present within 50 feet of the periphery of the current approach structures. The steel well
casings may or may not have been backfilled with grout or other material.
Miscellaneous debris from the previous construction may be present within the footprint
of the work. For example, a steel cable was encountered in a Shelby tube sample in Boring
17‐BH‐022‐OS at a depth between 15 and 20 feet below the mudline. For baseline
purposes, the Design‐Builder shall consider that miscellaneous construction debris may
be encountered within ±25 feet horizontally, and ±10 feet vertically from the limits of the
backfilled trench for the previous tunnels, as shown on the record drawings.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 34 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Timber, steel or concrete piles left‐in‐place from temporary piers may be present up to
50 feet from the perimeter of the islands (both 1950s and 1970s perimeters) and may
extend 10 feet below the top of the Yorktown Formation shown in Figure 4.1. For baseline
purposes, the Design‐Builder shall account for up to 4 such piles being encountered where
the tunnel alignment crosses the island perimeter (or former perimeter).
5.2.4.3 Unrecovered Equipment from Geotechnical Drilling Program During performance of the marine drilling program, equipment issues and failures led to pieces
of steel being left buried below the mudline at three test locations, as outlined below.
B‐018 After completion of the boring, a 40‐foot‐long section of 6‐inch casing
became de‐coupled during removal and was left in the borehole;
CPT‐034 After completion of the CPT probe, a 5‐foot‐long section of NQ casing became de‐coupled during removal and was left in the borehole; and
VST‐045 After completion of a vane shear test it was discovered that the connection
between the vane and the rods sheared off leaving the vane, a coupler,
and an extension rod in the borehole.
The surface coordinates and elevations of the buried equipment that could not be recovered is
detailed in Table 5.1 and shown in Figure 5.2. The coordinates should be considered to be
accurate within ±20 feet, and the elevation within ±30 feet.
Boring Northing Easting Elevation (ft NAVD88)
Description of Potential Obstruction
B‐018 36° 59’ 36.90773”N 76° 18’ 40.92049”W ‐76.2 to ‐116.2 6” Casing
CPT‐034 36° 59’ 30.56334”N 76° 18’ 40.06898”W ‐73.6 to ‐90.3 NQ Casing
VST‐045 36° 59’ 12.9209”N 76° 18’ 18.2663”W ‐81.7 to ‐83.7 Shear Vane
Table 5.1 ‐ Location of Unrecovered Equipment from Geotechnical Drilling Program
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 35 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Figure 5.2 ‐ Location of Unrecovered Equipment from Geotechnical Drilling Program
The Design‐Builder’s means and methods, and bid price, shall account for encountering these
potential obstructions and removing as necessary. If encountered with the TBM, these items
may create obstructions to inhibit TBM advance and or damage to the TBM and require special
effort to remove them such as through interventions.
5.2.4.4 Foundations for Survey Towers Horizontal and vertical control for the existing tunnels was established with the aid of survey
towers located in the Hampton Roads waterway. While the superstructure of the towers was
removed, the piles and other foundation elements were abandoned in place. The general
locations of the survey towers, which have since been removed, are indicated on the original
drawings (Commonwealth of Virginia, 1956, 1975). The Design‐Builder’s means and methods,
and bid price, shall account for encountering the piled foundations of these structures within ten
feet of the locations indicated on the original drawings, and removing as necessary. If
encountered with the TBM, these items may create obstructions to inhibit TBM advance and or
damage to the TBM and require special effort to remove them such as through interventions.
5.2.5 Sticky Clay Behavior The TBM tunnel drive will encounter cohesive layers within the Alluvial Marine Sediments (Qc,
Qf, Qo) and the Yorktown (Tyf, Tys) and Eastover (Tye) formations. The TBM design and
implementation of soil conditioning shall consider the potential for sticky clay behavior.
Selection of the specific materials, means, and methods for soil conditioning is the sole
responsibility of the Design‐Builder. The Design‐Builder must continuously monitor and adjust
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 36 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
the conditioning process to ensure these materials, means, and methods are appropriate for the
ground conditions being encountered at the face. This will require constant supervision and well‐
defined working plans and instructions for all construction personnel involved in TBM operations.
Accordingly, baselines for soil stickiness potential are not provided herein. The Design‐Builder is
solely responsible for determining how the soils, given the baseline soil properties as defined in
Tables 4.1 will respond to the means and methods selected and implemented by the Design‐
Builder. Sticky clay behavior will not be considered grounds for a Differing Tunnel Improvements
Site Condition for layers encountered with properties within the baseline values included in Table
4.1.
5.2.6 Cemented Sand and Shell Zones The Yorktown (Tyf, Tys) and Eastover (Tye) formations contain cemented layers and shell beds
that are classified as very dense or hard. The design and operation of the TBM should consider
the occurrence of these layers.
An upper bound unconfined compressive strength for the Yorktown (Tyf, Tys) and Eastover (Tye)
formations as indicated in Table 4.1 shall be a baseline for consideration of the potential
resistance that very dense granular, hard cohesive, or cemented sands or shells will present to
excavation equipment for the TBM tools and forward thrusting of the TBM.
5.2.7 Soil Abrasion Behavior The abrasion potential of the various soil strata that may be encountered by bored tunneling was
investigated by means of soil abrasion testing using a method based on Nilsen et al (2007). The
results of the testing are provided in the GDRs (Jacobs Engineering, 2018, ECS Mid‐Atlantic LLC,
2018).
Baseline values of soil abrasion for various soil strata (i.e., natural soil, without conditioners) are
presented in Table 5.2. The baselines were developed based upon the soil abrasion test results
included in the GDRs. As per Jakobsen et al. (2013), a soil with an SAT™ less than or equal to 7 is
classified as a “low” abrasive material, a soil with an SAT™ between 7 and 22 is classified as a
“medium” abrasive material and a soil with an SAT™ of greater than or equal to 22 is classified
as being a “high” abrasive material. These qualifiers notwithstanding, it is the numerical values
of the SAT™ that are baselined.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 37 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Stratum USCS Classification
Soil Abrasion Test Value
Baseline Range
Island Artificial Fill (af) SP, SM, SP‐SM 20‐40
Alluvial Marine Sediments – Coarse‐Grained (Qc)
SP, SM, SC 30‐55
Alluvial Marine Sediments – Fine‐Grained (Qf)
CL, CH N/A
Alluvial Marine Sediments – Organic/Fat Clay (Qo)
OL, OH, CH, PT N/A
Yorktown Formation – Coarse‐Grained (Tys) SM, SC 30‐40
Yorktown Formation – Fine‐Grained (Tyf) CL, CH 35‐50
Eastover Formation (Tye) SP, SM, SP‐SC 25‐35
Table 5.2 – Baseline Values for Soil Abrasivity
5.2.8 Gas Conditions Historic records indicating that the organic layers have previously been a source of methane gas
were described in Section 5.1.4.
The classification of the underground work associated with the bored tunnel option in
accordance with OSHA regulations (i.e., 29 CFR 1926.800 Subpart S) is provided in TR Section 23,
Bored Tunnel.
5.2.9 Soil pH Soil pH testing was conducted on samples from all strata that will be encountered in the
tunneling. For baseline purposes, the Design‐Builder shall consider the soil pH value will range
between a minimum of 7.0 and a maximum of 11.0.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 38 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
5.3 Island Expansions
Expansions of the existing North and South Islands may be required to provide portals for
horizontal tunnel alignments located to the west of the existing tunnels, and also to provide
sufficient cover for vertical alignments that would not allow the TBM to operate with existing
island grades.
5.3.1 Stratigraphy
Figure 4.1 shows the baseline stratigraphy below the islands based on the recent and historic
geotechnical information. For design and construction of the island expansions, the interfaces
between adjacent geological strata shown in the baseline profile are qualified by the statements
included in Section 5.1.1.
5.3.2 Obstructions
There are numerous potential obstructions that may affect the construction of the island
expansions and must be accounted for by the Design‐Builder both in the design and selection of
means and methods of construction. For design and construction of the island expansions the
potential impacts from obstructions shall be as presented in Section 5.1.2.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 39 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
6.0 Instrumentation and Monitoring
The Contractor shall be responsible for the design, installation, monitoring, and data
interpretation of the Instrumentation and Monitoring program in accordance with the Technical
Requirements.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 40 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
7.0 Limitations
The interpretations and assessments contained in this report are based upon the available
information from borings, in situ tests and laboratory tests. The geologic environment of the
Hampton Roads Bridge‐Tunnel Expansion project is complex, and as such, no amount of pre‐
construction information will convey as detailed an understanding as will exist during and
following excavation. The range of anticipated site and construction conditions presented in this
report is established as a baseline only to be used by all Bidders in preparing their bids, and by
the Department to evaluate claims relating to alleged Differing Tunnel Improvements Site
Conditions. The range of anticipated conditions was developed with the standard of care
commonly applied as the state of the practice in the profession. No warranty is included either
expressed or implied that the actual conditions encountered will conform exactly to the baseline
conditions described herein.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 41 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
8.0 References
1. AECOM, “Hampton Roads Crossing Archaeological Survey Hampton And Norfolk,
Virginia”, July 2017
2. Commonwealth of Virginia, Department of Highways, “Hampton Roads Project ‐ Record
Drawings”, 1956.
3. Commonwealth of Virginia, Department of Highways “Hampton Roads Project – Second
Bridge‐Tunnel Crossing Contract T‐1, South Island ‐ Record Drawings”, 1975.
4. Commonwealth of Virginia, Department of Highways “Hampton Roads Project – Second
Bridge‐Tunnel Crossing Contract T‐2, North Island, Tunnel and Completion of South
Island‐ Record Drawings”, 1975.
5. ECS Mid‐Atlantic LLC, “Preliminary Geotechnical Data Report – Hampton Roads Bridge
Tunnel – North and South Islands”, June 15, 2018.
6. Grantz W, “Immersed Tunnel Settlements Part 2: Case Histories”, Tunneling and
Underground Space Technology. Vol 16, 2001 pp203‐210
7. Hamilton P, and Larson J, “Hydrogeology and Analysis of the Ground‐water Flow System
in the Coastal Plain of Southeastern Virginia”, United States Geological Survey, Water
Resource Investigation Report 87‐4240, (1988).
8. Heuer, R.E., (1974), Important Ground Parameters in Soft Ground Tunneling: Proceedings
of Specialty Conference on Subsurface Exploration for Underground Excavation and
Heavy Construction, ASCE.
9. Kuesel T., Schmidt B., and Rafaeli D., “Settlements and Strengthening Of Soft Clay
Accelerated By Sand Drains” Highway Research Record number 457, Soil Slopes and
Embankments, 1973.
10. Jacobs Engineering, “I‐64 Hampton Roads Bridge‐Tunnel Expansion Project, Geotechnical
Data Report – Marine”, July 2018
11. Jakobsen, P. D., Bruland, A., and Dahl, F., “Review and Assessment of the NTNU/SINTEF
Soil Abrasion Test (SAT™) for Determination of Abrasiveness of Soil and Soft Ground”,
Tunneling and Underground Space Technology 37, 2013, pp107‐114.
12. Nilsen, B., Dahl, F., Holzhäuser J., Raleigh P., “New Test Methodology for Estimating the
Abrasiveness of Soils for TBM Tunneling”, Proceedings of RETC Conference, 2007, pp104‐
116.
13. Rafaeli, D., “Design of the South Island for the Second Hampton Roads Crossing”, Spec.
Conf. on Performance of Earth and Earth‐Supported Structures, Proc. ASCE, Purdue Univ.,
Vol. 1, Part 1, 1972, pp. 361‐378.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Page 42 Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
14. Steuerman S, and Murphy G, “Foundation of the Hampton Roads Tunnel”, Proceedings of
the Fourth International Conference on Soils Mechanics and Foundation Engineering,
1957.
15. Thewes, M., “Adhesion of Clays During Tunnelling with Slurry Shields”, Dissertation,
vol.21, Berichte aus Bodenmechanik und Grundbau der Bergischen University Wuppertal,
Department of Civil Engineering, 1999.
16. Thewes, M. and Burger, W., “Clogging of TBM Drives in Clay – Identification and Mitigation of Risks”, Proceedings ITA‐AITES World Tunnel Congress, Istanbul, Turkey, 2005, pp. 737‐742
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
APPENDIX A ‐ Boring Location Plan and Baseline Subsurface Profile
17BH-101N 17BH-102N
17BH-103N 17BH-104N17BH-105N
B-113B-8B-9
B-10
B-12
B-11
B-1417-BH-012-OS17-BH-011-OS
17-BH-013-OS
17-BH-014-OS
17-BH-015-OS
ASPHFL
FL
SP
SM
SC
SM
CH
SC
SM
SM
29 13 26 22 15 17 12 1 5 4 27 36 24 44 11 9 10 4 11 7 6 14 12 11 16 10 11 5 11 7 7 17 14 8 8
10 22 33 11 11 31 41 40 33 41 36 8 3 7 9 7
11 96 14 7 8
30 6 5 5
50/3 9
15 14
ASPHFL
FL
SM
SM
SC
SM
17 15 18 17 8 5 4 4 25 27 38 22 24 21 23 21 8 10 15 6 10 6 11 28 6 20 9 8 3 10 9 11 13 17 9
FLFL
FL
SM
SM
SC
SM
SM
SP-SC
10 10 15 7 6 4 18 7 30 21 16 19 11 19 9 10 16 3 6 9 11 12 13 5 5 12 9 12 7 7 23 8 15 11 11 47 30 10 13 32 35 75 41 26 39 31 9 5 8
27 7
50/2 7 7 8 8 8 6 4 9
14 11 16 9
FL
FLFLFLSC
SC
SM
34 12 10 12 26 15 27 28 18 3 24 25 19 18 9 7 5 11 7 17 9 12 22 7 7 16 5 12 5 16 5 6 10 11
FL
FL
FL
SP
SC
SM
CL
SM
SM
CL
15 8 9 8 12 9 12 9 9 6 8 33 7 13 7 5 9 5 11 5 8 16 7 27 13 7 13 5 11 4 6 12 8 18 6 8 14 56 40 8
17 29 32 38 36 23 40 8 9 6 5 8 8
50/4 11 8 9 7 7 4 6
50/5 14 10 13
18 12 18 19 28 46 24 30 20 22 21 15 13 18 16 25 25 51
5/12"
10/12"
13/12" 38/12"
50/12" 25/12"
14/12" 12/12"
17/12"
29/12"
20/12"
12/12"
12/12"
25/12"
25/12"
14/12" 128/12"
58/12"
38/12"
63/12"
46/12"
52/12"
83/12"
38/12"
62/12" 59/12" 46/12" 19/12" 6/12"
16/12"
7/12"
15/12"
7/12"
40/12"
35/12"
41/12"
48/12" 14/12"
38/12"
42/12"
20/12"
15/12" 18/12"
26/12"
14/12"
85/12" 82/12"
111/12"
30/12"
50/12"
35/12" 150/12"
135/12"
114/12"
93/12"
85/12"
21/12"
7/12" 11/12" 9/12" 10/12"
38/12" 11/12" 10/12" 11/12" 21/12" 16/12" 27/12" 11/12" 11/12" 11/12" 18/12" 22/12" 19/12" 59/12" 38/12" 36/12" 36/12" 64/12" 44/12" 83/12" 67/12" 47/12"
66/12" 15/12" 19/12"
13 11/12" 14/12"
3/12" 5/12" 3/12"
12/12" 20/12" 2/12" 38/12" 32/12"
15/12" 10/12" 10/12" 13/12" 15/12" 10/12" 10/12" 10/12" 12/12" 12/12" 13/12"
100/11" 54/12" 16/12" 34/12" 68/12" 37/12" 60/12" 37/12" 34/12" 28/12" 35/12" 11/12" 9/12"
12/12" 19/12" 21/12" 100/8" 10/12" 14/12" 15/12" 13/12" 28/12" 24/12" 12/12" 10/12" 28/12" 20/12" 100/3" 19/12" 29/12" 20/12" 13/12" 100/7" 17/12"
21/12" 22/12"
8/12" 18/12" 27/12" 10/12" 10/12" 19/12" 32/12" 32/12" 11/12" 11/12" 13/12" 31/12" 31/12" 32/12" 39/12" 40/12" 40/12" 24/12" 56/12" 36/12" 69/12" 66/12" 42/12" 42/12" 62/12" 46/12"
25/12" 12/12" 14/12" 17/12" 27/12" 21/12" 28/12" 16/12" 14/12" 21/12" 132/12" 85/12"
23/12" 36/12" 64/12" 84/12" 61/12" 80/12" 70/12" 58/12" 71/12"
60/12"
SM
CH
SC
SM
SC
SMSC
SM
CL
SMSMSMSMSMSC
SC/GCSC/CL
SM
SC
SM
SC
SMSC
WOH WOH WOH WOH WOH 2 WOH WOH WOH WOH 5
WOH
63 11
10 43 13 13 33 21
WOR 23 15 15 15 35 20 28 6
WOR WOR
50/5" WOH WOH
WOR 79
WOR
10 50/10"
22 8
4
SP
SMSM
CL/SCSM
CH
SM
SC
SM
SC
SMSP
SC
SM
SC
CH
SC-SM
SM
SC
SM
SC
CL
SC
WOR WOR WOR WOR WOR WOH WOH 9
25 12 12
WOH WOH
11 8
WOH 12
26 22 26 11 21 16 20 25 26 39 28 18
19 11
50/3
16 12
WOH WOR
9
9 WOR
11 10
SP-SM
SCSM
SC
SMSC
SM
CHCH
SC
SC-SM
SCSM
SC
SM
WOR WOR WOR 8 8 WOR WOR WOR WOR 11
16
9 4
8 11 9
11 14 9
26
10 14 16 19 15 23 27 23
WOR
WOR WOR WOR
5 WOR
WOR WOR WOH WOR WOR
10 6 3
19 37
50/1
ML
SM
SC
SP-SM
SM
CLSC
SC-SM
SC
21 18 10 2 8 3 7 13 15 5
13 8
12
15 15 15 49 43 8
13 18 27 23 33 34 22 30
WOR
9 8
WOR 21 9
6 7 5
9
7 12 5
50/6"
SM
SC
SM
CL
SC
CL
WOR WOR 8 5 5 25 13 45
8
6 15 10 48 52 12 25 23 24 21 29 28 32 11 5
WOH
50/6"
5 29 6 6 4 5 4
3 3 7
11 9
32
17BH-101N
17BH-102N
17BH-103N 17BH-104N 17BH-105N
B-8
B-9
B-10
B-11
B-12
B-13
B-14
17-BH-007-OS
B-113
17-BH-008-OS
17-BH-009-OS
17-BH-012-OS
17-BH-010-OS
17-BH-011-OS
17-BH-013-OS
17-BH-014-OS
17-BH-015-OS
PROFILEHOR. SCALE: 1"=100'VERT. SCALE: 1"=30'
PLANSCALE: 1"=100'
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-280-280852+00 854+00 856+00 858+00 860+00 862+00 864+00 866+00 868+00 870+00 872+00 874+00 876+00850+00
Tys
Qc
af
Tyf
Tye
17BH-101N B-113
928+00 930+00 932+00 934+00 936+00 938+00 940+00 942+00 944+00
Legend
Tye - Eastover Formation; Predominantly Coarse-grained(SC, SM, SP, SC-SM, SP-SC with minor lenses of CL)
Tyf - Yorktown Formation; Predominantly Fine-grained(CH, mainly fat clay with some lenses of CL, MH and SC)
Tys - Yorktown Formation; Predominantly Coarse-grained(SM, SP-SM, SP, SW, GP, SC, SW-SM, SC-SM)
Qc - Alluvial Marine Sediments; PredominantlyCoarse-grained (SP, SC, SM, SP-SM)
Qf - Alluvial Marine Sediments; PredominantlyFine-grained (CL, CH)
Qo - Alluvial Marine Sediments; Organic/Fat Clay(OL, OH, CH, PT)
af - Coarse-grained fill material (Fill)(SP, SM, SP-SM)
Water
3. This baseline profile is applicable for new tunnel alignments between the existing tunnels, and foralignments up to 500 feet to the west of the second tunnel alignment.
4. Qualifying statements related to interpretation of the subsurface profile for different elements ofthe proposed construction are presented in Sections 5.1.1, 5.2.1 and 5.3.1 of this report.
946+00 948+00
Notes:
1. This baseline profile was developed by projecting borings on to the alignment of the second bridge-tunnel built in the1970s. For clarity, the existing tunnel structure and associated backfill materials are not included in the profile. Referto project record drawings for limits of existing structures, and the associated backfill and scour protection materials.
2. For clarity, some CPT's are not shown and some have been moved slightly from their projected location.
B-111B-112B-15AB-15 B-15B B-16A B-17 B-18A B-19 B-2017-BH-016-OS17-BH-017-OS
17-BH-018-OS17-BH-019-OS 17-BH-020-OS
17-BH-021-OS
11 22 68 S
35 6
WOR
S WOR WOR
1 36 75 72 37
43 67 48
7 3 7
12 5
WOR
WOR
S WOR
WOR WOR
62 87 81 72 16 24 20 57
S 10/12" 9/12" 5/12"
10/12" 11/12" 17/12" 15/12" 17/12" 82/12"
150/12" 14/12" 27/12" 24/12" 26/12" 28/12" 42/12" 32/12" 41/12" 48/12"
25/12" 12/12" 14/12" 17/12" 27/12" 21/12" 28/12" 16/12" 14/12" 21/12" 132/12" 85/12"
23/12" 36/12" 64/12" 84/12" 61/12" 80/12" 70/12" 58/12" 71/12"
60/12"
WOP/12" 18/12" 5/12"
WOP/12" 6/12" 7/12"
52/12" 100/12" 22/12" 23/12" 30/12" 39/12" 70/12" 58/12" 29/12" 50/12" 19/12"
WOP/12" 7/12" 10/12" 6/12" 1/12"
20/12"
2/12"
2/12"
5/12" 16/12" 20/12" 13/12" 15/12" 58/12"
12/12" 8/12" 6/12" 8/12" 5/12" 2/12"
1/12"
2/12"
2/12"
40/12" 47/12" 31/12" 34/12" 61/12"
40/12" 36/12"
42/12" 14/12" 21/12" 20/12"
3/3" 1/12"
1/12"
2/12"
21/12" 38/12" 28/12" 33/12" 16/12" 18/12" 11/12"
S 9/12"
35/12" 38/12" 21/12" 1/12" WOP/6" WOP/12" WOP/12"
2/12"
3/12"
7/12"
17/12" 37/12" 20/12" 14/12" 18/12"
WOP/12" 6/12"
WOP/12" 8/12" S
S
10/12" 8/12"
11/12"
10/12" 23/12" 26/12" 26/12" 31/12" 21/12"
SP
CH
CH
CH
CH
SP-SM
SM
CL
SC-SM
SM
WOR 3 2 6 2 WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR
22 23 18 17 6
14 6
51 15 7 9
10 5
13 44 25
89/6
6 9
24 50/3"
SP-SM
CLSP-SMCL
CL
SC
SPSW
SMCH
SM
SC-SM
WOR 24 7 16 14 7 WOH WOR WOH
WOR WOR WOR WOR WOR
WOR
WOR WOH
22 32
WOR 61 27 35 49 29
WOR
5 7
85
7 8 5
WOR WOR
14 42 17 13
70/3"
CL
SMCH
CH
SP-SM
SP
SW
SC
SM
SC
CL
WOR WOR WOR WOR WOR WOH WOR
WOR WOR WOR WOR WOR WOR WOR WOR 13 WOR WOR WOR WOR 18 27
26 32 30
WOR WOR WOR
50/2"
7 50/5"
7 WOH
50/5"
WOR WOH WOR WOR WOR
10 WOR WOR
8
39
SP
SC
CL
CL
CLSCSM
SP-SM
CHSMSC-SM
SC
CL
WOR WOR WOR WOR WOR WOR 57 13 12 17 WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR
WOR 22 23 22 31
WOH 60/5"
50/5"
12 16 8
15 11
WOR WOR
7 12 14 8
17 18 31
9 21
SP
SC
SP-SM
SC-SM
SMSC
SM
SMCH
SC
SM
SC
CL
WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR 8 21 26
WOR 17
WOR 21 31 24 8
24 4
24 WOR WOR
48 20 86
WOR 13
WOR WOR WOR WOH
50/4" 15 11 11
WOH 14
WOR 21 27
SP
SC
CHSPCLSMSCSMCHSC
SWSMCHSCSMSC-SM
SC
SM
SC
WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR
12
4 2
34 30 28 36 6 7 4 6
50/6" 2
55 5 5
WOH 13
WOH 9
14 7
11 3
4
B-15 B-15A B-15B B-16A B-17 B-18A B-19B-20
B-111B-112
17-BH-020-OS
17-BH-016-OS
17-BH-017-OS
17-BH-018-OS
17-BH-019-OS 17-BH-021-OS
PROFILEHOR. SCALE: 1"=100'VERT. SCALE: 1"=30'
PLANSCALE: 1"=100'
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-280-280876+00 878+00 880+00 882+00 884+00 886+00 888+00 890+00 892+00 894+00 896+00 898+00 900+00 902+00
Qc
Qf
Qf
Tys
Tyf
Qo
Qc
Tye
928+00 930+00 932+00 934+00 936+00 938+00 940+00 942+00 944+00
Legend
Tye - Eastover Formation; Predominantly Coarse-grained(SC, SM, SP, SC-SM, SP-SC with minor lenses of CL)
Tyf - Yorktown Formation; Predominantly Fine-grained(CH, mainly fat clay with some lenses of CL, MH and SC)
Tys - Yorktown Formation; Predominantly Coarse-grained(SM, SP-SM, SP, SW, GP, SC, SW-SM, SC-SM)
Qc - Alluvial Marine Sediments; PredominantlyCoarse-grained (SP, SC, SM, SP-SM)
Qf - Alluvial Marine Sediments; PredominantlyFine-grained (CL, CH)
Qo - Alluvial Marine Sediments; Organic/Fat Clay(OL, OH, CH, PT)
af - Coarse-grained fill material (Fill)(SP, SM, SP-SM)
Water
3. This baseline profile is applicable for new tunnel alignments between the existing tunnels, and foralignments up to 500 feet to the west of the second tunnel alignment.
4. Qualifying statements related to interpretation of the subsurface profile for different elements ofthe proposed construction are presented in Sections 5.1.1, 5.2.1 and 5.3.1 of this report.
946+00 948+00
Notes:
1. This baseline profile was developed by projecting borings on to the alignment of the second bridge-tunnel built in the1970s. For clarity, the existing tunnel structure and associated backfill materials are not included in the profile. Referto project record drawings for limits of existing structures, and the associated backfill and scour protection materials.
2. For clarity, some CPT's are not shown and some have been moved slightly from their projected location.
B-110B-21 B-22 B-23 B-24 B-2517-BH-022-OS17-BH-023-OS
17-BH-024-OS17-BH-025-OS
17-BH-026-OS
17-BH-027-OS
0
WOR WOR
WOR 0
WOR
WOR
WOR
18 23 18 25 54 37 28 34
118 11 40
WOP/12" WOP/12" WOP/12"
S
S
7/12" 4/12"
5/12"
3/12" 16/12" 21/12"
21/12" 14/12" 13/12" 27/12" 38/12"
S S
S
1/12"
6/12" 20/12" 18/12" 8/12"
23/12" 20/12" 38/12" 27/12" 28/12" 37/12"
22/12"
S S
12/12" 18/12"
1/12"
29/12" 19/12" 24/12" 6/12"
5/12" 6/12"
12/12" 48/12"
127/12"
5/12"
13/12" 1/12" 1/12" 1/12"
1/12"
1/12"
1/12"
11/12" 4/12"
2/12"
2/12"
73/12" 9/12"
19/12" 6/12" 25/12" 46/12" 65/12" 76/12"
25/12" 38/12"
S
S
S
1/12"
1/12"
14/12"
8/12"
2/12"
22/12" 22/12" 39/12" 35/12" 91/12" 38/12" 60/12" 53/12" 65/12"
CL
CH
CH
SMCLSC
CL
SC-SM
SM
CH
SC
CL
CH
WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR 30 WOR
WOR WOR WOR WOR
26 18 9
19 6 3 3
WOR WOH
50/2"
WOR
WOR WOR
5 10 9 8 7 6
20
SMCL
CH
SM
CH
CHCHSCSPCH
SW
SM
CH
SC
SM
SM
SM
WOR WOR WOR WOR WOR WOR WOR WOR WOR 9 WOR WOR WOR WOR WOH WOR
WOR
WOR 20
WOR
23 6
12 16 32 24 19 6
10 2 3
86 9 3
24 WOR
WOR
50/5"
11 26
28
GW
SM
SW
CL
CH
SP
CH
SC
SW
CL
SM
CHCH
SC
SC-SM
SC
34 9 15 26 7 7 6 5 2 7 15 19 11 17
WOR WOR WOR WOR WOR 6 WOR WOR WOR WOR WOR WOR WOR WOH 26
WOR WOR WOR WOR WOR
10 20 15 11 16 12 11 15 30 33 30 9
WOR WOR
22 21 13 5
12 7
11
50/4
SMSPMLSP
GW-GMSP-SM
SC
CL
CH
OH
SC
CH
CLSP
SM
CL
SC
SM
SC
SM
16 18 21 14 12 12 17 17 25 92 10 20 30 10 12 WOH WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR
26 22 48
WOR
WOR WOR
WOR WOR
11 17 20
WOH 12 58 28 4
WOR WOR WOR
11 50/5" WOR
7 WOR WOR
15 WOR WOH
13 20
CL
OH
CL
SPSC
SM
SW-SM
CH
SC
WOR WOR WOR WOR WOR WOR WOR WOR WOH WOH WOR WOH WOR WOH WOH 6 WOH WOH WOR WOR WOR 16 29
WOR WOR WOR WOR
36 27 19 37 16 21 21
18 15 14
WOR WOR
47 50/3"
21 17 9
13
WOR 11
SP-SM
OH
SC
CH
SC
CLCHSPSWGP
SM
CLSCCLSC
SM
WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR 6 4 24 2 WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR
12 5
17 27 10 21 41 41 35 27
WOR WOR WOR
9
47 5
15 15 7 7
13 13
15
B-21 B-22 B-23 B-24B-25
B-110
17-BH-025-OS
17-BH-022-OS
17-BH-023-OS
17-BH-024-OS
17-BH-026-OS
PROFILEHOR. SCALE: 1"=100'VERT. SCALE: 1"=30'
PLANSCALE: 1"=100'
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-280-280902+00 904+00 906+00 908+00 910+00 912+00 914+00 916+00 918+00 920+00 922+00 924+00 926+00 928+00
QfQc
Qo
QfQc
Qf
Tys
Tye
Tyf
Qc
Qf
af
928+00 930+00 932+00 934+00 936+00 938+00 940+00 942+00 944+00
Legend
Tye - Eastover Formation; Predominantly Coarse-grained(SC, SM, SP, SC-SM, SP-SC with minor lenses of CL)
Tyf - Yorktown Formation; Predominantly Fine-grained(CH, mainly fat clay with some lenses of CL, MH and SC)
Tys - Yorktown Formation; Predominantly Coarse-grained(SM, SP-SM, SP, SW, GP, SC, SW-SM, SC-SM)
Qc - Alluvial Marine Sediments; PredominantlyCoarse-grained (SP, SC, SM, SP-SM)
Qf - Alluvial Marine Sediments; PredominantlyFine-grained (CL, CH)
Qo - Alluvial Marine Sediments; Organic/Fat Clay(OL, OH, CH, PT)
af - Coarse-grained fill material (Fill)(SP, SM, SP-SM)
Water
3. This baseline profile is applicable for new tunnel alignments between the existing tunnels, and foralignments up to 500 feet to the west of the second tunnel alignment.
4. Qualifying statements related to interpretation of the subsurface profile for different elements ofthe proposed construction are presented in Sections 5.1.1, 5.2.1 and 5.3.1 of this report.
946+00 948+00
Notes:
1. This baseline profile was developed by projecting borings on to the alignment of the second bridge-tunnel built in the1970s. For clarity, the existing tunnel structure and associated backfill materials are not included in the profile. Referto project record drawings for limits of existing structures, and the associated backfill and scour protection materials.
2. For clarity, some CPT's are not shown and some have been moved slightly from their projected location.
B-101B-102
B-103B-104B-105
B-10617BH-101S17BH-102S
17BH-104S 17BH-105S17BH-106S 17BH-108S17BH-110S
17BH-109S 17BH-112S17BH-113S
17BH-103S 17BH-107S 17BH-111SB-26 B-29B-30 B-31B-46 B-44B-45
WOH
WOH
WOH
WOH
WOH
4
5
5
7
25
33
34
65
49
WOR
11
10
WOR
5
3
3 3
1 2
3 5
WOR
5
53 23
48 31
20
31
13
22
3
7
10
2
2 2
4
WOH
6
5
WOH
31
16
43
61
123/3"
32
10
11
7
10
0
WOR
2
WOR
8
9 16
55
62
33
22
64
51
49
16
8
8
4
3
5
6
11
8
6
20
17
20
10
8
9
28
36
72
72
19
70
32
45
32
37
11
14
31
11
2
5
5
6
20
10
19
8
21
44
28
11
6
8
7
10
49
52
28
50
72
WOR
40 50
FL
FL
SP-SM
MLSMCLCH
OH
OHOH
SMOHPTSPSM
SM
MHCH
SM
SM
14 9 12 14 15 16 21 17 13 16 17 11 4 7 2 2 6 WOH 3 3 6 5 5 3 4 3 6 6 4 7 4 8 2 4 6 7 6 10 33 19 25 9
34 15 40 9 5
20 23 13 10 20 36 22 10 6 3 6 5
50/3'' 6
50/2'' 8 3 6
11 7 5
11 10
FLFLFL
SP
SMSPOHML
CHCHSMSM
7 14 13 9 5 16 11 17 24 17 10 14 15 17 8 7 13 10 9 6 11 12 12 12 5 5 4 5 5 8 7 6 6 6 11 30 13 23 14 16 50/3"
FLFLFLFLFL
FL
SCCHSECH
OH
CHCHSMSM
13 8 8 8 11 8 10 9 6 8 6 5 2 5 WOH 4 4 4 WOH 8 5 6 6 6 6 6 5 8 10 16 22 19 8 12 14
FL
FL
FLSMMLCLSMOLSM
SM
CH
SM
SM
SP
17 13 WOH WOH
2 WOH 2 4 4 12 8 3 3 2 3 9 6 8 9 18 8 7 12 6 13 7 7 8 13 8 9 6 7
11 7
20 16 12 9
16 11 11 19 33 29 24 9
12 5 4
50/1'' 11 12 6 5 8 8 6 8
11 20
FL
CL
CHCH
OH
MLSMSM
17 7 7 9 10 10 12 8 15 2 2 5 3 5 3 3 4 6 4 5 7 6 6 5 7 4 6 3 2 5 6 5 3 6 10 6 11 13 34 25 9 12 10 20 23 13 44
FL
FL
SCCLSMCHSC
SM
4
5 4 4 6 6 7 3 5 9
10 8 8 18 9 16 9 7 17 9 25 10
FL
CH
SC-SM
CL
OH
OHSMCLPTSM
SM
CHSC-SM
SM
SM
3 13 2 8 2 2 3 WOH
WOH 3 2 3
4 3 5 3 3 4 5 4 2 4 3 3 3 7 5 5 7 6 6 13 38 27
18 11 WOH 2 WOH 2 2 2 WOH 2 2 3 WOH 2 2 3 2 2 5 6 5 2 2 2 2 2 3 2 2 2 4 3 5 5
15 30 13 15 29 12 12 35 9 13 9
13 13 18 24 34 37 27 4 9
9 9 8
50/1'' 19 7 4
11 9 5
10 12 30
FL
FL
CHSM
CL
CL
SMSP-SM
FL
FLCHSMCLSM
OH
OH
SPSM
7 14 6 8 5 2 2 WOH 2 2 3 3 8 10 7 3 4 4 4 5 5 3 4 5 6 5 3 6 7 23 21 19 11
FLFL
FL
CL
SM
SM
SP-SM
SM
CHSC
SM
10 6 9 15 2 WOH 2 2 2 4 2 3 4 20 8 6 4 4 17 15 9 9 10 10 11 10 5 11 11 12 10 17 9 12
12 8
18 17 30 32 16 12 20 15 14 31 41 40 36 10 9 4 4
50/2'' 8 50/4''
FL
SP-S
M
CLOL
OH
OHOHSP
SM
CH
SM
SM
14 12 4 6 9 8 9 6 5 9 16 6 3 2 WOH 3 3 4 5 5 5 4 4 3 6 3 4 6 5 6 4 4 10 38 39 9 9
50/3'' 23 12 8
14 15 10 19 19 31 17 5
15 4 5
10 12 14 18 20 4 9 8 5 9 9
14
FLFL
FL
MHSP-SMCL
CL
SC
OH
SCSMSM
8 4 5 3 12 6 2 3 2 2 4 2 3 3 6 5 4 5 4 7 4 4 6 4 7 4 5 8 4 6 5 6 46 23 33 8
FL
CL
OH
SP
SM
CH
SM
SM
11 6 2 9 3 3 2 3 2 2 WOH
WOH 3 4 2 2 3 3 6 4 4 5 4 3 6 6 5 5 27 32 12 13 15
14 25 25 10 9
13 11 8
19 27 41 21 8 9
5 50/2''
7 50/4''
11 10 10 11 7 6 9
16 13
S 1/12" 1/12" 1/12"
1/12" 1/12" 1/12" 2/12" 2/12" 1/12" 1/12"
1/12"
27/12" 21/12" 36/12" 36/12" 32/12"
48/12" 37/12" 75/12" 39/12" 36/12" 35/12" 72/12" 63/12"
1/12" 3/12" 1/12" 1/12" 1/12" 1/12" 1/12" 1/12" 1/12" 3/12" 3/12" 3/12" 3/12"
66/12" 32/12"
44/12" 43/12" 17/12" 14/12"
102/12" 96/12" 82/12" 27/12" 43/12" 33/12" 30/12" 12/12" 14/12" 10/12" 16/12" 6/12" S 24/12"
150/12" S
14/12" 16/12"
S 10/12"
25/12" 22/12"
S 22/12" 16/12"
S
13/12"
S
S
S S
S 2/12"
2/12"
2/12"
13/12"
15/12"
25/12"
17/12"
36/12" 96/12" 66/12"
28/12"
51/12"
33/12"
34/12" 19/12"
93/12"
S
S
S
2/12"
5/12"
5 6 5/12"
10/12"
15/12"
16/12"
43/12" 39/12"
21/12"
43/12"
38/12"
36/12"
45/12"
51/12"
31/12"
51/12"
39/12"
38/12"
41/12"
48/12"
WOH/12"
WOH/12"
WOP/12"
2/12"
5/12"
S
1/12"
1/12"
7/12"
55/12"
20/12"
S
S
S
1/12"
1/12"
1/12"
2/12"
3/12"
5 11/12"
33/12"
30/12" 18/12"
29/12"
65/12"
4/12"
S
1/12"
1/12"
1/12"
2/12"
4/12"
3/12"
4/12"
4/12"
22/12"
18/12"
22/12"
SMCL
SC
SC
SC-SM
WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR WOR 14 18 10 13 17 10 22 57 11 24 12 26 11 19
18 15 16 14 12 11
WOH WOH WOR WOR
5 WOR WOR WOR
22
17-BH-032-OS
17BH-101S
17BH-102S
17BH-103S 17BH-104S
17BH-105S
17BH-106S
17BH-107S17BH-108S
17BH-109S 17BH-110S 17BH-111S 17BH-112S
17BH-113S
B-26
B-27
B-28
B-29
B-30
B-31
B-44B-101
B-102 B-103
B-104B-105
B-106
17BH-032-OS
PROFILEHOR. SCALE: 1"=100'VERT. SCALE: 1"=30'
PLANSCALE: 1"=100'
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-260
-240
-220
-200
-180
-160
-140
-120
-100
-80
-60
-40
-20
0
20
40
-280-280928+00 930+00 932+00 934+00 936+00 938+00 940+00 942+00 944+00
af
Qc
Qf
Qo
Qc
Tys
Tyf
Tye
Qf
Legend
Tye - Eastover Formation; Predominantly Coarse-grained(SC, SM, SP, SC-SM, SP-SC with minor lenses of CL)
Tyf - Yorktown Formation; Predominantly Fine-grained(CH, mainly fat clay with some lenses of CL, MH and SC)
Tys - Yorktown Formation; Predominantly Coarse-grained(SM, SP-SM, SP, SW, GP, SC, SW-SM, SC-SM)
Qc - Alluvial Marine Sediments; PredominantlyCoarse-grained (SP, SC, SM, SP-SM)
Qf - Alluvial Marine Sediments; PredominantlyFine-grained (CL, CH)
Qo - Alluvial Marine Sediments; Organic/Fat Clay(OL, OH, CH, PT)
af - Coarse-grained fill material (Fill)(SP, SM, SP-SM)
Water
3. This baseline profile is applicable for new tunnel alignments between the existing tunnels, and foralignments up to 500 feet to the west of the second tunnel alignment.
4. Qualifying statements related to interpretation of the subsurface profile for different elements ofthe proposed construction are presented in Sections 5.1.1, 5.2.1 and 5.3.1 of this report.
946+00 948+00
Notes:
1. This baseline profile was developed by projecting borings on to the alignment of the second bridge-tunnel built in the1970s. For clarity, the existing tunnel structure and associated backfill materials are not included in the profile. Referto project record drawings for limits of existing structures, and the associated backfill and scour protection materials.
2. For clarity, some CPT's are not shown and some have been moved slightly from their projected location.
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
APPENDIX B – Tunnelman’s Classification System
Final Geotechnical Baseline Report November 28, 2018
Hampton Roads Bridge‐Tunnel Expansion Commonwealth of Virginia Project No. 0064‐M06‐032 Virginia Department of Transportation
Tunnelman’s Classification System (After Heuer, 1974)
Classification Behavior Typical Soil Type
Firm
Heading can be advanced without initial support, and final lining can be constructed before ground starts to
Loess above water table; hard clay, marl, cemented sand and gravel when not highly overstressed.
Raveling
Slow Raveling
Chunks or flakes of material begin to drop out of the arch or walls sometime after the ground has been exposed, due to loosening or to overstress and “brittle” fracture (ground separates or breaks along distinct surfaces, opposed to squeezing ground). In fast raveling ground, the process starts within a few minutes, otherwise the ground is slow raveling
Residual soils or sand with small amounts of binder may be fast raveling below the water table, slow raveling above. Stiff fissured clays may be slow or fast raveling depending upon degree of overstress.
Fast Raveling
Squeezing
Ground squeezes or extrudes plastically into tunnel, without visible fracturing or loss of continuity, and without perceptible increase in water content. Ductile, plastic yield and flow due to overstress.
Ground with low frictional strength. Rate of squeeze depends on degree of overstress. Occurs at shallow to medium depth in clay of very soft to medium consistency. Stiff to hard clay under high cover may move in combination of raveling at execution surface and squeezing at depth behind surface.
Running
Cohesive Running
Granular materials without cohesion are unstable at a slope greater than their angle of repose. When exposed at steeper slopes they run like granulated sugar or dune sand until the slope flattens to the angle of repose.
Clean dry granular materials. Apparent cohesion in moist sand, or weak cementation in any granular soil may allow the material to stand for a brief period of raveling before it breaks down and runs. Such behavior is cohesive‐ raveling
Running
Flowing
A mixture of soil and water flows into the tunnel like a viscous fluid. The material can enter from the invert as well as the face, crown, and walls, and can flow for great distances,
Below the water table in silt, sand or gravel without enough clay content to give significant cohesion and plasticity. May also occur in sensitive clay when such material is disturbed.
Swelling
Ground absorbs water, increases in volume, and expands slowly into the tunnel.
Highly pre‐consolidated clay with plasticity index in excess of about 30, generally containing significant percentages of montmorillonite.