WHERE AM I? Project
System Project Management Plan
Version: SPMP Final Copy
Prepared by
Team #13
Efraim KORKMAZ – Selcuk DEMIRCI –
Ismet Serturk BASOGLU
January 7th, 2010
Where am I? PROJECT
Preface
In this report, the correct way to get team members has made plans. These reports and team
members, supervisor checks. This report covers a summary including purpose, summary,
objectives, constraints, schedule, budget summary. Moreover, this report contains managerial
process like estimation, staffing resource allocation, quality control and risk management plans.
Version History
Version Status* Date Responsible Version Definition
1 Released 21.10.2009 Ismet Serturk BASOGLU
SPMP 1.0
2 In Change 08.01.2010 Ismet Serturk BASOGLU
SPMP 1.1
*: Draft, In Review, Released, Approved, Rejected, In Change
Atılım University
COMPE/SE/ISE 491-492
2/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
List of Figures
Figure 1. ganchart........................................................................................................................... 37
List of Tables
Table 1. Project Deliverables……………………………………………………………………..9
Table 2. Internal structure……………………………………………………………………….12
Table 3. Project Responsibilities…………………………………………………………………12
Table 4. Product Function I/O Summary…………………………………………………………13
Table 5. Function Point Metrics………………………………………………………………….14
Table 6. Complex Adjustment Values…………………………………………………………..16
Table 7. Project work activity……………………………………………………………………19
Table 8. Resource allocation for Work Activity………………………………………………..20
Table 9. Resource Allocation for customer Meeting……………………………………………20
Table 10. Resource Allocation for preparing SPMP…………………………………………….21
Table 11. Resource Allocation for preparing SRS………………………………………………22
Table 12. Resource Allocation for preparing SDD……………………………………………..22
Table 13. Resource Allocation for preparing STD……………………………………………….23
Table 14. Resource Allocation for Coding………………………………………………………23
Table 15. Resource Allocation for preparing Testing…………………………………………..24
Table 16. Resource Allocation for preparing User Manual……………………………………….24
Table 17. Resource Allocation for Deployment…………………………………………………..24
Table 18. Schedule and Budget Allocation for Customer Meeting………………………………..25
Table 19. Schedule and Budget Allocation for Preparing SPMP…………………………………25
Table 20. Schedule and Budget Allocation for Preparing SRS……………………………………26
Table 21. Schedule and Budget Allocation for Preparing SDD………………………………..26
Table 22. Schedule and Budget Allocation for Preparing STD…………………………………27
Table 23. Quality Control Plan…………………………………………………………………..28
Table 24. Probability of Risks……………………………………………………………………29
Table 25. Ratio of Probability……………………………………………………………………..29
Table 26. Product Time Schedule…………………………………………………………………32
Atılım University
COMPE/SE/ISE 491-492
3/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Table of Contents
PREFACE..........................................................................................................................................................2
LIST OF FIGURES...........................................................................................................................................3
LIST OF TABLES.............................................................................................................................................3
TABLE OF CONTENTS..................................................................................................................................4
1. OVERVIEW..........................................................................................................................................6
1.1. Project Summary.................................................................................................................................61.1.1. Purpose, Scope, and Objectives..................................................................................................61.1.2. Assumptions and Constraints......................................................................................................61.1.3. Project Deliverables....................................................................................................................71.1.4. Schedule and Budget Summary...................................................................................................9
1.2. Evolution of the SPMP........................................................................................................................9
2. REFERENCE MATERIALS.............................................................................................................10
3. DEFINITIONS, ACRONYMS, AND ABBREVIATIONS..............................................................11
4. PROJECT ORGANIZATION...........................................................................................................12
4.1. External Interfaces.............................................................................................................................124.2. Internal Structure...............................................................................................................................124.3. Project Responsibilities.....................................................................................................................12
5. MANAGERIAL PROCESS PLANS.................................................................................................13
5.1. Start-up Plan......................................................................................................................................135.1.1. Estimation Plan.........................................................................................................................135.1.2. Resource Acquisition Plan........................................................................................................165.1.3. Project Staff Training Plan.......................................................................................................17
5.2. Work Plan..........................................................................................................................................175.2.1. Work Activities...........................................................................................................................175.2.2. Schedule Allocation...................................................................................................................205.2.3. Resource Allocation...................................................................................................................205.2.4. Budget Allocation......................................................................................................................24
5.3. Control Plan.......................................................................................................................................275.3.1. Requirements Control Plan.......................................................................................................275.3.2. Schedule Control Plan...............................................................................................................275.3.3. Quality Control Plan.................................................................................................................275.3.4. Reporting Plan..........................................................................................................................285.3.5. Metrics Collection Plan.............................................................................................................29
5.4. Risk Management Plan......................................................................................................................295.4.1. Description of Risks...................................................................................................................30
6. TECHNICAL PROCESS PLANS.....................................................................................................32
6.1. Process Model...................................................................................................................................326.2. Methods, Tools, and Techniques.......................................................................................................336.3. Infrastructure Plan.............................................................................................................................336.4. Product Acceptance Plan...................................................................................................................34
7. SUPPORTING PROCESS PLANS...................................................................................................35
7.1. Configuration Management Plan.......................................................................................................357.2. Quality Assurance Plan.....................................................................................................................357.3. Documentation Plan..........................................................................................................................367.4. Deployment Plan...............................................................................................................................367.5. Review Plan.......................................................................................................................................36
8. APPENDICES.....................................................................................................................................37
Atılım University
COMPE/SE/ISE 491-492
4/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
8.1. Appendix 1 – Ganchart......................................................................................................................37
Atılım University
COMPE/SE/ISE 491-492
5/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
1. Overview
1.1. Project Summary
1.1.1. Purpose, Scope, and Objectives
1.1.1.1 Purpose:
Our main purpose of our project is with the help of GPS is to determine our position, save
our location, coordinate, path throught and search any location on a digital map.
1.1.1.2 Scope:
The main goal and scope of our project is with the help of GPS is to mark and save where
we are, to save the way we go and search cities, countries, streets etc... with the enter name or
coordinate.
1.1.1.3 Objectives:
Our objectives are ;
When user want save something like location or path throught, user will press save
button and save this location or path throught from system database.
When user want delete or show saved objects like locations or path thoughts, user
will press delete or show button and delete or show these objects from system
database.
When user want to go somewhere and if user do not know this place, user will
press search button and enter locations’ name or coordinate and find this location
with the help of GPS program.
When user want where he or she is, they open GPS program in his or her mobile
phone and start send coordinateness’ from host. And computer Take these
coordinates from host, and show where he or she is with markers.
1.1.2. Assumptions and Constraints
1.1.2.1 Assumptions:
We assumed that the following points exist:
Be present at the computer with the GPS map to establish a connection, we will do
some operations like save path throught on a map.
Due to external factors, program will not work nicely.
Atılım University
COMPE/SE/ISE 491-492
6/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Due to system failures, some functions may not work properly.
Connection between GPS and Computer, may not work properly.
Maybe, Program will bought by few users.
Maybe, our project will not finish at the proper time.
1.1.2.2 Constraints:
Our project constraints are:
To avoid a more expensive product
Density of the other courses in the university
Lack of experience of the members of the project.
Be limited to the project calendar.
Not to find enough time.
Lack of adequate communication between team members.
1.1.3. Project Deliverables
Work Product Description Delivery Date
Problem Statement Define the problem (submitted) 30.09.2009
Initial Plan Define the technical and managerial processes (submitted)
01.10.2009
Reviewed Initial Plan Revised version(submitted) 01.10.2009
SPMP Document Software Project Management Plans is used to define the scope, purpose and objectives of the project, to specify roles and responsibilities of team members, the customer company if it exists. Many plans are considered in order to define the assumptions and constraints of the project. It defines which process model is chosen for the project life cycle. It is used to document agreed deliverables
21.10.2009
Atılım University
COMPE/SE/ISE 491-492
7/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
and their dates.
Reviewed SPMP Document Revised version 08.01.2010
SRS Document Software Requirements Specification is used to describe the behavior of the software of the system to be developed. It documents the functional and nonfunctional requirements of the system. It includes a set of use cases which describes the user-system interactions.
16.11.2009
Reviewed SRS Document Revised version 25.01.2010
SDD Document Software Design Description is
used for complete description of
design of the software of the
system to be developed. It
documents all the information
about the design.
It specifies the form of the
document used to specify system
architecture and application
design in a software related
project.
30.12.2009
Reviewed SDD Document Revised version 22.02.2010
Presentation At the end of first and second semester 2 presentations will be done which reflects the work we done during project development.
26-27-28.01.2010
STD Document Software Test Documentation 15.03.2010
Atılım University
COMPE/SE/ISE 491-492
8/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
is used to describe plans for testing the software. Any verification and validation activity
Reviewed STD Document Revised Version 07.06.2010
Presentation At the end of first and second semester 2 presentations will be done which reflects the work we done during project development.
15-16-17.06.2010
Final Versions of documents All documents are given with last versions
07.06.2010
Project Contest 18.06.2010
Table 1. Project Deliverables
There will be four major deliverables in the project which are SPMP, SRS, SDD, and STD.
All these documents will be prepared according to the IEEE standards.
These deliverables can be downloaded from our website. Each and every updates of those
deliverables will be announced from the website as well.
1.1.4. Schedule and Budget Summary
We estimate schedule allocation in section 5.2.4 combining with budget allocation.
1.2. Evolution of the SPMP
After this report, students and advisors with the new additions are possible.
Atılım University
COMPE/SE/ISE 491-492
9/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
2. Reference Materials
IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans
Pressman, Roger S., Software Engineering, 4th edition, McGraw-Hill, 1997
Fairley, R. E., Work breakdown Structure, Software Engineering Project Management, IEEE CS Press, 1997
Atılım University
COMPE/SE/ISE 491-492
10/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
3. Definitions, Acronyms, and Abbreviations
CMMI: Capability Maturity Model Integration
SPMP: Software Project Management Plan
SRS: Software Requirements Specification
JVM: Java Virtual Machine
V&V: Verification and Validation
XML: Extensible Markup Language
HW: Hardware
SW: Software
LOC: Line of Code
KLOC: Kilo Line of Code
IEEE: Institute of Electrical and Electronical Engineers
JRE: Java Runtime Environment
COCOMO: Constructive Cost Model
IDE: Integrated Development Environment
RAM: Read Only Memory
XML: Extensible Markup Language
SDD: Software Design Description
STD: Software Test Documentation
WBS: Work Breakdown Structure
PC: Personal Computer
Atılım University
COMPE/SE/ISE 491-492
11/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
4. Project Organization
4.1. External Interfaces
This project is a senior project. Therefore, project will controlled by supervisor and quality group
in each step. Supervisor will determine mistakes on project before implementation. After GPS team
correct mistakes, documents are delivered as a new version.
4.2. Internal Structure
Phases Responsible
Project Management Project Manager
Web Development Web Developer
Documentation Documentation
Testing & maintenance Tester
Table 2. Internal structure
4.3. Project Responsibilities
MEMBER NAME Responsibility E-Mail
Ismet Serturk BASOGLU Project Member, Web Developer [email protected]
Efraim KORKMAZ Web Developer, Documentation [email protected]
Selcuk DEMIRCI Tester, Documentation [email protected]
Table 3. Project Responsibilities
Atılım University
COMPE/SE/ISE 491-492
12/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
5. Managerial Process Plans
5.1. Start-up Plan
This section contains our project’s estimation plan, staffing plan, resource acquisition plan,
and training plan. In the following subsections, all these plans will exist with their explanations in
the details.
5.1.1. Estimation Plan
The beginning of a project, it is difficult to predict. This report is the first design of SPMP,
we can not expect an adequate data. Using the following function points, we will predict our
estimation plan.
Inputs Outputs Inquiries
Enter the GPS Program Save something like
maps, path throught Delete objects like
saved maps and path throught
Load objects like saved maps and path throught by press load button
Search something like cities, countries etc.. with enter location name or location coordinate
User will ask where I am
Error Message (if user Search Wrong place or Press Load if system will not have saved Objects.)
Load Objects Show by after Press Load Button
Searched cities, countries etc… shown by after Press Search Button
Shown where user is after user ask where I am
User will look, system has saved Objects for Delete or Load some objects
User will do Search User will as where I am
Table 4. Product Function I/O Summary
Number of inputs: 6
Number of outputs: 4
Number of inquiries: 3
Number of files: There exist no files.
Number of external interface: 6 (Microsoft Visual C# 2008 or C# or Microsoft Visual Basic 2008,
GPS Track Maker, OS, Printing)
Measurement Count ( C) Weighting Factor(W) W*C
Atılım University
COMPE/SE/ISE 491-492
13/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Parameter
Inputs 6 3 18
Outputs 4 4 16
Inquiries 3 3 9
Files 0 7 0
External Interfaces 6 5 30
TOTAL 73
Table 5. Function Point Metrics
Atılım University
COMPE/SE/ISE 491-492
14/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
# Influence Factors Weight
(Fi)
Comments
1 Does the system require reliable backup
and recovery? 5
There is no back-up facility
provided by the system
2 Are data communications required?
5
Online data collection for batch
process
3 Are there distributed processing
functions? 1
Data transfer on-line in one direction
4 Is performance critical?
4
Online response time is not critical
5 Will the system run in an existing,
heavily utilized operational
environment?
1
Not directly related but will run in
the same memory space with other
operational programs.
6 Does the system require on-line entry? 5 Transaction is online
7 Does the on-line data entry require the
input transaction to be built over
multiple screens or operations?
4
8 Are the master files updated on-line? 1 Master files updated online
9 Are the inputs, outputs, files or inquiries
complex? 2
Only security issues are complex,
others are middle
10 Is the internal processing complex?
5
Authentication mechanism and
flexibility make the system complex
11 Is the code designed to be reusable?
4
The code can be adopted to other
systems
12 Are conversion and installation included
in the design? 4
Only for mobile application
13 Is the system designed for multiple
installations in different organizations? 0
There is no need to installation in
different organization
14 Is the application designed to facilitate Design and interfaces make the
Atılım University
COMPE/SE/ISE 491-492
15/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
change and ease of use by the user? 4 system flexible
ΣFi 45
Table 6. Complex Adjustment Values
Function Point= Count-Total*[0.65+0.01*sum(Fi)]
Function Point= 73*[0.65+0.01* 45]
Function Point= 80, 30
COCOMO
LOC=FP*Language factor
We use Visual C# or C# or Visual Basic. These programs average Language factor is 58. When
we put it to the equation we get:
LOC=80.30*58=4657.40
KLOC=4657.40/1000=4, 6574
By using cocomo equations, we found the following results;
E=ab(KLOC)bb (Effort)
D=cb (E) d
b (Duration)
Our Project is semi-detached so we use 3,0 for ab ; 1,12 for bb ; 2,5 for cb and 0,35 for d
b So:
E=3,0*(4,6574)1,12 = 16,805 person-month
D=2,5*(16,805)0,35= 6.711 months
E/D ratio gives the recommended number of people. For Our Project it is:
E/D=16,805/6,711=2.504 ≈3 as our group consist of three people we fulfill necessary human
resources.
5.1.2. Resource Acquisition Plan
Our entire Project, we will use team members computers. The worst computer has
following hardwares:
P IV – 3.0 GHZ
1.5 GB RAM (min)
120 GB hard disk space
Ethernet card
Atılım University
COMPE/SE/ISE 491-492
16/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
512 MB Graffic Card
In addition to these HW requirements also the following SW requiremnets should be
satisfied:
Visual C#
Visual Basic
C#
GPS Track Maker
MS Office
MS Project
Internet Explorer
5.1.3. Project Staff Training Plan
GPS team members will learn that don’t know topics and develop them. They will
continuously search about this project. When they meet, they transfer knowledge from member to
another. The team members don’t have enough knowledge and experience in Visual C#, Visual
Basic, C# and GPS Track Maker. Thus, they will gain knowledge about these programs.
5.2. Work Plan
5.2.1. Work Activities
In the following table you can see the work activities of the Our Project:
1 CUSTOMER MEETING
1.1 Contact with customer
1.2 Problem Description
1.3 Requirements Gathering
2 PREPARING SPMP
2.1 Work Products & Activities Decomposition
2.2 Product Size Estimation
2.3 Process Model
2.4 Resource Allocation
2.5 Schedule Allocation
2.6 Risk Management Plan
Atılım University
COMPE/SE/ISE 491-492
17/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
2.7 Technical Process Plans
2.8 Supporting Process Plans
2.9 Documentation
2.10 Review of SPMP
2.11 Revised SPMP
2.12 Approval of SPMP
3 PREPARING SRS
3.1 Contact with Customer
3.2 Formal Identification of User Group
3.3 Product Functions
3.4 Behavioral Requirements Specification
3.5 Non-Behavioral Requirements Specification
3.6 Documentation
3.7 Review of SRS
3.8 Revised SRS
3.9 Approval of SRS
4 PREPARING SDD
4.1 SDD Basic Concepts
4.2 Database Design
4.3 Interface Design
4.4 Algorithms Design
4.5 Documentation
4.6 Review of SDD
4.7 Revised SDD
4.8 Approval of SDD
5 PREPARING STD
5.1 V&V Management
5.2 V&V Acquisition
Atılım University
COMPE/SE/ISE 491-492
18/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
5.3 V&V Supply
5.4 V&V Development
5.5 V&V Operation
5.6 V&V Maintenance
5.7 Documentation
5.8 Review of STD
5.9 Revised STD
5.10 Approval of STD
6 CODING
6.1 GPS Track Maker Management
6.1.1 GPS Track Maker Parsing
6.1.2 GPS Track Maker Creation
6.2 CODE REVIEW
6.2.1 Authorization
6.2.2 User interface design
6.2.3 Report Preparation
7 TESTING
7.1 GPS Test
7.2 Location Test
7.3 System Test
8 USER MANUAL
8.1 GPS User Manual
8.2 Track Maker User Manual
9 DEPLOYMENT
9.1 Approval of the product
Table 7. Project work activity
Atılım University
COMPE/SE/ISE 491-492
19/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
5.2.2. Schedule Allocation
We estimate schedule allocation in section 5.2.4 combining with budget allocation.
5.2.3. Resource Allocation
Tables related to resource allocation are stated below:
WORK ACTIVITY
REQUIRED SKILL BASED ON
Customer Meeting Human RelationsFace to face, E-
Preparing SPMPKnowledge of IEEE Std and Estimation Techniques, Planning
And CoordinationIEEE Std. 1058-
1998
Preparing SRS SW EngineeringIEEE Std. 830-
1998
Preparing SDD SW EngineeringIEEE Std. 1058-
1998
Preparing STD SW EngineeringIEEE Std. 1016-
1998
Coding Knowledge of Java and GPS Track Maker IEEE Standards
Testing Knowledge Of Control Engineering and Testing Techniques IEEE Standards
User Manual Knowledge of User Manual StandardIEEE Std. 1063-
1987
Deployment Knowledge of Review Techniques IS 502 Standards
Table 8. Resource allocation for Work Activity
CUSTOMER MEETING
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES HW RESOURCES
1.1 Contact with customer - Team -
1.2 Problem Description Ms Office,
Java
Team PC and peripherals
1.3 Requirements Gathering Ms Office,
Java
Team PC and peripherals
Table 9. Resource Allocation for customer Meeting
Atılım University
COMPE/SE/ISE 491-492
20/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
PREPARING SPMP
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES
HW RESOURCES
2.1 Work Products & Activities Decomposition
MS Office, MS Project
Team PC and Peripherals
2.2 Product Size Estimation MS Office Team PC and Peripherals
2.3 Process Model MS Office Team PC and Peripherals
2.4 Resource Allocation MS Office Team PC and Peripherals
2.5 Schedule Allocation MS Office Team PC and Peripherals
2.6 Risk Management Plan MS Office Team PC and Peripherals
2.7 Technical Process Plans MS Office Team PC and Peripherals
2.8 Supporting Process Plans MS Office Team PC and Peripherals
2.9 Documentation MS Office Team PC and Peripherals
2.10 Review of SPMP - Supervisor and Customer
-
2.11 Revised SPMP MS Office Team PC and Peripherals
2.12 Approval of SPMP - - -
Table 10. Resource Allocation for preparing SPMP
PREPARING SRS
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES
HW RESOURCES
3.1 Contact with Customer - Team -
3.2 Formal Identification of User Group
Ms Office Team PC & Peripherals
3.3 Product Functions Ms Office Team PC & Peripherals
Atılım University
COMPE/SE/ISE 491-492
21/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
3.4 Behavioral Requirements Specification
Ms Office, Visual C#
Team PC & Peripherals
3.5 Non-Behavioral Requirements Specification
Ms Office Team PC & Peripherals
3.6 Documentation Ms Office, Visual C#
Team PC & Peripherals
3.7 Review of SRS - Supervisor and Customer
PC & Peripherals
3.8 Revised SRS Ms Office, Visual C#
Team PC & Peripherals
3.9 Approval of SRS - - PC & Peripherals
Table 11. Resource Allocation for preparing SRS
PREPARING SDD
WBS WORK PACKAGES
SW TOOLS HUMAN RESOURCES
HW RESOURCES
4.1 SDD Basic Concepts MS Office TeamPC and Peripherals
4.2 Database Design MS Office TeamPC and Peripherals
4.3 Interface Design MS Office TeamPC and Peripherals
4.4 Algorithms Design MS Office TeamPC and Peripherals
4.5. Documentation MS Office, Visual C#
TeamPC and Peripherals
4.6 Review of SDD - --
4.7Revised SDD
MS Office, Visual C#
TeamPC and Peripherals
4.8 Approval of SDD - - -
Table 12. Resource Allocation for preparing SDD
Atılım University
COMPE/SE/ISE 491-492
22/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
PREPARING STD
WBS WORK PACKAGES
SW TOOLS HUMAN RESOURCES
HW RESOURCES
5.1 V&V Management MS Office Team PC &Peripherals
5.2V&V Acquisition
MS Office, Visual C#
Team PC &Peripherals
5.3 V&V Supply MS Office Team PC &Peripherals
5.4 V&V Development MS Office Team PC &Peripherals
5.5 V&V Operation MS Office Team PC &Peripherals
5.6 V&V Maintenance MS Office Team PC &Peripherals
5.7 Documentation MS Office Team PC &Peripherals
5.8 Review of STD - - PC &Peripherals
5.9 Revised STD MS Office Team PC &Peripherals
5.10 Approval of STD - - PC &Peripherals
Table 13. Resource Allocation for preparing STD
CODING
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES
HW RESOURCES
6.1 GPS Track Maker Management
MS Office, GPS Track Maker Management
Team PC &Peripherals
6.1.1 GPS Track Maker Parsing
GPS Track Maker Team PC &Peripherals
6.1.2 GPS Track Maker Creation
GPS Track Maker Team PC &Peripherals
6.2 CODE REVIEW Team PC &Peripherals
6.2.1 Authorization Visual C# Team PC &Peripherals
6.2.2 User interface design Visual C# Team PC &Peripherals
6.2.3 Report Preparation MS Office Team PC &Peripherals
Table 14. Resource Allocation for Coding
Atılım University
COMPE/SE/ISE 491-492
23/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
TESTING
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES HW RESOURCES
7.1 GPS Test GPS Track Maker Team PC &Peripherals
7.2 Location Test GPS Track Maker Team PC &Peripherals
7.3 System Test GPS Track Maker Team PC &Peripherals
Table 15. Resource Allocation for preparing Testing
USER MANUAL
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES HW RESOURCES
8.1 GPS User Manual MS Office Team PC &Peripherals
8.2 Track Maker User Manual
MS Office Team PC &Peripherals
Table 16. Resource Allocation for preparing User Manual
DEPLOYMENT
WBS WORK PACKAGES SW TOOLS HUMAN RESOURCES HW RESOURCES
9.1Approval of the product
- Team PC &Peripherals
Table 17. Resource Allocation for Deployment
5.2.4. Budget Allocation
Work activities are stated in the section 5.2.1 and taken as a base of budget allocation. We
determined the salary of each team member as 15 YTL/hour and assumed that supervisor has 20
YTL/hour salary. Budget and schedule allocation tables for each work activity are shown below:
Customer Meeting
WBS Work Packages Start Date
(D.M.Y)
End Date
(D.M.Y)
Work Hour
People Assigned
Cost
(YTL)
1.1 Contact with customer
16.10.2009 16.10.2009 1 Team 45
1.2 Problem 16.10.2009 16.10.2009 2 Team 90
Atılım University
COMPE/SE/ISE 491-492
24/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Description
1.3 Requirements Gathering
16.10.2009 16.10.2009 2 Team 90
Table 18. Schedule and Budget Allocation for Customer Meeting
Preparing SPMP
WBS Work Packages Start Date
(D.M.Y)
End Date
(D.M.Y)
Work Hour
People Assigned
Cost
(YTL)
2.1 Work Products & Activities
Decomposition
17.10.2009 18.10.2009 5 Team 225
2.2 Product Size Estimation
18.10.2009 18.10.2009 5 Team 225
2.3 Process Model 19.10.2009 19.10.2009 4 Team 180
2.4 Resource Allocation
19.10.2009 19.10.2009 2 Team 90
2.5 Schedule Allocation
20.10.2009 20.10.2009 2 Team 90
2.6 Risk Management Plan
20.10.2009 20.10.2009 3 Team 135
2.7 Technical Process Plans
20.10.2009 20.10.2009 3 Team 135
2.8 Supporting Process Plans
20.10.2009 20.10.2009 2 Team 90
2.9 Documentation 21.10.2009 21.10.2009 10 Team 450
2.10 Review of SPMP 06.01.2010 08.01.2010 1 Supervisor 20
2.11 Revised SPMP 06.01.2010 08.01.2010 6 Team 270
2.12 Approval of SPMP
06.01.2010 08.01.2010 - - 0
Table 19. Schedule and Budget Allocation for Preparing SPMP
Preparing SRS
WBS Work Packages Start Date
(D.M.Y)
End Date
(D.M.Y)
Work Hour
People Assigned
Cost
(YTL)
3.1 Contact with Customer
10.11.2009 10.11.2009 1 Team 45
3.2 Formal 10.11.2009 10.11.2009 2 Team 90
Atılım University
COMPE/SE/ISE 491-492
25/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Identification of User Group
3.3 Product Functions 11.11.2009 12.11.2009 10 Team 450
3.4 Behavioral Requirements Specification
13.11.2009 14.11.2009 5 Team 225
3.5 Non-Behavioral Requirements Specification
15.11.2009 16.11.2009 3 Team 135
3.6 Documentation 17.11.2009 18.11.2009 6 Team 270
3.7 Review of SRS 25.01.2010 25.01.2010 1 Supervisor 20
3.8 Revised SRS 25.01.2010 25.01.2010 6 Team 270
3.9 Approval of SRS 25.01.2010 25.01.2010 - - 0
Table 20. Schedule and Budget Allocation for Preparing SRS
Preparing SDD
WBS Work Packages Start Date
(D.M.Y)
End Date
(D.M.Y)
Work Hour
People Assigned
Cost
(YTL)
4.1 SDD Basic Concepts
10.12.2009 10.12.2009 4 Team 180
4.2 Database Design 11.12.2009 12.12.2009 5 Team 225
4.3 Interface Design 13.12.2009 13.12.2009 10 Team 450
4.4 Algorithms Design
14.12.2009 15.12.2009 12 Team 540
4.5 Documentation 30.12.2009 30.12.2009 8 Team 360
4.6 Review of SDD 22.02.2010 22.02.2010 1 Supervisor 20
4.7 Revised SDD 22.02.2010 22.02.2010 8 Team 360
4.8 Approval of SDD 22.02.2010 22.02.2010 - - 0
Table 21. Schedule and Budget Allocation for Preparing SDD
Preparing STD
WBS Work Packages Start Date
(D.M.Y)
End Date
(D.M.Y)
Work Hour
People Assigned
Cost
(YTL)
Atılım University
COMPE/SE/ISE 491-492
26/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
5.1 V&V Management 09.03.2010 09.03.2010 4 Team 180
5.2 V&V Acquisition 09.03.2010 09.03.2010 3 Team 135
5.3 V&V Supply 10.03.2010 10.03.2010 3 Team 135
5.4 V&V Development 11.03.2010 11.03.2010 4 Team 180
5.5 V&V Operation 12.03.2010 12.03.2010 3 Team 135
5.6 V&V Maintenance 13.03.2010 13.03.2010 3 Team 135
5.7 Documentation 15.03.2010 15.03.2010 8 Team 360
5.8 Review of STD 24.03.2010 24.03.2010 1 Supervisor 20
5.9 Revised STD 24.06.2010 24.03.2010 8 Team 360
5.10 Approval of STD 24.06.2010 24.03.2010 - - 0
Table 22. Schedule and Budget Allocation for Preparing STD
5.3. Control Plan
5.3.1. Requirements Control Plan
Changes are to be made in the requirements, after the completion of the SPMP step. Team
members have a meeting for revision. Document will be examined for the major/minor revision.
Resource allocation, Schedule allocation and estimation plan will be reconsidered and updated.
Budget is not important due to this project is a senior Project. Document will be updated as a new
version of all projects.
5.3.2. Schedule Control Plan
The Project consists of certain time interval. Project group members constantly
conversation in messanger, meeting one or two days in a week, and they effort to finish the Project.
The results of the meeting between team members will be discussed with supervisor and keep on
regular basis.
5.3.3. Quality Control Plan
Supervisor, who is Atilla BOSTAN, will control all working (documents, coding, demo, etc.)
by GPS Team. If supervisor is not give approval to the working , GPS team will not do next step.
Work Products and Items
Suitable to
Standards
Needs Revisons Explation
Atılım University
COMPE/SE/ISE 491-492
27/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Software Requirements Specification (SRS)
X Major revisions
SRS Review X
SRS Approval X Revisions are made and plan is approved.
Software Design Description (SDD)
X Major revisions
SDD Review X
SDD Approval X Revisions are made and plan is approved.
Software Test Documentation (STD)
X X Major revisions
STD Review X
STD Approval X Revisions are made and plan is approved.
Project Plan
Project Plan Review
Approval of Project Plan
Design
Design Review
Design Approval
Coding
Test
Implementation
Product Review
Product Approval
Table 23. Quality Control Plan
5.3.4. Reporting Plan
Each of versions of all the documents and updates and status reports will be sent and
discussed with the supervisor and upon approval the approved document will be circulated to the
Atılım University
COMPE/SE/ISE 491-492
28/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
other members of the committee. The report on the status of the project will be sent to the members
and interview about mistakes or lacks of reports.
5.3.5. Metrics Collection Plan
In our project, each of metrics are saved system database. If we will encounter any problem, we
will use these saved metrics with connect system database.
5.4. Risk Management Plan
RISKS PROBABILITY IMPACT
1(low) – 5(high)
REFERENCES
Quality of product documentation and coding are not suitable
%35 3 5.4.1.1
Disagree between team members
%8 2 5.4.1.2
Unavailability of team members
%8 2 5.4.1.3
Timing Problem %15 4
Health problem %35 1
Mistake in coding %15 4
System may be not work
%15 4
Table 24. Probability of Risks
Probability Uncertainty Statement
> % 80 Almost certainly
%80 - %61 Probable, probably
%60 – %41 Doubtable
%40 – %21 Unlikely
< % 20 Highly unlikely
Atılım University
COMPE/SE/ISE 491-492
29/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Table 25. Ratio of Probability
5.4.1. Description of Risks
5.4.1.1. Quality of product documentation and coding are not suitable
GPS team prepares the project planning, software documentation and coding with less
experience. Thus, The GPS Team must, try to prepare every documents of project in high
priority and control all steps of documentation.
5.4.1.2. Disagree Between Team Members
The GPS Team must behave respectfully and be careful not disagree with each other. If
The GPS Team has this problem, they must solve the problem between team members in early time
and prevention disagreement things before the conflict.
5.4.1.3. Unavailability of Team Members
The GPS Team must use all common free time to work on project. Before The GPS Team
start does project, they have to adjust date before starting the project. If The GPS Team has a
problem about meeting, Team must use all communication (telephone, msn, e-mail …) , and may
be prevent problem of time.
5.4.1.4. Timing Problem
The GPS Team must split the project and prepare the working program in weekly and
check each team members program every week and control how project is run.
5.4.1.5. Health Problem
The GPS Team must take care of their health. If team have health problem, they must do
work overtime or adjust new part-time labors and work another team member to instead of ill team
member.
5.4.1.6. Mistake in Coding
If The GPS Team does not want any mistake in coding, Team must do control the coding
and test every week or control and test small part and back up codes every week.
5.4.1.7. System may be not Work
The GPS Team must do not notice the mistake in design or coding. If Team does not want
any problem, they must do control the design again and again and contact with instructor when
coding and designing.
Atılım University
COMPE/SE/ISE 491-492
30/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
Atılım University
COMPE/SE/ISE 491-492
31/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
6. Technical Process Plans
6.1. Process Model
We in our project, we used Waterfall Process Model. The initialization of the
project will start in October 2009, at the end of January 2010; a prototype of the project
will be developed. And finally at the end of June 2010, our project will be finished. The
schedule plan for the project table will be given in the following table, table 24.
Activity Start Date End DateTime
(date/man)
Defining PS Oct. 16, 2009 Oct. 20, 2009 4
Initial Planning Oct. 17, 2009 Oct. 20, 2009 21
Reviewing IP Oct. 22, 2009 Oct. 23, 2009 6
SPMP Documenting Oct. 07, 2009 Oct. 21, 2009 44
Reviewing SPMP Nov. 10, 2009 Jan. 08, 2009 6
SRS Documenting Nov. 10, 2009 Nov. 18, 2009 42
SDD Documenting Dec. 01, 2009 Dec.30, 2009 44
Coding and Testing Jan. 01, 2010 June 10, 2010 100
Total Elapsed Time Oct. 16, 2009 June 19, 2010 267 date/man
Table 26. Product Time Schedule
Atılım University
COMPE/SE/ISE 491-492
32/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
TASK DUE TO REVİEW DATE DELIVERED MAJOR Milestone
SPMP Oct.21, 2009 Jan.8, 2010 YES YES
SRS Nov.18, 2009 Jan.26-27-28, 2010 YES YES
SDD Jan.4, 2009 April 5, 2010 YES YES
STD Mar.15, 2010 June 07, 2010 YES YES
Coding & Testing NO YES
User Manual NO YES
Final Product June 07, 2010 NO YES
6.2. Methods, Tools, and Techniques
Tools and techniques used to realize these working and to develop final product are shown
below:
SW TOOLS: Java, MS Office, MS Project, GPS Track Maker 13.5.409, Internet Explorer,
HW TOOLS: PC and Peripherals
PERSONAL SKILLS: Communication skills, XML, Java, SW Engineering Processes, Review
and Testing Techniques, User Manual, Planning and Coordination.
6.3. Infrastructure Plan
This software, internet connection, hardware and operating system are available
from other sources and from the internet is provided by team members..Projects that help
us the GPS Track Maker and JAVA programs can be downloaded from the internet and
available free. Each team member has one PC with the operating system of Windows XP
and Vista. We also use GPS track maker program for transfer data from GPS to computer
and computer to GPS also we are make ourselves develop. Group members identify
themselves as areas of project work as a group and as individuals we project focuses.
These places may be one team member’s house, library, and school’s studying room.
Atılım University
COMPE/SE/ISE 491-492
33/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
6.4. Product Acceptance Plan
Customer wants a review process will be reviewed and problems will be solved. By
the consultant and the client is missing a delivery point is checked to determine. Then
cover the missing points, a new version is created and delivered to the customer is
presented. This process shall continue until the customer and supervisor satisfaction is
achieved. In this way, the customer really needs to improve the basic product warranties
may be the result. If there are problems to be solved, and the product will deliver the
necessary points will change.
Atılım University
COMPE/SE/ISE 491-492
34/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
7. Supporting Process Plans
7.1. Configuration Management Plan
This part is very important for future changes for our project. When our project supervisor
or customers comes a request for project change, we will quickly review our previous report and
we will change our report like desired format. As the regeneration of the report, the report names
will also change. Such as;
First Deliverable:
Deliverable Name V1.0, like SPMP V1.0
Major Change for Deliverable:
Deliverable Name V2.0, like SPMP V2.0
Minor Change for Deliverable:
Deliverable Name V1.1, like SPMP V1.1
7.2. Quality Assurance Plan
Quality Assurance Plan:
All project reports must be made according to the IEEE a standard format
and should be submitted according to this format. Customer meetings are very important, that’s
why these meetings should be well organized. Project members must follow project Schedule very
carefully and projects should be delivered in a time.
Verification and Validation Plan:
Verification Plan
The process of determining to make the right product.
Made full order to produce for needs of customers.
All project’s delivered time and every steps made according to
accuracy of the SW.
Validation Plan
Products are made to ensure that the correct process.
About producing the right product.
Made full order to produce for needs of customers.
Atılım University
COMPE/SE/ISE 491-492
35/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
7.3. Documentation Plan
All documents will be made according to IEEE standards. For these IEEE templates
considers for SPMP, SRS, SDD, and STD. Each deliverable document will be reviewed by the
supervisor.
7.4. Deployment Plan
After our project is finish, our project resembles a desktop application. Thus, every people use
our project. But, if people use GPS program, their computers or laptops must take signals from
satellite.
7.5. Review Plan
After each phase of Project which are SPMP, SRS, SDD, STD are completed, are reviewed.
There are two types of review.
First review is done by GPS team after the completion of deliverable.
Second review is done by supervisor. Supervisor controls verification of the deliverable and to
cover requirements of the product.
Atılım University
COMPE/SE/ISE 491-492
36/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy
Where am I? PROJECT
8. Appendices
8.1. Appendix 1 – Ganchart
Atılım University
COMPE/SE/ISE 491-492
37/37
Team # 13 (Team Lost)
System Project Management Plan
Version: Final Copy