Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
27 Eighth Street, AdamstownW/ (02) 40231266 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
En00
10/07/2018
917-6187
Unit Development
Engineering Drawing Index
Sheet Number Rev Sheet Name
En11 H Ground Floor Bracing Plan (Units 2 & 3)
En12 H First Floor Bracing Plan (Unit 1)
En13 H First Floor Bracing Plan (Units 2 & 3)
En14 H Waffle Pod Slab Details (Class M)
En15 H Bracing Details
En16 H Landscape Block Retaining Walls
En17 H Connection Details
En18 H Partiwall Detail
En19 H Typical Construction Details 3D
En20 H Typical Construction Sections
En21 H Typical Window Details
Engineering Drawing Index
Sheet Number Rev Sheet Name
En00 H Cover Sheet
En01 H Notes 1
En02 H Notes 2
En03 H Slab Plan (Unit 1)
En04 H Slab Plan (Units 2 & 3)
En05 H Retaining Wall Plan
En06 H First Floor Joist Layout (Unit 1)
En07 H First Floor Joist Layout (Units 2 & 3)
En08 H First Floor Roof Plan (Unit 1)
En09 H First Floor Roof Plan (Unit 2 & 3)
En10 H Ground Floor Bracing Plan (Unit 1)
Revision Schedule
Rev Date Description
H 08/03/19 Final Engineering
G 27/02/19 Council Changes
F 20/11/18 Council Changes
E 22/10/18 Council Changes
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 40231266 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A31 : 20
En01
10/07/2018
917-6187
Revision Schedule
Rev Date Description
H 08/03/19 Final Engineering
G 27/02/19 Council Changes
F 20/11/18 Council Changes
E 22/10/18 Council Changes
Earthworks:1. The earthworks shall be carried out in accordance with the
geotechnical report and engineering specifications.2. The site shall be stripped a minimum depth of 150mm under pavements
and buildings to remove the top soil. Any remaining uncontrolled fill matter, organic material, refuse or roots shall be removed.
3. If a vibrating type roller is used, consideration shall be given to the effects on adjacent properties.
4. All filling shall be under the supervision of the project geotechnical engineer who shall provide compaction certificates to the engineer for approval.
Formwork:1. All workmanship and materials shall be in accordance with AS3610 &
AS3600, except where varied by the project documentation.2. The design certification and the performance of the formwork shall be
the responsibility of the contractor.3. During construction support propping shall be required where there are
loads from stacked materials, formwork and other supported slabs. Once the concrete has achieved its nominated 28 days strength, the imposed loads shall not exceed those given in the loading table.
4. With multistory construction, it is expected that support propping will extend a minimum of 3 levels below the slab being poured. Prop removal is to be programmed so as not to overstress previously cast floors and shall be submitted tot he engineer for approval.
5. The suspended slabs shall be propped until the 28 days strength has been achieved for the slabs. the formwork may be removed once 20 MPa strength has been achieved, however the slab will need to be back propped until 28 days strength has been achieved. No masonry or partition walls are to be constructed on suspended levels until all propping is removed.
6. All exposed corners shall have a 20mm chamfer UNO.7. All finished shall be in accordance with the architectural specification.
Foundation Maintenance :1. All soils are affected by water. Silts are weakened by water and some
sands can settle if heavily watered, but most problems arise on clay foundations. Clays swell and shrink due to changes in moisture content and the potential amount of the movement is implied in the site classification in Australian Standard AS2870, which is specified as follows:
2. All sites shall be maintained at essentially stable moisture conditions and extremes of wetting and drying prevented. This will require attention to the following.
3. Site drainage: The site shall be graded or drained so that water cannot pond against or near the house. The ground immediately adjacent to the house shall be graded to a uniform fall of 50mmminimum away from the house over the first meter. The subfloor space for the houses with suspended floors shall be graded or drained to prevent ponding. The site drainage requirements shall be maintained.
4. Gardens: The gardens shall not interfere with the drainage requirements or the subfloor ventilation and weep holes drainage requirements. Garden beds adjacent to the house should be avoided. Over watering of gardens close to the house shall be avoided.
5. Restrictions on trees / shrubs: Planting of trees shall be avoided near the footings of the house or neighboring house on reactive sites as they can cause damage due to drying the clay. To minimise the possibility of damage, tree planting should be restricted to a distance from the house of:- 1.50 x The mature height for Class E sites.- 1.00 x The mature height for Class H sites.- 0.75 x The mature height for Class M sites.
6. Where rows or groups of trees are involved, the distance from the building should be increased. Removal of trees from the site can also cause similar problems.
7. Repair of leaks: Leaks in plumbing, including stormwater and sewerage drainage should be repaired promptly.
A - Stable (Non-reactive)M - Moderatley ReactiveE - Extremely Reavtive
S - Slightly ReactiveH - Highly Reavtive
General Notes:1. These drawings shall be read in conjunction with the architectural and
other consultants drawings / specifications and with other such written instructions as may be issued during the construction. Any discrepancy shall be referred to the Engineer before commencing the work.
2. All dimensions are in millimeters, Unless noted otherwise.3. These drawings shall not be scaled, refer to dimensions given only or
refer to the Architectural drawings.4. All levels and setting out dimensions shown on the drawings shall be
checked on site prior to the commencement of work.5. During construction the structure shall be maintained in a stable
condition with no part being overstressed with temporary supports / bracing installed as required.
6. The engineer shall approve any proposed substitution prior to the commencement of works.
Permanent Metal Formwork:1. The permanent metal formwork shall be installed in accordance with
the manufacturers recommendations and shall NOT be substituted from the product specified without written approval from the engineer.
2. The permanent metal formwork shall be suitably propped.3. The permanent metal formwork shall not be spliced or joined midspan.4. The permanent metal formwork shall have a minimum end bearing of
50mm.5. The permanent metal formwork shall be fixed to the supporting
structure with spot welds or fasteners, there shall be a minimum of 1 fixing per sheet to the support each end adjacent to the side lap.
6. The permanent metal formwork may need to have the side lap fastened together midspan, this shall be carried out in accordance with the manufacturers specifications
Reinforced Concrete:1. workmanship and materials shall be in accordance with AS3600, except
where varied by the project documentation.2. Concrete quality shall be as follows
(Subject to Subgrade being satisfied) :
3. The engineer shall approve any admixtures to be used in the concrete mix.4. The clear concrete cover to all reinforcement shall be as follows UNO:
5. Cover to reinforcement shall be obtained by the use of approved bar chairs placed at maximum 750mm cts in each direction.
6. All concrete shall be mechanically vibrated and the vibrators SHALL NOT be used to spread the concrete.
7. Size of the concrete elements do not include thickness of the applied final finishes.
8. Approval shall be obtained from the engineer prior to the drilling of any holes or cutting in any chases other than those shown on the structural drawings.
9. Construction joints where not shown on the structural drawings shall be located in accordance with the engineers approval.
10. Curing of all concrete it to be achieved by keeping surfaces continuously wet for a period of 7 days (10 days in summer months), and prevention of loss of moisture for a total of 10 days followed by gradual drying out. Approved spray on compounds complying with AS3799 may be used provided that they do not interfere with the performance of the proposed floor finishes. Polythene sheeting or wet hessian may be used if protection from wind and traffic.
11. The suspended slabs shall be propped until 28 day strength has been achieved for slabs. The formwork may be removed once 20 MPa strength has been achieved, however the slab will need to be back propped until 28 days strength has been achieved. No masonry or partition walls are to be constructed on suspended levels until all propping is removed.
12. Conduits, pipes, etc. shall only be placed in the middle third of the slab depth and spaced at not less than 3 diameters. They shall no be placed within the cover of the reinforcement.
13. Reinforcement symbols: S - Denotes grade 250 S bars to AS1302N - Denotes grade 500 normal ductility deformed bars to AS4671R - Denotes grade 250 normal ductility round bars to AS4671SL - Denoted grade 500 low ductility square welded mesh to AS4671RL - Denoted grade 500 low ductility rectangular welded mesh to AS4671L - Denoted grade 500 low ductility trench welded mesh to AS4671.
14. Reinforcement is represented diagrammatically and is not necessarily shown in true projection.
15. Splices in reinforcement shall be made only in positions shown or otherwise approved by the engineer.
Element
Footings
Bored Piers & Pile Caps
Floor Slabs on Ground
Suspended Floor Slabs
Hollowcore Floor Slabs
Walls & Columns
Slump(mm)
Maximum Aggregate size (mm)
Cement Type
Strength 28 Days (MPa)
Admixture
Nor
mal
Por
tlan
d
Typ
e A
Cem
ent
Exposure Classification to
AS3600
A1
Against Formwork
Exterior Surface
Strength 28 Days (MPa)
Interior Surface
Against Ground
With no Membrane
With Membrane
A2
B1
B2
Masonry Piers
Retaining Walls
16. Laps and cogs shall be in accordance with AS3600 and not less than the below:
17. Site bending of deformed reinforcing bars shall be done without heating and using mechanical bending tools.
18. Welding of the reinforcement shall not be permitted unless shown on the structural drawings or approved by the engineer.
19. Joggles to the bar shall be 1 bar diameter over a length of 12 bar diameters.
20. Bundled bars shall be tied together at 30 bar diameter centers with 3 wraps of tie wire.
21. Mesh shall be lapped 2 transverse wires plus 25mm.
Minimum Splice LengthsN12 400mmN16 600mmN20 800mmN24 1100mmN28 1400mm
Minimum Overall Cog Lengths200mm225mm275mm325mm375mm
25mm Min
Min Overlap
Alternative Mesh Splice Detail:50mm Max
N10 at wire centres x 1200mm long
80 20 25 -
80 20 25 -
80 20 25 -
80 20 32 -
80 20 32 -
80 20 32 -
20 20 30 30 50
25 40 30 40 50
32 40 40
40 45 45
150 7-14 20 -
80 20 32 -
I hereby certify that the above mentioned works are structurally adequate for their intended purpose. This certification is limited to the structural elements detailed, and based on the works being carried out in accordance with these structural/civil plans. The structure has been designed in accordance with the following:
- AS/NZS 1170.0:2002: Structural design actions - General principles - AS/NZS 1170.1:2002: Structural design actions - Permanent, imposed & other actions - AS/NZS 1170.2:2011: Structural design actions - Wind actions - AS 4055-2012: Wind Loads For Housing - AS 4100-1998: Steel Structures - AS 1163-1991: Structural Steel Hollow Sections - AS/NZS 1111-1996: ISO Metric Hexagon Commercial Bolts & Screws - AS 3600-2009: Concrete Structures. - AS 3700-2011: Masonry Structures - AS 2870-2011: Residential slabs and footings – Construction - AS 1684-2010: Residential timber framed construction - AS 1720.1-2010: Timber Structures – Design Methods - AS 3959-2009: Construction of buildings in bushfire prone areas - Building Code of Australia (BCA)
All works to be carried out by a licensed builder in accordance with the current edition of the Building Code of Australia (BCA) and relevant Australian Standards for construction. Based on the above parameters, I hereby certify that the structural components are adequate under the imposed loading provided that they are constructed in accordance with the relevant Australian Standards. I certify that I am a qualified and practising Structural Engineer in accordance with the requirements of the Building Code of Australia and The Institution of Engineers, Australia.
Murray PalmerBEng (Civil & Structural) HonsMember No: 3798337 Senior Engineer
Vision Engineers27 Eighth Street Adamstown
W/ (02) 4954 2422 M/ 0414 011 [email protected]
www.visioneng.com.au
27 Eighth Street, AdamstownW/ (02) 40231266 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A31 : 20
En02
10/07/2018
917-6187
Revision Schedule
Rev Date Description
H 08/03/19 Final Engineering
G 27/02/19 Council Changes
F 20/11/18 Council Changes
E 22/10/18 Council Changes
Blockwork:1. All workmanship and materials shall be in accordance with AS3700.2. Reinforced concrete blockwork shall comply with the following, UNO:
- Blocks: Minimum 10 MPa unconfined compressive strength conforming to AS4455.- Mortar: 1.0 : 1.0 : 6.0 ratio of cement: Lime: Sand UNO.- Blocks shall be either 'H' or 'Double U' configuration.- Provide clean out holes at the base of the wall & rod core holes to remove excess mortar.- Core filling shall be 20 MPa concrete with maximum 10mm aggregate size with a maximum slump of 120 ±20mm- Minimum cover of 55mm from the outside of the blockwork.
3. Masonry retaining walls are to be back filled with either of the following material:- Coarse grained soil with low silt content- Residual Soil Containing Stones- Fine silty sand- Granular materials with low clay content
4. Vertical control joints shall be provided at max 8m centers. They shall be reinforced with N20-400 dowels 600mm long. One end shall be greased and capped.
5. No admixtures shall be used in the mortar mix or the core fill mix without prior written consent from the engineer.
Masonry:1. All workmanship and materials shall be in accordance with AS3700.2. The design strength of masonry shall be:
3. All masonry walls supporting concrete slabs and beams shall have a slip joint comprising of two layers of galvanized steel in between the concrete and masonry.
4. All masonry walls supporting or supported by concrete floors shall have vertical joints located to match and control / construction joints in the concrete.
5. Do not construct any masonry walls on suspended slabs until the slab formwork has been stripped and de-propped.
6. Non load bearing masonry walls shall be separated from concrete slab or beam above by 20mm thick compressible filler.
7. Provide vertical control joints at 6m maximum centers, and 4 meters maximum from corners in masonry walls, and between new and existing brickwork. The joint shall have expansion joint ties and suitably sealed with mastic sealant.
8. Masonry retaining walls are to be back filled with either of the following material:- Coarse grained soil with low silt content- Residual Soil Containing Stones- Fine silty sand- Granular materials with low clay content
Exposure Classification to AS3600
A1 / A2
B1
B2
Brick Compressive
Strength (MPa)
Brick Salt Resistance
Grade
Durability Classification
of Built in Components
Mortar Mix
GP Portland eCement Lime:
Sand
f'c(MPa)
20
20
20
General Purpose
Exposure
R3 (Galvanised)
R3 (Stainless)
1.0 : 1.0 : 6.0
1.0 : 1.0 : 6.0
1.0 : 0.5 : 4.5
2.8
2.8
2.8
Structural Steel:1. All workmanship and materials shall be in accordance with AS4100 and
AS/NZ4600.2. The structural design has been baised on the following steel grades, UNO:
- Hot rolled universal beams, columns, channels & angles: - Circular, square & rectangular hollow sections: - Cold formed open DuraGal profiles: - Cold formed lipped Cee & Zed Purlins:
3. The structural design has been based on MBPMA nominal size Cee & Zed lipped purlins.
4. Qualifications for welding procedures and personnel shall conform to Section 4 of AS 1554.1. Non destructive testing of welds shall include 100% visual inspection and additional testing as shown on the drawings.
5. All welds shall be 6mm continuous fillet type GP, UNO. All butt welds shall be complete penetration in accordance with AS1554.1, UNO.
6. Bolt Designation:- 4.6/S - Commercial bolts to AS 1111, snug tightened.- 8.8/S - High strength structural bolts to AS1562, snug tightened.- 8.8/TB - High strength structural bolts to AS1562, full tensioned bearing joint.- 8.8/TF - High strength structural bolts to AS1562, fully tensioned friction joint.
7. All bolts shall be M16 8.8/S, with a minimum of 2 bolts per connection UNO.8. Fin plates shall be a minimum of 10mm thick, grade 300PLUS steel, UNO.9. Concrete encased steel work shall be wrapped with SL62 mesh and shall
have a minimum 50mm of cover, UNO.10. Steelwork to be encased in concrete shall have the following surface
treatment, UNO:
11. Where sealed tube members are hot dipped galvanised, the fabricator shall provide drill holes as neccessary to allow gases to escape.
12. All transport and erection damage, site welds etc., shall be reinstalled to an equivalent finish to adjacent steelwork.
13. If steel beams and posts are designated to be galvanised, then end plates, cap plates, and base plates shall also be galvanised.
14. All nuts and bolts shall be galvanised or marine grade stainless steel.
300PLUSC350/C450LOC350/C450LOG550/G500/G450
Exposure Classification
to AS3600
Steelwork Protection Required
A1 / A2 Power tool clean to AS1627 Class 1, 1 Coat Alkyd Primer (Zinc Phosphate)
B1 Abrasive blast to AS1627 Class 2.5 1 Coat Inorganic Zinc Silicate
B2 Hot Dipped Galvanised to AS1650
Timber:1. All workmanship and materials shall be in accordance with AS1684 and
AS1720.2. AS1684 shall be applied to domestic construction in sheltered
locations.3. Softwood to be a minimum of F7 MGP10 and hardwood to be a minimum
of F17 UNO.4. External timber shall be either hardwood durability class 1 or 2 as per
AS1720 or impregnated pine grade F7 MGP10. pressure treated to AS1604 and re-dried prior to use. Supplementary treatment shall be applied to all cut surfaces.
5. Two (2) copies of timber truss shop drawings shall be submitted to the engineer for approval, clearly indicating design loads and point loads applied to the structure.
6. All bolts in timber construction shall be M16 4.6/S UNO. Washers under heads and nuts shall be at least 2.5 times the bolt diameter.
7. All timber joints and notches shall be a minimum on 100mm away from loose knots, severe sloping grain, gum veins or other minor defects.
Ar03
Sec 1
3-11TM trimmer bars, 2000mm long at all internal edges of slab as shown
85 thick slab, SL82 (t) 30 cover, over 1090mm x 1090mm pods, Typical internally
Ar03
Sec 2
EB1
EB
2
Cut
Fill
CutFill
CutFill
Proposed 400mm diameter piers founded 1800 onto bedrock, refer geotechnical report for approximate depths. Note cutting and filling
will vary depths noted in report (typical)
EB
1
EB
1
EB1
SDB1
SD
B1
EB1
1090
1090 1090 1090
1090
1090 1090 78810
90
1090
1090
1010
900
1010
860
1090 800 788590
150
7000
150
7300
1350 8288 150
150
3710
3290
150
9788
150
1150
2560
150
3290
1300
1830
836
836 864 5950 1988 150
850
900
EB1
EB1
EB3
EB
3
110 thick slab, SL82 (t) 30 cover, for tank
VISION ENGINEERS FOOTING INSPECTIONS ARE REQUIRED:
1. Piers and trenches prior to reinforcing2. All steel reinforcement prior to pouring concrete
Contact Vision Engineers minimum 48 hours prior to organise inspections.
Widen footing locally to 450 SQ for post location over as shown
SF1
SF1
Ex01
Footpath Cross Section 02
Ex01
Footpath Cross Section 01
22
5
400
Brick pier locations, shown indicatively. Reinforce all brik piers with N12 vertical bars, embedded min 300 into the SF1 strip footing
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En03
10/07/2018
917-6187
Unit Development
1 : 100
Slab Plan (Unit 1)
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
NORTH
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Ar03
Sec 5
Ar03
Sec 3
1090
1090
1210
1010
1090
968
590 1090 1090 1090 1090
790
788
1010
109010901090
810
1010
900
370
968
1010
900
1090
1010
1090
1090
1090 1090 1090 1090 1090 1090 1090 788
900
850
150
3710
3448
3648
419
015
0
150
715
87838
150
15295
5950 1988 150
1700 8088
1350 8288 150
150 9488 150
9788
836 874 5950 1988 150
150 9498 150
1350 8298 150
9798
150
3710
3448
3648
419
015
0
1350
2510
150
1350
1780
836
3342
3498
1550
2790
150
15295
Proposed 400mm diameter piers founded 1800 onto bedrock, refer geotechnical report for approximate depths. Note cutting and filling
will vary depths noted in report (typical)
EB
3
EB
1
SDB1
EB
3
SD
B1
SD
B1
SDB1
EB3 EB1
EB1
EB1
EB
1E
B1
EB1
EB
1
SD
B1
SDB1
SDB1
SD
B1
PW1 PW1E
B3
EB
3
EB3
EB
1
Cut
Fill
Cut
Fill
Cut
Fill
110 thick slab, SL82 (t) 30 cover, for tank
Widen footing locally for post location over as shown
VISION ENGINEERS FOOTING
INSPECTIONS ARE REQUIRED:
1. Piers and trenches prior to reinforcing2. All steel reinforcement prior to
pouring concrete
Contact Vision Engineers minimum 48 hours prior to organise inspections.
410
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En04
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
NORTH
1 : 100
Slab Plan (Units 2 & 3)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
11900
11700
11400
1140011315
11615
11815
11815
11615
11815
11315
Unit 3FFL 11900
Unit 3 GarageFFL 11815
Unit 2 GarageFFL 11615
Unit 2FFL 11700
Unit 1 GarageFFL 11315
Unit 1FFL 11400
Batter up to natural ground
Driveway crossfall as to driveway sections.
Batter from driveway edge to boundary
Driveway crossfall as to driveway sections.
Batter from driveway edge to boundary
Driveway crossfall as to driveway sections.
Batter from driveway edge to boundary
Batter up to natural ground
Batter down to natural ground
Timber slat fence between courtyards
Timber slat fence between courtyards
Unit 1 Courtyard
Unit 2 Courtyard
Unit 3 Courtyard
Courtyard level to retaining wall
Courtyard level to retaining wall
Courtyard level to retaining wall
Batter up to natural ground
Visitor Carpark
Retaining wall 0 high
Retaining wall 1000 high
34225
200
200
2801
Retaining wall 800 high
Retaining wall 440 high
200
Retaining wall 350 high
Retaining wall 300 high
Retaining wall 0 high
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En05
10/07/2018
917-6187
Unit Development
1 : 200
Retaining Wall Plan
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Ar03
Sec 1
Proposed beam connection (see detail)
FJ
101
9788
Ar03
Sec 2
S1 S1L101
S1
S1 S1S1S1S1
S1
S1L102
L103 L104 L105
C1C1
L10
6
P1
B102
P2
S2S2
B103
B10
4FJ
101
R10
1
1200
S1
S1S1 L105
B10
5
S1S1
S1
S1
L10
7
L107
Lintel L107 shall have tie-downs as per AS1684.2 Table 9.20(A) - 4 nails each end (typical)
S1S1
S1S1
S1S1
B10
1
StudsStudsPostPost
ColumnBeamBeamBeamBeamBeamLintelLintelLintelLintelLintelLintelLintel
Floor JoistRafter
2/90 x 45 MGP10/F7, Nail laminated3/90 x 45 MGP10/F7, Nail laminated90 x 90 F7 K/D T/Pine OR 100 x 100 F11 Hardwood100 x 100 F11 Hardwood89 SHS 3.5, HDG or Inorganic Zinc Coating300 x 45 HYSPAN LVL140 x 45 MGP10 H3 (if not fully clad)300 x 45 HYSPAN LVL2/300 x 45 HYSPAN LVL, Nail laminated300 x 45 HYSPAN LVL200 x 63 HYSPAN LVLMin. 120 x 45 MGP10 200 x 63 HYSPAN LVL2/300 x 45 HYSPAN LVL200 x 63 HYSPAN LVL180 PFC + 200 x 10 Base PL, HDG or Inorganic Zinc Coating140 x 45 MGP10HYJOIST HJ30045 @ Max 600 cts (450 cts for wet areas)90 x 45 MGP10 @ Max 900 cts
S1S2P1P2C1
B101B102B103B104B105L101L102L103L104L105L106L107
FJ101R101
Member Description Size
Member Schedule (First Floor Joist) - Unit 1
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En06
10/07/2018
917-6187
Unit Development
1 : 100
First Floor Joist Layout Plan (Unit 1)
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultantNORTH
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
For all lintels in non-loadbearing walls, the fixings shall be nominal as per AS1684.2 Table 9.4
Tie-downs for lintels supporting sheet roof (AS1684.2 Table 9.20)
RLWUp to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
3000
4500
9.20(A) - 4 Nails
9.20(A) - 4 Nails
9.20(A) - 4 Nails
9.20(A) - 6 Nails
9.20(A) - 6 Nails
9.20(A) - 4 Nails
9.20(A) - 6 Nails
9.20(A) - 6 Nails
9.20(A) - 4 Nails
9.20(A) - 6 Nails
Minimum size for non-loadbearing lintels
Timber grade
MGP10/F7
Hyspan
Smart LVL 15
Span
Up to 1200 Up to 1800 Up to 2400 Up to 3000
90 x 45
95 x 36
90 x 42
90 x 45
95 x 45
120 x 35
120 x 45
130 x 36
120 x 35
190 x 45
130 x 45
130 x 58
Up to 3600
190 x 45
170 x 45
170 x 58
Minimum size for lintels supporting sheet roof up to 3m RLW (N1/N2)
Timber grade
MGP10/F7
Hyspan
Smart LVL 15
Span
Up to 1200 Up to 1800 Up to 2400 Up to 3000
2/90 x 45
95 x 45
120 x 35
140 x 35
130 x 45
120 x 35
190 x 35
150 x 45
150 x 42
240 x 35
200 x 45
170 x 42
Up to 3600
2/240 x 35
240 x 45
240 x 42
Minimum size for lintels supporting sheet roof up to 4.5m RLW (N1/N2)
Timber grade
MGP10/F7
Hyspan
Smart LVL 15
Span
Up to 1200 Up to 1800 Up to 2400 Up to 3000
120 x 45
90 x 45
120 x 35
190 x 35
130 x 45
130 x 42
190 x 45
150 x 63
150 x 42
240 x45
200 x 63
200 x 58
Up to 3600
2/240 x 45
240 x 63
240 x 58
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
Ar03
Sec 4
Ar03
Sec 5
Ar03
Sec 3
S1
S2S2 S1
P1
S1
S2
S2
C2C2
C2C2
P1
P2
L301
B302
B303
B30
4
L301
L302 L303
L30
4
B305 C1 L306
S1S1
L307
S1S1
L307
S1S1
L307
L30
5
8598
FJ
301
FJ
301
1200
R30
1
C3C1
S2
FJ302
FJ
30
2
B30
6
B307 B308
B30
9
B3
10Roof trusses over. Roof trusses,roof bracing and tie downs to themanufacturers specifications andAS1684.
S1
B30
0
S1S1
S1S1
S1
B3
01
S1S1
S1
S1
C1
C3
B313
FJ
302
A
4860
2980
FJ
30
2
Load bearing wall
C3
FJ
302
2807B313
S1 S1L308
B311 B312
Fix B309 to B307 using PRYDA split joist hanger, fixings as per manufacturer's specifications
S2
S1
SC1
ColumnColumnColumn
Stub ColumnStudsStudsPostPostBeamBeamBeamBeamBeamBeamBeamBeamBeamBeamBeamBeamBeamBeamLintelLintelLintelLintelLintelLintelLintelLintel
Floor JoistFloor JoistFloor Joist
Rafter
89 x 89 x 3.5 SHS, HDG or Inorganic Zinc Coating180 PFC, HDG or Inorganic Zinc Coating89 x 89 x 5.0 SHS, HDG or Inorganic Zinc Coating75 x 75 x 4.0 SHS, HDG or Inorganic Zinc Coating2/90 x 45 MGP10/F7, Nail laminated3/90 x 45 MGP10/F7, Nail laminated90 x 90 F7 K/D T/Pine OR 100 x 100 F11 Hardwood100 x 100 F11 Hardwood300 x 45 HYSPAN LVL300 x 45 HYSPAN LVL140 x 45 MGP10 H3 300 x 45 HYSPAN LVL2/300 x 45 HYSPAN LVL, Nail laminated140 x 45 MGP10 H3 140 x 45 MGP10 H3 2/300 x 45 HYSPAN LVL, Nail laminated250 PFC, HDG or Inorganic Zinc Coating300 x 45 HYSPAN LVL310 UB 32, HDG or Inorganic Zinc Coating2/360 x 45 HYSPAN LVL, Nail laminated250 PFC, HDG or Inorganic Zinc Coating2/360 x 45 HYSPAN LVL, Nail laminated200 x 63 HYSPAN LVL2/300 x 45 HYSPAN LVL, Nail laminated240 x 63 HYSPAN LVL200 PFC + 200 x 10 PL, HDG or Inorganic Zinc Coating200 PFC + 200 x 10 PL, HDG or Inorganic Zinc Coating180 PFC, HDG or Inorganic Zinc CoatingRefer typical lintel tables for sizes200 x 63 HYSPAN LVLHYJOIST HJ30045 @ Max 600 ctsHYJOIST HJ30090 @ Max 600 ctsHYJOIST HJ30090 @ Max 450 cts (for wet areas)90 x 45 MGP10 @ Max 900 cts
C1C2C3SC1S1S2P1P2
B300B301B302B303B304B305B306B307B308B309B310B311B312B313L301L302L303L304L305L306L307L308FJ301FJ302
FJ302AR301
Member Description Size
Member Schedule (First Floor Joist) - Units 2 & 3
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En07
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
First Floor Joist Layout Plan (Units 2 & 3)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Ar03
Sec 1
Ar03
Sec 2
L1
S1
SG
-185
5
S1 S1 S1 S1
S1S1
S1
L2
TG
-230
0
TG
-230
0MG
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
StudsLintelLintel
2/90 x 45 MGP10/F7, Nail laminated240 x 45 HYSPAN LVL (supports Girder Truss)140 x 45 MGP10
S1L1L2
Member Description Size
Member Schedule (First Floor Roof) (Unit 1)
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En08
10/07/2018
917-6187
Unit Development
1 : 100
First Floor Roof Plan (Unit 1)
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
NORTH
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 4501mm up to 6000mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10
Hyspan LVL13
Smart LVL15
Jamb Studs
190 x 45
130 x 45
130 x 42
A
2/190 x 45*
200 x 45
200 x 42
A
2/240 x 45*
240 x 45
240 x 42
B
2/290 x 45*
300 x 45
300 x 58
C
-
360 x 63
300 x 75
C
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 6001mm upto 7500mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10
Hyspan LVL13
Smart LVL15
Jamb Studs
190 x 45
130 x 45
130 x 42
A
2/190 x 45*
200 x 45
200 x 42
B
2/240 x 45*
240 x 45
240 x 58
B
2/290 x 45*
300 x 63
300 x 58
C
-
400 x 63
400 x 75
D
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Jamb Stud Sizes
Jamb Studs A
2/90 x 35 MGP10
Jamb Studs D
2/90 x 63 Hyspan LVL13
Jamb Studs B
2/90 x 45 MGP10
Jamb Studs C
3/90 x 45 MGP10
Typical Sheet Roof Lintels, Jamb and Tie-down Details
Minimum size for non-loadbearing lintels
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
90 x 45
95 x 36
90 x 42
A
90 x 45
95 x 45
120 x 35
A
120 x 45
130 x 36
120 x 35
A
190 x 45
130 x 45
130 x 58
A
190 x 45
170 x 45
170 x 58
A
Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW up to 3000mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
2/90 x 45*
95 x 45
120 x 35
A
140 x 35
130 x 45
120 x 35
A
190 x 35
150 x 45
150 x 42
A
240 x 35
200 x 45
170 x 42
A
2/240 x 35*
240 x 45
240 x 42
B
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 3001mm up to 4500mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
120 x 45
90 x 45
120 x 35
A
190 x 35
130 x 45
130 x 42
A
190 x 45
150 x 63
150 x 42
A
240 x 45
200 x 63
200 x 58
B
2/240 x 45*
240 x 63
240 x 58
B
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Tie-downs for lintels supporting sheet roof (AS1684.2 Table 9.20)
Lintel SpanRLW
Up to 1200
Up to 3000
3001-4500
4501-6000
6001-7500
For all lintels in non-loadbearing walls, the fixings shall be nominal as per AS1684.2 Table 9.4
9.20(A) 4 nails
9.20(A) 4 nails
9.20(A) 4 nails
Up to 1800
9.20(A) 6 nails
Up to 2400
9.20(A) 6 nails
9.20(A) 4 nails 9.20(A) 4 nails 9.20(A) 6 nails
9.20(A) 6 nails
9.20(A) 6 nails
Up to 3000
9.20(A) 6 nails
9.20(A) 4 nails
Up to 3600
9.20(B) 4 nails
9.20(B) 6 nails
9.20(B) 6 nails 9.20(B) 6 nails
9.20(B) 6 nails 9.20(C) M12
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Ar03
Sec 4
Ar03
Sec 5
Ar03
Sec 3
MG
L201
L202
S1S1
S1S1
S1
S1 S1
S1 S1
S1 S1S1
SG
-185
5
MT
G-2
00
0
MT
G-2
00
0
SG
-24
05
SG
-24
05
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
StudsLintelLintel
2/90 x 45 MGP10/F7, Nail laminated200 x 63 HYSPAN LVL (supports Girder Truss)140 x 45 MGP10
S1L201L202
Member Description Size
Member Schedule (First Floor Roof) (Unit 2 & 3)
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En09
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
First Floor Roof Plan (Units 2 & 3)
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 4501mm up to 6000mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10
Hyspan LVL13
Smart LVL15
Jamb Studs
190 x 45
130 x 45
130 x 42
A
2/190 x 45*
200 x 45
200 x 42
A
2/240 x 45*
240 x 45
240 x 42
B
2/290 x 45*
300 x 45
300 x 58
C
-
360 x 63
300 x 75
C
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 6001mm upto 7500mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10
Hyspan LVL13
Smart LVL15
Jamb Studs
190 x 45
130 x 45
130 x 42
A
2/190 x 45*
200 x 45
200 x 42
B
2/240 x 45*
240 x 45
240 x 58
B
2/290 x 45*
300 x 63
300 x 58
C
-
400 x 63
400 x 75
D
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Jamb Stud Sizes
Jamb Studs A
2/90 x 35 MGP10
Jamb Studs D
2/90 x 63 Hyspan LVL13
Jamb Studs B
2/90 x 45 MGP10
Jamb Studs C
3/90 x 45 MGP10
Typical Sheet Roof Lintels, Jamb and Tie-down Details
Minimum size for non-loadbearing lintels
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
90 x 45
95 x 36
90 x 42
A
90 x 45
95 x 45
120 x 35
A
120 x 45
130 x 36
120 x 35
A
190 x 45
130 x 45
130 x 58
A
190 x 45
170 x 45
170 x 58
A
Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW up to 3000mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
2/90 x 45*
95 x 45
120 x 35
A
140 x 35
130 x 45
120 x 35
A
190 x 35
150 x 45
150 x 42
A
240 x 35
200 x 45
170 x 42
A
2/240 x 35*
240 x 45
240 x 42
B
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Single / Upper Storey Lintel (Design wind speed N1/N2) -Sheet Roof with RLW 3001mm up to 4500mm
SpanTimber grade
Up to 1200 Up to 1800 Up to 2400 Up to 3000 Up to 3600
MGP10/F7
Hyspan LVL13
Smart LVL15
Jamb Studs
120 x 45
90 x 45
120 x 35
A
190 x 35
130 x 45
130 x 42
A
190 x 45
150 x 63
150 x 42
A
240 x 45
200 x 63
200 x 58
B
2/240 x 45*
240 x 63
240 x 58
B
* - Denotes nail laminated together as per AS1684.2Jamb size studs above to be used up to a height of 2750mm
Tie-downs for lintels supporting sheet roof (AS1684.2 Table 9.20)
Lintel SpanRLW
Up to 1200
Up to 3000
3001-4500
4501-6000
6001-7500
For all lintels in non-loadbearing walls, the fixings shall be nominal as per AS1684.2 Table 9.4
9.20(A) 4 nails
9.20(A) 4 nails
9.20(A) 4 nails
Up to 1800
9.20(A) 6 nails
Up to 2400
9.20(A) 6 nails
9.20(A) 4 nails 9.20(A) 4 nails 9.20(A) 6 nails
9.20(A) 6 nails
9.20(A) 6 nails
Up to 3000
9.20(A) 6 nails
9.20(A) 4 nails
Up to 3600
9.20(B) 4 nails
9.20(B) 6 nails
9.20(B) 6 nails 9.20(B) 6 nails
9.20(B) 6 nails 9.20(C) M12
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
Ar03
Sec 1
Ar03
Sec 2
GROUND FLOOR BRACING DETAILS UNIT 1:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.3) = 0.81 kPaContributory Surface Area = 49.8 m2Required Wind Bracing Capacity = 40.3 kNAchieved Bracing Capacity = 40.8 kN
Direction 2:Wind Pressure (AS1684.2 Table 8.5) = 0.85 kPaContributory Surface Area = 37.2 m2Required Wind Bracing Capacity = 31.6 kNAchieved Bracing Capacity = 32.4 kN
Bracing Units:
PA = 3.4 kN/mPB = 6.0kN/mSA = 1.5kN/mSB = 3.0kN/m
Direction 1
>
Direction 2 >
PB-1
150
Provide PB sheet bracing to entire ground floor wall, including above openings
PB-2
45
0
PB-3
20
0
SB-2700
PB-900
PA-900
PA-1500
SB-2700
SB-2700
PB-900 PB-900
Provide 30 x 0.8 G.I. strap bracing to underside of floor joists in these areas
similar to cross bracing for roof trusses, this is to assist the transfer of lateral bracing forces at the frotn elevation back to the
main bracing walls near the kitchen.
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En10
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
Ground Floor Bracing Plan (Unit 1)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
Ar03
Sec 4
Ar03
Sec 5
Ar03
Sec 3
GROUND FLOOR BRACING DETAILS UNIT 3:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.5) = 0.85 kPaContributory Surface Area = 51.1 m2Required Wind Bracing Capacity = 21.75 kN (Half Both Units' 43.5 kN)Achieved Bracing Capacity = 28.1 kN + Portal Frame 10kN
Direction 2: Wind Pressure (AS1684.2 Table 8.3) = 0.81 kPaContributory Surface Area = 76.5 m2Required Wind Bracing Capacity = 31.0 kN (Half Both Units' 62.0 kN)Achieved Bracing Capacity = 36.9 kN
GROUND FLOOR BRACING DETAILS UNIT 2:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.5) = 0.85 kPaContributory Surface Area = 51.1 m2Required Wind Bracing Capacity = 21.75 kN (Half Both Units' 43.5 kN)Achieved Bracing Capacity = 28.36 kN
Direction 2:Wind Pressure (AS1684.2 Table 8.3) = 0.81 kPaContributory Surface Area = 76.5 m2Required Wind Bracing Capacity = 31.0 kN (Half Both Units' 62.0 kN)Achieved Bracing Capacity = 33.4 kN + Portal Frame 10kN
Bracing Units:
PA = 3.4 kN/mPB = 6.0kN/mSA = 1.5kN/mSB = 3.0kN/m
Direction 1
>Direction 2 >
PA-900PA-900
PA-900
PA-900
SB-2700SB-2700 PA-900
PA-900
PA-900SA-2700
SA-2700SA-2700 PA-900
PA-900
PA-900PA-900
SA-2700
PA-1200
PB-900 PA-600PA-600
PA-6
00
PB-3
20
0
PB-1
90
0
Provide PB sheet bracing to entire ground floor wall, including above openings
PA-3
50
0
SB
-270
0
SB
-270
0
Port
al F
ram
ePo
rtal
Fra
me
SB-1800
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En11
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
Ground Floor Bracing Plan (Units 2 & 3)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
Ar03
Sec 1
Ar03
Sec 2
FIRST FLOOR BRACING DETAILS UNIT 1:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.2) = 0.70 kPaContributory Surface Area = 23.3 m2Required Wind Bracing Capacity = 16.3 kNAchieved Bracing Capacity = 29.5 kN
Direction 2:Wind Pressure (AS1684.2 Table 8.4) = 0.77 kPaContributory Surface Area = 17.3 m2Required Wind Bracing Capacity = 13.3 kNAchieved Bracing Capacity = 32.4 kN
Bracing Units:
PA = 3.4 kN/mPB = 6.0kN/mSA = 1.5kN/mSB = 3.0kN/m
Direction 1
>
Direction 2 >
SB-1800 SB-1800
SB-1800
SB-1800
PA-1200
PA-600
SB
-240
0
SB
-180
0
PA-6
00
PA-6
00
SB
-180
0
PA-6
00
PA-6
00
PA-1400
SB
-180
0
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En12
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
First Floor Bracing Plan (Unit 1)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
Ar03
Sec 4
Ar03
Sec 5
Ar03
Sec 3
FIRST FLOOR BRACING DETAILS UNIT 3:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.4) = 0.77 kPaContributory Surface Area = 26.8 m2Required Wind Bracing Capacity = 10.35 kN (Half Both Units' 20.7 kN)Achieved Bracing Capacity = 20.1 kN
Direction 2: Wind Pressure (AS1684.2 Table 8.2) = 0.72 kPaContributory Surface Area = 33.4 m2Required Wind Bracing Capacity = 12.05 kN (Half Both Units' 24.1 kN)Achieved Bracing Capacity = 14.4 kN
FIRST FLOOR BRACING DETAILS UNIT 2:
Wind Speed = N2
Direction 1: Wind Pressure (AS1684.2 Table 8.4) = 0.77 kPaContributory Surface Area = 26.8 m2Required Wind Bracing Capacity = 10.35 kN (Half Both Units' 20.7 kN)Achieved Bracing Capacity = 15.3 kN
Direction 2:Wind Pressure (AS1684.2 Table 8.2) = 0.72 kPaContributory Surface Area = 33.4 m2Required Wind Bracing Capacity = 12.05 kN (Half Both Units' 24.1 kN)Achieved Bracing Capacity = 23.6 kN
Bracing Units:
PA = 3.4 kN/mPB = 6.0kN/mSA = 1.5kN/mSB = 3.0kN/m
Direction 1
>
Direction 2 >
SA-2400
PA-6
00
SA-2700
SA-1800SA-1800
PA-1300
PA-600
PA-6
00
PA-6
00
PA-6
00
SA-1800SB-2700PA-600
SA
-240
0
SA
-240
0
SA
-240
0
SA-2700 SA-1800
PA-6
00
SB
-180
0
PB-1
00
0
SA
-240
0
SA
-240
0
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En13
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
NORTH
1 : 100
First Floor Bracing Plan (Units 2 & 3)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Pod voidPod void Pod void
Pod voidPod void
Pod void
SL82 mesh top (typical)
Damp-proofing membrane, Typical
50 sand layer (typical)
110300 1090 x 1090 pod void max.85
310
172
3-N12 bars bottom with R6 ties @ 900 cts
1-N12 bar bottom
300
300 300
310
85
86
3-N12 bar bottom with R6 ties @ 900 cts
25 x 200 weatherseal rebate across garage door opening
(where required)
EB1Scale 1:20
IB1Scale 1:20
SDB1Scale 1:20
EB2Scale 1:20
3-N12 bar bottom
3-N12 bar bottom with R6 ties @ 900 cts
SL82 mesh top (typical)
Pod void
400
PW1Scale 1:20
SL82 mesh top (typical)
SL82 mesh top (typical)
3-N12 bars bottom with R6 ties @900 ctrs
400
300
Groundline
90 x 90 kiln dried treated pine or 100 x 100 hardwood post
EB3Scale 1:20
100
23040
40 230
Bri
ckw
ork
Ope
ning
25 deep weatherseal rebate across garage door opening (where required)
Weatherseal Rebate Detail (Plan)Scale 1:20
NATURAL GROUND LINE
2
1
NATURAL GROUND LINE
400
Proposed 400mm diameter piers founded 1800 onto bedrock, refer
geotechnical report for approximate depths. Note cutting and filling will vary depths noted in report. Provide
4/N12 vertical bars in a 2 x 2 grid, R6 ligatures @ max 300 cts, extending min 150 into footing with 150 cog to
bottom bars, 50 cover. (typical)
400
Typical Slab Piering DetailsScale 1:20
Pod void
SL82 mesh top (typical)
Pod void
310
Pipe Penetrations Detail NTS
All pipes/plumbing penetrations through the footings shall be sleeved using closed-cell ployethylene lagging or similar as per AS2870 Clause 6.6
Provide flexible joints to all plumbing immediately outside
the footing, set in the mid postion with minimum total movement range of 60mm
2-N12 bars top, R6 tied to mesh @ max 900 cts
Damp proof membrane (typical)
4-N12 bars bottom with R6 ties @ 900 cts
4-N12 bars top, R6 tied to mesh @ max 900 cts
Damp-proofing membrane (typical)
1-N12 bar top, tied to mesh @ max 900 cts
2-N12 bars top, tied to mesh @ max 900 cts
2-N12 bars top, tied to mesh @ max 900 cts
2-N12 bars top, tied to mesh @ max 900 cts
3-12TM top and bottom with R10 ligatures @ 600 cts
350
700
750
SF1 DetailScale 1:20
NOTE: Where SBD1 width is 400mm provide an extra
bar top and bottom
Brick piers shown indicatively, N12 vertical bar in each pier, min 300 embedment
300
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En14
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
General Notes1. Bracing and tie-down details to the engineers details and AS1684.22. All timber and steel to be installed and treated to the manufacturers specifications, expecially for any exterior applications3. All white ant protection to be strictly within the guidelines of AS3660 and installed by a qualified licenced pest control consultant
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
-A
Type A Tension Strap Type A Metal Angle Type B Tension Strap Detail A
Type A - Strap Bracing (SA) Specifics Type B - Strap Bracing (SB) Specifics
Type A - Sheet Bracing (PA) Specifics Type B - Sheet Bracing (PB) SpecificsSheet Bracing Details
-
Type Of Diagonal Brace
Material & Size Nailing Requirements
To Each Stud
Special Requirements
ProductAustralian Standard
Minimum Thickness For Stud Spacing (mm)
450
Panel Length (mm)
Type / Grade
Nail Size (mm)
Nail Spacing (mm)
Edge
Special Requirements
Panel length
Tension strap shall be paired
and opposing
30 x 0.8mm galvanisedmetal strap looped over plate & fixed tostud with 4 x 30mm x Ø2.8 gal flat head nails at each end
Metal AngleGalvanised angle, nom. Section 20x18x1.2mm min. Net section 42mm²
Drill holes if necessary to prevent nail splitting
1x30xØ2.8mm Galv. Flat head nail
2x30xØ2.8mm Galv. Flat head nail
Tension Strap
Galvanised flat metal tension strapping of min. Thickness 0.8mm & min. Net section of 15.2mm²
Straps must be properly tensioned
1x30xØ2.8mm Galv. Flat head nail
3x30xØ2.8mm Galv. Flat
head nail
Tension Strap
Galvanised flat metal tension strap nom. Size 30x0.8mm & min. Section of 24mm²
Straps must be properly tensioned & strap must return over top plate & under the bottom plate. The stud nearest to each end of each diagonal strap shall be fixed to the plates with straps or framing anchors 4x30xø2.8mm nails at each end.
2/30xØ3.15mm galv. Flat head nail
4/30xØ2.8mm galv. Flat head nail
Plywood AS2269
F8F11F14F27
74.543
976
4.5
900 150 300
No nogging req'd Except at sheet Ends. Nails shall Be 7mm from all Edges
Hardboard (Masonite)
AS2458 G.P. 6.4 6.4 90030mm x
Ø2.8 Galv.100 300
Nails to be 10mm From vertical Edges & 20mm from Horizontal edges. No nogging req'd Except at sheet Ends.
AS2269
F8F11F14F27
7644
976
4.5
900 / 1200
50 to plates & 150 to edge studs
300
No nogging req'd except at sheet ends. Nails shall be 7mm from all edges
AS2458 G.P. 6.4 6.4900 / 1200
300
Nails to be 10mm from vertical edges & 20mm from horizontal edges. No nogging req'd except at sheet ends.
50 to plates & 150 to edge studs
1800 Min. To 2700 Max.1800 Min. To 2700 Max.1800 Min. To 2700 Max.
Type A - Sheet Bracing Notes
1. Panel lengths greater than those listed above can be considered as a number of bracing units directly proportioned to their installed length I.E. A 1200mm panel of plywood equals 1200 / 900 = 1.33 bracing units.2. Nails should be driven just below the surface of the sheet using the hammer face only. Nails must not be punched3. Plywood panel lengths of 600mm are equivalent to 1/3 of a type a bracing unit.4. For stud spacing of 600mm c/c where noggins are installed and the plywood bracing panels are nailed to the noggins at 1500mm c/c,the plywood thickness may be as for stud spacing at 450mm c/c.5. PA* indicates full length available.6. Refer to table 1 on the following sheet for top & bottom plate fixing details.
Type B - Sheet Bracing Notes
1. Panel lengths greater than those listed above can be considered as a number of bracing units directly proportioned to their installed length I.E. A 1200mm panel of plywood equals 1200 / 900 = 1.33 bracing units.2. Nails should be driven just below the surface of the sheet using the hammer face only. Nails must not be punched3. PB* indicates full length available.4. Refer to table 1 on the following sheet for top & bottom plate fixing details.
Horizontal joints shall occur over
noggins and nailed as per top &
bottom plate
Vertical edges to be supported by studs
Nai
l sp
acin
g in
term
edia
te
Nail spacing edge
Nai
l spa
cing
ed
ge
600
ProductAustralian Standard
Minimum Thickness For Stud Spacing (mm)
450
Type / Grade
Nail Size (mm)
Nail Spacing (mm) Special Requirements
600
Panel Length (mm)
Intermediate Edge Intermediate
Plywood
Hardboard (Masonite)
30mm x Ø2.8 Galv.
30mm x Ø2.8 Galv.
30mm x Ø2.8 Galv.
To Each Plate
Type Of Diagonal Brace
Material & Size Nailing Requirements
To Each Stud
Special RequirementsTo Each Plate
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
As indicated
En15
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Either premixed 15MPa no-fines concrete or site mixed 1 cement: 6 course graded 10mm aggregate (no sand) well rodded into block voids and around blocks as shown. With 20%-30% void ratio. Pour in Max 600mm lifts, allow to harden before next lift.
25 MPa concrete footing, cast into firm natural ground of minimum 150 kPa
100 Dia ag. pipe in geosock graded to outlet
SL82 slab fabric
Mechanically compacted fill to the engineer's details
Max
1200
Min 300
Min 600, to match No-Fines extent
Retaining Wall Detail 800-1200mmScale 1:20
Max
800
Min 600
Retaining Wall Detail < 800mmScale 1:20
25 MPa concrete footing, cast into firm natural ground of minimum 150 kPa
100 Dia ag. pipe in geosock graded to outlet
Mechanically compacted fill to the engineer's details
Either premixed 15MPa no-fines concrete or site mixed 1 cement: 6 course graded 10mm aggregate (no sand) well rodded into block voids and around blocks as shown. With 20%-30% void ratio. Pour in Max 600mm lifts, allow to harden before next lift.
Austral Heron blocks, refer
manufacturer's specifications
SL82 slab fabric
'B'
First block to be half buried below ground level
'B'Austral Heron blocks, refer
manufacturer's specifications
RETAINING WALL SCHEDULE FOR MAX. 1200 HIGH
1000800
HEIGHT'H'
650
NO FINES'B'
500
1200 850
First block to be half buried below ground level
Remove back wings from 30% of blocks to engage No-Fines
concrete behind wall
Remove back wings from 30% of blocks to engage No-Fines
concrete behind wall
150
150
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En16
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Typical C1 SHS Base Plate Connection DetailsScale 1:20
45
45
Typical Timber Beam to Studs Connection Detail
Scale NTS
Triple studs, nail laminated
Timber beam as specified
2/30 x 1.2mm galv. steel straps, pulled strap tight up and over beam, fix with Ø3.75 x 50mm long nails. (2 skew nailed into top of nailing plate & 3 into side
of stud cluster as shown) to AS1684.2
Nailing plate (if required)
PFC/UB
Min 45 thick LVL plates,fixed to PFC with M12 4.6/S bolts, with 50 SQ washers 3.0 thick, @ Max 300 CTS, Min 60 from edges.
Typical Floor Joist to Steel Beam DetailScale NTS
Fix floor joists to LVL plates with PRYDA framing brackets/joist
hangers to suit member sizes, fixings as per manufacturer's specifications
FJ#
16 thick base plate, 6CFW to column, on 20 thk non-shrink grout, inline with wall framing, 2/M12 Hilti Hit-HY200-R HIT-V rods, min 60 edge distance, min 60 anchor spacing, min 110 embedment, installed as per manufacturer's specifications (typical)
C1/C3
Typical C2 PFC Base Plate Connection DetailsScale 1:20
45
70 16 thick base plate, 6CFW to column, on 20 thk non-shrink grout, within wall framing, 2/M12 Hilti Hit-HY200-R HIT-V rods, min 60 edge distance, min 60 anchor spacing, min 150 embedment, installed as per manufacturer's specifications (typical)
C2
C2
L304/L305
10 thick flange cleat plate, 6CFW as cap plate to C2
column, 2/M16 8.8/S bolts to top flange of PFC beam
40
40
Typical L304/L305 to C2 Connection Detail
Scale NTS
10 thick flange cleat plate, 6CFW to C2 column, 2/M16 8.8/S bolts
to bottom flange of PFC beam
90 x 10 Cleat, 6CFW to C2,2/M16 8.8/S Bolts
90 x 45 MGP10 timber plate to PFC, 1/M10 4.6/S bolt @ Max 600 cts, with 40 SQ washer 2.5 thick to timber face (typical)
10 thick web stiffener plate, 6CFW between flanges of C2 at location
of bottom flange cleat plate
Base plate for L304/L305 shown indicatively, refer detail
L106 etc
200 x 10 PL, 6FW,Hit 150, Miss 100, 200 Continuous @ ends
Max 25mm brickwork overhang on base plate
Typical Cross Section Thru Garage Lintel
Scale 1:20
SHS Column
Column Shot Fixing DetailScale NTS
Min 90 x 35 MGP10 studs
Shot fixings @ max 400 cts vertically
Column
90 x 10 Cleat, 6CFW2/M16 8.8/S Bolts (Beams <250mm Deep)3/M16 8.8/S Bolts (Beams >250mm Deep)
PFC/UB/UC 6PL Cap, 6CFW
40
40
Typical PFC/UB "Cleat" Connection To SHS Detail
Scale NTS
45
45
Column
Timber Beam
Timber Beam to Column Connection DetailScale NTS
90 x 10 cleat, 6CFW,2/M16 4.6/S bolts,
57 SQ washers 4.0 thick
80
10PL Cap, 6CFW
Min
100
PFC/UB
90 x 10 Cleat, 6CFW,2/M16 8.8/S Bolts (Beams <250mm Deep)3/M16 8.8/S Bolts (Beams >250mm Deep)
For SB1 to SB3 use 3/M20 8.8/S bolts
PFC
PFC to PFC/UB CONNECTION DETAILSCALE NTS
FB102/FB1042/M16 8.8/S bolts one either side of column or 6mm CFW
Column 10 plate cap FPBW
Typical PFC/UB "Cap" Connection To Column Detail (Continuing Over)
Scale NTS
10 plate web thickener above column
SHS
Timber Beam
300mm Timber Beam to Column Connection DetailScale NTS
90 x 10 cleat, 6CFW,3/M16 4.6/S bolts,
57 SQ washers 4.0 thick
80
80
70
MIN 80
6PL Cap, 6CFW
Timber Beam
150 x 10 cleat, 6CFW,3/M16 4.6/S bolts,
57 SQ washers 4.0 thick
80
80
70
MIN 80
UB/PFC Beam
Timber Beam to PFC Connection Detail 1Scale NTS
90 x 45 MGP10 plate, fixed to top flange with M10 4.6/S bolts and 40 SQ 2.5 thick
washers @ max 900 cts3
00
300
70
from beam termination
80
SHS
Timber Beam
360mm Timber Beam to Column Connection DetailScale NTS
90 x 10 cleat, 6CFW,3/M20 4.6/S bolts,
65 SQ washers 5.0 thick
100
100
80
MIN 80
6PL Cap, 6CFW
360
360mm Timber Beam
150 x 10 cleat, 6CFW,3/M20 4.6/S bolts,
65 SQ washers 5.0 thick
100
100
80
MIN 80
UB/PFC Steel Beam
Timber Beam to PFC Connection Detail 2Scale NTS
90 x 45 MGP10 plate, fixed to top flange with M10 4.6/S bolts and 40 SQ 2.5 thick washers @ max 900 cts
360
NOTE: For timber beam to timber beam connections adopt the relevant
"Timber Beam to PFC Connection Detail 1 or 2" to suit the beam sizes
and instead of a steel plate welded to the steel beam, use a Min 150 x 150 x
10 EA and connect the two timber beam together.
Murray PalmerBEng (Civil & Structural) Hons
Member No: 3798337 Senior Engineer
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En17
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Boral Fire Rated Party Wall Details
(or similar by other manufacturers to relevant standards)
NTS
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En18
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
1 : 20
Boral Party Wall Detail
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Brick skin (veneer)
Slab edge beam (see relevant detail) Proposed slab top mesh (see
relevant detail)
Brick skin wall tie, to the manufacturers specifications,
schedule of specifications details and relevant Australian Standards
Wall stud
Bottom plate
Interior sheeting to the manufacturers specifications
Proposed floor coverings in concrete slab
Nogging
Skirting
Typical 3D Construction Detail - Brick Veneer - Slab
Scale 1:20
Proposed reinforcement and ties (see relevant detail)
Damp proof course
Proposed termite protection (Kordon, Termimesh or similar), installed to the manufacturers specifications and relevant Australian Standards
Proposed sand layer and Damp-proofing membrane, Typical under slab, installed to relevant Australian Standard's requirements
Insulation to the manufacturers specifications
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En19
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Typical Wall Section - Brick Veneer - Slab
Scale 1:20
See relevant Edge Beam detail
Floor lining
Skirting
Window sill flashing
Brick window sill
Wall lining
Bottom plate
Stud wall
Window architrave
Window sill lining
Window sill plate
Window frame (shown indicative only) installed to the manufacturers specifications
Window header to the wall manufacturers details, or schedule on plans if specified
Roof structure
Soffit trim
Window architrave
Top plate
Minimum 15mm gap between head of window frame and underside of
window head to allow for deflection
Cornice
Ceiling lining
Proposed steel angle or flat bar to the schedule of specifications details, BCA requirements and
relvant Australian Standards
Brick lining above window/door
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En20
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
Sill
mastic
sill brick
sill flashing
Sill
Jamb Jamb
brick veneer walling
jamb flashing
storm mould
architrave
cavity flashing
steel angle intel
timber reveals
mastic seal
aluminium framed window
Head
ALUMINIUM WINDOWS TIMBER WINDOWS
Head
Typical Wall/Window Relationship Details - Brick Veneer
Scale 1:20
ALUMINIUM WINDOW TIMBER WINDOW
flashingwindow head beam
trim firring
architrave
flashing
stud
sarking
timber reveals
aluminium window frame
timber window frame
'Z' flashing under sill
sill
architrave
Sill Sill
Jamb Jamb
Head Head
Typical Wall/Window Relationship Details - Weatherboard
Scale 1:20
27 Eighth Street, AdamstownW/ (02) 49542422 M/ 0414 011 483
Date Started:
Sheet:
Client:
Address:
Drawing No:
Scale: @ A3
Revision Schedule
1 : 20
En21
10/07/2018
917-6187
Unit Development
BUILDERS NOTE :
Use Dimensions in preference to scale. Site verify all dimensions before ordering Materials. Footings information shown on these plans may have to be changed if Builders site excavations reveal non-virgin ground. Consultation of Plan Vision Australia Pty Ltd would then be necessary to determine the required changes.Materials are under no circumstances to be ordered direct off plans.Materials to be ordered are only to be ordered from a Builders or applicable product manufacturers seperate site confirmed Materials list. Plans are not intended to be the absolute medium for construction information accuracy due to site discrepencies. See schedule of specifications for further details.
SURVEY NOTE :
Boundary dimensions are assumed only and taken from site information, others or owners information. Confirm boundaries before commencement of construction.Full project specific detailed survey plans have not been supplied to Plan Vision for planning purposes. See schedule of specifications for details.
'M'
N2 (W33N) (Assumed)Wind Class:
Soil Class: (Assumed)
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering
22.10.18 Council Changes
20.11.18 Council Changes
27.02.19 Council Changes
08.03.19 Final Engineering