  • Ex-Post Project Evaluation 2013: Package I-3

    (India, Sri Lanka, Bangladesh)

    December 2014

    JAPAN INTERNATIONAL COOPERATION AGENCY

    IC NET LIMITED

    EV

    JR

    14-11

  • Preface

    Ex-post evaluation of ODA projects has been in place since 1975 and since then the coverage of

    evaluation has expanded. Japans ODA charter revised in 2003 shows Japans commitment to

    ODA evaluation, clearly stating under the section Enhancement of Evaluation that in order to

    measure, analyze and objectively evaluate the outcome of ODA, third-party evaluations

    conducted by experts will be enhanced.

    This volume shows the results of the ex-post evaluation of ODA Loan projects that were mainly

    completed in fiscal year 2011, and Technical Cooperation projects and Grant Aid projects, most

    of which project cost exceeds 1 billion JPY, that were mainly completed in fiscal year 2010. The

    ex-post evaluation was entrusted to external evaluators to ensure objective analysis of the

    projects effects and to draw lessons and recommendations to be utilized in similar projects.

    The lessons and recommendations drawn from these evaluations will be shared with JICAs

    stakeholders in order to improve the quality of ODA projects.

    Lastly, deep appreciation is given to those who have cooperated and supported the creation of

    this volume of evaluations.

    December 2014

    Toshitsugu Uesawa

    Vice President

    Japan International Cooperation Agency (JICA)

  • Disclaimer

    This volume of evaluations, the English translation of the original Japanese version, shows the

    result of objective ex-post evaluations made by external evaluators. The views and

    recommendations herein do not necessarily reflect the official views and opinions of JICA.

    JICA is not responsible for the accuracy of English translation, and the Japanese version shall

    prevail in the event of any inconsistency with the English version.

    Minor amendments may be made when the contents of this volume is posted on JICAs website.

    JICAs comments may be added at the end of each report when the views held by the operations

    departments do not match those of the external evaluator.

    No part of this report may be copied or reprinted without the consent of JICA.

  • 1

    India

    Ex-Post Evaluation of Japanese ODA Loan Project

    Chhattisgarh Sericulture Project1

    External Evaluator: Ryujiro Sasao, IC Net Limited

    0. Summary

    This project aimed to increase the production of tasar silk2 in the State of Chhattisgarh

    through the development of the sericulture infrastructure and the provision of technical guidance

    to sericulture farmers, thereby contributing to employment creation and poverty reduction for

    the poor (especially women).

    Because the implementation of this project is sufficiently consistent with the Indian

    Governments development plan, the target sites development needs and Japans aid policy, its

    relevance is high. Silkworm feed trees were planted as planned initially. Regarding the initially

    estimated impacts, such as employment creation and an improvement in the standard of living

    of the poor, although each of the production of seeds3, cocoons, silk yarn and spun yarn are

    lower than initially planned, many poor women are able to work in sericulture and their

    standard of living is improving. Therefore, it can be judged that the effectiveness and the impact

    are fair. The efficiency is also fair, because the project costs were within the plan, while the

    project period was longer than planned. Although the operation and maintenance of this project

    is stable in terms of organization and personnel, there are problems in the technical and financial

    aspects. Therefore, the sustainability of the effects produced by this project is fair.

    In light of the above, this project is evaluated to be partially satisfactory.

    1. Project Description

    Project Location Silkworm Seed Station Established

    under The Project

    1 Although the title of this project was "Madhya Pradesh Sericulture Project at first, the region that includes the site

    covered by this project separated from the State of Madhya Pradesh and became independent as the State of

    Chhattisgarh in December 2000, the title was changed accordingly. 2 Four types of silkworm for sericulture exist in India: tasar, mulberry, muga, and eri. Tasar silkworms eat the leaves

    of trees such as Terminalia tomentosa and Terminalia arjura, and are reared outdoors. 3 This means silkworm eggs.

    Project site (Chhattisgarh State)

    India

    Pakistan

    Nepal

    China

    Bangladesh

    Myanmar

  • 2

    1.1 Background

    Sericulture was introduced into India during the prehistoric age. Recently, it has drawn

    attention as a rural household industry contributing to employment creation and poverty

    reduction, and the Indian Government has strived to develop it. The production of raw silk

    sharply increased from about 2,300 tons in 1970 to about 14,000 tons in 1995, which accounted

    for 13% of the worlds total production (99,000 tons) (according to the statistics in 1994)4. In

    the meantime, India received much development assistance to increase the production and

    improve the quality. With the assistance of the World Bank and others, India carried out the

    Karnakata Sericulture Project (1980), the Tasar Sericulture Project (1981), which covered

    several states, and the National Sericulture Project (1989). Japan also has given assistance to

    India for a long time. Japanese experts have given technical guidance since the 1960s, and Japan

    gave projecttype technical cooperation to the Central Silk Boards laboratory in the State of

    Karnataka in carrying out its plan to develop bivoltine sericulture technology since fiscal year

    (FY) 19915.

    The former State of Madhya Pradesh, where the target site of this project is located, is one

    of the poorest states in India. In FY1991, 60.1% of the state population was below the poverty

    line6 (28.9% for the whole of India)

    7. The state economy is based on monoculture rice

    cultivation, and there are hardly any industries that can absorb additional manpower. In this

    situation, the sericulture industry, which includes tasar sericulture, has great importance. The

    production of raw silk from tasar silkworms was 43 tons in FY1994, the second largest in

    India8.

    1.2 Project Outline

    In the seven districts of Bilaspur, Janjgir, Korba, Raigarh, Jashpur, Surguja and Korea of the

    State of Chhattisgarh9, this project aims to expand the production of tasar silk through the

    development of the sericulture infrastructure and the provision of technical guidance to

    sericulture farmers10

    , thereby contributing to employment creation and improvement in the

    standard of living of the poor.

    4 Source: JICA materials for appraisal. 5 Bivoltine sericulture means sericulture of a silkworm that has two broods per year. 6 In FY1993, the poverty line was an income of 2,747 rupees per person. 7 Source: JICA materials for appraisal. 8 Source: JICA materials for appraisal. 9 When administrative districts were revised in 1998, Bilaspur, Raigarh, and Surguja, the target three districts of this

    project at the time of the appraisal, were divided into seven districts of Bilaspur, Janjgir, Korba, Raigarh, Jashpur,

    Surguja, and Korea. There was no change in the project site. 10 This project initially included consideration of the feasibility of mulberry sericulture (for details, see the section

    on Efficiency).

  • 3

    Loan Approved Amount/

    Disbursed Amount

    2,212 million yen / 1,205 million yen

    Exchange of Notes Date/

    Loan Agreement Signing Date October 1997 / December 1997

    Terms and Conditions

    Interest Rate 2.3%

    Repayment Period:

    (Grace Period:)

    30 years

    (10 years)

    Conditions for

    Procurement General untied

    Borrower/

    Executing Agency (ies)

    President of India/

    Chhattisgarh Sericulture Department

    Final Disbursement Date February 2007

    Main Consultant

    (Over 100 million yen)

    Nippon Koei (Japan)

    Feasibility Studies, etc.

    Agriculture Finance Corporation Ltd., Bombay: F/S ,

    1993

    JICA: Special Assistance for Project Formation

    (SAPROF) for the Madhya Pradesh and Manipur

    Sericulture Projects, 1996

    Related Projects

    (Japanese ODA loan)

    Manipur Sericulture Project (1997)

    (Technical cooperation)

    Project for Promotion of the Popularization of

    Practical Bivoltine Sericulture Technology in India

    (1997 - 2002)

    Strengthening the Extension System for Bivoltine

    Sericulture in India (2002 - 2007)

    (Other organizations projects)

    World Bank: Kartanaka Sericulture Project

    World Bank and Swiss Agency for Development and

    Cooperation: National Sericulture Project

    Swiss Agency for Development and Cooperation:

    Interstate Tasar Project

    * All these projects were carried out in other states.

  • 4

    2. Outline of the Evaluation Study

    2.1 External Evaluator

    Ryujiro Sasao (IC Net Limited)

    2.2 Duration of Evaluation Study

    Duration of the Study: August 2013 December 2014

    Duration of the Field Study: January 26 February 1, 2014; May 5 May 18, 2014

    2.3 Constraints during the Evaluation Study

    In the State of Chhattisgarh, the External Evaluator could not basically enter the project site

    for security reasons. As a result, the local consultant familiar with the situation in the state and

    sericulture carried out a survey on the beneficiaries and inspection of the facilities under the

    supervision of the External Evaluator, who then carried out an evaluation based on the

    information.

    3. Results of the Evaluation (Overall Rating: C11

    )

    3.1 Relevance (Rating: 12)

    3.1.1 Relevance to the Development Plan of India

    At the time of the appraisal (in 1994), India was the second highest producing country after

    China for the production of raw silk with a share of 13% of the world total production13

    . With

    rapid economic growth, however, the demand for silk sharply increased and domestic

    production could not keep up with the increase in demand, so that India imported about 4,000

    tons of raw silk every year as the warp for weaving. Against this background, India placed

    importance on the development of sericulture mainly to meet domestic demand.

    In the Eighth Five-Year Plan (19921996), besides the food crop production, the Indian

    Government mentioned sericulture as an agricultural industry that can increase incomes and

    employment in areas with rainfed agriculture and poor areas, in particular, those for the

    small-scale farmers.

    At the time of the ex-post evaluation, the Twelfth Five-Year Plan (20122017) states that the

    annual production of silk should increase to 32,000 tons by 2017, assuming that it would

    increase by 7.14% every year14

    . To achieve this target, it is necessary to organize farmers

    associations to create a multiplier effect between Research and Development/technical transfer

    and the promotion/production processes of the companies. In addition, in the 2014 annual plan,

    11 A: Highly satisfactory; B: Satisfactory; C: Partially satisfactory; D: Unsatisfactory. 12 : High; Fair; Low. 13 India produced 14,579 tons of raw silk in 1994. 14 According to the Central Silk Boards 2013 material entitled The Sericulture Industry in India, the provisional

    production of raw silk in 2011 was 23,060 tons.

  • 5

    the Chhattisgarh Department of Sericulture specified three objectives: employment creation

    through cocoon production and reeling/spinning; the supply of silk to local silk textile

    manufacturers; and meeting the demand for silk in India and abroad.

    As described above, the Indian Government has continued to place importance on the

    promotion of sericulture in its development plans since the ex-ante evaluation. Therefore, this

    project is highly relevant to the development plan.

    3.1.2 Relevance to the Development Needs of India

    At the time of the appraisal, in the target seven districts in the State of Chhattisgarh, there

    were few industries other than those based on a single crop of rice, and the average poverty

    rate15

    was 75%. In addition, Schedule Caste and Schedule Tribes16

    accounted for about a half

    of the total population. Most of the households below the poverty line belonged to the Schedule

    Caste and Schedule Tribes. Therefore, it was highly necessary to provide the jobs for the poor

    people in the districts which enable them to be independent in a sustainable manner. Sericulture

    is particularly suitable as a means to achieve poverty reduction, because it enables the farmers to

    gain higher incomes with small investment, compared to other agricultural activities. In addition,

    it is regarded to be suitable for women because it mainly require delicate and detailed operations.

    At the time of the ex-post evaluation, the State of Chhattisgarh is one of the poorest states in

    India. Therefore, there is a great need for economic development on behalf of the poor17

    .

    It was confirmed beforehand that, in addition to such clear development needs, there is

    demand for silk yarn, a precondition for the feasibility of this project. Moreover, it has been

    confirmed since then that this demand has continued to remain high. According to the Indian

    Governments statistical information, the production of raw silk from tasar silkworms in the

    State of Chhattisgarh increased 2.1 times between 2004 and 201218

    . In India as a whole, it

    increased 5.4 times and imports of raw silk account for about a half of the domestic production

    of all types of raw silk19

    . Because trends in production and imports correspond to the demand, it

    can be inferred that the demand for tasar silk, a precondition for this project, was certain to

    exist.

    Therefore, at the time of both the ex-ante evaluation and the ex-post evaluation, the

    development need for sericulture was high.

    15 The ratio of population that belongs to families with annual income less than 11,000 rupee (FY 1994). 16 The Scheduled Castes are the castes authorized to be protected under the Constitution of India. The Scheduled

    Tribes are the indigenous people recognized under the Constitution of India. Reservation systems for the seats in the

    national and state assemblies, education, etc., exist on behalf of both the Scheduled Castes and Scheduled Tribes. 17 According to statistics in FY20112012, the ratio of poor people to the population of the State of Chhattisgarh is

    39.93%, which is higher than any other state in India (Source: Press Note on Poverty Estimates, 201112, July

    2013, Planning Commission). 18 It increased from 145.2 tons in 2004 to 298.6 tons in 2012 (Source: Chhattisgarh Department of Sericulture). 19 It increased from 322 tons in 2004 to 1,729 tons in 2012 (Source: Central Silk Board).

  • 6

    3.1.3 Relevance to Japans ODA Policy

    According to Japans policy for ODA to India established in 1995, poverty reduction is

    one of the priority fields together with economic infrastructure development and

    environment conservation. One of the priority subfields of poverty reduction is agricultural

    and rural development, including agricultural infrastructure development. Since this project,

    which contributes to poverty reduction through agricultural development, is consistent with the

    important issues specified in Japans policy for ODA to India, it is highly relevant to Japans

    ODA policy.

    This project has been highly relevant to the countrys development plan, the target areas

    development needs, as well as Japans ODA policy. Therefore its relevance is high.

    3.2 Effectiveness20

    (Rating: )

    3.2.1 Quantitative Effects (Operation and Effect Indicators)

    Although, at the time of the appraisal, clear operation and effect indicators had not been set

    for this project, the outcome expected under this project is expansion of the production of tasar

    silk. With regard to this outcome, it was judged that it is appropriate to evaluate it using the

    indicators related to the production of tasar silk that have been specified in the revised Detailed

    Project Report (hereinafter referred to as DPR)21

    . Table 1 shows the targets and results of the

    indicators. The following are the achievement rates of the initial target values of the main

    outcome indicators:

    Production of tasar silkworm seeds: 38% Production of cocoons: 17% Production of silk yarn and spun yarn: 49%

    20 Sub-rating for Effectiveness is to be put with the consideration of the Impact. 21 After the beginning of this project, project management consultant engaged in the project prepared a DPR in May

    1999. The DPR was revised in November 2000.

  • 7

    Table 1: Targets and Results of Indicators Related to Production of Tasar Silk

    Item

    Target*1

    (2006:

    scheduled

    year of

    project

    completion)

    Results Perfor

    mance *3

    2003

    2009*3

    (2 years

    after project

    completion)

    2010 (3 years

    after project

    completion)

    2011 (4 years

    after project

    completion)

    2012 (5 years

    after project

    completion)

    2013 (6 years

    after project

    completion)

    1. Sericulture

    (1)

    Production

    of cocoons

    (000) *2

    94,463 1,862 15,628 14,166 15,412 13,366 13,427 17%

    2. Total

    production of

    seeds

    (00,000)

    27.33 0 10.32 12.82 11.75 13.59 12.06 38%

    3. Process

    after cocoon

    production

    (tons)

    (1) Silk yarn 87.04 19.23 55.84 73.23 66.71 67.51 52.47

    (2) Spun yarn 54.96 4.62 13.40 17.58 16.00 16.20 34.98

    Total 142.00 23.85 69.24 90.81 82.71 83.71 87.45 49%*4

    Note: *1. Source: revised DPR.

    *2. The revised DPR calculated the production of cocoons, including the impact of this project on the existing

    plantations. However, because data on the existing plantations is difficult to collect and is not so influential, the

    figures are limited to new planting.

    *3. According to the Economic Cash Flow specified in the revised DPR, it was assumed that the project effects would

    be fully developed two years after the completion of the facilities. Therefore, the performance was calculated by

    dividing the results of two years after the completion (2009) by the target.

    *4. The target of 142 tons is a value for the entire project area. It means that consideration was given to not only the

    reelers/spinners who use the machines installed under this project, but also those for traditional reelers/spinners (not

    using the machines installed under this project). If the target is limited to the direct beneficiaries for the purpose of

    the calculation of performance, the target and the result (2009) are 45 tons and 35 tons, respectively. In this case, the

    performance is 78%. (The source for the target is the revised DPR, while the source for the result is the results of the

    interviews with the executing agency.)

    The following are comparisons between the plan and the results according to the basic

    production processes of tasar sericulture (1. Planting of trees 2. Production of seeds 3.

    Production of cocoons 4. Production of silk yarn and spun yarn):

    1. Planting of trees: Trees have been planted on 4,000 hectares by 2003 as planned. However, of the 4,000 hectares of the planted area, only 2,600 hectares remained in

    2013. The loss of 1,400 hectares was mainly due to the natural death of the feeding

    trees and airborne ash deposition22

    . It is inferred that 7080% of the lost trees were

    due to natural death. The main reason for this is that the Department of Sericultures

    22 According to an interview with the executing agency, the ash came from smoke emitted into the air from the

    chimneys of the neighboring steel plants or coal thermal power plants. Because they seem to fulfill the emissions

    standards in India, the executing agency has not made any special protest or proposal. As an alternative measure, the

    executing agency has planted trees in 1,529 hectares for tasar sericulture in areas where it is difficult for the ash to

    impact on these plants.

  • 8

    payment of maintenance expenses ended four years after the planting23

    , however, the

    sericulture farmers could not fully pay the maintenance expenses afterwards. As a

    result, there was a shortage of money for fertilizers, and the necessary nourishment

    was not given to the feeding trees. With regard to the remaining 2,600 hectares, the

    quality and quantity of the feeding trees was also inadequate due to the lack of

    nourishment.

    2. Production of seeds: The planned amount of 2.73 million seeds consisted of 1.8 million seeds for this project and 930,000 seeds for other purposes. In reality (in 2009),

    the production of seeds was only 1.03 million, which consisted of 570,000 for this

    project and 460,000 for other purposes. Only 57,000 seeds were supplied for this

    project because the number of seeds actually necessary for this project was far lower

    than planned. The reason why the number of supplied seeds was lower than planned

    was not because the seed stations production and supply capabilities were

    insufficient.

    3. Production of cocoons: In 2009, the production of cocoons was 15.63 million, only 17% of the planned amount of 94.46 million. The main reasons are as follows: 1) the

    above-described decrease in the planting area of feeding trees for tasar silkworms; 2) a

    decrease in the number of seeds as input; and 3) the underdevelopment of the

    silkworms.

    With regard to 2), although it was assumed that 450 seeds would be distributed per

    hectare, the actual number of distributed seeds was about 200. With regard to 3),

    although it was initially assumed that the production of cocoons would be 50 cocoons

    per silkworm seed, the actual number was only 25, a half of the assumed number.

    Moreover, 2) was caused by a decrease in demand for seeds because of a decrease in

    the amount of feeding tree leaves and the immature sericulture skills of the farmers; 3)

    was caused by not only the immature sericulture skills of the farmers, but also the

    problematic quality of the feeding tree leaves. According to a sericulture expert, both

    2) and 3) were caused by the poor maintenance of the planted trees and problematic

    sericulture skills.

    4. Production of silk yarn and spun yarn: Although the initial target was 142 tons, the production of silk yarn and spun yarn in the seven project districts was actually 69

    tons in 2009. In terms of raw materials, it was estimated that 18 tons were made from

    cocoons produced under this project, while 51 tons were made from cocoons produced

    in other areas.

    Given the number of reelers/spinners24

    , their production level through the use of the

    machinery provided under this project was estimated to be about 35 tons. Therefore,

    23 Based on the preliminary analysis (which was carried out when the revised DPR was prepared), it was predicted

    that if the number of cocoons were produced as planned, the income from this would make it possible for sericulture

    farmers to pay maintenance expenses. According to the revised DPR, a micro-level simulation was carried out on

    how each farmers income and expenditure levels would change if the Department of Sericulture paid maintenance

    expenses for several years just after the completion of planting until the production become stable. However, the

    incomes of the sericulture farmers do not seem to have increased as simulated, and confirmation as to whether the

    farmers had the intention to pay maintenance expenses seemed insufficient. Concretely, according to the simulation,

    the introduction of sericulture would increase each farmers income by about 11,000 rupees, from which the

    additional cost of about 3,000 rupees for sericulture (mainly, expenses for fertilizers and pesticides) would be paid.

    However, because the increment was only about 8,000 rupees per farmer, the farmers hardly paid even the fertilizer

    expenses. According to an interview survey, one beneficiary farmer said that such a level of increment did not enable

    them to pay fertilizer expenses (which would require an increment of about 20,000 rupees). 24 There are two types of spinning: reeling (weaving of yarn from normal cocoons) and spinning (weaving of yarn

    from broken cocoons). We mean either reeler or spinner by reeler/spinner.

  • 9

    the production capacity of the machinery provided under this project25

    seems to have

    been sufficiently used.

    In the production flow of sericulture, the causes for the differences between the initial plan

    and the results can be summarized as follows:

    Figure 1: Explanatory Chart of the Differences between the Initial plan and Results

    in the Production Flow Source: Prepared by the External Evaluator

    Note: *The result in 2013 is the planting area of 2,628 (ha) input of 200 seeds per unit hectare 25.5 (number of

    produced cocoons per silkworm seed) = 13,427,000 (number of produced cocoons).

    25 When the revised DPR was prepared, a theoretical value was calculated at 45 tons on the assumption that all the

    beneficiaries (750 people) work for 300 days.

    Initial plan Results* (2009)

    4,000 ha 4,000 ha

    (Maintenance) 2,852 ha

    Seeds:

    input of 450/ha Seeds:

    input of 200/ha

    Production of

    cocoons per seed:

    50 cocoons

    Production of

    cocoons per seed:

    27.4 cocoons

    (estimate)

    94.5 million

    cocoons 15.6 million

    cocoons

    (90 million + adjustment) Procured from

    other areas

    18 tons + 51 tons

    (Total: 69 tons) 107 tons

    (Including existing trees;

    the total target is 142 tons)

    Production

    flow

    Planting of

    trees

    Production/

    input of seeds

    Cocoon

    production

    Production of

    silk yarn and

    spun yarn

    Causes for the differences

    Shortage of nourishment due to insufficient money for fertilizers and death of feeding trees due to the impact of airborne ash deposition

    Decrease in the quantity of feeding tree leaves

    Immature sericulture skills of the farmers

    Qualitative deterioration in the feeding tree leaves

    Immature sericulture skills of the farmers

    Because the operation rate of the machinery introduced under this project is high, it is highly possible that production through the use of the machinery existing at the beginning of this project was actually much lower than planned.

  • 10

    3.2.2 Qualitative Effects26

    Although, according to the results of the questionnaire survey on the beneficiaries carried

    out during this ex-post evaluation27

    , the farmers gave a relatively high evaluation on the

    condition of leaves of the feeding trees for the silkworms28

    , the condition of the leaves is not

    good because of the lack of nourishment, and the number of silkworms per leaf area is low,

    according to an Indian expert on sericulture. However, the quality of the cocoons produced by

    the farmers is high, and the average selling price is almost the same as the standard price for the

    highest-quality cocoons in India29

    . Almost all the farmers answered that the selling price reflects

    the quality and is appropriate. Therefore, although there are problems in the quality of the

    feeding trees during the intermediate processes of the production flow, the quality of the

    cocoons is high as the final product.

    The following summarizes an analysis of the emergence of outcomes according to

    cause-effect logic:

    26 Qualitative effects of this project other than statistical data were confirmed. Concretely, the quality of the products

    and the feeding trees for the silkworm was confirmed. 27 During the nine days in late May 2014, five investigators, including a sericulture expert, carried out an interview

    survey on the beneficiary farmers in the seven target districts to investigate the effectiveness, impact, and

    sustainability of this project, applying random systematic sampling. The total number of samples was 211, consisting

    of 136 sericulture households and 75 reelers/spinners. With regard to the category of sericulture households, 32

    beneficiaries (all of whom are women) are absent and male farmers responded to the questionnaire in place of the

    beneficiaries. The female respondents can be divided by age as follows: one woman in her 10s (1%); three women in

    their 20s (3%); 28 women in their 30s (27%); 43 women in their 40s (41%); 17 women in their 50s (16%); 12 women

    in their 60s and over (12%). Their average age is 44.9. Although all the reelers/spinners are also women, three

    respondents were men (surrogate respondents). The female respondents can be divided by age as follows: two women

    in their 10s (3%); 17 women in their 20s (24%); 31 women in their 30s (43%); 16 women in their 40s (22%); four

    women in their 50s (6%); two women in their 60s and over (3%). Their average age is 35.4. 28 The number of respondents choosing Highly satisfactory, Satisfactory, Improvement needed and Very

    problematic were 43, 85, 8 and 0 respectively. 29 Quality rank A (the other ranks are B, C, D and defective).

  • 11

    Figure 2: Analysis of the Emergence of Outcomes

    3.3 Impact

    3.3.1 Intended Impacts

    The initially intended impact was the creation of employment and improvement of the

    standard of living of the poor (especially, women).

    With regard to the creation of employment, according to the executing agency, all the

    farmers and reelers/spinners participating in this project were newcomers. Therefore,

    employment was created for the number of beneficiaries involved (about 3,350)30

    . The

    qualifications for farmers covered by this project include the following: an income less than the

    poverty line; no ownership of land; and that they are female. These farmers were selected as

    30 Total of 2,600 new sericulture farmers and 750 new reelers/spinners.

    Limited-time payment by

    Dept. of Sericulture for

    maintenance expenses

    Insufficiency of absolute

    amount of farmers income

    from sericulture

    Insufficient motivation

    for maintenance

    Insufficient skills of the farmers in the

    maintenance of the feeding trees Insufficient payment of feeding tree maintenance

    expenses (mainly fertilizer expenses)

    Decrease in quality and quantity

    of the feeding trees

    Insufficient sericulture skills of the

    farmers

    Insufficient increase in the production of cocoons

    Effect

    Cause

    Insufficient maintenance of the feeding trees

    Insufficient increase in the production of

    cocoons because of the insufficient sericulture

    skills of the farmers and the lack of fertilizers

  • 12

    planned initially and the sites for planting trees for tasar sericulture were selected under certain

    criteria31

    .

    Although the target number of tasar sericulture farmers in the project districts (all of them

    were women) was 4,000, the actual number was 0 in 2000, 3,718 in 2001 and 4,984 in 2002

    (peak year). Subsequently, the number gradually declined and was 2,604 in 2013 (see Appendix

    1). Because the number of sericulture farmers should be basically one per hectare, the decrease

    in the number of sericulture farmers reflects the above-mentioned decrease in the area of

    planting trees. Although the area of planting decreased partially because the feeding trees died

    due to ash deposition from neighboring steel plants and power plants, the death of the feeding

    trees is mainly caused by the failure of the sericulture farmers to provide fertilizers or take the

    necessary care of them. According to an interview with a sericulture expert who interviewed the

    sericulture farmers and the executing agency, it can be inferred that the farmers who continued

    to conduct sericulture can maintain the feeding trees because they have used pesticides, paid

    some fertilizer expenses by managing to raise funds and take care of the feeding trees somewhat

    carefully under the guidance of the Department of Sericulture.

    Besides environmental factors, the reasons for the decline in the number of sericulture

    farmers include the failure to give fertilizers or take necessary care of them as described

    above. This seems to be because of the following: (1) the motivation for maintenance among the

    farmers is weak because they do not own the land on which the feeding trees are grown; and (2)

    the farmers awareness of the problems and basic skills required for sericulture could not be

    developed fully because training for them at the first stage of this project was insufficient.

    Therefore, the continuation of sericulture by the farmers requires the establishment of a

    system for providing a certain amount of pesticides and fertilizer, promotion of understanding

    by the farmers of the importance of the provision of pesticides and fertilizers, and the provision

    of the basic technical guidance necessary for sericulture.

    Although the current number of beneficiary sericulture farmers is about 60% of the initial

    target, the number of sericulture farmers covered by this project has almost ceased to decline

    since 2009. The number of sericulture farmers does not include the number of reelers/spinners.

    The number of beneficiary reelers/spinners covered by this project is 750 (all of them are

    women), which is in accordance with the plan specified in the revised DPR (achievement rate:

    100%).

    31 The criteria include accessibility from the house of the beneficiary farmers, flat plantation land, and a sufficient

    amount of soil.

  • 13

    In regard to improvement of the standard of living of the poor, according to the results of

    the questionnaire survey on the beneficiaries, the farmers covered by this project receive

    benefits from this project, such as an increase in income32

    and an improvement in their standard

    of living, as shown in the following tables:

    Table 2: Sericulture Farmers Change in the Standard of Living after Participation

    in This Project

    Item Highly

    improved

    Fairly

    improved

    No

    change Worsened Total

    No. of people 61 74 1 0 136

    Ratio (%) 45 54 1 0 100

    Table 3: Sericulture Farmers Concrete Items indicating an Improvement

    in the Standard of Living *1

    (Top Five Items)

    Item No. of

    people

    Ratio

    (%)

    Purchase of more food 135 99

    Receiving more medical services 129 95

    Provision of better education to the children 89 65

    Repair of the house 71 52

    Savings 55 40

    Note: **1. Multiple answers allowed.

    As shown in the following tables, the results of the questionnaire survey on the beneficiaries

    also indicates that the beneficiary reelers/spinners of this project received benefits, such as an

    improvement in food consumption and the benefits of medical services:

    Table 4: Reelers/Spinners Change in the Standard of Living after Participation

    in This Project

    Item Highly

    improved

    Fairly

    improved

    No

    change Worsened

    No

    answer Total

    No. of people 49 22 3 0 1 75

    Ratio (%) 65 29 4 0 1 100

    32 Information was collected through the questionnaire. Although the incomes of the farmers are generally on an

    upward trend, the External Evaluator refrained from calculating the average income because there are clearly

    abnormal values (including answer and interview mistakes) and because the units of the values are sometimes not

    uniform.

  • 14

    Table 5: Reelers/Spinners Concrete Items indicating Improvement

    in the Standard of Living *1

    (Top Five Items)

    Item No. of

    people Ratio (%)

    Purchase of more food 70 93

    Receiving more medical services 70 93

    Provision of better education to the children 49 65

    Increase in entertainment expenses 42 56

    Increase in the purchase of daily necessities 38 51

    Note: *1. Multiple answers allowed.

    3.3.2 Other Impacts

    1. Impacts on the natural environment

    Because negative impacts on the environment were not assumed at the time of the

    appraisal, an environmental impact survey was not regarded as necessary. Moreover, it

    can be considered that this project restored forest resources through tree planting,

    thereby contributing to prevention of the degradation of forest vegetation and the

    discharge of sediment in the rainy season.

    2. Land Acquisition and Resettlement

    Because the sites where tasar sericulture was planned are owned by the

    Department of Forests, it was not necessary to acquire private land or resettle the

    residents.

    3. Unintended Positive/Negative Impact

    At the time of the appraisal, the participation of women (consideration of gender)

    was assumed as another impact of this project. The revised DPRs Section 6

    Institutional and Social Development Plan has a heading entitled Involvement of

    Women in the Project33

    . Under this heading, importance is placed on the role of

    self-help groups (hereinafter referred to as SHG). According to the executing agency,

    womens group activities had the following effects: improvement in the sanitary

    condition of homes through the development of peoples consciousness of public

    health; development of peoples consciousness of nutrition; participation in health

    services provided by the government (such as vaccination); and improvement of

    womens status in their home.

    33 This is virtually the same as the Action Plan for the Consideration of Women, which was supposed to be

    prepared at the time of the appraisal.

  • 15

    According to the results of the questionnaire survey on the beneficiary sericulture

    farmers, almost all the respondents (135 of 136) answered that womens social

    standing improved. The following factors contributed to this improvement:34

    Table 6: Factors Contributing to the Improvement of Womens Social Standing *1

    Item No. of people Ratio (%)

    Provision of a regular job and salary 132 97

    Provision of work outside the home 101 74

    Acquisition of self-confidence

    through sericulture 95 70

    Various kinds of training 46 34

    Note: *1. Multiple answers allowed.

    Moreover, according to investigators of the questionnaire surveys on the beneficiaries, some

    women commented Although before I did not have self-confidence and could not talk with

    strangers, lifting my face, now I can talk, lifting my face, because Im earning a regular income

    from sericulture35

    and contributing to the family budget and I have become able to talk with

    my husband on an equal footing.

    As described above, there are three types of indicators related to the production of tasar

    cocoons. With regard to the rating of the project in terms of effectiveness, performance is 38%

    for the production of seeds, 17% for the production of cocoons and 49% for the production of

    silk yarn and spun yarn. Because each of the indicators is important for the production of tasar

    silk36

    , the average of the three indicators, which is 35%, is regarded as performance in terms of

    the quantitative effect (which falls under Rating 37). On the other hand, from the viewpoint of

    employment creation and poverty reduction, both of which are the ultimate objective and main

    impacts of this project, the results of employment creation (the total number of new sericulture

    farmers and reelers/spinners to whom equipment was newly provided) reached 70% of the

    planned value38

    . With regard to poverty reduction, almost all the respondents to the

    questionnaire survey on the beneficiaries answered that their standard of living Highly

    improved or Fairly improved. The ratio of those answering Highly improved is 45% for

    sericulture farmers and 65% for reelers/spinners. With regard to poor women, the target group

    of this project, almost all the respondents answered that womens social standing had improved.

    34 According to the results of the questionnaire survey on spinners, 72 of the 75 respondents also answered that

    womens social standing improved. 35 According to the results of an interview with the executing agency, if a woman of an agriculture household is

    employed as a cleaner in a project district, she can earn about 42 rupees a day. On the other hand, if the income

    earned from sericulture under this project is converted into a daily wage, it becomes about 180 rupees. 36 From the viewpoint of the actual inputs also, support is frequently given to activities related to the three indicators.

    Therefore, it cannot be said that one of them can represent the whole. 37 This is evaluated as unsatisfactory. 38 The actual value (2,604 farmers + 750 spinners) planned value (4,000 farmers + 750 spinners) = 70.6%.

  • 16

    Taking into comprehensive consideration what has been described above, the effectiveness

    and the impact are fair.

    3.4 Efficiency (Rating: )

    3.4.1 Project Outputs

    The plan and results of the project outputs are as follows:

    The table below shows the results concerning the facilities. Although some of the result

    numbers are less than planned, they are not so different from the initially planned values. With

    regard to the consulting services, all the initially planned services were carried out, except for

    the detailed design for mulberry sericulture.

    Table 7: Plan and Results of the Outputs

    Item Facility

    Initial target

    (at the time of

    appraisal *1

    )

    Revis

    ed

    DPR*2

    Revise

    d

    target*3

    Result*4

    Reason for the change

    1. Tasar silkworm facilities

    1) Tasar Plantation

    Tasar feeding

    treesha 4,000 4,000 4,000 4,000 None

    2) Infrastructure for sericulture

    Grainage

    (Mud House

    & Pairing

    Cage) (no.)

    14 15 10 10

    At the meeting in

    February 2002, ECC

    decided that the number

    of facilities should be

    reduced because the

    Dept. of Sericultures

    existing facilities could

    be used.

    P2 Station

    (no.) 4 5 3 3 Same as above

    P3 Station

    (no.) 1 0 0

    Because P3 station is

    maintained by the

    Central Silk Board and

    therefore the

    construction of stations

    was not essential for

    carrying out this project,

    it was excluded from the

    scope (although the

    initial plan aimed to

    establish the production

    flow of silkworms under

    this project, this change

    does not seem especially

    problematic).

  • 17

    Cocoon

    godown for

    each District

    (no.)

    3 3 3 3

    Facilities were not

    newly established as

    initially planned; the

    Dept. of Sericultures

    existing facilities were

    reconstructed.

    Village

    Cocoon

    Storage (no.)

    30 30 10 10

    Because the Dept. of

    Sericultures existing

    facilities could be used,

    the number of facilities

    was reduced.

    Multiend

    Reeling

    Center (no.)

    2

    (40 machines)

    500

    machi

    nes

    500

    machin

    es

    500

    machin

    es

    Although it was initially

    planned that 20 reeling

    machines would be

    installed at two places,

    the groups of reelers

    were unable to secure

    places where all the 20

    machines could be

    installed. To improve the

    capacity to reel thread,

    500 reeling machines

    were distributed to 48

    womens groups in

    accordance with ECCs

    guidelines.

    Pedal Reeler

    (no.) 150 250 250 250

    The number of machines

    was increased because

    demand for the

    production of silk yarn

    increased when the

    revised DPR was

    prepared and, as a result,

    it was necessary to

    improve the spinning

    capacity.

    Field

    Research and

    Training

    Center (no.)

    1 1 1 1 None

    Project office 1 1 0 0

    It was decided that the

    Dept. of Sericultures

    existing facilities should

    be used.

    3) Equipment

    Vehicles for

    technology

    transfer (no.)

    4 8 8

    Although it was initially

    assumed that the project

    office would have one

    vehicle and each project

    district would have one

    vehicle, the number of

    vehicles was increased

    because the number of

  • 18

    project districts

    increased from 3 to 7.

    2. Consulting services

    2-1.

    Person-months

    International

    consultants

    (person-mont

    hs)

    86 78 74 The total number of

    person-months

    decreased because some

    of the initially planned

    services were cancelled.

    Domestic

    consultants

    (personmont

    hs)

    244 182 166

    Technical

    support,

    clerical staff

    (person-mont

    hs)

    300

    According to the

    executing agency, it was

    initially planned that

    staff members within the

    Dept. of Sericulture

    would be assigned to

    this category. Because

    there is no detailed

    record of the staff

    members operations

    during the project

    period, the actual value

    cannot be calculated.

    2-2. Operations Plan Result Reason for the change

    1. Baseline survey and interviews with

    the people concerned Carried out None

    2. Review and preparation of the

    overall development plan and DPR for

    the planning of 4,000 ha of tasar and

    3,000 ha of mulberry

    Carried out None

    3. Detailed design for the planting of

    4,000 ha of tasar and 800 ha of

    mulberry

    The detailed

    design for tasar

    was carried out,

    but that for

    mulberry was not

    carried out.

    As described below in

    the text

    4. Assistance in bidding for the

    planting of 4,000 ha of tasar and 800 ha

    of mulberry

    It was carried out

    for tasar, but was

    not carried out

    for mulberry.

    As described below in

    the text

    5. Supervision of planting of 4,000 ha

    of tasar Carried out None

    6. Technical guidance and training Carried out None Note: *1. December 1997.

    *2. February 2007 (Because figures for the equipment (vehicles) were not written in the revised DPR, confirmation

    was made by an interview with the executing agency).

    *3. February 2002 (set at the ECC meeting).

    *4. February 2007 (source: project completion report).

    In this way, the quantities decreased concerning many items. This is mainly because the

    Department of Sericultures existing facilities were used. According to the executing agency,

  • 19

    neither the decrease in the number of seed stations nor the decrease in the number of rural

    silkworm warehouses had an adverse impact on this project. In contrast, to meet on-site demand,

    the number of spinning machines increased from the initial target set when the appraisal was

    carried out.

    The plan (in accordance with the revised DPR) and results of the consulting service are as

    shown in the table above. Although most of the items were carried out according to plan, neither

    the detailed design for mulberry nor the supervision of the planting of the mulberry was carried

    out. With regard to mulberry silkworms, E/S (engineering service) was planned to be carried out.

    Although activities for the formation of central seedbeds, the experimental planting of 60 ha of

    mulberry, and experimental breeding of mulberry silkworms were carried out to examine the

    feasibility of mulberry sericulture, it was finally decided in September 2001 that the detailed

    design for mulberry sericulture would not be carried out, under the agreement with JICA,

    because it was agreed that mulberry sericulture is not suitable for the project districts

    considering the discussions at the Empowered Committee of Chhattisgarh (hereinafter referred

    to as ECC)39

    , the agency for supervising this project40

    . The executing agencys judgment that

    the detailed design for mulberry silkworms should be discontinued seems reasonable also in

    light of the weak financial condition of the farmers covered by the project.

    Although the description above mainly concerns physical outputs, excluding the consulting

    services described last, this project also places importance on the strengthening of the

    capabilities and organization of people engaged in sericulture. Such non-physical outputs will

    be summarized below.

    During this project, training was planned and provided to the personnel of the Department

    of Sericulture, NGOs and sericulture farmers. The trainings conducted for each type of

    participant are as follows:

    39 In this project, the relevant agencies were coordinated by ECC, which consists of principal secretaries of the

    Department of Sericulture, the Department of Finance, the Department of Co-operatives, and the Department of

    Forests. 40 The reasons are as follows:

    A larger amount of investment in infrastructure is necessary for introducing mulberry sericulture than for introducing tasar sericulture. This is not realistic for poor farmers.

    The nature of the soil in the State of Chhattisgarh is not suitable for feeding trees for mulberry silkworms.

    Although irrigation facilities are necessary for mulberry sericulture, they have not been established in the State of Chhattisgarh.

  • 20

    1. Training for the Personnel of the Department of Sericulture

    Table 8: Outline of the Training for Personnel of the Department of Sericulture

    Training for the personnel of the Department of Sericulture was held from 1999 to

    2000. Table 8 shows the subjects and lecturers. The table also shows the number of

    participants. The participants were field officers who supervise the field staff members

    directly engaged in the provision of guidance to sericulture farmers. According to an

    executive of the executing agency, they were highly satisfied with the training. As a

    result, the participants were able to use what they learned to carry out on-site

    activities42

    . Therefore, the training seems to have indirectly contributed to the

    realization of the project effects through the provision of guidance to the farmers

    (OJT) by the field staff members.

    41 Lectures by consultants were conducted as a part of the consulting services (corresponding to Table 7, 2.

    Consulting Services, 2-2. Operations, 6. Technical guidance and training). 42 There are no detailed records on the degree of satisfaction as in the case of a questionnaire survey of the

    participants.

    Training

    subjects/lecturers Detail

    Plan Results

    No. of

    participan

    ts

    Period

    No. of

    participan

    ts

    Period

    (Subjects)

    Tasar sericulture technology

    Mulberry sericulture technology

    Organization of farmers

    Lecturers training

    (Lecturers)

    Staff members of public research

    institutes

    Consultants41

    1. Overseas

    training 8

    2

    weeks

    Cancelled during the

    process of the State of

    Chhattisgarhs

    separation and

    independence

    2. Domestic

    training by

    relevant

    institutes in

    India

    60 1

    month 60 Unknown

    3. On-site

    training 80 1 week

    None (Judged

    unnecessary)

  • 21

    2. Training for NGOs

    Table 9: Outline of the Training for NGOs

    Note: *1. NGO staff.

    *2. NGOs local coordinators.

    Training for NGOs was also held from 1999 to 2000. Table 9 shows the subjects,

    the lecturers and the participants. According to an interview with an executive of the

    executing agency, the participants were highly satisfied with the training. A concrete

    effect of the training is the participants use of what they learned in the workshops to

    provide guidance for the farmers, which contributed to the achievement of the project

    purpose to some extent at the early stage of the project.

    3. Training for sericulture farmers

    Training was planned to be given to 4,175 silkworm farmers, 250 silkworm seed

    farmers and 540 reelers/spinners for 45 days, 15 days and 60 days respectively.

    However, because construction of the technical training center at which the training

    was to be given was completed in September 2006, the final stage of the project period,

    full-scale training was hardly given to the beneficiary farmers during the period.

    Basically, only a two-day workshop was held at the early stage. The contents of the

    workshop included a summary explanation of tasar sericulture (A two-page pamphlet

    full of illustrations was used, because the beneficiary farmers cannot read or write

    much.) and encouragement of the farmers to organize themselves. In addition to the

    workshop, on-the-job instructions about actual sericulture activities were given by

    staff members of the Department of Sericulture. They have been monitoring the

    43 Lectures by consultants were conducted as a part of the consulting services (corresponding to Table 7, 2.

    Consulting Services, 2-2. Operations, 6. Technical guidance and training).

    Outline of the training Details

    Plan Results

    No. of

    participants Period

    No. of

    participants Period

    (Subjects)

    Sericulture technology Organization of farmers Marketing Accounting Management of

    co-operatives

    (Lecturers)

    Consultant43 Personnel of the

    Sericulture Dept.

    External resource person

    1. Domestic

    training by

    relevant

    institutes in

    India

    21 1

    month 21

    *1 Unknown

    2. Onsite

    training 60

    2

    weeks 60

    *2 Unknown

  • 22

    farmers work, visiting their workplaces almost every day during the sericulture period.

    At the time of the ex-post evaluation, however, the technical level of the beneficiary

    farmers is still primitive. Therefore, it cannot be said that there was sufficient guidance

    given to the beneficiary farmers44

    .

    In summary, although training was given to the personnel of the Department of Sericulture

    and NGOs and has had some effects, fullscale training was not given to sericulture farmers,

    resulting in a lack of appropriate sericulture skills.

    3.4.2 Project Inputs

    3.4.2.1 Project Cost

    The planned and actual project costs are as follows:

    Table 10: Project Cost (Currency unit: million)

    Item

    Planned cost (at the

    time of appraisal) *1

    Actual cost

    *2

    Rupee Yen Rupe

    e

    Yen

    1-1.Tasar Plantation*3

    207 705 181 485

    1-2. Supporting Facilities 179 609 61 164

    2.Procurement of Equipment 34 117 21 56

    3.Land Acquisition 295 1,006 215 576

    4.Department of Sericulture:

    Recurrent Cost for Project

    119 406 326 874

    5.Contingency 83 284 29 78

    6.Price Escalation 30 80

    7.Consultancy services 182 622 121 324

    8.Interest during construction 72 245 30 80

    Total 1,171 3,995*4 1,014 2,718

    *4

    Note: *1. Conditions for the calculation are as follows (JICA materials for appraisal):

    Date of the calculation: April 1997 Exchange rate: 1 rupee = 3.41 yen Contingency: 10.0% Price escalation: foreign currency, 2% per year: domestic currency, 8.6% per year *2. Sources: the actual costs in rupees were provided by the executing agency; those in yen were

    calculated by the use of the average rate during the loan period (1 rupee = 2.68 yen).

    *3. Concretely, labour cost (which accounts for about 50%), fertilizers, pesticides, etc.

    *4. Figures may not match the total due to rounding off.

    44 Although JICA carried out two technical cooperation projects, The Project for Promotion of the Popularization of

    Practical Bivoltine Sericulture Technology in India and Strengthening the Extension System for Bivoltine

    Sericulture in India, JICA could not use them for supporting the capability improvement of the staff of the

    Department of Sericulture and the beneficiary farmers in this project. Although bivoltine sericulture technology was

    applied for tasar in the project, the bivoltine sericulture technology in two technical cooperation projects on the above

    is for mulberry, therefore it cannot be applied for tasar.

  • 23

    Comparing the planned cost at the time of the appraisal and the actual cost in terms of yen,

    the actual cost (2,718 million yen) is lower than planned and only 68% of the planned cost

    (3,995 million yen)45

    . The reasons are as follows.

    In terms of rupees, although there was an increase in the actual cost for the Department of

    Sericultures administrative costs46

    , the total actual cost (1,014 million rupees) was lower than

    the initially planned total cost (1,171 million rupees) by 13% due to the following factors:

    Decrease in the cost of establishing the infrastructure for tasar sericulture47

    Decrease in the cost of consulting services48

    Moreover, because the yen appreciated by about 21% from the time of the appraisal during

    the implementation of the project, the ratio of the actual cost to the planned cost further

    decreased in terms of yen.

    3.4.2.2 Project Period

    This project was scheduled for 88 months from December 1997, when the L/A (loan

    agreement) was expected to be signed, to March 2005, which was the scheduled date of

    completion49

    . In reality, it took 111 months from December 1997 to February 2007. Thus the

    actual period was longer than planned and 126% of the planned one.

    The main reasons for the prolonged period are as follows:

    In November 2000, the State of Chhattisgarh, in which the project site is located, was

    separated and became independent from the State of Madhya Pradesh. After this, ECC was

    established to supervise this project, and DPR, the detailed plan for this project, was approved

    in February 2002. Because of this, various construction works, which was initially scheduled to

    start in 2000 and 2001, actually started in 2002 and 2003. Because of a delay in the approval of

    the detailed plan as a result of the separation and independence of the State of Chhattisgarh,

    there was a delay in the construction work and training activities could not be carried out in

    earnest, although there was no serious impact on planting activities in particular.

    The construction work was delayed for six to eight months because of the above reason and

    also of the following reasons. Because a hike in the prices for materials caused some successful

    bidders to withdraw, it was necessary to hold bidding for some work again. The hiking of prices

    also caused a delay in some constructors start of the construction. There was also a delay in the

    supply of materials for roofs.

    45 There was a minute increase or decrease in the infrastructure costs, which accounted for only a slight portion of

    the project costs. In addition, some portions of the consulting services were excluded. However, neither seems to

    have reached a level that required adjustment, especially in the calculation of the ratios. 46 The cost increased because it might have been underestimated and because commodity prices rose. 47 The cost was saved because existing facilities were more actively used than initially planned. 48 The cost decreased because consulting services (detailed design) related to mulberry sericulture was excluded. 49 The scheduled date of completion is defined as the date when all the project facilities are completed.

  • 24

    In this way, the project period was prolonged mainly because of external factors, such as

    stagnant project activities during the process of the states independence and the hiking of prices

    for materials.

    3.4.3 Results of Calculations of Internal Rate of Return (Reference only)

    Because the detailed process of the calculation of the economic internal rate of return

    (EIRR) at the time of appraisal was unknown, the EIRR was recalculated for this ex-post

    evaluation using the calculation method specified in the revised DPR50

    .

    Table 11: Results of the Calculation of the EIRR

    The time of

    calculation

    At the time of the

    appraisal (1997)

    Recalculation at the

    time of the ex-post

    evaluation

    1. Calculation method

    (in local currency)

    Costs: construction costs, material and

    equipment procurement costs, consulting

    costs, administrative costs, contingency,

    maintenance costs, replanting/material and

    equipment renewal costs

    Benefits: Additional benefits from an increase

    in cocoon production, additional benefits from

    the processing of cocoons into raw silk and

    silk products

    Project life: 30 years

    2. EIRR 15.9% Negative

    The recalculated EIRR is negative and is far lower than the EIRR at the time of the appraisal

    or the EIRR specified in the revised DPR. This is because, although the project cost was a little

    lower than planned, the production of cocoons was only 17% of the target, and the benefits

    greatly decreased.

    Although the project cost was within the plan, the project period exceeded the plan.

    Therefore, the efficiency of this project is fair.

    3.5 Sustainability (Rating: )

    3.5.1 Institutional Aspects of Operation and Maintenance

    This project was carried out by the Chhattisgarh Department of Sericulture.

    The project period can be divided into the start-up period and the production period. As

    planned initially, the Department of Sericulture and the consultant played central roles in the

    first half of the start-up period, while the Department of Sericulture, the sericulture

    50 According to the revised DPR, the EIRR is calculated at 17.4%. Because no data on the benefits related to the

    portion of existing trees were provided from the executing agency, the data at the time of the planning were used as

    they were.

  • 25

    co-operatives, the federation of co-operatives and NGOs supported the planting of the feeding

    trees and the production of cocoons and silk yarn in the second half of the start-up period and

    the production period51

    . Sericulture farmers formed the Sericulture Farmers Group (SFG) and

    the Self-Help Group (SHG), both of which are carrying out activities. Under this project,

    relevant agencies were coordinated by ECC, which consists of principal secretaries of the

    Department of Sericulture, the Department of Finance, the Department of Co-operatives and the

    Department of Forests.

    Since the completion of this project, sericulture has been carried out as follows:

    Figure 3: Relationships among Sericulture-related Organizations

    The role of each agency can be described in detail as follows:

    1) Department of Sericulture

    The total number of personnel of the Department of Sericulture is about 1,00052

    . Under the

    supervision of the Joint Director of the Headquarters, the Deputy Director or the Assistant

    Director is in charge of the 16 districts in the state, and guidance is given to sericulture farmers

    51 NGOs mainly gave guidance to the beneficiary farmers during the start-up period of this project, but were not

    carrying out activities at the time of the ex-post evaluation. 52 As of May 2014.

    Federation of co-operatives

    Co-operative: PSCS

    Department of Sericulture

    Sericulture farmers: SFG

    Sericulture farmers: SHG

    Each farmer

    Supervision

    Technical guidance Advice Cocoon trading

  • 26

    in each of the districts. Guidance is directly given to the farmers by field staff members of the

    Department of Sericulture53

    . They monitor the farmers work during the sericulture season,

    visiting fields almost every day. Because the number of field staff members is about 90 per

    district, each field officer is in charge of six farmers. Therefore, the number of them is sufficient.

    The Department of Sericulture also supports farmers in repairing spinning machines. In addition,

    the technical training center under the Department provides training and workshops for the

    personnel of the Department of Sericulture and sericulture farmers. The number of participants

    in training and workshops has been increasing year by year and was 1,278 in FY201213.

    2) SFG

    This is a group for the rearing of silkworms and the production of cocoons. One group is

    established in one site (the total number of sites is 155). The number of members of each SFG is

    about 17 on average.

    3) SHG

    This is a group for savings and other economic activities (for pooling a fixed amount of

    money and mutually lending money when needed). Because, in light of its economic activities,

    it is desirable to minimize the size of the organization, an SFG has been divided into two or

    three SHGs. Both the SFGs and SHGs have remained active even after the end of this project.

    4) Co-operative

    Aggregates of a number of SFGs form Primary Sericulture Co-operative Societies

    (hereinafter referred to as PSCS). PSCS are not organizations newly established under this

    project, but existing organizations in which each SFG has participated in each district. Each

    farmer sells cocoons to a PSCS, which then sells them to reelers/spinners in the district. The

    PSCS also give advice to farmers about methods of producing high-grade cocoons and provide

    small loans to farmers for the purchase of pesticides.

    5) Federation of co-operatives

    The federation of co-operatives is officially called the Chhattisgarh Khadi and Village

    Industries Board. This organizations activities are limited to the supervision of the

    co-operatives under its control.

    The following is a comparison between the sericulture system under this project and those in

    other regions of India:

    53 They are called field men or operatives.

  • 27

    Table 12: Sericulture Systems in India

    Region

    Characteristics

    Ownership of

    plantations

    Responsibility for

    maintenance of the

    planted trees

    Technical guidance to

    farmers

    1. This project Sericulture farmers

    have only the right to

    use the land.

    Responsibility

    belongs to the farmers

    (the Department of

    Sericulture gives

    financial support only

    for the initial four

    years).

    Provided by the

    Department of

    Sericulture.

    2. Other sericulture

    in Chhattisgarh

    Sericulture farmers do

    not have any official

    right to use the land,

    but are allowed to rear

    silkworms.

    Responsibility

    belongs to the

    Department of

    Sericulture.

    Somewhat

    compulsory guidance

    is provided by the

    Department of

    Sericulture.

    3. Other main tasar sericulture states

    1) Madhya Pradesh Same as 2 above

    2) Bihar, Jharkhand Plantations: belongs

    to the farmers.

    Responsibility for

    maintenance of the

    planted trees: belongs

    to the farmers.

    Provided by the

    Department of

    Sericulture with the

    participation of local

    NGOs.

    As shown in the table above, usually sericulture farmers who own plantations are

    responsible for maintaining them. If sericulture farmers do not own the plantations, the

    Department of Sericulture maintains them. This project is exceptional because farmers do not

    have ownership of plantations, but are responsible for their maintenance. According to

    interviews about examples in the main tasar sericulture states, the average income for sericulture

    farmers in the States of Bihar and Jharkhand is clearly higher than that in the project districts.

    The sericulture farmers in those states can use some of their income for purchasing fertilizers.

    Next, with regard to the system for maintaining the sericulture facilities, a person in charge

    of maintenance has been appointed for each facility. The working directive/job chart has

    specified the missions and duties of the Department of Sericultures officers in charge of

    maintenance (for details of the maintenance system, see Appendix 2). According to the

    executing agency, the number of people in charge of the maintenance of each facility has

    reached a level that is sufficient to carry out the necessary operations. In addition, according to

    the results of inspections by an Indian sericulture expert, there are a sufficient number of people

    in charge of maintenance. Although the Department of Sericulture rotates the officers in charge

    of maintenance every three to five years, the number of them is stable. With regard to the

    management of each facility, there are simple guidelines, and there is no problem in the

    procurement of spare parts.

  • 28

    With regard to the organizational aspects, as shown in Figure 3 and the description thereafter,

    the roles of the agencies related to sericulture farmers are clear and the necessary functions have

    been performed. However, this projects method whereby farmers do not have the ownership of

    the plantations, but are responsible for the maintenance seems to lack fairness somewhat and

    makes it difficult for the farmers to develop their motivation to maintain the planted trees.

    3.5.2 Technical Aspects of Operation and Maintenance

    According to the executing agency, training and OJT at the Central Silk Board and the Field

    Research and Training Center have made it possible to maintain the sericulture facilities using

    appropriate techniques. Inspections by sericulture expert in four districts have also confirmed

    that sericulture facilities have been maintained by appropriate techniques. There is no special

    problem in the actual management of the facilities. However, the skills of sericulture farmers are

    still primitive. For example, although it is usual that at the initial stage of silkworm rearing, the

    trees should be covered by nets to prevent the larvae from being eaten by birds or from being

    washed off by the rainwater, only about 20% of the farmers seem to take such measures54

    .

    While co-operatives give advice about the quality of the cocoons, the federation of

    co-operatives does not give technical guidance.

    Therefore, there are some technical issues to be improved and it is necessary to strengthen

    the guidance to sericulture farmers.

    3.5.3 Financial Aspects of Operation and Maintenance

    According to the executing agency, the budgets for the maintenance of the facilities are as

    follows55

    :

    54 This inference was made by the sericulture expert who inspected the districts, accompanying the beneficiary

    survey. 55 Because the maintenance costs limited to the facilities established under the project were not calculated after the

    completion of this project, it was difficult to extract information on the cost of maintaining the project facilities. The

    maintenance costs for sericulture facilities for the whole state have been on an upward trend for the past three years.

  • 29

    Table 13: Budgets for the Maintenance of the Facilities

    Facilities

    Four-grade

    evaluation of

    budget sufficiency*

    Measures in case of insufficient budget

    Tasar Plantation 1 There is room for the use of government

    support measures.

    Grainage (Mud House &

    Pairing Cage) (10)

    3 Not applicable

    P2 Station (3) 3 Not applicable

    Cocoon godown for each

    District (3)

    3 Not applicable

    Village Cocoon Storage

    (10)

    3 Not applicable

    CSTRI Reeling machines

    (500)

    3 Not applicable

    Pedal Reeler (250) 3 Not applicable

    Field Research and

    Training Center (1)

    4 Not applicable

    Note: * 4: Sufficient to maintain the facilities; 3: Minimum required level for maintenance; 2: Not very sufficient;

    1: Not sufficient at all.

    Although there is no special problem in the budgets for the maintenance of the facilities, the

    budget for maintaining the feeding trees for tasar silkworms is clearly insufficient. Therefore, it

    is necessary to secure the budget.

    The financial condition of each organization is as follows:

    1) Farmers

    According to an interview with the executing agency, a typical beneficiary farmer earns an

    annual income of about 29,000 rupees. Of this amount, about 8,000 rupees are from sericulture

    (this can be said to be the net income increment produced by this project). All the income

    (29,000 rupees) is said to be used for consumption. As described above, farmers are responsible

    for the maintenance of trees planted for tasar sericulture. However, farmers cannot afford to

    maintain them. In reality, benefits are paid to farmers for four years during the planting period,

    and the farmers were required to save 25% of these benefits. The saved money becomes a fund

    for the maintenance of the plantations and the interest is used for maintenance. The amount of

    annual interest is about 700 rupees per hectare, which can be used only for purchasing pesticides.

    As farmers neither have enough money nor land ownership, they lack the motivation to

    maintain the plantations and have not purchased sufficient fertilizers to maintain them.

    2) Co-operative (PSCS)

    There is no problem in particular, but the co-operatives cannot financially afford to support

    maintaining the planted trees.

  • 30

    With regard to budgets for the maintenance of the feeding trees for tasar sericulture,

    availability of the governments support measures for two schemes to plant trees for sericulture

    was confirmed during the study for this ex-post evaluation. One of them is called MG NREGA

    (Mahatma Gandhi National Rural Employment Guarantee Act), utilizing which the government

    can give financial support for wages for the replanting of trees during the first three years. The

    other scheme is the Central Silk Boards CDP (Catalytic Development Program). This financial

    support program is applied not only to the replanting of trees, but also to the maintenance of

    existing trees. Although the executing agency of this project has already applied for MG

    NREGA and replanted trees on 1,359 hectares, it will be possible to apply for CDP to support

    the maintenance of trees planted under this project.

    The entire financial condition can be summarized as follows: although the maintenance of

    sericulture facilities has no problem in particular, the financial conditions require remedies that

    enable sericulture farmers to appropriately maintain the plantations for tasar sericulture.

    3.5.4 Current Status of Operation and Maintenance

    A four-grade evaluation56

    of the operation of the facilities (eight types) was conducted by

    the executing agency. Because all are evaluated as 2nd or higher, there is no serious problem. In

    addition, appropriate maintenance of the sericulture facilities was confirmed through the

    above-described inspection of four districts by the sericulture expert. With regard to the feeding

    trees for tasar silkworms, more than six years have already passed after the completion of this

    project, and the area of feeding trees has ceased to reduce and is on a stable trend, but the

    quality of the feeding trees is still problematic due to the insufficient use of fertilizers.

    Under such circumstances, with regard to the three preconditions for the maintenance, the

    organization and personnel of the sericulture facilities are stable. The number of sericulture

    farmers is also stable, although the number has not reached the peak level. With regard to

    techniques, the sericulture techniques of the farmers in particular have room for improvement.

    However, this problem is not so serious as to threaten the sustainability, because the production

    of cocoons has been generally stable for the six years since the completion of this project. With

    regard to the financial aspects, although the maintenance of the sericulture facilities has no

    problem in particular, the farmers lack of funds for maintaining their plantations (especially

    funds for purchasing fertilizers) is problematic. However, in spite of the lack of funds for

    maintaining them, the sericulture business conditions for the farmers are not so unfavorable as

    to threaten sustainability in the near future57

    .

    56 The four grades are 4: Highly satisfactory, 3: Satisfactory, 2: Not especially problematic and 1:

    Problematic. 57 According to the results of the questionnaire survey on the beneficiaries, 105 respondents (77%) answered that

    tasar sericulture will be Sustainable in the future, followed by 25 respondents answering Dont know (18%) and

    six respondents answering Not sustainable (4%).

  • 31

    Therefore, although the operation and maintenance of the facilities established under this

    project are stable in terms of the organizational and personnel aspects, they have minor

    problems with regard to the technical and financial aspects. In addition, although the facilities

    have been maintained appropriately and the area of feeding trees for tasar silkworms has ceased

    to decline and has been stable, the quality of the feeding trees is still problematic. The

    sustainability of the effects produced by this project is fair.

    4. Conclusion, Lessons Learned and Recommendations

    4.1 Conclusion

    Because the implementation of this project is sufficiently consistent with the Indian

    Governments development plan, the target sites development needs and Japans aid policy, its

    relevance is high. Silkworm feed trees were planted as planned initially. Regarding the initially

    estimated impacts, such as employment creation and an improvement in the standard of living

    of the poor, although each of the production of seeds, cocoons, silk yarn and spun yarn are

    lower than initially planned, many poor women are able to work in sericulture and their

    standard of living is improving. Therefore, it can be judged that the effectiveness and the impact

    are fair. The efficiency is also fair, because the project costs were within the plan, while the

    project period was longer than planned. Although the operation and maintenance of this project

    is stable in terms of organization and personnel, there are problems in the technical and financial

    aspects. Therefore, the sustainability of the effects produced by this project is fair.

    In light of the above, this project is evaluated to be partially satisfactory.

    4.2 Recommendations

    4.2.1 Recommendations to the Executing Agency

    Figure 2 shows the causes for the insufficient emergence of outcomes under this project.

    Because the provision of financial support to the farmers for planting ended when the

    production of cocoons had still not reached a sufficient level, and because the weak motivation

    of the farmers to carry out maintenance due to their insufficient incomes and their lack of

    ownership of the planting sites, maintenance budgets became insufficient, resulting in a

    decrease in the quality and quantity of the feeding trees. The inadequate skills of the farmers

    due to a lack of training also resulted in sluggish growth in the production of cocoons. In states

    other than project ones, however, there are cases where sericulture farmers own the plantations,

    earning higher incomes and managing to purchase fertilizers. Moreover, according to the

    sericulture expert, an increase in the investment per hectare by only 2,000 rupees will have a

    considerable effect. Thus, the potential for the expansion of production seems great in the

    project site. It is therefore desirable to improve technical guidance to the farmers by introducing

  • 32

    government financial support for maintenance, such as CDP, standardizing the minimum

    necessary maintenance operations in the form of a checklist and thoroughly teaching how to use

    the checklist through training or on-the-job instruction.

    4.2.2 Recommendations to JICA

    JICA should encourage the Department of Sericulture to provide government support for the

    maintenance budget.

    4.3 Lessons Learned

    1) Necessity for the establishment of effective maintenance systems at a planning stage

    The reasons for an insufficient maintenance budget for feeding trees in this project are

    farmers insufficient incomes owing to sluggish growth of cocoon production, weak

    motivation of the farmers due to their lack of ownership of the planting sites, inadequate skills

    of the farmers, as well as the Department of Sericulture gave financial support for the

    maintenance of feeding trees for only limited time.

    Therefore, at the stage of preparing the detailed plan in the future projects in sericulture

    sector, it is necessary to consider how the parties concerned should share responsibilities over a

    certain period, taking into consideration the situation of plantation and land ownership,

    capability of cost shouldering, technical guidance and also cases in other states.

    2) Necessity of training of new sericulture farmers

    At the early stage of this project, the initially assumed full-scale training was not given to

    the farmers. Only two-day workshops and OJT after tree planting were conducted. Therefore,

    newcomer sericulture farmers only partially carried out the basic operations needed for

    sericulture. Because such insufficient technical guidance seems to have impeded the realization

    of the effects, it will be necessary to strengthen the training of farmers (especially at the early

    stage) when a similar project is carried out in the future.

  • 33

    Appendix 1

    The following table shows the trends in the number of beneficiary sericulture farmers (tasar)

    and the number of sericulture farmers in the whole of the state (tasar):

    Table: Trends in the Number of Tasar Sericulture Farmers

    Year

    Number of tasar

    sericulture farmers

    in the project site

    Number of tasar

    sericulture farmers in

    the State of Chhattisgarh

    Ratio of

    sericulture

    farmers in the

    project site to the

    state total

    2000 0 4,965 0%

    2001 3,718 6,811 55%

    2002 4,984 8,430 59%

    2003 1,582 7,832 20%

    2004 3,047 9,098 33%

    2005 2,735 9,124 30%

    2006 3,320 9,709 34%

    2007 3,503 11,604 30%

    2008 3,103 8,057 39%

    2009 2,754 7,434 37%

    2010 2,567 6,881 37%

    2011 2,278 8,179 28%

    2012 2,606 8,729 30%

    2013 2,604 n.a. n.a.

    Source: Chhattisgarh Department of Sericulture

    According to the executing agency, the number of sericulture farmers changed frequently

    and has not become stable because of the following (the numbers of farmers in the table are not

    annual averages, but numbers counted at specific points in time):

    People left their homes to work in factories.

    Withdrawal from sericulture because of the weather. (If the