  • Semi-Annual Evaluation Report S1/2015

    E G E C Q a t a r

    1 1 0 D - R i n g R o a d , D o h a , Q A T A R

    ( + 9 7 4 ) 4 4 6 4 3 1 3 5 / 4 4 3 6 3 6 9 0

    Prepared by Osama Shawky May 2015

  • EGEC Qatar | Semi-Annual Evaluation Report 1

    Contents

    1. Executive Summary ....................................................................................................................... 3

    2. Terms of Reference ....................................................................................................................... 4

    2.1. Preface ................................................................................................................................... 4

    2.2. Why are we evaluating? ........................................................................................................ 5

    2.3. What are we evaluating? ....................................................................................................... 5

    2.4. How are we evaluating? ........................................................................................................ 6

    2.4.1. Activity-Based Costing .................................................................................................... 7

    2.4.2. Employee Performance Evaluation ................................................................................ 9

    2.5. How will the evaluation be managed? ................................................................................ 10

    3. Findings and Recommendations ................................................................................................. 11

    3.1. Using Attributes while defining Spaces in Master-planning ............................................ 11

    3.2. Use DIESEL Expressions for Attributes and Dynamic Blocks ............................................... 12

    3.3. Use BatchInEditor for batch processing of drawings .......................................................... 13

    3.4. Revitology experts affirm that Revit is the future ........................................................ 14

    3.5. GSAS Green Compliance is no more an option ................................................................ 16

    3.6. Providing ELEC Loads for equipment to ELEC department ................................................. 17

    3.7. As-Built drawings ................................................................................................................. 18

    3.8. Documentation & LOG files ................................................................................................. 19

    3.9. Interpersonal skills ............................................................................................................... 20

    3.10. Becoming Part of the Research Community .................................................................... 20

    4. Sample Project Evaluation (Qetaifan Islands) ............................................................................. 21

    4.1. Background to the Project ................................................................................................... 21

    4.2. Scope of Works .................................................................................................................... 21

    4.3. Project Main Objective ........................................................................................................ 21

    4.4. Critical Success Factors ........................................................................................................ 22

    4.5. Outputs ................................................................................................................................ 22

    4.6. Resources Management ...................................................................................................... 22

    4.7. Evaluation ............................................................................................................................ 22

    5. Status of Current Projects (HVAC Department) .......................................................................... 23

  • EGEC Qatar | Semi-Annual Evaluation Report 2

    List of Figures

    Figure 1: Evaluation and Control Process ............................................................................................ 6

    Figure 2: Sample WBS (Qetaifan Islands) ............................................................................................. 8

    Figure 3: Sample Evaluation Form (Revit: Links, Imports and Groups) ........................................... 10

    Figure 4: Exporting Fields data to EXCEL ............................................................................................ 11

    Figure 5: Using DIESEL expressions in AutoCAD ................................................................................ 12

    Figure 6: BatchInEditor Plugin for AutoCAD ...................................................................................... 13

    Figure 7: Revit model proposed for the generator room in Al-Jassimeya project .......................... 15

    Figure 8: GSAS Calculators ................................................................................................................. 16

    Figure 9: ELEC Loads of Mechanical Equipment using unprintable layers ........................................ 17

    Figure 10: Sample As-Built drawing for a Chiller plant ...................................................................... 18

    Figure 11: Sample Folder Hierarchy of inputs (Qetaifan Islands Project) .......................................... 19

    Figure 12: Planned vs extended working days in Qetaifan Islands .................................................... 21

  • EGEC Qatar | Semi-Annual Evaluation Report 3

    1. Executive Summary

    This report provides an analysis and evaluation of the current and prospective progress of

    activities performed in the first and second quarters of 2015. The outcome is to find a

    strategic fit between external opportunities and internal strengths while working around

    external threats and internal weaknesses. This is achieved by uncovering deficiencies

    experienced, and directing the team towards tools that will help improving and

    developing some important skills.

    The main goal is to focus on improving the competitive position of our companys services

    within the consulting industry. It can be said that the essence of the strategy formulation

    is mainly divided into:

    Functional strategy: the approach a department (functional area) takes to achieve

    corporate and business unit objectives and strategies by maximizing resource

    productivity. It is concerned with developing and nurturing a distinctive

    competence to provide a company or business unit with a competitive advantage.

    Corporate strategy: Through a series of coordinating devices, a company transfers

    skills and capabilities developed in one unit to other units that need such

    resources. In this way, it attempts to obtain synergy among numerous business

    units so that the corporate whole is greater than the sum of its individual business

    unit parts.

    The intent is to issue this evaluation report on a biannual basis, to ensure success of our

    mission.

  • EGEC Qatar | Semi-Annual Evaluation Report 4

    2. Terms of Reference

    2.1. Preface

    In this section, aspects of the evaluation process will be defined. The process is composed

    from four basic elements:

    Environmental scanning is the monitoring, evaluating, and disseminating of

    information from the external and internal environments to key people within the

    corporation. Its purpose is to identify strategic factorsthose external and

    internal elements that will determine the future of the corporation.

    Strategy formulation is the development of long-range plans for the effective

    management of environmental opportunities and threats, in light of corporate

    strengths and weaknesses. It includes defining the corporate mission, specifying

    achievable objectives, developing strategies, and setting policy guidelines.

    Strategy implementation is a process by which strategies and policies are put into

    action through the development of programs, budgets, and procedures. This

    process might involve changes within the overall culture, structure, and/or

    management system of the organization.

    Evaluation and control is a process in which corporate activities and performance

    results are monitored so that actual performance can be compared with desired

    performance. Managers at all levels use the resulting information to take

    corrective action and resolve problems.

    Environmental Scanning Strategy

    Formulation Strategy

    Implementation Evaluation and

    Control

  • EGEC Qatar | Semi-Annual Evaluation Report 5

    2.2. Why are we evaluating?

    The aim of the evaluation is to analyze the activities performed throughout the different

    stages of the projects so as to identify the tedious, repetitive & time-consuming activities

    that has to be properly setup so as to speed-up the workflow. A variety of tools and

    techniques once introduced will make the workflow runs faster. Examples are not limited

    to the list hereafter:

    Eliminating Human Error by automating most of the activities.

    Limiting Human Intervention and reducing the time consumed by the activities.

    Introducing the concept of Intelligent Dynamic Update to cope effectively with

    projects changes.

    2.3. What are we evaluating?

    The following factors are being evaluated:

    Automational: elimination of human intervention and achievement of more

    efficient structuring of processes.

    Informational: capturing of process information for purposes of analyzing and

    better understanding.

    Sequential: transformation of sequential processes to parallel in order to

    achieve cycle-time reductions.

    Tracking: monitoring the status of executing processes and objects on which the

    processes operate

    Analytical : analysis of information and decision making

    Geographical: allowing the organizations to effectively overcome geographical

    boundaries

    Integrative: improvement of process performance promoting the coordination

    between different tasks and processes also thanks to common database and

    information exchange.

    Intellectual: capturing and distribution of employee expertise

    Dis-intermediating: increasing efficiency by eliminating human intermediaries in

    relatively structured tasks.

  • EGEC Qatar | Semi-Annual Evaluation Report 6

    2.4. How are we evaluating?

    By means of monitoring activities to identify the strengths and challenges of each, an

    organization can assess the quality (maturity level) of its activities. The evaluation and

    control process ensures that a company is achieving what it set out to accomplish. It

    compares performance with desired results and provides the feedback necessary for

    management to evaluate results and take corrective action, as needed. This process can

    be viewed as a five-step feedback model:

    1. Determine what to measure: The processes and results must be capable of being

    measured in a reasonably objective and consistent manner. The focus should be on

    the most significant elements in a processthe ones that account for the highest

    proportion of expense or the greatest number of problems.

    2. Establish standards of performance: Standards used to measure performance are

    detailed expressions of strategic objectives. They are measures of acceptable

    performance results. Each standard usually includes a tolerance range, which defines

    acceptable deviations.

    3. Measure actual performance: Measurements must be made at predetermined times.

    4. Compare actual performance with the standard: If actual performance results are

    within the desired tolerance range, the measurement process stops here.

    Figure 1: Evaluation and Control Process

  • EGEC Qatar | Semi-Annual Evaluation Report 7

    2.4.1. Activity-Based Costing

    Activity-based costing (ABC) is a recently developed method for allocating indirect and

    fixed costs to activities going into a product. This method is thus very useful in doing a

    value-chain analysis of a firms activities for making outsourcing decisions.

    A work breakdown structure lets project managers plan their activity based costing more

    efficiently through properly defining the following items:

    Scope: One of the key functions of the project management is to define the scope

    of the project. The challenge is to make sure that everything within the project

    scope is completed without carrying out any extra work. The WBS helps define

    scope by listing individual tasks that make up the project. The project team

    completes all the listed tasks but no additional work.

    Tasks: The main purpose of a WBS is to reduce complicated activities to a

    collection of tasks. This is important for the project manager because he can

    oversee the tasks more effectively than the complex activities. Tasks must be

    measurable and independent, with clearly defined limits. All the project work

    must be included in one of the tasks and the tasks must not include any non-

    project work.

    Schedule: Because the WBS tasks have clearly defined limits, the project

    management can determine how advanced the project is by checking which of the

    tasks are finished. Even within each task, the project management can check for

    percent completion because each task is measurable.

    Responsibility: An important part of project management is to assign

    responsibility for the work. With a WBS, the project management assigns

    responsibility for each of the tasks. The task manager is responsible for completing

    the full scope of the project on time, within the budget and with all of its planned

    functionality intact.

  • EGEC Qatar | Semi-Annual Evaluation Report 8

    Figure 2: Sample WBS (Qetaifan Islands)

    As shown in the figure mentioned here-above, each activity has a specific duration,

    starting date, ending date, with specific requirements for the activity to be done, as well

    as set of deliverables that has to be submitted by the end of each activity (either

    internally between disciplines, or externally to the client). Once the actual man-hours are

    compared against the planned (scheduled) man-hours, the bleed in resources can be

    identified, and corrective actions are undertaken.

    18-J

    an

    19-J

    an

    20-J

    an

    21-J

    an

    22-J

    an

    23-J

    an

    24-J

    an

    25-J

    an

    26-J

    an

    27-J

    an

    28-J

    an

    29-J

    an

    30-J

    an

    31-J

    an

    1-Fe

    b

    2-Fe

    b

    3-Fe

    b

    4-Fe

    b

    5-Fe

    b

    6-Fe

    b

    7-Fe

    b

    8-Fe

    b

    9-Fe

    b

    10-F

    eb

    11-F

    eb

    12-F

    eb

    13-F

    eb

    14-F

    eb

    1.1 Review of Project Scope of Works x

    1.2 Project Drawings (Layouts, Elevations, Sections ) x

    1.3 Internal Loads Parameters (People, Lighting, ) x

    1.4 Construction Parameters (Roofs, Walls, ) x

    1.5 Review of Project Requirements (GSAS, QCDD, ) x

    2.1 Define and Schedule Project Activities x

    2.2 Define Project List of Deliverables and Submission Dates x

    2.3 Define Project Responsibility Matrix for each Activity x

    3.1 Preparation of Block Load Calculations

    3.2 Preparation of Design Basis Report x x

    3.3 Request for Space/Shaft Requirements GV1 GV2 WF1 WF2

    3.4 Review of Space/Shaft Requirements GV1 GV2 WF1 WF2

    3.5 Provide ELEC Loads to ELEC Department GV1 GV2 WF1 WF2

    3.6 Provide Drainage Locations to P&FF Department GV1 GV2 WF1 WF2

    4.1 Preparation of Single-Line Layouts

    4.2 Preparation of Air & Water Risers GV1 GV2 WF1 WF2

    4.3 Preparation of Schedule of Equipment GV1 GV2 WF1 WF2

    5.1 Preparation of Detailed-Design Layouts

    5.2 Update of Air & Water Risers GV1 GV2 WF1 WF2

    5.3 Update of Schedule of Equipment GV1 GV2 WF1 WF2

    5.4 Preparation of Typical Details Drawings GV1 GV2 WF1 WF2

    GV1 GV2 GV4WF1

    GV4WF1GV2GV1

    Detailed Design

    GV1

    Schematic Design

    Preliminary Design

    GV2 WF1 GV4

    Structuring Work Breakdown

    Gathing Project Data

    Week 01 Week 02 Week 03 Week 04

    Work Breakdown Structure

  • EGEC Qatar | Semi-Annual Evaluation Report 9

    2.4.2. Employee Performance Evaluation

    Good modern personal development and evaluation extend beyond the obvious skills and

    knowledge required for the job or organization or qualification. Effective personal

    development must also consider: individual potential (natural abilities often hidden or

    suppressed); individual learning styles; and whole person development (life skills, in other

    words).

    For effective training and learning evaluation, the principal questions should be:

    To what extent were the identified training needs objectives achieved by the

    program?

    To what extent were the learners' objectives achieved?

    What specifically did the learners learn or be usefully reminded of?

    What commitment have the learners made about the learning they are going to

    implement on their return to work?

    And back at work,

    How successful were the trainees in implementing their action plans?

    To what extent were they supported in this by their line managers?

    To what extent has the action listed above achieved a Return on Investment (ROI)

    for the organization, either in terms of identified objectives satisfaction or, where

    possible, a monetary assessment.

  • EGEC Qatar | Semi-Annual Evaluation Report 10

    Topics

    Score

    Before Course

    Q1 2015

    Q2 2015

    Q3 2015

    Q4 2015

    Links, Imports, and Groups

    1. Linking AutoCAD DWG files

    2. Creating topography from a DWG link

    3. Understanding CAD inserts

    4. Import tips

    5. Create a group

    6. Mirroring groups to create a layout

    7. Creating Revit links

    8. Rotating and aligning a Revit link

    9. Establishing shared coordinates

    10. Managing links

    11. Understanding file formats

    TOTAL

    Figure 3: Sample Evaluation Form (Revit: Links, Imports and Groups)

    The figure shown here-above is a sample from learning topics related to Revit. Each time

    an employee is assigned to a new task, the features of this task should be properly

    defined so as to have way for measuring development of skills.

    2.5. How will the evaluation be managed?

    The conclusion for new/corrective actions has to be discussed with all the departments, a

    key person will be assigned responsible to assure that these actions are adopted and

    properly applied. These actions will be evaluated quarterly, and will be subject to

    continuous improvement until we reach a satisfactory level of workflow.

  • EGEC Qatar | Semi-Annual Evaluation Report 11

    3. Findings and Recommendations

    3.1. Using Attributes while defining Spaces in Master-planning

    A CAD drawing can be used to export data to another file (such as Microsoft) for others to

    use. By using attributes rather than simple text fields, very useful information can be

    exported

    Taking ASHGHAL Custom Training Center and Warehouses project as an example, it is

    required to prepare a block load calculation. By means of using attributes in the earliest

    stages of the project (Master-planning): Spaces names, descriptions and areas will be

    exported to spread sheets in which the design criteria will be applied for each space, thus

    a very close load estimation can be obtained rather than using rules of thumb. This will

    have its impact on the level of details in the design basis report which is assumed to be

    the first contact with the client. In addition, the gap between preliminary & detailed

    stages will be gapped.

    This recommendation should be addressed to our Arch. Department.

    Figure 4: Exporting Fields data to EXCEL

  • EGEC Qatar | Semi-Annual Evaluation Report 12

    3.2. Use DIESEL Expressions for Attributes and Dynamic Blocks

    Make intelligent drawings by using AutoCAD Fields. Fields are used to add intelligence to

    the drawings. Drawings can be customized with title-blocks, blocks, tables, plot stamps,

    email links, web page links and much more. When you use Fields, the text information in

    the drawing stays current reducing errors and aiding in drawing consistency.

    Taking Qetaifan Islands project as an example, the client requested to change the file-

    naming format after issuing more than 600 DWGs. Using DIESEL expressions, the

    manipulation of this enormous amount of drawings will be much easier by setting the

    attribute in only one drawing, then calling for a batch processor to apply the

    modifications for all drawings.

    Figure 5: Using DIESEL expressions in AutoCAD

    This recommendation should be addressed to our CAD department.

    The figure shown here above is an example of a file-naming structure composed of 10

    fields, of which 8 fields have to be updated for each submitted drawing. If each field

    consumes 5 seconds to be updated, then for a submission of 500 drawings, the saved

    time is:

    500 drawings X 8 fields / drawing X 5 seconds / field

    = 20,000 seconds

    5 hrs 33 mins

  • EGEC Qatar | Semi-Annual Evaluation Report 13

    3.3. Use BatchInEditor for batch processing of drawings

    BatchInEditor is a program that takes AutoCAD batch process to a new level with

    powerful built-in commands and an easy to use interface. You can run multiple

    commands on selected drawings or selected layouts, Import/Export of drawing list and

    commands list and check drawing version. Key Features:

    1. Easy to use Interface and Automated batch process.

    2. Run multiple built-in commands , lisp and scripts commands on selected

    drawings/Layouts

    3. Run multiple plot task on layouts and Model by assigning multiple page setup (PDF,

    DWF, PLT, image format and to printer).

    4. Drawing version check could be done instantly by loading drawings in the Bacth

    process.

    5. Drawing version change only could be done by setting drawing version (2000 to 2013)

    with no commands added.

    6. Import/Export of Drawing list and commands list.

    7. Supports Windows 32/64 bit AutoCAD 2012 to 2015 and Verticals

    Figure 6: BatchInEditor Plugin for AutoCAD

    This recommendation should be addressed to our CAD department.

  • EGEC Qatar | Semi-Annual Evaluation Report 14

    3.4. Revitology experts affirm that Revit is the future

    Building Information Modeling or BIM is a process and it is already having an enormous

    impact on the construction and infrastructure industry. The very face of Qatar will change

    over the next decade as work on the countrys various mega projects is undertaken and

    completed, while further advancements will be made as the vision for 2030 is realized.

    The nature and size of the projects means that Qatar has turned to Building Information

    Modelling (BIM) facilitate its building ambitious schedule.

    From Dohas Metro System to the numerous sporting stadiums, BIM will enable project

    teams of architects, engineers, building and infrastructure owners and construction firms

    to use 3D digital models to collaborate and support building projects throughout their

    lifecycle - from design and documentation to building and field support - ensuring that

    projects are delivered to the required specifications on schedule and within budget.

    In recent years, a series of high profile success stories in the Middle East has meant that

    BIM is now being viewed as a critical factor in the design, planning and construction

    stages of todays complex and ambitious architecture projects. It can also have a very

    positive effect on the whole lifecycle of a building. Future BIM Implementation Qatar is

    the essential platform in 2015 for all those involved in the architecture, design,

    construction, engineering, consulting, building and infrastructure industry in Qatar and

    the GCC to stay up-to-date on how this software and technology is facilitating future cities

    in the region.

    QP Mosques project will be our launching base for Revitology; it is requested to prepare

    6 Revit models for 6 different plots (mosque + imam house). We proposed to prepare

    one model as a sample; development of this sample will be developed in the form of a

    small workshop, so as to assist our design team getting familiar with BIM modeling. Our

    next step will be to develop the remaining 5 plots in parallel using the first plot as a guide

    (template).

    This recommendation should be addressed to our Engineering and CAD departments.

  • EGEC Qatar | Semi-Annual Evaluation Report 15

    Figure 7: Revit model proposed for the generator room in Al-Jassimeya project

  • EGEC Qatar | Semi-Annual Evaluation Report 16

    3.5. GSAS Green Compliance is no more an option

    Green building is no longer an option it is an obligation to secure the environment for

    generations to come, according to the co-founder of a sustainable engineering

    consultancy. Green building regulations and certification are driving the performance of

    buildings in the UAE and the MENA region to the next level.

    Qatars revamped its QSAS green building rating system. Re-launched under a new name,

    the Global Sustainability Assessment System (GSAS) is muscling in as Middle East- North

    Africas green standard.

    Public works authority Ashghal is the first governmental institution to fully adopt GSAS.

    Established by Emiri Decree in 2004, Ashghal has oversight of all state buildings and

    infrastructure projects in Qatar. All new government buildings including mosques, schools

    and hospitals approved as of 2012 must adhere to these green specifications.

    Ashghal Custom Training Center and Warehouses project will be our launching base so as

    to prepare for GSAS certification rather than outsources the task. The project has been

    defined as four different typologies which are:

    Commercial

    Mosque

    Light industry

    Hotel

    The project has to achieve a 3 stars certification which is quite challenging.

    Figure 8: GSAS Calculators

  • EGEC Qatar | Semi-Annual Evaluation Report 17

    3.6. Providing ELEC Loads for equipment to ELEC department

    It has been brought to our attention that the activity of providing the electrical loads of

    mechanical equipment has not been properly defined, resulting in too much frustration,

    especially after getting approval from KAHRAMAA. This has been encountered in many of

    the projects. The proposed scheme is to:

    Prepare a library of mechanical equipment. The electrical loads will be mentioned

    along with the unit name size and capacity.

    This library will be used in the preliminary design stage while the mechanical

    department is allocating spaces/shafts for MEP services.

    The ELEC loads will always be available on the mechanical drawings throughout

    the development of mechanical design. The ELEC loads will use a separate

    AutoCAD layer which will be set as unprintable.

    In case the design has to be updated/modified, Equipment affected by this deign

    change will be clouded with a Revision-cloud (Rev-01, Rev-02 etc.) so as to help

    the ELEC department to focus only on the modified equipment rather than going

    through all the plan. Again, the Revision-cloud will use an unprintable AutoCAD

    layer, with each revision having a separate layer.

    By default the ELEC department is collecting the Electrical demand from all departments,

    and locating equipment on his drawings. A preliminary coordination for equipment is

    performed, and in case of clashing between equipment from different disciplines, the

    clash is addressed so as location of equipment is rectified.

    Figure 9: ELEC Loads of Mechanical Equipment using unprintable layers

  • EGEC Qatar | Semi-Annual Evaluation Report 18

    3.7. As-Built drawings

    As built drawings are important since they are a record from which future system changes

    and/or additions can be designed. Future renovation projects will be more efficient and

    less disruptive if the as built documents can be depended upon for critical information

    such as pipe and duct routing and sizing, terminal unit locations, control system sensor

    locations, etc.

    Few of the current projects in hand are renovation projects (MMUP, Domasco, QDB,

    etc.). The design team has been disappointed with the accuracy, completeness, and

    timeliness of as built drawings they have received. The client also was disappointed

    because either he is receiving unworkable set of drawings, or the submission has been

    delayed to accommodate these design conditions.

    In case this task will be outsources, a specialized surveyor has to be assigned to the task,

    and our engineers should very the deliverables on site, otherwise, EGEC design team will

    inherit the deficiencies encountered in these drawings.

    Figure 10: Sample As-Built drawing for a Chiller plant

  • EGEC Qatar | Semi-Annual Evaluation Report 19

    3.8. Documentation & LOG files

    Proper documentation procedures have to be followed by the Project Coordinator:

    LOG files should be instantly recording activities of receiving new inputs, and

    submission of new deliverables.

    New inputs should be located on the server, even if is a simple drawing, and not to

    be sent to individuals by email.

    Folder name has to specify the date of the input, the description and the sender.

    The input folder write permission is only granted to the Project Coordinator.

    The Project coordinator has the responsibility of updating the XREFs as per the

    new input, and notifying the MEP team so as to update their works accordingly.

    Folders Hierarchy should be the same for all projects, so as to facilitate the hand-

    over process, and for ease of information tracking.

    Contacts of Key persons (Client, Contractor, etc.) have to be documented along

    with Project information.

    Handover procedure should be clearly defined, and controlled.

    Figure 11: Sample Folder Hierarchy of inputs (Qetaifan Islands Project)

  • EGEC Qatar | Semi-Annual Evaluation Report 20

    3.9. Interpersonal skills

    Personal development is a lifelong process. Its a way for people to assess their skills and

    qualities, consider their aims in life and set goals in order to realize and maximize their

    potential.

    The CAD draftsmen are identified to nee for improvement pertaining to one's level of

    personal quality. Video Training materials will be provided to them covering basics,

    drawing techniques as well as advanced techniques. For those of them who didnt

    encounter real MEP works in their experience, site visits should be scheduled so as they

    get familiar with the systems as well as the equipment. It is also suggested that they

    should attend the as-build exercise, with the plan to rely on them in the future for

    carrying this task out.

    3.10. Becoming Part of the Research Community

    Publishing your ideas is important for several reasons: it gives you a source of feedback

    from people who read your papers; it establishes you as a member of the research

    community; and it forces you to clarify your ideas and to fit them in the context of the

    current state of research in your field.

    Breaking into the research community requires attending conferences, meeting

    established researchers, and making ourselves known. Just going to conferences and

    standing in the corner isn't enough. Especially if we are not normally outgoing

    participants, we have to make a conscious effort to meet and build relationships with

    other researchers. Presenting papers is a good way to do this, since people will often

    approach us to discuss our presentation.

    If someone expresses an interest in our work, we follow up! Send them e-mail talking

    about new ideas or asking questions; send them drafts of papers; ask them for drafts of

    their papers and send them comments. Maintain the relationships we form via e-mail,

    and by re-establishing contact at each workshop or conference we attend. If we work at

    it, and use our initial acquaintances to meet new people, we will find that our network

    grows rapidly.

  • EGEC Qatar | Semi-Annual Evaluation Report 21

    4. Sample Project Evaluation (Qetaifan Islands)

    4.1. Background to the Project

    Owner: LREDC (Lusail Real Estate Development Company,)

    Tender Complete Title: Design Consultancy & Pre-Contract Quantity Surveying

    Services for Qetaifan Islands Villas and Apartment Blocks

    Total Plot Area: Approx. 370,000 m2

    Land Use: Luxury Villas (Waterfront and Garden & Middle Villa) and

    Luxury Apartment Blocks

    Total Built Area: Approx. 218,000 m2

    4.2. Scope of Works

    Prepare the necessary Design Drawings (excluding SPECS, BOQ, tender documents and

    bid analysis) for the MEP works, defined as follows:

    2 types of Waterfront villa

    2 types of Garden & Middle villa

    1 types of Apartment Block

    Follow up to obtain the related authorities permits (DC1, DC2, and QCDD).

    4.3. Project Main Objective

    The objective was to prepare and submit the MEP design in 28 days, the design for the

    villas was completed and submitted in 114 days.

    Figure 12: Planned vs extended working days in Qetaifan Islands

    25%

    75%

    Project Duration

    Planned

    Extension

  • EGEC Qatar | Semi-Annual Evaluation Report 22

    4.4. Critical Success Factors

    The assigned team exhibits flexibility & commitment, sharing willingly all the information,

    knowledge and experience. In such a dynamic and face-pace project, the team has

    successfully issued ~40 official submissions (Around one submission each three days). All

    of the above mentioned submissions met their submission dates.

    4.5. Outputs

    More than 600 MEP design drawings are issues for Qetaifan Islands project.

    4.6. Resources Management

    The project consumed 400% the planned man-hours due to the following main reasons:

    Architectural drawings were not frozen, and they were continuously subjected to

    modifications.

    MEP requirements Space/Shafts were not considered in the Architectural design

    and it took so much time so as to be implemented.

    Information such as interior design, false ceiling layouts, landscape, kitchens,

    laundries were not provided in the early stages of the project.

    Technical specifications were not part of the scope, but according to top

    management instructions, we added the specifications to our scope.

    4.7. Evaluation

    Projects in which Architectural design is carried out by others, MEP requirements should

    be addressed clearly at the early stages of the project so as to avoid bleeding unnecessary

    man-hours.

  • EGEC Qatar | Semi-Annual Evaluation Report 23

    5. Status of Current Projects (HVAC Department)

    Task Action (By)

    ??? :: Al-Bustan (The Avenue Office building)

    The tie in points has changed and the external MEP

    needs to be redesigned to accommodate that change.

    We are requested to study, evaluate, and submit request

    for variation.

    Changes will not affect the HVAC design (-)

    157 :: Ali Al-Kuwari Villa extension

    Architecture and MEP design review & obtain the

    required municipal approvals in order to obtain the

    required modified final building permit.

    For MEP, As-built drawings from client are not received.

    MEP review shall be carried out after

    receiving necessary documents (-)

    002 :: Al-Jassimeya Tower

    Provide new proposal (along with calculations) for the

    generator room, and the pump room, to cover the

    comments received from Qatar Civil Defense.

    Action plan for remaining site activities has to be

    prepared. Facility management personnel as well as

    client representative have to attend any future hand-over

    inspections.

    Proposal has been provided (along with a

    Revit model for the generator room). The

    proposals got approved from QCDD (-)

    Action plan shall be carried out by site team

    (-)

    097 :: Al-Khoor Park

    Review and implement the clients comments on

    preliminary design package.

    Awaiting Detailed design to be reviewed

    (Wael Hassan)

    159 :: Al-Muraikhi Private Villa

    Provide requirements to be taken into consideration in

    preliminary stage.

    Provided on 19-Apr-2015 (Wael Hassan)

    139 :: AWQAF Design & Supervision at Meshireb

    Update MEP design and provide BOQ. Provided on 4-Mar-2015 (Abdullah ElAwady)

    ??? :: Barar Nursery

    Proceed with the FF, FA & ACMV No action required from HVAC team (-)

  • EGEC Qatar | Semi-Annual Evaluation Report 24

    Task Action (By)

    145 :: Barwa Office

    Submit MEP design to QCDD for approval. Design got approved by QCDD on 25-Feb-

    2015 (Abdullah Abo-ElAta)

    143 :: Bus Station

    Update MEP design and provide BOQ. Provided on 26-Feb-2015 (Abdullah ElAwady)

    163 :: Coast Guard

    Update MEP design. Provided on 5-May-2015 (Abdullah ElAwady

    & Wael Hassan)

    162 :: Al-Sadd Building (Saeed ElKhayreen)

    Review design drawings and prepare assessment report Provided on 9-May-2015 (Osama A.Shawky)

    156 :: DOMASCO's Workshop St.10

    Review as-build drawings provided by Concord. Reviewed on 3-May-2015 (Osama A.Shawky)

    003 :: ECQ D16

    Review and implement the clients comments on design

    package

    Reviewed and submitted on 29-Apr-2015

    (Osama A.Shawky)

    117 :: H-Compound

    Update the HVAC package as per QCDD comments, and

    provide CFD analysis for car park ventilation.

    Request for CFD analysis has been sent on

    25-Feb-2015. Awaiting results (Osama

    A.Shawky)

    ??? :: Lekhweya Car Parking

    Provide preliminary BOQ and cost estimate Submitted on 9-May-2015 (Osama A.Shawky)

    128 :: MMUP

    Update design package as per site modifications Submitted on 4-May-2015 (Wael Hassan)

    079 :: MOFA

    Review design package prior to submitting to client Reviewed and submitted on 9-May-2015

    (Wael Hassan)

  • EGEC Qatar | Semi-Annual Evaluation Report 25

    Task Action (By)

    129 :: MOI

    Review and implement the clients comments on design

    package

    Reviewed and submitted on 30-Apr-2015

    (Wael Hassan)

    ??? :: Pearl Grand Cinemas Building

    Provide load calculations Submitted on 29-Mar-2015 (Wael Hassan)

    118 :: PHCC

    Obtain QCDD approvals Design got approved by QCDD on 3-May-

    2015 (Wael Hassan & Ahmed Hamied)

    161 :: PWA 5 Mosques

    Prepare and submit the Design Basis Report Submitted internally on 25-Apr-2015 (Osama

    A.Shawky)

    150 :: PWA Custom Training Center & Warehouses

    Update the Design Basis Report as per the clients

    comments.

    Schedule a meeting for Dr. Sameh Nada to meet with

    Eng. Bibi Malik

    Start in the preliminary design & space allocation

    Awaiting the results from the meeting of Dr.

    Sameh with Eng. Bibi Malik (Osama

    A.Shawky)

    Preliminary design will start starting Sunday

    24th of May (Ahmed Abdullah)

    144 :: QDB

    154 :: Qetaifan Islands

    Submit tender packages for GV1, GV2, GV3.

    Submit tender packages for WF1, WF2, WF3.

    Reply to all Queries sent by the contractor.

    Cover all comments received from the client.

    All deliverables are submitted, and we are

    awaiting the Architectural Package of the

    apartment buildings so as to proceed with

    the MEP design (Osama A.Shawky & Others)

  • EGEC Qatar | Semi-Annual Evaluation Report 26

    Task Action (By)

    134 :: QP Mosques

    Review and update Sample drawings.

    Update Layers request.

    Submit General Details drawings.

    Submit HVAC calculations for all plots.

    Submit preliminary design for all plots.

    Submit Tag-Numbers request

    Submitted on 5-May (Ahmed Abd-ElHamied)

    Submitted on 5-May (Ahmed Abd-ElHamied)

    Submitted on 29-Apr (Wael Hassan)

    Submitted on 23-Apr (Wael Hassan)

    Submitted on 15-May (Wael Hassan)

    Pending

    115 :: Sleil Store

    Obtain QCDD approvals for ACMV. Design got approved by QCDD on 1-Jan-2015

    (Abdullah Abo-ElAta)

    149 :: Khalifa South Commercial Building

    Prepare and submit HVAC tender pakage. BOQ has to be prepared and submitted

    (Abdullah Abo-ElAta)

    142 :: Valentino

    Prepare and submit HVAC tender package. Submitted on 1-Jan-2015

    (Abdullah Abo-ElAta)