Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Eskom Presentation
27 August 2014
Select Committee on Communications and Public
Enterprises
Summer Plan 2014/15
27 August 2014
Overview
• The system outlook shows that the system will remain tight going forward and additional levers are required including OCGTs to ensure security of supply.
• Maintenance is set to increase from 9.46% to 10% based on the sustainable generation strategy and on the need to clear partial load losses, with few flexible outages
• May have to cater for higher maintenance in December including half station shutdowns for 3 of our stations. These are
• Taking the Generation strategy and predicted challenges into account there will be risks to the system and an effective Demand Reduction Protocol must be in place to manage risks should they materialise.
2014/08/25 3
Winter 2014
• The winter plan has yielded the desired results thus far. We had a better handle on the system while on the other hand managed to deal with some opportunity maintenance
• During winter we also managed to achieve the following:
• Reduced Partial Load Losses from an excess of 3500MW to 1500MW
• Connected 538MW renewables IPP winter 2014, bringing the total to 1000MW.
• Total PV installed: 460 MW
• Total Wind installed: 430 MW
• Extended STIPP and Aggreko contracts and they have delivered
• Predictable generation fleet performance still a challenge:
• UCLF cannot change quickly and can only be reduced by removing/repairing each and every damaged component in a power station
• Out of 87 coal fired generating units 32 that require major ‘surgery’ and 4 are in a critical condition
• We are confident inroads are being made to arrest UCLF.
4
Summer
• Summer poses a different challenge as the profile looks flat and our planned maintenance (PCLF) increases significantly compared to Winter
2014/08/25 6
22000
24000
26000
28000
30000
32000
34000
00
:00
01
:00
02
:00
03
:00
04
:00
05
:00
06
:00
07
:00
08
:00
09
:00
10
:00
11
:00
12
:00
13
:00
14
:00
15
:00
16
:00
17
:00
18
:00
19
:00
20
:00
21
:00
22
:00
23
:00
Summer points to note
• Table Mountain profile
• Constrained all day incl. from 6am - 10pm
• Air-conditioning, geysers & pool pumps primarily
impact demand
• Commercial, agricultural & residential customers
can make the biggest difference
Constrained all day
Base Case Assumptions
• The following assumptions were used to determine the summer power system
outlook
• Eskom’s sales forecast based on a1.3% average growth over this period.
• Best estimate of generation plant availability of 75.5% for the 2014/15
Financial Year.
• No additional renewable IPPs in this period
• OCGT use is limited to the approved Corporate Plan budget
• Contracted supply levers (STIPPs and Cross Border) are generating at an
average of 600MW
• Maintain current levels of demand levers
• While Medupi unit 06 will synchronise this year, full power will only be
available in winter 2015
• In the event of load shedding we will not allow the system to go beyond
Stage1 (routine load shedding as it is incredibly disruptive and difficult to
manage) 7
Projected System Outlook
• With the maintenance that needs to be done, the system will remain tight
• The degree of tightness will depend on the UCLF performance as well as the available capacity
• For a 6000MW UCLF the system will most likely operate in Purple, excluding OCGTs
• Purple: 3000 -4000MW short of meeting demand and reserves . All available resources required most of the day throughout the week ILS will be required during peak periods, high risk that their contract time will be reached.
• For a 6500MW UCLF the system will most likely operate in Purple and Brown, excluding OCGTs
• Brown: > 4000MW short of meeting demand and reserves, rotating manual shedding probable.
• For a 8000MW UCLF the system will most likely operate in Brown, excluding OCGTs
9
Summer Risks
Variability increases due to the following risks:
• Increased full and partial load losses:
• High vacuum load losses, especially at Matimba: ( >1000MW).
• Deteriorating coal quality impacting on plants ability to reach full load.
• Wet coal
• Below minimum coal stock days at Arnot, Kriel UG, Majuba and Tutuka
• Outage management capability and quality
• Increased outage durations due to scope creep or outage slip
• High post outage UCLF
• Insufficient diesel levels to run OCGTs and fuel oil levels
• Continuous heavy rain
• Unreliable availability of supply from HCB
Reputational risks of continual load shedding
10
Options to Close the Gap Supply
Lever Operational
Capacity (MW)
Potential
Capacity (MW)
Additional Cost
(R’m)
Comments
STIPPs 300 1643 Expires in March 2015. Extend by 2years
Aggreko 108 - Expires in March 2016
Sasol 200 2310 Available for summer
Tshwane 90 513 Available for summer
City Power 220 1052 Expires in March 2015. Extend by 2years
EDM 80 1421 Available for summer
Barges 42 266 Available for winter 2015
ZPC 47 569 Available for winter 2015
WEPS 50 -
REIPP 700 1200 - Additional 500MW from CSP,PV and Wind
in summer
TOTAL 7774
Coal Stock Days Improvement 900
TOTAL 8674
11
• Range for Domestic: R923 - R998 R/MWh
• Range for Cross-border: R1387 – R1618 R/MWh • OCGTs costs R3000 R/MWh
Conclusions
• Constraining the OCGT diesel usage to budget could result in an inability to meet the
demand throughout the remainder of FY15. If target EAF is met then low risk of load
shedding – but this cannot be ruled out due to daily variability
• If load is shed during summer it is likely to be from 06h00 until 22h00 and as per
published schedules
• To avoid load shedding - costs to mitigate depend on EAF achieved
• Opportunities to reduce outage duration and improve post outage UCLF exist.
• Post outage UCLF <10%
12
Conclusions cont’d
• Current protocols, NRS048-9, do not allow for planned load reductions due to financial
constraints.
• An alternative protocols and legislative framework is being developed
• To avoid or limit planned or scheduled load reductions could require additional use for
OCGT.
• Additional REIPPs provide an opportunity to displace the use of OCGT during the day
• Considering a country perspective, it is preferable to run OCGTs than to perform planned
or scheduled load reductions over an extended period
13
Eskom Holdings SOC Limited
New-Build Programme Update
August 2014
STRICTLY CONFIDENTIAL
• ~ 17.4GW of new capacity (6 137MW installed and commissioned) • ~ 9 756 km of new transmission network (5 524km installed) • ~ 42 470 MVA of new transmission strengthening (27 565MVA installed)
15
New Generation Capacity and Transmission Lines Leading and partnering to keep the lights on
Un
der
co
nstr
ucti
on
In
dev
elo
pm
en
t
Return-to-service
(RTS) Base load
Peaking and
renewable
Mpumalanga
refurbishment Transmission
• None • Nuclear New Build Programme
• Next Coal (Coal 3) • Biomass • Majuba Underground Coal
Gasification Demo Plant (UCG)
• Primary Energy projects (Road and Rail)
• Pilot Concentrated Solar Power (100 MW)
• Open Cycle Gas Turbine Conversion Project – conversion of Ankerlig and Gourikwa OCGT power plants to a Combined Cycle Gas Turbine (CCGT)
• Photovoltaic (own use)
• Refurbishment and air quality projects
• >60 Grid strengthening projects
• Komati (1 000 MW) • Camden (1 520 MW) • Grootvlei (1 180 MW)
• Medupi (4 764 MW) • Kusile (4 800 MW)
• Ankerlig (1 338.3MW) • Gourikwa (746 MW) • Ingula (1 332 MW) • Sere (100 MW) • Acacia relocation • Solar PV installations:
MWP, Lethabo, Kendal (1.62 MW)
• Arnot capacity increase (300 MW)
• Matla refurbishment • Kriel refurbishment • Duvha refurbishment • Grootvlei Fabric Filter
Plant (FFP) • Kriel Retrofit
• 765kV projects • Central projects • Northern projects • Cape projects
Medupi is the first coal-generating plant in Africa to use supercritical power generation technology
3 700 MW 9 564 MW 3 517.92 MW 300 MW 9 756 km
1. Date moved out after the accident at Ingula end October 2013
Synchronisation of the first units are expected as follows:
• Medupi in the second half of 2014
• Kusile in the second half of 2015
• Ingula in the second half of 20151
Medupi Power Station Project Description: Supercritical, coal-fired power station Location: Lephalale, Limpopo Capacity: 4,800MW (6 x 800MW)
16
▪ Boiler Chemical Clean is currently ongoing and is targeted for completion by the end
of August 2014
▪ First Fires are targeted for September 2014
▪ First Unit (Unit 6) Synchronization is targeted for December 2014
▪ Coal has been received on the Coal Stockyard
▪ Other activities continue to support the First Unit synchronization date.
▪ Construction progress in critical areas was hindered due to the industrial action of July
2014, with labour attendance of 40% - 70% during the period
▪ The workforce is back on site
▪ Through risk mitigation plans and re-assignment of available resources, the target for
First Unit (Unit 6) synchronization remains December 2014
▪ Additional resources have been mobilised to Unit 6 by both the boiler contractor and
control and instrumentation (C&I) contractor to mitigate any resource-driven delays
▪ Similarly, additional shifts have been introduced 24 hours a day, 7 days a week to
accelerate progress on site
▪ Eskom is working with contractors to resolve any issues which could affect the
schedule.
Industrial
Action Impact
First Unit
Synch
Mitigation to
achieve First
Synch in Dec
2014
17
Medupi: Executive Summary
Medupi Unit 6 – Key Milestones in support of First Unit Synchronization
18
Activity Name Current Target Forecast
Boiler Chemical Clean Start 7-Aug-14 7-Aug-14
Turbine on Barring (with Distributed Control System) 26-Aug-14 31-Aug-14
Chemical Clean Complete 2-Sep-14 25-Aug-14
Draught Group Test Run 13-Sep-14 5-Sep-14
First Oil Fire and Burner commissioning 29-Sep-14 30-Sep-14
First Coal Fires Start 6-Oct-14 8-Oct-14
Blow Through Start 6-Oct-14 8-Oct-14
Steam to Set (Turn on Steam) 1-Dec-14 3-Dec-14
1st Synchronization 24-Dec-14 26-Dec-14
Medupi: Pictorial Progress
19
The First Chemical Clean Injection
completed – 19 Aug 2014
Kusile Power Station Project Description: Supercritical, coal-fired power station Location: Witbank, Mpumalanga Capacity: 4,800MW (6 x 800MW)
20
▪ The boiler contractor improved boiler construction progress from 0.48%/week (March
2014) to 0.68%/week
▪ Further improvement by the boiler contractor is required to achieve the target date of
December 2015 and Eskom is addressing this
▪ Eskom continues to work with the control and instrumentation (C&I) contractor to ensure the
contractor supports the December 2015 synchronization date
▪ Eskom has also implemented additional measures to mitigate schedule risk associated to C&I.
▪ Priority areas were defined for 2014 in order to support the First Unit (Unit 1)synchronization
target date of December 2015
▪ However, the latest forecast indicates First Unit Synchronization by January 2016
▪ Stringent tracking process and recovery plans have been established by Eskom, together
with contractors, to recover the schedule and achieve the target date of December 2015
▪ A commercial strategy has been defined to increase contractors’ resources and improve their
performance
▪ In addition to the protected strikes from Metal and Engineering contractors, Eskom
experienced unprotected industrial action from Civil contractors during July 2014
▪ Disciplinary action, against Civil contractors whose workers caused disruptions, has been
taken
▪ Resources were transferred to Project Medupi in order to support Medupi’s recovery plan
▪ The workforce is back on site
Industrial
Action Impact
First Unit
Synch
Productivity
Challenges
21
Kusile: Executive Summary
22
Current Target Schedule/Forecast
To mitigate the schedule risk relating to Control and Instrumentation (C&I), an Early Works Order (EWO) has been placed in parallel to the current C&I contractor work at both Projects Kusile and Medupi
23
▪ Work in the two Inclined High Pressure Shafts (IHPS) was placed on hold after the
6 fatalities in October 2013
▪ A plan has been established to re-initiate work on the shafts
▪ Approval has been received to remove equipment and start equipping the shafts (in
progress)
▪ Dedicated teams have been staffed to fast track reviews in preparation of re-starting
work on the IHPS
▪ The enquiry by the Department of Mineral Resources, relating to the fatal incident of
October 2013 is underway at site
▪ First Unit Synchronization (Unit 3) is targeted for October 2015
▪ Two critical areas to support the First Unit Synchronization target date have been
identified: i) The completion of Upstream Waterways and ii) The completion of
Downstream Waterways as well as Surge Chambers
First Unit
Sync
October 2013
Fatalities
Update
24
Ingula: Executive summary
First Synchronisation and Commercial Operation Forecast Dates for Ingula units
FIRST
SYNCHRONIZATION U3
Ja
nu
ary
Fe
bru
ary
Ma
rch
Ap
ril
Ma
y
Ju
ne
Ju
ly
Au
gu
st
Se
pte
mb
er
Octo
be
r
Nove
mb
er
Dece
mb
er
2015
Ja
nu
ary
Fe
bru
ary
Ma
rch
Ap
ril
Ma
y
Ju
ne
2016
U 4 U2 U1
COMMERCIAL
OPERATION (COM OP.) U1 U2 U3 U4
Ju
ly
Ju
ly
Au
gu
st
25
Ingula: Overall Project Progress
26
Re-baseline due to ERA
revision
Planned
COD for U1
of June
2015
Forecasted
COD for U1 of
August 2016
Transmission Projects
27
Transmission: On target to meet the Shareholder Compact of Lines Built
28
KM LINE BUILT Jun-14
YTD Plan YTD Actual YE Plan YE Projection
Plan Actual
Northern Grid Projects: 36.4 33.7 100.1 113.5 208.8 204.9
HPM: 132kV interconnecting line, 400kV line 8.0 0.0 8.0 7.7 57.2 58.3
Kusile: Vulcan bypass, loop 1 and 2 0.0 0.0 0.0 0.0 2.0 2.0
Anglo deviation 0.0 0.0 0.0 0.0 1.5 1.5
Medupi: Section E, F, G and Medupi Masa 28.4 33.7 92.1 105.8 148.1 143.1
765kV Projects: 5.0 8.7 10.0 13.9 70.0 73.9
Kappa Turn ins 5.0 8.7 10.0 13.9 10.0 13.9
Kappa Sterrekus 0.0 0.0 0.0 0.0 60.0 60.0
Cape Grid Projects: 0.0 0.0 0.0 0.0 6.0 6.0
Mercury Mookodi 400kV line 0.0 0.0 0.0 0.0 6.0 6.0
Central Grid Projects 0.0 0.0 0.0 0.0 30.3 30.3
Eros-Vuyani 400kV line Section A and B 0.0 0.0 0.0 0.0 25.9 25.9
Verwoerdburg Loop-in Loop-out 0.0 0.0 0.0 0.0 4.4 4.4
Power Delivery Projects 41.4 42.4 110.1 127.4 315.1 315.1
Transmission: On target to meet the Shareholder Compact of MVA Installed
29
Key Issues - Projects
8/25/2014 30
Item Description Resolution
Welding
Defects
- Inadequate and/or failed Weld Procedure
Qualification Records (WPQRs) and Post Weld
Heat Treatment (PWHT) on the boilers
- Welds for which there was no evidence of PWHT
- Misalignment of the Super-Heater that resulted in
design changes
- Defective and sub-standard welds needed to be re-treated
or redone
- Contractors had to revisit and correct their quality data
books to ensure compliant and adequate quality control.
- All boiler repair work has since been completed.
Control and
Instrumentati
on (C&I)
- The contractor was not able to meet some of its
contractual requirements relating to C&I
- This posed a risk to both Projects Medupi and
Kusile and could have delayed the projects
further
- Eskom has worked- and continues to work with the
contractor to resolve identified issues within the required
timelines.
- However, an alternative supplier was contracted on the
Boiler Protection System (BPS) component for the 1st two
units of Medupi and an Early Works Order (EWO) has
been placed in parallel to the current C&I work to further
mitigate schedule delays
Safety
Performance
- Poor safety performance on sites, including the 6
fatalities at Project Ingula in October 2013
- Eskom and its contractors have implemented safety
interventions, appointed additional resources, removed
non-performing resources and changed work methods
- Safety performance and behaviour has improved
significantly
- Eskom and its contractors will continue with efforts to
further improve performance
Thank you