Agenda

• Validation deliverables• GxP Impact• Data Conversion

• Security• Standard transactions• ERP extension frameworks

• Agile, Waterfall and Spiral• Cadenced Delivery• Image Synchronisation

• Real Time Analysis• Implications of Cloud Computing

Deliverables

Implementation

Development Methodologies

HANA, Exalytics and The Cloud

Slide 3 © PharmOut 2015

Guidelines

Please contribute

Please stop me to ask a question

Please relax and enjoy yourself

Please place your phone on silent mode

Slide 4 © PharmOut 2015

Validation Deliverables

• Vendor Audit

• Validation Plan

• Business Process – models, descriptions etc.

• System requirements and Design specifications

• Risk management file

• GxP Impact assessment

• Test plans, protocols, reports

• Data Conversion – mapping, cleansing, migration

• Security Authorisations and SOPs

• Training documents

• Change management documents

• Validation certificate

Slide 5 © PharmOut 2015

GxP Impact

• Product quality

• Patient Safety

• Data Integrity

• Regulatory requirement

• Process based – process decomposition

• Transaction based

• Do we validate non-GxP processes?

Slide 6 © PharmOut 2015

Data Conversion

• Mapping

• Cleansing

• Migration

• Verification

• Selecting a sample size

• 100% verification if possible

• Impact of diacritics et al

Slide 7 © PharmOut 2015

Security

• Generic user accounts

• Wide access profiles

• Align security settings with the organisation

• Define roles for groups

• Users – segregation of duties

• User access and periodic review

• Change management – transports (Dev | QA | Prod)

• Access to sensitive functions

• Business ownership of security processes

Slide 8 © PharmOut 2015

Standard Transactions

• Select appropriate transaction codes

• e.g. MM01, MM02, MM03?

• MM01 – Create Material Master

• MM02 – Change Material Master

• MM03 – Display Material Master

• Least risk

• Daisy chaining - UI overhead

• What modules do we implement first?

• When do we decide to customise?

Slide 9 © PharmOut 2015

ERP Extension Frameworks

• SAP RICEF(W)

• Reports, Interfaces, Conversions, Enhancements, Forms

• Oracle CEMLI

• Configuration, Extension, Modification, Localisation, Integration

• Customised extensions

• Assess for GxP impact

• Can turn into a full-blown sub project

• Core Changes

• Modify standard transactions

• Invalidates warranty - unsupported

• Lost on next update

Slide 10 © PharmOut 2015

Package Slam

• Bypass the ‘as-is’ and ‘to-be’

• Consequence of fixed price implementation

• Result can be verified but not truly validated

• ‘Improvements’ continuing 1-2 years after Go-Live

• Hidden cost in ‘BAU’

• Time and Materials contract will minimise the risk

Slide 11 © PharmOut 2015

Agile vs Waterfall

• SAP – asap Oracle - AIM

• V Model = Waterfall with a kink

• Documentation maps nicely to Waterfall

• Agile is more representative of development

• Versions or ERP modules in an Epic

• Walk part way up the ‘V’

• Update requirements and tests after multi sprints

• A plan is a plan – avoid doc-centric mindset

• Reports say what we did – variance from plan

Slide 12 © PharmOut 2015

Cadenced Delivery

• Cadencing provides stability for clients

• Potential savings – known release dates

• Unfinished features pushed to next release

• Identify a suitable cadence for the organisation

Slide 13 © PharmOut 2015

Image Synchronisation

• Vital to maintain system integrity

• Manage transports across images

• Identify orphan transports

• Validated state cannot be guaranteed unless synched

• May trigger re-validation

• Part of maintaining the configuration baseline

Slide 14 © PharmOut 2015

HANA and Exalytics

• Near real-time processing

• Memory resident vs Disk based

• Not for Big Data (terabytes rather than petabytes)

• Good for:

• Optimising supply chain

• Security monitoring

• Energy use

• Network optimisation

Slide 15 © PharmOut 2015

Cloud Computing Implications

• HANA and Exalytics can utilise the Cloud

• How secure is secure?

• Life of a secure encryption algorithm – 10 years max

• Cloud providers are suppliers.

• Apply the existing standards and regulations for

handling suppliers

• Formal agreements (SLA) including GxP

requirements

• Audits

Slide 16 © PharmOut 2015

Cloud Security

• ISO 27001 – 43% of certified companies subsequently shown to

not be compliant

• Physical theft, employee mistakes (like lost devices), and insider

threats were responsible for 42.7% of 2013 data breaches in the

US.

• Computers, laptops, and company servers are responsible for

the large majority of your vulnerabilities, not the cloud.

• An enterprise data center (EDC) is 4x more likely to suffer a

malware/bot attack than a cloud hosting provider (CHP).

• EDCs and CHPs are equally vulnerable to a “vulnerability scan”

and a “brute force” hack.

• EDCs are 3x times more likely to suffer a recon and 4x an app

attack

Slide 17 © PharmOut 2015

Australian Regulations & Guidelines

2013 - National Cloud Computing Strategy

2014 – Cloud Computing Regulatory Stock Take (91 Pages)

• Competition and Copyright - 2012, ALRC Inquiry, Technology centric

• Consumer Protection - 2010, Competition and Consumer Act

• Data Protection and Privacy - 2014, Changes to the Privacy Act

• Cybersecurity - 2012, Cybercrime Legislation Amendment Act

• Law Enforcement Access - 2013, Parliamentary report

• Regulatory Burden - Over 450 pieces of legislation at present

Government policy – regulation should not be the default option

NSCCC – National Standing Committee for Cloud Computing

Breach Notification - May 2013, Legislation lapsed due to the Election