ERP Project Internal Discussion

September 12, 2013

Page 2: ERP Project Internal Discussion September 12, 2013

Agenda / Topic Discussion1. Item Coding / Equipment Coding

Conclusion: see slide# 3

2. Raw Material / Spare Part Procurement Conclusion: see slide# 4

3. Maintenance Center Conclusion: see slide# 5

4. Tuck Scale & Belt Scale (LiGu System) Conclusion: see slide# 7

5. Unify PLC Log sheet for production Conclusion: see slide# 8

6. Inter-company transaction Conclusion: It will be re-discussed with Mr. Ryan when doing operation training

7. Costing must be separated by different production line Conclusion: ratio will be provided by CFC

8. Fixed Assets management must be separated by Fixed Assets / Expense Assets. Conclusion: CFC will make discussion of a standard code rule and will update the result on Monday 16 th Sep. Accounting

dept. will be in charge for creating code rule as well as management and GA Dept. will be in charge for maintaining the transactions of assets.

9. ID & VN some report for outside need to print out the 2 languages ( Title and contents )

Page 3: ERP Project Internal Discussion September 12, 2013

1. Item Coding

• Item code rule in CFC

9 Digits 12 – 34 – 12345

First 2 digit are group (10= item with value; 20= item without value; 30= expensed item; 40= item for project; 50= Disposes item)

Second 2 digit are part category (using matrix table, separately for Plant and GA)

Third 5 digits are bin card number / sequence number)

• Currently CG (Kupang) follows CFC’s item code principles with little modification such as: only using 1 matrix table for all, there is no grouping.

• Need same item coding principles when we use integrated ERP system in group company and facing some issues such as:

- Unify item code principles that can be applied to various business unit (Cement plant, Ready Mix Concrete and Aggregate Company, Transportation, Trading)

- Item code rule should be flexible, extensibility, and easy to recognize and applicable for whole group and can be fast learn by new employ.

Background

1. It is agreed to use matrix table content in order to make it consistence and easy to extended to other business growth in future. CFC & CG will use the same table. Mr. Tony will held the meeting on Sep 16 to discuss about variant code will start from number 1 instead of adding number zero in first digit in front of existing bin card.

Discussion Results

Main Objectives:- Our Group will have same Item Coding principles

Definition:

Scope:

Principles:

1 2 3 4 1 2 3 4 5 6

Sub-Category grouping code (see matrix table in coloum)

Category Grouping Code (see matrix table in row)

- Identification of duplicated and substitutable items- Consolidation and analysis

Varian code (Sequential number to identify each item of a sub-category)

ITEM CODE PRINCIPLES

A set of rules / principles that define the systematic order of the item code in order to identify it in the system. For one item this code must be unique, and for one code it must have only one item

- Warehouse items- Semi Finished Product & Finish ProductPurpose:- Identification of items

Page 4: ERP Project Internal Discussion September 12, 2013

2. Raw Material / Spare Part Procurement

• CFC recommend PR for raw material and spare parts will be raised by users instead of W/H. Current practices are:

• Users are more familiar equipment life cycle to raise PR for purchasing the spare parts for maintenance.

• Any departments issue PR will be integrated and approved by plant director who take the whole responsibility of the plant operation.  

• W/H may more suitable to manage the inventory and ready for users only instead of play the role of integration. Hence, recommend PR will be raised by users instead of W/H in CFC

• CG (Kupang) practices are

• W/H will raised PR for all of stock items procurement like Raw material & spare part , based on defined minimum stock availability (Minimum and maximum stock warehouse availability must be setup by users together with warehouse based on estimation/historical usage)

• WH have authority to postponed on raising PR if the stock items not moving in certain period

• PR for non stock items / non warehouse items should be raised by users.

Background

1. Due to specific requirements in each country, so we proposed to have different way in CFC and CG

Discussion Results

Main Objectives:- Concept alignment on stock item procurement

Page 5: ERP Project Internal Discussion September 12, 2013

Work Centre 1

Plant Maintenance

Electrical / Instrumentation

GA (Office, Public facility, Vehicle) Maintenance

Mechanical / Workshop

Civil /Utilities

Mining and Heavy Equipment

Work centre 2

Plant Maintenance

GA (Office, Public facility, Vehicle) Maintenance

Electrical / Instrumentation

Mechanical / Workshop

Civil /Utilities

Work centre 3

GA (Office, Public facility, Vehicle) Maintenance

(i.e. Kupang, Bayah Plant) (i.e. Ciwandan, Head Office) (i.e. Cemindo)

3. MaintenanceMain Objectives:- Concept alignment on Maintenance Centre or work flow mechanism on repairing order

1. We propose all of maintenance notification (repairing note) pass through to designated functions in each Work Centre like shown on below

2. We will have some work center (or other name) for each location site which system applied. A work centre is an organizational unit where a work steps is carried out, producing an output. The work center defines where and by whom an operation is to be carried out.

3. The maintenance modules (CMMS) only applied to non CAPEX order. For Investment work (CAPEX) and/or Maintenance / repair work to improved Fixed Asset in order to extend their life time will be using Project Management Module

Page 6: ERP Project Internal Discussion September 12, 2013

Maintenance System in brief

Pick-list (to take W/H

spare parts for stock items)

Notification create by user and direct sending to the each PIC in their Work Centre (see previous page) with the following type of notification

1. Maintenance Request. (notifications will be written for the equipment that failed. User don’t know exactly problem, i.e. abnormal noise etc).

2. Malfunction Report. (notifications will be written for the equipment that failed. User already know what the problem, i.e. motor burn etc).

3. Production line stop. (notification will be written against the equipment that caused the production line to stop. The downtime in these notifications will be the duration of the downtime of the production line.

These type will determine of work priorities and calculated KPI

PIC (Person in Charge) verify notifications that requested by other departments and create maintenance order or not after verify/checked., if not requestor will be notified.Verify

Notification

Maintenance / Work Order

Maintenance Order type1. Corrective maintenance order (i.e. equipment breakdown, repair etc)2. Preventive maintenance Order (i.e. scheduled, overhaul etc)Note: Preventive maintenance triggered from schedule/planning therefore notification not required and automatic

generated from the system

Work Planning (assigning

people/technician)

Generate Purchase Req, for non stock

item or services/outsources

Maintenance orders must be planned daily, weekly, monthly, and quarterly period

In case of additional stock material required after maintenance order has been released, there will be a goods issue form to fill in and sign by leaders or above before goods issue can be processed

Maintenance Execution

Maintenance Completion

Actual information of maintenance order (e.g. man-hour, spare part used, external services used etc) must be updated into the system during maintenance works are in process and after the maintenance works are completed.

A maintenance order can be completely closed if:All relevant activities are finished.All of actual labor costs have been confirmed and settled.All relevant costs in maintenance order are captured (labor costs, external services, and materials costs) and settled.

For discussion only

Page 7: ERP Project Internal Discussion September 12, 2013

4. Truck Scale & Belt Scale

• Currently CFC have 2 system which integrated each other (LIGU System and Application System). LIGU system is weighbridge system which widely customized covering other functions such as Truck registration (scan Driver ID & truck license), ticketing, weigh tolerance, packer control panel, and monitoring the In-Plant truck movement. LIGU system in CFC is also used for belt-scale in production area.

• LIGU System well proven implemented for years and requires special customization to ensure no impacted to the daily operational.

• Currently CG have weighbridge for Kupang Plant operational and F/G Warehouses.

• CG’s weighbridge running with simple process just tools to get tare and nett weight.

Background

• It recommend TIPTOP ERP replace LIGU system for the Truck Scale & Belt scale control. (LIGU System can’t used due to basic data cannot be unified with ERP System).

Notes: Now CFC already have 12 sets Truck Scale + 7 Belt Scale, But because LIGU system is using local database, When User Dept. create the basic data for Goods / Products / Vendor / Customer can not match with the ERP system and will have different ID code.

• With considered to project scope and feasibility, it’s suggested LIGU replacing will be done later.

• CG & CFC will use truck scale to provide tare weight and net weight to TIPTOP system (weight ticket printout from ERP) and in future we will use ERP to control weight scale to include in-plant truck monitoring.

• We will run parallel the two system LIGU & ERP until TIPTOP system established and stable.

• Asking LIGU to provide open database mode.

Discussion Results

Main Objectives:- To find best solution for ERP system interface to existing system (LIGU System)

Page 8: ERP Project Internal Discussion September 12, 2013

5. Unify PLC Log Sheet

• CFC have 3 kinds of PLC data. 1st Line / 2nd Line / Hiep Phuoc Grinding Plant.

• CG have some kind of Log file data generated from Hyperion (DCS application software)

• To unify those kind of Log file data is impossible because different purposes

• Unified PLC log file data required for interface purpose between ERP system and field device.

• To unify it its impossible because different purposes. So, TIPTOP should based on different equipment to design and get the data automatically. Also have to design the interface for user can entry data manually

Background

• TIPTOP should based on different equipment  to design and get the data automatically from SQL DB of CFC & CG.

• TIPTOP should design the interface for user can entry data manually (for emergency case)

• TIPTOP provide DB template base on CG and CFC log file data then TIPTOP will generate related reports

• The log file must include production report, operation report, control room, finger-printer, gate access, telephone switch board, weight scale, belt scale, gasoline station.

Discussion Results

Main Objectives:- Unify PLC Log Sheet for system interfacing purpose

Page 9: ERP Project Internal Discussion September 12, 2013

RED word means manual input (others auto generate from system)

Customer

     S/O PR P/O      S/O P/O      S/O   

     D/N G/R     D/N G/R     D/N  

     A/R   A/P    A/R A/P      A/R   Transfer

CG AASTAR CFC

TipTop Inter-Company Transaction

Since AASTAR also manage their own customer and product (i.e. plywood & palm oil), means it's not just inter-company transaction pass through