Company Overview
• Name of Company : Ergon Power Representaciones S.A.C
• General Manager : Ricardo A. Velasco, Eng.
• Peru Offices address:
• 125 F. Bolognesi St, Office 1401 – Centro Ejecutivo Pardo, Miraflores,
Lima – Perú (GM and Commercial Office)
• Perú Telephone Central : (511) 7165907 – Tel.Fax : (511) 4466617
• Chile Office address:
• 2670 Vitacura Av, Floor 15, Las Condes, Santiago – Chile
(Commercial Office)
• Chile Telephone Central: (56 2) 8204339
• Web: www.ergonpower.com
Company Overview
• ERGON POWER is a privately held company, created mainly to provide
specialized machinery, equipment and services for energy industries.
• We have exclusive contracts and commercial agreements with
worldwide known manufacturers and the main providers of such
equipment in Latin America, Asia and Europe.
• We have always obtained from our customers complete satisfaction for
our modus operandi, our sincerity in leading them to choose the best
kind of equipment for their needs and our after sales service.
• We are also Advisors and Consultants of a very important Investors and
International Generation Companies, that are interested in taking part in
Energy Projects in Latin America or make an Investment in that market.
Energy
Representations
ERGON POWER
Harbin Electric Corporation Ltda:
(www.hec-china.com) Chinese group recognized worldwide by its
technology and quality in the manufacturing
of Electromechanical Equipment for Medium
and High Power Plants. Ergon Power is
working with Harbin in all the Latin America
Energy market with success.
ERGON POWER
ERGON POWER
China GEZHOUBA Group Corporation:
(www.gzbgj.com/english ) One of the most important EPC Contractors
in the world. Main Contractor of Three
Gorges Project.
Its business scope includes infrastructure
construction, investment, electrical
projects(with financing) and highways as well
as real estate.
ERGON POWER
SEPCO III Electric Power Construction
Corporation:
(www.sepco3.com/english.asp ) No.58 of Top 225 International Engineering
Contractors. More than 23,000MW of power
plant in operation. Contractor in model EPC,
BOO, BOOT + Financing. Its business scope
includes thermal power plants, wind farms
and Solar power plant.
ERGON POWER
Harbin Mechanical & Electric Equipment
Co. Ltd. – HMEC
Chinese commercial company from Harbin
Group (HE), Supplier all the Electromechanical
Equipments for Small and Medium Power Plant
(W2W scope). Also of factories as Harbin Boiler
Co. and Harbin Turbine Co. from thermal
electromechanical equipments.
ERGON POWER
Wuhan GuoCeSanlian Hydropower
Equipment Co.,Ltd :
:
Chinese company that is a key member of
Wuhan Guoce Science & Technology Co.
Ltd. Partner of HMEC and Specialist
Supplier of Control System for Small
Power Plants.
ERGON POWER
SanBian Sci-Tech Co.,Ltd :
Chinese company that was established in
1968, the most important manufacturer of
Transformers in the world, with annual
production capacity more than 24.000.000
kVA.
ERGON POWER
Chongqing Fengyu Electric Equipment
Co., Ltd: (www.fengyugroup.com) Top BIOMASS gasifier manufacturer with a history of
more than 24 years, Chinese biomass gasification
technology forerunner, and we own fluided-bed
gasifier patent, which available feedstock are rice husk,
woodchips, sawdust, bark, bagasse, crop stalks, olive
pomace, palm kernel shell, coconut shell, bamboo,
macadamia nut shell and other agricultural residues.
Electro Aço Altona S/A – ALTONA :
(www.altona.com.br)
Brazilian company recognized worldwide by
its technology and quality in the foundry and
manufacture of pieces and components for
manufacturing sector and electrical
generation industry
ERGON POWER
ERGON POWER
REIVAX Automation and Control :
(www.reivax.com)
Brazilian company recognized worldwide by
its technology and quality supplying
systems and solutions for the control of
energy generation and in modernization of
existing plants.
ERGON POWER
Wuhan GuoCe Nordic New Energy Co.,Ltd :
Joint venture company founded by Chinese
Wuhan Guoce Science & Technology Co.,Ltd.
and Swedish Deltawind AB. The business
scope of the company is the production, erection,
commissioning, operation, maintenance and
after-sales service of Wind Turbines
ERGON POWER
SUMEC Complete Equipment & Engineering
Co.,Ltd (www.sumec.com ) :
:
SUMEC Complete Equipment & Engineering Co. Ltd
(SUMEC-CEEC) is one of the core subsidiaries of
SUMEC Group Corporation. EPC contractor for Small
Hydro power plants, Biomass Power Plants, Wind
Power Plant, Solar Power Plant Seawater
Desalinization. Manufacturer of Gen Set for Biomass
Power Plant.
ERGON POWER
Jiangsu Antai New Energy Technology
Co., Ltd.(JAE):
:
JAE., is a joint venture established by Jiangsu Antai Power
Machinery Co., Ltd. (one of the most famous engine
manufacturer in China) and SUMEC Complete Equipment
& Engineering Co., Ltd. (a reputable International
Engineering Company). JAE is the largest low speed gas
engine and gas generator set manufacturer in China with
technology joint venture with MAN (Germany).
ERGON POWER
PHONO SOLAR Technology Co.:
:
Phono Solar Technology Co., Ltd., was founded by SUMEC
Group Corporation, a member of the China National
Machinery Industry Corporation (SINOMACH). Phono Solar
is a leading brand in the renewable energy industry,
producing high quality solar products since 2004. The
Phono Solar brand has become synonymous with high
performing, top quality photovoltaic panels and specializes
in PV technology innovation, application and system
development.
Hydro Projects
ERGON POWER
Contract in operation
• POECHOS 2 HPP (02 x 5.5 MW) - Peru
• Client: Sinersa (Private Company)
• Scope: 02 Butterfly Valves - 3.2m including commissioning
• Contractual Date: August , 2007
• BONYIC HPP (03 x 11 MW) - Panama
• Final Client: Hidroecologica del Teribe S.A.
• Scope: Harbin (HE) supplied Mechanical BoP Equipments (Francis Turbines) in
consortium with ABB. The scope include commissioning.
• Contractual Date: June, 2008
Contracts in operation
• PIAS 1 HPP (2 x 6.2 MW) - Peru
• Client: AYEPSA (Private Company)
• Scope: Harbin (HE) supplied the Electromechanical Equipments, Horizontal
Francis Turbines (without Main Transformer and electrical auxiliaries), including
erection and commissioning. ( Turn Key)
• Operation Date: October 2011
• INTERPLUS HPP (5 KW) - Chile
• Final Client: Universidad de Santiago de Chile
• Scope: Tubular Compact Turbine-Generator-Governor-Valve Group
• Operation Date: July 2011
• .
Contracts in operation
• YAUPI HPP (112 MW) - Peru
• Direct Client: REIVAX Brazil
• Scope: Erection of 5 generation groups including man power, tools, local
transportation, supervisors, commissioning and maintenance service.
• Contractual Date: Since August 2010
• MACHUPICCHU HPP (1 x 100 MW) - Peru
• Final Client: EGEMSA (Public Company)
• Direct Client: Grana y Montero (EPC contractor)
• Scope: Francis Turbine, Generator, Valves, Governor, Excitation Sys from Harbin
(HE), and Substation and Control Sys. from ABB. The scope include
commissioning of the equipments supplied
Contracts on execution
• CHUCAS HPP (02 x 25 MW) - Costa Rica
• Final Client: ICE / Direct Client: ENEL
• Scope: Harbin (HE) will supply Mechanical BoP Equipments (Francis Turbines) in
consortium with ABB. The scope include commissioning.
• Updated Situation : Contract on execution.
• SOPLADORA HPP (03 x 164 MW) - Ecuador
• Final Client: Government Project
• Scope: EPC Contract (with CGGC as EPC Contractor and Harbin (HEC) as
supplier of E&M Equipments – Francis Turbines).
• Updated Situation: Contract on execution.
• TOPO HPP (02 x 14.8 MW) - Ecuador
• Final Client: Hydrotopo
• Scope: Harbin (HEC) offered Main Electromechanical Equipments (Horizontal
Francis Turbines)
• Updated Situation: Contract on execution.
• CANCHAYLLO HPP (5.2 MW) - Peru
• Client: Empresa de Generacion Electrica Canchayllo (Private Company)
• Scope: Complete Electromechanical Equipments (02 Horizontal Francis Turbine)
from Harbin (HMEC), erection and commissioning (Turn Key)
• Updated Situation: Contract on execution.
Contracts on execution
Contracts on execution
• ITATA HPP (2 x 10.2 MW) - Chile
• Client: Electrica Puntilla S.A. (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
commissioning (Turn Key) considering Vertical Francis Turbine.
• Updated Situation: Contract on execution.
• CHAPIQUINA HPP ( 10.2 MW) - Chile
• Client: E-CL (GDF Suez – Private Company)
• Scope: Erection of governor and control systems from REIVAX, including man
power, tools, local transportation, supervisors, commissioning and maintenance
service.
• Updated Situation: Contract on execution.
Contract on execution
• Transformers Corporate Purchase(163 MVA) - Peru
• Client: Electro Oriente, SEAL, ELSE, ELSUR, ELPU, Electro Ucayali, Grupo
Distriluz (Public Company)
• Scope: Supply of 1650 transformers to all country (Sanbian factory)
• Updated Situation: contract on execution.
• Mazuko Substation (35 MVA) - Peru
• Client: ELSE (Public Company)
• Scope: Supply of transformer of 35 MVA 138/22.9/10kV, erection service and civil
works (Sanbian factory)
• Updated Situation: contract on execution.
Contract on execution
• Restitucion HPP (3 x 100 MW) - Peru
• Client: Electroperu (Public Company)
• Scope: Voltage Regulators, Excitation System of Generators with test, erection,
supervision and commissioning ( REIVAX factory)
• Updated Situation: contract on execution
• Canon del Pato (263 MW) - Peru
• Client: Duke Energy (Private Company)
• Scope: Service in site , Exciter Rings, 6 pairs
• Updated Situation: contract on execution.
Contract awarded
• SANTA MARIA HPP (750 MW) - Peru
• Client: Energia Azul (Private Company)
• Scope: EPC Contract (CGGC as EPC Contractor – 04 units x 187 MW).
• Updated Situation: EIA was approved. Energia Azul signed a MoU Agreement
with CGGC, CGGC will obtain the 96% of shares, will be the EPC Constructor and
will obtain the financial close. The construction could be beginning in year 2014.
• PIAS I HPP (3rd Unit - 6 MW) - Peru
• Client: AYEPSA (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: The client approved this project.
Contract awarded
• Hydrika 1 HPP (6.6 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies.
• Hydrika 2 HPP (4.0 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies
Contract awarded
• Hydrika 3 HPP (10 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies.
• Hydrika 4 HPP (8 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies.
Contract awarded
• Hydrika 5 HPP (10 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies.
• Hydrika 6 HPP (8.8 MW) - Peru
• Client: Hydrika Generacion SAC (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: This project are finalizing the feasibility studies.
Contracts in Negotiation
• SANTA RITA HPP (3 x 85 MW) – Peru
• Client: ELECTRICIDAD ANDINA (Private Company)
• Scope: EPC Contract by CGGC including Electromechanical Equipments (03
Francis Turbine).
• Updated Situation: CGGC prepared an Optimization Technical Study ,. The
Chinese Banks are analyzing the client.
• Huatziroki 1 HPP (20 MW) - Peru
• Client: ARSAC – GEHISA (Private Company)
• Scope: Complete Electromechanical Equipments (HMEC), (Turn Key)
• Updated Situation: This project obtained RER contract with government for 20
years.
Contracts in Negotiation
• COLCA HPP – CHILCAY HPP (4 x 8.2 MW) - Peru
• Client: Cascade Hydropower (Private Company)
• Scope: Complete Electromechanical Equip.from Harbin (HMEC), erection and
commissioning (Turn Key) (02 Francis Turbines for each HPP)
• Updated Situation: In negotiation.
• HUASICANCHA HPP (2 x 4.6 MW) - Peru
• Client: Cascade Hydropower (Private Company)
• Scope: Complete Electromechanical Equip.from Harbin (HMEC), erection and
commissioning (Turn Key) (02 Francis Turbines for each HPP)
• Updated Situation: In negotiation.
Contracts in Negotiation
• M HPP (2 x 9.1 MW) - Peru
• Client: ENDESA – Generalima (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key) (02 Pelton Turbines)
• Updated Situation: In negotiation.
• A HPP (2 x 6.1 MW) - Chile
• Client: ENDESA (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key).
• Updated Situation: In negotiation.
Contracts in Negotiation
• POTRERO HPP (20 MW) - Peru
• Client: KIEV Asociados (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key) (02 Francis Turbines)
• Updated Situation: In negotiation.
• PIAS 2 HPP (24 MW) - Peru
• Client: AYEPSA (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key).
• Updated Situation: The client confirmed the investment.
Contracts in Negotiation
• CHILCOCO HPPs (2 MW + 20 MW) - Chile
• Client: Carran Ltd. (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: We are in negotiation
• ALLIPENO HPP (20 MW) - Chile
• Client: GTD (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: We are in negotiation
Contracts in Negotiation
• CHERQUENO HPP (9 MW) - Chile
• Client: GTD (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: We are in negotiation
• ANIHUERAQUIO HPP (4.5 MW) - Chile
• Client: GTD (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key)
• Updated Situation: We are in negotiation
Contracts in Negotiation
• EDEGEL HPPs - Peru
• Direct Client: REIVAX (Private Company)
• Scope: Erection services of Control equipments including manpower, tools, local
transportation, supervisors and commissioning, for Huinco, Matucana,
Moyopampa and Huampani HPPs for 5 years.
• Updated Situation: In stand by until year 2014.
• ANGEL II, III HPP (04x 10.3 MW) - Peru
• Client: GEPSA (Privates Companies)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC), erection
and commissioning (Turn Key) with 2 Pelton units for each hpp.
• Updated Situation: In negotiation.
Contracts in Negotiation
• Marino 1 HPP (8 MW) - Peru
• Client: Marino Co. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection and
commissioning (Turn Key) – 02 Kaplan turbines.
• Updated Situation: 2Q 2013 will be defining contractors.
• Marino 2 HPP (10 MW) - Peru
• Client: Marino Co. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection and
commissioning (Turn Key) – 02 Kaplan turbines.
• Updated Situation: 2Q 2013 will be defining contractors
• Marino 3 HPP (8 MW) - Peru
• Client: Marino Co. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection
and commissioning (Turn Key) – 02 Kaplan turbines.
• Updated Situation: 2Q 2013 will be defining contractors.
• Marino 4 HPP (19 MW) - Peru
• Client: Marino Co. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection
and commissioning (Turn Key) – 02 Kaplan turbines.
• Updated Situation: 2Q 2013 will be defining contractors.
Contracts in Negotiation
• Cativen 1 HPP (15 MW) - Peru
• Client: Minera Poderosa. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection
and commissioning (Turn Key).
• Updated Situation: 4Q 2013 will be defining contractors.
• Cativen 2 HPP (15 MW) - Peru
• Client: Minera Poderosa. (Private Company)
• Scope: Complete Electromechanical Equipments from HMEC, erection
and commissioning (Turn Key).
• Updated Situation: 4Q 2013 will be defining contractors.
Contracts in Negotiation
Projects in bid
LA PERLA HPP (18 MW) - Costa Rica
• Client: Gas Natural Fenosa
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
erection and commissioning (Turn Key)
• LAGUNA AZUL HPP(19.9 MW) - Peru
• Client: Hidroelectrica Laguna Azul SRL (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
erection and commissioning (Turn Key), Kaplan turbines
Projects in bid
BELESAR 3 HPP (2 x 107 MW) - Espana
• Client: Gas Natural Fenosa (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
erection and commissioning (Turn Key) – 02 Reversible Turbines
• PEARES 3 HPP (157 MW )- Espana
• Client: Gas Natural Fenosa (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
erection and commissioning (Turn Key), Francis turbine
• AGUAS VERDES (20 MW) - Peru
• Client: Energoret (Private Company)
• Scope: Complete Electromechanical Equipments from Harbin (HMEC),
erection and commissioning (Turn Key).
• Updated situation: the client are founding investor partner.
Project on Evaluation
• LLUTA I, II & LLUCLLA HPPs (510 MW) - Peru
• Client: EGASA – PROINVERSION (Public Company)
• Scope: EPC contract, probably Concession Contract (30 years).
03 Power Plants : LLuta I HPP - 2 Pelton (214MW), Lluclla HPP - 2
Pelton (238.4 MW), Lluta II HPP: 2 Francis (52.47 MW)
• Investment $ 1076 MM aprox.
• ERGON POWER are defining the Representation to taking part.
Government will be bidding on 2013.
Project on Evaluation
• SAN JOSE HPP (127 MW) - Bolivia
• Client: ENDE (Public Company)
• Scope: EPC contract, using 03 Pelton turbines of 42.3 MW each.
-First stage: HPP with 2 Pelton Turbines, 42.3 MW per each.
-Second stage: HPP with 1 Pelton Turbines, 42.3 MW
• Investment : 197 MM aprox.
• TANGARA HPP (75 MW) - Bolivia
• Client: EDEGEL (Private Company)
• Scope: EPC contract.
• Investment : 100 MM aprox.
Project on Evaluation
Biomass Projects
ERGON POWER
Contracts in Negotiation
• CAMPOSOL (4 MW) - Peru
• Client: Camposol (Private Company)
• Scope: Considering 08 gen sets of 500kW, Biomass Power Plant using
Asparagus - Turn Key Contract with FENGYU.
• VIRU (1.2 MW) - Peru
• Client: Viru (Private Company)
• Scope: Considering 03 gen sets of 400kW, Biomass Power Plant using
Asparagus - Turn Key Contract with FENGYU
Contracts in Negotiation
• DANPER (3.6 MW) - Peru
• Client: Danper (Private Company)
• Scope: Considering 07 gen sets of 500kW, Biomass Power Plant using
Asparagus - Turn Key Contract with FENGYU.
• CAMPOSUR (1.5 MW) - Peru
• Client: Camposur (Private Company)
• Scope: Considering 03 gen sets of 500kW, Biomass Power Plant using
Rice husk - Turn Key Contract with FENGYU
Thermal Projects
ERGON POWER
• PIRQUENES Coal Power Plant (60 MW) - Chile
• Client: SWC (Private Company)
• Scope: EPC Contract with CGGC as EPC Contractor.
• Updated Situation: We are in the short list. The client are waiting the
approbation of the EIA.
• EL FARO Dual Power Plant (300 MW) - Peru
• Client: Shougesa (Chinese Private Company)
• Scope: EPC Contract. Considering 01 gas turbine, a heat recovery boiler
and steam turbine.
Contracts in Negotiation
• OLIMPIC Gas Power Plant (10 MW) - Peru
• Client: Clean Energy (Private Company)
• Scope: Turn Key electromechanical equipments and commissioning.
• Updated Situation: We are in the short list.
• INKA Gas Power Plant (300 MW) - Peru
• Client: Cemento Inka (Private Company)
• Scope: Turn Key electromechanical equipments and commissioning.
• Updated Situation: We are in the short list.
Contracts in Negotiation
• CALDERA Coal Power Plant (900 MW) - Chile
• Client: ABS GROUP(Private Company)
• Scope: EPC Contract.
• Updated Situation: Ergon Power are helping the owner to obtain EPC
Contractor and Investor. Investment : 1,200 MM aprox
• NODO SUR Power Plant (500 MW) - Peru
• Client: Enersur (Private Company) – IC Power (Private Company)
• Scope: EPC Contract.
• Updated Situation: Ergon Power are interested in taking part in the bid
Project on Evaluation
Wind Farm Projects
ERGON POWER
Project on Evaluation
• CALAMA Wind Farm (128 MW) - Chile
• Client: E-CL S.A.(Private Company)
• Scope: EPC Contract with financing. Considering turbines of 2.0 MW or
1.5 MW.
• Investment: $ 240 MM aprox.
• Updated Situation: ERGON POWER are helping the owner to obtain
EPC Contractor - Investor.
Project on Evaluation
• LEBU Wind Farm (280 MW + 158 MW) - Chile
• Client: Bosquemar Ltd.(Private Company)
• Scope: EPC Contract with financing. Considering 140 turbines of 2.0 MW
+ 79 turbines for the second stage.
• Investment : $ 540 MM aprox.
• Updated Situation: ERGON POWER are helping the owner to obtain
EPC Contractor - Investor.
Project on Evaluation
• LLANQUIHUE Wind Farm (54 MW) - Chile
• Client: ENER RENOVA.(Private Company)
• Scope: EPC Contract with financing. Considering turbines of 2.0 MW.
• Updated Situation: ERGON POWER are helping the owner to obtain
EPC Contractor - Investor.
• CKANI Wind Farm (240 MW) - Chile
• Client: AM Eolica Alto Loa S.P.A.(Private Company)
• Scope: EPC Contract with financing. Considering turbines of 2.0 MW or
1.5 MW.
• Updated Situation: ERGON POWER are helping the owner to obtain
EPC Contractor - Investor.
Project on Evaluation
• LLAY LLAY Wind Farm (56 MW) - Chile
• Client: Servicios Eolicos L S.A.(Private Company)
• Scope: EPC Contract with financing. Considering 28 turbines of 2.0 MW.
• Updated Situation: ERGON POWER are helping the owner to obtain
EPC Contractor - Investor.
Solar Projects
ERGON POWER
Projects in bid
• Danper Power Plant (3 MW) - Peru
• Client: Danper (Private Company)
• Scope: EPC Contract with SUMEC.
• Updated Situation: We are preparing the proposal.
• Solar Power Plant (20 MW) - Peru
• Client: Peru Energia Renovable – Enhol (Private Company)
• Scope: EPC Contract with SUMEC.
• Updated Situation: We are preparing the proposal.
Infrastructure Projects
ERGON POWER
Project on Evaluation
• San Martin Port - Peru
• Client: PROINVERSION (Public Company)
• Scope: BOOT Contract - Concession bid for 30 years
• Investment: $ 101.2 MM aprox.
• ERGON POWER are defining the Representation to taking part. The
Government opened the qualification bid.
Project on Evaluation
• Chincheros International Airport - Peru
• Client: PROINVERSION (Public Company)
• Scope: BOOT Contract - Concession bid for 30 years
• Investment: $ 420 MM aprox.
• ERGON POWER are defining the Representation to taking part. The
Government opened the qualification bid.
Project on Evaluation
• Electric Train Metro – Line 2 - Peru
• Client: PROINVERSION (Public Company)
• Scope: BOOT Contract - Concession bid for 30 years
• Investment: $ 3000 MM aprox.
• ERGON POWER are defining the Representation to taking part. The
Government will open the qualification bid on year 2013.
Project on Evaluation
• National Highway - Peru
• Client: PROINVERSION (Public Company)
• Scope: BOOT Contract - Concession bid for 30 years
• Investment: $ 3800 MM aprox.
• ERGON POWER are defining the Representation to taking part. The
Government will open the qualification bid on year 2013.
OFICINA EN PERÚ:
Dirección:
F. Bolognesi 125 Of. 1401 – Centro Ejecutivo
Pardo, Miraflores, Lima – Perú.
Gerencia General y Of. Comercial
Central Telefónica: (511) 7165907
OFICINA EN CHILE:
Dirección:
Av. Vitacura 2670 Piso 15, Las Condes, Santiago –
Chile.
Oficina Comercial
Central Telefónica: (56 2) 8204339
Request a Reference Lists of our
Representations by email
THANKS !