Environmental Room Construction

Environmental Room

Embed Size (px)

Citation preview

Environmental Room Construction

The assembly starts with building the floor first. The next

step is to assemble the walls.

After the walls are installed,

the ceiling is set in place.

View from above showing walls and door in place with out ceiling.

Setting

of door

thresh

hold.

Completion of the chamber. Now the components are installed.

The control console is

mounted along with the

disconnect for the power

supply.

The duct work and humidifier need to be installed.

After the duct work is installed the desiccant dryer is installed along

with it’s duct work connections.

The compressor is set in place and the remote lines to condenser

are run.

Close up view of compressor.

View of compressor, ductwork, and remote lines completed.

Last items to be install are the interior ceiling grid with lighting and

ductwork.