Environmental Room Construction
The assembly starts with building the floor first. The next
step is to assemble the walls.
After the walls are installed,
the ceiling is set in place.
View from above showing walls and door in place with out ceiling.
Setting
of door
thresh
hold.
Completion of the chamber. Now the components are installed.
The control console is
mounted along with the
disconnect for the power
supply.
The duct work and humidifier need to be installed.
After the duct work is installed the desiccant dryer is installed along
with it’s duct work connections.
The compressor is set in place and the remote lines to condenser
are run.
Close up view of compressor.
View of compressor, ductwork, and remote lines completed.
Last items to be install are the interior ceiling grid with lighting and
ductwork.