21
Environmental Monitoring Report July 2015 GEO: Regional Power Transmission Enhancement Project Prepared by the Georgian State Electrosystem JSC for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Environmental Monitoring Report July 2015

GEO: Regional Power Transmission Enhancement

Project

Prepared by the Georgian State Electrosystem JSC for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed

herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,

and may be preliminary in nature. In preparing any country program or strategy, financing any

project, or by making any designation of or reference to a particular territory or geographic area

in this document, the Asian Development Bank does not intend to make any judgments as to

the legal or other status of any territory or area.

Page 2: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 2 of 21

ABBREVIATIONS

ADB Asian Development Bank

EA Executing Agency

EARF Environmental Assessment and Review Framework

EIA Environmental Impact Assessment

EIP Environmental Impact Permit

EMP Environmental Management Plan

GoG Government of Georgia

GSE Georgian State Electrosystem JSC

IA Implementing Agency

IEE Initial Environmental Examination

MoENRP Ministry of Environmental and Natural Resources Protection

PMU Project Management Unit RAP Resettlement Action Plan RPTEP Regional Power Transmission Enhancement Project SSEMP Site-Specific Environmental Management Plan TA Technical Assistance

Page 3: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 3 of 21

Contents

1. INTRODUCTION ................................................................................................ 4

1.1 Construction activities and project progress during the reporting period ..................... 5

1.2 Changes in Project Organization and Environmental Management Team ...................... 7

1.3 Relationship with Contractors, Owners, Lenders, etc. ..................................................... 8

2. ENVIRONMENTAL MONITORING ................................................................... 10

Waste Management .................................................................................................................. 13

Archaeology.............................................................................................................................. 13

Soil and Water Contamination (pollution prevention) ........................................................... 13

3. ENVIRONMENTAL MANAGEMENT ................................................................ 13

3.1Environmental management system, site-specific environmental management plan (SSEMP), and work plans .............................................................................................................. 13

3.2 Site inspections and audits ............................................................................................... 14

3.3 Non-compliance Notices and Corrective Actions ........................................................... 14

4. ANNEXES......................................................................................................... 16

Annex 1: Measurement results of noise level at construction site ...................................... 16

Annex 2. Photos of Project Sites (Khorga) ............................................................................ 17

Annex 3. Implementation Report On The Initial Environmental Examination (IEE) Mitigation Requirements:................................................................................................................................ 20

Page 4: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 4 of 21

1. INTRODUCTION

The reliability of the GSE's transmission infrastructure have been vastly improved for recent years as a result of intensive capital investment programs successfully implemented with the support of international financial institutions and donors. Besides, the improved financial position of GSE for the last few years enabled GSE to implement a number of rehabilitation and construction activities with its own resources and funds. As a result of these joint efforts, about 80% of primary equipment and 30% of secondary equipment at GSE substations, as well as a significant part of transmission lines, have already been replaced or rehabilitated. These projects significantly improved the situation in GSE substations and lines, shortened the outages and maintenance, reduced transmission losses and improved the power transmission quality criteria.

However, GSE is still investing in the remaining portions of the assets to achieve further improvement of the transmission grid. GSE is committed to have all the GSE substations fully rehabilitated/upgraded by 2015-2016, with all remaining primary and secondary equipment replaced and/or refurbished and effectively controlled from the National Control Center (NCC).

The Regional Power Transmission Enhancement Project (the RPTEP) financed from the proceeds of the ADB loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once implemented, will further enhance the reliability and stability of GSE’s transmission and interconnection infrastructure and remarkably improve the capability of cross-border energy exchange for export, import and transit.

The RPTEP activities include the following two physical components: 1. Construction of a new 220/110kV Substation Khorga;

The new Khorga substation, together with other ongoing transmission system investment projects, will improve the reliability of the grid and power supply quality. The new substation will strengthen and stabilize the transmission network operation. It will guarantee stable transmission of energy produced at Enguri HPP to the industrial zone of Poti and to Turkey through Batumi Substation. Besides, it will help stabilize transmission power flows providing additional event redundancy and lowering the incidence of outages.

2. Substation Rehabilitation and Improvement: Lot 1: Rehabilitation of the 500kV substation Ksani, including HV primary equipment and complete relay

protection and control systems; Lot 2: Rehabilitation and expansion of Marneuli substation with 500/220/10kV bays, including:

501MVA autotransformer (3x167MVA +1x167MVA spare); connection to existing 220kV part of Marneuli substation via 220kV line (about 400m); Realignment of existing 500kV lines Vardzia and Mukhrani to ensure looping in and looping out

of 500/220/10kV substation.

Lot 3: Supply and installation of one 125MVA autotransformer 220/110/10 kV for the 220 kV substation Menji, replacing one of the two existing 220/110/10 kV autotransformers (63 MVA).

Once implemented, this project component:

will improve the existing 500 kV and220 kV connections in the east part of Georgia,

Will serve as an additional/alternative source of power supply for Tbilisi metropolitan area in case of emergencies.

Page 5: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 5 of 21

Expansion of existing 500 kV link (Akhaltsikhe-Gardabani) with Ksani-Marneuli connection will further increase the reliability and stability of 500kV network, thus increasing the reliability of export/import/transit of electric energy.

Locations of the substations to be constructed and rehabilitated/extended under the Project are highlighted in the map below:

Map 1: Location of the substations (Khorga, Ksani, Marneuli and Menji)

Physical completion of the RPTEP is expected by end of 2016. These two components of the RPTEP, the components 1 (Construction of a New 220/110kV Substation Khorga) and 2 (Substation Rehabilitation and Improvement) involve the activities that could have an impact on the environment. Following ‘Environmental Considerations in ADB Operations’ of September 2006, the RPTEP has been classified as Category B requiring an Initial Environmental Assessment (IEE), which will not have significant irreversible or permanent negative environmental impacts during or after construction and requires preparation of Initial Environmental Examination (IEE). The environmental categorization of subprojects was conducted using ADB’s Safeguard Policy Statement (2009).

1.1 Construction activities and project progress during the reporting period

Civil works under Component 1 - Construction of a New 220/110kV Substation Khorga Following the International Competitive Bidding (ICB) for this component, the contract was awarded to Siemens AG Osterreich (Austria) and the Contract Agreement was signed on 9th of July, 2014. The implementation period from the effective date of the Contract Agreement is 18 months.

Page 6: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 6 of 21

During reporting period the following activities have been carried out: Khorga SS:

Excavation of the drainage channel and leveling of the platform up to bottom of foundations

Precast of the equipment foundations

Excavation and preparation of the gantries foundations

Placing of the prefabricated foundations on 110 kV and 220kV substation

Civil work on the control building

Construction of the roads inside the substation

Construction of the fence

Construction of the guard house

Construction of the transformer foundations with oil pit

Backfilling around foundations and increasing of the platform level

Erection of the steel structure of 110 kV and 220kv

Installation of the earthing system

The Table 1 below shows project progress in percentage during 6 months period for Khorga Project.

Table 1: Project progress during 6 months period

Actual Variance

Design&Engineering 4% 100% 100% 0,0%

Site preparaion works 1% 100% 100% 0,0%

Procurement 8% 100% 96,9% -3,1%

Manufacturing 60% 93,3% 78,9% -14,4%

Construction and commissioning 26% 17,2% 6,5% -10,7%

As built documents 1% 0,0% 0,0% 0,0%

Grand Total Progress 100% 73,5% 61,8% -11,7%

Khorga 220/100kV Substation

Task Name Weight Cumulative Baseline PlanCumulative

Civil works under Component 2 – Substation Rehabilitation and Extension

Menji The turnkey contract has been signed by BEST on October 31, 2014. The effectiveness of contract is December 18, 2014. The implementation period from the effective date of the contract will be 18 months. The construction activities have not been started yet.

Marneuli

The turnkey contract has been signed by BEST on October 31, 2014. The effectiveness of contract is December 18, 2014. The implementation period from the effective date of the contract will be 18 months. Mobilization started on the 2nd of January 2015 year.

Page 7: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 7 of 21

Marneuli SS:

Stripping of topsoil

Excavation of sub soil

Constructing of access road

Installation of temporary office

The Table 2 below shows project progress in percentage during 6 months period for Marneuli Project.

Table 2: Project progress during 6 months period

Actual Variance

Design&Engineering 100% 70% -30%

Site preparaion works 83,7% 67,4% -16,3%

Procurement 100% 84,5% -15,5%

Manufacturing 45,5% 22,6% -22,9%

Construction and commissioning 0,0% 0,0% 0,0%

As built documents 0,0% 0,0% 0,0%

Grand Total Progress 36,8% 20,9% -15,9%

Extension of 220/100kV SS Marneuli with 500kV

Task Name Cumulative Baseline PlanCumulative

Ksani The turnkey contract has been signed by Siemens on October 31, 2014. The effectiveness of contract is December 22, 2014.The implementation period from the effective date of the contract will be 18 months. The construction activities have not been started yet.

1.2 Changes in Project Organization and Environmental Management Team

Environmental Protection and Resettlement Unit (REU) comprised of three specialists has been established under the International Projects and Reporting Department of GSE. This unit closely monitors the compliance with all safeguards requirements during the implementation of the RPTEP. GSE Projects Coordinator for Environment Safeguards Issues - Zezva Khvedelidze is responsible for:

Participate in working meetings related to projects.

Ensure projects compliance with the Environmental Legislation of Georgia as well as with the rules and

requirements of other donors (ADB, WB, EBRD, USAID, KFW, others)

Ensure coordinating among involved parties during project implementation period.

Participate in Environmental component monitoring.

Review and analysis of existing documentation.

Monitor Environmental protection issues; prepare reports in compliance with the requirements of the

donors as well as in accordance with the Georgian Legislation.

Page 8: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 8 of 21

Review comments and complaints; elaborate recommendations.

Prepare official letters to projects Implementation Company and/or consultant.

Review documents submitted by contractors.

Establish and have relations with other organizations, state bodies of Georgia, International organizations

and bodies of other countries for the purpose of implementation of the objectives, tasks and functions

specified under this document.

The Supervision Consultant has employed national environmental specialist Paata Chankotadze, who is responsible for:

Reviewing and approval of environmental documentation, submitted by the Contractor;

Monitoring of construction activities;

Relationship with the Contractor and the Employer;

Support of the Contractor in obtaining of environmental permits and licenses;

Correspondence with the Employer, the Contractor and local authorities. The Contractors (Siemens and Best) have hired national HSE specialists, Giorgi Merabishvili and Konstantine Zarandia, who are responsible for:

To prepare environmental documentation, mentioned in Contract, EIA and IEE;

To establish a routine system

To ensure that physical monitoring is undertaken properly

To review works schedules

To participate in progress meetings

Help identify practical solutions to actual and potential problems

Use trends in monitoring data to predict/identify possible future problems

To provide daily environmental field supervision

To notify noncompliance and take relevant actions

To keep records: maintain site diary and checklists, complete files

Communicate with local community regarding works progress

Receiving relevant permissions and licenses. Consulting Services for Project Supervision and Management The Contract for Consulting Services with Fichtner GmnH&Co.KG (Germany) was signed on 19 May, 2014. TOR for supervision consultant contains tasks for a national environmental specialist to monitor the EMP/SSEMP implementation. The consultant is conducting environmental monitoring of project progress.

1.3 Relationship with Contractors, Owners, Lenders, etc.

GSE ensures of availability of all environmental information and facilitates environmental supervision of the projects. The GSE through its environmental specialist reports to the ADB every 6 months on the status of environmental compliance of construction works by EMRs.

Page 9: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 9 of 21

Component 1 - Construction of a New 220/110kV Substation Khorga: Construction Contractor of Khorga SS – Siemens Ltd. has contractors/sub-contractors. The status of environmental permits and licenses submitted by the contractors/sub-contractors are reflected in the Table 2 below:

Table 2: Status of environmental permits and licenses of Siemens Ltd. subcontractors

Item status Comment

Permit for cutting of grass, bushes and trees, located on construction site

Not needed Land plot is a property of GSE.It is not needed to take any permission for cutting of grass, bushes and trees located on construction site.

License for borrow pit Yes Contractor buys inert material from subcontractor - “Prime Beton” Ltd. Subcontractor has licensed borrow pit (license No1001289). License has been submitted to the Consultant.

Inventory of Emissions of hazardous substances in to ambient air from batching plant

Not needed Contractor buys concrete from subcontractor - “ Prime Beton” Ltd.

Disposal of municipaland construction waste

Yes The sub-contractor “Prime Beton” Ltd has signed agreement with “Georgian Solid Waste Management Company” Ltd, who is responsible for handling of municipal and construction waste.

Hazardous waste Yes The Sub contractor has signed agreement with “Sanitari” Ltd, who is responsible for handling of hazardous waste.

Component 2 - Rehabilitation and expansion of Marneuli substation with 500/220/10kV (Contractor- Best): Construction Contractor of Marneuli SS – Best Ltd. has contractors/sub-contractors. The status of environmental permits and licenses submitted by the contractors/sub-contractors are reflected in the Table 3 below:

Table 3: Status of environmental permits and licenses of Best Ltd. subcontractors

Page 10: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 10 of 21

Item status Comment

License for borrow pit N/A The Contractor does not use inert materials on this stage of project. In the future the Contractor will buy inert material from licensed subcontractor.

Inventory of Emissions of hazardous substances in to ambient air from batching plant

Not needed Contractor has not own batching plant. In the future the Contractor will buy concrete material from licensed subcontractor.

Disposal of municipaland construction waste

No The Contractor has not submitted agreement with municipaland construction waste management company. Currently these types of waste are temporally stored on construction site. The Contractor was instructed to sign contract with licensed waste management company.

Hazardous waste No The Contractor has not submitted agreement with hazardous waste management company. Currently hazardous waste is temporally stored on construction site. The Contractor was instructed to sign contract with licensed waste management company.

2. ENVIRONMENTAL MONITORING

2.1 Component 1 - Construction of a New 220/110kV Substation Khorga During site inspections, the environmental specialists of the Contractor and the Consultant monitored the following issues: availability of relevant permissions and licenses, waste management, pollution prevention, top soil protection, community safety, air emissions, protection of private property outside Construction Site, etc. Table 4 below shows the schedule of conducted audits and monitoring during the reporting period.

Table 4: The schedule of conducted audits and monitoring in Khorga during the reporting period Khorga Site visit Organization Date 1 Audit and monitoring GSE and Fichtner

environmental specialists 11-12 March. 2015

2 Audit and monitoring GSE and Fichtner environmental specialists

31 Mar.- 1 Apr. 2015

3 Audit and monitoring GSE and Fichtner environmental specialists

29-30 Apr. 2015

4 Audit and monitoring GSE and Fichtner environmental specialists

27-28 May. 2015

Page 11: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 11 of 21

5 Audit and monitoring GSE and Fichtner environmental specialists

15-17Jun. 2015

6 Audit and monitoring GSE and Fichtner environmental specialists

16-17 Jul. 2015

Protection of Top Soil

In the beginning of reporting period some violations of top soil protection procedures have been recorded, in particular: heavy construction equipment was disposed directly on topsoil; Excavated spoil was disposed on construction site, without stripping of topsoil; stored topsoil was mixed with subsoil. The Contractor has immediately improved abovementioned non-compliances after the Engineer`s verbal instruction. Currently the Contractor pays attention to all top soil protection rules. Stored top soil is protected from mixing with subsoil and all types of erosion and losses.

Subsoil Disposal

After removal of top soil, construction site has been leveled, all extra subsoil was used for filling of existing channels on the construction site.

Noise/vibration

Construction site is located far from settlement. Noise and vibration do not disturb local people. The consultant every month measures noise level at construction site. Results of measurement are less, than maximum permissible level (80Db). Measurement results of noise level at construction site are given in Annex 1.

Air pollution

No significant pollution was observed.

Emission and Dust

During reporting period significant emissions and dust have not been observed on construction site and access roads.

Impact on Flora and Fauna

N/A.

Waste Management

The Contractor has disposed on the construction site different containers for disposal of hazardous and non-hazardous wastes. Toilets have been installed on construction site. Sewage water is collecting in underground container and periodically removing by licensed subcontractor. Currently waste management issues are in compliance with relevant procedures.

Archaeology

No archaeological findings have been observed during reporting period.

Soil and Water Contamination (pollution prevention)

Spillages during reporting period have not been recorded. The Contractor has installed drip trays under oil barrels, diesel generators and containers with hazardous materials.

Page 12: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 12 of 21

The contractor has installed temporary refueling area on construction site, conditions of which are in compliance with pollution prevention management plan. 2.2 Component 2 - Rehabilitation and expansion of Marneuli substation with 500/220/10kV During site inspections, the environmental specialists of the Contractor and the Consultant Companies monitored the following issues: availability of relevant permissions and licenses, waste management, pollution prevention, top soil protection, community safety, air emissions, protection of private property outside Construction Site, etc. Table 5 below shows the schedule of conducted audits and monitoring during the reporting period.

Table 5: The schedule of conducted audits and monitoring in Marneuli during the reporting period

Marneuli Site visit Organization Date 1 Audit and monitoring GSE and Fichtner

environmental specialists 17March. 2015

2 Audit and monitoring GSE and Fichtner environmental specialists

15 Apr. 2015

4 Audit and monitoring GSE and Fichtner environmental specialists

13 May. 2015

5 Audit and monitoring GSE and Fichtner environmental specialists

10 Jun. 2015

6 Audit and monitoring GSE and Fichtner environmental specialists

8Jul. 2015

Protection of Top Soil Top soil has been removed from construction site in accordance with IEE and technical specifications. The amount of topsoil is around 2700-2780 cubic meter. Stored top soil is disposed on South-West of construction site.To reduce the risk of water erosion, the contractor was instructed to dispose sand bags around the stockpile. Subsoil Disposal After removal of top soil, construction site has been leveled, all extra subsoil was stored on the North, near construction site on the Employer’s own land plot. The amount of extra subsoil will be around 450000 cubic meter. Noise/vibration Construction site is located far from settlement. Noise and vibration do not disturb local people. The consultant every month measures noise level at construction site. Results of measurement are less, than maximum permissible level (80Db). Measurement results of noise level at construction site are given in Annex 1. Air pollution No significant pollution was observed. Emission and Dust During reporting period significant emissions and dust have not been observed on construction site and access roads.

Page 13: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 13 of 21

Impact on Flora and Fauna N/A.

Waste Management

The Contractor has disposed on the construction site different containers for hazardous and non-hazardous wastes. Toilets have been installed on construction site. Sewage water is collecting in underground container and will be removed by licensed subcontractor.

Archaeology

No archaeological findings have been observed during the reporting period.

Soil and Water Contamination (pollution prevention)

Spillage of diesel fuel around refueling area has been recorded during reporting period. Hazardous materials as well as containers with oil products are disposed on site without secondary containment devises (drip trays). The Contractor was instructed to dispose all containers with hazardous materials on drip trays and bring refueling area in accordance with pollution prevention management plan.

3. ENVIRONMENTAL MANAGEMENT

3.1Environmental management system, site-specific environmental management plan (SSEMP), and work plans

GSE’s environmental specialist carried out on-site monitoring of ongoing contracts to check environmental compliance of construction works and effectiveness of supervisory company’s activities. Records of on-site environmental monitoring are kept at GSE office and at construction camp. The environmental staff has created a project environmental safeguard files and an electronic track record system. The Contractors submit monthly progress reports to the supervisor and GSE which will include a chapter on environmental performance. The table below shows the status of SSEMPs and management plans to be submitted by the Construction Contractors:

Table 6: Status of SSEMPs and management Plans

Management Plan Status

Page 14: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 14 of 21

Khorga Marneuli

SSEMP Approved Approved Environmental Monitoring Program Approved Approved

Fire prevention and management plan Approved SSEMP contains very general information,

require separate plan submission.

Waste management plan for construction phase Approved Approved

Hazardous materials and waste management and handling plan.

Approved SSEMP contains very general information,

require separate plan submission.

Oil spill Emergency response plan Approved SSEMP contains very general information,

require separate plan submission.

Used Oil Management plan Approved Not submitted, deadline-25.07.2015

HS Plan Approved Approved

3.2 Site inspections and audits

“Siemens”Ltd. has employed full time HSE specialist for Khorga SS construction project. “Best” Ltd. has representative of subcontractor, HSE field supervisor in Marneuli. Monitoring visits were conducted jointly by GSE and Supervision Consultant - Fichtner. During the field visits a number of EHS issues were noted and brought to the attention of the Environmental Consultant and the H&S manager of Siemens Ltd. and Best Ltd. Mitigation measures were then discussed with the contractor on-site and detailed written instructions were given. Site monitoring visits during the reporting period have been carried out on: 11-12March. 2015; 17 Mar. 2015; 31 Mar. 1 Apr. 2015; 29-30 Apr. 2015; 13 May 2015; 27-28 May 2015; 10 Jun. 2015; 17-19 Jun. 2015; 08 Jul. 2015; 16-17 Jul. 2015; Monitoring Compliance and Inspection monitoring forms have been filled in during the site visits.

3.3 Non-compliance Notices and Corrective Actions

Non-Compliance at “Khorga Sub-Station”

All corrective actions requested after the monitoring of sites were immediately improved by the Construction Contractor; the non-compliance notices have not been issued by the supervision consultant’s environmental specialist, during the visit he has instructed verbally the Contractor to follow top-soil protection and pollution prevention procedures mentioned in IEE.

Non-Compliance at “Marneuli Sub-Station”

The non-compliance notices have not been issued by the supervision consultant’s environmental specialist, during the site-visit he has instructed verbally the Contractor to follow top-soil protection and pollution prevention procedures, mentioned in IEE.

Page 15: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 15 of 21

As it was requested in IEE the following documents have not been prepared before construction activities by the Construction Contractor, in particular:

1. Hazardous materials and waste management and handling plan; 2. Oil spill emergency response plan.

The supervision consultant has requested from the Contractor to submit the above mentioned management plans. Deadline of submission-15.07.2015

3.4 Consultations and Complaints

Consultations have not been conducted so far. At present complaints register book is kept at GSE office. The complaints register book will be placed at construction camps in Khorga and Marneuli SS at the nearest future.

Page 16: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 16 of 21

4. ANNEXES

Annex 1: Measurement results of noise level at construction site

Location Noise level, db

11.03.2015 29.04.2015 Max. permissible level

Khorga substation

68 71 80

Location Noise level, db

17.03.2015 13.05.2015 Max. permissible level

Marneuli substation

59 77 80

Page 17: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 17 of 21

Annex 2. Photos of Project Sites (Khorga)

Khorga, Construction site

All diesel generators are disposedin drip trays Khorga, Construction site

The fence has been installed around the construction site

Khorga, Construction site

Containers for hazardous and non-hazardous waste was disposed on construction site

Khorga, Construction site Underground tank for sewage water

Page 18: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 18 of 21

Khorga, Construction site

First aid kit and medical personnel are available on site

Khorga, Construction site Power generators are disposed in secondary containment devise; all workers use PPE

Khorga, Construction site

Drainage system has been installed around construction site

Marneuli, Construction site Containers for each type of waste

weredisposed on construction site

Page 19: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 19 of 21

Marneuli, Construction site

Hazardous materials are disposed directly on the ground

Marneuli, Construction site Spillage of diesel on refueling area

Page 20: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Page 20 of 21

Annex 3. Implementation Report On The Initial Environmental Examination (IEE) Mitigation Requirements:

Item Requirement Action to date Action required/comment

Protection of top soil The topsoil should not be handled when: I) The top-soil is frozen; ii) The site is experiencing persistent rainfall; iii) The topsoil is saturated; Segregation from subsoil stockpiles; The storage of topsoil in stockpiles; No more than 2m high with side slopes at a maximum angle of 450;Dedicated storage locations that prevent the stockpiles being compacted by vehicle movements or contaminated by other materials; Erosion protection measures (erosion matting, berms etc.). No storage where there is potential for flooding. No storage at less than25m from river/streams, subject to site specific Topography. Topsoil from the sites, which should not be reinstated to the initial conditions should be distributed carefully on the surrounding area.

Improved partially Contractor’s environmental Specialist instructed to follow topsoil protection rules.

Impacts on cultural heritage sites

If physical cultural resources are encountered during the construction phase, all works at the find site should be immediately halted. The find should be assessed by a competent expert, and procedures to avoid, minimize or mitigate impacts to the physical cultural resources should be developed by the expert in Cooperation with the relevant local heritage authority.

No impacts during reporting period

Biological recontamination during earthworks

Permanent monitoring during land clearance and excavation activities. Stoppage and suspension of construction activities in case of burial site findings. Notification to the local Division of Veterinary Department. Veterinary clearance before start up.

No impacts during reporting period

Noise and Dust Caused by Construction Activities and Emissions of Harmful

Require adherence to engine maintenance schedules and standards to reduce air pollution; Use of defined, well planned haulage routes and reductions in vehicle speed where required; Periodically water down temporary roads on site;

In compliance with IEE requirements, do not need improvement

Page 21: Environmental Monitoring Report€¦ · loan is among the top investment priorities of GSE’s Strategic Development Plan 2012-2020 and, once ... Following the International Competitive

Bi-annual Environmental Monitoring Report

Page 21 of 21

Substances into the Atmosphere Air

Wet or cover trucks carrying stone/ sand/ gravel; Haul materials to and from the site in off peak traffic hours; Halting work during excessive winds; No truck movements in inhabited areas between22:00 and 6:00.

Potential to pollute nearby water bodies, underground water and namely drainage channels and irrigation canals

Fuel, oil and hazardous materials should be stored in designated areas with temporary impermeable bunds at distance of at least 100 m from any water course. Refueling of machinery, equipment and vehicles should be undertaken at distance of at least 100 m from any water course. Any major work including oil changing and engine maintenance with the potential for oil to be spilled will be done in designated areas at distance of at least 100 m from any water course and with containment to prevent any oil spills washing away. Waste oil shall be collected and taken away for recycling. Oil contaminated material shall be disposed of at designated waste disposal facilities.

Improved partially

The Contractor was instructed to construct proper refueling area before 01.03.2015

Pollution prevention issues

Contractors should ensure the proper handling of lubricants, fuel and solvents. All tanks should be placed in a bund of at least 110% of the tank’s maximum capacity. Accumulated rainwater in bunds should be pumped out of the bund to either drains or onto the ground if uncontaminated. In case of fuel spillage the spilled fuel should be recollected and the contaminated bund shall be treated using the absorbents: Sawdust, sand or straw. All fuel/hydrocarbon dispensing nozzles are to be of a drip control design and securely locked when not in use. Vehicles should not be left without the supervision during refueling process. All refueling operations on the working sites should use absorbent pads and/or straw To minimize spills, which shall be put in place prior to the commencement of refueling operations.

Improved, the Contractor has disposed all containers with hazardous materials in to drip trays