Environmental Monitoring Report
Quarterly Progress Report No. 10 June – August 2016
VIE: Central Mekong Delta Region Connectivity
Project
Part II/Annexes (pages 58-117)
'This environmental monitoring report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,
and may be preliminary in nature. Your attention is directed to the “terms of use” section of this
website. In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area
Prepared by Detailed Design and Implementation Support: CDM Smith-WSP-Yoo-shin
Consultant Joint Venture for the Socialist Republic of Viet Nam and the Asian Development
Bank.
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 58
CW2B
Rach Vuot Bridge
Launching Voided slab girder
Date: 14-08-2016
CW2B
Rach Vuot Bridge
Launching Voided slab girders
Date: 14-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 59
CW2B
Rach Vuot Bridge
Fabrication of Voided slab girders
Date: 04-08-2016
CW2B
Tan Binh Bridge
Launching I Girder
Date: 05-09-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 60
CW2B
Tan Binh Bridge
Launching I Girder
Date: 12-08-2016
CW2B
Xang Muc Bridge
Construction of Column P1
Date: 06-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 61
CW2B
Xang Muc Bridge
Construction of Pier Cap P2
Date: 05-08-2016
CW2B
Xang Muc Bridge
Construction of RC piles
Date: 06-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 62
CW2B
Xang Muc Bridge
Preparation for casting super T girders
Date: 02-08-2016
CW2B
Xang Nho Bridge
Reinforcement cage at place for casting Pier Cap
P2
Date: 01-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 63
CW2B
Xang Nho Bridge
Construction of Voided slab gieders
Date: 24-08-2016
CW2B
2/9 Bridge
Construction of Pier Cap P2
Date: 30-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 64
CW2B
Rach Vuot Bridge
Erection of girders
Date: 24-08-2016
CW2A
Km8+072-Km8+550
Monitoring at stage 2
Date: 24-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 65
CW2A
Km10+333-Km11+342
Surcharge fill stage 2
Date: 24-08-2016
CW2A
Km11+577-Km13+208
VCM on going
Date: 24-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 66
CW2A
km12+580-km13+126
VCM ongoing
Date: 02-08-2016
CW2A
km13+650-km13+750
preparation for earth berms for VCM
Date: 13-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 67
CW2A
km14+250-km15+267
Construction of VCM
Date: 04-08-2016
CW2A
km15+360-km15+580
PVD under construction
Date: 06-08-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 68
Package CW2C
CW2C
LAP VO BRIDGE
P7→P8
Competing segment K9
Date: 25-07-2016
CW2C
LAP VO BRIDGE
P7→P8
Completing segment K9-left side
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 69
CW2C
LAP VO BRIDGE
P8→P9
Preparing formwork segment K10-left side
Date: 25-07-2016
CW2C
LAP VO BRIDGE
P9→P12
Casting concrete for desk slab span 11 and
12
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 70
CW2C
LAP VO BRIDGE
Fabricating super T girder.
Date: 25-07-2016
CW2C
LAP VO BRIDGE
P14
Completing Pier Cap
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 71
CW2C
LAP VO BRIDGE
Preparing construction platform for abutment
A1.
Date: 25-07-2016
CW2C
XEP CUT BRIDGE
Abutment A2
Completing a part of body wall
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 72
CW2C
XEP CUT BRIDGE
Installation rebar for supporting slab A2.
Date: 25-07-2016
CW2C
XEP CUT BRIDGE
Fabricating voided slab.
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 73
CW2C
XEP CUT BRIDGE
A1 area.
Date: 25-07-2016
CW2C
ROAD WORK
Km19+072-Km19+700.
Completing surcharge stage 2
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 74
CW2C
ROAD WORK
Km19+700-Km19+900.
Completing surcharge stage 2 and carrying
stage 3
Date: 25-07-2016
CW2C
ROAD WORK
Km21+100-Km21+300.
Completing surcharge stage 2.
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 75
CW2C
ROAD WORK
Km18+200-Km18+400.
Completing surcharge stage 2.
Date: 25-07-2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 76
ANNEX 4-1: PROJECT DATA
General
Name of Employer Cuu Long CIPM
Name of GD/ CIPM Mr. Duong Tuan Minh
Name of Consultant CDM Smith , WSP , Yooshin JV
Name of PM/Consultant Mr. Anders Loof
Package CW1A: Northern Approach to Cao Lanh Bridge
Name of Contractor JV of Hoang An – Tuan Loc – Thang Long
Name of PM/ Contractor Mr. Dang Xuan Lich
Contract Amount 1,107,850,611,799 VND (inclusive of VAT & contingency)
Contract Period 1092 days (36.0 months)
Commencement date 29 October 2014
Completion date 24 October 2017
Package CW1B: Cao Lanh Bridge Project
Name of Contractor CRBC – VINACONEX E&C JV
Name of PM/ Contractor Mr. Xue Zhi Gua
Contract Amount 3,037,357,144,006 VND (inclusive of VAT & contingency)
Contract Period 1308 days (43.0 months)
Commencement date 25 March 2014
Completion date 22 October 2017
Package CW1C: Southern Approach to Cao Lanh Bridge
Name of Contractor Joint Venture of Dat Phuong – Tranimexco
Name of PM/ Contractor Nguyen Van Huong
Contract Amount 410,645,249,667 VND (inclusive of VAT & contingency)
Contract Period 1000 days
Commencement date 29 December 2014
Completion date 23 September 2017
Package CW2A: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
Km 07+800 – Km 13+750
Name of Contractor Jiangsu Provincial Transportation Engineering Group Co., Ltd.
Name of PM/ Contractor Mr. Ji Lei
Contract Amount 1,046,035,095,222 VND (inclusive of VAT & contingency)
Contract Period 1028 days
Commencement date 31 December 2014
Completion date 23 October 2017
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 77
Package CW2B: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
Km 13+750 – Km 18+200
Name of Contractor Jiangsu Provincial Transportation Engineering Group Co., Ltd.
Name of PM/ Contractor Mr. Ji Lei
Contract Amount 1,054,429,875,970 VND (inclusive of VAT & contingency)
Contract Period 1028 days
Commencement date 31 December 2014
Completion date 23 October 2017
Package CW2C: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
Km18+200 – Km23+450
–
–
Name of Contractor Joint Venture of Phuong Thanh – Quyet Tien – Anh Giang – Thang Loi
Name of PM/ Contractor Nguyen Manh Tuan
Contract Amount 1,263,959,579,550 VND (inclusive of VAT & contingency)
Contract Period 1028 days
Commencement date 29 December 2014
Completion date 21 October 2017
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 78
ANNEX 4-2: PROJECT FINANCIAL PROGRESS
The activities undertaken during the period are listed here below and estimated value of the works undertaken.
Package CW1A: Northern Approach to Cao Lanh Bridge Division BoQ Value (Incl.VAT) Value to date (Incl.VAT) Percent (%)
General Requirement 15,758,878,793 9,956,219,900.00 63.18
Site Clearing 2,974,150,197 2,852,798,979.18 95.92
Earthworks 139,463,751,221 101,968,373,499.16 73.11
Drainage Works 6,248,028,478 1,619,441,118.92 25.92
Sub base and base course 24,896,852,398 - -
Pavement 39,434,835,691 - -
Structure Works 752,867,744,944 413,480,953,093.00 54.92
Miscellaneous 13,125,446,470 - -
Lighting & Power 4,575,265,741 - -
Sub Total 999,344,953,933 529,877,786,590.27 53.02
Day works 4,556,865,885 -
Sub Total 1,003,901,819,818 529,877,786,590.27 52.78
Provisional Sums 3,235,100,000 -
Sub Total 1,007,136,919,818 529,877,786,590.27 52.61
Contingency 100,713,691,982 (15,144,301,282) -15.04%
V.O (12,388,829,173)
Adjustment price (2,755,472,110)
Total Tender Price 1,107,850,611,800 514,733,485,308.27 46.46
Package CW1B: Cao Lanh Bridge Project
Division BoQ Value (Incl.VAT) Value to date (Incl.VAT) Percent (%)
General Requirement 36,757,242,370 29,604,270,889.01 80.54
Site Clearing 1,332,742,989 342,848,429.66 25.73
Earthworks 27,395,479,432 21,658,256,136.08 79.06
Drainage Works 823,760,654 309,581,287.40 37.58
Sub base and base course 2,173,800,024 - -
Pavement 19,116,175,611 - -
Structure Works 2,556,657,602,933 1,810,950,590,841.12 70.83
Miscellaneous 3,787,454,897 - -
Lighting & Power 20,963,192,757 - -
Sub Total 2,669,007,451,667 1,862,865,547,583 69.80
Day works 10,445,715,610 -
Sub Total 2,679,453,167,277 1,862,865,547,583 69.52
Provisional Sums 81,780,600,000 28,612,474,685.30 34.99
Sub Total 2,761,233,767,277 1,891,478,022,269 68.50
Contingency 276,123,376,728 -10,261,201,710 (3.72)
V.O 3,518,398,488.00
Adjustment price (13,779,600,198.10)
Total Tender Price 3,037,357,144,005 1,881,216,820,558 61.94
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 79
Package CW1C: Southern Approach to Cao Lanh Bridge
Division BoQ Value (Incl.VAT) Value to date (Incl.VAT) Percent (%)
General Requirement 3,287,680,000 2,817,386,000.00 85.70%
Site Clearing 277,868,573 277,868,573.40 100.00%
Earthworks 69,377,009,194 49,829,027,956.24 71.82%
Drainage Works 3,090,459,510 1,456,050,750.00 47.11%
Sub base and base course 17,363,153,974 - -
Pavement 20,989,398,976 - -
Structure Works 240,598,860,434 186,343,472,883.33 77.45%
Miscellaneous 7,844,225,446 - -
Lighting & Power 6,845,307,227 - -
Sub Total 369,673,963,334 240,723,806,163 65.12%
Day works 910,800,000 -
Sub Total 370,584,763,334 240,723,806,163 64.96%
Provisional Sums 2,729,100,000 -
Sub Total 373,313,863,334 240,723,806,163 64.48%
Contingency 37,331,386,333 (1,761,750,313.40) -4.72%
V.O
1,022,381,041.00
Adjustment price
(2,784,131,354.40)
Total Tender Price 410,645,249,667 238,962,055,850 58.19%
Package CW2A: Interconnecting Road Between Cao Lanh Bridge and Vam Cong Bridge (Km7+800 - Km13+750)
Division BoQ Value (Incl.VAT) Value to date (Incl.VAT) Percent (%)
General Requirement 23,445,746,293 17,150,334,421.00 73.15%
Site Clearing 425,047,897 393,230,208.72 92.51%
Earthworks 285,432,771,638 176,650,783,109.71 61.89%
Drainage Works 13,668,803,877 239,800,885.50 1.75%
Subbase and base course 27,268,040,825 0 0.00%
Pavement 34,712,795,710 0 0.00%
Structure Works 539,069,603,571 269,785,190,826.52 50.05%
Miscellaneous 15,574,161,505 0 0.00%
Lighting & Power - 0
Sub Total 939,596,971,316 464,219,339,451 49.41%
Day works 7,564,424,340 0 0.00%
Sub Total 947,161,395,656 464,219,339,451 49.01%
Provisional Sums 3,779,600,000 212240000 5.62%
Sub Total 950,940,995,657 464,431,579,451 48.84%
Contingency 95,094,099,565 0 0.00%
Total Tender Price 1,046,035,095,222 464,431,579,451 44.40%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 80
Package CW2B: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge (Km13+750 – Km18+200)
Division BoQ Value (Incl. VAT) Value to date (Incl. VAT) Percent (%)
General Requirement 24,843,378,560 17,482,424,961.47 70.37%
Site Clearing 356,781,791 298,779,692.93 83.74%
Earthworks 235,796,643,575 189,820,656,190.12 80.50%
Drainage Works 2,317,241,881 0 0.00%
Sub base and base course 18,949,239,241 0 0.00%
Pavement 26,676,941,992 0 0.00%
Structure Works 619,146,457,269 296,193,978,870.44 47.84%
Miscellaneous 18,744,436,270 0 0.00%
Lighting & Power - 0
Sub Total 946,831,120,579 503,795,839,715 53.21%
Day works 7,884,893,940 0 0.00%
Sub Total 954,716,014,518 503,795,839,715 52.77%
Provisional Sums 3,856,600,000 212622000 5.51%
Sub Total 958,572,614,518 504,008,461,715 52.58%
Contingency 95,857,261,452 0 0.00%
Total Tender Price 1,054,429,875,970 504,008,461,715 47.80%
Package CW2C: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge (Km18+200 – Km23+450)
Division BoQ Value (Incl. VAT) Value to date (Incl. VAT) Percent (%)
General Requirement 13,535,885,000 10,496,585,000 77.55%
Site Clearing 509,559,852 690,826,047 135.57%
Earthworks 278,438,711,670 234,739,747,156 84.31%
Drainage Works 15,900,313,639 0 0.00%
Subbase and base course 42,724,491,402 0 0.00%
Pavement 58,755,940,329 0 0.00%
Structure Works 699,534,662,764 454,844,987,537 65.02%
Miscellaneous 22,056,356,713 0 0.00%
Lighting & Power 10,792,331,045 0 0.00%
Sub Total 1,142,248,252,414 700,772,145,740 61.35%
Day works 2,797,510,815 0 0.00%
Sub Total 1,145,045,763,228 700,772,145,740 61.20%
Provisional Sums 4,008,400,000 264,824,480 6.61%
Sub Total 1,149,054,163,228 701,036,970,220 61.01%
Contingency 114,905,416,322 0 0.00%
Total Tender Price 1,263,959,579,550 701,036,970,220 55.46%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 81
ANNEX 4-3: ONGOING WORKS DURING THIS PERIOD
Completed
On going
Package CW1A
No Item Jun-16 Jul-16 Aug-16
1 Dinh Chung Bridge (Bored pile at Atnutment 1)
3 Tinh Thoi Bridge (Bored pile, pilecap, pier columns, piercaps)
2 Super T Girder for Dinh Chung & Tinh Thoi Bridge
5 Driven Piles for Rach Mieu Bridge
6 Linh Son Bridge (Bored piles, pilecaps)
7 Embankment construction from Borrow
8 Vacuum Consolidation Method
9 Dinh Chung Bridge (Bored pile at Atnutment 1)
Package CW1B
No. Item North Bank Main Bridge South Bank
Jun-16 Jul-16 Aug-16 Jun-16 Jul-16 Aug-16 Jun-16 Jul-16 Aug-16
1 Surcharge for Approach Road
2 Super T Girder
3 Pilecap for P17 & P20 (Anchor Piers)
4 Pier column for P17 & P20
5 Concreting for deck slab
6 Pylon Tower P18
7 Pylon Tower P19
8 Construction for Pier table of P18 & P19
Package CW1C
No Item Jun-16 Jul-16 Aug-16
1 Embankment construction from Borrow
2 Geotextile type 2 installation
3 Construction of curb at piers
4 Construction of center media at piers
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 82
Package CW2AB
No. Typical Items june-16 July-16 August-16
1 Survey and Design of Construction Drawings 2 Separation Geotextile 12kN/m non-woven (Type 1) 3 Prefabricated Vertical Drain (PVD) 4 Vertical Sand Drain (VSD) 5 High Strength Geotextile 200kN/m / 50kN/m woven (Type 2) 6 Vacuum Consolidation Method (VCM) 7 Embankment construction from Borrow (K95) 8 Coarse sand blanket (CSB) 9 Bored Pile 1,000 mm diameter 10 Driven Precast Piles (450 mm x 450 mm) fabrication and driving
11 Bridge sub-structure construction (Pile Cap - Column Pier - Pier Head ) _ Concrete Class C30 Mpa
12 Voided slab girder fabrication - L=21m
Package CW2C
No. Typical Items june-16 July-16 August-16
1 Survey and Design of Construction Drawings
2 High strength Geotextile 200KN/m/ 50KN/m (Type 2)
3 Vacuum Consolidation Method (VCM) 4 Embankment construction from Borrow K95 5 Driven Precast Pile (300mmx300mm) 6 Bored Pile 1000mm Diameter 7 Bored Pile 1500mm Diameter
8 Bridge sub-structure construction (Pile Cap - Column Pier - Pier Head - Abutment ) _ Concrete Class C30 Mpa
9 Lap Vo Bridge (on right side)_ Cantilever box girder's segment construction [40 Mpa]
10 Super T Girder L=38.10 - 38.30 m (all Types). [ 50 Mpa ] 11 Super T Girder L=28.70 m (all Types). [50 Mpa]
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 83
ANNEX 4-4: CONTRACTOR’S MANPOWER
Package CW1A: Northern Approach to Cao Lanh Bridge
Contractor/ subcontractor
Description
Up to previous Quarter
This Quarter
OCS Actual up to date Percent
completed (%) Target date for completion
1 2 3 4=1+2 5=4/3
CONTRACTOR
+ LABORATORY
Project Manager 1 - 1 1 100%
Deputy Project Manager
3 (1.00) 3 2 67%
Translator 1 - 1 1 100%
Road Superintendent 2 - 3 2 67%
Bridge Superintendent 5 - 5 5 100%
Material Manager 1 - 1 1 100%
Office Staff 3 - 3 3 100%
Laboratory Technician 5 - 6 5 83%
Surveyor 3 - 3 3 100%
HSE Officer 1 - 1 1 100%
Total 25 -1 27 24 89%
Package CW1B: Cao Lanh Bridge Project
Contractor/ subcontractor
Description
Up to previous Quarter
This Quarter
OCS Actual up to
date
Percent completed
(%)
Target date for
completion 1 2 3 4=1+2 5=4/3
MAIN CONTRACTOR
+ LABORATORY
Project Manager 1 -
1 1 100%
Quality Control Manager 1 -
1 1 100%
Superstructure Engineer of Cable Stayed Bridge
1 -
1 1 100%
Geotechnical or Foundation Engineer
1 -
1 1 100%
Bridge Superintendent 1 -
1 1 100%
Material Manager 1 -
1 1 100%
Engineer + Manager 41
(21) 41 20 49%
Officer 6 -
6 6 100%
Laboratory 1 -
1 1 100%
Surveyor 2 -
2 2 100%
Operator 4
1 4 5 125%
Labor + Worker 38
(2) 38 36 95%
Total 98 -22 98 76 78%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 84
SUB-CONTRACTOR
624
Project Manager 1 1 1 100%
Engineer + Manager 5 8 5 63%
Officer 1 2 1 50%
Laboratory 1 2 1 50%
Surveyor 1 2 1 50%
Operator 2 2 2 150%
Labor + Worker 32 31 32 116%
Total 43 48 43 90%
SUB-CONTRACTOR
BRIDGE 12
Project Manager 01 01 01 100%
Engineer + Manager 10 17 10 59%
Officer 07 07 07 100%
Laboratory 0 03 0 0%
Surveyor 03 05 03 60%
Operator 37 38 37 97%
Labor + Worker 221 300 221 40%
Total 179 371 179 48%
SUB-CONTRACTOR
SONG DA THANG LONG
Project Manager 0 - 0 0 -
Waiting for construction
of 02 Abutments
Engineer + Manager 1 1 1 100%
Officer
Surveyor
Operator
Labor + Worker 29%
Total 1 1 1 100% 2016.02
HOANG HAI JSC
Project Manager 01 - 01 01 100%
Engineer + Manager 04 - 02 04 200%
Officer 01 01 01 100%
Surveyor 02 02 02 100%
Operator 05 -3 05 02 100%
Labor + Worker 10 - 10 10 59%
Total 23 - 23 23 100%
TUAN LOC COMPANY
Project Manager 1 1 1 100%
Deputy Project Manager 2 1 2 200%
Engineer + Manager 9 8 9 113%
Surveyor 2 1 2 200%
Labor + Worker 88 - 54 88 148%
Total 102 - 65 102 100%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 85
Package CW1C: Southern Approach to Cao Lanh Bridge
Contractor/ subcontractor
Description
Up to previous Quarter
This Quarter
OCS Actual up
to date
Percent completed
(%)
Target date for
completion 1 2 3 4=1+2 5=4/3
CONTRACTOR + LABORATORY
Project Manager 1 - 1 1 100%
Vice Project Manager 1 - 1 1 100%
Quality Control Manager 1 - 1 1 100%
Geographical or Foundation Engineer
2 - 2 2 100%
Bridge Engineer 1 - 1 1 100%
Material Manager 4 - 4 4 100%
Road Engineer 1 - 1 1 100%
Quantity/Payment Engineer 3 - 3 4 75%
Head of Laboratory 1 - 1 2 50%
Environmental Officer 1 - 1 1 100%
Safety Officer 1 - 1 1 100%
Survey Engineer 2 - 2 2 100%
Test Engineer 2 - 2 2 100%
Workers 21 - 21 23 91%
Total 42 0 42 46 110%
Package CW2AB: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
Contractor/ subcontractor
Description
Up to previous Quarter
This Quarter
OCS Actual up to date
Percent completed (%)
Target date for
completion 1 2 3 4=1+2 5=4/3
MAIN C0NTRACTOR
Project Manager 1 0 1 1 100%
De. Project Manager 1 0 1 1 100%
Bridge Engineer/ Assistant (Ass.) 2 0 2 2 100%
QS engineer 3 0 3 3 100%
QC engineer 3 2 3 3 100%
Surveyor 3 0 3 3 100%
Geotechnical or Foundation Engineer (Ass.)
1 0 2 1 200%
Material Engineer/ Ass. 2 0 2 2 100%
Site engineers 6 0 6 6 100%
officer 6 3 6 6 100%
Safety engineers 1 0 2 1 200%
Environmental engineer 1 0 1 1 100%
Sub total 1 30 0 32 30 107%
SUB C0NTRACTORS
Engineer 48 0 50 48 104%
Worker 179 70 250 249 100%
Sub total 2 227 70 300 297 100%
Total 254 70 332 327 95%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 86
Package CW2C: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge (Km18+200 – Km23+450)
Contractor/ subcontractor
Description
Up to previous Quarter
This Quarter
OCS Actual up to date
Percent completed
(%)
Target date for
completion 1 2 3 4=1+2 5=4/3
MAIN PROJECT MANAGEMENT
BOARD
Project Manager 1 1 1 100.00%
De. Project Manager 3 2 3 66.67%
Bridge engineer 7 5 7 71.43%
Geotechnical/ Foundation Engineer
1 0 2 1 200.00%
Material Engineer/ Laboratory manager
1 0 0 1 0%
QC Manager 2 1 2 50.00%
Road engineer 1 1 1 100.00%
QS engineer 7 5 7 71.43%
Office staff 2 2 2 100.00%
Surveyor engineer 6 6 6 100.00%
Safety engineers 4 3 4 75.00%
Environmental engineer 1 1 1 100.00%
Head of Laboratory 1 0 1 0.00%
Site engineers 1 2 1 200.00%
Site Manager 4 4 4 100.00%
Design engineer 5 5 5 100.00%
Sub total 1 47 0 40 47 117.50%
JV MEMBERS
Skilled Worker for bridge construction
185 268 185 69.03%
Skilled Worker for road construction
61 61 4 212 65
Sub total 2 246 4 480 250 52.08%
Total 293 4 520 297 57.12%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 87
ANNEX 4-5: CONTRACTOR’S PLANT AND EQUIPMENT
Package CW1A: Northern Approach to Cao Lanh Bridge
Contractor/ subcontractor
Equipment Details
Up to previous Quarter
This Quarter
OCS Actual up to date
Percent completed (%)
Planned date of
completion 1 2 3 4=1+2 5=4/3
HOANG AN
Excavator Kobelco SK220
3 - 2 3 150%
Crane 3 - 2 3 150%
Bulldozer Komatsu D30T15
2 - 2 2 100%
Roller XCMG XS142J
1 - 1 1 100%
Barge 2 - 1 2 200%
Mix truck 5 - 5 5 100%
Shovel Excavator 1 - 0 1
Substation 2 - 2 2 100%
Concrete batching Plant
3 - 2 3 150%
PVD machine 1 - 1 1 100%
TUAN LOC
Crane 4 - 3 4 133%
Mix truck 5 - 5 5 100%
Excavator Sumitomo 0,5 3 - 3 3 100%
Shovel Excavator 1 - 0 1
Substation 2 - 2 2 100%
Concrete batching Plant
3 - 2 3 150%
THANG LONG
Excavator Hitachi 07 1 1 2 2 100%
Bulldozer Komatsu D30T15
4 (3) 1 1 100%
Roller Liugong 5 (3) 2 2 100%
Barge 3 (1) 1 2 200%
Mix truck 2 - 2 2 100%
Excavator Kobelco SK220
3 - 2 3 150%
Package CW1B: Cao Lanh Bridge
Contractor/ subcontractor
Equipment Details
Up to previous Quarter
This Quarter
OCS Actual up to date
Percent complete
d (%)
Planned date of
completion 1 2 3 4=1+2 5=4/3
MAIN CONTRACT
OR
Mixing Truck 6m3 3 4 3 75%
Generator 200KW/250KVA 1 1 1 100%
Loader ZL50CN 1 2 1 50%
Cooling system DAKIN60HP 1 1 1 100%
Mixing plant HZS90JZ 1 1 1 100%
Mixing plant 60m3 1 1 1 100%
SUB-CONTRACT
OR 624
Drilling machine KH180-3 0 0 0 #DIV/0!
Crane KH180-3 2 2 2 100%
Barge Minh Phong 1 1 1 100%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 88
Excavator Kobelco SK220 1 1 1 100%
Mixed Truck Truong Hai 1 1 1 100%
Bentonite Tank 0 0 0
D1500 bored pile complete
d
Generator Denyo 1 1 1 100%
Other IHI-IPD100
1 1 1 100% KOBELCC
SUB-CONTRACT
OR BRIDGE 12
Drilling machine Bauer680, RCD S500
& S600. 1 - 2 1 50%
Crane Dek631,QY25E,
KOBELCO 7055, HITACHI-KH180
3 - 5 3 60%
Barge 650T 3 3 3 100%
Excavator Komatsu PC200 1 - 2 1 50%
Batching plant 60m3/h 2 - 2 2 100%
Batching plant 90m3/h 1 - 1 1 100%
Loader XCMG LW300F 1 - 2 1 50%
Mixed Truck Kamaz 6 6 6 100%
Bentonite Tank 30m3 3 - 3 3 100%
Generator 175/250Kw 1 - 3 1 33%
Gantry Crane 1 - 1 1 100%
Auto-climbing formwork
VITRAVICO 1 - 1 1 100%
Tower Crane Dahan DH 7027 2 - 2 2 100%
Hoist VPV 100N 1 - 1 1 100%
Other (Bulldozer) 0 - 2 0 0%
Ruler vibrator 2 2 2 100%
Spud vibrator 4 2 4 200%
Pump 6 4 6 150%
SUB-CONTRACTOR SONG DA THANG
LONG
Drilling machine Soilimeco R625 0 0 0%
Crane Sumitomo 307 0 0 0%
Excavator Huyndai HX80 0 0 0%
Bentonite Tank 3 3 3 100%
Generator Mitsubishi-Japan 1 1 1 100%
Other Crane PUYUINGY25 0
HOANG HAI JSC
Excavator Kobelco SK07 01 01 01 100%
Bulldozer Komatsu PC200 02 02 02 200%
Roller LiuGong-CLG614 01 01 01 100%
Sewing machine HV-T01 - - - -
Gradienter Leica Jogger 24 - - - -
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 89
Tachometer Nikon Tx02 - -
PVD - - - -
SD - - - -
TUAN LOC COMPANY
Drilling machine Hitachi DCH 1000 0 0 0 -
Drilling machine Kobelco 1000 0 0 0 -
Service crane
IHI CCH 2000, HITACHI KH150-3,
SUMITOMO LS120RHD
2
4
2
50%
Excavator Kobelco 0.7m3 0 2 0 0%
Generator 1 4 1 25%
Vibrating hammer 60KVA, 90KVA 2 4 2 50%
Mixing plant On floating 1 2 1 100%
Barge 4 5 4 80%
Pump 2 4 2 50%
Concrete Pump 2 3 2 66.7%
Bentonite tank
Auto-climbing formwork
1 1 1 100%
Package CW1C: Southern Approach to Cao Lanh Bridge
Contractor/ subcontractor
Equipment Details
Up to previous Quarter
This Quarter
OCS Actual up
to date
Percent completed
(%) Planned date of completion
1 2 3 4=1+2 5=4/3
DAT PHUONG
Cement Concrete Mixing Plant
60m3/h 1 0 1 1 100%
Wheel Loader 2,3m3 1 0 1 1 100%
Crane 35-55T 3 -1 1 2 200%
Drilling Machine (D1500) 1,5m 0 2 2 2 100%
Concrete Pump 100m3/h 0 2 1 2 200%
Mix Truck 6m3 2 2 2 4 200%
Gantry Crane For Casting Yard
100T 0 2 1 2 200%
Crane for Launching Beam 100T 0 2 1 2 200%
TRANIMEXCO
PVD 30 m 0 2 1 2 200%
SD 35 m 0 2 1 2 200%
Bulldozer 140 HP 1 1 2 2 100%
Motor Grader 105 KW 0 1 1 1 100%
Excavator 1,25-2m3 1 1 2 2 100%
Truck 10-13T 0 4 1 4 400%
Pumping sand machine 1 1 2 2 100%
Vibrating roller 4 -2 3 2 67%
Tyred Roller 0 2 1 2 200%
Asphalt hot mix plant 40TPH 0 1 1 1 100%
Aggregate Spreader 50-60m3/h 0 1 1 1 100%
Asphalt Spreader 9m 0 1 1 1 100%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 90
Package CW2AB: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
Contractor/ subcontractor
Equipment Details
Up to previous Quarter
This Quarter
OCS Actual up to date
Percent completed
(%) Planned date of completion
1 2 3 4=1+2 5=4/3
MAIN CONTRACTOR
+ SUB-
CONTRACTOR
Cement Concrete Batching Plant
≥ 30 m3/h -
4 0 4 4 100% -
Bulldozer ≥ 110 HP - 5 0 32 5 16% -
Excavator ≥ 0.8 m3 - 20 0 26 20 77% -
Dump Truck ≥ 12 t - 0 0 30 0 0 -
Macadam Spreader - 0 0 16 0 0 -
Motor Grader ≥108CV - 4 0 9 4 44%
Steel Wheel Roller ≥ 12 t - 8 0 56 8 14% -
Water Tank Truck ≥ 5 m3 - 0 0 6 0 0 -
Concrete Mix Truck ≥ 6 m3 - 10 0 11 10 91% -
PVD Machine - 7 -5 8 2 25% -
SD Machine - 5 -3 11 2 18% -
Excavator ≥ 1.25 m3 - 0 0 8 0 0 -
Vibrating Roller ≥ 10 t - 0 0 32 0 0 -
Hot Mixing Asphalt Plant ≥ 120 ton/h
- 0 0 2 0 0 -
Vacuum Pump & Generator - 4 0 12 4 33% -
Concrete Pump Truck ≥60 m3/h - 4 0 7 4 57% -
Concrete Mix Truck - 10 0 11 10 91% -
Bored Pile Drilling Machine - 9 0 11 9 82% -
Launching Girder Frame - 1 0 6 1 17% -
Pile Driving Machine - 1 0 9 1 11% -
Crane ≥ 25 ton - 11 0 16 11 69% -
Unit Truck Crane 4 0 4 4 100%
Trailer (For transporting Girder) 2 0 2 2 100%
Asphalt Paver Finisher ≥ 4.2 m 0 0 0
Rubber Tire Roller ≥ 15 t 0 0 0
Barges ( For transporting Sand Material )
0 0 0
Total 109 -8 329 101 31% -
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 91
Package CW2C: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge
No Machinery & Equipment Unit Up to previous Quarter THIS Quarter Actual up to date
OCS Percent
(%) Target
completion PT QT AG TL PT QT AG TL PT QT AG TL
I Equipment for Bridge construction
1 Bored pile equipment D1,5m set 1 2 2 1 0 0 0 0 1 2 2 1 2 300.00%
2 Concrete Batching Plant nos 1 2 0 0 0 0 0 0 1 2 0 0 2 150.00%
3 Front Loader nos 1 2 0 0 0 0 0 0 1 2 0 0 4 75.00%
4 Barge ≥ 250T nos 1 1 0 0 0 0 0 0 1 1 0 0 1 200.00%
5 Crawler or Mobile Cranes nos 3 3 2 0 0 0 0 0 3 3 2 0 3 266.67%
6 Vibration hammer machine nos 2 1 1 1 0 0 0 0 2 1 1 1 3 166.67%
7 Mono Hydraulic Jack ≥24T set 2 2 2 2 0 0 0 0 2 2 2 2 5 160.00%
8 Formwork of Voided Slab Girder set 0 0 2 0 0 0 0 0 0 0 2 0 4 50.00%
9 Gantry Crane 100T set 1 1 1 0 0 0 0 0 1 1 1 0 5 60.00%
10 Transformer Station ≥250KVA nos 2 1 1 0 0 0 0 0 2 1 1 0 3 133.33%
11 Mixer nos 4 5 0 0 0 0 0 0 4 5 0 0 8 112.50%
Total I nos 18 20 11 4 0 0 0 0 18 20 11 4 40 132.50%
II Equipment for Road construction
1 PVD installation rig ≥ 30m nos 1 1 1 1 0 0 0 0 1 1 1 1 2 200.00%
2 Sand drain rig ≥35m nos 2 1 2 1 0 0 0 0 2 1 2 1 2 300.00%
3 VCM equipment set 1 0 0 0 0 0 0 0 1 0 0 0 1 100.00%
4 Bulldozer nos 1 1 2 1 0 0 0 0 1 1 2 1 3 166.67%
5 Excavator nos 2 2 5 2 0 0 0 0 2 2 5 2 6 183.33%
6 Vibrating roller nos 2 2 2 1 0 0 0 0 2 2 2 1 4 175.00%
Total II 9 7 12 6 0 0 0 0 9 7 12 6 18 188.89%
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 92
ANNEX 4-6: SOURCE MATERIAL APPROVALS
Package CW1A: Northern Approach to Cao Lanh Bridge
No. ITEM SOURCE TO BE USED FOR REMARK
1 Steel reinforcement Pomina grade 60; Hoa Phat steel
(CB500V) Concrete structure Approved
2 Sonic Pipe T190 Concrete structure Approved
3 Admixture
Sika visco-3000M-20, Sikaplast 257 Concrete structure Approved
Mighty 3000-PC2 Concrete structure Approved
Mighty 3000-RC Concrete structure Approved
4 Portland Cement Holcim, HaTien, Nghi Son PCB40 Concrete structure Approved
5 Bentonite Truong Thinh, Nam Toan Thang, TECO-
API Bored Pile Approved
6 Coarse Aggregate Ba Ria - Vung Tau Concrete structure Approved
7 Fine Aggregate Tan Chau -An Giang province Concrete structure Approved
8 Water source Tap water, Living water Concrete structure Approved
Well water at Trung Liem batching plant Concrete structure Approved
9 Embankment material (VL K95) Tien Giang source Embankment construction Approved
10 Geotextile fabric and PVD
ART, VNT Viet Nam, DJL 20, GET 20; Ficon Miltec (A5, A7), DML20 from
Daeyoun Geotech, VID DRAIN 75 PVD from ART, VID DRAIN 4.0 from ART
Embankment construction Approved
11 Cohesive slope material On site Embankment construction Approved
12 Steel plate for permanent casing
and connection box Tangshan Yanshan Iron Steel Co.Ltd. Concrete structure Approved
13 Pipe culvert Hung Vuong Construction Ltd Pipe culvert Approved
14 Bridge bearing
ESCO Ltd. Korea, BRC Rubber Mechanical
Joint Stock Company(Viet Nam), Taiwan-Pillar pot bearing
Bridge bearing Approved
15 Pc Strand (15.24 ; 15.27 ; 15.7) Quy Chau factory (China); Dong-IL factory;
Kiswire (Malaysia), Siam (Thailand) Used for Bridge Approved
16 Anchorage QVM Hangzhou Zhemao(China), Guangxi
Liugong Group Used for Bridge Approved
17 Rubber Bearing - Pot Bearing -
Expansion Joint Deakyoung (Korea); Vinh Hung (Viet
Nam); Kawakin (Vietnam) Used for Bridge Approved
18 Elastomeric bearing BRC rubber mechanical corporation Used for Bridge Approved
19 HDPE pipe Truong Phat Company Soft soil treament Approved
20 Crushed sand Antraco _Angiang Concrete Approved
21 Coarse Aggregate BBC (Binh Duong) Concrete Approved
22 Bearing Steel Plate TangShan YanShan Iron Steel Co.Ltd
China Used for Super T girder Approved
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 93
Package CW1B: Cao Lanh Cable-stayed Bridge
No. ITEM SOURCE TO BE USED FOR REMARK
1 Steel reinforcement Vinakyoei, Pomina, Hoa Phat Concrete structure Approved
2 Sonic Pipe T190; Hoa Phat Concrete structure Approved
3 U bolt Hieu Hung, Song Da-Hoa Phát Bored Pile Approved
4 Coupler Vinakuoei, Lien Luc,Song Da-Hoa Phát Bored Pile Approved
5 Admixture Sikamen NN, Sikaplat 257,
Concrete structure Approved
Basf ,Mighty, Basf 8713 (C50) Approved
6 Portland Cement Nghi Son, Holcim, But Son, HaTien Concrete structure Approved
7 Bentonite Truong Thinh, Viet Long, A-Ben-C
Bored Pile Approved
Indian, Australia Approved
8 Coarse Aggregate BBC, Vung tau
Concrete structure Approved
Antraco Approved
9 Fine Aggregate
Dong nai & Tan Chau -An Giang province Concrete structure
Approved
Co To An Giang province Approved
Antraco – An Giamg Concrete structure Waiting for testing
source result
10 Water source
Deep well ,water Processing factory for north side
Concrete structure
Approved
Deep well ,water Processing factory for south side
Approved
11 Embankment material (VL
K95) Tien Giang source
Embankment construction
Approved
12 Geotextile fabric and PVD VNT Viet Nam; Fotai Taiwan Embankment construction
Approved
13 Permanent casing D2500 Nippon sumakin Viet Nam Bored Pile (D2500) Approved
14 PC strand (15.24 & 15.27)
Guizhou Wire Rope (China) Pylon, Tie-down Pier, Superstructure of main
Bridge
Approved
Siam (Thailand) Approved
Kiswire (Korea), Kiswire( Malaysia) (15.7mm)
Prestressed concrete Waiting for testing
source result
15 Anchorage
QVM Hangzhou (China),
Deck of Main Bridge
Approved
Freyssinet (France) The related document has
been submitted, the engineer has
comment and need to visit factory, take
samples & test
XinJin Teng Zhong Transportation Construction Cooperation (China), Liuhou
VLM Pretressing (China)
16 Rubber Bearing and Pot
Bearing:
Mageba (Switzerland), Bearing
Waiting for testing source result Kawakin (Japan)
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 94
Mechanical pot bearing-Freyssinet (France)
Elastomeric Bearing and Mechanical (Seoul - Korea)
Approach bridges Approved
17 Bridge expansion joint Mageba (Switzerland)
Expansion Waiting for testing
source result CIPEC Freyssinet (France)
18 Macadam for Base & Subbase
Filling Bien Hoa Base & Subcase
Waiting for testing source result
19 Steel Plate for Permanent
casing D1500 JIANGSU SHAGANG GROUP Bored Pile Approved
20 Steel Plate for Permanent
casing D2500 NIPPON STEEL & SUMIKIN Bored Pile Approved
21 Geotextile fabric and PVD THAI CHAU TMPORT-EXPORT CO.,LTD Roadbed Approved
22 Current cohesive slope North side and south side Embankment Approved
23 Non- shrink grout, type A Sika grout 214-11 Bearing pad Approved
24 Lightning rod, Lightning
conductor, and Earth electrode for lightning
Viet Nam, Turker Lightning protection Approved
25 Ducts Long Ngoc Phu Producing Trading
Company Limited To cover pre-stress
cable Waiting for testing
source result
26 Anchorage and damper Freyssinet products Stay cable system Waiting for testing
source result
27 Stay cable ARCELORMITTAL Stay cable system Waiting for testing
source result
28 HDPE tube SOTRA-SPEREF, DYKA PLASTIC Stay cable system Waiting for testing
source result
29 PC bars D36, D47, D57, D65
Germany, Singapore Pylon Waiting for testing
source result
Sas Asia Bar Systems Pte. LTD (Germany)
BBV Systems Co. LTD (Thailand) Pylon tower
Waiting for testing source
30 Stayed cable Kiswire (Malaisia) Main bridge Accepted source
31 Formwork tube and steel plate SHIJIAZHUANG HONGLIJIA(China) Stayed cable Accepted source
32 Elastomeric Bearing Unison (Korea) Main bridges Waiting
33 Steel plate INNER MONGOLIA BAOTOU STEEL UNION Co. Ltd (China)
Super T girder Waiting
34 Drainage System and Galvanized Dowel
Minmetals Yingkou Medium Plate Co. , Ltd. Manufacturer: Le Minh Construction One Member Co., Ltd., -Manufacturer: The First Chemical Plastic Co., Ltd.
Bridge Drainage System and pier head
Waiting
35 Ladder inside Pylon Thanh Loc Mechanical Manufacture Co., Ltd
Pylon tower Waiting
36 Sika Sikadure 732 Protection of
Prestressing Waiting
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 95
Anchorages
37 Material source Traveler Fahrication Manufacturer Hieu Hung
Traveler Fahrication Accepted source
38 Material source Ladder and cable tray Lighting power system Accepted source
39 Material source Minmetals Yingkou Medium Plate Co. , Ltd. Manufacturer: Le Minh Construction One Member Co., Ltd., -Manufacturer
Drainage system Accepted source
Package CW1C: Southern Approach to Cao Lanh Bridge
No. ITEM SOURCE TO BE USED FOR REMARK
1 Steel reinforcement Pomina, Vina Kyoei, Hoa Phat Concrete structures Approved
2 Sonic Pipe No190, Hoa Phat Concrete structures Approved
3 U bolt Hieu Hung Bored Piles Approved
4 Admixture
Sikaplat 257, Sika NN Concrete structures
Approved
Mighty Approved
Grace Mira 188, Basf Bored piles Approved
5 Portland Cement Holcim, HaTien, Nghi Son Concrete structures Approved
6
Bentonite Truong Thinh, Viet Long
Bored Piles Approved
Indian, Australia Approved
7 Coarse Aggregate Ba Ria-Vung Tau, BBC Binh Duong
Concrete structures Approved
8 Fine Aggregate, CSB Tan Chau –An Giang province, Dong Nai
Concrete structures Approved
9 Water source Tap Water, Deep well water Concrete structures Approved
10 Embankment material (VL K95) Tien Giang source Embankment construction Approved
11 Geotextile fabric and PVD VNT Viet Nam, ART, DML20, GET 20, VID 75, VID 65, PP25, Fonta VN
Embankment construction Approved
12 Coarse sand blanket Tan Chau –An Giang province Soft soil treatment Approved
13 HDPE pipe Tan Tien Soft soil treatment Approved
14 Coupler Tran Huy Concrete Structure Approved
15 PC strand SIAM (Thailand) Concrete Structure Approved
16 Elastomeric bearing Kien Kiet, BRC, Pillar-Taiwan, Samil-Tech (Korea), BRC
Concrete Structure Approved
17 Pot bearing Pillar (Taiwan), Samil (Korea) Concrete Structure Approved
18 Slope Protection Local Soil Road Works Approved
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 96
Package CW2AB: Interconnecting road between Cao Lanh and Vam Cong Bridges
No. ITEM SOURCE TO BE USED FOR REMARK
1 High strength Woven Geo-textile 200/50kN/m
Daejung Company Limited (DJL – Korea) Soft soil treatment Approved
2 High strength Woven- Geotextile DML20-Korea
Deayoun Geotech Co., Ltd -Korea Soft soil treatment Approved
3 High Strength Woven – Geotextile GET20
Viet Nam geotextile joint Stock company Soft soil treatment Approved
4 Woven Geo-textile 25kN/m Dong Phuong Company Limited(PP - Viet Nam)
Soft soil treatment Approved
5 Non-woven Geo-textile 12kN/m TencateGeosynthetics Asia Sdn. BHD (SP 34 Tencate – Malaysia)
Soft soil treatment Approved
6 Non-Woven- Geotextile VNT24 VNT Investment and Trading Joint Stock company (Viet Nam).
Soft soil treatment Approved
7 Non-Woven- Geotextile ARITEX12 Viet Nam geotextile joint Stock company Soft soil treatment Approved
8 HDPE pipe for horizontal ditch Ba An Joint Stock Company Soft soil treatment Approved 9 PVD-VD55R-C SPE-VINA Co., Ltd Soft soil treatment Approved
10 PVD-VD70R-C SPE-VINA Co., Ltd Soft soil treatment
with VCM Approved
11 VID RID 4.0 Viet Nam geotextile joint Stock company Soft soil treatment
with VCM Approved
12 Airtight Geo-membrane (Airtight Sheet) Yansheng City Hengsheng plastic Product Co. Ltd - China
Soft soil treatment
with VCM Approved
13 The geotextile for covering the Filtration Pipe D50
Yansheng City Hengsheng plastic Product Co. Ltd - China
Soft soil treatment
with VCM Approved
14 Plastic Pipe D75 Binh Minh Joint stock company Road soft soil
treatment for VCM Approved
15 Steel reinforcement Pomina, Vina Kyoei, Hoa Phat Concrete structure Approved
16 PC strand
Siam (12.7mm, 15.24mm) - Thailand Concrete structure Approved
Kiswire (12.7mm, 15.24mm) - Malaysia Concrete structure Approved
Dong ILL (12.7mm) - Korea Concrete structure Approved 17 U bolt Cuong Dung Company Concrete structure Approved
18 Sonic pipe Sonic Tube (T190 steel pipes Co.,ltd) Concrete structure Approved
Sonic Tube D114.3/107.3 (Hoa Phat) Concrete structure Approved
19 Steel plate for precasting concrete pile Tangshan yanshan Iron & steel Co., Ltd(China)
Concrete structure Approved
20 Portland Cement Holcim, Nghi Son, Ha Tien Concrete structure Approved
21 Coarse Aggregate Ba Ria - Vung Tau Concrete structure Approved 22 Fine Aggregate Tan Chau - An Giang Concrete structure Approved
23 Black sand TienGiang River Embankment construction
Approved
24 Sand for Coarse Sand Blanket (CSB) & Sand Drain (SD)
Phu Tan–An Giang Embankment construction
Approved
Tan Chau medium sand source Embankment construction
Approved
25 Admixtures
Sikament NN, Sika intraplast Z-HV Concrete structure Approved
Mighty 3000 RC, Mighty 3000 PC2 Concrete structure Approved Sikaplast 257, Sikament Visconcrete 3000-20M
Concrete structure Approved
26 Water for concrete and curing Tap water & Drilled The Water Well Concrete structure Approved
27 Bentonite TECO-API BENTONITE POWDER, POWDER Indian
Concrete structure Approved
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 97
Package CW2C: Interconnecting road between Cao Lanh Bridge and Vam Cong Bridges
No. ITEM SOURCE/ SUPPLIER TO BE USED FOR REMARK
1 Steel reinforcement Pomina, Vinakyoei Concrete Structure Approved
2 PC strand Siam_Thailan (15.24), Dong ILL_Korea (15.24), Hunan _China
(15.24) Concrete Structure Approved
3 Duct Pipe Long Ngoc Phu Concrete Structure Approved
4 Concrete Batching plant No.1 (Phuong Thanh), Batching plant No.2
(Quyet Tien) Batching plant No.3 (Quyet Tien) Concrete Structure Approved
5 Portland Cement Holcim, HaTien, Nghi Son Concrete Structure Approved
6 Coarse Aggregate BBC - Vung tau, Atraco - An Giang Concrete Structure Approved
7 Fine Aggregate Tan Chau (E=2.3-3.1)-An Giang Concrete Structure Approved
8 Admixture
SikaPlast 257,Viscincrete 3000-20M, Sikament NN, Intraplast Z-HV
Concrete Structure Approved
Mighty 3000RC, 3000PC2 Concrete Structure Approved
BaSF Master Glenium Sky 8735BaSF, Master Glenium Sky 8713 Concrete Structure Approved
9 Water Tap Water, drilled well water Concrete Structure Approved
10 Pot Bearing Kawakin Core-Tech Co.,Ltd (Japan) Bridges Approved
11 Sonic Pipe T190 Bored Pile Approved
12 Ubolt Cuong Dung Company, Le Minh Company Bored Pile Approved
13 Bentonite Truong Thinh, Viet Long, POWDER API – India, TECO -
Bentonite API Powder Bored Pile Approved
14 Permanent Casing for bored
pile D1.5m Jiangsu Shagang Group - China Bored Pile Approved
15 Embankment material (VL
K95) TienGiang source
Embankment construction
Approved
16 Base course Antraco - An Giang Embankment construction
Approved
17 Coarse sand Blanket and
Sand Drain Tan Chau -An Giang Soft Soil Treatment Approved
18 PVD FCM A5– FeconMiltec; VID 75 – Aritext Viet Nam Soft Soil Treatment Approved
LD70-Sungwoo TM - South Krea Soft Soil Treatment Approved
19 Geotextile fabric
Non woven geotextile ART12– Aritext Viet Nam Soft Soil Treatment Approved
Non woven geotextile VN24 - VNT Viet Nam Soft Soil Treatment Approved
Separation Woven Geotextile PP25 (25KN)- Fonta Viet Nam company
Soft Soil Treatment Approved
Commercial investment joint stock company VNT (Nonwoven Geotextile PET15)
Soft Soil Treatment Approved
Commercial investment joint stock company VNT (Nonwoven Geotextile PET30)
Soft Soil Treatment Approved
Viet Nam Geotextile Joint Stock Company (High Strength Woven Geotextile GET20)
Soft Soil Treatment Approved
20 Airtight Sheet - Geomembrane
Luoyang three Rainbow High - Techmaterial Equipment Co., Ltd Soft Soil Treatment Approved
21 The Geotextile for covering of
Filter pipe D50 Wuxi Chenglong Pipe Co.,Ltd Soft Soil Treatment Approved
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 98
ANNEX 4-7: SUMMARY OF MATERIAL TEST RESULTS
Package CW1A
Result of Testing in Laboratory
No. Description of tests This
Period Previous Quarter
Cumulative Pass Fail Frequency/ Quantity
1 Concrete compressive strength at 7 days with Class C30,C25, C35,C40,C10,C20
208 368 576 576 0 18 samples/1 Pile
2 Concrete compressive strength at 28 days with Class C30,C25, C35, C40, C10, C20
192 473 665 665 0 18 samples/1 Pile
3 Sonic grout 70 66 136 136 0 9 samples/1 Mix
design
4 Testing samples cement on plant 16 42 58 58 0 1 sample/ lot
5 Testing samples fine aggregate on barge and Coto fine stone
9 43 52 52 0 1 sample/ Barge
6 Testing samples coarse aggregate on barge
19 44 63 63 0 1 sample/barge
7 Testing samples source at the site 0 27 27 27 0 1 sample/Source
8 Reinforcing steel bar 25 111 136 136 0 1 sample/50ton
9 Sonic pipe 2 10 12 12 0 1 sample/delivery
10 Testing samples bentonite at the site 0 68 68 68 0 1 sample/delivery
11 PDA test 21 0 21 21 0
12 Coring and Testing at Pile Base per pile 149 0 149 149 0
13 Sonic test 26 123 149 149 0 1 test/pile
14 Testing sample black sand on barge 55 256 311 311 0 1 test/1000m3
15 Testing sample coarse sand on barge 12 108 120 114 6 1 test/500m3
16 Testing samples water at the site 18 23 41 40 1 1 sample/month
17 Testing sample PC strand 2 7 9 9 0 1 test/20T
18 Testing Soil sloped surface of the embankment
2 20 22 22 0 1 test/1000m3
19 Geotextile none woven 8 32 40 40 0 1 test/10000m2
20 PVD Ficon Miltec (A5, A7) 0 10 10 10 0 1 test/100,000m
21 Steel plate 0 8 8 8 0 1 test/50T
22 Pot bearing 4 0 4 4 0 1 test / 25 each
23 Elastomeric bearing 3 0 3 3 0 1 test / 50 each
24 Bearing Steel Plate for super T 1 0 1 1 0 1 sample/50ton
Results of Concrete Mix Design Tests
No. Description of Tests This Period Previous Quarter
Cumulative
Total Remarks
1 Concrete Class C30 for D1500 0 16 16 Passed
2 Concrete Class C 30 for pile 45x45 cm 0 1 1 Passed
3 Concrete Class C50 for super T girder, precast girder 0 6 6 Passed
4 Concrete Class C20 for other item 0 6 6 Passed
5 Concrete Class C10 for Blinding concrete 0 4 4 Passed
6 Concrete Class C35 for other item 0 4 4 Passed
7 Concrete Class C25 for other item 0 4 4 Passed
8 Concrete Class C40 for other item 0 3 3 Passed
9 Concrete Class C30 for other item,using crushed sand 3 0 3 Passed
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 99
Antraco
10 Concrete Class C10 for Blinding concrete, using crushed sand Antraco
3 0 3 Passed
11 Concrete Class C35 for other item ,using crushed sand Antraco
3 0 3 Passed
12 Concrete Class C25 for other item, using crushed sand Antraco
3 0 3 Passed
13 Concrete Class C40 for other item, using crushed sand Antraco
3 0 3 Passed
Package CW1B
Result of Testing in Laboratory
No. Description of tests This
Period Previous Quarter
Cumulative Pass Fail Frequency/
Quantity
1 Concrete compressive strength at 7 days with Class C30,C10,C35, C50, C25
102 1815 1917 1916 1 9 samples/1 pile
2 Concrete compressive strength at 28 days with Class C30,C10, C35, C50
129 1770 1899 1899 0 9 samples/1 pile
3 Testing samples cement on barge 16 215 231 231 0 1 sample/400ton
4 Testing samples fine aggregate on barge and Coto fine stone
5 173 178 169 9 1 sample/barge
5 Testing samples coarse aggregate on barge 5 184 189 186 3 1 sample/barge
6 Testing samples source at the site 4 53 57 57 0 1 sample/month
7 Reinforcing steel bar 54 680 734 732 2 1 sample/50ton
8 Sonic pipe 0 63 63 63 0 1 sample/delivery
9 Testing samples bentonite at the site 0 16 16 16 0 1 sample/delivery
10 Koden test 0 48 48 48 0 1 test/pile
11 Sonic test 0 304 304 304 0 1 test/pile
12 Testing sample black sand on barge 0 111 111 111 0 1 test/1000m3
13 Testing sample coarse sand on barge 0 41 41 39 2 1 test/500m3
14 Testing samples water source at the site 5 56 61 56 0 1 sample/month
15 Testing sample PC strand 36 40 76 40 0 1 test/ 20T
16 Testing sample Elastomeric pad bearing 3 12 15 12 0 1 test/50 sets
17 Testing sample pot bearing 0 12 12 12 0 1 test/25 sets
18 Testing sample PC bar D36, D47, D57, D65 0 8 8 8
19 Testing sample pylon’s fromwork tube and bearing plate
0 2 2 2 0 1 test/25 sets
Results of Concrete Mix Design Tests
No. Description of Tests This Period Previous Quarter
Cumulative
Total Remarks
1 Concrete Class C30 for D1500 0 18 18 Passed
2 Concrete Class C 35 for D2500 0 18 18 Passed
3 Concrete Class C 30 for cap pile and pier 0 16 16 Passed
4 Concrete Class C 50 for Super T 1 7 8 Passed
5 Concrete Class C 35 Crossbeam of Super T 0 5 5 Passed
6 Concrete Class C10 for Blinding Concrete 0 3 3 Passed
7 Concrete Class C40 for pile cap of main bridge 0 3 3 Passed
8 Concrete Class C15 for Supporting, Sign support foundation, Post, Traffic signage, km port, Curb,
0 1 1 Passed
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 100
Vehicular guardrail foundation, Slope protection
9
Concrete Class C20 for Sealing concrete, Manhole, catch basin, Ditch, Fence column foundation, Backfill in cable stay bridge pylon guardrail foundation, Slope protection
0 2 2
Passed
10 Concrete Class C25 for Precast concrete panel of main bridge, Parapet, Bridge Curbs, guardrail foundation, Slope protection
0 3 3 Passed
11 Concrete Class C60 for blockout of tendon Anchorages
0 1 1 Passed
Package CW1C
Result of Testing in Laboratory
No. Description of test This Period Previous Total
Cumulative Pass Fail Frequency/Quantity
1 Concrete compressive strength at 7 days with Class C50,C35,C30,C25,C15,C10
35 433
468 468 0 9 samples/pile
2 Concrete compressive strength at 28 days with Class C50,C35,C30,C25,C15,C10
57
780 837 837
0 9 samples/pile
3 Sonic grout 0 61 61 61 0 9 samples/Mix design
4 Testing samples cement on plant 4 62 66 66 0 1 sample/ 50T
5 Testing samples fine aggregate on barge 4 38 42 42 0 1 sample/ 200m3
6 Testing samples coarse aggregate on barge
4 39 43 43
0 1 sample/350m3
7 Testing samples source at the site 24 0 24 24
8 Reinforcing steel bar 3 123 126 126 0 1 sample/50ton
9 Sonic pipe 0 3 3 3 0 1 sample/delivery
10 Testing samples bentonite at the site 0 50 50 50 0 1 sample/delivery
11 Koden test 0 0 0 0
12 Sonic test 0 73 73 73 0 1 test/pile
13 Testing sample black sand on barge 24 215 239 239 0 1 test/1000m3
14 Testing sample coarse sand on barge 0 88 88 88 0 1 test/500m3
15 Testing samples water at the site 2 18 20 19 1 1 sample/month
16 Testing sample PC strand 0 25 25 25 0 1 test/20T
17 Testing Soil sloped surface of the embankment
0 13 13 13
0 1 test/1000m3
18 Geotextile none woven 0 17 17 17 0 1 test/10,000m2
19 PVD VID 75 0 8 8 8 0 1 test/100,000m
Results of Concrete Mix Design Tests
No. Description of Test This Period Previous
Total Cumulative
Total Remarks
Quantity/ Frequency
1 Concrete Class C30 for D1500 bored piles
0 24 24 Passed
1 time per new material source
2 Concrete C10, C15, C30, C35 for concrete structures
0 12 12 Passed
3 Concrete C50 for Super-T girders 0 1 1 Passed
4 Concrete Class C25, C30, C35 for concrete structure
0 3 3 Passed
5 Concrete Class C30 for pile 45x45 cm
12 0 12 Passed
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 101
Package CW2AB Result of Testing in Laboratory
No. Description of test This
month Previous
Total Cumulat
ive Pass Fail Frequency/ Quantity
1 Concrete compressive strength at 7 days of class C10,C20, C25, C30, C35, C40, C50
163 928 1091 1091 5 3 samples/1test
2 Concrete compressive strength at 28 days of class C10,C20, C25, C30, C35, C40, C50
163 892 1055 1055 0 3 samples/1test
3 Testing samples cement 4 76 80 80 0 1 sample/ delivery
4 Testing samples fine aggregate 5 52 57 57 0 1 sample/barge
5 Testing samples coarse aggregate 5 52 57 57 0 1 sample/barge ( except
Antraco coarse aggregate 200m3)
6 Reinforcing steel bar 4 117 121 121 1 1 sample/50ton
7 Sonic pipe 0 22 22 22 0 Checking the mill
certificate /delivery
8 Testing samples bentonite 0 14 14 14 0 1 sample/ delivery
9 Testing sample U bolt 0 24 24 24 0 Checking the mill
certificate /01 delivery
10 PC strand 0 22 22 22 0 1 sample/ lot/20ton/
delivery
11 Testing of black sand for embankment K95
120 806 926 926 1 1 sample/ 1000m3
12 Testing of non woven textile (12KN) 0 49 49 49 0 1 sample/10000m2
13 Testing of Normal PVD 0 14 14 14 0 1 sample/100000m
14 Testing of VCM-PVD 1 564 565 565 0 1 sample/10000m
15 Sand for drain layer and sand well 0 262 262 262 9 1 sample/500m3
16 High strength woven Geotextile 200/50KN
4 47 51 51 0 1 sample/10000m2
Result of Concrete Mix Design Test
No. Description of test This
month Previous
Total Cumulative Pass Fail
Frequency/ Quantity
1 Concrete compressive strength at 7 days of class C10,C20, C25, C30, C35, C40, C50
0 80 80 80 0 3 samples/test
2 Concrete compressive strength at 28 days of class C10,C20, C25, C30, C35, C40, C50
8 72 80 80 0 3 samples/test
3 Sonic pipes Mortar 07 days 0 2 2 2 0 3 samples/test
4 Sonic pipes Mortar 28 days 0 2 2 2 0 3 samples/test
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 102
Package CW2C
Result of Testing in Laboratory
No. Description of Test This
month Previous
Total Cumulative
Total Pass Fail Quantity/ Frequency
1 Concrete compressive strength at 7 days of class C10,C20, C25, C30, C35, C40, C50
65 539 604 603 1 3 samples/1test
2 Concrete compressive strength at 28 days of class C10,C20, C25, C30, C35, C40, C50
90 482 572 571 1 3 samples/1test
3 Testing samples cement 10 203 213 213 0 1 sample/ delivery
4 Testing samples fine aggregate 11 139 150 150 0 1 sample/barge
5 Testing samples coarse aggregate
20 139 159 159 0 1 sample/barge ( except Antraco
coarse aggregate 200m3)
6 Reinforcing steel bar 2 128 130 130 0 1 sample/50ton
7 Sonic pipe 0 12 12 12 0 Checking the mill
certificate /delivery
8 Testing samples bentonite 0 9 9 8 0 1 sample/delivery
9 Testing sample U bolt 0 15 15 15 0 1 set of samples/
delivery
10 PC strand 2 19 21 21 0 1 sample/ lot/20ton/
delivery
11 Testing of black sand for embankment K95
38 513 551 551 0 1 sample/ 1000m3
12 Testing of non woven textile (12KN) 0 30 30 30 0 1 sample/10000m2
13 Testing of normal PVD 0 10 10 10 0 1 sample/100000m
14 Testing of VCM-PVD 0 26 26 26 0 1 sample/10000m
15 Coarse Sand Blanket (CSB), Sand drain (SD)
0 250 250 250 0 1 sample/500m
16 Non woven Geotextile PET 15 (for VCM)
0 2 2 2 0 1 sample/10000m2
17 Non woven Geotextile PET 30 (for VCM)
0 1 1 1 0 1 sample/10000m2
18 High strength woven Geotextile 0 30 30 30 0 1 sample/10000m2
Result of Concrete Mix Design Test
No. Description of test This
month Previous
Total Cumulative Pass Fail Frequency/ Quantity
1 Concrete compressive strength at 7 days of class C10,C20, C25, C30, C35, C40, C50
60 60 60 0 3 samples/test
2 Concrete compressive strength at 28 days of class C10,C20, C25, C30, C35, C40, C50
60 60 60 0 3 samples/test
3 Sonic pipes Mortar 07 days 0 1 1 1 0 3 samples/test
4 Sonic pipes Mortar 28 days 0 1 1 1 0 3 samples/test
5 Grout for Duct 07 days 0 1 1 1 0 3 samples/test
6 Grout for Duct 28 days 0 1 1 1 0 3 samples/test
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 103
ANNEX 4-8: PLAN FOR NEXT QUARTER
The action plan for the anticipated Work in the next Quarter is described here below.
Package CW1A: Northern Approach to Cao Lanh Bridge
Bill No. Description Unit Unit Price (VND)
Sep-16 Oct-16 Nov-16
Q’ty Amount (B.VND)
Q’ty Amount (B.VND)
Q’ty Amount (B.VND)
01100-07 Maintenance and Protection of Waterway Traffic LS 7,500,000,000 0.03 0.26 0.03 0.26 0.03 0.26
01200-06 Provision & Maintenance of Temporary Engineer’s Site Office Type 2 Month 7,000,000 1.00 0.01 1.00 0.01 1.00 0.01
01200-07 Provision and Maintenance of the Engineer’s Laboratory Office Month 7,000,000 1.00 0.01 1.00 0.01 1.00 0.01
01200-10 Payment of Phone Charges and Repairs Phone Months 1,000,000 5.00 0.01 5.00 0.01 5.00 0.01
01200-13 Maintenance of 4WD Vehicle Vehicle Months 20,000,000 1.00 0.02 1.00 0.02 1.00 0.02
01200-14a Maintenance of Motor Bike Cycle Months 100,000 5.29 0.00 5.29 0.00 5.29 0.00
01200-15 Provision & Maintenance of Boat Type 2 Boat Months 38,181,818 1.00 0.04 1.00 0.04 1.00 0.04
01300-02 Environmental monitoring (internal monitoring) and reporting LS 500,000,000 0.03 0.01 0.03 0.01 0.03 0.01
03400-01 Embankment construction from Borrow m3 158,904 28,899.20 4.59 12,586.22 2.00 12,586.22 2.00
03500-10 Monitoring/Reading/Reporting for all instruments Months 11,634,793 1.00 0.01 1.00 0.01 1.00 0.01
03500-12 High Strength Geotextile 200kN/m / 50kN/m woven (Type 2) m2 44,747 38,965.63 1.74 38,965.63 1.74 - -
03500-13 Separation Geotextile (25kN/m woven) (Type 3) m2 33,089 - - 18,022.73 0.60 15,018.94 0.50
05100-02 Aggregate Base m3 458,155 - - - - 2,078.81 0.95
05100-03 Aggregate Levelling Course m3 465,613 - - - - 37.78 0.02
07100-04 Concrete Class C35 MPa m3 2,708,361 - - - - 155.09 0.42
07100-06 Concrete Class C30 MPa m3 5,462,907 872.10 4.76 872.10 4.76 1,238.21 6.76
07100-07 Concrete Class C25 MPa m3 4,029,119 119.26 0.48 178.90 0.72 178.90 0.72
07100-08 Concrete Class C20 MPa m3 2,286,009 252.74 0.58 126.37 0.29 - -
07100-09 Concrete Class C10 MPa m3 1,482,399 48.92 0.07 24.46 0.04 24.46 0.04
07200-01 Driven Precast Piles (300 mm x 300 mm) m 1,125,088 - - 4,238.38 4.77 - -
07200-04 Driven Precast Piles (450 mm x 450 mm) m 3,226,896 2,124.90 6.86 2,124.90 6.86 2,124.90 6.86
07300-05 Bored Pile 1,500 mm diameter m 15,596,102 - - 448.00 6.99 384.71 6.00
07300-21 Coring and Testing at Pile Base per pile each 8,064,509 - - 8.00 0.06 - -
07300-22 Cross Hole Sonic Logging per pile each 5,760,363 - - 8.00 0.05 - -
07350-04 Pile Dynamic Test for Bored Pile (Dia. 1,500mm) each 69,124,360 - - 1.00 0.07 - -
07400-01 Sheet Piled Revetment Wall m2 1,811,737 - - - - 418.32 0.76
07400-02 Capping Beam to Sheet Piled Revetment Wall m 3,923,766 - - - - 28.00 0.11
07450-01 Super T Girder L=38.10 - 38.30 m (all Types) each 382,275,322 10.00 3.82 5.00 1.91 10.00 3.82
07450-03 Super T Girder L=28.70 m (all Types) each 293,170,288 - - - - 11.00 3.22
07450-04 Super T Girder L=26.30 m (all Types) each 242,909,147 - - 5.00 1.21 - -
07450-06 Voided Slab Girder - L=24 m each 264,235,186 20.00 5.28 - - 20.00 5.28
07500-01 Reinforcing Steel kg 21,710 124,954.25 2.71 124,954.25 2.71 154,600.57 3.36
Total 31.27 35.14 41.18
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 104
Package CW1B: Cao Lanh Bridge Project
Pay Item Description Unit
Unit Price Sep-16 Oct-16 Nov-16
(VND) Q’ty Amount (B.VND)
Q’ty Amount (B.VND)
Q’ty Amount (B.VND)
01100-05 Provision and Maintenance of Laboratory and Equipment LS 8,769,212,652 0.01 0.10 0.01 0.10 0.01 0.10
01200-04 Provision & Maintenance of Engineer’s HCMC Liaison Office Month 23,076,882 1.00 0.02 1.00 0.02 1.00 0.02
01200-05 Provision & Maintenance of Temporary Engineer’s Site Office Type 1
Month 41,538,387 1.00 0.04 1.00 0.04 1.00 0.04
01200-07 Provision and Maintenance of the Engineer’s Laboratory Office Month 2,769,226 1.00 0.00 1.00 0.00 1.00 0.00
01200-10 Payment of Phone Charges and Repairs Phone Months 1,384,613 10.00 0.01 10.00 0.01 10.00 0.01
01200-13 Maintenance of 4WD Vehicle Vehicle Months 23,076,882 2.00 0.05 2.00 0.05 2.00 0.05
01200-14a Maintenance of Motor Bike Cycle Months 646,153 10.00 0.01 10.00 0.01 10.00 0.01
01200-15 Provision & Maintenance of Boats Months 46,153,763 1.00 0.05 1.00 0.05 1.00 0.05
03210-01 Blinding Crushed Stone m3 379,331 0.00 0.00 1094.00 0.41 0.00 0.00
03400-03 Removal of Surcharge Fill m3 32,890 4139.59 0.14 4139.59 0.14 4139.59 0.14
03400-05 Construction of Subgrade m3 386,468 0.00 0.00 1036.84 0.40 1036.84 0.40
03500-13 Separation Geotextile (25kN/m woven) (Type 3) m2 33,092 4315.28 0.14 0.00 0.00 4315.28 0.14
04100-03 Reinforced Concrete Pipe Culvert, 1.25m diameter m 11,672,257 0.00 0.00 0.00 0.00 10.10 0.12
04200-04 Side Ditch Type A (Earth, trapezoidal with base width 0.5m) m 24,171 0.00 0.00 0.00 0.00 248.70 0.01
04300-04 Apron and Wing Wall, Pipe Culvert, 1.25m diameter each 54,341,645 0.00 0.00 0.00 0.00 0.67 0.04
07100-01 Concrete Class C50 MPa m3 11,157,961 1166.23 13.01 1166.23 13.01 1166.23 13.01
07100-04 Concrete Class C35 MPa m3 4,529,296 306.48 1.39 306.48 1.39 306.48 1.39
07100-07 Concrete Class C25 MPa m3 6,812,197 0.00 0.00 0.00 0.00 512.49 3.49
07200-01 Driven Precast Piles (300 mm x 300 mm) m 1,138,884 6282.30 7.15 6282.30 7.15 0.00 0.00
07450-01 Super T Girder L=38.10 - 38.30 m (all Types) each 597,336,077 15.22 9.09 15.22 9.09 15.22 9.09
07450-05 PC Strand kg 61,111 37392.11 2.29 37392.11 2.29 37392.11 2.29
07500-01 Reinforcing Steel kg 25,781 404948.14 10.44 404948.14 10.44 503119.04 12.97
07720-01 Stay Cables kg 216,415 37726.24 8.16 47157.80 10.21 56589.36 12.25
07800-06 Elastomeric bearing (600x250x85mm - 1,350 kN) each 17,202,854 22.00 0.38 22.00 0.38 22.00 0.38
07810-01 Pot Bearing, free sliding (1,350 kN) each 71,353,481 6.15 0.44 6.15 0.44 6.15 0.44
07810-02 Pot Bearing, guided sliding (1,350 kN) each 77,572,395 0.62 0.05 0.62 0.05 0.62 0.05
Total 52.96 55.68 56.47
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 105
Package CW1C: Southern Approach to Cao Lanh
Pay item Description Unit
Unit Price Sep-16 Oct-16 Nov-16
(VND) Q’ty Amount (VND)
Q’ty Amount (VND)
Q’ty Amount (VND)
01100-08 Survey and design of construction drawings LS 650,000,000 0.00 0.00 0.00 0.000 0.00 0.00
01200-06 Provision & Maintenance of Temporary Engineer's Site Office Type 2
month 15,000,000 0.00 0.01 0.00 0.010 0.00 0.01
01200-07 Provision and Maintenance of the Engineer's Laboratory office
month 5,000,000 0.00 0.00 0.00 0.003 0.00 0.00
01200-10 Payment of Phone charges and Repairs Phone Months
500,000 0.00 0.00 0.00 0.002 0.00 0.00
01200-13 Maintenance of 4WD Vehicle Vehicle Months
3,000,000 0.00 0.00 0.00 0.004 0.00 0.00
01200-14a Maintenance of Motor Bike Cycle Month
200,000 0.00 0.00 0.00 0.001 0.00 0.00
01300-02 Environmental Monitoring (internal monitoring) and reporting
LS 180,000,000 0.00 0.02 0.00 0.000 0.00 0.00
03500-10 Monitoring/Reading/Reporting for all instruments Months 8,000,000 0.00 0.01 0.00 0.008 0.00 0.008
07100-07 Concrete Class C25 MPa m3 3,607,929 0.00 0.00 0.00 - 0.00 0.05
07200-01 Driven Precast piles (300mm x 300mm) m 1,198,924 0.00 0.00 0.00 1.94 0.00 4.52
07300-05 Bored Pile 1,500 mm diameter m 14,675,158 0.00 0.00 0.00 2.11 0.00 8.45
07300-21 Coring and Testing at Pile base per pile each 3,000,000 0.00 0.00 0.00 0.01 0.00 0.02
07300-22 Cross Hole Sonic Logging per pile each 2,200,000 0.00 0.00 0.00 0.00 0.00 0.02
07350-04 Pile Dynamic Test for Bored Pile (Dia 1,500mm) each 25,000,000 0.00 0.00 0.00 0.03 0.00 -
07450-01 Super T Girder, L = 38.10 - 38.30m ( all types ) each 364,599,613 0.00 0.00 0.00 - 0.00 3.65
TOTAL 0.044 4.116 16.743
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 106
Package CW2A: Interconnecting Road Between Cao Lanh Bridge and Vam Cong Bridge (Km 7+800 - Km 13+750)
Pay Item Description Unit Price (VND) Perform Qty up date (May
2016)
Sep-2016 Oct-2016 Nov-2016
Q'ty Amount (VND) Q'ty Amount (VND) Q'ty Amount (VND)
1 DIVISION 1 GENERAL REQUIREMENTS
01100-08 Survey and Design of Construction Drawings
LS 3,196,662,000 0.0625 0.00 0 0.00 0 0.00 0
3 DIVISON 3 EARTHWORKS
03100-01 Excavation of Unsuitable Material m3 17,470 369.94 0.00 0 0.00 0 0.00 0
03200-01 Structural Excavation m3 28,634 0 904.01 25,885,458 904.01 2,889,818,423,662 0.00 0
03400-01 Embankment construction from Borrow m3 119,381 57388.15 20,114.35 2,401,270,644 5,028.59 16,074,690,734,563 20,114.35 2,401,270,644
03500-01 Prefabricated Vertical Drain (PVD) m 6,232 116089.4 0.00 0 0.00 0 0.00 0
03500-02 Vertical Sand Drain (VSD) m 104,316 9259.7 0.00 0 0.00 0 0.00 0
03500-04 Coarse Sand Blanket (CSB) m3 203,314 14475.3 0.00 0 0.00 0 0.00 0
03500-11 Separation Geotextile 12kN/m non-woven (Type 1)
m2 13,706 20762.57367 0.00 0 0.00 0 0.00 0
03500-12 High Strength Geotextile 200kN/m / 50kN/m woven (Type 2)
m2 34,268 0 23,594.56 808,538,460 5,898.64 18,855,960,150,277 23,594.56 808,538,460
03600-01 Vacuum Consolidation Method m2 693,008 0 4,317.35 2,991,959,821 0.00 0 0.00 0
7 DIVISION 7 STRUCTURAL WORKS
07100-06 Concrete Class C30 MPa m3 2,950,359 0 1,190.13 3,511,315,515 1,636.43 5,231,116,690,204 1,041.37 3,072,401,076
07100-07 Concrete Class C25 MPa m3 2,852,770 0 1.00 2,852,770 2.00 6,393,324,000 2.00 5,705,540
07100-08 Concrete Class C20 MPa m3 2,764,423 0 0.00 0 3.00 9,589,986,000 3.00 8,293,269
07100-09 Concrete Class C10 MPa m3 1,313,362 0 222.49 292,210,962 127.14 406,415,934,691 95.35 125,233,269
07200-01 Driven Precast Piles (300 mm x 300 mm) m 915,104 0 2,378.30 2,176,387,268 1,978.02 6,323,061,369,240 525.92 481,266,920
07300-01 Bored Pile 1,000 mm diameter m 8,908,373 3207 1,879.00 16,738,832,867 1,549.00 4,951,629,438,000 1,843.00 16,418,131,439
07450-06 Voided Slab Girder - L=24 m each 228,785,727 0 21.40 4,896,014,558 51.00 163,029,762,000 39.00 8,922,643,353
07450-08 I Girder L = 33m each 279,760,662 0 0.00 0 1.60 5,114,659,200 3.20 895,234,118
07500-01 Reinforcing Steel kg 19,589 0 139,584.77 2,734,325,990 191,929.05 613,532,313,205,275 122,136.67 2,392,535,241
Total 36,579,594,312.84 668,449,133,677,112.00 35,531,253,329.57
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 107
Package CW2B: Interconnecting Road Between Cao Lanh Bridge and Vam Cong Bridge (Km 13+750 - Km 18+200)
Pay Item Description Unit Price (VND) Perform Qty up date (May
2016)
Sep-2016 Oct-2016 Nov-2016
Q'ty Amount (VND) Q'ty Amount (VND) Q'ty Amount (VND)
1 DIVISION 1 GENERAL REQUIREMENTS
01100-08 Survey and Design of Construction Drawings
LS 3,261,440,000 0.0625 0.00 0 0.00 0 0.00 0
3 DIVISON 3 EARTHWORKS
03100-01 Excavation of Unsuitable Material m3 17,824 0 0.00 0 0.00 0 0.00 0
03200-01 Structural Excavation m3 29,215 0 (0.00) (0) (0.00) (0) 0.00 0
03400-01 Embankment construction from Borrow m3 121,800 7843.393395 4,559.80 555,384,122 2,279.90 277,692,061 2,279.90 277,692,061
03500-01 Prefabricated Vertical Drain (PVD) m 6,358 402055.1 0.00 0 0.00 0 0.00 0
03500-02 Vertical Sand Drain (VSD) m 106,430 20804.33025 0.00 0 0.00 0 0.00 0
03500-04 Coarse Sand Blanket (CSB) m3 207,434 1606.61 0.00 0 0.00 0 0.00 0
03500-11 Separation Geotextile 12kN/m non-woven (Type 1)
m2 13,984 0 0.00 0 0.00 0 0.00 0
03500-12 High Strength Geotextile 200kN/m / 50kN/m woven (Type 2)
m2 34,963 0 7,413.49 259,197,985 3,706.75 129,598,993 3,706.75 129,598,993
03600-01 Vacuum Consolidation Method m2 707,051 0 0.00 0 0.00 0 0.00 0
7 DIVISION 7 STRUCTURAL WORKS
07100-06 Concrete Class C30 MPa m3 3,010,146 0 2,403.47 7,234,792,062 3,143.00 9,460,881,927 2,403.47 7,234,792,062
07100-07 Concrete Class C25 MPa m3 2,910,579 0 0.00 0 165.71 482,316,897 386.66 1,125,406,093
07100-08 Concrete Class C20 MPa m3 2,820,442 0 172.64 486,921,107 57.55 162,307,036 172.64 486,921,107
07100-09 Concrete Class C10 MPa m3 1,339,977 0 232.11 311,017,523 132.63 177,724,299 165.79 222,155,374
07200-01 Driven Precast Piles (300 mm x 300 mm) m 933,648 0 1,470.39 1,372,826,191 0.00 0 0.00 0
07300-01 Bored Pile 1,000 mm diameter m 8,908,373 1096 771.00 7,007,537,274 771.00 7,007,537,274 0.00 0
07450-06 Voided Slab Girder - L=24 m each 209,682,233 0 9.06 1,898,789,110 0.00 0 27.17 5,696,367,330
07450-08 I Girder L = 33m each 285,429,806 0 5.83 1,665,007,202 5.83 1,665,007,202 2.92 832,503,601
07500-01 Reinforcing Steel kg 19,986 0 410,070.81 8,195,675,306 536,246.45 10,717,421,553 410,070.81 8,195,675,306
Total 28,987,147,882 30,080,487,242 24,201,111,926
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 108
Package CW2C: Interconnecting Road between Cao Lanh Bridge and Vam Cong Bridge (Km 18+200 - Km 23+450)
Pay Item Description Unit
Price (VND)
Perform Qty up
date (May 2016)
Sep-2016 Oct-2016 Nov-2016
Q’ty Amount (VND) Q’ty Amount (VND) Q’ty Amount (VND)
1 DIVISION 1 GENERAL REQUIREMENTS
01100-07 Maintenance and Protection of Waterway Traffic LS 5,500,000,000
-
0.05
275,000,000.00
0.05
275,000,000.00
0.05
275,000,000.00
01100-08 Survey and Design of Construction Drawings LS 2,800,000,000
-
-
-
-
-
-
-
3 DIVISON 3 EARTHWORKS
03100-01
Excavation of Unsuitable Material
Đào vật liệu không phù hợp m3 39,776
-
-
-
-
-
-
-
03200-01
Structural Excavation
Đào kết cấu m3
706,919
-
-
-
542.00
383,150,098.00
-
-
03200-02
Structural Excavation in River: P7, P8 Lap Vo Bridge
Đào kết cấu dưới sông: trụ P7, P8 cầu Lấp Vò LS
20,000,000,000
-
-
-
-
-
-
-
03400-01
Embankment construction from Borrow
Thi công nền đường từ mỏ vật liệu mượn m3
148,123
9,955.60
20,768.17
3,076,243,464.54
20,768.17
3,076,243,464.54
20,768.17
3,076,243,464.54
03500-01
Prefabricated Vertical Drain (PVD)
Bấc thấm đứng (PVD) m
7,445
-
-
-
-
-
-
-
03500-02
Vertical Sand Drain (VSD)
Cọc cát đứng (VSD) m
77,189
-
-
-
-
-
-
-
03500-04
Coarse Sand Blanket (CSB)
Tầng đệm cát thô (CSB) m3
268,824
-
-
-
-
-
-
-
03500-11
Separation Geotextile 12kN/m non-woven (Type 1)
Vải địa kỹ thuật ngăn cách (12kN/m không dệt) (Loại 1) m2
18,318
-
-
-
-
-
-
-
03500-12
High Strength Geotextile 200kN/m/50kN/m woven (Type 2)
Vải địa kỹ thuật cường độ cao (200kN/50kN dệt) (Loại 2) m2
43,966
-
-
-
-
-
-
-
03600-01
Vacuum Consolidation Method
Phương pháp cố kết hút chân không m2
698,088
-
5,516.34
3,850,887,965.57
-
-
-
-
7 DIVISION 7 STRUCTURAL WORKS
07100-02 Concrete Class C40 MPa (Box Girder _ Lap Vo Bridge) m3 18,441,607
253.93
450.81
8,313,660,851.67
58.88
1,085,841,820.16
-
-
07100-06 Concrete Class C30 Mpa Bê tông mác C30 Mpa m3
2,855,938
113.73
-
-
394.36
1,126,267,709.68
604.34
1,725,952,811.02
07100-09 Concrete Class C10 Mpa Bê tông mác C10 Mpa m3
1,284,340
8.62
-
-
87.91
112,906,329.40
32.57
41,830,953.80
07200-01
Driven Precast Piles (300 mm x 300 mm)
Cọc đóng đúc sẵn (300 mm x 300 mm) m
1,048,272
2,630.40
-
-
-
-
-
-
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 109
07200-01
Driven Precast Piles (300 mm x 300 mm)
Cọc đóng đúc sẵn (300 mm x 300 mm) m
587,032.00
2,630.40
-
-
-
-
-
-
07200-04
Driven Precast Piles (450 mm x 450 mm)
Cọc đóng đúc sẵn (450 mm x 450 mm) m
3,236,306
-
-
-
-
-
-
-
07300-01
Bored Pile 1,000 mm diameter
Cọc khoan nhồi đường kính 1.000 mm m
9,556,922
-
-
-
-
-
-
-
07300-05
Bored Pile 1,500 mm diameter
Cọc khoan nhồi đường kính 1.500 mm m
17,397,477
295.00
885.00
15,396,767,145.00
295.00
5,132,255,715.00
-
-
07400-01
Sheet Piled Revetment Wall
Tường vây cọc cừ ván m2
1,669,336
-
-
-
-
-
-
-
07450-01
Super T Girder L=38.10 - 38.30 m (all Types)
Dầm Super T, L=38,10 - 38,30m (tất cả các Loại) each
426,415,977
8.00
-
-
-
-
-
-
07450-01-72%
Super T Girder L=38.10 - 38.30 m (all Types)
Dầm Super T, L=38,10 - 38,30m (tất cả các Loại) each
307,019,503.00
8.00
-
-
-
-
-
-
07450-01-28%
Super T Girder L=38.10 - 38.30 m (all Types)
Dầm Super T, L=38,10 - 38,30m (tất cả các Loại) each
119,396,474.00
8.00
-
-
-
-
-
-
07450-03
Super T Girder L=28.70 m (all Types)
Dầm Super T (L=28,70m) (tất cả các loại) each
314,711,491
-
-
-
-
-
-
-
07450-03-72%
Super T Girder L=28.70 m (all Types)
Dầm Super T (L=28,70m) (tất cả các loại) each
226,592,274.00
-
-
-
-
-
-
-
07450-03-28%
Super T Girder L=28.70 m (all Types)
Dầm Super T (L=28,70m) (tất cả các loại) each
88,119,217.00
-
-
-
6.00
1,888,268,946.00
-
-
07500-01
Reinforcing Steel
Cốt thép kg 22,171
181,311.34
85,799.51
1,902,260,936.21 106,204.0
5
2,354,649,905.62
162,898.7
6
3,611,628,364.21
32,814,820,362.99
15,434,583,988.40
8,730,655,593.58
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 110
ANNEX 5-1: STATUS OF RESETTLEMENT ACTIVITIES
Pkg
Commune/
ward
Affected
Area
(ha)
Affected
HH
AHs who
received
compensation
AH who
hand-over
land
AHs who have not received
compensation AHs who have not handed-over
HH Reason HH Reason
Component 1 61.4 699 694 690 5 0 9
An Binh 5.7 103 103 99 0 4
- 3 HHs (Lan, Loc, Trieu) requeted some
additional support
CW1A
- 1 HHs is affected by both project,
requested to increase price for wood
Ward 3 4.8 47 47 47 0
0
Tinh Thoi 29.4 370 370 370 0 0
CW1B
Tan My 1 21.5 179 174 174 5
5
CW1C
- 5 HHs Cườ g, Ngâ , Ba, Nă , Hồ g refused compensation
5 HHs Cườ g, Ngâ , Ba, Nă , Hồ g refused compensation
Component 2 100.1 619 619 619 0 0
Tan My 2 4.5 28 28 28 0
CW2A
My An
Hung B 29 175 175 175 0 -
Binh Thanh
Trung 24.7 142 142 142 0 0
CW2B
Binh Thanh 30.9 173 173 173 0 0
CW2C
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 111
Dinh An C2 11 101 101 101 0 0
Component 3 28.6 207 207 207 0 0
CW3B Dinh An C3 28.6 207 207 207 0
CW3A
Total Dong Thap 190.1 1525 1520 1516 5 0 9
CW3A Thoi Thuan 18.8 190 190 190 0 0
CW3B Vinh Trinh 9.7 68 66 68 2
- Mai Anh Tuấ mortgaged LURC in the
Bank;
0
- Nguyễ Ngọc Mạ h: he died, his children are
disputing
Total Can Tho 28.5 258 256 258 2 0
TOTAL PROJECT 218.6 1783 1776 1774 7 9
Source: CHLFD/CFLD August 2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 112
ANNEX 5-2: HOUSEHOLDS NEEDING RELOCATION
Package Commune/ward Affected HH
Household who Need Relocation
Total HH opted for Self-Relocation
HH opted to relocate in RS
Component 1 699 116 123 239
An Binh 103 7 41 48
CW1A Ward 3 47 0 19 19
Tịnh Thoi 370 93 33 126
CW1B
Tan My 1 179 16 30 46 CW1C
Component 2 619 124 50 174
Tan My 2 28 5 0 5
CW2A My An Hung B 175 6 26 32
Binh Thanh Trung 142 23 6 29
CW2B
Binh Thanh 173 72 1 73
CW2C Dinh An C2 101 18 17 35
Component 3 207 59 4 63
CW3B Dinh An C3 207 59 4 63
CW3A
Total Dong Thap 1525 299 177 476
CW3A Thoi Thuan 190 35 32 67
CW3B Vinh Trinh 68 16 12 28
Total Can Tho City 258 51 44 95
TOTAL PROJECT 1783 350 221 571
Source: CHLFD/CHLD August 2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 113
ANNEX 5-3: SUMMARY OF COMPENSATION PAYMENTS
Component Total Nb
of HH
HH who received
compensation
Total compensation
Total disbursed Budget needed to
complete compensation
Billion VND Billion VND
% Billion VND
%
Component 1 699 694 390.7 373.9 96% 16.8 4%
Component 2 619 619 434.2 422.5 97% 11.7 3%
Component 3 207 207 154.2 153.5 100% 0.7 0%
Total Dong Thap
1525 1520 979.1 949.9 97% 29.2 3%
Component 3 258 256 200 182 91% 18 9.0%
Total Can Tho 258 256 201.8 184.4 91.0% 18 9.0%
TOTAL PROJECT
1783 1776 1180.9 1134.3 96% 46.6 4%
Source: CHLFD/CHLD August 2016
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 114
ANNEX 6: LOAN COVENANTS
No. Description
Loan Grant Gov. of Vietnam
TOTAL
ADB Kexim AusAID USD
1 Package 1
Construction 110.75 - 110.75 - 221.51 Supervision - - See belowa -
2 Package 2
Construction 162.12 - - - 162.11 Supervision - - See belowa -
3 Package 3
Construction - 215.25 - 22.05 237.30 Supervision - 14.13 - 1.41 15.54 UXO - - - 0.05 0.05
4 Land acquisition and re-settlement
37.18 - - 15.79 52.97
5 Contingencies 86.45 29.79 23.25 12.07 151.56
6 Financing Charges 13.50 0.83
14.33
7 Project Management Support
4.63 4.63
410.00 260.00 134.00 56.00 860.00 Add associated TA 78.22
26.00
26.00 410.00 260.00 160.00 56.00 886.00
a Financed by AusAID separately under associated TA 7822 Based on Project Administration Manual dated 11 June 2013
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 115
ANNEX 7: KEY PERFORMANCE INDICATOR (KPI) REPORTING
KPI 1 - CONSTRUCTION - Quarterly during implementation (Quarter ending 31 August 2016)
Indicator Units
CW1A
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress 53.02%. Planned progress 57.76%, behind Schedule -4.74%
Payment approved (IPCs) 576.68 billion VND, disbursement plan 595.02 billion VND Construction Work Inspections (cumulative): 7031 inspections and testing (RFI/T) Test results: Material source (cumulative): 32 tests, 0 failures; Materials delivered (this quarter): 899 tests, 0
failures; Materials in Works (cumulative): 2674 tests, 7 failures
CW1B - Cao Lanh Bridge: Main bridge & approach bridge
Physical progress against physical plan
Financial progress against disbursement plan Quality standard against plan
Physical progress 69.78%. Planned progress 68.58%, ahead of Schedule +1.20%
Payment approved (IPCs) 2047.28 billion VND, disbursement plan: 2129.25 billion VND
Construction Work Inspections (cumulative): 12627 inspections and testing (RFI/T)
Test results: Material source (cumulative): 62 tests, 0 failures; Materials delivered (this quarter): 359 tests, 8 failures; Materials in Works (cumulative): 5962 tests, 17 failures
CW1C
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress: 65.12%. Planned progress: 57.92%, ahead of Schedule: +7.20%
Payment approved (IPCs) 258.04 billion VND, disbursement plan: 235.68 billion VND
Construction Work Inspections (cumulative): 3311 inspections and testing (RFI/T)
Test results: Material source (cumulative): 21 tests, 0 failures; Materials delivered (this quarter): 157 tests, 1 failures; Materials in Works (cumulative): 2203 tests, 1 failures
CW2A
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress: 48.48%. Planned progress 50.38%, Ahead the Schedule 1.81%
Payment approved (IPCs) 288.71 billion VND (excluded advance payment), disbursement plan 350.24 billion VND
Construction Work Inspections (cumulative): 12766 inspections (RFIs) for CW2AB
Test results: Material source (cumulative): 39 (CW2A+CW2B); accumulative test result (including road and bridge) for material in this quarter 4446 in which 16 test failed.
CW2B
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress: 54.05%. Planned progress 53.86%, Ahead of Schedule 0.19%
Payment approved (IPCs) 320.72 billion VND (excluded advance payment), disbursement plan 420.65 billion VND
Construction Work Inspections (cumulative): 12766 inspections (RFIs) for CW2AB
Test results: Material source (cumulative): 39 (CW2A+CW2B); accumulative test result (including road and bridge) for material in this quarter 4446 in which 16 test failed.
CW2C
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress: 60.51%. Planned progress 58.22%, Ahead of Schedule 2.29%
Payment approved (IPCs) 443.13 billion VND, disbursement plan 577.6 billion VND (excluded advance payment)
Construction Work Inspections (cumulative): 6816 inspections (RFIs) (Some RFIs is repeated, so reducing)
Test results: Material source (cumulative): 33; accumulative test result (including road and bridge) for material in this quarter 2785 in which 2 test failed.
CW3A
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress 68.52%. Planned progress 68.33%, Ahead of Schedule 0.19%
Payment approved (IPC) N/A VND, disbursement plan N/A VND
Construction Work Inspections: N/A inspections, N/A satisfactory, N/A unsatisfactory
Test results: Material source N/A tests, N/A failures; Materials delivered: N/A tests, N/A failures. Materials in Works: N/A tests, N/A failures
CW3B
Physical progress against physical plan
Financial progress against disbursement plan
Quality standard against plan
Physical progress 34.99%. Planned progress 32.06%, Ahead of Schedule 2.93%
Payment approved (IPC) N/A VND, disbursement plan N/A VND
Construction Work Inspections: N/A inspections, N/A satisfactory, N/A unsatisfactory
Test results: Material source N/A tests, N/A failures; Materials delivered: N/A tests, N/A failures. Materials in Works: N/A tests, N/A failures
KPI 2 - CONSTRUCTION EMPLOYMENT (Quarter ending 31 August 2016) Indicator Units
All packages: CW1A, CW1B, CW1C, CW2A, CW2B, CW2C Local, unskilled workers employed (person months) Men: 720 person-months in Quarter
Women: 900 person-months in Quarter
Average wage rates for unskilled workers (or wage indices) Men: VND 4,500,000 per month
Women: VND 3,600,000 per month
Vam Cong bridge: Main bridge & approach bridge (CW3A)
Local, unskilled workers employed (person months) Men: 180 person-months in Quarter
Women: 270 person-months in Quarter
Average wage rates for unskilled workers (or wage indices) Men: VND 4,500,000 per month
Women: VND 3,600,000 per month
KPI 3 - CONSTRUCTION SAFETY (Quarter ending 31 August 2016) Indicator Units
All packages: CW1A, CW1B, CW1C, CW2A, CW2B, CW2C No. of workers
Killed
Seriously Injured
Killed: 02 Men, 00 Women
Seriously injured: 00 men, 00 women Vam Cong bridge: Main bridge & approach bridge (CW3A) No. of workers
Killed
Killed: N/A
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 116
Seriously Injured Seriously injured: N/A Note1: any construction-related serious accidents or deaths among local population to also be reported on an exception basis
Note 2: a road safety awareness program will be delivered in advance of the opening of the project. KPIs for monitoring implementation will be developed nearer the time for inclusion in the quarterly report.
KPI 4 – ENVIRONMENTAL MANAGEMENT (Quarter ending 31 August 2016) Indicator Units
All Packages: CW1A, CW1B, CW1C, CW2A, CW2B, CW2C
Number of environmental grievances received Total 58 grievances
Total 43 people
Outstanding cases of grievance with construction Total 32 grievances
Vam Cong Bridge & Approach Road (CW3A, CW3B)
Number of environmental grievances received Total 06 grievances
Total 32 people
Outstanding cases of grievance with construction Total 01 (grievances)
KPI 5 – LAND ACQUISITION AND RESETTLEMENT (Quarter ending 31 August 2016)
Indicator Units
All Packages: CW1A, CW1B, CW1C, CW2A, CW2B, CW2C, CW3A, CW3B
Land acquisition against plan HH 1776/1783, Ha 254.3/254.5
Disbursement of compensation & allowances against plan VND 1,134.3 billion/1,180.9 (96%)
Disbursement of compensation & allowances within agreed time limit1 (cases)
99% Total, 100% Vulnerable HH
Compensation plans agreed jointly by husband and spouse 24 % eligible cases (45 cases)
Provision of consultation counseling against plan Activity completed
Households self-relocated against plan Total 350 HH/23, Vulnerable 85 HH/N/A
Households relocated to service resettlement site against plan Total 218 HH/571, Vulnerable 132 HH/N/A
LURC / asset titles issued jointly in husband and spouse names % Total eligible, % eligible Vulnerable HH
In Dong Thap, DPC issued new LURC for 84 HHs, in which 10 HHs had LURC is issued both husband and wife
Resettlement completed within agreed time limit (cases) 94% Total, % 98 Vulnerable HH
Beneficiaries satisfied with compensation counseling 100 %
Outstanding cases of grievance with land acquisition Total 4 (HH), Vulnerable HH 0 (HH),
Beneficiary satisfaction with resettlement site Only 34 HH among 221 HH built a house in a RS; overall satisfaction
KPI 6 – INCOME RESTORATION PLAN (Quarter ending 31 August 2016)
Indicator Units
All Packages: CW1A, CW1B, CW1C, CW2A, CW2B, CW2C, CW3A, CW3B
Implementation of Detailed IRP activities against plan1:
Agriculture
Training
MSE development
– Agriculture training started in August;
– Vocational training started;
– Training for small business completed in Can Tho City
– Delivering of input for HHs from November 2015
Participation in IRP activities against plan
Agriculture
Training
MSE development
In Can Tho City
+ Agriculture: training: 51/57 HH; handed-over inputs: 55/57HH
+ Vocational training: 31/48 HH
+ Small business: training: 40/40 HH; handed-over inputs: 40/40 HH
In Dong Thap province
+ Agriculture: training: 137/824 HH; handed-over inputs: 370/824HH
+ Vocational training: 13/57 HH
+ Small business: training: 157/272 HH; handed-over inputs: 258/272 HH
Overall expenditure of IRP against plan Dong Thap: Amount disbursed by CIPM to SC : 9,705,000,000 VND/23,386,309,000 VND
Can Tho: Amount disbursed by CIPM to SC: 2,654,164,078 VND/3,108,285,242 VND. Beneficiary satisfaction with IRP services provided % Total, % Vulnerable HH, % Women (N/A)
Adoption / application of IRP services % Total, % Vulnerable HH, % Women (N/A)
KPI 7 – HIV/AIDS and HUMAN TRAFFICKING PREVENTION PLAN (Quarter ending 31 August 2016)
Indicator Units
Packages: CW1B CW3A CW1C, CW2A, CW2B, CW2C, CW1A, CW3B: ALL packages are implementing
Implementation of awareness raising activities against plan
HIV/AIDS for all packages
HAPP and HTPP for community
100% completion for 8 CWs (training, group meeting, IEC material and condom distribution) 100 % completion (training, IEC material, condom and Peers Educator’s kit distribution)
Participation in activities against plan
HIV/AIDS for all packages CWs
HAPP and HTPP for community - Capacity strengthening of institutional stakeholders - Advocacy - IEC and BCC - Medical package
- Monitoring and evaluation
100% completion HIV/STIs examine and testing
100% completion
100% completion
100% completion
100% completion 100% completion
Overall expenditure against plan
HIV/AIDS for all packages CWs
HAPP and HTPP for community (DDIS)
Not available
4.019.718.495 VND, planned 4.298.478.695 VND
Learning and satisfaction with HAPP activities
Implementing partners at district and commune levels
Construction workers
Female Sex Workers
Completed first time training workshops in Dong Thap and Can Tho for the second year
100 % demonstrating adequate learning, 100% satisfaction
100% demonstrating adequate learning, 100% satisfaction 100% demonstrating adequate learning, 100% satisfaction
QUARTERLY PROGRESS REPORT
Quarterly Progress Report # 10 CMDRCP – August 2016 Page 117
Learning and satisfaction with HTPP training activities
Implementing partners at district and commune levels
Female Sex Workers
Completed first time training workshops in Dong Thap and Can Tho for the second year
100 % demonstrating adequate learning, 100 % satisfaction
100 % demonstrating adequate learning, 100 % satisfaction
KPI 8 – CAPACITY BUILDING PROGRAM (Quarter ending 31 August 2016)
Indicator Units
Improvement and application of knowledge No activity
KPI 9 – GRIEVANCE PROCESS MONITORING (Quarter ending 31 August 2016)
Indicator Units
Outstanding grievances at start of quarter 38 Cases
New grievances this quarter 24 Cases
Grievances satisfactorily resolved this quarter 31 Cases
Outstanding grievances exceeding agreed time limits 100%