Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
Monthly Report January 2014
CAM: Road Asset Management Project Maintenance Construction Supervision Consultant
Prepared by the EGIS International in association with VIDO Engineering Consultant for the Ministry of Public Works and Transport, the Kingdom of Cambodia, and the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 1 February 2014)
Currency unit – riel (KR)KR1.00 = $0.00025
$1.00 = KR3,995
NOTE
In this report, "$" refers to US dollars unless otherwise stated.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
Page 75
KINGDOM OF CAMBODIA
Ministry of Public Works and Transport
Road Asset Management Project (RAMP)
Maintenance Construction Supervision Consultant
Annex 2: Safeguard Compliance
and Monitoring of HIV/AIDS Campaign
ENVIRONMENT AND SOCIAL SAFEGUARD MONITORING REPORT
(January 2014)
Commune Council Meeting for
the Implementation of Road Maintenance
In association with
VIDO Engineering Consultant
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 76
Environmental and Social Safeguard Monitoring
A. Project Background
The Royal Government of Cambodia (RGC) is implementing the Road Asset Management Project (RAMP) with supports from the International Development Association (IDA), ADB, AUSAID, OPEC, and KTF. The activities will include periodic maintenance of the National and Provincial Roads under the responsibility of the Ministry of Public Works and Transport (MPWT).
The objective of the project is to ensure continued effective use of the road network in support of Cambodia's economic development. It will do so by improving the institutional and technical capacity of the Ministry of Public Works and Transport (MPWT) for road maintenance planning, budgeting and operations, and by expanding and strengthening maintenance activities. The outcome will be a more sustainable road sector based on a sound MPWT network and sustained road maintenance.
B. Environmental and Social Safeguard
The Contractors are made aware of this obligation and their safeguard performance during construction will be closely supervised and monitored by the Project Engineers with close supervision of the Project Supervision Consultants.
In the RAMP-MPWT project, environmental and social impacts of the projects were identified in the Environmental and Social Safeguard Framework (ESSF) and the mitigation measures of these impacts have been addressed through Environmental Management Plan (EMP) submitted by Contractors before commencement of construction work. The protection and enhancement of human-wellbeing is a common demonstrator for both government and donors system and can be seen as ultimate goal of sustainable development.
Prior to the road maintenance activity there ESS conducted meeting with local authorities in the project influence area to create a sense of social, environmental and safety awareness within all construction activities. During the meeting the complaint mechanism was also introduced to commune council as well as local community living along the road project.
The purpose of meeting with local authority (commune councils) is not only to hear complaints, social and environmental impacts and satisfaction with the maintenance project but also to verify and confirm whether or not HIV/AIDS campaigns are conducted in the project influence area. In addition, it is an effective public disclosure of safeguard information to local authorities.
The ESS explained and discussed impact mitigation measures during the field visit to Contractors, Engineer and RE‟s of the project, if there is, in order to comply with EMP set in the Technical Specification. It is observed that, however, there is no adverse environmental and social impact to local community along the project influence area during civil works of road construction.
The ESS/RE/TL visited NR2, NR11, NR7.1, NR7.2 and NR7.3 to investigate on environment and social related issues during and after maintenance projects.
Following are the site observations and discussions during the visits:
It is observed that there was no serious environmental and social impact in the project area according to site investigation in this month. However, there were a few minor points that were noticed: a) In NR2 worker‟s toilet need repair, b) Clearance of rubbish around the campsite to mitigate these problems, ESS advised the related workers for cleanness and importance of hygiene in personal health and keep clean environment.
Generally, however, all road projects are limited to maintenance on the existing paved road and no widening or cause resettlement. It is concluded that the maintenance activities in every road sections cause no adverse environmental and social impact on lands or communities in the area. Below is the summarize table of the environmental and social safeguard monitoring report:
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 77
Safeguard Monitoring Report
The outcomes of safeguard monitoring exercise are tabulated below.
Nº Road Maintenance related
issue
Safeguard Monitoring Activity
(Observation)
Suggestion/Comment Achievement/Remarks
1 Pollution caused by domestic
sewage and solid waste
1-1. Flash toilet is used with septic tank (in engineer office) or soak away sewerage system in labor campsite
1-2. Most waste from kitchen is organic waste.
1-3. Solid waste collects in a tank for burning, as there is no waste disposal site in the village.
The toilets of some of local worker
temporary campsite need to be
improved.
Sanitation shall take into account for
every worker campsites. Sanitation of
some local worker in temporary
campsite needs to be improved.
Contractor advised to attend.
ESS/RE following up for full
compliance
2 Possible development of
camp into permanent
settlement
There are limited numbers of skilled workers, living in the rental houses or temporary huts.
Local workers live in their own home.
No possibility for permanent
settlement
Complied
3 Noise, vibration and dust
could affect any nearby
settlements or other
environmentally sensitive
areas
Dust pollution is observed in some
limited base repair area.
To mitigate dust during constructions sprayed water.
After completion of base work to spray
prime coat
Contractor was instructed to
work on section to finish
within 1 or 2 days, to
minimize the dust pollution in
urban area.
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 78
Nº Road Maintenance related
issue
Safeguard Monitoring Activity
(Observation)
Suggestion/Comment Achievement/Remarks
4 Possible under/ground water
contamination by fuel and oil,
grease, and fuel in yards
There is no possibility of under/ground
water contamination by the projects.
5 Erosion from earthworks can
increase sedimentation in
drains, waterways and
irrigation ditches
No erosion was observed
New Land Developments Adjacent to
National Roads created the filling up
the drainage system of roadway, the
water stranded in pavement layers
destroy the asphaltic wearing courses,
creates big potholes and dangerous
condition that may cause fatal
accidents
MPWT is informed through local
authorities to prevent further
obstruction
MPWT organized a seminar
80 staffs of DPWT‟s and
local government, to stop the
breach of ROW and
drainage system.
6 Possible pollution of
waterways or ground water
by bituminous products or
solvents used in resurfacing
of pavement
In one occasion leaking oil of
equipment was observed.
Since there is possibility of oil
spillages during the maintenance
work, it is recommended that all
equipment and machineries must be
free of oil, solvent and bituminous
material leaking along the
construction road section
At labor campsite shall take
necessary measure to ensure that no
underground water pollution that may
cause by the road maintenance
activity from storage area. Contractor
was advised to fix leaking equipment
As recycled oil is economical
for Contractor, they try not to
waste oil.
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 79
Nº Road Maintenance related
issue
Safeguard Monitoring Activity
(Observation)
Suggestion/Comment Achievement/Remarks
7 Traffic and pedestrian safety Contractor using traffic control
measures to limit disruption to traffic
and ensure safety of traffic and
pedestrians.
Sometimes the traffic barrier posts
were not removed after working hour
at end of the day which can cause
traffic accident to road user during
night time (reported by people during
site visit on NR2)
TL/RE issued written instruction to
Contractor for strengthening of Traffic
Management & Safety
Contractor was warned the
punitive consequences
would be applied if breaches
continued
8 Possible pollution of
waterways by solids waste
from material stockpiles on
shoulder
Aggregates are store on available
land, there is no possibility of
waterway pollution.
No pollution from material stockpiles
was observed
Site instruction was issued to
Contractor to remove the solid waste
material of removal of existing
pavement away from side ditch and
waterway after completion of each
section (NR73 and NR71&PR2714).
Contractors agreed to clean-
up after completion of work.
This activity will be inspected
in the next mission.
9 Possible impact of road user
safety
“Safety First” is introducing to all
contractors
Flagman is used for traffic
management and traffic control
schemes are submitted to RE for
approval
TL/RE issued written instruction to
Contractor for strengthening of Traffic
Management & Safety
Contractor was warned the
punitive consequences
would be applied if breaches
continued
10 Cutting of trees No such activity happens at the
project area.
-
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 80
Nº Road Maintenance related
issue
Safeguard Monitoring Activity
(Observation)
Suggestion/Comment Achievement/Remarks
11 Disposal of excavated
material from shoulder and
drain and scarified materials
During site visit excavated materials
was not transported out of road sides
in some road sections.
It is suggested that all excavated
material should transport out of the
road shoulder after completion of work
or donate to people if possible
Contractor was accepted to
remove out after completion
of work (NR73)
12 First aid kits First aid kits is not observed in some
units
It is strongly recommended that all
labor campsite shall have first aid kits
Contractor agreed to provide
in January 2014
13 Firefighting facilities Most of Engineer‟s, contractor‟s
offices and worker campsites are not
equipped with fire extinguisher.
It is recommended that the fire
extinguishers to be installed in all
necessary hot work places
ESS checked asphalt plant,
fuel storage and so on in
result it was installed
properly.
14 Wearing of protective
clothing and safety gear and
safety shoes
All engineers are well equipped with
helmet, reflective clothing, cone for
warning traffic and flagman to give
sign to road users.
Some of workers are not using safety
shoes during work implementation.
It is suggested that safety shoes must
be used during working hour. The
Contractor safety officer shall ensure
the workers have appropriate
protective clothing.
In response to instruction,
most of worker was
introduced and equipped
with reflective clothing,
safety gear, traffic cone and
so on.
15 Displaying warning boards Deficiency observed on adequate
warning signs at construction sites
TL/RE issued written instruction to
Contractor for strengthening of Traffic
Management & Safety
In response to TL's site
instruction, warning board
was installed properly.
Egis International Monthly Progress Report Nº 34
Chapter 14 -Annexes
Road Asset Management Project (RAMP), Component A-2 (c) Maintenance Construction Supervision Consultant
January 2014 Page 81
Environmental and Social Safeguard Monitoring Impact
The ESS, RE & Contractor through monitoring of site activities and joint consultation with community leaders and residents could achieve the following improvement on the current environmental/social safeguard issues:
I. Introduction:
This is the environmental and social safeguard monitoring monthly report is in January 2014, site visited to NR 72, 7-2, 11 and NR 2 of RAMP project target area in Kampong Cham to Kratie, Prey Veng and Takeo province. And at NR 7-2, 72 and NR 11 has 85 % to 90% and NR 71 has 30% of road maintenances activities completed and NR11 will handover by end of by February or March 2014, to MPWT and NR 2 has more than 20% achievement of the project implementation.
II. Conclusion and recommendation environment and safeguards complaining:
NR 2 is busy doing asphalt concrete overlay and repairing pothole
ESS Visited to the NR 72 at the site; working has new and old potholes maintenance;, discussed with the contractor about using a young age driver (has under 18 year old) and has not enough material for traffic management to protect the workers and the drivers. During the working time and proposed to Contractor should consider more on traffic management in order to protect the workers and the drivers during the working hours.
The shrub is growing along the road cause obstruction to road user not to the road furniture such as KM posts, road sign, guide post, safety barriers... so Contractor have to clear.
Meeting on site with Contractor's worker
KM stone installation
The NR 2 has not improved much based on the minute in Khmer detail the environment and social safeguard reviewed during field visited in January 2014. Because the contractor‟s site manager agreed and signed on the minute to take action then next month will review their action. Please see attachment of main point that they agreed to improve after observation during field visit, with assistant of team leader, consultant of quality control and contractor‟s site manager.