Upload
wynter-malone
View
28
Download
1
Embed Size (px)
DESCRIPTION
Environmental Infrastructure Section 219 and 592 Authorities. Alabama Water Resources Conference Orange Beach, Alabama September 8, 2011. Environmental Infrastructure Federal Funds Expended/Obligated. TN. TN. •. AL. MS. AL. GA. GA. $0M. $0M. $8.8M. $10M. $42M. FL. FL. 15. - PowerPoint PPT Presentation
Citation preview
US Army Corps of Engineers
BUILDING STRONG®
Environmental Infrastructure Section 219 and 592 Authorities
Alabama Water Resources Conference
Orange Beach, Alabama
September 8, 2011
BUILDING STRONG®
Environmental InfrastructureFederal Funds Expended/Obligated
15
FLFL
TNTN
ALGAGA
$0M
•
$8.8M $42M
MSMS ALAL
$0M
TNTN
GAGA
FLFL
$10M
BUILDING STRONG®
Metro Atlanta Environmental Infrastructure
Projects
Section 219, WRDA 1992, as amendedCost shared 75% Federal / 25% Non-Federal
Water Supply: Intakes, distribution, groundwater production, raw water treatment, etc.
Stormwater: Detention, catch basins, piping, created wetlands, capacity improvements, storage, etc.
Wastewater: Treatment, collection, connectivity, expansions, separation, etc.
BUILDING STRONG®
McDaniel Branch Stormwater Capacity Improvement Project
Sponsor: City of Atlanta, Georgia
This project consists of the design and construction of a system of storm water detention basins as a feasible watershed improvement project.
These basins would provide water quality treatment and storm water runoff control from approximately 200 acres of urban watershed.
Design is 85% Complete
Delays due to sewer main relocation
Expected Completion in 2013
BUILDING STRONG®
Chattahoochee River Water Intake
Sponsor: City of Atlanta, Georgia
The purpose of this project is to upgrade upper and lower sill structures in order to improve conditions at the City of Atlanta’s Chattahoochee River Raw Intake structure and stabilize the east bank of the Defoors Island.
Projected Cost - $1,900,000
Cost shared on a 75 / 25% (Federal /Non-Federal basis)
Design Awarded August 2011
Projected Construction Completion in 2013
UPPER SILL
EROSION CONTROL
LOWER SILL
EROSION CONTROL
DEFOORS ISLAND
CHATTAHOOCHEE RIVER
5
BUILDING STRONG®
Groundwater Production Wells Treatment Facility
Sponsor: City of Roswell, Georgia
This project focuses on the expansion of the Roswell Water Plant from its current 1.2 million gallons per day (MGD) to 5 MGD. The groundwater production wells will help the City meet the 5 MGD to comply with the Metro North Georgia Water Planning District Water Supply Plan.
Projected Cost – Out for Bid
Construction Award Sep 2011
Expected Project Completion in 2012
30 GPM WELL
350 GPM WELL COMBINED
GROUNDWATER WELLS PROJECT
BUILDING STRONG®
Swaybranch Detention Pond
Sponsor: City of Roswell, Georgia
The purpose of this project is to rehabilitate and combine a failing dual detention pond by removing the existing wet pond and dry detention dams and creating a single storm water detention facility
Projected Cost – Out for Bid
Construction Award Sep 2011
Expected Project Completion in 2012
BUILDING STRONG®
Mark Avenue/Noonday Creek Stormwater Structure - (ARRA)
Sponsor: Cobb County, Georgia
The purpose of this project is to construct a storm water detention structure across a tributary to Noonday Creek; about 300 to 400 feet upstream of Mark Avenue.
Projected Cost - $2,500,000 ARRA
Design Completed Spring of 2010
Construction started Mar 2011
Rock Encounter Delayed Construction 3 Months
Expected Project Completion in Mar 2012
BUILDING STRONG®
DeKalb County Stormwater Section 219 (ARRA)
Sponsor: DeKalb County, Georgia
The purpose of the project is to repair failing culverts that are inadequately sized to handle the storm water runoff.
Repairs include limited bank
shaping/rock stabilization upstream or downstream of the enlarged culvert
Projected Cost - $3,500,000 ARRA
Construction started Aug 2011
Expected Project Completion Aug 2012
BUILDING STRONG®
Vistavia Drive Stormwater Crossing
10
BUILDING STRONG®
Vistavia DriveStromwater Crossing
BUILDING STRONG®
Metropolitan North Georgia Water Planning District
The Water Resources Development Act (WRDA) of 2007, Section 5065 authorized the Corps to assist MNGWPD in carrying out environmental infrastructure projects.
Assisting the City of Atlanta and the North Georgia Regional Water Planning District Addressing Environmental Infrastructural Problems.
15 County Planning District Project Area.
75/25% Fed/Non-Fed Cost Share
Total Project Authorization Limited to $20 Million.
No Funds Appropriated
Model After Mississippi 592 Program
BUILDING STRONG®
Environmental InfrastructureSummary of North Georgia Authorities
(Sections 219, 5002, 5064 and 5065)
Section 219 – Design & Construction of water-related environmental infrastructure and resource protection and development projects (Maximum Authority $25M).
Section 5002 – Technical, Planning & Design Assistance. (No Construction)
Section 5064 – Design and Construction of water-related development and protection projects in the Big Creek Watershed.
Section 5065 – Design & Construction of water & wastewater infrastructure projects (Maximum Authority $20M ) .
Eroding Stormwater Detention Pond Spillway(219 Project)
BUILDING STRONG®
Environmental Infrastructure WRDA 1999 - Section 592 Program, Mississippi
Publicly owned
Project Partnership Agreement (PPA)
75% Federal/25% non-Federal
Operation & Maintenance 100% non-Federal
Authorization Limit $200 Million
BUILDING STRONG®
Section 592 Project StatusRegular Appropriations
Brooklyn – Installation of a New Centralized Wastewater System
Coahoma County –Sewer Rehabilitation and Installation of New
Water Distribution System *
Culkin – Upgrade of Water Distribution System *
Cruger - New Water Well and Distribution System Installation
Forest – Rehabilitation of the City’s Sewer System
Hattiesburg – Sewer System Improvements
McComb – Surface Water Resource Improvements *
Natchez – Surface Water Resource Improvements
Olive Branch – Sewer Rehabilitation and Installation of a Collection
System
Philadelphia Utilities- Water System Improvements and Sewer System
Rehabilitation
Summit – Sewer System Improvements
Wiggins – Rehabilitation and Extension of Sewer System
* - Scheduled for Close-out in FY11
ARRA Appropriations Biloxi, MS - Sewer Collection System
Greenwood, MS - Replace Sewer Force Main
Columbus, MS - Surface Water Resource Protection Improvements
Jackson County Utility Authority - Design & Construction For
Water Supply
Macon, MS - Replace & Improve Sewerage System *
Pascagoula, MS - Improvements To Municipal Sewer System
Pearl River County, MS - Waste Water Treatment Facility
Improvement
Richton, MS - Sanitary Sewer System Extension And Water Well
Installation
Tupelo, MS - Surface Water Resource Improvements
West Rankin Utility Authority – Wastewater Force Main
Replacement
Moss Point, MS – Sewer Rehabilitation Project
Port Gibson, MS – Water System Improvements
Pearlington, MS – New Water Well Installation
Waveland, MS – Sewer Rehabilitation Project
BUILDING STRONG®
Section 592 Project Status
CLOSED PROJECTS
► FY08
• MS Gulf Coast Community College, Perkinston, MS
• City of Gulfport
• City of Helena
► FY09
• City of Picayune
• City of Vicksburg
• West Rankin Utility Authority
► FY10
• Madison County Wastewater Authority
• City of Richland
• Community of Pearlington
BUILDING STRONG®
Section 592 Projections Project Partnership Agreement Execution Schedule
► Regular Obligations
• Pearl River Valley Water Supply District – August 2010
East Reservoir Area Sewer System Improvements
Total Cost: $5,995,100
Federal Cost: $4,016,325
• Hiwannee Water Association – September 2010
Water Well Installation
Total Cost: $1,075,000
Federal Cost: $806,200
• City of Vicksburg, MS – September 2010
Water Distribution System Improvements
Total Cost: $3,271,538
Federal Cost: $2,203,653
• Ocean Springs, MS – September 2010
Sewer Rehabilitation Project
Total Cost: $4,045,000
Federal Cost: $2,833,750
BUILDING STRONG®
Section 592 Projects
Culkin Water District
► 300,000 Gallon Elevated Water
Tank
► Total Project Cost: $1,560,950
BUILDING STRONG®
Section 592 Projects
Madison County Wastewater Authority
► Sewer Collection System
BUILDING STRONG®
Planning Process
Non-Federal public interest (sponsor) request USACE (Corps) for assistance.Must have a detailed description of project, design concept and a detailed cost;
Corps prepares letter report showing Federal interest for Division approval;
Upon report approval – Corps and sponsor sign Project Partnership Agreement (PPA);
Sponsor provides share of project funds to initiate design and construction. Sponsor can design and construct and be reimbursed against contract invoices;
All projects are subject to the National Environmental Policy Act (NEPA) requirements;
Sponsor shall acquire all needed lands, easements, rights-of-way, relocations and disposal (LERRD); and,
Sponsor operate and maintain 100 percent of the completed project.
US Army Corps of Engineers
BUILDING STRONG®
Questions?
Environmental Infrastructure Projects