Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
ENVIRONMENTAL IMPACT STATEMENT
August 2013 Report No. 11507150226.R01.A1
Record of Issue
Company Client Contact Version Date Issued Method of Delivery
NTCC Nuala O’Connell A.1 08/08/13 Hand delivery
ENVIRONMENTAL IMPACT STATEMENT
August 2013 Report No. 11507150226.R01.A1
Table of Contents
1.0 INTRODUCTION ........................................................................................................................................................ 1
2.0 PROJECT DESCRIPTION ......................................................................................................................................... 2
3.0 HUMAN BEINGS ....................................................................................................................................................... 3
4.0 ECOLOGY & APPROPRIATE ASSESSMENT ......................................................................................................... 4
5.0 SOILS AND GEOLOGY ............................................................................................................................................. 5
6.0 WATER ...................................................................................................................................................................... 6
7.0 CLIMATE ................................................................................................................................................................... 7
8.0 AIR ............................................................................................................................................................................. 8
9.0 NOISE ........................................................................................................................................................................ 9
10.0 LANDSCAPE ........................................................................................................................................................... 10
11.0 MATERIAL ASSETS: ARCHAEOLOGY & UTILITIES............................................................................................ 11
12.0 CLOSURE, RESTORATION & AFTERCARE ......................................................................................................... 12
13.0 INTER-RELATIONSHIPS ........................................................................................................................................ 13
LIST OF TABLES
Table 1.1: EIS Team Members
Table 1.2: Consultee List
Table 1.3: Assessment of alternatives and estimation of magnitude of impact
Table 2.1: Storage and Construction Volumes of Permitted Water impoundment Facility
Table 2.2: Type B Material
Table 2.3: Type C Material
Table 2.4: Type D Material (Road surfacing material)
Table 2.5: HDPE Properties
Table 2.6: GCL Properties
Table 2.7: Non-Woven Geotextile Properties
Table 2.8: Material Quantities for Permitted Water Impoundment Facility
Table 3.1: Population Statistics for Moyne DED
Table 3.2 Previous Planning Applications for Lisheen Mine with an EIS
Table 3.3: Employment Structure Classified by Broad Occupational Group for the Moyne DED
ENVIRONMENTAL IMPACT STATEMENT
August 2013 Report No. 11507150226.R01.A1
Table 3.4: Journey Times
Table 3.5: Details of local suppliers benefiting from Lisheen Mine continued operations
Table 4.1: Criteria for establishing receptor sensitivity/importance
Table 4.2: Criteria for Assessing Significance of Predicted Impacts
Table 4.3: Designated nature conservation sites within a 15 km radius of the proposed Site
Table 4.4: Main habitats recorded in the Study Area (Fossitt, 2000)
Table 4.5: Breeding Bird Survey Data
Table 4.6: Q-values Recorded by the Environmental Protection Agency (EPA Envision)
Table 4.7: Predicted Impacts of proposed works before mitigation
Table 4.8: Residual Impacts
Table 5.1: Importance of Geological Attributes in Vicinity of the Application Site
Table 5.2: Significance of Impacts on Soil and Geology
Table 5.3: Geotechnical Parameters for Stability Analysis
Table 5.4: Stability Modelling Results
Table 7.1: Monthly, annual means and extreme values from Lisheen Mine weather station (2008 – 2012) (Source:
Lisheen Mine)
Table 7.2: Dominant wind direction at Lisheen Mine over five years, (2008 - 2012).
Table 8.1: Particulate Limit Values of CAFE Directive 2008/50/EC & S.I. 58 of 2009
Table 8.2: Ambient Air Limits in former IPC Reg. No. 550
Table 8.3: Dust Deposition Limits in former IPC Reg. No. 550
Table 8.4: Ambient Air Limits in current IPPCL Reg. No. P0088-03
Table 8.5: Dust Deposition Limits in current IPPCL Reg. No. P0088-03
Table 8.6: Summary of air quality compared to current IPPCL Limit (2008 to 2012 inclusive)
Table 8.7: Summary of PM10 monitoring for assessment period 2010 to 2013
Table 8.8: Summary of general particulates at downwind receptors for the assessment period 2008 to 2012
Table 9.1: Noise Limits Set Out Under IPPC Licence
Table 9.2: Summary of noise results at Lisheen Mine for assessment period 2008 to 2012
Table 9.3: Published Sound Power Levels of Operational/capping plant
Table 13.1: Interactions
LIST OF FIGURES
Figure 1.1: Site Location Map (Regional)
Figure 1.2: Site Location Map (Local)
Figure 2.1: Site Location Map (Regional)
ENVIRONMENTAL IMPACT STATEMENT
August 2013 Report No. 11507150226.R01.A1
Figure 2.2: Site Location Map (Local)
Figure 2.3: Site layout plan for permitted water impoundment facility
Figure 2.4: Site layout plan for modification to store tailings
Figure 2.5: Sections A-A` & B-B` (See Figure 2.3 for section locations)
Figure 2.6: Sections C-C` & D-D` (See Figure 2.4 for section locations)
Figure 2.7: Typical sections & details of permitted water impoundment facility
Figure 2.8: Final closure plan (conceptual)
Figure 2.9: Plan & section showing instrumentation
Figure 2.10: Instrumentation details
Figure 4.1: EU and National Designations within 15 km of Lisheen Mine
Figure 4.2: Habitat Map
Figure 4.3: Sampling locations. (Sweeney, 2013)
Figure 5.1: Soil Classification (Source: GSI)
Figure 5.2: Sub-soil Classification (Source: GSI)
Figure 5.3: Bedrock Classification (Source: GSI)
Figure 7.1: Average monthly rainfall at Lisheen Mine for five years, (2008 - 2012)
Figure 7.2: Dominant wind direction at Lisheen Mine over five years, (Assessment Period 2008 to 2012)
Figure 8.1: Ambient Air Monitoring Locations
Figure 8.2: Dust Deposition Monitoring Locations
Figure 9.1: Noise Sensitive Locations, Noise Monitoring Locations and On-Site Noise Sources
Figure 12.1: Final Closure Plan (Conceptual)
Figure 12.2: Volume C of CRAMP (2013) - Details of wetland (Pg. 45)
LIST OF APPENDICES
Appendix 1.1: Review of relevant plans and policies
Appendix 4.1: NPWS Site Synopsis
Appendix 4.2: Water Quality Reports – Q values
Appendix 5.1: Stability Analysis
Appendix 6.1: SWS Water Impact Assessment
Appendix 9.1: BS 5228 Part 1 2009 Site Noise Calculation Methodology
Appendix 10.1: Landscape and Visual Impact Screening Letter
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1
Table of Contents
1.0 INTRODUCTION ........................................................................................................................................................ 1
1.1 Background................................................................................................................................................... 1
1.2 Overview of Proposed Development ............................................................................................................ 1
1.3 Structure of the EIS ...................................................................................................................................... 1
1.4 Methodology ................................................................................................................................................. 2
1.5 Structure ....................................................................................................................................................... 2
1.6 Team ............................................................................................................................................................ 3
1.7 Consultation .................................................................................................................................................. 3
1.8 Alternatives ................................................................................................................................................... 4
1.8.1 Introduction ............................................................................................................................................. 4
1.8.2 Summary of alternatives ......................................................................................................................... 4
1.8.3 Assessment of alternatives ..................................................................................................................... 5
1.9 Plans and Policies Assessment .................................................................................................................... 5
1.10 Difficulties in Compiling the Specified Information ........................................................................................ 5
1.11 References ................................................................................................................................................... 6
TABLES
Table 1.1: EIS Team Members ................................................................................................................................. 3
Table 1.2: Consultee List........................................................................................................................................... 3
Table 1.3: Assessment of alternatives and estimation of magnitude of impact ......................................................... 5
FIGURES
Figure 1.1: Site Location Map (Regional)
Figure 1.2: Site Location Map (Local)
APPENDICES
APPENDIX 1.1 Review of relevant plans and policies
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 1
1.0 INTRODUCTION
1.1 Background
This document comprises an Environmental Impact Statement (EIS), prepared in support of an application
made by Lisheen Milling Ltd. (Applicant/Lisheen Mine/Lisheen) to North Tipperary County Council (NTCC)
for permission to modify the use of a permitted water impoundment facility to store mine tailings at Lisheen
Mine, Killoran, County Tipperary. Regional and local site location maps have been provided in Figures 1.1
and 1.2, respectively. The EIS has been compiled in accordance with statutory requirements and non-
statutory guidance on EIS preparation for development projects.
The prime purpose of this EIS is to assist NTCC in determination of this ‘modification’ planning application.
To this end, the EIS provides information on the extent to which the proposed ‘modification’ activities have
the potential to result in any significant effects on the human and biophysical environment, and where this
potential is identified, to describe measures that would be undertaken where possible to avoid these effects
from arising. The consideration of this information in the form of an EIS is a requirement of the process for
determination of a planning application by NTCC described within the Planning and Development Acts, 2000
– 2012 and the associated Planning and Development Regulations, 2001 to 2012.
This EIS has been prepared by Golder Associates Ireland Ltd, (Golder), with the support of other
consultancy advisors and Lisheen Mine staff as necessary. A list of the main contributors to this EIS is
provided in Section 1.6 below. Consultations have been held with NTCC to confirm the scope of the
assessment required to support the content of the EIS and associated planning application.
Key areas of information presented within this EIS concern the nature and extent of the Proposed
Development, the character of the receiving environment and likely interactions between the two that could
result in significant environmental impacts. Information presented on the receiving environment identifies the
intrinsic value and importance of potential impact receptors.
1.2 Overview of Proposed Development
The proposed development, which is the subject of this planning application and associated EIS is
summarised as follows:
The development will consist of modification of the permitted water impoundment facility (permitted
under An Bord Pleanála Ref. No. PL22.100093 (North Tipperary County Council Reg. Ref.
PLC17663)) including use of the facility to provide for the storage and management of mine tailings
within the same structure (for the purposes of extending life of mine), and associated capping and
reinstatement activities. The proposed development also includes: the installation of spigots and
reclaim pumps; and all other ancillary site development works.
It is noted that any water displaced as a result of the proposed development, which cannot be accommodated in the permitted water impoundment facility/tailings structure as the mine nears closure, will be managed in the existing TMF, or in a wetland feature located downstream of the structure. This wetland feature already forms part of the Closure, Restoration and Aftercare Management Plan (CRAMP) (Volume C), and is in accordance with IPPC Licence Ref. No. P0088-03 and Planning Permission Ref. No. PL22.100093. Further details on this wetland feature are provided in Chapters 4.0 (Flora and Fauna), 6.0 (Water) and 12.0 (Closure).
1.3 Structure of the EIS
The EIS is made up of 13 no. chapters including this Chapter 1.0 – Introduction, with tables within each
chapter, and figures at the end of each chapter where relevant. The Non-Technical Summary appears as a
separate document.
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 2
1.4 Methodology
The methods of assessment have regard to guidance documents published by the Environmental Protection
Agency and other relevant statutory bodies, namely:
Guidelines for Planning Authorities and An Bord Pleanála on carrying out Environmental Impact
Assessment (Department of Environment, Community and Local Government, 2013);
Advice Notes on Current Practice in the preparation of Environmental Impact Statements
(Environmental Protection Agency, 2003); and
Guidelines on the Information to be contained in Environmental Impact Statements
(Environmental Protection Agency, 2002).
Each of the 13 no. chapters of the EIS follows the same general format, as follows:
An Introduction describing the purpose of the chapter;
A description of the Methodology used in the chapter;
A description of the aspects of the Existing Environment relevant to the environmental topic
under consideration;
An assessment of the Impact resulting from the proposed activities at the Application Site;
Recommendations for Mitigation measures to avoid, reduce, and where possible remedy any
significant negative impacts identified; and
An assessment of the Residual/Likely Significant Effects which will remain assuming that the
recommended mitigation measures are fully successfully implemented.
1.5 Structure
The EIS is structured under the following subject headings:
Chapter 1.0 Introduction;
Chapter 2.0 Project Description;
Chapter 3.0 Human Beings and Traffic;
Chapter 4.0 Flora and Fauna;
Chapter 5.0 Soils and Geology;
Chapter 6.0 Water;
Chapter 7.0 Climate;
Chapter 8.0 Air;
Chapter 9.0 Noise;
Chapter 10.0 Landscape;
Chapter 11.0 Material Assets: Archaeology and Utilities;
Chapter 12.0 Closure, Restoration and Aftercare; and
Chapter 13.0 Inter-relationships.
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 3
1.6 Team
The following team members were involved in the preparation of this EIS and are included in Table 1.1
below:
Table 1.1: EIS Team Members
Chapter Team Member
Introduction
Golder
Project Description
Human Beings and Traffic
Flora and Fauna
Soils and Geology
Water Schlumberger Water Services
Climate
Golder and Lisheen Milling Ltd. Air Quality
Noise
Landscape and Visual MosArt Landscape Architects
Material Assets: Archaeology and Utilities Irish Archaeology Consultancy, Golder
Closure, Restoration and Aftercare Golder and Lisheen Milling Ltd.
Inter-relationships Golder
Planning matters Tom Philips & Associates
1.7 Consultation
In preparation for this EIS and Planning Application, a number of consultation meetings and written
communications have been undertaken by Lisheen and Golder. Table 1.2 below summarises the consultee
list contacted in preparation of this EIS.
Table 1.2: Consultee List
North Tipperary Co. Council Planning Offices,
Nenagh Co. Tipperary (Meeting)
National Monuments Dun Sceine,
Harcourt Lane, Dublin 2 (Correspondence)
EPA Headquarters PO Box 3000,
Johnstown Castle Estate, Co. Wexford (Meeting)
Bord Gáis Energy 3
rd floor, City Quarter,
Lapps Quay, Cork (Meeting)
Lisheen Mine Community Forum Moyne,
Co. Tipperary (Meetings)
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 4
1.8 Alternatives
1.8.1 Introduction
In order to consider possible alternatives to the proposed development, the key principles of sustainable
development have been incorporated into this alternatives assessment, namely the consideration of social,
environmental and economic factors. This provides a systematic approach to evaluate project alternatives in
a robust manner, with the strengths and weaknesses of each option discussed under these principles of
sustainability.
1.8.2 Summary of alternatives
The following alternatives were considered as part of this alternatives assessment:
Alternative A - Construct a new tailings management facility (TMF) in an alternative location,
and not make use of the permitted water impoundment structure to store tailings. Due to
planning timelines and the potential of seasonal restrictions, construction would not commence
until spring 2014. The earliest this new TMF would be available for tailings storage would be
approximately Autumn/Winter 2014. Additional capacity to store tailings at Lisheen is required
in advance of this timeline;
Alternative B – Do nothing scenario. If additional tailings capacity is not made available, this
would result in the closure of the mine prematurely;
Alternative C – Planning application for modification of the permitted water impoundment to
store mine tailings. This would facilitate the additional capacity that Lisheen Mine requires for
tailings storage, and within the appropriate timeline. This would also allow for the continued
management of surface water (during operation) and through a permitted wetland feature (post
closure) (Volume C of current CRAMP for Lisheen). This alternative also facilitates the
progressive capping of the main TMF, as requested by the local community forum; and
Alternative D – Raising the existing TMF from 136.5mOD to 137.5mOD over an area of
approximately 40 ha. Following consultation with the local community, this alternative was
considered to be unfavourable based on social grounds, as the local community were very
much in favour of continued progressive restoration of the main TMF.
Each alternative is considered below with regard to the principles of sustainability (Social, Environmental and
Economic considerations).
Social considerations
Prior to the preparation of this EIS, Lisheen Mine has consulted with the local community representative
forum on a number of occasions. During these meetings, it was evident that the local community were very
much in favour of progressive capping of the main TMF, and that this should remain a priority of the
Applicant in the run up to mine closure. As such, the proposed modification of the permitted water
impoundment facility to store tailings (Alternative C) will facilitate such progressive capping works on the
main TMF by providing the additional tailings capacity required, and also allowing advanced capping
activities to continue uninterrupted. Alternatives A, B and D are less desirable from a social point of view, for
the following reasons:
Additional structure to be built in an alternative (greenfield) location thus presenting potentially
new social concerns e.g. landscape impact (Alternative A);
Significant loss of earnings in the local community due to closure of the mine prematurely
(Alternative B); and
Possible slowdown of capping operations due to raising of the existing TMF across 40 ha. area.
(Alternative D).
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 5
Environmental considerations
Alternative A is much less desirable than Alternative C from an environmental viewpoint, given that the
modification of the permitted water impoundment facility (Alternative C) is essentially the re-use of a
permitted structure, rather than the construction of a new facility in another greenfield location (Alternative
A). A new structure would result in additional land-take, and possibly give rise to fresh
planning/environmental concerns, in particular archaeology, landscape and traffic impacts as a minimum.
It is notable that the water that was to be stored in the permitted water impoundment structure will otherwise
be suitably managed during operation of the mine through the existing TMF and modified structure (in the
freeboard above tailings), and following capping and restoration, in a constructed wetland which already
forms part of the permitted CRAMP. This element of Alternative C is thus neutral in terms of environmental
impact. From the environmental perspective therefore, Alternative C is again most desirable.
Regarding, Alternative D, this option is favourable from an environmental viewpoint, however social concerns
were the over-riding consideration for this option (progressive restoration of main TMF).
Economic considerations
The re-use of the permitted water impoundment facility to store tailings is again most desirable from the
economic viewpoint, given that Alternative A (new TMF structure) would incur significant cost, and
Alternative B (closure prematurely), would be a cost of much greater significance to the operator and the
local community/people employed by the mine. Chapter 3.0 highlights the number of local businesses that
benefit from Lisheen Mine, which is quite significant.
From the economic perspective, Alternative D was also less desirable than Alternative C, given that an
upstream raise of 1.0 metre over an area of 40 ha. would be required.
1.8.3 Assessment of alternatives
Table 1.3 below provides a summary of the alternatives assessment:
Table 1.3: Assessment of alternatives and estimation of magnitude of impact
Description of Alternatives Social
Considerations Environmental Considerations
Economic Considerations
Alternative A - Construct new tailings management facility in alternative location
Moderate adverse
Moderate adverse
Significant adverse
Alternative B - Do nothing scenario - result in the closure of the mine prematurely
Significant adverse
Negligible Significant adverse
Alternative C - Planning application for modification of water impoundment to store mine tailings
Significant beneficial
Moderate beneficial
Significant beneficial
Alternative D - Raising the existing TMF from 136.5mOD to 137.5mOD over an area of approximately 40ha.
Significant adverse
Moderate beneficial
Slight beneficial
1.9 Plans and Policies Assessment
A review of plans and policies considered relevant to this application for proposed modification of the water
impoundment facility is included in Appendix 1.1 attached.
1.10 Difficulties in Compiling the Specified Information
No difficulties were encountered in the preparation of the EIS and planning application.
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1 6
1.11 References
1) Guidelines for Planning Authorities and An Bord Pleanála on carrying out Environmental Impact
Assessment (Department of Environment, Community and Local Government, 2013);
2) Advice Notes on Current Practice in the preparation of Environmental Impact Statements
(Environmental Protection Agency, 2003); and
3) Guidelines on the Information to be contained in Environmental Impact Statements (Environmental
Protection Agency, 2002).
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1
FIGURES
0 1,000 2,000500Meters
1.1 V.1Golder Associates (IRL) Ltd
Town Centre HouseDublin Road
NaasCo. Kildare
Tel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
Lisheen Milling Ltd.
KMG CW CW AUGUST 2013
AR0056013 11 5071 5 0226
A4 A.01:50,000
Planning Application
Site Location Map (Regional)
2N
LegendApplication Site BoundaryLands Under Control of the Applicant
0 500 1,000250Meters
1.2 V.1Golder Associates (IRL) Ltd
Town Centre HouseDublin Road
NaasCo. Kildare
Tel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
KMG CW CW AUGUST 2013
AR0056013 11 5071 5 0226
A4 A.01:25,000
OSI Tile Purchased - 04/04/2013Discovery Series 60
Lisheen Milling Ltd.
Planning Application
Site Location Map (Local)
2N
LegendApplication Site BoundaryLands Under Control of the Applicant
CHAPTER 1.0 INTRODUCTION
August 2013 Report No. 11507150226.R01.1.A1
APPENDIX 1.1 Review of relevant plans and policies
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1
Table of Contents
1.0 PLANS AND POLICIES REVIEW ............................................................................................................................. 1
1.1 Introduction ................................................................................................................................................... 1
1.2 Broad Planning Context ................................................................................................................................ 1
1.3 NTCC County Development Plan 2010-2016 ............................................................................................... 2
TABLES
Table 1: Chapter 4 - Environment ....................................................................................................................................... 2
Table 2: Chapter 6 - Economic Activity ............................................................................................................................... 4
Table 3: Chapter 8 - Built and Natural Heritage .................................................................................................................. 5
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 1
1.0 PLANS AND POLICIES REVIEW
1.1 Introduction
This document reviews the principal development control policies of particular relevance to the Application
Site. In particular, situations are identified where key policy objectives are supported or contravened by the
proposals.
Section 1.2 of this chapter reviews the broad planning context to development control decisions within North
Tipperary County Council (NTCC).
Development control decisions within NTCC are made largely within the context of the County Development
Plan. The Plan sets out the development control policy framework against which the planning application
would be determined. This is described in the Section 1.3.
1.2 Broad Planning Context
The broad planning context to development control decisions within NTCC includes the National Spatial
Strategy, Regional and National Planning Guidelines, the Water Framework Directive, the County
Landscape Assessment, Flood Guidelines and adjoining local Authority Development Plans. The following
sections provide an overview of these aspects of the NTCC broad planning context.
The National Spatial Strategy (2002) is a 20-year planning framework that aims to achieve a better balance
of social, economic and physical development across the Country supported by more effective planning.
Core messages from the National Spatial Strategy include:
A wider range of work opportunities;
A better quality of life for all; and
Effective urban and rural planning leading to an environment of the highest quality.
Regional Authorities have an important role in the implementation of the National Spatial Strategy through
the preparation and implementation of regional socioeconomic strategies and regional planning guidelines.
The North Tipperary County Development Plan is fully supportive of strategic policy guidelines set out in the
Mid-West Regional Economic Strategy and Regional Planning Guidelines (2010 to 2022).
The Water Framework Directive (2000) describes a framework for comprehensive water resource
management within the European Community. The fundamental objective of the Water Framework Directive
concerns the maintenance of “high status” water resources and the prevention of deterioration in the existing
status of water resources. This is addressed in Chapter 4.0 and 6.0 of the EIS.
The County Landscape Character Assessment provides the basis for assessment and classification of
landscape for the County to inform planning decisions that concern the potential for a change in landscape
character.
Flood Guidelines (2009) introduce comprehensive mechanisms for the incorporation of flood risk
identification, assessment and management into the planning process.
The County Development Plan has been prepared with regard to Development Plan Guidelines (2007),
guidelines and circular documents published by the Department of Environment, Heritage and Local
Government (DoEHLG) as they relate to land use planning. Relevant guidelines and circulars are referenced
against specific County Development Plan policies as appropriate.
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 2
1.3 NTCC County Development Plan 2010-2016
The NTCC County Development Plan (CDP) has been prepared in accordance with the Planning and
Development Act 2000 (as amended) and sets out the Council’s Strategy, vision and objectives for planning
and sustainable development within the County. The CDP draws upon relevant National and Regional
Plans, Policies and Strategies that concern planning and sustainable development.
Of particular relevance to the Application Site, the CDP sets out objectives for:
Environmental protection;
Economic activity; and
Built and natural heritage.
The following sections of this appendix provide a synopsis of key policy implications of the Proposed
Development for the above NTCC CDP development control considerations.
CDP Chapter 4 - Environment
Policies concerning environmental protection aspects of development control within NTCC are presented
within Chapter 4 of the CDP. A brief assessment of the policies is undertaken in the context of the proposed
application.
Table 1: Chapter 4 - Environment
Policy Assessment
Policy ENV 1: General Policy
It is the policy of the Council to implement the
Habitats Directive and that where relevant, projects
will be screened by the Council for the need to
undertake a Habitats Directive Assessment under
Article 6 of the Habitats Directive.
A Habitats Directive Assessment is required
for the Application Site and a Natura Impact
Statement has been prepared accordingly,
which concludes that no significant effect on
the receiving waters will occur following the
introduction of mitigation measures. Final
details of which are to be agreed with the
regulators.
Policy ENV 2: Landscape Protection
It is the policy of the Council in assessing
applications for development that would impact on
landscape to balance the need to protect landscape
character against the requirement for socio-
economic development in accordance with value
assessment and sensitivity as identified in the
County Landscape Character Assessment 2009.
The assessment presented in this EIS
concludes that no aspect of the proposed
modification from permitted water
impoundment to a tailings storage facility will
result in any significant adverse effects on
landscape conservation priorities within North
Tipperary.
Policy ENV 3: Vulnerable Landscapes
It is the policy of the Council to resist development
that would:
(d) Materially impact upon the character, integrity or
uniformity of a vulnerable landscape or scenic area
when viewed from scenic routes and the environs of
archaeological or historic sites.
This policy identifies the protection of vulnerable
As Chapter 10 of this EIS screens out the need for visual impact assessment, this Policy is not considered to be relevant for this planning application
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 3
Policy Assessment
landscapes or scenic areas, views from scenic
routes and landscapes in proximity to historic sites
as priority objectives.
Policy ENV 4: Views and Prospects
It is the policy of the Council to protect views and
prospects of special amenity value or special
interest.
As Chapter 10 of this EIS screens out the need
for visual impact assessment, this Policy is not
considered to be relevant for this planning
application.
Policy ENV 5, ENV 7, ENV 17, ENV 18
Policy ENV 5: Water Framework Directive
It is Council policy to implement the provisions of any
water quality management plans prepared at a
national, regional or local level. These policies
concern the protection of surface and groundwater
resources from adverse effects of development
projects.
A detailed water impact assessment (Chapter
6.0) has been prepared by Schlumberger
Water Services (SWS) to address these
policies. As concluded by SWS, there will be
no significant impact on water quality of the
receiving waters (surface and groundwater),
including the Drish and Rossestown Rivers, as
a result of the proposed activities.
Policy ENV 7: Groundwater Protection
It is the Council’s policy to protect groundwater
resources and drinking water catchments.
Policy ENV 17 Water Protection
Land uses shall not give rise to the pollution of
ground or surface waters.
Policy ENV 18: Flooding
It is the policy of the Council to implement the
recommendations of the DoEHLG Guidelines entitled
‘The Planning System and Flood Risk Management’
in the management of development within the
County.
Policy ENV 20: Agriculture
It is the policy of the Council to protect the viability of
farms and best quality land for agriculture and
related uses. Proposals that are considered to have
a negative impact on the viability of existing farms
will not be favourably considered.
With regard to the proposed tailings facility,
local farmland is vulnerable to loss of value
through changes in groundwater quality that
could arise from contamination associated with
a failure of the TMF liner. The proposed
facility is adjacent to the existing TMF and will
be engineered to address any potential
seepage impacts. In addition a significant
monitoring network will be established similar
to that of the existing TMF and will act as a
warning system for potential contamination
issues. As described in subsequent sections
of this EIS, in particular Chapter 6.0 (Water),
significant adverse effects of the Proposed
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 4
Policy Assessment
Development on groundwater and surface
water are considered unlikely to occur. As a
consequence, the proposals will not to
contravene this policy.
Policy ENV 43: Noise and Dust
It is the policy of the Council to seek to minimise the
noise through the planning process by ensuring that
the design of future developments incorporates
measures to prevent or mitigate the transmission of
noise and vibration where appropriate.
As described later in this EIS (Chapter 9.0),
management controls are in place to mitigate
potential impacts associated with noise or
dust. As a consequence, the proposed
modification from permitted water
impoundment to tailings facility would not
contravene objectives of Policy ENV 43 that
seek the avoidance of vibration associated
with development projects.
CDP Chapter 6 – Economic Activity
Policies relating to aspects of development control decisions that concern economic activity within NTCC are
presented within Chapter 6 of the CDP. Policies of particular relevance to determination of the planning
application, are considered below.
Table 2: Chapter 6 - Economic Activity
Policy Assessment
Policy ECON 1
Policy ECON 1: Employment Growth and Promotion
It is the policy of the Council to promote, encourage
and facilitate enterprise and employment throughout
the County.
Modifying the use of the permitted water
impoundment to a tailings facility supports continued
mining activities and as such consolidation of
employment prospects. It is therefore considered
that the proposed activities support the objective of
Policy ECON 1.
Policy ECON 4: Masterplan for Lisheen Mine Site,
Moyne Templetouhy, Thurles
It is a policy of the Council to co-operate with the
owners/operators of the Lisheen Mine site in the
promotion and the development of lands situated at
Moyne Templetouhy to provide for proper planning
and sustainable development of the area. The
Council will promote development which will provide
for the following:
(e) Reuse of existing infrastructure within the mine
complex wherever possible.
Re-using the permitted water impoundment as a
tailings facility reduces potential for impact on land if
a new tailings facility were to be sited elsewhere. As
such the proposed activities are considered to
support the objective of Policy ECON 4, given that
this application is proposing to reuse a water
impoundment facility currently permitted under An
Bord Pleanála Ref. No. PL22.100093 (North
Tipperary County Council Reg. Ref. PLC17663).
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 5
Policies relating to aspects of development control decisions that concern built and natural heritage within
NTCC are presented within Chapter 8 of the CDP. Policies concerning this planning application are
considered below.
Table 3: Chapter 8 - Built and Natural Heritage
Policy Assessment
Policy HERT 25/26 – Historically Important Sites
It is the policy of the Council to:
(iii) Preserve, protect and where necessary enhance
significant heritage objects such as mass rocks and holy
wells and/or other significant cultural features that form part
of the cultural heritage of the County. Chapter 11.0 of the EIS addresses
archaeology and cultural heritage. The
proposed activities will not impact on any
archaeological features, therefore an
archaeological assessment was screened
out.
Policy HERT 26: Archaeology
It is the policy of the Council to protect all monuments
included in the Record of Monuments and Places. The
Council will also seek to protect, where practicable, the
setting of and access to sites, views and prospects of the
sites and will ensure sympathetic development adjoining and
in the vicinity of sites.
Policy HERT 27: Tree Preservation
It is the policy of the Council to seek the protection of mature
trees and hedgerows that contribute to amenities of the area.
No trees or hedgerows will be removed as a
result of this proposed application, therefore
this policy is not considered to be relevant to
this application.
Policy HERT 29: Designated Environmental Sites
It is the policy of the Council to maintain the quality and
conservation value of designated environmental sites,
including SACs, cSACs, SPAs, cSPAs, NHAs and pNHAs,
and when assessing development proposals to provide for
the protection, conservation and enhancement of wildlife
habitats and designated sites.
Chapters 4.0 (Flora and Fauna), 6.0 (Water)
and 12.0 (Closure) are intended to address
these policies, to ensure that all designated
environmental sites will be protected during
any proposed activities in this planning
application.
Policy HERT 29a: Protection of Designated Environmental
Sites
It is the policy of the Council to restrict any development
which would be harmful to or that would result in a significant
deterioration of habitats and/or disturbance of species in a
SAC, cSAC, SPA, cSPA, NHA or pNHA.
Policy HERT 30: Protection of Areas of Nature Conservation
It is the policy of the Council in Areas of Nature Conservation
that proposals for development will only be permitted where
it can be clearly demonstrated there is no direct or indirect
adverse effect on:
(i) areas designated as sites or candidate or potential sites of
national or international importance for wildlife;
APPENDIX 1.1 - PLANS AND POLICIES REVIEW
August 2013 Report No. 11507150226.R01.1.1.A1 6
Policy Assessment
(ii) protected species and their habitats;
(iii) features of major importance to wild flora and fauna;
(iv) important features of geological or geomorphological
importance; and
(v) local biodiversity.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 1
2.0 THE PROPOSED DEVELOPMENT
2.1 Introduction
This chapter of the EIS provides details of the main features of the permitted water impoundment facility,
which is currently permitted under Planning Permission Ref. No. PLC17663 and ABP Ref. No.
PL22.100093. It is proposed to modify use of this facility to accept tailings, therefore a detailed description of
this facility is considered relevant to set out the baseline conditions, into which mine tailings will be placed
over a c. 12 month period.
As the proposed development is an extension to current operations at Lisheen Mine, an outline of the main
components and mining activities currently under way at Lisheen is also provided. Where appropriate,
specific design features necessary to enable the permitted water impoundment facility to store tailings are
identified.
2.2 Current Operation
Lisheen Mine has been operational since 1997, with production underway since 1999. The mine is located
c. 12 km north east of Thurles and c. 4 km south west of Templetouhy, County Tipperary. The general
location of the current operation at Lisheen Mine is shown in Figure 2.1.
The current mining operation at Lisheen comprises the following principal facilities:
A 1.5 km long main decline, providing primary access to four key mining zones;
A mine ventilation system with above ground vent raise structures;
Underground primary crushing plant and conveyor system for transport of mined rock above ground;
Surface ore stockpile and ore processing mill;
Paste backfill plant, operational since 2005;
Tailings Management Facility (c. 68 ha.), with approximately 10 ha. capped in 2010, and Phase 2
capping currently being undertaken as of May 2013. Progressive capping is expected to continue in the
next 2 years;
Minewater treatment plants, conditioning ponds and infrastructure for discharge of treated mine-water to
the Drish and Rossestown Rivers; and
Site offices, maintenance shops, weighbridge, access roads and associated facilities.
The mine currently produces c. 7,000 tonnes of Zinc and Lead ore per day, with extraction taking place from
several ore bodies within an extensive area of Carboniferous Waulsortian Limestone. Excavated rock is sent
to a primary underground crusher, with crushed ore transferred by covered conveyor along the main decline
to an above ground covered stockpile.
The ore is then transferred by covered conveyor to the processing plant where it is crushed to a powder by
sag and ball mills. Recycled water is then used to convert crushed ore to a slurry that is passed to floatation
cells for separation of Zinc and Lead. These are then thickened and filtered to form a stable concentrate.
This is then transferred by road to a coastal transfer facility where the concentrate is loaded to ships for
distribution to countries around the world.
Lisheen Mine currently operates four principal mining areas with an average ore depth of c. 170 m below
ground surface:
Main Zone – the largest mining area and the first to be developed;
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 2
Derryville Zone – also mined from the outset at Lisheen;
Bog Zone – three separate ore bodies that have been mined since 2007; and
Derryville Island pod – mined since 2012.
Much of the ore deposit has been mined from the full area of each mining zone. With the exception of Bog
Zone, Derryville Island pod and a small area of the Main Zone, the footprint of the mine has not been
significantly extended since around 2007. Mining operations are programmed to cease at Lisheen in spring
2015. Provisions for progressive closure, decommissioning, monitoring and aftercare at Lisheen are
reviewed within Chapter 12.0 of this EIS.
2.3 Need for the Development
The following section highlights the need for this proposal to modify use of the permitted water impoundment
facility to accept tailings:
As the mine approaches the end of its life it becomes increasingly difficult to predict the extent of
tailings likely to be ultimately produced due to a variety of factors including;
Mine plan optimisation – the Lisheen Mine is required to maximise the national resource under the
terms of the mine lease. To achieve this annual reviews of the mine plan are carried out to extract
as much economic ore as technically possible. This is influenced strongly by the markets e.g. metal
price, exchange rates etc.;
Increased ore reserve as a result of developing the mine; and
Increased ore tonnage reserve from the Derryville Island ore body (Permission granted in 2012).
These changing circumstances are constantly under review with the mine planners and geologists as
the extraction of the tail of the mine project is maximised, and therefore makes it very difficult to
accurately predict the final tailings quantum for storage at surface. In this regard, the final exact
quantum of tailings is currently unknown. Current indications however predict additional storage is
required;
Through careful design, the quantum of storage in the existing TMF may be further maximised. This
too is an evolving process. As with the mine, when the TMF is reaching capacity, accurately predicting
its final capacity is also difficult. The ability to manage storm water surges is another consideration. In
this regard, the proposed modification of the permitted water impoundment facility will still allow for the
ancillary use of the structure for surface water management purposes as part of the site’s overall water
management system;
At current estimates, it is predicted that it may be necessary to provide for an additional storage of
approximately 390,000 m3 void for tailings in order to maximise the mine life through the exploitation of
the ore in the mine (as is required, by the Department under its mining lease);
In order to minimise the footprint of the residual development following closure, and facilitate
progressive capping of the main TMF, the ideal location for this contingency tailings storage is in the
permitted water impoundment structure located adjoining the existing TMF; and
The design of the permitted water impoundment facility is identical in engineering terms to a structure
required for the storage of tailings.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 3
2.4 Site Conditions
The following sections describe the site conditions under the permitted water impoundment facility, providing
background to the receiving environmental setting of the facility to accept tailings.
2.4.1 General
Site investigation work was undertaken at the location of the permitted water impoundment facility from
previous studies and the following text is based on data obtained from this and construction records relating
to the removal of peat during the raising of the main Tailings Management Facility (TMF), (Planning Study
Technical Report, 1995).
2.4.2 Bedrock
The bedrock underlying the permitted water impoundment facility comprises a thin layer of Waulsortian
Limestone some 30 m to 80 m thick with the upper section dolomitised. This overlies the argillaceous
limestone of the Ballysteen Limestone Formation.
The dolomitised Waulsortian Limestone can contain paleokarst features particularly when faulted. However,
the permitted water impoundment facility is located on the footwall side of the ore zones within an area of low
fault incidence, and therefore, the paleokarstic potential of the site is low as previously indicated for the
existing TMF (Planning Study Technical Report, 1995).
2.4.3 Hydrology
The existing TMF and adjoining permitted water impoundment facility is located in the Suir River catchment,
between the Rossestown River and the Drish River (Planning Study Technical Report, 1995). The Drish
River flows northwards around the southern edge of the site, then deviates south westwards to join the Suir
River south of Thurles. A small tributary of the Drish River rises in the Derryville Bog and flows across farm
land to join the Drish River 3 km south of the orebodies. The Rossestown River rises 1.5 km east of
Templetouhy and initially flows through the bog, then farmland to the Suir River.
Rainfall data at Lisheen has been collected since 1991 and indicates the mean annual rainfall between
840 mm and 900 mm. The mean potential evapotranspiration at Lisheen has been estimated to be
approximately 450 mm (GAUK, 1997, Report No. 96512126). The dry periods correspond to the summer
months when evaporation is at a maximum. The wet periods are late autumn and winter.
2.4.4 Groundwater
The peat aquifer in the vicinity of the permitted water impoundment facility is connected to the regional
groundwater regime by the relatively low permeability glacial till which occurs beneath the peat. During
mining, the major dewatering activities have had an impact on the groundwater levels beneath the existing
TMF and adjoining permitted water impoundment facility. The maximum drawdown is between 3 m and 10
m from the existing water levels which equates to between 0 m and 6 m into the bedrock.
2.4.5 Seismicity
A peak horizontal ground acceleration of 0.16 g, representing a 1 in 10,000 year event (Maximum Credible
Earthquake, MCE) has been used in stability calculations (Planning Study Technical Report, 1995).
2.5 Design details of the Permitted Water Impoundment Facility
The proposed development that is the subject of this EIS comprises a modification from water storage to the
storage of tailings at a permitted water impoundment facility adjoining the main TMF. The general location of
the permitted water impoundment facility is depicted in Figures 2.1 and 2.2.
The following sections describe the permitted water impoundment facility in detail. It is noted that the
permitted impoundment facility was originally designed to accept both water, and if the need arose, to also
store tailings as a contingency measure. Its design is similar to the existing main TMF facility, previously
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 4
approved under Planning Reference No. PLC17663/ABP Ref. No. PL22.100093, and IPPC Licence Reg.
no. P0088-03.
2.5.1 General
The location of the permitted water impoundment facility is along the northern sector of the north-west wall
(Figures 2.1 and 2.2.) and confined between the mine site boundary and a nearby wind turbine, and provides
a potential water storage of 390,000 m3 at a maximum water elevation of 130.5 metres above Ordnance
Datum (mOD) and embankment crest elevation of 131.5 mOD. The storage and construction volumes of the
permitted water impoundment facility are presented in Table 2.1 below.
Table 2.1: Storage and Construction Volumes of Permitted Water impoundment Facility
Final water elevation mOD
Crest Elevation mOD Water and/or Tailings Storage Volumes m
3
Cumulative Months Storage for tailings
130.5 131.5 c. 390,000 10.7 months
The plan area of the permitted water impoundment facility at a crest elevation of 131.5 mOD is presented in
Figure 2.3. Figure 2.4 depicts the structure once modification activities commence. Sections and details
through the structure permitted to store water and accept tailings are presented in Figures 2.5 and 2.6
respectively.
The shape of the permitted water impoundment facility is a truncated triangle with a footprint area of
approximately 9.0 ha. at a crest elevation of 131.5 mOD. The dam wall is designed in a similar manner to
the original main TMF design (GAUK, 2011, Report No. 1051415188).
2.5.2 Dam wall sections
Design details of the dam walls are further presented in Figure 2.7. A perimeter roadway is located at an
approximate elevation of 126 m and merges with the perimeter road around the existing TMF, with a crest
width of c. 6.0 m.
The adjoining wall of the permitted water impoundment facility to the existing TMF is already at an elevation
of 136.5 m. A bench is located to an elevation of 131.5 mOD. This bench supports a road that provides
access around the perimeter of the permitted water impoundment facility, and in which the anchor trench for
the lining system is located.
2.5.3 Permitted water impoundment construction materials
The bulk of the permitted water impoundment dam wall is made up of rockfill termed Type B material,
primarily limestone or shaley limestone with a maximum particle size of 300 mm. A 300 mm layer of
screened rockfill Type C material is placed over the Type B on the upstream side of the dam walls to provide
protection for the lining system. The maximum particle size of the Type C is 20 mm and the material is well
graded.
A 1,000 grm/m2 non-woven geotextile is placed on top of the Type C material prior to placement of the lining
system. The adjoining TMF wall is cleaned of vegetation, trimmed to receive the 300 mm layer of Type C
followed by 1,000 grm/m2 non-woven geotextile. The Type C on the dam walls is connected with the 100
mm layer of Type C placed on the basal construction platform formed underneath the footprint of the basin
area. When these materials are placed, the composite lining is formed along the base, up the slope and
anchored on the crest.
The grading sizes for the various materials in the construction of the permitted water impoundment facility
are summarised in Tables 2.2, 2.3 and 2.4 below.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 5
Table 2.2: Type B Material
Sieve Size (mm) % Passing
300 100
75 50-100
20 30-65
2 0-30
0.600 0-10
Table 2.3: Type C Material
Sieve Size (mm) % Passing
20 100
6.3 65-90
1.18 30-60
0.300 15-30
0.075 0-20
Table 2.4: Type D Material (Road surfacing material)
Sieve Size (mm) % Passing
37.5 100
20 85-100
10 70-100
6.3 60-90
1.18 15-30
0.300 5-20
0.075 0-10
2.5.4 Composite lining
The permitted water impoundment facility incorporates a composite lining system specifically designed to
store both water and tailings, which consists of high density polyethylene (HDPE) geomembrane over a
geosynthetic clay liner (GCL) as shown in section in Figure 2.7.
High Density Polyethylene (HDPE)
The HDPE is 2 mm thick, double textured and is placed directly over GCL on the 2H:1V upstream slopes of
the dam wall. In the basin area the HDPE is smooth and is placed directly over the GCL. The HDPE and
GCL are anchored along the dam crest.
The geomembrane materials consist of high density polyethylene, produced from new resins and containing
no fillers, plasticisers or additives of any kind with the exception of carbon black.
The geomembrane complies with the requirements set out in the Table 2.5 below for 2.0 mm double textured
and smooth geomembrane.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 6
Table 2.5: HDPE Properties
Parameters Properties
Material Double Textured 2 mm Smooth 2 mm
Thickness (minimum average) nom. (mil)
lowest individual of 10 values -10% -10%
Density mg/l (minimum.) 0.940 g/cc 0.940 g/cc
Tensile Properties (minimum average)
yield strength 29 kN/m 29 kN/m
break strength 21 kN/m 53 kN/m
yield elongation >12% >12%
break elongation >100% >700%
Tear Resistance (minimum average) 250 N 249 N
Puncture Resistance (minimum average) 500 N 640 N
Stress Crack Resistance 300 hr. 300 hr.
Carbon Black Content (range) 2.0-3.0% 2.0-3.0%
The geomembrane installation is independently supervised and subjected to a strict CQA procedure, in
accordance with EPA and IPPC Licence requirements.
Geosynthetic Clay Liner (GCL)
The GCL is placed beneath the HDPE geomembrane and over the Type C sub-base material on the
upstream dam slopes and basin area of the permitted water impoundment facility.
The GCL is Bentofix/approved equivalent and the grade is 3600 g/m2 dry weight with a maximum
permeability of 5E-11 m/s. The GCL consists of a layer of natural sodium bentonite clay encapsulated
between two polypropylene textiles (geotextile), the properties of which are displayed in Table 2.6 below.
Table 2.6: GCL Properties
Parameter Properties
Bentonite Layer
Swell Index, Minimum 24 ml/2g
Fluid Loss, Maximum 18 ml
Sodium Bentonite, Minimum 3600 g/m2
Geotextile Mass (Minimum Average Roll Value)
Slit-Film Woven 105 g/m2
Nonwoven Needle Punched 200 g/m2
Index Flux (Maximum) 8x10-9
m3/m
2/s
Hydraulic Conductivity (Maximum) 5x10-11
m/s
Peel Strength (Minimum) 240 N/m
Strip Tensile Strength (Minimum)
Machine Tensile Strength 8 kN/m
Elongation 8%
Across Tensile Strength 8 kN/m
Elongation 8%
Hydrated Internal Shear Strength (Minimum) 24 kPa
For purposes of strength, performance, and integrity, the GCL is manufactured by mechanically bonding the
geotextile using a needle-punching process. Needle-punched GCLs are those which, by the use of a
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 7
needling board, have fibres of the non-woven geotextile pushed through the bentonite clay layer and
integrated into a woven or non-woven geotextile.
The bentonite sealing compound or bentonite granules used to seal penetrations and make repairs are made
of the same natural sodium bentonite as the GCL and are as recommended by the GCL manufacturer.
The GCL installation is independently supervised and subjected to a strict CQA procedure, again in
accordance with EPA and IPPC Licence requirements.
2.5.5 Geotextile
General
Three types of geotextile material are used, a 1000 grms non-woven needle punched to protect the lining
system from underneath, a carbon rich 500 grms non-woven needle punched to protect the lining system
from above on the slope and a Terram 1000 or equivalent as a separation material.
500 grms and 1000 grms/m2 Non-Woven Geotextile
A 1000 grm/m2 non-woven needle punched geotextile is required to protect the GCL and HDPE
geomembrane from the underlying Type C material which in turn is placed on top of the Type B material. A
carbon rich 500 grm/m2 non-woven needle punched geotextile is required in the anchor trench and on the
surface of the HDPE to protect this material from the surcharge and movement of pipe work.
The physical and mechanical properties of the 1000 grm/m2 and 500 grm/m
2 non-woven needle punched
geotextile are given in Table 2.7 below.
Table 2.7: Non-Woven Geotextile Properties
Parameter Specification 1000 grms/m2 Specification 500 grms/m
2
CBR Puncture Resistance Minimum 10,000 N Minimum 5,000 N
Wide Width Tensile Strength Minimum 75 kN/m Minimum 40 kN/m
Elongation at break Minimum 50% Minimum 50%
Thickness Minimum 8.0 mm Minimum 5.0 mm
Mass per unit area Minimum 1000 g/m2 Minimum 500 g/m
2
2.5.6 Anchor trench
The geo fabrics are fixed in an anchor trench excavated along the crest of the dam wall as shown in Figure
2.7. The trenches are excavated with rounded shoulders where the geotextile and geomembrane lining
adjoin the trench in order to avoid sharp curvatures in the membrane material. The trench is then backfilled
with screened Type C material and compacted in layers not exceeding 150 mm deep.
2.5.7 Permanent surcharge
A permanent surcharge is used on the exposed geomembrane to prevent the HDPE from being lifted and
damaged by wind action and minimise damage from pipe movements. It also acts as a ladder if someone
accidently falls into the facility. The surcharge consists of car tyres in-filled with Type C material and placed
on the carbon rich 500 grms/m2 non-woven needle punched geotextile. Each line of surcharge has a
maximum of 2 m centres longitudinally and anchored on the crest and the weights consisting of car tyres are
a maximum of 1.5 m apart down slope, and where applicable on the lining placed on the floor of the tailings
and a minimum distance of 1 tyre width beyond the downstream toe. The two tyres at the toe of the slope
and 1 tyre width beyond are tied together. The tyres are also attached by suitable rope with a minimum life
of 4 years.
2.5.8 Material quantities
The volumes of material that make up the permitted water impoundment facility are listed in Table 2.8 below.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 8
Table 2.8: Material Quantities for Permitted Water Impoundment Facility
Description Crest Elevation 131.5 mOD
Volume m3
Volume of impoundment facility 390,000
Type B Wall construction 149,000
Type B Platform construction (basin) 23,500
Type B to Existing Embankment 5,200
Type C Wall construction 3,000
Type C Platform construction (basin) 4,500
Type C Existing Embankment 2,100
Type D Road surfacing 1,600
Area m2
1000 grms/m2 geotextile 63,500
500 grms/m2
geotextile 16,500
Terram 1000 23,500
GCL 63,500
HDPE 63,500
2.5.9 Seepage
Seepage from the permitted water impoundment facility is controlled by the low permeability composite lining
system, and the level of stored material within the basin. Experience of a large number of quality assured
and controlled geomembrane installations indicates (Proposed Construction Quality Assurance and Control
Plan for the TMF Construction at Lisheen Mine, 1997) the presence of between 2 and 5 leaks per ha. and
these are generally less than 10 mm2 in size.
Seepage calculations have been based on the design equations given in Giroud, et al. (1989 and 1992) and
for the worst case, when the facility is filled with tailings.
The volume of seepage flowing laterally through the dam wall via the GCL and geomembrane would be in
the range of <2 m3/day to <3 m
3/day at the final condition. After 30 years some deterioration of the
geomembrane can be expected and seepage through the dam wall could increase to the order of <2 m3/day
to <5 m3/day through the total area of the structure.
2.5.10 Perimeter interceptor channel
Seepage passing through any potential defects in the lining system from the walls of the dam will
theoretically discharge into the perimeter interceptor channel.
2.5.11 Embankment stability modelling
The stability analysis for the water impoundment facility was carried out using commercially available limit-
equilibrium slope stability software, SLOPE/W version 7.15. Further details on this modelling are included in
Chapter 5.0 (Soils and Geology).
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 9
2.6 Proposed Operations – Storage of Tailings
2.6.1 Operation phase
The new tailings facility will be operated similarly to the existing TMF by discharging the tailings from spigots
on the dam crest. The spigots will be opened sequentially and the tailings will be discharged uniformly over
the new TMF. Because of the limited perimeter length, consideration is given to discharge points every 50 m
and two tailings lines will be operated around the facility in opposite directions. Unlike the main TMF, there
will be a significant depth between the crest and the basin floor and the system currently used on the main
TMF is not well suited to cope with such a depth as that found in the new facility. A slotted discharge pipe
from the valve to the floor of the basin is therefore proposed. The slotted discharge pipe will be anchored on
top of the tyre surcharge which is placed directly on the lining. Alternatively, the end of the pipe could be cut
off as the tailings rises although this will require further consideration if it is to be utilised.
It is anticipated that tailings deposition will be alternated between the main TMF and the new facility to
optimise the filling of both facilities. As part of the current closure plan the tailings is progressively capped
with 700 mm of limestone once the tailings beach is at its final height and has reached sufficient strength
through drainage. Operationally it is difficult to ensure that the rate of tailings beach formation matches the
rate at which they become ready for capping once the facility gets close to full capacity. Being able to switch
the tailings deposition between the two facilities will thus assist progressive restoration and ensure tight filling
of the main facility.
When tailings are deposited in the new facility it will be done at a rate of about 3,500 tonnes/day. The
tailings will have a consolidated density of about 1.9 t/m3
and will thus be filling the facility at a rate of about
1,850 m3/day.
Once modification activities commence, sufficient water will remain in the structure to provide a 0.5-1 metre
water buffer and to provide a suction head for the reclaim pumps.
The tailings will be placed to an elevation of 130.5 mOD and it is expected that the tailings will beach at a
slope gradient of 0.4% towards the pumps.
The reclaim pumps on the new facility will immediately return tailings water to the reclaim pumps on the main
TMF. The pumps will be located in the southern corner of the facility. The main TMF will provide the
required retention time for the settling of any dirty tailings water pumped from the adjoining new TMF cell
following modification of use.
Sufficient water storage will also be retained in the main TMF to allow for flexibility in the operation and
management of surface waters.
2.6.2 Closure Phase
Closures activities are described in detail in Chapter 12.0 of the EIS.
2.7 Surface Water Management
2.7.1 Operational phase
During operation as a tailings facility, the structure will retain an ancillary use for surface water management
as described above. When required, the existing TMF will also facilitate the storage of ‘dirty’ tailings water in
combination with the new facility, which would otherwise have been managed if the structure had remained
as a water impoundment facility only. This type of perimeter rockfill dam, which has no external catchment
area, is operated without spillways. There is always adequate control on the tailings water level which can
be achieved by adjusting the recharge and discharges into the facility.
As the new structure begins to fill progressively following permission for modification activities, any water
freeboard up to 131.5 mOD will continue to act as additional water storage capacity in combination with the
existing TMF, thus managing waters in accordance with IPPCL P0088-03.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 10
2.7.2 Closure phase (Spillway)
Following capping, the surface water runoff will subsequently be channelled via a spillway to the permitted
wetland system that currently forms part of the CRAMP (Chapters 6.0 Water and 12.0 Closure).
The spillway will be constructed prior to closure of the facility when filled with tailings to 130.5 mOD (Figures
2.4 and 2.8). The level of the tailings water in the TMF will be dependent on the discharge from the mill into
the facility, water reclaim from the facility and the effective rainfall. Both the discharge and reclaim are
controlled by the mill operators and can be adjusted at short notice. The probable maximum precipitation
(PMP) for this area will be of the order of 250 mm over 24 hours which is readily retained within the
freeboard of the facility.
The spillway will be located and designed in detail after filling of the existing TMF is completed and agreed
with the regulatory authorities, in accordance with the CRAMP (Figure 2.8). Further details are provided in
the Water Chapter of this EIS (Chapter 6.0).
2.7.3 Groundwater monitoring
The monitoring system for the new TMF following modification is presented in Figures 2.9 and 2.10 and
indicates monitoring wells at c. 250 m spacing around the new cell and one piezometer in each of the new
dam wall sections.
The water level and quality of the groundwater in and beneath the dam wall of the new TMF cell will be
monitored from the piezometers installed immediately above and below the base of the dam and the
monitoring wells installed into the bedrock at the downstream dam toe. The construction of the piezometers
and wells are shown in Figures 2.9 and 2.10.
The water level and water quality sampling will be undertaken in accordance with the IPPC Reg. No. P0088-
03.
2.8 Closure
The new cell will be capped with approximately 700 mm of Type B material as constructed on the existing
TMF together with 300 mm of growing material consisting of 50% peat and 50% soil. The procedure would
be the same as currently undertaken on the existing facility.
The key to long term closure will be the requirement to maintain the cap in a saturated condition. The cap
will be initially placed on top of the tailings, expected to finish at 130.5 mOD and the top of the growing
medium is at approximately 131.5 mOD, at the crest elevation. If the mine closes before the tailings reach
130.5 mOD, then the cap will be lower than the crest accordingly.
The spillway arrangements will be engineered once the facility is approaching closure. Further details on
closure are provided in Chapter 12.0 (Closure). Figure 2.8 provides further details on the closure plan.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2 11
2.9 References
Planning Study, Tailings Management Facility, Technical Report. December 1995.
Golder Associates (UK) Ltd. Report No. 96512126 Lisheen TMF Detailed Design. November 1997.
Golder Associates (UK) Ltd. Report No. 01121529. TMF Stage 2 Detailed Design Lisheen Mining Limited.
December 2001.
Golder Associates (UK) Ltd. Report No. 10514150188. TMF Stage 2 Detailed Design of the Stage 2 Raise.
April 2011.
Proposed Construction Quality Assurance and Control Plan for the TMF Construction at Lisheen Mine.
March 1997.
Leakage through Liners Constructed with Geomembranes. Part II. Composite Liners. J. P. Giroud, et al.,
Geotextiles and Geomembranes, 8(4) pp71-111 1989.
Rate of Leakage through a Composite Liner due to Geomembrane Defects. J. P. Giroud, et al., Geotextiles
and Geomembranes, 11(1) pp1-28 1992.
CHAPTER 2.0 DESCRIPTION OF THE DEVELOPMENT
August 2013 Report No. 11507150226.R01.2.A2
FIGURES
MOYNE VILLAGE
COOLEENY FARM
TAILINGS
MANAGEMENT
FACILITY
PERMITTED WATER
IMPOUNDMENT
FACILITY
SITE NOTICE
SITE
NOTICE
SITE
NOTICE
SITE
NOTICE
Client:
Project:
Location:
Title:
1:37,500 A4
Scale
11.5071.5.0226
Fig 2.1
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
July '13ATo Lisheen Mine
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SITE LOCATION MAP
(Regional)
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-01revB
NOTE:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
Lisheen Milling Ltd.
Planning Application
Aug. '13
BTo North Tipperary County Council
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL
OF APPLICANT
1:12,500
500 1,000 1,500m0
1:37,500
TAILINGS
MANAGEMENT
FACILITY
PERMITTED WATER
IMPOUNDMENT
FACILITY
Mine Site Boundary
VR 8-Intake & alimak raise
Turbine FND base
3
3
m
9
7
m
8
1
m
SITE
NOTICE
Client:
Project:
Location:
Title:
1:3,750 A4
Scale
11.5071.5.0226
Fig 2.2
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SITE LOCATION MAP
(Local)
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-02revB
Lisheen Milling Ltd.
Planning Application
NOTE:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL
OF APPLICANT
1:1,250
50 100 150m0
1:3,750
TAILINGS
MANAGEMENT
FACILITY
B B'
PERMITTED WATER
IMPOUNDMENT
FACILITY
VR 8-Intake & alimak raise
Turbine FND base
1
2
0
120
120
1
2
0
1
2
0
1
2
0
1
2
1
121
1
2
1
1
2
1
1
2
1
1
2
2
122
1
2
2
1
2
2
122
1
2
2
122
1
2
2
1
2
2
1
2
3
1
2
3
1
2
3
1
2
3
123
1
2
3
123
123
123
123
1
2
3
1
2
4
1
2
4
124
124
1
2
4
124
1
2
4
1
2
4
124
1
2
4
1
2
4
1
2
4
124
1
2
4
124
1
2
4
1
2
4
1
2
5
1
2
5
125
1
2
5
1
2
5
1
2
5
125
125
1
2
5
1
2
5
1
2
5
1
2
5
1
2
5
1
2
5
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
126
1
2
6
126
126
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
127
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
127
1
2
7
1
2
7
1
2
8
1
2
8
1
2
8
1
2
8
1
2
8
1
2
8
128
1
2
8
128
1
2
8
1
2
8
128
1
2
8
1
2
8
1
2
8
1
2
8
128
1
2
9
1
2
9
129
1
2
9
1
2
9
1
2
9
129
1
2
9
129
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
3
0
1
3
0
1
3
0
130
1
3
0
1
3
0
1
3
0
130
1
3
0
130
1
3
0
1
3
0
1
3
0
1
3
0
1
3
0
130
1
3
0
1
3
0
1
3
0
1
3
1
131
131
1
3
1
1
3
1
1
3
1
1
3
1
131
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
131
1
3
1
1
3
1
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
1
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
134
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
4
1
3
2
1
3
3
1
3
5
1
3
2
1
3
5
1
3
3
1
3
4
1
3
6
1
3
6
1
2
7
1
2
8
1
2
9
1
2
9
130
131
1
3
2
128
1
2
2
1
2
3
1
2
4
1
2
5
1
2
6
1
2
7
1
2
8
1
2
9
1
3
0
1
3
1
121
122
123
124
125
126
127
128
129
130
1
2
2
1
2
9
126.0
Existing embankment crest
(Elevation 136.5)
Crest
(Elevation 131.5)
Service road
Ramp
Mine Site Boundary
Perimeter Interceptor Channel
Ramp
136.5
136.5
Crest
(Elevation 131.5)
1
3
2
1
3
0
1
3
4
3
3
m
9
7
m
8
1
m
Site
Notice
Approximate location of spillway
- subject to detailed design upon closure
Water Reclamation Pump & Pipework
from Permitted Water Impoundment
Facility connects to main TMF
Client:
Project:
Location:
Title:
1:3,000 A4
Scale
11.5071.5.0226
Fig 2.3
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SITE LAYOUT PLAN FOR PERMITTED
WATER IMPOUNDMENT FACILITY
Lisheen Milling Ltd.
Planning Application
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-03revB
NOTES:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
REFER TO FIG 2.5 FOR CROSS SECTION
DETAILS
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL OF APPLICANT
GROUND LEVEL CONTOUR
EXISTING WIND TURBINE
1:1,000
40 80 120m0
1:3,000
TAILINGS
MANAGEMENT
FACILITY
C C'
PERMITTED WATER
IMPOUNDMENT FACILITY
TO BE USED AS TAILINGS
STORAGE FACILITY
VR 8-Intake & alimak raise
Turbine FND base
1
2
0
120
120
1
2
0
1
2
0
1
2
0
1
2
1
121
1
2
1
1
2
1
1
2
1
1
2
2
122
1
2
2
1
2
2
122
1
2
2
122
1
2
2
1
2
2
1
2
3
1
2
3
1
2
3
1
2
3
123
1
2
3
123
123
123
123
1
2
3
1
2
4
1
2
4
124
124
1
2
4
124
1
2
4
1
2
4
124
1
2
4
1
2
4
1
2
4
124
1
2
4
124
1
2
4
1
2
4
1
2
5
1
2
5
125
1
2
5
1
2
5
1
2
5
125
125
1
2
5
1
2
5
1
2
5
1
2
5
1
2
5
1
2
5
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
126
1
2
6
126
126
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
6
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
127
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
1
2
7
127
1
2
7
1
2
7
1
2
8
1
2
8
1
2
8
1
2
8
1
2
8
1
2
8
128
1
2
8
128
1
2
8
1
2
8
128
1
2
8
1
2
8
1
2
8
1
2
8
128
1
2
9
1
2
9
129
1
2
9
1
2
9
1
2
9
129
1
2
9
129
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
2
9
1
3
0
1
3
0
1
3
0
130
1
3
0
1
3
0
1
3
0
130
1
3
0
130
1
3
0
1
3
0
1
3
0
1
3
0
1
3
0
130
1
3
0
1
3
0
1
3
0
1
3
1
131
131
1
3
1
1
3
1
1
3
1
1
3
1
131
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
1
3
1
131
1
3
1
1
3
1
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
1
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
134
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
4
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
5
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
6
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
7
1
3
4
1
3
2
1
3
3
1
3
5
1
3
2
1
3
5
1
3
3
1
3
4
1
3
6
1
3
6
1
2
7
1
2
8
1
2
9
1
2
9
130
131
1
3
2
128
1
2
2
1
2
3
1
2
4
1
2
5
1
2
6
1
2
7
1
2
8
1
2
9
1
3
0
1
3
1
121
122
123
124
125
126
127
128
129
130
1
2
2
1
2
9
126.0
Existing embankment crest
(Elevation 136.5)
Crest Elevation 131.5 with
final tailings level 130.5
Service road
Ramp
Mine Site Boundary
Ramp
136.5
1
3
2
1
3
0
1
3
4
Perimeter Interceptor Channel
Tailings Discharge points
Tailings Discharge Pipeline
3
3
m
9
7
m
8
1
m
Site
Notice
Crest Elevation 131.5 with
final tailings level 130.5
Approximate location of spillway
- subject to detailed design upon closure
Tailings Discharge Pipeline connects
to main TMF Discharge Pipeline
136.5
Client:
Project:
Location:
Title:
1:3,000 A4
Scale
11.5071.5.0226
Fig 2.4
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SITE LAYOUT PLAN FOR
MODIFICATION TO STORE TAILINGS
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-04revB
Lisheen Milling Ltd.
Planning Application
NOTES:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
REFER TO FIG 2.6 FOR CROSS SECTION
DETAILS
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL OF APPLICANT
GROUND LEVEL CONTOUR
EXISTING WIND TURBINE
1:1,000
40 80 120m0
1:3,000
Datum 100.00mAOD
Datum 180.00mAOD
Datum 100.00mAOD
Datum 180.00mAOD
Datum 140.00mAOD Datum 140.00mAOD
Section A-A'
0 50 100 150 200 250 300 350
North
400m
South
Datum 100.00mAOD
Datum 180.00mAOD
Datum 100.00mAOD
Datum 180.00mAOD
Datum 140.00mAOD Datum 140.00mAOD
Section B-B'
0 50 100 150 200 250 300 350
West
400m
East
450
131.50m131.50m
136.50m
130.50m (Water Level)
136.50m
131.50m131.50m
130.50m (Water Level)
Client:
Project:
Location:
Title:
1:3,000 A4
Scale
11.5071.5.0226
Fig 2.5
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SECTIONS A-A' & B-B'
(See Fig 2.3 for section locations)
Lisheen Milling Ltd.
Planning Application
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA05 & PA06revB
NOTES:
DIMENSIONS ARE IN METRES.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
1:1,000
40 80 120m0
1:3,000
Datum 100.00mAOD
Datum 180.00mAOD
Datum 100.00mAOD
Datum 180.00mAOD
Datum 140.00mAOD Datum 140.00mAOD
Section C-C'
0 50 100 150 200 250 300 350
North
400m
South
Datum 100.00mAOD
Datum 180.00mAOD
Datum 100.00mAOD
Datum 180.00mAOD
Datum 140.00mAOD Datum 140.00mAOD
Section D-D'
0 50 100 150 200 250 300 350
West
400m
East
450
131.50m 131.50m
136.50m
136.50m
131.50m131.50m
130.50m (Tailings Level)
130.50m (Tailings Level)
Client:
Project:
Location:
Title:
1:3,000 A4
Scale
11.5071.5.0226
Fig 2.6
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
SECTIONS C-C' & D-D'
(See Fig 2.4 for section locations)
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA05 & PA06revB
NOTES:
DIMENSIONS ARE IN METRES.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
Lisheen Milling Ltd.
Planning Application
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
1:1,000
40 80 120m0
1:3,000
Downstream Upstream
Downstream Upstream
EXISTING EMBANKMENT
TYPICAL SECTION OF PERMITTED WATER IMPOUNDMENT FACILITY EMBANKMENT
DOWNSTREAM TOE DETAIL
DETAIL 1
DETAIL 2
TYPICAL CONSTRUCTION PLATFORM SECTION
NTS
11.5071.5.0226
Fig 2.7
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
CW
CW
POB
TYPICAL SECTIONS & DETAILS OF
PERMITTED WATER IMPOUNDMENT FACILITY
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-07revB
Lisheen Milling Ltd.
Planning Application
NOTES:
DIMENSIONS ARE IN MILLIMETRES.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
TYPE B MATERIAL:
BULK OF EMBANKMENTS FOR THE WATER IMPOUNDMENT FACILITY
ARE EITHER LIMESTONE OR SHALEY LIMESTONE WITH A
MAXIMUM PARTICLE SIZE OF 300mm
TYPE D MATERIAL:
ROAD SURFACING MATERIAL c.200mm THICK PLACED AT THE TOP OF
THE DAM CREST AND THE LOWER PERIMETER ROAD, PASSING A SIEVE
SIZE OF 37.5mm
TYPE C MATERIAL:
SCREENED ROCKFILL MATERIAL WITH MAXIMUM PARTICLE SIZE OF 20mm
(PROVIDES PROTECTION FOR THE LINING SYSTEM WITHIN THE
WATER IMPOUNDMENT FACILITY)
TYPICAL SECTION THROUGH EXISTING TMF EMBANKMENT SHOWING
TIE-IN WITH PERMITTED WATER IMPOUNDMENT FACILITY
July '13
ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
Spillway
Open channel with
gravel base
Outflow
Open channel
with gravel base
Open channel
with gravel base
Permitted wetland system
under CRAMP (Final
design to be agreed with
relevant authorities)
Discharge
Small pool
Willow edge linking
wetland
Surface
drainage
channel
Surface
drainage
channel
Surface
drainage
channel
Surface
drainage
pond
Phase 3
(~6ha)
Phase 2 North
(~24ha)
Phase 1
(~9ha)
Phase 2 South
(~33ha)
Outflow
Spillway
Spillway
Restoration Surface (conceptual)
Final details to be included in CRAMP
Restoration Surface (conceptual)
Final details to be included in CRAMP
Client:
Project:
Location:
Title:
1:9,000 A4
Scale
11.5071.5.0226
Fig 2.8
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
FINAL CLOSURE PLAN
(Conceptual)
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-08revB
Lisheen Milling Ltd.
Planning Application
Works formation
level
Rock fill
Growth media
Geotextile
Tailings
Finished level
Proposed TMF Capping Detail
(Schematic only)
Agricultural grass
NOTE:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
July '13ATo Lisheen Mine
Aug. '13
BTo North Tipperary County Council
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL
OF APPLICANT
1:6,000
0 120 240 360m
VR 8-Intake & alimak raise
Turbine FND base
126.0
Existing embankment crest
(Elevation 136.5)
Crest
(Elevation 131.5)
Service road
Ramp
Mine Site Boundary
Perimeter Interceptor Channel
Ramp
136.5
136.5
Crest
(Elevation 131.5)
TAILINGS
MANAGEMENT
FACILITY
PERMITTED WATER
IMPOUNDMENT FACILITY
TO BE USED AS TAILINGS
STORAGE FACILITY
SITE
NOTICE
9
7
m
8
1
m
3
3
m
TYPICAL SECTION SHOWING INSTRUMENTATION INSTALLATION DETAILS
Downstream
500
GLACIAL
TILL
2000
4000
Upstream
GLACIAL
TILL
6000
Client:
Project:
Location:
Title:
1:2,500 A3 or as shown
Scale
11.5071.5.0226
Fig 2.9
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
Issue to
Date
DrawingProject number
File Location
Reviewed by
Checked by
Created By
Version
CW
CW
POB
PLAN & SECTION SHOWING
INSTRUMENTATION
Lisheen Milling Ltd.
Planning Application
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-09revB
LEGEND:
APPLICATION SITE BOUNDARY
LANDS UNDER CONTROL OF
APPLICANT
EXISTING WIND TURBINE
PIEZOMETER
MONITORING WELL
1:2,500
0 50 100 150m
NOTES:
DIMENSIONS ARE IN MILLIMETRES.
LEVELS ARE IN METRES RELATIVE TO O.S.
DATUM MALIN HEAD.
Killoran, Thurles, Co Tipperary.
NOTE:
COORDINATES ARE IN METRES RELATIVE TO
IRISH NATIONAL GRID.
O.S. MAPS - TIPPERARY SHEETS 30 & 36 (parts)
July '13ATo North Tipperary County Council
July '13BTo North Tipperary County Council
MONITORING WELL PEIZOMETER
11.5071.5.0226
ORDNANCE SURVEY IRELAND LICENCE NUMBER
AR0056013
INSTRUMENTATION DETAILS
Lisheen Milling Ltd.
Planning Application
Killoran, Thurles, Co Tipperary.
P:\PROJECTS\MINING\LISHEEN\13 5071 5 0032 - Wetland
Construction....\Graphics\8. Planning\01\PA-10revB
NOTE:
DIMENSIONS ARE IN MILLIMETRES.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2
Table of Contents
3.0 HUMAN BEINGS ....................................................................................................................................................... 1
3.1 Introduction ................................................................................................................................................... 1
3.2 Methodology ................................................................................................................................................. 1
3.3 Existing Environment .................................................................................................................................... 1
3.3.1 Land-use and social consideration .......................................................................................................... 1
3.3.2 Populations ............................................................................................................................................. 2
3.3.3 Traffic ...................................................................................................................................................... 3
3.3.4 Economic activity .................................................................................................................................... 3
3.3.5 Tourism and recreation ........................................................................................................................... 4
3.3.6 Health and safety .................................................................................................................................... 5
3.3.7 Subsidence ............................................................................................................................................. 5
3.4 Assessment .................................................................................................................................................. 6
3.4.1 Land-use and social considerations ........................................................................................................ 6
3.4.2 Economic activity .................................................................................................................................... 6
3.4.3 Tourism and recreation ........................................................................................................................... 7
3.4.4 Traffic ...................................................................................................................................................... 7
3.4.5 Subsidence ............................................................................................................................................. 7
3.5 Mitigation ...................................................................................................................................................... 8
3.6 Residual / Likely Significant Effects .............................................................................................................. 8
3.7 References ................................................................................................................................................... 9
TABLES
Table 3.1: Population Statistics for Moyne DED .................................................................................................................. 3
Table 3.2 Previous Planning Applications for Lisheen Mine with an EIS ............................................................................. 3
Table 3.3: Employment Structure Classified by Broad Occupational Group for the Moyne DED ........................................ 4
Table 3.4: Journey Times .................................................................................................................................................... 4
Table 3.5: Details of local suppliers benefiting from Lisheen Mine continued operations .................................................... 6
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 1
3.0 HUMAN BEINGS
3.1 Introduction
This chapter of the EIS describes the human environment and identifies and assesses any impacts from the
proposed modification from a permitted water impoundment facility to store tailings at the Application Site.
The human environment is discussed under the following headings:
Land-use and social considerations;
Populations;
Economic Activity;
Tourism and Recreation;
Traffic; and
Health and Safety.
Interactions between humans and other facets of the environment are discussed under relevant sections of
this EIS, including:
Air (Chapter 8.0)
Noise (Chapter 9.0)
Landscape (Chapter 10.0)
3.2 Methodology
Information for the assessment of potential impacts on human beings was obtained by means of a desk-
based review, and included the following sources:
Census Returns (Central Statistics Office (CSO) 1996, 2002, 2006 and 2011 Census);
North Tipperary Development Plan (2010-2016);
Kilkenny County Council Development Plan (2008 – 2014); and
Aerial and ordnance survey maps of the area.
In addition, the following also informed the preparation of this Chapter:
Field surveys of the Application Site; and
Site visits and drive by surveys of residences and local facilities.
The existing/past environment is described. Any potential significant impacts from the proposed tailings
storage activities at the site are identified and assessed, and where possible mitigation measures are
proposed.
3.3 Existing Environment
3.3.1 Land-use and social consideration
The Application Site comprises c. 9.0 ha. and is located in the town land of Killoran, Moyne, County
Tipperary. The location of the Application Site in a regional context is depicted in Figure 1.1. The village of
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 2
Killoran is located approximately 1.5 km west of the Site and is accessed via the Ballyduff Road. The
Application Site comprises land associated with mining activities and this EIS has been prepared to support
an application for planning permission to modify the use of a permitted water impoundment facility to store
tailings at the Lisheen Mine site.
The land surrounding the Application Site is currently an active mine site with a TMF to the south and mine
surface operations to the northwest and west. A number of wind turbines are also located within lands under
the control of the Applicant, owned and operated by Bord Gáis. To the north there is Templetouhy bog
which is operated by Bord Na Móna and local turf/peat operators, and to the east there is agricultural use
which is mainly grazed pastureland consisting of several intensively managed agricultural fields bordered by
hedgerows.
The Application Site is within Moyne Electoral Division at the border with County Kilkenny to the east. The
neighbouring Electoral Division in Kilkenny is Baunmore. The nearest residential property to the site is
located in Baunmore Electoral Division along the R502 approximately 650 m to the northeast. There are
residential properties in the vicinity of the mine site, primarily concentrated in ribbon form development on
the Cooleeny road where access is gained to the Mine Site as depicted in Figure 2.1 and Figure 2.2. These
properties are located at a distance of 1,200 m to 1,700 m from the Application Site. The Application Site
can only be accessed via private roads within the Mine Site.
While there are a number of agricultural uses for land in the vicinity of the Application Site, it is understood
that water is sourced via the Moyne Group Water Scheme which has been operating to compensate for cone
of drawdown associated with Mine operations. As such it is considered unlikely that local land use will be
affected by the modification of the Application Site from a permitted water impoundment facility to a storage
facility for tailings, in particular as the TMF structure will be fully lined and capped in accordance with best
international practice (Chapter 2.0, Project Description).
There are no proposed National Heritage Areas (pNHA) located within 5 km of the Application Site. The
following conservation sites have been noted in the wider area:
Galmoy Fen, pNHA/SAC, 9.6 km northeast;
The Loughans, pNHA/SAC, 10 km east, southeast;
Spahill and Clonmantagh Hill, pNHA, SAC, 11 km east;
Cabragh Wetlands, pNHA, 11 km southwest;
Kilcooley Abbey Lake, pNHA, 11.5 km southeast;
Templemore Wood pNHA, 12 km, northwest;
Cullahill Mountain, pNHA, SAC, 13 km, northeast; and
Lower River Suir SAC, c. 13 km southwest.
Further details regarding these ecological designations are included in Chapter 4.0 of this EIS. A Natura
Impact Assessment also accompanies this Application / EIS submission.
3.3.2 Populations
The census reports for 1996, 2002, 2006 and 2011 produced by the Central Statistics Office details
population figures in terms of district electoral divisions and their respective populations. The Application
Site is located within the District Electoral Division (DED) of Moyne, which includes the following town lands:
Moyne, Lisheen, Lisdonowley, Moynetemple, Moyneard, Shanballyduff, Cooleeny, Killoran, Deryville,
Bernalisheen, Boolaree, and Ballyerk.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 3
Population statistics for Moyne are depicted in Table 3.1. The figures indicate Moyne DED has seen an
increase in population in the last ten years. In 2011 the Moyne DED had a population of 532 persons, an
increase of 7.1% on the 2006 population.
Table 3.1: Population Statistics for Moyne DED
No. Persons Actual Increase Percentage Increase
1996 492 -
2002 484 -8 -1.6
2006 494 10 2.0
2011 532 38 7.1
3.3.3 Traffic
The proposed development, which is the subject of this EIS, is to modify the use of a permitted water
impoundment facility to store mine tailings. It is proposed to place tailings in the impoundment over a c. 12
month period. All tailings will be transported to the site via pipeline from the concentrator located in the main
mine plant facility, using existing surface mine infrastructure. As such, no additional traffic will be generated
as a result of this ‘modification’ application to place tailings in the permitted water impoundment facility
during the operation phase. In addition, once modification of the permitted water impoundment facility
occurs, no additional traffic will result during management of surface water at the site.
In addition, all employee traffic on the public road network relating to the management of tailings at the
Application Site, and associated ancillary activities will remain unchanged from the current situation. The
traffic impact of the existing Lisheen Mine has been assessed under a number of previous applications as
outlined in Table 3.2 below.
Table 3.2 Previous Planning Applications for Lisheen Mine with an EIS
Planning Ref. No.
ABP Ref. No.
Date Description of Application EIS Prepared
17663 22.100093 1997 Parent application to development the Lisheen Mine.
Yes
4511667 22.212637 2007 Extension to existing mine and construction of 3 No. ventilation shafts.
Yes
12510034 n/a 2012
Develop the Derryville Island Ore Deposit underground workings as an extension to the existing Lisheen Mine and the construction of 1 No. ventilation shaft.
Yes
Based on the above, a Traffic and Transport Assessment is screened out of this Application/Environmental
Impact Assessment (EIA) process.
3.3.4 Economic activity
The Village of Moyne, c. 3.7 km to the west is the nearest centre of economic activity to the Application Site,
with Lisheen, Templetouhy and other towns such as Urlingford, Templemore and Johnstown also acting as
employment centres within 5 km of the Site (Figure 1.1 for locations). Census 2011 statistics show that
23.6% of the workforce in the Moyne DED is employed in the Agriculture, Fishing and Forestry indicating
they may work locally. The next highest employment sector is Professional Services at 21.5% as shown in
Table 3.3. It is likely that the majority of these workers travel to population centres stated previously, or
Lisheen Mine. The next highest employment sector is Commerce and Trade at 19.7 %. Table 3.3 below
outlines the employment structure classified by broad occupational group for the Moyne DED as reported
from Census 2011.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 4
Table 3.3: Employment Structure Classified by Broad Occupational Group for the Moyne DED
Occupational Group No. of Persons Employed 2006
No. of Persons Employed 2011
% of Total 2006 % of Total 2011
Agricultural, Fishing and Forestry
50 55 20.7 23.61
Manufacturing Workers 29 5 12 2.15
Building and construction workers
15 40 6.2 17.17
Commerce and Trade 46 46 19 19.74
Public Administration 18 7 7.44 3.00
Transport and Communications
17 7 7.02 3.00
Professional services 38 50 15.7 21.46
Others 29 23 12 9.87
Total in Labour Force 242 233 100 100
Table 3.4 below outlines the time travelled by the population of Moyne to school, college or work, obtained
from the Central Statistics Office from Census 2011.
Table 3.4: Journey Times
Population aged five years and over by journey time to work, school or college
Under 15 minutes 132
1/4 hour - under 1/2 hour 103
1/2 hour - under 3/4 hour 26
3/4 hour - under 1 hour 15
1 hour - under 1 1/2 hours 10
1 1/2 hours and over 6
Not stated 28
As highlighted previously, the main economic activity in the vicinity of the Application Site is located in Moyne
c. 3.7 km west of the Site. There are several small businesses in the village including public houses, shops,
and a garage. In the immediate vicinity of the village are cheese manufacturers, building contractors,
transport and haulage business, agriculture and construction plant hire and sales, quarrying (ready mix
concrete) and carpet cleaning businesses.
The Application Site forms part of the larger Lisheen Site and will be managed by full time employees of the
Mine. No additional staff are proposed to be employed as a result of this Application. In addition, the end of
life of mine remains on schedule to close by Quarter 1 2015 which is the current projection.
3.3.5 Tourism and recreation
As outlined in Section 6 of the North Tipperary County Development Plan 2010 – 2016 tourism in North
Tipperary generated only 42,000 visitors in 2000 which increased to 68,000 by 2006. However this equates
to only 5.4% of people visiting the broader Shannon Region of North Tipperary, Clare, Limerick and South
Offaly.
The North Tipperary County Development Plan indicates that the council will support the development of
eco-tourism and other tourist activities that promote the natural and cultural assets of the county. These
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 5
include and are not limited to walking, cycling, nature trails, green, eco, geo and agri-tourism farmhouse
accommodation, open farms, water sports and archaeological guided walks. The specific objectives
frequently focus on regions in the north and eastern parts of North Tipperary such as Nenagh, Lough Derg,
Roscrea and Templemore. There are no major tourist facilities within a 10 km radius of the Application Site.
However it is noted that some activities such as cycling, walking and horse riding may occur within a smaller
radius. The Application Site itself is not accessible and is surrounded on all sides by private property e.g.
Lisheen Mine, Agricultural land, Bord Na Móna Operations.
The Kilkenny County Development Plan 2008 to 2014 indicates that Tourism is a dominant industry in the
county. However, there are no major tourist attractions within the Baunmore DED. In addition the 2011
census indicates the population was generally employed in areas of skilled trades and professional
occupations. Four people indicated they were employed in the area of caring leisure and other services.
Tourist and Recreational Amenities located in the wider area include:
Templemore, Thurles and Rathdowney Golf Clubs;
Lough Derg and associated water activities;
Cycling, walking and equestrian facilities;
Heritage areas including:
Roscrea Castle and Fancroft Mill and Gardens, 20 km to the north;
Caragh Wetland Trust, Thurles, 15 km south west; and
Farney Castle, Holycross, 20 km
The nearest population centres provide a variety of restaurants, pubs, hotels and B&Bs.
3.3.6 Health and safety
The safety of the Applicant’s employees, contractors and the communities in which it operates is an integral
part of their business. Lisheen Mine’s goal is zero harm. Decision making and thinking for safety is directed
by the Lisheen Safety Policy which sets the minimum safety standards for The Lisheen Mine as an
organisation.
Lisheen Mine seeks to create a mind-set and an environment where people believe it is possible to work
injury free, regardless of what role they undertake.
The Applicant’s approach to safety is incorporated in their policy which states that they will:
Hold all managers and supervisors accountable for safety, occupational health and environmental
issues; and
Prevent or control risks, personal injury and illness, property and environmental damage, by
implementing The Lisheen Mine vision and principles of zero harm as well as through appropriate
planning, design, investment, management and workplace procedures.
Across the organisation Lisheen Mine manages safety through their risk-based safety management system
and procedures. The line managers are accountable for the implementation of these procedures and are
responsible for ensuring that support systems are in place.
3.3.7 Subsidence
At the outset of the Lisheen Mine project, in the early 1990’s, the risk of subsidence or ground settlement
was recognised. The two mechanisms that may give rise to settlement are the mining process itself,
whereby voids are excavated underground, and dewatering. Section 3.4.5 provides an assessment of the
potential for subsidence effects as a result of the proposed modification activities.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 6
3.4 Assessment
3.4.1 Land-use and social considerations
Mining and related surface ancillary activities have been undertaken at the property since the late 1990’s,
and there will be no change to the land use at this location as a result of the proposed modification of the
permitted water impoundment facility to store tailings at the Application Site. With respect to social
considerations, the modification of the permitted water impoundment facility will result in a positive social
outcome, given that the mine will operate for an additional 12 months, which results in extended employment
at the mine facility. It is noted that the parent permission is for 30 years (c. 2027).
In addition, and as outlined in Chapter 2.0, the modification application will facilitate progressive capping
works on the main TMF, which again result in a positive outcome from the social viewpoint. This positive
outcome has been communicated to Lisheen Mine during recent public forum meetings.
3.4.2 Economic activity
As a result of this proposed development, there will be a direct positive knock on effect to the wider economy
in the vicinity of Lisheen Mine. As this proposal will result in an extended c. 12 months of operation,
Table 3.5 provides details of the following local businesses that will benefit.
Table 3.5: Details of local suppliers benefiting from Lisheen Mine continued operations
Supplier Name Goods Service Description
SANDVIK MINING CONSTRUCTION Trackless Mining Equipment
NOEL O'BRIEN CEMENT Bulk Materials
MAHER QUARRIES Bulk Materials
ATLAS COPCO CONSTRUCTION MINING Trackless Mining Equipment
CLOGRENNANE LIME LTD. Process Chemicals, Industrial Gases
LYONS TYRES & BATTERIES Tyres & Tubes
VALE OIL COMPANY LTD Fuel and Lubes
P O DWYER ELECTRICAL SERVICES LT Temporary Personnel Services
KILKENNY VAN & TRUCK LTD Mining Support Vehicles
E.BUTTIMER & CO LTD Temporary Personnel Services
TEMPLEMORE MOTOR WORKS Mining Support Vehicles
JOHN BOURKE ENGINEERING LTD. Industrial Machinery & Supplies
HANLEY CONTROLS CLONMEL LTD Electronic Components & Supplies
GLENNON PLANT HIRE LIMITED Site Services
AYLWARD HEAVY HAULAGE LTD Temporary Personnel Services
GLEESON STEEL ENG LTD Fabricated Steel/Plate Work
ALPHA DRIVES LTD Industrial Pumps & Compressors
GMC CLEANERS Industrial Cleaning Services
SISTER ITA LTD T/A DORAN OIL Fuel and Lubes
LIAM YOUNG PLANT SALES LTD Industrial Machinery & Supplies
STAKELUMS HARDWARE LTD Industrial Machinery & Supplies
TEMPLETUOHY MEDICAL CENTRE Health Services
M WALSH HIRE LIMITED Industrial Machinery & Supplies
IMTECH SUIR ENGINEERING Temporary Personnel Services
AIR-IMPACT LTD PPE
E K FABRICATIONS Temporary Personnel Services
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 7
Supplier Name Goods Service Description
J. L. BRADSHAW & CO. LTD. Industrial Machinery & Supplies
ELECTRICAL GENERATOR & PUMP SERV Electronic Equipment & Supplies
BLS BULK LIQUID STORAGE CORK Transport & Logistics
KILKENNY WELDING SUPPLIES LTD Industrial Machinery & Supplies
CAFE MHR ltd Mitchel House Corporate
G4S SECURE SOLUTIONS LTD Security services
JOHN.J.RONAYNE LTD Industrial Machinery & Supplies
SKYLINE SCAFFOLDING LTD Temporary Personnel Services
SUIRWAY AUTOMATION Industrial Machinery & Supplies
Approximately 400 employees will maintain employment for an additional 12 months, resulting in continued
significant contributions to the public exchequer through tax and universal social payments. In addition,
royalties of 3.5% of revenues will also be contributed to the Dept. of Communications, Energy and Natural
Resources.
3.4.3 Tourism and recreation
Given that any existing tourism/recreation businesses in the vicinity of the Site have developed since
commencement of mining activities in the mid 1990’s, it is unlikely that the proposed modification of the
permitted water impoundment will impact on the tourist potential of the local area. Local roads are
considered an amenity to residents in the vicinity of the Site. Existing traffic volumes on local roads will not
increase as a result of this development as all tailings will be transported to the Application Site via pipeline,
and therefore, it is considered the amenity value of the local road network will not been affected by proposed
use. In addition once modification of the permitted water impoundment facility occurs, no additional traffic
will result during management of surface water at the site.
Local residents or other receptors are not likely to observe any alterations to the facility as the mine tailings
will be placed within the permitted water impoundment structure (Chapter 10.0, Landscape). In summary,
the proposed modification of the permitted water impoundment facility to store tailings is not considered likely
to impact on tourism or recreational potential.
3.4.4 Traffic
As highlighted in Section 3.3.3 above, the proposed modification activities will not give rise to any additional
traffic movements during the operation phase, as all tailings will be pumped via pipeline to the permitted
water impoundment facility/new TMF cell. Ancillary traffic relating to closure activities will not impact the
public road network. Therefore no impacts from traffic activities will occur. A Traffic and Transport
Assessment was screened out for this reason.
3.4.5 Subsidence
The risk of settlement due to the mining process at Lisheen Mine is mitigated by the ongoing placement of
backfill (a mixture of cemented tailings) into selected voids underground to provide support. A series of
monitoring stations has been established and maintained, on surface, over the underground workings in
order to ascertain what degree, if any, of settlement has occurred. Measurements from these monitoring
stations are taken on a regular basis. While measurements do indicate that some settlement has occurred, it
is within the range that was predicted at the time of the original mine planning application.
The vast majority of mining at Lisheen is complete and as such the extent of void space will not increase
significantly during the remaining months of mining (c. 20 months). As part of the mine closure planning,
particular attention is placed on backfilling at this time to ensure adequate underground support is in place as
the mine is essentially in ‘retreat mining’, moving from the extremities back towards the centre of the mine.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 8
The water table at Lisheen Mine was lowered over a period of time from 1998. Other than some seasonal
variation, the footprint affected by dewatering has been essentially at steady state for over ten years. In
those ten years there has been no settlement attributed to dewatering from Lisheen Mine. There was a
slight increase in catchment and the dewatering footprint associated with extension into the Bog Zone ore
body and the Derryville Island ore body, but again, there has been no settlement attributed to mining
activities as a result. At this time there are no other new ore bodies into which Lisheen is planning to mine
and as such the dewatering footprint is expected to remain static.
Having regard to the above, it is considered that the additional mining (c. 12 months) that will be facilitated
by the proposed modification of the permitted water management facility for use for tailings storage activities,
will not have any significant impacts on ground subsidence. In any event, the existing monitoring
programme will continue for the remaining period of mining operations.
3.5 Mitigation
Given the Site will operate for an additional 12 months as a result of this application, this will allow Lisheen
Mine some additional time to prepare for mine closure. As with any mine closure, there will be negative
impacts on the socio-economic environment as production ceases. Whilst this application is concerned with
keeping the facility open for an extended period, the following activities are being undertaken by Lisheen
Mine in the run up to closure (which is supported by this Application), to mitigate against such negative
impacts of the overall facility closure:
Discussions with industrial operators to re-use the plant footprint, surface infrastructure and workforce;
Capping activities on the main TMF;
Fisheries / hatchery operations; and
Playing / leisure facilities post closure.
3.6 Residual / Likely Significant Effects
Potential/residual emissions arising from the placement of tailings in the permitted water impoundment cell,
relating to dust, water and noise, are dealt with in the relevant chapters of the EIS. It is notable that the
IPPC Licence Reg. No. P0088-03 and associated emission limit values will be adhered to for the duration of
tailings placement and subsequent closure works, as proposed in this planning application and EIS.
CHAPTER 3.0 HUMAN BEINGS
August 2013 Report No. 11507150226.R02.3.A2 9
3.7 References
Central Statistics office - www.cso.ie
Kilkenny County Council Development Plan. 2008 - 2014 -
http://www.kilkennycoco.ie/eng/Services/Planning/Development_Plans_2008-2014/ - Accessed 17 May
2013.
North Tipperary Development Plan 2010 – 2016 -
http://www.tipperarynorth.ie/planning/plan_County_Development_Plan_2010_2016.html - Accessed 17 May
2013
Central Statistics Office. Census Returns 1996, 2002, 2006 and 2011 – http://www.cso.ie/en/census/ -
Accessed: 11 February 2013
National Roads Authority. 2007. Traffic and Transport Assessment Guidelines. National Roads Authority, St.
Martin’s House, Waterloo Road, Dublin 4.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 1
4.0 FLORA AND FAUNA
4.1 Introduction
The flora and fauna impact assessment describes the baseline ecology of the Site, an evaluation of the
ecological features of the Site and surrounding area and following on from this an impact assessment to
establish potential impacts of the proposed development on habitats, flora and fauna. This assessment was
conducted in accordance with ‘EPA Guidelines on the Information to be contained in Environmental Impact
Statements’ (EPA, 2002), ‘EPA Advice Notes on Current Practice’ (EPA, 2003), and with reference to the
‘Guidelines for Ecological Impact Assessment in the United Kingdom’ (IEEM, 2006, reviewed 2011).
A separate Natura Impact Statement (NIS) for Appropriate Assessment Stage 2 has been carried out for the
Lower River Suir SAC (Golder Report Ref: 13 5071 5 0046 R.2 V.0). The study area for this assessment
encompasses the permitted water impoundment facility, adjacent lands and the receiving waters of the
discharges associated with the proposed modification development.
There is a number of National and International nature conservation sites within a 15 km radius of Lisheen
Mine and these are detailed in Section 4.3 below and shown in Figure 4.1 at the end of the document.
4.2 Methodology
4.2.1 Desktop survey and consultations
A desktop review was conducted of available published and unpublished information, including existing
Lisheen reports together with informal consultation with Inland Fisheries. The National Parks and Wildlife
Service (NPWS) wish to comment when the application is submitted to the Development Applications Unit.
A review of data available on the NPWS http://www.npws.ie/en/ and National Biodiversity (NBDC)
http://maps.biodiversityireland.ie/ web-based databases was also carried out. The review aimed to identify
key sites, habitats and species that may be present in the study area, particularly those protected by
legislation.
4.2.2 Phase I habitat survey
A walkover survey of the Site and adjacent lands (Phase I Survey) was conducted on 19 April 2013 to record
the habitats of the Site and surrounding area, however it is not a suitable time of year to carry out a flora
survey. Given that the area was largely cutaway peat and peat stockpiles, the area is not considered to be
of importance for flora. The area is now under preparation for the construction of the permitted water
impoundment facility and the habitats surrounding this are described.
Ecological Survey methods were in general accordance with those outlined in the following documents;
Heritage Council (2011). Best Practice Guidance for Habitat Survey and Mapping;
Phase 1 Habitat Survey methodology (Joint Nature Conservation Committee (JNCC), 1990, revised
2003) and;
Ecological Surveying Techniques for Protected Flora and Fauna during the Planning of National Road
Schemes (NRA, 2009).
Aerial photographs and site maps assisted the habitat survey. Mammals and birds were surveyed based
upon sightings and signs of mammal activity during the habitat survey and also the identification of possible
suitable habitats.
Habitats have been named and described following Fossitt (2000), and are depicted in the attached Figure
4.2 (Habitat map, attached at end of document).
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 2
4.2.3 Breeding bird survey
This survey was carried out using a modified version of the Countryside Bird Survey. Surveys were timed to
coincide with the main period of activity of breeding birds in the study area. The survey took place between
07.00h and 13.00h on 19 April 2013.
All birds heard or seen within the Application Site and adjacent areas (100 m buffer) were recorded. The
position of the bird (seen or heard) relative to the observer was recorded, as was any specific activity such
as display or nesting behaviour. The habitats used by the birds were also noted.
Emphasis was placed on mapping the locations of birds exhibiting breeding behaviour, that is:
Birds observed displaying or singing;
Nests, eggs or young;
Adults repeatedly alarm call;
Birds are seen carrying food to nest or young;
Distraction displays are seen; and
Territorial disputes are seen.
Following completion of the survey, registrations were mapped showing the location and density of breeding
territories or breeding pairs estimated within the open areas.
Records of non-breeding species were also made; including flying birds (a note of the species, height and
direction was noted).
The mapped results of the visits were combined. The total number of pairs and their exact location (where
possible) was recorded for each field and on a 1:10,000 scale map of the study area.
4.2.4 Impact assessment methods
Habitats were assessed in accordance with the guidance contained in the document Guidelines for
Ecological Impact Assessment for the United Kingdom and Ireland (IEEM, 2006 - Draft Review 2011), with
reference to Guidelines for Assessment of Ecological Impacts of National Roads Schemes (NRA, 2009).
The evaluation, impact and significance criteria used in this Impact Assessment are given in Table 4.1
overleaf.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 3
Evaluation criteria
Table 4.1: Criteria for establishing receptor sensitivity/importance
Importance Ecological Valuation
International
Sites, habitats or species protected under international legislation e.g. Habitats and Species Directive. These include, amongst others: SAC’s, SPA’s, Ramsar Sites, Biosphere Reserves, including sites proposed for designation, plus undesignated sites that support populations of internationally important species.
National
Sites, habitats or species protected under national legislation e.g. Wildlife Act 1976 and amendments. Sites include designated and proposed NHAs, Statutory Nature Reserves, National Parks, plus areas supporting resident or regularly occurring populations of species of national importance (e.g. 1% national population) protected under the Wildlife Acts, and rare (Red Data List) species.
Regional Sites, habitats or species which may have regional importance, but which are not protected under legislation (although Local Plans may specifically identify them) e.g. viable areas or populations of Regional Biodiversity Action Plan habitats or species.
High Local/County
Areas supporting resident or regularly occurring populations of protected and red data listed-species of county importance (e.g. 1% of county population), Areas containing Annex I habitats not of international/national importance, County important populations of species of habitats identified in county plans, Areas of special amenity or subject to a Tree Preservation Order.
Moderate Local
Areas supporting resident or regularly occurring populations of protected and red data listed-species of local importance (e.g. 1% of local population), Undesignated sites or features which enhance or enrich the local area, Sites containing viable area or populations of local Biodiversity Plan habitats or species, local Red Data List species etc.
Low Local Undesignated sites or features, which enhance or enrich the wildlife resource at a Parish or neighbourhood level.
Significance Criteria
An impact’s significance is measured bearing in mind the site’s evaluation for nature conservation. An impact
of severe significance is one which is likely to cause a considerable drop in the biodiversity value of a site
that is extremely important for nature conservation. An impact of major significance will also impinge on an
important nature conservation site or species but the impact will be less marked. An impact of moderate
significance will cause a significant loss in biodiversity on a site but is unlikely to impinge on statutory sites or
species. A minor impact will have only a very limited impact on biodiversity whereas an impact that is termed
negligible/not significant is one that is most unlikely to impact in any way on biodiversity.
IEEM (2006, Draft Review 2011) define an ecologically significant impact as an impact (negative or positive)
on the integrity of a defined site or ecosystem and/or the conservation status of habitats or species within a
given geographic area.
The integrity of a site is the coherence of its ecological structure and function, across its whole area, which
enables it to sustain the habitat, complex of habitats and/or the levels of populations of the species for which
it was classified (IEEM, 2006, Draft Review 2011).
Best scientific professional judgement has been used in some cases, to assess the significance of predicted
effects. The significance criteria are expressed on a six point scale, including both adverse and beneficial
effects, as follows in Table 4.2.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 4
Table 4.2: Criteria for Assessing Significance of Predicted Impacts
Impact Level Description
Severe Impact
Ecological effects of a scale or magnitude which would result in permanent, total loss of an irreplaceable species or habitat of international or national importance (occasionally of local importance), or which would result in the substantial loss of a protected/rare habitat or a population of a protected/rare species. They represent key factors in the decision-making process. Typically, mitigation measures would be unlikely to remove such effects.
Major Impact
These effects are likely to relate to permanent impacts at a regional or local level, or temporary impacts at an international or national level, and could be potential concerns to the project depending upon the relative importance attached to the issue during the decision making process. The effects are likely to be large in scale or magnitude, and result in substantial medium term loss of protected/rare species or habitats. Mitigation and detailed design work are unlikely to entirely eliminate all ecological effects.
Moderate Impact
These effects are usually only at local or regional level, and may be short or medium term only, or temporary impacts on a small part of an international site. However, the cumulative effects of such issues may lead to an increase in the overall effect on ecological features. They represent issues where effects will be experienced, but mitigation measures and detailed design work may ameliorate/enhance some of the consequences upon affected interests, but some residual effects will still arise.
Minor Impact
These effects are likely to be local issues only; or small magnitude impacts at the regional and national level, they are usually temporary, and are unlikely to be of importance in the decision making process. However, they are of relevance in enhancing the subsequent design of the development and consideration of mitigation measures.
Not Significant / No Impact
No perceivable impacts on ecological features (habitat or species). Impacts may be beneath levels of perception, within normal bounds of variation, within the margin of forecasting error, or impacting on exceptionally poor baseline conditions.
Beneficial / Positive Impact
These effects are those, which through implementation, would be anticipated to benefit the ecology of the Site. They may advance the objectives of local, national or international species or habitats.
Impact Characteristics
Direct and Indirect Impacts - An impact can be caused either as a direct or as an indirect consequence of
a proposed development.
Magnitude - Magnitude measures the size of an impact, which is described as high, medium, low or very
low.
Extent - The area of which the impact occurs, where the receptor is a habitat, magnitude and extent may
become synonymous.
Level - An impact is assessed based on whether it is of international, national, regional or local importance
(Refer to Table 4.2). This has a direct bearing on its magnitude and significance.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 5
Duration - The time for which the impact is expected to last prior to recovery or replacement of the resource
or feature.
Short Term: The effects would be of short duration and would not last more than 2-5 years from the
commencement of development;
Medium Term: The effects would take 5-15 years to be mitigated; and
Long Term: The effects would be reasonably mitigated over a long period of time (15 years or more).
Reversibility – An irreversible / permanent impact is one from which recovery is not possible within a
reasonable timescale, while a reversible/temporary impact is one from which spontaneous recovery is
possible.
Likelihood
Near Certain: >95% chance of occurring as predicted;
Probable: 50-95% chance as occurring as predicted;
Unlikely: 5-50% chance as occurring as predicted; and
Extremely Unlikely: <5% chance as occurring as predicted.
4.3 Protected Sites
There are eight designated sites within a 15 km radius of the Site, these include five EU Natura 2000 sites
and eight nationally proposed Natural Heritage Areas. These are given in Table 4.3 and Figure 4.1.
Table 4.3: Designated nature conservation sites within a 15 km radius of the proposed Site
Site Name EU Natura 2000 site National Designation Site Code
Galmoy Fen SAC pNHA 001858
Culahill Mountain SAC pNHA 000831
Spahill and Clonmantagh Hill
SAC pNHA 000849
The Loughans SAC pNHA 000407
Lower River Suir SAC pNHA 002137
Kilcooley Abbey Lake pNHA 000958
Cabragh Wetlands pNHA 001934
Templemore Woods pNHA 000942
Cullahill Mountain SAC and Spahill / Clonmangagh Hill SAC are not considered further in this assessment as
the designated features of semi natural grasslands are not impacted by Lisheen Mine. Galmoy Fen SAC
and Loughlans SAC are also not considered further as although the fen and turlough are groundwater
dependent terrestrial habitats, they do not lie within the Lisheen Groundwater Body (GWB)
(www.wfdireland.ie).
With regard to the remaining national designations, Kilcooley Abbey Lake pNHA, and Templemore Woods
pNHA are not affected by Lisheen Mine and are not considered further.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 6
Lisheen mine discharges to both the Rossestown River and Drish River and these rivers occur within 15 km
upstream of the Lower River Suir SAC – an EU designated Natura 2000 site and also Cabragh Wetlands
pNHA.
Therefore, the Lower River Suir and Cabragh Wetlands pNHA, Rossestown River and the Drish River are
included in the Ecological Impact Assessment. A Natura Impact Statement has also been prepared for the
Lower River Suir SAC and accompanies the EIS.
4.4 Lower River Suir SAC and Cabragh Wetlands pNHA
The Lower River Suir SAC (Site code: 002137) and Cabragh Wetlands pNHA (Site code: 001934) are
located southwest of Lisheen c.13 km downstream of the Site.
The Lower Suir SAC consists of the freshwater stretches of the River Suir immediately south of Thurles,
the tidal stretches as far as the confluence with the Barrow/Nore immediately east of Cheekpoint in
Co. Waterford and many tributaries including the Clodiagh in Co. Waterford, the Lingaun, Anner, Nier, Tar,
Aherlow, Multeen and Clodiagh in Co. Tipperary.
A list of the features of interest of the Lower Suir SAC follows:
Features of Interest:
Freshwater pearl mussel (Margaritifera margaritifera) [1029];
White-clawed crayfish (Austropotamobius pallipes) [1092];
Sea lamprey (Petromyzon marinus) [1095];
Brook lamprey (Lampetra planeri) [1096];
River lamprey (Lampetra fluviatilis) [1099];
Allis shad (Alosa alosa) [1102];
Twaite shad (Alosa fallax fallax) [1103];
Salmon (Salmo salar) [1106];
Atlantic salt meadows (Glauco-Puccinellietalia maritimae) [1330];
Otter (Lutra lutra) [1355];
Mediterranean salt meadows (Juncetalia maritimi) [1410];
Water courses of plain to montane levels with the Ranunculion fluitantis and Callitricho-Batrachion
vegetation [3260];
Hydrophilous tall herb fringe communities of plains and of the montane to alpine levels [6430];
Old sessile oak woods with Ilex and Blechnum in British Isles [91A0;]
Alluvial forests with Alnus glutinosa and Fraxinus excelsior (Alno-Padion, Alnion incanae, Salicion
albae) [91E0]; and
Taxus baccata woods of the British Isles [91J0].
The above list was taken from NPWS Conservation Objectives for this SAC (www.npws.ie, 2011). The
NPWS site synopsis is given in Appendix 4.1.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 7
4.4.1 Cabragh Wetlands pNHA
Cabragh Wetlands pNHA overlaps with the River Suir SAC. This summary site synopsis is from old records
for the pNHA.
There are two parts to this site, both situated close to the River Suir near Thurles. The largest section is the
Cabragh marshes which lie in a low-lying tributary valley into which the main river floods in winter. Here
there is an extensive area of Common Reed (Phragmites australis) with associated marshland and peaty
fen. The transition between vegetation types is often well displayed. A number of wetland plants of interest
occur, in particular the Narrow-leaved Bulrush (Typha angustifolia), Bottle Sedge (Carex vesicaria) and
Blunt-flowered Rush (Juncus subnodulosus). The site is naturally eutrophic, but it has also the nutritional
legacy of the former sugar factory which discharged into it through a number of holding lagoons, now
removed. Production is high which is seen in the size of such species as Celery-leaved Buttercup
(Ranunculus sceleratus) as well as in the reeds themselves. There is abundant food for surface feeding
wildfowl which total at 1,000 or so in winter. Widgeon, teal and mallard are numerous and the latter has a
large breeding population- with up to 400 in summer. In addition, less frequent species like shoveler and
pintail occur and there are records for both whooper and Bewick's swans.
The second site is the Tank wetland in Ardbaun, north of the town. This is higher up a tributary valley than
Cabragh and is mainly fed by springs of lime-rich groundwater.
4.5 Flora – Species of Conservation Importance
In addition to the important flora within Lower River Suir SAC and Cabragh Wetlands, records of important
plant species held on the NPWS database for the 10 K square S26 in which the study area is located include
Opposite-leaved pondweed Groenlandia densa at Urlingford (most likely in the River Goul), a species that is
legally protected under the Flora Protection Order, 1999. It occurs in lakes, rivers, canals and ditches with clear
base-rich water. However, more recent data for the area indicate that it occurs further north at Durrow in the
River Goul (NBDC). The River Drish and Rossestown do not occur in the River Goul catchment and
therefore this species is not considered further in this assessment.
4.6 Fauna – Species of Conservation Importance
The white-clawed crayfish Austropotamobius pallipes is noted throughout the River Suir catchment (NBDC)
and is listed on Annex II of the EU Habitats Directive. This species is still widespread in lakes and rivers
over much of Ireland, but it is becoming increasingly restricted to headwater streams elsewhere in Europe.
Lamprey another Annex II species is also noted in the river catchment of the River Drish.
Electrofishing carried out on behalf of Lisheen in 2006 recorded a number of native fish species including
European eel Anguilla anguilla, Salmon Salmo Salar and Brown trout Salmo trutta in the River Drish with the
latter dominating and Brown trout in the Rossestown River. The conservation status of Brown trout is
currently of Least Concern (NPWS, 2012). However, both the former two species are now on the Red list of
endangered species in Ireland. Salmon is a species listed on Annex II of the EU Habitats Directive. Currently
the conservation status of this species is considered Vulnerable (NPWS, 2011). The European eel is a fish
of significant ecological importance. In recent decades, this species has undergone a dramatic decline
throughout its range. The conservation status of this species is considered Critically Endangered.
Otter is protected under Wildlife Act 1976/2000, the EU Habitats Directive 92/43 Annex II, Annex IV and the
Bern Convention Appendix III. Currently the conservation status of this species is Amber –
Unfavourable / Inadequate. Otter is noted further downstream at the Suir / Rossestown confluence at
Thurles (NBDC).
Kingfisher, an Annex I Bird species under the EU Birds Directive, is noted throughout the catchment (NBDC).
Kingfisher is Amber-listed in Ireland. BirdLife International has evaluated the European population as
Depleted, due to a moderate historical decline (BWI).
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 8
Both Otter and Kingfisher are species that use the Suir catchment and rely on the aquatic species as prey
items.
4.7 Existing Environment
The Site comprises the permitted water impoundment facility that is surrounded by cutover bog with some
scrub and bog woodland. A large stockpile of peat and some highly disturbed amenity grassland occurs on
the western edge of the Site. The Lisheen Mine Tailings Management Facility (TMF) is to the east and
hardstanding areas such as buildings, car parks and roads to the south.
Habitats and some associated flora are described below.
4.8 Habitats
4.8.1 Other artificial lakes and ponds FL8
The main area of the assessment is the permitted water impoundment facility under construction which will
be modified to a tailings storage area. The permitted water impoundment facility replaces a small area of
milled peat and has low ecological value that has limited time for any development of natural habitat or
colonisation before its use as a water impoundment / tailings storage facility.
4.8.2 Habitats surrounding the Site
Habitats surrounding the Site in a 200 m buffer zone are discussed below, (Table 4.4).
Table 4.4: Main habitats recorded in the Study Area (Fossitt, 2000)
Habitat Habitat code
Cutover Bog PB4
Bog Woodland WN7
Spoil and Bare Ground ED2
Amenity Grassland GA2
Scrub WS1
Buildings and Artificial Surfaces BL3
Other Artificial Lakes and Ponds FL8
Cutover Bog PB4
This habitat dominates the northern area surrounding the Site and comprises an area of bare exposed peat
that has been cut and drained with no intact vegetation remaining.
Bog Woodland WN7
A remaining small patch of bog woodland habitat characterised by deciduous woodland species edges the
Application Site. This patch contains downy birch Betula pubescens and willow Salix spp, with some Rowan.
The understorey is mainly thick bramble with, patches of heather.
Spoil and Bare Ground ED2
A stockpile of peat is located adjacent to the Application Site which is not vegetated.
Scrub WS1
Patches of scrub occur in the area of amenity grassland along the edge of the cutover bog. The scrub
consists of gorse Ulex europaeus, bramble Rubus fruticosus agg., silver birch Betula pendula and willow
Salix spp.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 9
Amenity Grassland GA2
The grass areas to the west of the cutover bog are highly disturbed and are defined as amenity grassland.
The species include perennial rye grass Lolium perenne, Yorkshire fog Holcus lanatus, dandelion
Taraxacum agg., creeping buttercup Rannunculus repens and common nettle Urtica dioica. Colt’s-foot
Tussilago farfara dominates some of the disturbed areas along with some patches of soft rush Juncus
effusus.
Buildings and Artificial Surfaces BL3
Wind turbines occur to the west of the Site along with the buildings, roads and car park to the south.
Other Artificial Lakes and Ponds FL8
This habitat comprises the existing TMF and the adjacent complex of conditioning ponds. In addition, a
variety of other artificial ponds and lagoons are present elsewhere within the mine site that form components
of the mine water treatment and discharge infrastructure. The TMF has been partially restored to agricultural
pasture currently grazed by cattle.
4.9 Fauna
It is unlikely that the proposed Site is used regularly by fauna given potential disturbance to the area from
ongoing construction activities.
Fauna of the adjacent area include common mammal species fox, rabbit, rat, wood mouse and also Irish
Hare which are all protected under the Irish Wildlife Act 1976 (Amended 2000). Irish Hare use the area
around the wind turbines adjacent to the Site as resting area during the day and this will be avoided. As the
area is largely cutaway bog, hardstanding areas and buildings, there is very little valuable habitat for
important fauna species. Amphibians including frog Rana temporaria may use some of the drains and
ditches of the cutaway areas for breeding and for wildlife corridors in heavily disturbed areas. The Common
Lizard lacerta vivipara is often found on bogs including cutaway areas.
Given the lack of diversity of habitats, offering little potential suitable habitat for various stages of the life
cycles of invertebrates other than some drains, a limited diversity of invertebrates is likely to occur in the
area. There was no suitable habitat for bats on the Site and the surrounding mine buildings will not be
affected by the proposed modifications to the permitted water impoundment facility.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 10
4.9.1 Bird surveys
Breeding bird surveys were carried out in April and May 2013. The results are summarised in the following
section and Table 4.5.
Table 4.5: Breeding Bird Survey Data
All of the bird species noted on the Site are common in Ireland and are not of conservation concern. The
Black-headed Gull noted on the adjacent TMF but not on the Site is a Red listed species due to its rapidly
declining and localised breeding population. The European population is regarded as Secure, despite
declines in several countries. Snipe an Amber listed species feeds in the rushy area next to the Site.
All birds, nests, eggs and nestlings are fully protected under law in Ireland Wildlife Act (1976) as amended
2000. The bird nesting season is from the 1 March to the 31 September in Ireland. The cutting of trees,
bushes and hedgerows is restricted during this period and care should be taken to ensure that any such
activities do not result in an offence being committed under the Wildlife Act (1976) or the Wildlife Amendment
Act (2000).
4.10 Water Quality
4.10.1 Water Framework Directive
The Water Framework Directive (WFD) provides the basis for future EU water legislation for many years to
come (European Commission, 2000a). The Directive aims to ensure the quality of EU waters and takes a
holistic approach to water management. It updates existing water legislation through the introduction of a
statutory system of analysis and planning based upon the river basin, the use of ecological as well as
chemical standards and objectives, the integrated consideration of groundwater and surface water quality and
quantity, the introduction of some new regulatory factors, and the phased repeal of several older European
Directives.
Species Conservation Status
Breeding Pairs (possible / probable /
confirmed)
Location Present (no. individuals)
Other Activities (no. individuals)
Blackbird Green 1 Nesting in Bog woodland
2 1
Chaffinch Green 1 Nesting in trees of Bog woodland
2 -
Wren Green 1 Nesting in scrub 2 -
Willow Warbler
Green 1 Singing from willow tree
1 -
Dunnock Green 1 Nesting in scrub 2 -
Black Headed Gull
Red listed - - - 5 from TMF. Nesting pairs likely in TMF area.
Meadow Pipit
Green listed - - - 1 flying towards windturbine area to west.
Snipe Amber Listed - - - 3 Feeding on disturbed
ground in rushes next to
the Site.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 11
Item 7 of Article 16 (strategies against pollution water) of the WFD, states that the Commission shall submit
proposals for quality standards applicable to the concentrations of the priority substances surface water,
sediments or biota. Item 35 of Article 2 defines an Environmental Quality Standard (EQS) as the
concentration of a particular pollutant or group of pollutants in water, sediment or biota that should not be
exceeded in order to protect human health and the environment. Finally, in Annex 5 of the Directive, the
procedure described for setting these EQSs by Member States.
The use of EQSs is currently under constant review and scientific study. Bioavailability corrections through
the use of biotic ligand models (BLMs) allow a more accurate assessment to be made of potential metal
toxicity. The Dissolved Organic Carbon (DOC) concentrations are particularly important in defining the
bioavailability of copper and zinc and of other metals, such as nickel (EA, 2012, www.wfd.uk.org). Other
parameters such as pH and calcium conditions may also affect bioavailability of metals.
For many substances, the main risk to plants and animals is through direct toxicity in water → water column
EQS. But for lipophilic substances that bioaccumulate, the main risk is to predators exposed to the chemical
via the food chain → biota EQS. The biota EQS is expressed as a concentration in body tissue of prey
organism. Using bioaccumulation data, it can be converted to corresponding concentration in water. Biota
standards potentially offer a more reliable measure of environmental exposure than water samples for
substances that bioaccumulate. Biota can act as a composite sample. However, biota standards require
serious attention before we can use them to assess waterbody status with confidence (EA, 2012).
Therefore this report relies upon a combination of Q values and the water column EQS described in the
water impact assessment (Chapter 6).
4.10.2 WFD water quality reports
Lisheen mine discharges to both the Rossestown River and Drish River. These rivers occur upstream of the
River Suir SAC – an EU Natura 2000 site. The current WFD reports for these rivers are summarised below:
Rossestown River, a tributary of the River Suir, occurs in the South Eastern River Basin District within
the Upper Suir Water Management Unit (WFD Reports). The water quality of Rossestown is
considered Poor under the WFD. It is described as uunsatisfactory throughout with poor ecological
quality at all locations;
The Drish, a tributary of the River Suir, is considered Poor under the WFD. In particular, the ecological
status of the Drish is considered Poor which gives the overall rating. The physio-chemical rating is
Moderate; and
The EPA River Water Quality Report (2011) indicates that both the Rossestown and Drish rivers are
seriously polluted at times with water quality poor downstream of Lisheen with elevated levels of
ammonia and nitrite. Toxic effects are indicated downstream of Lisheen on the Drish. Cumulative
impacts of discharges from Lisheen Mine, Templetouhy WWTP and Derryfada Bog are indicated for the
Rossestown River in the report.
4.11 Rossestown River at Lisheen
4.11.1 Biological monitoring
Biological Monitoring of the Rossestown River has been carried out in April 2013, in order to establish the Q
values1 upstream and downstream of the Lisheen discharge. The survey is designed to assess the current
biological water quality, based on macroinvertebrate communities. There was no suitable sampling location
upstream of the discharge (and below the WWTP) therefore the EPA station upstream of the WWTP at the
Bridge NW of Derryville was sampled. The report is given in Appendix 4.2. Sampling locations of this 2013
biological monitoring are depicted on Figure 4.3 at the end of the document.
1 The Q-scheme values range from Q1 (grossly polluted) to Q5 (pristine), with the suffix /0 indicating a suspected toxic effect.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 12
The EPA Station upstream of both the Lisheen discharge point and the WWTP is Q3-4* which indicates
Moderate Ecological Quality, with a siltation effect. The sample taken downstream of Lisheen discharge and
Templetouhy WWTP is rated as Q3 which indicates Poor Ecological Quality.
4.12 Drish River at Lisheen
4.12.1 Biological monitoring
Biological monitoring of the River Drish has been undertaken by the EPA and Lisheen Mine over the past 20
years. A yearly sampling programme has been undertaken on behalf of Lisheen Mine since 2004. This
entails three sampling events for aquatic invertebrates (Q values), macrophytes and diatoms. The river is
sampled upstream and downstream of the Lisheen Mine discharge point. Figure 4.3 (attached at the back of
this document) depicts locations of surface water sampling locations referred to in Table 4.6. Site 1 and
Stretch A are upstream of the discharge. Sites 2 and 3 and Stretch B are downstream of the discharge. In
2012, water quality of Q3-4 at Site 1 is seen to decline to Q3 at Site 2, with a toxic impact evident at Site 2
since 1999. In May 2013, a water quality of Q3 with no toxic effect is recorded at all Sites in the first round of
3 sampling rounds for the year. The report is given in Appendix 4.2.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 13
Table 4.6: Q-values Recorded by the Environmental Protection Agency (EPA Envision)
Year 1992 1996 1999 2002 2005 2008 2011
Month July Aug May July
Survey EPA EPA EPA EPA EPA EPA EPA
Site
1
EPA 0040 (u/s of discharge)
- - 3-4 3-4 3 3 3-4
2
EPA (d/S of discharge) 0070
4-5 3-4 2/0 2-3/0 3/0 3/0 3/0
3
EPA No Code (ds/ of discharge)
Lisheen data
-
- - - - - -
/0 = possible toxic effect
*= siltation
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 14
4.13 Impact Assessment
4.13.1 Water quality
A detailed water impact assessment for the proposed development and associated activities is given in
Chapter 6.0 of the EIS. The cumulative impacts of water quality from the proposed development are the
main potential source of impact on the Rossestown and Drish rivers and the ecological species/habitats
associated with the rivers. Therefore, this assessment relies upon the water impact assessment in order to
establish if the proposed development will impact significantly on water quality and therefore affect the
ecology of the receiving surface waters.
4.13.2 Predicted impacts of proposed works
The main impacts under consideration in this report include;
Disturbance to habitats and species;
Habitat loss;
Species loss; and
Impacts on water quality.
Potential direct and indirect impacts from water quality are as follows:
Effects on important aquatic species such as salmon and eel;
Effects on SAC and pNHA habitats due to water quality impacts and possible indirect impacts resulting
in changes in the vegetation community of rivers;
Otter prey species have specific water quality requirements and any decline in water quality in the rivers
could have indirect impacts on the otter populations using the area; and
Increased macrophyte and algal growth – oxygen depletion, alteration of invertebrate/fish populations
which serve as food sources, vegetation changes causing alterations to fish habitats.
4.13.3 Evaluation
Terrestrial Habitats and Flora
Habitats and flora within the study area comprising the Site and surrounding area are all of Low ecological
value following criteria described in Table 4.2.
Surface Receiving Waters
The receiving waters of the Rossestown River and Drish River are considered of High local value and further
downstream the Lower River Suir is considered of International value as it is a European Natura 2000 site.
The Lower River Suir pNHA is also a national designation and is considered to be of ecological value for the
diversity of species it supports along its linear habitats.
Aquatic Fauna
The Rossestown and Drish support populations of protected species namely white-clawed crayfish, eel,
salmon and trout.
Eel is currently Critically Endangered and the EU requires management plans from Member States deal with
this population decline, therefore this species is considered of importance at International level, as a
precautionary approach.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 15
Salmon are currently Vulnerable, and as population data is not available for the study area it must be
assumed that the local populations are potentially important at a county level (e.g. 1% of county population),
and are therefore considered of importance at County level.
Otter
Signs of otter were recorded south of the study area and in the Suir catchment. Therefore it is possible that
they utilise the Rossestown or Drish rivers. As population data is not available for the study area it must be
assumed that the local population is potentially important at a county level (e.g. 1% of county population),
and as otter species are protected under EU legislation and in Ireland, they are considered to be of high local
value following criteria described in Table 4.2.
Other Terrestrial Fauna
There were eight bird species recorded in the study area during the bird surveys (Section 4.3) and four of
these believed to be breeding. All birds noted were common species and mainly associated with the
patches scrub and trees/woodland.
Other fauna such as mammals recorded in the study area include common mammal species; fox, rabbit, rat,
wood mouse and Irish Hare. The area is not likely to support a diversity of invertebrates given the low value
of habitats present on the Site and surrounding area. Amphibian species – newt and frogs may use the
study area along with lizard however there is little available habitat for them.
Given the low diversity of fauna and habitats, these are therefore considered to be of low local value
following criteria described in Table 4.2 as their presence enhances and enriches the local neighbourhood
area.
4.13.4 Impacts of proposed works
As highlighted in the Schlumberger Water Services (SWS) water impact assessment (Chapter 6.0), there is
no significant impact on the water quality of the Drish and Rossestown or on the groundwater at the various
stages of the mine closure, either alone or cumulatively. It is considered in the water impact assessment,
that the current water treatment processes in place at Lisheen are sufficient to treat the water discharge to
surface water quality standards and salmonid standards with some exceptions. Given the effects of other
parameters on EQS values, such as pH and DOC, it is the condition of the receiving waters and the Q values
(with siltation or toxic effects) that are taken as the indicators of the potential cumulative impacts of Lisheen
discharges and other diffuse/point discharges on ecological receptors.
Given that the overall status of both receiving waters (rivers) is considered Poor and that the Q rating for
ecological status is considered Poor, it would be important to ensure that the current mine water treatment is
in place and operating at full capacity at all stages of the proposed development for current and future
discharges.
In order to improve and protect the ecological status downstream of Lisheen in both rivers, optimisation of
the existing treatment of the water discharging from Lisheen Mine is required and additional treatment is
recommended as a precautionary measure, specifically in relation to the post closure water discharge.
Lisheen Mine have put in place treatment systems for the discharge which have succeeded in reducing
some of the water quality parameters, in particular for ammonia. This demonstrates that a wetland system
can achieve improvements in water quality for some parameters. The monitoring data for the current
treatment system can be used to determine the design of the wetland system proposed for post closure.
Direct and Indirect impacts that may be caused by the proposed works are summarised in Table 4.7 below,
and described in more detail in the following paragraphs.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 16
Table 4.7: Predicted Impacts of proposed works before mitigation
Description of Impact Direct/Indirect Magnitude/Size of Impact
Level (Evaluation of Feature)
Duration and reversibility
Likelihood Significance
Remaining Operational Period
Impacts from discharges on water quality and on aquatic species of the Rossestown and Drish rivers e.g. salmon and eel.
Direct Unquantified International/County Level
Medium term, Temporary Near Certain Moderate Negative
Impacts from discharges on water quality and on
Otter and Kingfisher
Indirect Unquantified International Medium term, Temporary Near Certain Moderate Negative
Active Mine Closure
Disturbance of habitats
during capping/closure activities
Direct Low Low Local Short-term, Temporary Near Certain Minor Negative
Disturbance to birds during
capping/closure activities Direct Low High local Short-term, Temporary Near Certain Minor Negative
Impacts from discharges on water quality and on important aquatic species e.g. salmon and eel.
Direct Unquantified International/County Level
Medium term, Temporary Near Certain Moderate Negative
Impacts from discharges on water quality and on
Otter and Kingfisher.
Indirect Unquantified International Medium term, Temporary Near Certain Moderate Negative
Long term post closure
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 17
Description of Impact Direct/Indirect Magnitude/Size of Impact
Level (Evaluation of Feature)
Duration and reversibility
Likelihood Significance
Impacts from discharges on water quality and on aquatic species of the Rossestown and Drish rivers e.g salmon and eel.
Direct Unquantified International/County Level
Long term, Permanent Near Certain Moderate Negative
Impacts from discharges on water quality and on
Otter and Kingfisher
Indirect Unquantified International Long term, Permanent Near Certain Moderate Negative
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 18
4.13.5 Discussion of predicted impacts
Following on from Table 4.7, predicted impacts prior to mitigation are described in more detail below.
4.13.5.1 Disturbance to habitats and species
Disturbance during capping and closure to habitats and species of the TMF and surrounding area is
considered Minor negative. Disturbance may occur due to adjacent areas due to increased presence of
humans and machinery during closure activities for example during the bird breeding season and works may
require screening from the surrounding area. Disturbance to Snipe feeding in adjacent areas may also be
addressed through screening. An ecological survey and recommendations at the appropriate time will be
needed to review and update any potential impacts during closure.
4.13.5.2 Loss habitats and species due to runoff to surface and ground water systems
The risk of runoff from the proposed works to ground and surface water systems can affect a number of
habitats and species. For example groundwater impacts may affect groundwater dependent terrestrial
ecosystems such as the Rossestown and Drish. Runoff may also affect the surface waters of both the
Rossestown and Drish rivers and associated important species such as crayfish, salmon, eel etc.
The cumulative impact of water quality on habitats and species is considered of moderate negative
significance, given the presence of important species. As the magnitude of the impact on these species is
unknown and given the ecological status of both rivers is Poor, mitigation as a precautionary measure is
therefore required to reduce the level of this potential impact.
Therefore, mitigation is required.
4.13.5.3 Impacts on otter and kingfisher
Indirect impacts of water quality may affect Otter and Kingfisher in the catchment, as they rely on the river for
prey species such as fish and aquatic invertebrates. The impact is considered moderate negative.
Therefore, mitigation is required.
4.14 Mitigation Measures
The principal objectives of ecological mitigation are to take measures to minimise adverse impacts of the
proposed project upon the existing nature conservation value of the study area. The output of the
assessment is to determine the significance of residual effects on the various ecological features.
4.14.1 Habitats and species disturbance
An ecological survey will be required immediately prior to closure to ascertain mitigation measures, if any
required during capping and closure.
4.14.2 Water quality
Although there are currently water treatment processes at Lisheen, the receiving waters are in Poor
ecological condition. Reductions to certain parameters of water quality have been achieved such as
ammonia through the addition of treatment wetlands and sediment traps at Lisheen. However, in order to
address the cumulative impact in the catchment and given the potential for impact on sensitive ecological
receptors such as salmon and eel, it is prudent for a precautionary approach to be taken and mitigation is
therefore recommended. The main mitigation measure to reduce the potential impacts on water quality, to
no significance, is the provision of a wetland treatment system which will be agreed with Inland Fisheries, in
terms of detailed design and implementation, once formal closure activities commence. The monitoring data
from the current wetland treatment system can be used to design the wetland system for closure.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 19
The proposed Biodiversity Action Plan by Lisheen Mine (2009) provides details of opportunities to enhance
biodiversity. An update of the proposed Lisheen BAP aimed at improving the riparian habitats and habitats
of the Rossestown and Drish Rivers, where possible, at Lisheen would further protect the rivers.
4.15 Residual Impacts
Residual cumulative impacts to features following mitigation are presented below. The conclusions of the
SWS Water Section are used to assess the residual impacts on water quality and therefore to some extent,
on aquatic habitats and species of the Rossestown and Drish rivers and also potential downstream impacts
on the Suir and Cabragh wetlands.
Table 4.8: Residual Impacts
Description of Impact Significance before mitigation
Mitigation Significance post mitigation
Remaining Operational Period
Impacts from discharges on water quality and on aquatic species of the Rossestown and Drish rivers e.g. salmon and eel.
Moderate Negative See long-term closure below
Impacts from discharges on water quality and on
Otter and Kingfisher
Moderate Negative See long-term closure below
Active Mine Closure
Disturbance of habitats
during capping/closure activities Minor Negative
Ecological Surveys and Recommendations
Minor Negative or less
Disturbance to birds during
capping/closure activities Minor Negative
Ecological Surveys
and
Recommendations
Minor Negative or less
Impacts from discharges on water quality and on aquatic species especially salmon and eel.
Moderate Negative
Design and Installation of a wetland system with consultation with Inland Fisheries
No significant impact
Impacts from discharges on water quality and on
Otter and Kingfisher.
Moderate Negative
Design and Installation of a wetland system in consultation with Inland Fisheries
No significant impact
Long term post closure
Impacts from discharges on water quality and on aquatic species of the Rossestown and Drish rivers especially salmon and eel.
Moderate Negative
Design and Installation of a wetland system in consultation with Inland Fisheries
No significant impact
Impacts from discharges on water quality and on
Otter and Kingfisher
Moderate Negative
Design and Installation of a wetland system with consultation with Inland Fisheries
No significant impact
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 20
4.16 Conclusions
Based upon the water impact assessment by SWS in Chapter 6.0, and once the wetland system is designed
and implemented in consultation with Inland Fisheries, no significant impacts are considered likely on
ecological features, in particular the Rossestown and Drish rivers and also the River Suir (SAC) and Cabragh
wetlands (pNHA) downstream.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 21
4.17 References
European Communities (2000). Managing NATURA 2000 sites: the provisions of Article 6 of the Habitats
Directive ‘92/43/EC.
Environmental Agency (2012) Environmental Quality Standards for trace metals in the aquatic ., EA Bristol
European Communities (2001). Assessment of plans and projects significantly affecting Natura 2000 sites:
Methodological guidance on the provisions of Article 6 (3) and (4) of the Habitats Directive 92/43/EEC.
European Union Habitats Directive (1992) Council Directives 92/43/EEC of 21 May 1992 on the conservation
of natural habitats and of wild fauna and flora.
Flora (Protection) Order (1999). Statutory Instrument, S.I. No. 94 of 1999. Published by the Stationery
Office, Dublin.
Fossitt, J.A. (2000). A guide to habitats in Ireland. The Heritage Council.
Heritage Council (2011). Best Practice Guidance for Habitat Survey and Mapping.
IEEM (2006). Guidelines for Ecological Impact Assessment in the United Kingdom (version 7 July 2006).
Institute of Ecology and Environmental Management.
Igoe, F., Quigley D.T.G., Marnell, F., Meskell, E., O’Connor W. and Byrne, C. (2004). The sea lamprey
Petromyzon marinus (L.), river lamprey Lampetra fluviatilis (L.) and brook lamprey Lampetra planeri (Bloch) in
Ireland: General biology, ecology, distribution and status with recommendations for conservation. Biology
and Environment: Proceedings of the Royal Irish Academy. 104b (3): 43-56.
JNCC (1990, Revised 2003). Handbook for Phase 1 habitat survey – a technique for environmental audit.
Joint Nature Conservancy Committee, Peterborough.
Kelly, F. L. and King, J. J. 2001 A review of the ecology and distribution of three lamprey species, Lampetra
fluviatilis (L.), Lampetra planeri (Bloch) and Petromyzon marinus (L.): a context for conservation and
biodiversity considerations in Ireland. Biology and Environment : Proc. R. Ir. Acad. 101B, 165-185.
King J.J., Lordan M., & Wightman G.D. (2008) Ecological Impact Assessment (EcIA) of The Effects of
Statutory Arterial Drainage Maintenance Activities on Whiteclawed Crayfish (Austropotamobius pallipes).
Series of Ecological Assessments on Arterial Drainage Maintenance No 10 Environment Section, Office of
Public Works, Headford, Co. Galway.
Lynas, P. Newton, S.F., Robinson, J.A. 2007. The status of birds in Ireland: an analysis of conservation
concern 2008- 2013. Irish Birds. Vol.8, No.3.
Maitland, P. S. 2003. Ecology of the River, Brook and Sea Lamprey. Conserving Natura 2000, Rivers
Ecology Series No. 5. English Nature, Peterborough.
NPWS (2009). Appropriate Assessment of Plans and Projects in Ireland. Guidance for Planning Authorities.
NRA (2009). Guidelines for the Assessment of Ecological Impacts of National Roads Schemes. National
Roads Authority, Ireland.
NRA (2008). Ecological Surveying Techniques for Protected Flora and Fauna during the Planning of National
Road Schemes. National Roads Authority, Ireland.
NRA (2005). Guidelines for the Treatment of Otters Prior to the Construction of National Road Schemes.
National Roads Authority, Ireland.
OPW (2006). Series of Ecological Assessments on Arterial Drainage Maintenance No. 4: Ecological Impact
Assessments (EcIA) of the Effects of Statutory Arterial Drainage Maintenance Activities on the Otter (Lutra
lutra). Office of Public Works, November 2006.
Webb, D.A., Parnell, J., Doogue, D. (1996). An Irish Flora. Dundalgan press. Dundalk.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1 22
Wildlife Act (1976) Wildlife Act, Ireland, 22 December 1976: An act for the conservation of wildlife (including
game).
Wildlife Amendment Act (2000) Wildlife Amendment Act, Ireland, 18 December 2000, No. 38 of 200.
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1
FIGURES
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1
Figure 4.1: EU and National Designations within 15 km of Lisheen Mine
4.2 V.10 100 20050
Meters
Lisheen Milling Ltd.
Planning Application
Habitat MapKMG CW CW AUGUST 2013
AR0056013 11 5071 5 0226
A4 A.0
LegendApplication Site Boundary200m Buffer of Application Site BoundaryLands Under Control of Lisheen MineFL8 - Other Artificial Lakes and PondsED2 - Spoil and Bare GroundWN7 - Bog Woodland (Remnant)WS1 - ScrubBL3 - Buildings and Artificial SurfacesGA2 - Amenity GrasslandPB4 - Cutover Bog
Note 1 - Highly Disturbed
1:4,500
Constructed Area
Golder Associates (IRL) LtdTown Centre House
Dublin RoadNaas
Co. KildareTel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
Note1
2N
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1
Figure 4.3: Sampling locations. (Sweeney, 2013)
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1
APPENDIX 4.1 NPWS Site Synopsis
SITE SYNOPSIS
SITE NAME : LOWER RIVER SUIR
SITE CODE : 002137
This site consists of the freshwater stretches of the River Suir immediately south ofThurles, the tidal stretches as far as the confluence with the Barrow/Nore immediatelyeast of Cheekpoint in Co. Waterford and many tributaries including the Clodiagh in Co.Waterford, the Lingaun, Anner, Nier, Tar, Aherlow, Multeen and Clodiagh in Co.Tipperary. The Suir and its tributaries flows through the counties of Tipperary, Kilkennyand Waterford. Upstream of Waterford city, the swinging meanders of the Suir criss-cross the Devonian sandstone rim of hard rocks no less than three times as they leave thelimestone-floored downfold below Carrick In the vicinity of Carrick-on-Suir the riverfollows the limestone floor of the Carrick Syncline. Upstream of Clonmel the river andits tributaries traverse Upper Palaeozoic Rocks, mainly the Lower Carboniferous Viseanand Tournaisian. The freshwater stretches of the Clodiagh River in Co. Waterfordtraverse Silurian rocks, through narrow bands of Old Red Sandstone and Lower AvonianShales before reaching the carboniferous limestone close to its confluence with the Suir.The Aherlow River flows through a Carboniferous limestone valley, with outcrops of OldRed Sandstone forming the Galtee Mountains to the south and the Slievenamuck range tothe north. Glacial deposits of sands and gravels are common along the valley bottom,flanking the present-day river course.
The site is a candidate SAC selected for the presence of the priority habitats on Annex I ofthe E.U. Habitats Directive - alluvial wet woodlands and Yew Wood. The site is alsoselected as a candidate SAC for floating river vegetation, Atlantic salt meadows,Mediterranean salt meadows, old oak woodlands and eutrophic tall herbs, all habitatslisted on Annex I of the E.U. Habitats Directive. The site is also selected for the followingspecies listed on Annex II of the same directive - Sea Lamprey, River Lamprey, BrookLamprey, Freshwater Pearl Mussel, Crayfish, Twaite Shad, Atlantic Salmon and Otter.
Alluvial wet woodland is declining habitat in Europe as a result of drainage andreclamation. The best examples of this type of woodland in the site are found on theislands just below Carrick-on-Suir and at Fiddown Island. Species occurring hereinclude Almond Willow (Salix triandra), White Willow (S. alba), Grey Willow (S.cinerea), Osier (S. viminalis), with Iris (Iris pseudacorus), Hemlock Water-dropwort(Oenanthe crocata), Angelica (Angelica sylvestris), Pendulus Sedge (Carex pendula),Meadowsweet (Filipendula ulmaria) and Valerian (Valeriana officinalis). The terrainis littered with dead trunks and branches and intersected with small channels whichcarry small streams to the river. The bryophyte and lichen floras appear to be rich andrequire further investigation. A small plot is currently being coppiced and managedby National Parks and Wildlife. In the drier areas the wet woodland species mergewith other tree and shrub species including Ash (Fraxinus excelsior), Hazel (Corylusavellana), Hawthorn (Crataegus monogyna) and Blackthorn (Prunus spinosa). Thisadds further to the ecological interest of this site.
Eutrophic tall herb vegetation occurs in association with the various areas of alluvialforest and elsewhere where the flood-plain of the river is intact. Characteristic species ofthe habitat include Meadowsweet (Filipendula ulmaria), Purple Loosestrife (Lythrumsalicaria), Marsh Ragwort (Senecio aquaticus), Ground Ivy (Glechoma hederacea) andHedge Bindweed (Calystegia sepium).
Old oak woodlands are also of importance at the site. The best examples are seen inPortlaw Wood which lies on both sides of the Clodiagh River. On the south-facingside the stand is more open and the Oaks (mainly Quercus robur) are well grown andspreading. Ivy (Hedera helix) and Bramble (Rubus fruticosus) are common on theground, indicating relatively high light conditions. Oak regeneration is dense, varyingin age from 0-40 years and Holly (Ilex aquifolium) is fairly common but mostly quiteyoung. Across the valley, by contrast, the trees are much more closely spaced andthough taller are poorly grown on average. There are no clearings; large Oaks extendto the boundary wall. In the darker conditions, Ivy is much rarer and Holly muchmore frequent, forming a closed canopy in places. Oak regeneration is uncommonsince there are as yet few natural clearings. The shallowness of the soil on the north-facing slope probably contributes to the poor tree growth there. The acid nature of thesubstrate has induced a “mountain” type Oakwood community to develop. There is anextensive species list present throughout including an abundance of mosses, liverwortsand lichens. The rare lichen Lobaria pulmonaria, an indicator of ancient woodlands,is found.
Inchinsquillib Wood consists of three small separate sloping blocks of woodland in avalley cut by the young Multeen River and its tributaries through acidic Old RedSandstone, and Silurian rocks. Two blocks, both with an eastern aspect, located to thenorth of the road, are predominantly of Sessile oak (Quercus petraea) and Hazel, withDowny Birch (Betula pubescens), Ash and Holly. The ground flora is quite mixed withfor example Wood sedge (Carex sylvatica), Bluebell (Hyacinthoides non-scriptus),Primrose (Primula vulgaris), Wood-sorrel (Oxalis acetosella), Pignut (Conopodiummajus) and Hard fern (Blechnum spicant). The base poor nature of the underlying rock is,to some extent masked by the overlying drift. The third block, to the south of the road,and with a northern aspect, is a similar although less mature mixture of Sessile Oak, Birchand Holly, the influence of the drift is more marked, with the occurrence of Woodanemone (Anemone nemorosa) amongst the ground flora.
Floating river vegetation is evident in the freshwater stretches of the River Suir andalong many of its tributaries. Typical species found include Canadian Pondweed(Elodea canadensis), Milfoil (Myriophyllum spp.), Fennel Pondweed (Potamogetonpectinatus), Curled Pondweed (P. crispus), Perfoliate Pondweed (P. perfoliatus), PondWater-crowfoot (Ranunculus peltatus), other Crowfoots (Ranunculus spp.) and themoss Fontinalis antipyretica. At a couple of locations along the river, Opposite-leaved Pondweed (Groenlandia densa) occurs. This species is protected under theFlora (Protection) Order, 1999.
The Aherlow River is fast-flowing and mostly follows a natural unmodified river channel.Submerged vegetation includes the aquatic moss Fontinalis antipyretica and StreamWater-crowfoot (Ranunculus pencillatus), while shallow areas support species such asReed Canary-grass (Phalaris arundinacea), Brooklime (Veronica beccabunga) and Water
Mint (Mentha aquatica). The river bank is fringed in places with Alder (Alnus glutinosa)and Willows (Salix spp.).
The Multeen River is fast flowing, mostly gravel-bottomed and appears to follow anatural unmodified river channel. Water Crowfoots occur in abundance and the aquaticmoss Fontinalis antipyretica is also common. In sheltered shallows, species such asWater-cress (Rorippa nasturtium-aquaticum) and Water-starworts (Callitriche spp.)occur. The river channel is fringed for most of its length with Alder, Willow and anarrow strip of marshy vegetation.
Salt meadows occur below Waterford City in old meadows where the embankment isabsent, or has been breached, and along the tidal stretches of some of the in-flowingrivers below Little Island. There are very narrow, non-continuous bands of thishabitat along both banks. More extensive areas are also seen along the south bank atBallynakill, the east side of Little Island, and in three large salt meadows betweenBallynakill and Cheekpoint. The Atlantic and Mediterranean sub types are generallyintermixed. The species list is extensive and includes Red Fescue (Festuca rubra),Oraches (Atriplex spp.), Sea Aster (Aster tripolium), Sea Couch Grass (Elymuspycnanthus), frequent Sea Milkwort (Glaux maritima), occasional Wild Celery (Apiumgraveolens), Parsley Water-dropwort (Oenanthe lachenalii), English Scurvygrass(Cochlearia anglica) and Sea Arrowgrass (Triglochin maritima). These species aremore representative of the Atlantic sub-type of the habitat. Common Cord-grass(Spartina anglica), is rather frequent along the main channel edge and up the internalchannels. The legally protected (Flora (Protection) Order, 1999) Meadow Barley(Hordeum secalinum) grows at the landward transition of the saltmarsh. Sea Rush(Juncus maritimus), an indicator of the Mediterranean salt meadows, also occurs.
Other habitats at the site include wet and dry grassland, marsh, reed swamp, improvedgrassland, coniferous plantations, deciduous woodland, scrub, tidal river, stony shore andmudflats. The most dominant habitat adjoining the river is improved grassland, althoughthere are wet fields with species such as Yellow Flag (Iris pseudacorus), Meadow Sweet(Filipendula ulmaria), Rushes (Juncus spp.), Meadow Buttercup (Ranunculus acris) andCuckoo Flower (Cardamine pratensis).
Cabragh marshes, just below Thurles, lie in a low-lying tributary valley into which themain river floods in winter. Here there is an extensive area of Common Reed(Phragmites australis) with associated marshland and peaty fen. The transition betweenvegetation types is often well displayed. A number of wetland plants of interest occur, inparticular the Narrow-leaved Bulrush (Typha angustifolia), Bottle Sedge (Carexrostrata) and Blunt-flowered Rush (Juncus subnodulosus). The marsh is naturallyeutrophic but it has also the nutritional legacy of the former sugar factory whichdischarged into it through a number of holding lagoons, now removed. Production is highwhich is seen in the size of such species as Celery-leaved Buttercup (Ranunculussceleratus) as well as in the reeds themselves.
Throughout the Lower River Suir site are small areas of woodland other than thosedescribed above. These tend to be a mixture of native and non-native species, althoughthere are some areas of semi-natural wet woodland with species such as Ash and Willow.Cahir Park Woodlands is a narrow tract of mixed deciduous woodland lying on the flat-lying floodplain of the River Suir. This estate woodland was planted over one hundred
years ago and it contains a large component of exotic tree species. However, due tooriginal planting and natural regeneration there is now a good mix of native and exoticspecies. About 5km north west of Cashel, Ardmayle pond is a long, possibly artificialwater body running parallel to the River Suir. It is partly shaded by planted Lime (Tiliahybrids), Sycamore (Acer pseudoplatanus) and the native Alder. Growing beneath thetrees are shade tolerant species such as Remote sedge (Carex remota).
The site is of particular conservation interest for the presence of a number of Annex IIanimal species, including Freshwater Pearl Mussel (Margaritifera margaritifera andM. m. durrovensis), Freshwater Crayfish (Austropotamobius pallipes), Salmon (Salmosalar), Twaite Shad (Alosa fallax fallax), three species of Lampreys - Sea Lamprey(Petromyzon marinus), Brook Lamprey (Lampetra planeri) and River Lamprey(Lampetra fluviatilis) and Otter (Lutra lutra). This is one of only three knownspawning grounds in the country for Twaite Shad.
The site also supports populations of several other animal species. Those which are listedin the Irish Red Data Book include Daubenton’s Bat (Myotis daubentoni), Nattererer’sBat (M. nattereri), Pipistrelle (Pipistrellus pipistrellus), Pine Marten (Martes martes),Badger (Meles meles), the Irish Hare (Lepus timidus hibernicus), Smelt (Osmeruseperlanus) and the Frog (Rana temporaria). Breeding stocks of Carp are found inKilsheelan Lake. This is one of only two lakes in the country which is known to havesupported breeding Carp. Carp require unusually high summer water temperatures tobreed in Ireland and the site may therefore support interesting invertebrate populations.
Parts of the site have also been identified as of ornithological importance for a number ofAnnex I (EU Birds Directive) bird species, including Greenland White-fronted Goose(10), Golden Plover (1490), Whooper Swan (7) and Kingfisher. Figures given in bracketsare the average maximum counts from 4 count areas within the site for the three wintersbetween 1994 and 1997. Wintering populations of migratory birds use the site. Flocksare seen in Coolfinn Marsh and also along the reedbeds and saltmarsh areas of the Suir.Coolfinn supports nationally important numbers of Greylag Geese on a regular basis.Numbers between 600 and 700 are recorded. Other species occurring include Mallard(21), Teal (159), Wigeon (26), Tufted Duck (60), Pintail (4), Pochard (2), Little Grebe(2), Black-tailed Godwit (20), Oystercatcher (16), Lapwing (993), Dunlin (101), Curlew(195), Redshank (28), Greenshank (4) and Green Sandpiper (1). Nationally importantnumbers of Lapwing (2750) were recorded at Faithlegg in the winter of 1996/97. InCabragh marshes there is abundant food for surface feeding wildfowl which total at 1,000or so in winter. Widgeon, Teal and Mallard are numerous and the latter has a largebreeding population - with up to 400 in summer. In addition, less frequent species likeShoveler and Pintail occur and there are records for both Whooper and Bewick's swans. Kingfisher, a species that is listed on Annex I of the EU Birds Directive, occurs alongsome of the many tributaries throughout the site.
Landuse at the site consists mainly of agricultural activities including grazing, silageproduction, fertilising and land reclamation. The grassland is intensively managed andthe rivers are therefore vulnerable to pollution from run-off of fertilisers and slurry.Arable crops are also grown. Fishing is a main tourist attraction on stretches of the Suirand some of its tributaries and there are a number of Angler Associations, some with anumber of beats. Fishing stands and styles have been erected in places. Both commercialand leisure fishing takes place on the rivers. The Aherlow River is a designated Salmonid
Water under the EU Freshwater Fish Directive. Other recreational activities such asboating, golfing and walking are also popular. Several industrial developments, whichdischarge into the river, border the site including three dairy related operations and atannery.
The Lower River Suir contains excellent examples of a number of Annex I habitats,including the priority habitat Alluvial Forest. The site also supports populations ofseveral Annex II animal species and a number of Red Data Book animal species. Thepresence of two legally protected plants (Flora (Protection) Order, 1999) and theornithological importance of the river adds further to the ecological interest of this site.
6.10.2006
CHAPTER 4.0 FLORA AND FAUNA
August 2013 Report No. 11507150226.R01.4.A1
APPENDIX 4.2 Water Quality Reports – Q values
Lisheen Mine
Receiving Water Monitoring – Biological.
Invertebrates, Diatoms, Macrophytes
Licence Reg. No. P0088-03
May 2013
Prepared by:
Pascal Sweeney M.Sc., MIEEM
& Niamh Sweeney M.Sc.,
Sweeney Consultancy,
Rahan,
Mallow
Co. Cork.
Tel. 022/26780
2
TABLE OF CONTENTS
Page
SECTION 1 INTRODUCTION 3.
SECTION 2 INVERTEBRATES 4.
SECTION 3 DIATOMS 7.
SECTION 4 MACROPHYTES 9.
SECTION 5 CONCLUSIONS 10.
APPENDIX 1 SAMPLING SITE LOCATIONS 11.
APPENDIX 2 SAMPLING SITE DETAILS 12.
APPENDIX 3 PHOTOGRAPHS OF SAMPLING SITES 17.
APPENDIX 4 INVERTEBRATE FAUNAL RESULTS 21.
APPENDIX 5 DIATOM SPECIES RECORDED 22.
APPENDIX 6 REFERENCES 23.
3
1. INTRODUCTION
Monitoring of the receiving water for the IPPC Licence (Reg No. P0088-03) of the Lisheen
Mine includes the following biological parameters: Invertebrates, Diatoms and Macrophytes.
Assessments are to be carried out upstream and downstream of the groundwater discharge to
the River Drish. Sampling locations for these biological parameters are shown in Appendix
1. Site details are presented in Appendix 2.
Invertebrate monitoring (Q-value) sites. One upstream and two downstream:
Site 1. 2nd
bridge upstream of Longfordpass Bridge (EPA Site 16/D02/0040). This is the
nearest EPA site upstream of the discharge. It is also the first upstream location properly
suited to the Q-scheme methodology. Although it is over 5.5km upstream, results from this
site give information on the water quality of the upstream catchment which can be directly
compared with EPA data.
Site 2. Bridge NE of Castletown (EPA Site 16/D02/0070). This is the nearest EPA site
downstream of the discharge. Results from this site can be directly compared with EPA data
and give information on changes occurring in the stretch of river within 300m of the
discharge. However, because of the depth and physical conditions, sampling opportunities at
this site can be limited in periods of high flow. Sampling at Site 3 is therefore also
undertaken, so that a downstream sample will be obtainable on every occasion.
Site 3. Bridge NW of Castletown. Results from this site give information on the condition
of the river c. 1.8km downstream of the discharge.
Diatom monitoring (TDI) sites. Two of the same sites as for invertebrate monitoring are
used:
Site 1. 2nd
bridge upstream of Longfordpass Bridge (EPA Site 16/D02/0040). This site is
the nearest location site upstream of the discharge suitable for standard TDI methodology.
Because of the depth and physical conditions, Site 2 is not suited to the TDI methodology.
Site 3. Bridge NW of Castletown. Results from this site give information on the condition
of the river c. 1.8km downstream of the discharge.
4
Macrophyte monitoring (MTR) sites. Macrophyte sites are not the same as those used for
monitoring invertebrates and diatoms, but rather are two 100m stretches of river, upstream
and downstream of the groundwater discharge:
Stretch A: 100m stretch directly upstream of the discharge point.
Stretch B: 100m stretch directly upstream of EPA Site 0070 (starting c. 200m downstream
of the discharge point.
All field work was carried out by Pascal Sweeney on 16 May, 2013. Most of the section of
river surveyed had been dredged late summer/autumn 2012. Only Site 1 (EPA Site
16/D02/0040) was unaffected by dredging.
2. INVERTEBRATES
2.1 Methodology.
The procedure of assessment of biological water quality using invertebrates in this survey is
the Q-Rating System used by the Environmental Protection Agency (Toner et al., 2005).
2.2 Field and Laboratory Procedures
Field work was carried out by Pascal Sweeney on 16 May, 2013. At each sampling site, a
general assessment of the relevant physical conditions was made prior to macroinvertebrate
sampling. Physical conditions recorded are presented in Appendix 2 and photographs are
presented in Appendix 3. A five-minute kick and stone wash sample was taken. Following
sieving, each sample was live sorted for 30 minutes under laboratory conditions.
Macroinvertebrates were preserved in 70% alcohol, examined microscopically and identified
to the taxonomic level required to calculate Q-ratings by the EPA methodology. A list of
taxonomic keys used to identify macroinvertebrates is presented in Appendix 4. Based on the
abundance of indicator groups and other relevant environmental data, a Q-value was
determined for each site in accordance with the biological assessment procedures used by the
EPA.
5
2.3 Invertebrate Results
The list of macroinvertebrate taxa identified to the level required for the Q-scheme and
numbers recorded in 30 minutes sorting at each site are presented in Appendix 4.
The Q-scheme values range from Q1 (grossly polluted) to Q5 (pristine). Suffixes of /0,
indicating a suspected toxic effect, and *, indicating a siltation effect may be added.
Macroinvertebrate Community Analysis by Site.
Site 1. The fauna of this eroding site is dominated by the freshwater shrimp, Gammarus
duebeni, which is in EPA Indicator Group C (Relatively Pollution Tolerant). No Group A
(Very Pollution Sensitive) were found. Group B (Relatively Pollution Sensitive) is
represented by two specimens of Glossosomatidae and three of Limnephilidae. Group D
(Very Pollution Tolerant) is represented by two specimens of the water slater, Asellus
aquaticus. Group E (Most Pollution Tolerant) is absent.
The absence of Groups A taxa in a fauna dominated by Group C, with very little
representation of Group D and no Group E representation, indicates a Q-value of Q3.
Site 2. While the invertebrate faunal diversity is low, with 9 taxa identified, abundance is
good, with 157 individuals found in 30 minutes sorting. Groups C is dominant, while
Groups A and E are absent.
Because the expected invertebrate groups are represented and the freshwater shrimp,
Gammarus duebeni, which was absent from this site throughout 2011 and in May and July
2012, is present in good numbers, a toxic effect is not evident here on this occasion. The Q-
value ascribed is therefore Q3.
Site 3. Over half the invertebrates found at this site were non-biting midge larvae
(Chironomidae, GroupC). No Group A or Group Btaxa were found. Asellus aquaticus
(Group D) is the second most abundant invertebrate at this site. No Group E taxa were found.
6
The dominance of non-biting midge larvae indicates that the invertebrate fauna of this site is
in recovery from a recent perturbation, which depleted the fauna, allowing re-colonisation by
the multi-voltine midge larvae. This could have been caused by the dredging in late
summer/autumn 2012. The absence of Groups A, B and E indicates a Q-value of Q3.
7
3. DIATOMS
3.1 Methodology.
The procedure of assessment of biological water quality using diatoms in this survey is the
Trophic Diatom Index (TDI) (Kelly et al., 2008).
3.2 Field and Laboratory Procedures
Field work was carried out by Pascal Sweeney on 16 May, 2013. At each sampling site, a
general assessment of the relevant physical conditions was made prior to diatom sampling.
Physical conditions recorded are presented in Appendix 2 and photographs are presented in
Appendix 3. Sampling was conducted according to the guidelines outlined in European
Committee for Standardisation EN 13946 (2003). Five cobbles, preferably free from silt and
filamentous algae, were randomly selected along a stretch of approximately 10m. Loosely
attached organic debris was removed by gentle agitation in stream water. Diatom
assemblages were removed by placing the cobbles in a basin containing 100ml of river water
and brushing the upper surface of each cobble with a stiff toothbrush. The sample at each site
was pooled, transferred to a polyethylene bottle and preserved with Lugo’s iodine. Samples
were stored under refrigerated conditions to prevent the sublimation of iodine.
Samples were processed by Niamh Sweeney. For the preparation of permanent slides, 15 ml
of sample was pipetted into a beaker and 20-30 ml of 30% hydrogen peroxide was added to
each beaker to oxidise organic material and the cell contents in order to observe the
ornamentation on the frustules. The beakers were placed in a water bath at 90°C for 3-4
hours until oxidised. Three drops of 1 M hydrochloric acid were added to remove carbonates.
Each sample was rinsed with distilled water at least four times at the end of the treatment to
neutralise the sample. One ml of sample was pipetted onto 20 mm square, 0 thickness
coverslips and left to air-dry. Coverslips were mounted on glass slides using Naphrax®
diatom mountant for microscopic observation at x1000 magnification. A diatom valve was
used as the count unit and valves were counted according to the guidance standard BS EN
14407 (2004). Full valves and broken valves, where approximately three-quarters of the
valve was present, were counted. All diatoms visible in a field of view were counted and
identified before moving vertically to the next field of view. Diatom species were identified
using Krammer & Lange-Bertalot (1986, 1988, 1991a, 1991b) and Kelly (2000). Valve
8
counts per slide were in the range of 300-350 valves. Using species sensitivity values,
assigned according to their tolerance to nutrients, ranging from 1 (low tolerance) to 5 (high
tolerance) (Kelly et al., 2001), the TDI for the site is calculated.
3.3 Diatom Results
Lists of diatom species identified at each site are presented in Appendix 5.
TDI values are most significantly correlated with nutrients, in particular soluble reactive
phosphorus (Kelly et al., 2008). The scoring system runs from 0-100 with low scores
reflecting oligotrophic waters and high scores indicating eutrophic conditions. The index may
also be influenced by non-nutrient factors such as siltation (Kelly, 2003).
Diatom Analysis by Site.
Site 1. 26 species of diatom were identified. The TDI value calculated is 83.25
Site 3. 15 species of diatom were identified. The TDI value calculated is 26.76
9
4. MACROPHYTES
4.1 Methodology.
The procedure of assessment of biological water quality using macrophytes in this
monitoring programme is the Mean Trophic Rank (MTR) (Holmes et al., 1999). According
to the EPA website, while the MTR method is not yet included in EPA ecological status
assessments, it is the macrophyte assessment method which they are in the process of
intercalibrating. As the MTR method should ideally be carried out from mid-June to mid-
September, results from outside this period might not be reliable. The raw data collected
could also be used in some other assessment methodology, in the future.
3.2 Field and Laboratory Procedures
While the two assessment stretches were surveyed, because the dredging in 2012 removed
practically all the macrophytes, they have not recovered sufficiently to make a MTR
calculation meaningful. Lemna minor, Sparganium erectum, Sparganium emersum, Apium
nodiflorum, potamogeton natans and Nuphar lutea were present, but at less than 3%
occurrence each. Photographs of the stretches are presented in Appendix 3.
10
5. CONCLUSIONS
At Site 1, approximately 5.5km upstream of the Lisheen Mine discharge, the
macroinvertebrate and diatom communities indicate that the Drish River is affected by
eutrophication. This site is half a Q-value lower than was the case in both May 2011 and May
2012, indicating a decrease in dissolved oxygen. The Trophic Diatom Index is higher than in
May of the two previous years, indicating more nutrient enriched conditions.
As Q3 was also recorded at Sites 2 and 3 and as a toxic effect is not evident in the faunal
composition and abundance, the Lisheen Mine discharge is not seen to be currently affecting
the macroinvertebrate fauna. However Q3 is defined as Poor Ecological Status in accordance
with the European Communities Environmental Objectives (Surface Waters) Regulations
2009.
The diatom results do not show any negative impact of the discharge from Lisheen Mine.
Indeed, the TDI indicates better biological water quality at Site 3 than at Site 1. However, it
must be borne in mind that this index is designed on a scale of nutrient enrichment, rather
than on other factors affecting water quality.
11
APPENDIX 1
SAMPLING SITE LOCATIONS
12
APPENDIX 2
RIVER DRISH SAMPLING SITE DETAILS
Macroinvertebrate &
Diatom Site Code
1
GPS Reading S2518 5992
EPA Site 0040
Location 2nd
br. u/s of Longfordpass Br.
Photograph No. 1
Wet Width (m) 3.5
Sampling depth (m) 0.25
Flow Glide/Run: 100%
Substrate 1. Cobble
2. Gravel
3. Sand
Instream Vegetation Apium nodiflorum 10%
Ranunculus sp. 10%
Shade Light
13
Macroinvertebrate Site
Code
2
GPS Reading S2173 6353
EPA Site 0070
Location Br. NE of Castletown
Photograph No. 2
Wet Width (m) 12
Sampling depth (m) 0.25
Flow Riffle: 100%
Substrate 1. Cobble
2. Gravel
3. Silt
Instream Vegetation Sparganium emersum <5%
Ranunculus sp. <5%
Shade Medium
14
Macroinvertebrate &
Diatom Site Code
3
GPS Reading S2067 6345
EPA Site N/A
Location Br. NW of Castletown
Photograph No. 3
Wet Width (m) 7
Sampling depth (m) 0.35
Flow Glide/Run: 100%
Substrate 1. Cobble
2. Gravel
3. Silt
4. Large rocks
Instream Vegetation Filamentous algae 10%
Ranunculus sp. 10%
Potamogeton natans 5%
Apium nodiflorum <5%
Callitriche sp. <5%
Shade Light
15
Macrophyte Stretch A
Length of stretch (m) 100
Upstream end location and
GPS Reading
At last 2 hawthorns on bank u/s of discharge
S22118 63670
Upstream end photo 4
Downstream end location and
GPS Reading
At intake pipe and buoy
S22045 63621
Downstream end photo 5
Wet Width (m) >5-10
Average depth (m) >1.0
Substrate Peaty silt: 100%
Flow Habitat Slack: 100%
Shading None: 100%
Water Clarity Clear: 100%
Bed Stability Soft/Sinking: 100%
16
Macrophyte Stretch B
Length of stretch (m) 100
Upstream end location and
GPS Reading
13m d/s ESB pole stay wire
S21819 63492
Upstream end photo 6
Downstream end location and
GPS Reading
Bridge
S21744 63523
Downstream end photo 7
Wet Width (m) 10 – 20
Average depth (m) >0.5 – 1.0
Substrate Silt: 50%
Gravel: 40%
Cobble: 10%
Flow Habitat Run: 100%
Shading None: 100%
Water Clarity Turbid: 100%
Bed Stability Stable: 50%
Unstable: 50%
17
APPENDIX 3
PHOTOGRAPHS OF SAMPLING SITES Photo 1: Site 1
Photo 2: Site 2
18
Photo 3: Site 3
Photo 4: Macrophyte Stretch A, Upstream end
19
Photo 5: Macrophyte Stretch A, Downstream end
Photo 6: Macrophyte Stretch B, Upstream end
20
Photo 7: Macrophyte Stretch B, Downstream end
21
APPENDIX 4
INVERTEBRATES RESULTS
Numbers presented are the numbers of specimens sorted per sample in 30 minutes.
TAXON SITE 1 SITE 2 SITE 3
Group A (Sensitive)
None recorded
Group B (Less Sensitive)
Glossosomatidae 2 1
Limnephilidae 6 1
Group C (Relatively Tolerant)
Hydracarina 2
Bithynia tentaculata 5
Gammarus sp. 86 92 2
Baetis rhodani 1
Ephemerellidae 1
Hydropsychidae 3 1
Polycentropodidae 4 4
Elmidae 136 2 17
Hygrobiidae 3
Simuliidae 1 5
Chironomidae (ex. Chironomus) 6 103
Group D (Very Tolerant)
Asellus aquaticus 2 47 46
Group E (Most Tolerant)
None recorded
APPENDIX 5
Diatom Species Identified at Sites 1 and 3
Site 1
TDI=83.25
Achnanthes hungarica
Achnanthidium minutissimum
Amphora pediculus
Fragilaria capucina
Gomphonema angustatum
Gomphonema minutum
Gomphonema olivaceum
Gomphonema parvulum
Gyrosigma acuminatum
Meridion circulare
Navicula atomus
Navicula cryptocephala
Navicula cryptotenella
Navicula gregaria
Navicula lanceolata
Navicula menisculus
22
Navicula minima
Navicula slesvicensis
Navicula tenelloides
Navicula tripunctata
Nitzschia linearis
Nitzschia palea
Planothidium lanceolatum
Reimeria sinuata
Rhoicosphenia abbreviata
Surirella brebissonii
Site 3
TDI=26.76
Achnanthidium minutissimum
Diatoma tenue
Encyonema silesiacum
Fallacia tenera
Fragilaria capucina
Gomphonema parvulum
Navicula cryptocephala
Nitzschia gracilis
Nitzschia linearis
Nitzschia palea
Nitzschia pusilla
Planothidium lanceolatum
Surirella brebissonii
Surirella minuta
23
APPENDIX 8
REFERENCES
European Communities Environmental Objectives (Surface Water) Regulations 2009, S.I.
No. 272 of 2009, Dublin: Stationary Office.
Haslam SM, Sinker CS & Wolsey PA (1982). British Water Plants. Field Studies Council,
Nettlecombe, Taunton, Somerset.
Holmes, N., Newman, J., Chadd, S., Rouen, K., Saint, L. and Dawson, F. (1999). Mean
Trophic Rank: A User ’s Manual. R&D Technical Report E38. Environment Agency, UK.
Kelly, M.G. (2000). Identification of common benthic diatoms in rivers. Field Studies. 9,
583-700.
Kelly, M.G. (2003). Short term dynamics of diatoms in an upland stream and implications
for monitoring eutrophication. Environmental Pollution. 125, 117-122.
Kelly, M.G., Adams, C., Graves, A.C., Jamieson, J., Krokowski, J., Lycett, E.B., Murray-
Bligh, J., Pritchard, S. and Wilkins, C. (2001). The Trophic Diatom Index: A user’s manual,
Revised ed., Bristol, U.K.: Environmental Agency.
Kelly, M.G., Juggins, S., Guthrie, R., Pritchard, S., Jamieson, J., Rippey, B., Hirst, H. and
Yallop, M. (2008). Assessment of ecological status in U.K. rivers using diatoms. Freshwater
Biology. 53, 403-422.
Kelly-Quinn, M., Bradley, C., Dodkins, I., Harrington, T.J., Ní Chathain, B., O’Connor, M.,
Rippey, B., and Trigg, D. (2005) Water Framework Directive- Characterisation of reference
conditions and testing of typology of rivers (2002-W-LS-7). Wexford, Ireland: Environmental
Protection Agency.
Toner, P., Bowman, J., Clabby, K., Lucey, J., McGarrigle, M., Concannon, C., Clenaghan,
C., Cunningham, P., Delaney, J., O’Boyle, S., MacCárthaigh, M., Craig M. and Quinn, R.
(2005). Water Quality in Ireland 2001-2003. EPA.
Taxonomic Keys used for Macroinvertebrate Identification:
Chironomidae: Wiederholm, T. (1983). Chironomidae of the Holarctic Region.
Ent. Scan. Suppl. 19
Coleoptera, Larvae: Richoux, P. (1982). Introduction Pratique a la Systematique des
Organismes des eaux continentales Françaises. Bull. Soc. Linné.
Lyon 51; 114-128
Coleoptera, Adults: Friday, L.E. (1988). A Key to the Adults of British Water Beetles.
Field Studies Council Publication 189.
24
Ephemeroptera: Elliott, J.M., Humpesch, U.H. and Macan, T.T. (1988). Larvae of
the British species of Ephemeroptera. Sci. Publ. Freshwat. Biol.
Assoc. 49.
Gastropoda: Macan, T.T. (1977). British fresh- and brackish- water gastropods.
Sci. Publ. Freshwat. Biol. Assoc. 13
Bivalvia Killeen, I., Aldridge, D. and Oliver, G. (2004) Freshwater bivalves
of Britain and Ireland. Field Studies Council Occasional
Publication 82.
Hirudinae: Mann, K.H. (1964). A Key to the British freshwater leeches. Sci.
Publ.Freshwat. Biol Assoc. 14
Malacostraca: Glendhill, T., Sutcliffe, D.W. and Williams, W.D. (1993). British
Freshwater Crustacea Malacostraca: A Key with Ecological Notes.
Sci. Publ. Freshwat. Biol Assoc. 52
Oligochaeta: Brinkhurst, R.O. (1971). A guide to the identification of aquatic
oligochaetae. Sci. Publ. Freshwat. Biol Assoc. 22
Plecoptera: Hynes, H.B.N. (1977). A key to the adults and nymphs of the
British stoneflies (Plecoptera). Sci. Publ. Freshwat. Biol. Assoc. 17
3rd ed.
Trichoptera: 1. Edington, J.M. and Hildrew, A.G. (1995). A key to the caseless
caddis larvae of the British Isles. Sci. Publ. Freshwat Biol Ass. 53
2. Wallace, I.D., Wallace, B. and Philipson, G.N. (2003). Keys to
the case-bearing caddis larvae of Britain and Ireland. Sci Publ.
Freshwat. Biol. Assoc. 61
Biological Water Quality Assessment of the Rossestown
Stream Upstream and Downstream of a Discharge from
Lisheen Mine
April 2013
Prepared by:
Pascal Sweeney M.Sc., MCIEEM,
Consultant Ecologist
Rahan,
Mallow
Co. Cork. Tel. 022/26780
2
TABLE OF CONTENTS
Page
SECTION 1 INTRODUCTION 3.
SECTION 2 METHODOLOGY 3.
SECTION 3 RESULTS 5.
SECTION 4 CONCLUSIONS 8.
SECTION 5 REFERENCES 8.
Appendix 1 PHOTOGRAPHS 9.
3
1. INTRODUCTION
The purpose of the present report by Pascal Sweeney, Consultant Ecologist, is the biological
assessment of water quality in the Rossestown Stream upstream and downstream of a discharge
from Lisheen Mine that enters this watercourse at ING S2020 6926. The survey is designed to
assess the current biological water quality, based on macroinvertebrate communities.
2. METHODOLOGY
2.1 Choice of Sampling sites.
Field work was carried out on 26th
April, 2013. The stream was first surveyed to establish the
most appropriate locations with instream habitat suitable for the application of the Q-scheme
methodology. Two biological sampling sites were chosen, one upstream and one downstream of
the Lisheen Mine discharge.
2.2 Habitat Assessment.
Habitat assessment was carried out at each of the sites in terms of:
Stream width and depth.
Substrate type, listing substrate fractions in order of dominance.
Flow type, listing percentage of riffle, glide and pool in the sampling area.
Instream vegetation, listing plant species occurring and their percentage coverage of the
stream bottom at the sampling site.
4
Dominant bankside vegetation, listing the main species overhanging the stream.
Estimated summer cover by bankside vegetation.
Grid references were recorded at all sites using a GARMIN GPS 12 handset.
To illustrate habitat quality, photographs were taken using an Olympus µ300 digital camera.
2.3 Invertebrate Sampling and Biological Water Quality Assessment.
A pond net invertebrate sample was taken at each site using standard methodology employed by
EPA. Samples were retained in plastic containers at the sampling site. Sample processing and
preservation was carried out under laboratory conditions within 24 hours of sampling. Silt was
removed from each sample by sieving under running water through a 500μ sieve. Sieved samples
were then live sorted for 30 minutes in a white plastic sorting tray under a bench lamp.
Macroinvertebrates were stored in 70% alcohol. Preserved invertebrates were identified to the
level required for the EPA Q-rating method (Toner et al, 2005) using dissecting and compound
binocular microscopes, as necessary. The Q-scheme biological assessment procedure used by the
Environmental Protection Agency was then applied to the results.
5
3. RESULTS
3.1 Physical Data
The physical data recorded at each site are presented in Table 1.
TABLE 1
Site 1 Site 2
Location Rossestown Stream, c. 600m
upstream of discharge.
Rossestown Stream, c. 80m
downstream of discharge.
Grid Reference S2080 6925 S7143 2212
Nearest EPA
Sampling Site
At 16/R01/0020 Just downstream of
16/R01/0040
Photograph No. 1 2
Width (m.) 2-4m 3m
Sampling Depth (cm.) 30 40
Substrate
Composition (in order
of occurrence)
1. Peat silt
2. Cobble
3. Gravel
1. Gravel
2. Silt
3. Cobble
Flow Type Fast Glide: 100% Fast Glide: 100%
Summer shade Light Moderate
Dominant Bankside
Vegetation
Alder, grasses, sedges,
reedmace.
Willow, alder
3.2 Instream plants
Percentage cover of the substratum by plants at each site is given in Table 2.
TABLE 2
Site 1 Site 2
Filamentous algae <5% <5%
Sparganium erectum 5%
6
3.3 Macroinvertebrate Community Analysis by Site.
The numbers of individuals of each macroinvertebrate taxon sorted in 30 minutes from samples
taken at the two sites are given in Tables 3 and 4.
TABLE 3
SITE 1
INDICATOR GROUP
POLLUTION SENSITIVITY/TOLERANCE
TAXON NUMBER
A Very Pollution Sensitive None Recorded
B Moderately Pollution Sensitive
Leuctra sp. 2
Sericostomatidae 7
Lepidostomatidae 1
Goeridae 1
Limnephilidae 27
Phrygaenidae 1
C Moderately Pollution Tolerant Hydracarina 2
Gammarus duebeni 52
Baetis rhodani 2
Tipulidae 3
Chironomidae (ex. Chironomus)
1
D Very Pollution Tolerant Pisidium sp. 23
Asellus sp. 19
E Most Pollution Tolerant None recorded
Taking the physical habitat into account, the good representation of Group B taxa, including one
stonefly species, combined with the absence of Group E and Group D not excessive, this fauna
warrants a Q-value of Q3-4. Heavy siltation with fine peat material undoubtedly limits the
presence of mayfly and stonefly nymphs. Therefore the suffix * is added.
Q3-4* indicates Moderate Ecological Quality, with a siltation effect.
7
TABLE 4
SITE 2
INDICATOR GROUP
POLLUTION SENSITIVITY/TOLERANCE
TAXON NUMBER
A Very Pollution Sensitive None Recorded
B Moderately Pollution Sensitive
Sericostomatidae 13
Limnephilidae 2
Glossosomatidae 1
C Moderately Pollution Tolerant Hydracarina 7
Gammarus duebeni 50
Hydropsychidae 3
Polycentropodidae 1
Elmidae 25
Gyrinidae 4
Tipulidae 7
Chironomidae (ex. Chironomus)
2
D Very Pollution Tolerant Pisidium sp. 109
Asellus sp. 12
E Most Pollution Tolerant Tubificidae 2
The instream habitat at Site 2 is better suited to the Q-scheme methodology than that at Site 1.
However, it is still not an eroding riffle site and allowance must be made for this when analysing
the faunal composition.
As at Site 1, Group A is absent. Group B is less well represented, with no stonefly nymphs. The
fauna is dominated by Group D and Group E has a low representation. Q3 is therefore ascribed.
Q3 indicates Poor Ecological Quality.
8
4. CONCLUSIONS
From Site 1 to Site 2, the invertebrate fauna of the Rossestown Stream currently shows a slight
drop in biological water quality, by half a Q-value.
5. REFERENCES
Toner et al (2005) Water quality in Ireland 2001 – 20003. Environmental Protection Agency.
APPENDIX I
Photo 1: Site 1, upstream.
Photo 2: Site 2, downstream.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1
Table of Contents
5.0 SOILS AND GEOLOGY ............................................................................................................................................. 1
5.1 Introduction ................................................................................................................................................... 1
5.2 Methodology ................................................................................................................................................. 1
5.3 Previous work ............................................................................................................................................... 1
5.4 Existing Environment .................................................................................................................................... 2
5.4.1 Topography ............................................................................................................................................. 2
5.4.2 Overburden ............................................................................................................................................. 2
5.4.3 Bedrock geology ..................................................................................................................................... 2
5.4.4 Structural geology ................................................................................................................................... 2
5.4.5 Seismicity ................................................................................................................................................ 2
5.4.6 Description of geological attributes ......................................................................................................... 3
5.5 Assessment .................................................................................................................................................. 3
5.5.1 Embankment stability modelling .............................................................................................................. 4
5.6 Mitigation ...................................................................................................................................................... 6
5.7 Residual Effects ............................................................................................................................................ 6
5.8 References ................................................................................................................................................... 7
TABLES
Table 5.1: Importance of Geological Attributes in Vicinity of the Application Site ................................................................ 3
Table 5.2: Significance of Impacts on Soil and Geology ..................................................................................................... 4
Table 5.3: Geotechnical Parameters for Stability Analysis .................................................................................................. 5
Table 5.4: Stability Modelling Results ................................................................................................................................. 5
FIGURES
Figure 5.1: Soil Classification (Source: GSI)
Figure 5.2: Sub-soil Classification (Source: GSI)
Figure 5.3: Bedrock Classification (Source: GSI)
APPENDICES
APPENDIX 5.1 Stability Analysis
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 1
5.0 SOILS AND GEOLOGY
5.1 Introduction
This Chapter of the Environmental Impact Statement considers and assesses any potential impact resulting
from the proposed modification of the permitted water impoundment facility on the surrounding soils and
geology environment. It is noted that the proposed activity at the Application Site will involve a modification
from storage of water only, to storage of tailings and water, resulting in an extension to the existing tailings
management facility (TMF).
The proposed modification activities to provide an extension of the existing tailings facility will consist of two
main phases:
Operational Phase - this will involve the placement of tailings over a c. 12 month period to a final
level of c. 130.5 mOD. Tailings are placed via a spigot pump as is the case in the existing TMF.
The spigots will be opened sequentially and the tailings will be discharged uniformly over the new
TMF cell; and
Closure Phase – The cell will then be capped with approximately 700 mm of Type B material as
constructed on the existing TMF together with 300 mm of growing material consisting of 50% peat
and 50% soil. The procedure will be the same as currently undertaken on the existing TMF facility
(see Chapters 2.0 and 12.0).
The most likely emission to the soils and geology environment is the potential for release of contamination
into the underlying subsurface, through the base or sides of the permitted impoundment facility, once storage
of tailings commences. Other potential impacts include effects on the soils and geology environment during
capping activities. The following Chapter provides details on the baseline environment, an assessment of
potential impacts, and mitigation measures to address identified impacts. It is noted that further details on
the proposed modification activities are included in Chapter 2.0, and potential water impacts are addressed
in Chapter 6.0 of this EIS. Closure activities are detailed in Chapter 12.0 of this EIS.
5.2 Methodology
The geological information described in this Chapter is based on data gleaned from the Geological Survey of
Ireland (GSI) publication entitled Geology of Tipperary, and its accompanying map (Sheet 18) (GSI, 1996).
Additional data has been taken from other works previously undertaken at, and in the vicinity of the Site. A
site walkover was completed by a senior Golder geologist, and discussions were undertaken with the
Lisheen Mine geology department. Additional detailed information has also been taken from online data
(www.gsi.ie).
In order to assess impacts on the soil and geology, ‘Guidelines for the Assessment of Geology, Hydrology
and Hydrogeology for National Road Schemes’ published by the National Roads Authority (2009) has been
referenced.
5.3 Previous work
Previous studies have been prepared for the existing TMF (Planning Study, 1995; Golder Associates (UK)
Ltd., 1997, Report No. 96512126), and additional site investigation work was also undertaken at the location
of the permitted water impoundment facility in advance of construction activities to confirm ground
conditions.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 2
5.4 Existing Environment
5.4.1 Topography
The Application Site is approximately 2 km east-south-east of the Lisheen Mine orebodies, and 12 km
northeast of Thurles, Co. Tipperary. The general area around the application site is underlain by peat
deposits, with agricultural farmland to the south west. The footprint of the permitted cell is c. 9 ha. in area,
with an internal storage area of c. 6.15 ha. and a capacity of 390,000 m3.
5.4.2 Overburden
The Quaternary deposits of the regional area were described by Coxon and Delaney (1991) as:
– “very variable over the whole area but nowhere does it appear to be extensive or thick except
possibly below some of the poorly drained zones occupied either by marginal (in places reclaimed)
land or bog. Till cover is uniformly thin on higher ground with only 1 or 2 metres of sandy diamicton
containing predominantly local clasts (i.e. >80% limestone). Over much of the area till forms only the
basal part of the rich brown earth soil of the region.”
General details of the soils and sub-soils in the vicinity of the Application Site are included in Figures 5.1 and
5.2 attached. Within the vicinity of the Application Site, above the bedrock is a thin layer of glacial till
generally varying in thickness from 0.5 m to 3.0 m (Planning Study, 1995; Golder Associates (UK) Ltd., 1997,
Report No. 96512126), typically consisting of clayey silty sands and gravels and gravelly sandy silts.
5.4.3 Bedrock geology
The GSI publication (Geology of Tipperary) and its accompanying geological map, Sheet 18, indicate that
the Lisheen Mine site falls within Waulsortian Limestones of Lower Carboniferous age. These rocks are
common throughout Ireland, and the general description of the Formation is of pale-grey, sparry, fossiliferous
(bryozoan) poly-mud micritic limestones, often massive knoll forms, with cinoidal or pale cherty shaly
interbeds, frequently dolomitised.
However, the rocks in the vicinity of the Application Site are at or close to the base of Waulsortian Limestone
Formation and are dolomitised. These limestones are reported to range from 30 to 80 m in thickness at the
Application Site, with an upper dolomitised section.
Rocks of the Ballysteen Formation underlie the Waulsortian Limestones. This formation consists of dark
grey bioclastic, wackstone, packstone and grainstone, shale-parted limestones, and the formation becomes
increasingly muddy upwards. The bedrock geology is shown in Figure 5.3.
5.4.4 Structural geology
The major structural elements of the regional sub-surface geology are shown in Figure 5.3.
The mining area is located on the Rathdowney Trend, which is a 40 km belt of Lower Carboniferous
limestones and dolostones stretching between Thurles and Abbeyleix (Robertson and Kirsten, 1995). Within
this trend, close to Lisheen, a major fault zone known as the Killoran-Derryville Fault is present.
A series of north-south trending faults offset the Waulsortian Limestones with the Crosspatrick Formation,
and to the south of the Site, a series of East-west trending faults offset the Waulsortian Limestones and the
Ballysteen Formation.
5.4.5 Seismicity
Ireland has low level seismic activity, and there have been no known occurrences of severe earthquakes
over the past 1,000 years. The largest earthquake in recent times was the magnitude 5.4 earthquake in
Wales in 1984, which is approximately 400 km from the Application Site. A peak horizontal ground
acceleration of 0.16 g, representing a 1 in 10,000 year event (Maximum Credible Earthquake, MCE) has
been used in stability calculations, as per the original TMF (Robertson & Kirsten, 1995).
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 3
5.4.6 Description of geological attributes
The evaluation of impacts on the soil and geology at and in the vicinity of the Application Site is based on a
methodology similar to that outlined in the ‘Guidelines for the Assessment of Geology, Hydrology and
Hydrogeology for National Road Schemes’ published by the National Roads Authority (2009).
The importance of existing soil and geology attributes identified above is assessed in Table 5.1 below.
Table 5.1: Importance of Geological Attributes in Vicinity of the Application Site
Attribute Status Occurrence
Geohazards/Geotechnical The Application Site is located in an area of low seismic activity.
Low
Geological Heritage
The application site is located within Derryville Bog, which is part of the Erill-Urlingford Bog (Steffen, Robertson & Kirsten (Canada Inc), 1995).
High
Economic Geology
The Application Site is located within an area of high economic geology, however it is noted that the 4 main Lisheen ore bodies are located some distance away from the Application Site.
Low
Agricultural Soils The Application Site is a permitted water impoundment facility, with no presence of agricultural soils within the structure.
Low
Made Ground The Application Site is a permitted water impoundment facility, with made-ground making up the majority of the structure.
High
5.5 Assessment
The significance of potential impacts on the receiving soil and geology environment as a result of this
proposed modification application are summarised in Table 5.2 below. Further details are then provided on
embankment stability of the structure.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 4
Table 5.2: Significance of Impacts on Soil and Geology
Attribute Status Magnitude of Impact
Geohazards/Geotechnical
The design of the permitted structure incorporates a composite liner, comprising rockfill and a high density polyethylene liner (Section 2.0).
Regarding integrity of the structure’s embankments, an analysis on slope stability has been undertaken. Details are provided in Section 5.5.1 and Appendix 5.1 attached.
Small adverse
Geological Heritage
The permitted water impoundment facility proposed for modification is previously permitted under Ref. No. PLC17663 and ABP No. PL22.100093.The proposed modification application from storage of water to storage of tailings and water will not have an impact on the integrity of the Derryville Bog complex.
Negligible
Economic Geology
The proposed modification activities will facilitate the continued extraction of ore from the Lisheen Mine for an additional 12 months.
Major beneficial
Agricultural Soils
The capping materials proposed for restoration of the new cell will consist of the re-use of excavated peat and glacial till, sourced from stockpiles on the Lisheen Mine site (previously permitted activities under Ref. No. PLC17663 and ABP No. PL22.100093). This will result in an additional c. 6.15 ha. of agricultural farmland (or other use as agreed and adopted in the CRAMP) upon restoration and closure (Chapter 12.0).
Minor beneficial
Made Ground
The proposed modification application will have no impact on the made ground status of the permitted water impoundment facility.
Rockfill for the cap will be sourced from the Carrick Hill borrow source (previously permitted under Ref. No. PLC17663 and ABP No. PL22.100093).
Negligible
5.5.1 Embankment stability modelling
A stability analysis for the permitted water impoundment facility was carried out using commercially available
limit-equilibrium slope stability software, SLOPE/W version 7.15. The analytical method used was the
Morgenstern and Price Method of Slices, which satisfies both force and moment equilibrium. The stability
analysis indicates that the Factor of Safety (FoS) for the dam walls is adequate under the modelled
conditions. Details of the modelling approach and the results are presented below.
Model Geometry
The model geometry is shown in Appendix 5.1 and is based on a typical cross-section of perimeter wall for
the facility. The permitted water impoundment facility embankment height is approximately 11.5 m above the
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 5
glacial till foundation level. The modelled sub-surface conditions are based on the geotechnical investigation
information at the site.
Geotechnical Parameters
The geotechnical strength parameters adopted in the stability modelling are presented in the following
Table 5.3.
Table 5.3: Geotechnical Parameters for Stability Analysis
Material Type Unit Weight (kN/m3)
Effective Strength
c' (kPa) ø' (deg)
Type B 21 0 35
Type C 21 0 33
Tailings 18 0 32
Glacial Till 20 5 30
Limestone* - - -
*Limestone was considered bedrock and impenetrable by slope failure.
Effective strength parameters are typically used to assess long-term stability (after closure), whereby the
excess pore pressures developed in any fine grained soils have dissipated.
Stability Modelling
The stability of the permitted water impoundment facility wall for each case scenario was considered under
the following conditions:
Case 1: Long-term downstream embankment stability, with tailings level 1 m below the crest. The
HDPE liner was assumed to be intact and an assumed phreatic surface was drawn down through the
embankment by the free draining rockfill;
Case 2: Long-term downstream embankment stability, with tailings level 1 m below the crest. The
HDPE liner was considered to undergo complete failure and the rockfill was no longer free draining and
the phreatic surface exits the dam wall in the slope at one third of its height. This is a very extreme
scenario which is unlikely to develop; and
Case 3: Further analyses were undertaken using pseudo static conditions corresponding to 0.16 g
acceleration for Case 1.
Results of Stability Modelling
The results of the stability analyses are presented in Table 5.3 below in the form of the FoS for the most
critical slip surface. The required minimum FoS was exceeded under all conditions analysed. The stability
models are as presented in Appendix 5.1.
Table 5.4: Stability Modelling Results
Case Condition Location FoS
1 Long-term, tailings 1 m below crest, liner intact. Static condition. Downstream 1.9
2 Long-term, tailings 1 m below crest, complete failure of liner system, phreatic surface exits 1/3 dam height. Static condition.
Downstream 1.4
3 Long-term, tailings 1m below crest. Ground Acceleration 0.16 g. Pseudo static condition.
Downstream 1.4
The factor of safety for the static and pseudo static cases are satisfactory. Because the dam wall is
constructed of rockfill, then there is no detrimental effect on stability by failure of the lining.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 6
5.6 Mitigation
The following mitigation measures have been adopted for the proposed modification activities, to reduce and
mitigate potential impacts of the receiving soils and geology environment:
Growth media proposed for the final cap is reuse material, sourced from on-site peat and glacial till
stockpiles resulting from previously permitted activities at the Lisheen Mine site;
Construction materials for the rockfill cap upon closure will be sourced from an existing borrow source;
Embankment stability modelling has been undertaken on the permitted water impoundment structure to
ensure it will perform within satisfactory factors of safety, with the results being equally applicable for
the storage of tailings; and
The TMF will be returned to productive agricultural grassland or other use as agreed and adopted in the
Closure, Restoration and Aftercare Management Plan (further details in Chapter 12.0).
In addition, the following mitigation measures have and will continue to be employed during the
capping/restoration activities at the Application Site:
All refuelling of mobile plant to be undertaken with care on designated fuelling areas;
Any processing plant and/or mobile plant on the Site be regularly maintained, and where plant is
damaged or leaking, this will be dealt with as part of on-going operational management of the Site;
Maximise non-economic materials in restoration and closure activities;
Lisheen Mine will ensure compliance with relevant safety and statutory legislation and best practices
recommended by the EPA and other statutory bodies during the proposed placement of tailings and
subsequent capping operations to mitigate any potential impacts on the soils and geology receiving
environment; and
All proposed modification activities will be undertaken in compliance with the IPPC Licence Ref. No.
P0088-03, and extant planning permissions.
5.7 Residual Effects
The construction of a new tailings cell will provide additional storage for the tailings being produced at the
Lisheen Mine, until its proposed closure date in spring 2015. The lead and zinc ore extracted from Lisheen
has been used as raw materials worldwide which is considered an acceptable use of the resource. The
additional tailings storage will allow the remaining underground ore to be recovered, and will provide
additional tailings storage capacity while the existing TMF is progressively restored. The new extension cell
will then itself be capped and restored in a similar fashion (Chapter 12.0).
In the long term, no deleterious effects on the remaining overburden or bedrock caused by the proposed
modification activities on-site are expected, once the restoration and closure activities proposed in Chapters
4.0 (Flora and Fauna), 6.0 (Water) and 12.0 (Closure) are undertaken.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1 7
5.8 References
Geological Survey of Ireland website, www.gsi.ie; online mapping services.
Geological Survey of Ireland (1996). The Geology of Tipperary: A Geological Description, with
accompanying Geology 1:100,000 Scale Map, Sheet 18 Geology of Tipperary. GSI Publications.
Planning Study, Tailings Management Facility, Technical Report. December 1995.
Golder Associates (UK) Ltd. Report No. 96512126 Lisheen TMF Detailed Design. November 1997.
Steffen, Robertson & Kirsten (Canada Inc). 1995. Lisheen Project, Ireland – Planning Study, Tailings
Management Facility Technical Report.
National Roads Authority (2009). Guidelines on Procedures for Assessment and Treatment of Geology,
Hydrology and Hydrogeology for National Road Schemes.
Golder 1998b, Report No. 97512347 – Volume 5.
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1
FIGURES
TLs Cut
A
GLs
RckCa
LMade
BasEsk
Mrl
0 1,000 2,000500Meters
5.1 V.1Golder Associates (IRL) Ltd
Town Centre HouseDublin Road
NaasCo. Kildare
Tel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
KMG CWAR0056013 11 5071 5 0226
A4 1:50,000
CW AUGUST 2013
LegendApplication Site BoundaryLands Under Control of the Applicant
A.0
A
BasEsk
Cut
FenPt
GLs
L
Made
Mrl
RckCa
TLs
OSI Tile Purchased - 04/04/2013Discovery Series 60
2N
Lisheen Milling Ltd.
Planning Application
Soil Classification (Source: GSI)
TLs
Cut
A
GLs
Mrl
L
Rck
Made
BasEsk
5.2 V.1Golder Associates (IRL) Ltd
Town Centre HouseDublin Road
NaasCo. Kildare
Tel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
KMG CW CW AUGUST 2013
AR0056013 11 5071 5 0226
A4 1:50,000
OSI Tile Purchased - 04/04/2013Discovery Series 60
LegendApplication Site BoundaryLands Under Control of the Applicant
A
BasEsk
Cut
FenPt
GLs
L
Made
Mrl
Rck
TLs
Lisheen Milling Ltd.
Planning Application
Sub-soil Classification (Source: GSI)
0 1,000 2,000500Meters
2N
A.0
CDWAULdo
CDCROS
CDWAUL
CDBALL
CDAGHM
CDBALLO
0 1,000 2,000500Meters
5.3 V.1Golder Associates (IRL) Ltd
Town Centre HouseDublin Road
NaasCo. Kildare
Tel: 045 874411
Drawing No. Rev
Size Scale Status
OS Licence No. Project No.
Created by DateRequested by Approved by
Title
Project
Client
KMG CW CW AUGUST 2013
AR0056013 11 5071 5 0226
A4 1:50,000
CDAGHM - Darh shaly micrite, peloidal limestoneCDBALL - Dark muddy limestone, shaleCDBALLO - Oolitic limestonesCDCROS - Pale-grey crinoidal limestoneCDWAULdo - Dolomitised massive fine grained limestone
LegendApplication Site BoundaryLands Under Control of the Applicant
A.0
OSI Tile Purchased - 04/04/2013Discovery Series 60
Lisheen Milling Ltd.
Planning Application
Bedrock Classification (Source: GSI)
2N
CHAPTER 5.0 SOILS AND GEOLOGY
August 2013 Report No. 11507150226.R01.5.A1
APPENDIX 5.1 Stability Analysis
APPENDIX 5.1 Stability Analysis
August 2013 Project No. 11507150226.R01.5.1.A1 1/2
1.9
Material Properties
#1Type B 21 kN/m³0 kPa37 °
#2Glacial Till 20 kN/m³5 kPa35 °
#1
Lisheen Adjoining CellStage 1 Stability Analysis
Case 1:Long-term Downstream Embankment StabilityHDPE Liner Intact
#3Tailings 18 kN/m³0 kPa32 °
#4Type C 21 kN/m³0 kPa35 °
#2
#3
#4
1.4
Material Properties
#1
Type B
21 kN/m³
0 kPa
37 °
#2
Glacial Till
20 kN/m³
5 kPa
35 °
#1
Lisheen Adjoining CellStage 1 Stability Analysis
Case 2:Long-term Downstream Embankment StabilityHDPE Liner Failure
#3
Tailings
18 kN/m³
0 kPa
32 °
#4
Type C
21 kN/m³
0 kPa
35 °
#2
#3
#4
APPENDIX 5.1 Stability Analysis
August 2013 Project No. 11507150226.R01.5.1.A1 2/2
1.4Material Properties
#1
Type B
21 kN/m³
0 kPa
37 °
#2
Glacial Till
20 kN/m³
5 kPa
35 °
#1
Lisheen Adjoining CellStage 1 Stability Analysis
Case 3:Long-term Downstream Embankment StabilityPseudo-Static - 0.16g Ground Acceleration
#3
Tailings
18 kN/m³
0 kPa
32 °
#4
Type C
21 kN/m³
0 kPa
35 °
#2
#3
#4