Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Environmental Compliance Monitoring Report
Semi-Annual Report
Project Number: 44214-024
Grant Number: 0357-NEP
July 2020
Nepal: Building Climate Resilience of Watersheds in
Mountain Eco-Regions Project
Prepared by the Government of Nepal for the Asian Development Bank.
This environmental Compliance Monitoring Report is a document of the borrower. The views expressed herein do
not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in
nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference
to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make
any judgments as to the legal or other status of any territory or area.
Government of Nepal Department of Forests and Soil Conservation Building Climate Resilience of Watersheds in Mountain Eco-Regions (BCRWME) Project (ADB Loan/Grant No.: GO357/0358-NEP)
Semiannual Environemntal Monitoring Report of BCRWME Sub-projects
(January to June 2020)
Preparaed By
BCRWME Project Project Management Unit
Dadeldhura
July, 2020
i
ABBREVIATION
ADB : Asian Development Bank
BCRWME : Building Climate Resilience of Watersheds in Mountain Eco- Regions
BOQ : Bills of Quantity
CDG : Community Development Group
CFUG : Community Forest User Group
CO : Community Organizer
CPC : Consultation, Participation and Communications (Plan)
CS : Construction Supervisor
DDR : Due Diligence Reports
DFO : Division Forest Office
DFSC : Department of the Forests and Soil Conservation
DSCO : District Soil Conservation Office
EARF : Environmental Assessment and Review Framework
EIA : Environmental Impact Assessment
EO : Environment Officer
FAC : Feasibility Approval Committee
FTT : Field Technical Team
GRC : Grievance Redress Committee
GoN : Government of Nepal
Ha : Hectare
IEE : Initial Environmental Examination
MoFE : Ministry of Forests and Environment
NCB : National Competitive Bidding
NDF : Nordic Development Fund
NES : National Environmental Specialist
O& M : Operation and Maintenance
PAM : Project Administrative Manual
PCR : Project Completion Report
PIU : Project Implementation Unit
PMIC : Project Management Implementation Consultant
PMU : Project Management Unit
PS : Post Support
REA : Rapid Environmental Assessment
RVT : Reservoir Tank
SES : Senior Environment Specialist
SEMR : Semiannual Environment Monitoring Report
SP : Subproject
SPPR : Subproject Preparation Report
SWMC : Sub-watershed Management Committee
VDC : Village Development Committee
WMA : Watershed Management Associate
WME : Watershed Management Engineer
ii
EXECUTIVE SUMMARY
Building climate Resilience of Watersheds in Mountain Eco-Regions Project being implemented by the
Department of the Forests and Soil Conservation with grant assistance from Asian Development
Bank, Nordic Development Fund and Government of Nepal intends to improve access to and
reliability of water supplies to communities living in watershed vulnerable to the impacts of climate
change. The project has considered environment safeguard to address environmental issues of
subprojects implementation. The project has an environmental assessment review framework that
specifies subprojects selection procedures, subproject’s environment categorization, environment assessment procedure, community consultation, grievance redress mechanism and mechanism for
environment monitoring and reporting.
There are 108 SPPRs (Batch I-8, Batch II-20, batch II-40 and Batch IV-40) and all of them are category
C projects. The environmental safeguard requirements of GoN and ADB are satisfactorily addressed
in SPs planning and implementation stages. The project has adopted procedural requirements such as
environmental screening, SPs categorization, due diligence report inclusion, community consultation,
voluntary land donation documents during sub-project preparation report (SPPR) preparation and
approval process. No violations of local traditions and culture, no resettlement of indigenous people,
worker’s safety, avoidance of under aged workers, community consultations, slope stabilization,
minimizing trees cutting (if unavoidable), quarry site management, spoil management are considered
during implementation of SPs. The project has the provision an environment officer (a government
deputed soil conservation officer) and an intermittent input of senior environment specialist (SES) to
take care the safeguard issues of the project implementation.
Environment compliance status of the subprojects during January-June, 2020. Preparation of 108
DDRs and inclusion of 515 numbers of voluntary land donation documents were already completed.
About 378 subproject level meetings and 1077 ward level consultations were conducted during
planning stage. Quarry site management, burrow pit management, spoils management, soil erosion
and landslide control are adopted in SPs implementation. For 108 subprojects, aabout 302 m of brush
layering, 1965 m of check dam and 11230 m of live fencing were done till reporting period. Bamboos
are planted in an area of 121 ha for bio-engineering purpose to control erosion. To stabilize the land,
6357 units (2×1×1 m3 or 3×1×1 m3 per unit) of gabion wall are used to protect source water. It is
reported that 55,078 winter plantation, 261882 fruit trees and 2188353 fodder species, 455823
forestry species were planted in 108 SPs till June, 2020. Cultivation of 1893039 numbers of grasses is
reported. To increase the ground recharge, the SPs have also constructed 11230 recharge pits, 157
recharge ponds, 21 conservation ponds. No involuntary land acquisition, resettlement issues, social
conflicts, child labour were noticed during SPs implementation. No safeguard related grievance is
received till date.
The SPs have great environment benefits in terms of catchment management, ground water recharge,
surface water management, water source protection, land stabilization and erosion control. Caring
of planted trees, considering grazing alternatives, safety measures and coordination with other
government bodies should also be considered during implementation stage. Preparation of
environment safeguard guidelines, training on safeguard monitoring and reporting to project staffs
and preparation of environment code of practices should be considered during initial phase of the
project.
iii
Table of Contents
Abbreviation……………………………… ............................................................................................. i
Executive Summary…………………………….. ................................................................................... ii
1. Background………………………… ............................................................................................ 1
2. Environment Safeguard in The BCRWME Project ....................................................................... 2
3. Construction Approach……………. ........................................................................................... 2
4. Overall Environmental Safeguard Status ....................................................................................... 3
5. Compliance Status with Environmental Covenants ...................................................................... 3
6. Institutional Arrangement…………………….. ........................................................................... 4
7. Environment Monitoring and reporting mechanism ..................................................................... 4
8. Compliance with Environmental Safeguard Measures .................................................................. 5
8.1 During Planning and Approval Phase ...................................................................................... 5
8.1.1 Environment Screening and SP categorization, environment assessment ..................... 6
8.1.2 Project Procedural Requirement ................................................................................... 6
8.1.3 Rapid Environment Assessment and Due Diligence Report ......................................... 7
8.1.4 Environmental officers ................................................................................................... 7
8.1.5 Grievance redress mechanism and Environment safeguard desk ................................. 7
8.1.6 Community consultation and downstream users’ consent ........................................... 7
8.1.7 Land Donation ............................................................................................................... 7
8.1.8 Trainings ......................................................................................................................... 7
8.1.8 Environment management related activities .................................................................. 8
8.2 During Implementation Stage .................................................................................................. 8
8.2.1 Quarry Site and Burrow Pit Management ..................................................................... 8
8.2.2 Excess Spoil and excavated top soil management ......................................................... 9
8.2.3 Tree cutting and plantation ........................................................................................... 9
8.2.4 Soil erosion and landslide control ................................................................................. 9
8.2.5 Grazing land management .............................................................................................. 9
8.2.6 Catchment management .............................................................................................. 10
8.2.7 Water source protection ............................................................................................ 10
8.2.8 Irrigation Pond and Cattle Ponds ................................................................................ 10
8.2.9 Impact in Forest ........................................................................................................... 10
8.2.10 Waste management and Environment sanitation ...................................................... 11
8.2.11 Downstream water use ............................................................................................. 11
8.2.12 Worker’s safety and Work Camp ............................................................................. 11
8.2.13 Land acquisition and impacts to indigenous people .................................................. 11
iv
8.2.14 Child labor ................................................................................................................. 11
8.2.15 Employment and wage discrimination ....................................................................... 11
8.2.16 Violation of laws and regulation of GoN ................................................................... 11
8.2.17 Field Visits by project team and SES .......................................................................... 12
8.2.18 Safeguard Training to Project Team (COs/CSs/FTTs/Environment Officer) ............ 12
8.2.19 Safeguard monitoring and reporting system .............................................................. 12
8.2.20 Grievance redress mechanism ................................................................................... 12
8.2.21 Replication of good practices .................................................................................... 12
9. Corrective action and recommendation .................................................................................... 13
List of Table
Table 1: Summary of planning stage safeguard compliance status .......................................................... 6
Table 2: Summary of Statistical information of the Subprojects during Implementation Stage ........... 10
Table 3 : Recommendations and Lessons Learned ............................................................................... 13
List of Figure
Figure 1: BCRWME Project Area in Far Western Province ............................................................ 1
Figure 2: Institutional arrangement for environment safeguard monitoring and reporting ...... 5
Annexes
Annex 1: Planning stage (Annex 1a) and Implementation stage (Annex 1b) environmental
compliance status (As of June, 2020)
Annex 2: Status of compliance with loan and grant covenants (As of June, 2020)
Annex 3: Photographs
1
1. BACKGROUND
Building climate Resilience of Watersheds in Mountain Eco- Regions (BCRWME) Project being
implemented by the Department of the Forests and Soil Conservation (DFSC) with grant
assistance from ADB, Nordic Development Fund and Government of Nepal intends to improve
access to and reliability of water supplies to communities living in watershed vulnerable to the
impacts of climate change. Access and reliability to water resources will be improved through a
participatory program of integrated watershed management with interventions in upland areas to
increase surface water storage and ground water recharge. The project will support communities
to manage catchment areas for development and protection of their water sources (springs and
streams). This will include (i) protection of the area surrounding the water source and preparation
and implementation of the water source catchment management plans, (ii) treatment of gully
erosion and slope/landslide stabilization that threatens the water sources, water infrastructure,
and beneficiary communities (iii) construction of water collection chambers, spring boxes or
infiltration galleries; (iv) construction of water conservation ponds and storage for irrigation and
livestock, and (v) construction of drinking water storage tanks and tap stands. The project will also
provide participating communities with education and facilitate programs on water conservation
practices (including micro-irrigation), methods for maintaining soil moisture in agriculture, grazing
and fodder management, and ways to regenerate vegetative cover. A total of 108 sub-projects
under the project are being implemented in six districts of the Lower West Seti and Budhi Ganga
watersheds of the Far Western Province of Nepal.
As per Safeguard Policy Statement of ADB (2009), the BCRWME Project is classified as
environmental category “B” Project, the semiannual environmental monitoring report has been
prepared for the January to June, 2020.
Figure 1: BCRWME Project Area in Far Western Province
2
2. ENVIRONMENT SAFEGUARD IN THE BCRWME PROJECT
The major objectives of the ADB on the environment are to incorporate environmental
component in development planning and integrate environmental safeguards across ADB
operations. The project has considered environmental component to address environmental
issues during SPs implementation. The project has an environmental assessment review
framework (EARF) that specifies sub-project (SP) selection procedures, SP’s environment categorization, environment assessment procedure, community consultation, grievance redress
mechanism, institutional arrangement for environment management. In order to address
environmental issues, the project has adopted/included formats of Rapid Environment
Assessment (REA) checklist and Environment Due Diligence Reports (DDRs) to be included
during Sub-project Preparation Report (SPPR) with compliance to both ADB’s and GoN’s environmental requirements. Environment is considered during selection of schemes, subprojects
and community actions, SPPRs preparation, approval of SPPRs by Feasibility Approval Committee
(FAC), agreement to Community Development Group (CDG) and SPs’ monitoring and reporting.
All SPs are screened for environmental impact and due diligence reports (DDRs) are prepared
and included in the SPPRs during planning stage. The project has the provision of Environment
Safeguard Desk and designated environment officers (EOs). To ensure the safeguard compliance,
the project has also the provision of intermittent inputs of senior environment specialist (SES) in
Project Management Implementation Consultants (PMIC) to train the project team and monitor
the quality of environmental screening reports, SPs categorization, due diligence reports and
environment management practice and preparing of semiannual environmental monitoring
reports along with biannual environment monitoring of SPs.
3. CONSTRUCTION APPROACH
The approach adopted a community-driven subproject ensuring a high level of public awareness
and their involvement in planning, implementation, operation, maintenance, protection and
benefit sharing of activities related to water access and reliability. The project applies the
community contract to execute, manage and supervise the SPs in close supervision and technical
guidelines from the PMU/PIU and PMIC. A Consultation, Participation and Communications Plan
(the CPC Plan) has been incorporated into project implementation guidelines. An Item rate
contract is adopted for civil works. Local materials for civil works such as boulder, sand, coarse
aggregates etc. were managed by the community as per requirement in the Bills of Quantities
(BOQs) of contract. Materials for civil works such as cement, steel bars, GI wire/ boxes, barbed
wire, HDP, GI pipes, pipe fittings etc. are procured by the PMU/PIU (earlier DSCO) from the
market/factory under the guidance and supervision of responsible PMIC technicians/engineers.
Similarly, material required for catchment restoration works are procured by concerned
PMU/PIU through standard ADB’s shopping methods and community contract is adopted in labor works only. Community participation/contribution is 20% of the catchment restoration works
(vegetative works).
3
4. OVERALL ENVIRONMENTAL SAFEGUARD STATUS
The environmental safeguard requirements of GoN and ADB are satisfactorily addressed in SPs
planning and implementation stages. The project had adopted procedural requirements such as
environmental screening, SPs categorization, DDR inclusion, community consultation, voluntary
land donation during SPPR preparation and approval process. The provision of catchment
restoration practices such as fodder/grass cultivation, trees plantation, recharge pit, conservation
pond, brush layering, check dam etc. were included in SPPRs. Similarly, the SPPRs had also
included the water source protection measures such slope and gullies stabilization etc.
There are 108 SPPRs (Batch I-8, Batch II-20, batch II-40 and Batch IV-40) and all of them are
category C projects. None of these SPs requires environment assessments (i.e. IEE and EIA). The
project itself is a climate resilient project; it has also included the environment management
related activities. The activities are performed to increase surface water storage, enhance soil
water and ground water recharge, stabilize slopes and gullies and reduce erosion. The project
has ensured that there are no violations of local traditions, culture and no resettlement of
indigenous people due to SP implementation. The project has considered the provision of
worker’s safety, avoidance of child labor, consent for utilizing water sources, slope stabilization
through engineering and bioengineering measures, quarry site, spoil and waste management.
No safeguard related grievance was reported during the reporting period of January to June,
2020. The project has prepared and adopted monitoring and reporting formats for safeguard
compliance monitoring. The project has strengthened environmental compliance monitoring and
reporting by structured formats, follow ups, feedbacks, orientations to the project team. The
SES, WME/WMA, EO, FTTs and CO/CS are involved in environment compliance monitoring.
The project has focused on quantitative information of environment aspects from civil work and
catchment restoration work such as conservation pond, recharge pit, cattle pond, irrigation pond,
tree loss, fruit trees plantation, grass/fodder cultivation, land stabilization, brush layering and
grievances etc. The project has also addressed the mission recommendations such as safeguard
training to CO/CS, GRC formation as per restructuring of local government, inclusion of
environment sections in other reports and environment component in PCR.
5. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS
There are 4 loan and grant covenants for environment safeguard specified for the project namely;
i. compliance with environment requirements, ii. human resource to implement safeguard
compliance, iii. provision of environment safeguard in bidding and contract documents, and iv.
safeguard related monitoring and reporting. For social safeguard, there are 3 loan and grant
covenants; namely i. voluntary land donation, ii. no involuntary resettlement of indigenous people
and iii. grievance redress mechanism1. Environmental and social safeguard covenants are
satisfactorily complied. (Refer Annex 2).
1 Formation of a project district level special committee for grievance redress were not accomplished due to restructuring of local bodies, however Rural/municipality level committees are existed to look after the projects including grievances
4
6. INSTITUTIONAL ARRANGEMENT
Regarding to the institutional arrangement, the project has established PMU in Dadeldhura under
Department of Forests and Soil Conservation (DFSC). MoFE has appointed a Class-II officer from
the DFSC as a Project Director to head the PMU. The PMU is responsible for coordination,
monitoring and evaluation of the SPs including environment safeguard compliance monitoring.
The PMU comprises government deputed staffs, mid-level technician and team of consultants
(PMIC, NDF-1 and NDF-II)) to implement the SPs. Similarly, the project has also established
project implementation unit (PIU) in Achham along with team of PMIC to implement, monitor of
SPs and to supervise FTTs. The PIU has designated a soil conservation officer as an environment
officer (EO). To ensure the safeguard compliance during planning and implementation stages, the
project has the provision of intermittent inputs of SES in PMIC.
At SP level, community development groups (CDGs) is established to link users of each scheme.
A subproject implementation committee, comprised of the chairpersons of each CDG, will be
established for each SP. PMU/PIU (earlier DSCOs) have engaged one CO and two CSs to monitor
and supervise SP implementation. CO will assist the FTTs in community mobilization, organization
of the CDGs and interactions with the communities during source scheme verification,
implementation of the agreed measures, the post support (PS) for the catchment management
and O&M activities. The CSs will assist the FTTs with the day to day supervision of the
construction, bio-engineering and vegetative restoration works that will be implemented under
NCB works contracts or community contracts.
The SES and designated EO takes overall responsibility of environment management of the
project. The FTT supported by EO screens the SPs on the basis of environment and social criteria.
The EO will clear the REA screening and prepare the DDRs. The SES reviews the REAs and
DDRs to ensure that subprojects have been categorized accurately. Similarly, the SES will endorse
these DDRs during planning stage. WME under the support of PMU engineers, integrate
environment issues of DDRs in design and contract documents.
7. ENVIRONMENT MONITORING AND REPORTING MECHANISM
The CDGs Implement required environmental measures and EOs supervise implementation of
environmental measures during construction. The EOs will review the compliance status
prepared by them and forwards it to the SES. The SES supports capacity development of project
team of environmental planning, monitoring and reporting. Each PMU/PIU has a team of COs,
CSs, FTTs and watershed experts (WMA/WME) to monitor the SPs’ environmental compliance
status. The SES also prepares environmental monitoring report on the basis of biannual field visit.
The SES reviews and makes necessary recommendation and compiles them to incorporate in
quarterly, semiannual and annual report as per requirement.
5
Existing environment safeguard monitoring and reporting mechanism is given in following chart.
Figure 2: Institutional arrangement for environment safeguard monitoring and reporting
8. COMPLIANCE WITH ENVIRONMENTAL SAFEGUARD MEASURES
Compliance status of environmental safeguard measures of 108 SPs for both planning and
implementation stage is provided in Annex 1a and Annex 1b respectively (as prescribed formats
by ADB). Both qualitative and quantitative information on planning and implementation stages are
collected/updated by field team (CO/CS/FTT/WME/WMA), checked by environment officer and
sent to the senior environment specialist/PMU on biannual basis.
8.1 DURING PLANNING AND APPROVAL PHASE
The project has followed the ADB’s safeguard and the GoN’s procedural requirement during
planning stage. The planning stage safeguard indicators such as SP selection, environment
screening, environment categorization, DDR inclusion, government permits, community
consultation, GRC formation and environment related management activities are acquired from
approved SPPRs, PAM, EARF and contract document. Besides safeguard training, safeguard
indicators such as impact to indigenous people, voluntary land donation, water source utilization
and grievances are also considered in planning stage. Summary of planning stage safeguard
compliance status of the project is given in Table 1 and planning stage safeguard compliance
status of108 SPs is given in Annex 1a.
Senior Environment
Specialist
SPs Environment
Safeguard Compliance
• Monitor social and environmental
Safeguard requirements/status
• Document/redress grievances
• Manage project staffs and experts
PMU
CDG/COs/CS/F
TTs
• Supervise field implementation team
• Monitor environment and social safeguard
requirements/ status
• Agreement with CDG
• Appointing Environment Officer
• Review compliance status both in planning & implementation stage
• Sub-projects visits, feedbacks, follow ups, design monitoring and
reporting formats, prepare environment safeguard guidelines.
organize training,
• Prepare EMR and necessary reports
• Screen environment requirements &
prepare DDR
• Assess environment compliance
• Report to Environment Expert/Expert
(WMA/WME)
• Document/redress grievance
PMIC/NDF
• SPPRs preparation
• Monitoring of SPs & training
• Supervise CO/CS/FTT
• Check received report
• Report to PMU/SES
PIU
6
Table 1: Summary of planning stage safeguard compliance status
8.1.1 Environment Screening and SP categorization, environment assessment
Indicators such as forest permission for catchment protection, land donation, impact to downstream users, ecologically sensitive area, cultural aspects and
indigenous people were assessed during SP selection. All the contracted SPs under the project were category “C” project and did not require EIA/IEE level
of assessment. As per PAM/EARF, the SPs under the project if not requiring an IEE study will be subjected to preparation of environment DDR.
8.1.2 Project Procedural Requirement
The project procedural requirements such as submission of voluntary land donation documents, community consultation minutes, environmental screening
of SPs and field verification by technical team were considered during SPPRs preparation. These SPPRs were reviewed by Feasibility Approval Committee
(FAC). The project procedural requirements were adopted for all 108 contracted SPs.
Trees/Fodder/
Fruits/Shrubs
Plantation
(Y/N)
Provision of
channel &
Spillway
(Y/N)
Erosion/Land
slide
Protectionn
measures
(Y/N)
Watershed
Conservation
practices
(Y/N)
Catchment
Restoration
Practices
(Y/N)
Ground Water
Recharge
practice (Y/N)
BCRWME
108 SPs
are
screened
All SPs are
category C
EARF is
prepared
for Project
REAs is
included in
all SPs
DDRs are
prepared
and
included in
all SPs
No
safeguard
training is
conducted
separately,
Safeguard
issues are
incorporat
ed in
other
trainings
Establishe
d in PMU
Appointed
Class III
officer in
PIU
No.
Environme
nt healp
desk was
taking
care of it.
Monitoing
by SES in
coordinati
on with
project
team
Mandatory
part for all
SPs. 515
voluntary
land
donation
paper are
received
The
consent is
received
from
communit
y
consultatio
n
In
coordinati
on with
DFO.
Positive
impacts
No formal
permision
letter.
SPs has
CDGs
looking
afetr it.
Communit
y
consultatio
n minute
is included
in all SPs.
378 SP
level and
1077 ward
level
meetings
are
conducted
Yes (in all
SPs)
Yes if
needed
Yes (in all
SPs)
Yes (in all
SPs)
Yes (in all
SPs)
Yes (in all
SPs)
EARF is
prepared
(Y/N)
REA is
included in
SPPR (Y/N)
DDR is
prepared
and
included in
SPPR
(Y/N)
Note: Y: Yes, N: No, GRM: Grievance Redress Mechanism, DFO: Divisional Forest Office, NA: Not Applicabe, EARF: Environment Assessment and Review Framework, DDR: Due delligence report
Consent for
Downstream
Water Use
(Y/N)
Impact on
Forest (Y/N)
Permits
from DFO
(Y/N/NA)
Water
distribution
system is
defined
(Y/N)
Public
consultation
minute
included
(Y/N)
Environment mgmt Related activities
Training to
FTTs/COs
(Y/N)
Environmen
t Help Desk
Etablished
(Y/N)
Provision of
Environmen
t Focal
Person (Y/N)
GRM
established
(Y/N)
Safeguard
monitoring
and
coordination
mechanism
established
Voluntary
Land
Donation
(Y/N/NA)
Name of
Project
Environmen
tal screening
is carried
out? (Y/ N)
Environmen
t category of
the /
subproject
(A/B/C/FI)
7
8.1.3 Rapid Environment Assessment and Due Diligence Report
For planning stage, all subprojects were screened for environmental impact, and due diligence
reports (DDRs) are prepared. The FTTs conducted REA; the staff designated as Environment
Officer checked each completed REA before it was finalized; DDRs were also prepared and
included in the all 108 SPPRs.
8.1.4 Environmental officers
Earlier, one of the DSCO’s staff had been designated as environment officer in Doti and
Dadeldhura. Due to restructuring of local bodies there is no existence of DSCO. Thus, the PIU
has appointed a soil conservation officer as an environment officer. The EO is responsible for
monitoring and reporting of environment safeguard and coordination with the SES.
8.1.5 Grievance redress mechanism and Environment safeguard desk
As per PAM/EARF, the project needs to form the grievance redress committee (GRC) for project
district level to document, redress and report of received grievances. No formal grievance
redress committee were formed due to restructuring of local bodies. However, a project level
environmental safeguard desk has been established in PMU Dadeldhura which also looks after
the grievances received. The project director/head of PIU are the main responsible persons to
redress the received grievances. Similarly, for SP level, Rural Municipality and CDG has jointly
formed a committee which is also responsible to redress the safeguard grievancess. Grievances
will be received verbally or written and will be resolved in both SP level and PMU level.
8.1.6 Community consultation and downstream users’ consent
The project has assessed the community consultation minutes for all SPPRs during evaluation.
Thus, all the contracted SPs have included community consultation minute. Besides few
suggestions, these minutes also include resource utilization consent from downstream users
committee. About 378 subproject level meetings and 1088 ward level consultations (n=108 SPs)
were conducted during planning stage.
8.1.7 Land Donation
The SPs require land for activities such as civil works and catchment protection measures. The
land is private, government/public or community owned. For each land acquisition, the SPs
require voluntary land donation paper. About 515 voluntary land donation papers were received.
8.1.8 Trainings
The senior environment specialist was responsible for training the environment officers and
project team. Immediately after orientation program conducted at PMU Dadeldhura, FTT were
given training on environmental issues and details of the data to be collected. The appointed COs
were also provided training about the environmental issues and their mitigation measures. It
seems that the safeguard training of the project team is inadequate.
8
8.1.8 Environment management related activities
The SPs have great environment benefits in terms of catchment management, ground water
recharge, surface water management, water source protection, land stabilization and erosion
control mechanism. Therefore, with an aim to manage and conserve watersheds, the
environmental benefits of the project outweigh minor adverse impacts incurred during
construction. These adverse impacts were also addressed during planning stage.
8.2 DURING IMPLEMENTATION STAGE
Besides monitoring of planning stage indicators, COs/CSs/FTTs of the respective districts use the
environment monitoring formats to collect the information on quarry site management, spoil
management, safety gears, grazing land, cut trees, trees plantation, grass cultivation, catchment
management, gully control measures, landslide protection measures, recharge pits, cattle ponds
and irrigation ponds. The safeguard issues observed by the expert during field visit are also
included in implementation stage safeguard status. Considering the issues and mitigation measures
as provided in EARF, and SPs specific issues during field visit, a summary of compliance status of
implementation stage is provided in Annex 1b.
Safeguard issues during implementation stage are satisfactorily complied. No quarry and burrow
pit area are located near to schemes or construction area. The majority of SPs’ civil structures are small-scale, extraction of sand, gravel and boulder is very low. The project has the provision
of re-grade the quarry sites. All the generated spoils from minor construction activities are
managed by SPs themselves such as backfilling. Excavated top soil is recommended for final
dressing of the sites. Waste generation is insignificant due to the nature of the SPs. Workers’ safety concern during construction is included in contract paper. However, the SP should make
the provision of protective gears like gloves, shoes, helmets etc. during construction. No grazing
practice is seen in the catchment protection area; however, the project should have the provision
of alternative grazing practice. Though no tree cutting issues are reported, the project should
have cleared vegetation during land preparation. The project has not received grievances
regarding to safeguards. Other statistical information is given in Table 2 below.
8.2.1 Quarry Site and Burrow Pit Management
The majority of SPs’ civil structures were small-scale, extraction of sand, gravel and boulder was
very low. Stones were used for gabion wall to protect source. An average 120 m3 of stone per
subproject is used for the gabion structures. These stones were collected with an approval of the
concerned municipality. During civil construction, all raw materials were collected from the
location specified by the designated engineers to avoid the issues of material transportation and
haphazard collection. As the project had the provision of re-grade the quarry sites, no adverse
impact due to quarrying and burrow pit was seen.
9
8.2.2 Excess Spoil and excavated top soil management
All the generated spoils from minor construction activities were managed by SPs themselves.
These spoils were used in back filling. As the top soil is very important, it is recommended to use
excavated top soil for final dressing of the sites and suggested to plant soil stabilizing shrubs to
prevent from erosion during rainfall.
8.2.3 Tree cutting and plantation
Although it was reported that no trees were cut, few trees might have been cleared by few SPs
during the land preparation for civil construction activities and recharge pit construction. The SPs
had provision of summer and winter trees plantation on both in private and public land which
includes fruit trees plantation, fodder trees plantation which has surely compensated these minor
numbers of cut trees. It is reported that 55078 winter plantation, 261882 fruit trees and 2188353
fodder species, 455823 forestry species were planted in 108 SPs till June, 2020. Besides restoring
upslope catchment, these plantations will help to generate income of community people, fodder
for animal. The SPs are recommended to care the planted trees until they grow. (Table 1).
8.2.4 Soil erosion and landslide control
Soil erosion and landslide issues occur during construction and land preparation for SPs’ activities.
Earthworks and trenching are generally done manually and concrete and cement masonry
structures erected using local skilled labour. Most aspects of the proposed works engage a limited
number of workers to lay piping, construct forms for reinforced concrete structures and prepare
ground for planting soil stabilizing grasses and shrubs. The project has recommended to plant
shrubs and grass on exposed slopes after construction. Thus, landslide and soil erosion issues
due to construction activities are not significant. The project has encouraged SPs to adopt
landslide stabilization, erosion control, gully area treatment and bioengineering practices. About
2469 m of brush layering, 1965 m of check dam and 11974 m of live fencing were done till
reporting period. Bamboos are planted in an area of 67.91 ha for bio-engineering purpose to
control erosion (Refer Table 2). To stabilize the land, the project has also adopted measures such
as gabion wall. 6357 units of gabion walls (Major) and masonry wall (minor) are used to protect
source water (Table 3). During the field visit, it came to know that few of the structures are
located in slope land which need to be stabilized to avoid possible damage to the structure.
8.2.5 Grazing land management
To prevent the possible damage of the catchment area, the project has the provision of
prohibiting animal grazing in catchment area. Few SPs have practiced grass/fodder cultivation.
Cultivation of 1893039 numbers of grasses in 122.93 ha of land is reported till the reporting
period (Table 2). Communities are encouraged to stall feeding by sufficient grass/fodder
cultivation. Rotational grazing and acceptable grazing area should be defined for grazing type’s alternatives.
10
8.2.6 Catchment management
The project has supported trees cultivation, grass cultivation for catchment improvement which
add the greenery as well. Brush layering, check dam and live fencing are adopted to protect
catchment area. To increase the ground recharge, the SPs have also constructed 11230 recharge
pits, 157 recharge ponds, 21 conservation ponds. (Table 2).
8.2.7 Water source protection
Water source is protected by considering the intake and protection wall around the source.
Prevention of gully erosion by check dams and gabion protection and source covering have helped
the water source protection. The trees around the water source are retained in water source
area.
Table 2: Summary of Statistical information of the Subprojects during Implementation Stage
SN Activity No. SN Activity No.
1 Winter Plantation (Nos) 55078 14 Brush Layering Length (m) 2469
2 Winter Plantation (Ha) 369 15 Recharge Pit No 11230
3 Forestry Species (Nos) 455823 16 Recharge Pit Ha 17492
4 Forestry Species (Ha) 181.96 17 Recharge Pond N 157
5 Fodder Trees Planted (Nos) 2188353 18 Recharge Pond H 7195
6 Fodder trees/grass plantation (Ha) 387.58 19 Conservation Pond N 21
7 Fruits trees planted (Nos) 261882 20 Conservation Pond H 864
8 Fruit plantation (Ha) 1235.03 21 Irrigation pond (Nos) 498
9 Grass Species Number 1893039 22 Cattle pond (Nos) 90
10 Shrubs/Grass Cultivation Area (Ha)
122.93 23 Water Source Protection (Nos)
1279
11 Bamboo Species Number 27773 24 Landslide Stabilization (ha) 6
12 Bamboo Species ha 67.91 25 Bamboo Check dam (M) 1965
13 Live Fencing (m) 11974
8.2.8 Irrigation Pond and Cattle Ponds
Besides providing drinking water to the community, the project has also supported 498 irrigation
ponds, 90 cattle ponds which benefit community to grow vegetable and crops and cattle drinking
(Refer Table 2).
8.2.9 Impact in Forest
No civil work was done in forest land. It is also reported that no single tree was removed from
the forest area. During the catchment restoration in community forest, the SP has received the
permits from CFUG. The SPs and project should also coordinate with Division Forest Offices
(DFO) during such work.
11
8.2.10 Waste management and Environment sanitation
According to the nature of SPs, construction wastes are common which are managed later. There
are plastic covers, scrap of chocolates, tobacco and biscuits etc. seen around few taps stands, the
reservoir tank and ponds which needs to be cleaned. This issue should be considered during PS.
8.2.11 Downstream water use
Community consultations with downstream community and formation of CDG have mitigated
the potential social conflict. SPs have allocated budget for construction of intake, reservoir tank,
RVT, irrigation pond, cattle pond etc. Few SPs are provided budget for drip irrigation, sprinkle.
These infrastructures are also used by downstream community as well. Till reporting period, 378
subproject level consultations and 1077 ward level consultations were conducted.
8.2.12 Worker’s safety and Work Camp
The construction activities are minor in the SPs and most of the construction activities are
completed. Workers’ safety concern during construction is included in contract paper. The SP
should make the provision of protective gears like gloves, shoes, helmets etc. during construction.
It is suggested that safety gears and first aid box should be provisioned in on-going construction
activities or PS activities. The contract document also contains safe working place. Local people
with CDG are used, thus, provision of construction work camp is non-significant.
8.2.13 Land acquisition and impacts to indigenous people
As the project has the provision of voluntary land donation, no involuntary land acquisition issue
arises due to SPs implementation. No negative impact to the life of indigenous people was
reported yet. It is found that the indigenous people are also benefitted positively in terms of
employment and drinking water facilities.
8.2.14 Child labor
No child below 18 years is employed as a labour in any SP activity. The SPs’ contract documents
also include the prohibition of child labours in SP activities.
8.2.15 Employment and wage discrimination
No wage discrimination for women performing similar nature of work is reported yet. The
contract document has also assured the no wage discrimination.
8.2.16 Violation of laws and regulation of GoN
The project/SPs have followed the rules and regulation of GoN during their implementation.
12
8.2.17 Field Visits by project team and SES
All SPs of implementation stages have been visited by PMIC consultant, experts, PMU/PIU staffs
and technical persons. The project has helped in capacity building of the CDG members through
training and orientation program. However, the project should orient the community and CDG
members about the importance of catchment restoration work. During field visit, the watershed
management experts has also instructed the FTT, CO and CS about supervision of the
construction quality and maintaining the safe environmental condition there. Due to the COVID
pandemic, the SES could not conduct the biannual visit; the information was collected through
personal contacts to the field staffs. Meeting regarding to PCR and SEMR were shared to the
project team as well.
8.2.18 Safeguard Training to Project Team (COs/CSs/FTTs/Environment Officer)
No specific safeguard training was conducted separately, however few sessions of safeguard
related issues were delivered during the training of watershed management, catchment
restoration and GESI related activities. The project staffs were orientated during the joint visit
with SES.
8.2.19 Safeguard monitoring and reporting system
The SES has prepared and shared environment monitoring and reporting formats. The capacity
for environment monitoring and reporting of the project team should be enhanced. CSs have
also been instructed to monitor the environmental condition at site to gather the environmental
issues and have been instructed to fill up the checklist and forward it to the FTT and finally at
PMIC office to check the environmental issues and whether need to be addressed them.
8.2.20 Grievance redress mechanism
Subprojects have been implemented through the consensus of local people. During planning stage,
the SP will form the community development group and the concern of local people has been
taken in to consideration. Till June, 2020, no major environmental grievances were reported.
However, the PIU has received the grievances of inadequate monitoring by the project. No special
committee for resolving grievances was formed, however, Project Director and PIU head at
project level and Rural municipality ward with CDG at SP level are dealing with the grievances.
8.2.21 Replication of good practices
The project has supported recharge pits, conservation pond for catchment restoration works
which are also replicated by Rural Municipalities. Capacity enhancement of conservation ponds
by RM and Province Government are also reported during this reporting period.
13
Photo 1: Capacity enhancement of Conservation pond in by Chaurpati RM
Photo 1: Capacity enhancement of conservation pond in of Banda, Achham by Far west Province Government
9. CORRECTIVE ACTION AND RECOMMENDATION
As the project is in its completion phase and no more monitoring report needs to be prepared,
the recommendations could not be considered in next EMR. However, the lesson learned could
be apply in the similar project in future. The project should strengthen environmental monitoring
and reporting mechanism as provisioned in planning stage. Similarly, caring of planted trees,
considering grazing alternatives, safety measures and coordination with other government bodies
should also be considered during implementation stage. Preparation of environment safeguard
guidelines, training on safeguard to project staffs, preparation of environment code of practices
should be considered at the beginning.
Field visits should also include the safeguard monitoring and reporting mechanism as per
EARF/PAM. The project needs to include environmental safeguard information so that the project
could receive safeguard information in upcoming PCR.
Table 3 : Recommendations and Lessons Learned
SN Issues Recommendation
1 Grievance Redress Committee
(GRC) Form GRC in Project Level and SP level
2 Environment Section/Environment
Window
Include environment section in Knowledge
Products to be developed by NDF and
environment window in MIS
3 Environment code of practice Prepare and place in each SPs
4 Training on Safeguard to the Project
team Incorporate in other trainings
14
Annexes
Annex 1: Status of Environmental Safeguards during Planning (Annex 1 a) and
Implementation stage (Annex 1 b)
Annex 2: Status of compliance with loan and grant covenants
Annex 3: Photographs
Trees/Fodder/
Fruits/Shrubs
Plantation
(Y/N)
Provision of
channel &
Spillway (Y/N)
Erosion/Landsli
de Protectionn
measures
(Y/N)
Watershed
Conservation
practices
(Y/N)
Catchment
Restoration
Practices (Y/N)
Ground Water
Recharge
practice (Y/N)
Bajhang
1 Syandi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
2 Deulek Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Baitadi
3 Chaukham Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y
4 Sikash Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
5 Siddheshwor Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
6 Siddapur Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
7 Shikharpur Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
8 Gajari Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
9 Dhungad Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
10 Shivling Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
11 Thalakada Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Dadeldhura
12 Ganeshpur Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
13 Mastamandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
14 Nawadurga Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
15 Koteli Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
16 Amargadi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
17 Asigram Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
18 Belapur Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
19 Manilek Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
20 Kaipilmandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Doti
21 Banlek Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
22 Jijodhamandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
23 Latamandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
24 Sanagau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
25 Tijali Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
26 Pachnali Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
27 Warpata Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
28 Ganjari Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
29 Kadamandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
30 Khirsain Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
31 Gairagaun Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
32 Daud Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
33 Toleni Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
34 Bajhakakani Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
35 Khatiwada Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
36 Mahadevsthan Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
37 Lamikhal Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
38 Dahakalikasthan Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
39 Kalikasthan Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
40 Waglek Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Annex 1a: Status of Environmental Safeguards during Planning Stage
S. N. Name of Subproject
Environmental
screening is
carried out?
(Y/ N)
Environment
category of the
/ subproject
(A/B/C/FI)
Consent for
Downstream
Water Use
(Y/N)
Impact on
Forest
(Y/N)
Public
consultation
minute
included
(Y/N)
Safeguard
monitoring and
coordination
mechanism
established
(Y/N)
Voluntary
Land
Donation
(Y/N/NA)
EARF is
prepared
(Y/N)
REA is
included in
SPPR (Y/N)
DDR is
prepared and
included in
SPPR (Y/N)
Water
distribution
system is
defined
(Y/N)
Training to
FTTs/Cos
(Y/N)
Provision of
Environment
Focal Person
(Y/N)
Environment
Help Desk
Etablished
(Y/N)
GRM
establishe
d (Y/N)
Permits
from DFO
(Y/N/NA)
Environment mgmt Related activities
Trees/Fodder/
Fruits/Shrubs
Plantation
(Y/N)
Provision of
channel &
Spillway (Y/N)
Erosion/Landsli
de Protectionn
measures
(Y/N)
Watershed
Conservation
practices
(Y/N)
Catchment
Restoration
Practices (Y/N)
Ground Water
Recharge
practice (Y/N)
S. N. Name of Subproject
Environmental
screening is
carried out?
(Y/ N)
Environment
category of the
/ subproject
(A/B/C/FI)
Consent for
Downstream
Water Use
(Y/N)
Impact on
Forest
(Y/N)
Public
consultation
minute
included
(Y/N)
Safeguard
monitoring and
coordination
mechanism
established
(Y/N)
Voluntary
Land
Donation
(Y/N/NA)
EARF is
prepared
(Y/N)
REA is
included in
SPPR (Y/N)
DDR is
prepared and
included in
SPPR (Y/N)
Water
distribution
system is
defined
(Y/N)
Training to
FTTs/Cos
(Y/N)
Provision of
Environment
Focal Person
(Y/N)
Environment
Help Desk
Etablished
(Y/N)
GRM
establishe
d (Y/N)
Permits
from DFO
(Y/N/NA)
Environment mgmt Related activities
41 Chhapali Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
42 Girichauka Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
43 Mudhegau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
44 Mudabhara Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
45 Kapalleki Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
46 Ranagau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
47 Durgamandau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
48 Basudevi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
49 Chawara Chautara Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
50 Dhirkhamandau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
51 Gaguda Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
52 Tikhatar Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
53 Satphari Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
54 D.S. Municipality Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
55 Kalena Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Achham
56 Bannatoli Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
57 Baijanath Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
58 Bhageshwor Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
59 Budhakot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
60 Bindabasani Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
61 Dunni Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
62 Gajara Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
63 Hatikot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
64 Jupu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
65 Markhu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
66 Mastamandu Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
67 Nandegada Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
68 Nawathana Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
69 Oligau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
70 Patalkot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
71 Ridikot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
72 Siddheshwor Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
73 Sokot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
74 Timmalsen Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
75 Lungra Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
76 Chandika Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
77 Mangalsen Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
78 Batulasen Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
79 Kalika Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
80 Bardadevi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
81 Janalikot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
82 Payal Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
83 Malatikot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
84 Kalagau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Trees/Fodder/
Fruits/Shrubs
Plantation
(Y/N)
Provision of
channel &
Spillway (Y/N)
Erosion/Landsli
de Protectionn
measures
(Y/N)
Watershed
Conservation
practices
(Y/N)
Catchment
Restoration
Practices (Y/N)
Ground Water
Recharge
practice (Y/N)
S. N. Name of Subproject
Environmental
screening is
carried out?
(Y/ N)
Environment
category of the
/ subproject
(A/B/C/FI)
Consent for
Downstream
Water Use
(Y/N)
Impact on
Forest
(Y/N)
Public
consultation
minute
included
(Y/N)
Safeguard
monitoring and
coordination
mechanism
established
(Y/N)
Voluntary
Land
Donation
(Y/N/NA)
EARF is
prepared
(Y/N)
REA is
included in
SPPR (Y/N)
DDR is
prepared and
included in
SPPR (Y/N)
Water
distribution
system is
defined
(Y/N)
Training to
FTTs/Cos
(Y/N)
Provision of
Environment
Focal Person
(Y/N)
Environment
Help Desk
Etablished
(Y/N)
GRM
establishe
d (Y/N)
Permits
from DFO
(Y/N/NA)
Environment mgmt Related activities
85 Caphamandau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
86 Santada Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
87 Thanti Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
88 Babala Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
89 Jalapadevi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
90 Kushkot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
91 Khodashadevi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
92 Ghughurukot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
93 Sutar Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Bajura N
94 Barhabis Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
95 Jayabageshwari Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
96 Kaanda Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
97 Dogadi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
98 Brahmatola Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
99 Gudukhati Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
100 Kuldevmandau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
101 Atichaur Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
102 Manakot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
103 Martadi Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
104 Budiganga Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
105 Kailashmandau Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
106 Tollidewal Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
107 Jugada Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
108 Dahakot Y C Y Y Y Y Y Y N Y Y Y N NA Y Y Y Y Y Y Y Y
Note: Y: Yes, N: No, GRM: Grievance Redress Mechanism, DFO: Divisional Forest Office, NA: Not Applicabe, EARF: Environment Assessment and Review Framework, DDR: Due delligence report
SN SNName of
SPs/Address
Location
of Quarry
& Burrow
Pit area
within 100
m (Y/N)
Quarry
Site
Manage
ment
(Y/N/NA
)
Excess
Spoil is
manag
ed
(Y/N)
Excava
ted
Top
Soil is
used
(Y/N)
Waste
generati
on (Y/N)
Use of
Safety
Gears
(Y/N)
Grazing
practice
in
catchme
nt
protecti
on area
(Y/N)
Alternati
ve
Animal
Grazing
Practice
(Y/N)
Cut tree
(Nos)
Winter
Plantation
(Nos)
Winter
Plantation
(Ha)
Forestry
Species
(Nos)
Forestry
Species
(Ha)
Fodder
Trees
Planted-
Survived
(Nos)
Fodder
trees/grass
plantation
(Ha)
Fruits plant
planted-
Survived
(Nos)
FRUIT
plantation
(Ha)
Grass
Species
Number
Shrubs/Gra
ss
Cultivation
Area (Ha)*
Bamboo
Speces
Number
Bamboo
Species
ha
Live
Fencing
(m)
Brush
Layering
Lngth (m)
Area of brush
layering/Bioe
ngineering
work (Ha)
Recharg
e Pit No
Recharge
Pit Ha
Recharge
Pond N
Recharge
Pond H
Conservati
on Pond N
Conserva
tion Pond
H
Irrigatio
n pond
(Nos)
Cattle
pond
(Nos)
Water
Source
Protectio
n (Nos)
Landslide
Stabilizati
on (ha)
Bamboo
Checkda
m (M)
Nos of
grievances
document
ed
No of
grievance
s
resolved
No of
grievances
under
processing
1 Doti Banlek N Y Y Y N NA N N 0 1552 6.88 0 0 82914 21.23 3431 19.61 32801 2.1 640 1.6 0 700 0.045 15 15 0 0 0 0 1 0 22 120 0 0 0
2 Doti Jijodhamandu N Y Y Y N NA N N 0 598 3.12 0 0 7855 1.74 2337 11.99 14083 0.9 220 0.55 0 0 15 15 0 0 0 0 11 1 13 0 0 0 0
3 Doti Latamandu N Y Y Y N NA N N 0 430 4.3 0 0 24025 5.44 1973 11.08 21079 1.35 348 0.87 160 710 0.071 160 160 0 0 0 0 6 3 16 0 0 0 0
4 Doti Sanagau N Y Y Y N NA N N 0 321 2.85 550 0.22 7849 2.79 2657 11.57 8724 0.56 96 0.24 0 507 0.015 350 350 0 0 0 0 6 0 17 2.39 0 0 0 0
5 Dadeldhura Ganeshpur N Y Y Y N NA N N 0 693 4.08 29218 11.69 14378 2.08 7356 29.66 24958 1.6 804 2.01 512 0 0 0 3 58 2 100 2 1 26 2.83 428 0 0 0
6 Dadeldhura Mastamandu N Y Y Y N NA N N 0 1358 10.89 27969 11.19 24900 4.71 6457 29.8 23438 1.5 564 1.41 0 250 0.025 0 0 8 144 5 44 3 2 10 0.13 222 0 0 0
7 Dadeldhura Nawadurga N Y Y Y N NA N N 0 925 3.54 20188 8.08 102124 39.54 4826 29.63 11720 0.75 140 0.35 0 0 0 0 3 71 0 0 1 3 28 247 0 0 0
8 Dadeldhura Koteli N Y Y Y N NA N N 0 332 1.19 11654 4.66 86978 23.24 4661 24.99 25781 1.65 770 1.93 0 0 17 50 0 0 0 0 5 0 26 0.65 40 0 0 0
0 6209 36.85 89579 35.84 351023 100.77 33698 168.33 162584 10.41 3582 8.96 672 2167 0.156 557 590 14 273 7 144 35 10 158 6 1057 0 0 0
1 Bajhang Syandi N Y Y Y N NA N N 0 5004 30.87 16282 6.51 154543 9.89 3718 13.37 14216 0.91 0 0 0 0 0.03 120 120 0 0 0 0 3 0 11 0 0 0 0
2 Bajhang Deulek N Y Y Y N NA N N 0 5722 35.18 0 0 95418 6.11 4460 16.04 17132 1.1 0 0 0 0 165 165 0 0 0 0 2 0 14 0 0 0 0
3 Baitadi Chaukham N Y Y Y N NA N N 0 2404 12.11 16332 6.53 96000 6.14 3513 12.64 38058 2.44 0 0 0 0 158 315 0 0 0 0 3 0 17 0 0 0 0
4 Baitadi Sikash N Y Y Y N NA N N 0 679 6.79 0 0 61517 6 5018 18.05 24532 1.57 995 2.49 0 0 80 160 0 0 0 0 2 0 13 0 0 0 0
5 Baitadi Siddheshwor N Y Y Y N NA N N 0 150 1.5 1100 0.44 126040 9.18 3375 12.14 29767 1.91 0 0 0 0 178 345 0 0 0 0 3 2 12 0 0 0 0
6 Baitadi Siddapur N Y Y Y N NA N N 0 242 2.42 25963 10.39 30610 4.27 1163 4.18 19356 1.24 0 0 0 0 115 230 0 0 0 0 5 1 20 0 0 0 0
7 Baitadi Shikharpur N Y Y Y N NA N N 0 200 2 19304 7.72 37696 3.32 1263 4.54 35626 2.28 0 0 0 0 95 190 0 0 0 0 2 0 4 0 0 0 0
8 Baitadi Gajari N Y Y Y N NA N N 0 1962 19.62 16472 6.59 27250 3.59 3658 13.16 33313 2.13 12 0.03 0 0 0.0015 275 550 0 0 0 0 0 5 20 0 0 0 0
9 Dadeldhura Amargadi N Y Y Y N NA N N 0 0 0 18590 7.44 142295 13.1 10043 37.73 62499 4 6475 16.19 0 0 0 0 0 0 0 0 3 0 16 0 0 0 0
10 Dadeldhura Asigram N Y Y Y N NA N N 0 385 3.85 2604 1.04 68234 4.37 8207 29.79 7812 0.5 466 1.17 0 0 3 15 5 102 0 0 1 0 9 0 0 0 0
11 Dadeldhura Belapur N Y Y Y N NA N 143 0.81 16850 6.74 16250 1.04 6681 31.08 75703 4.84 2818 7.05 700 0 1 8 0 0 5 500 3 0 11 0 0 0 0
12 Dadeldhura Manilek N Y Y Y N NA N N 0 0 0 7638 3.06 33429 3.76 5493 28.08 6250 0.4 922 2.31 0 0 27 55 1 30 0 0 3 0 25 0 0 0 0
13 Dadeldhura Kaipilmandu N Y Y Y N NA N N 0 39 0.39 6585 2.63 15175 6.07 4833 18.67 0 0 1194 2.99 0 0 6 35 11 195 0 0 6 0 8 0 0 0 0
14 Doti Tijali N Y Y Y N NA N N 0 594 2.78 19030 7.61 20707 5.76 1546 7.96 12604 0.81 259 0.65 0 0 20 20 0 0 0 0 3 0 11 31 0 0 0
15 Doti Pachnali N Y Y Y N NA N N 0 395 2.29 9810 3.92 15612 5.04 1213 7.67 6796 0.43 360 0.9 0 50 0.0015 130 130 1 20 0 0 5 0 9 54 0 0 0
16 Doti Warpata N Y Y Y N NA N N 0 339 1.86 11261 4.5 4000 0.26 2457 14.47 10129 0.65 260 0.65 0 0 10 10 0 0 0 0 4 0 20 16 0 0 0
17 Doti Ganjari N Y Y Y N NA N N 0 0 0 12354 4.94 13749 5.5 1337 4.37 0 0 200 0.25 0 30 900 900 0 0 0 0 5 0 12 54 0 0 0
18 Doti Kadamandu N Y Y Y N NA N N 0 192 0.69 6276 2.51 7432 2.97 2253 10.06 0 0 0 0 0 0 380 380 0 0 0 0 8 0 7 0 0 0 0
19 Doti Khirsain N Y Y Y N NA N N 0 153 0.9 523 0.21 17270 6.91 3244 10.36 23436 1.5 0 0 4000 0 280 280 0 0 0 0 4 0 14 0 0 0 0
20 Doti Gairagaun N Y Y Y N NA N N 0 0 0 6051 2.42 12676 5.07 3314 12.53 15624 1 0 0 1800 0 550 550 0 0 0 0 6 0 20 0 0 0 0
0 18603 124.06 213025 85.2 995903 108.35 76789 306.89 432853 27.71 13961 34.68 6500 80 0.033 3493 4458 18 347 5 500 71 8 273 0 155 0 0 0
1 Doti Lamikhal N Y Y Y N NA N N 0 623 3.39 0 0 3987 1.59 3131 11.66 50544 3.23 0 0 200 0 275 275 1 40 0 0 11 0 17 0 0 0 0
2 Doti Chhapali N Y Y Y N NA N N 0 0 0 0 0 3062 1.22 1142 5.39 0 0 452 1.13 0 0 0 0 0 0 0 0 7 2 8 0 0 0 0
3 Doti Girichauka N Y Y Y N NA N N 0 0 0 0 0 4462 0.59 1200 6.88 3563 0.23 575 1.44 0 0 0 0 0 0 8 160 12 3 22 0 0 0 0
4 Doti Daud N Y Y Y N NA N N 0 581 3.21 0 0 5425 0.78 1675 7.47 5000 0.32 300 0 0 0 105 105 3 60 0 0 1 1 31 0 0 0 0
5 Doti Toleni N Y Y Y N NA N N 0 2482 24.82 300 0.12 5300 0.61 4347 15.64 45515 2.92 1300 1 0 222 0.24 105 105 5 100 0 0 1 0 15 0 0 0 0
6 Doti Bajhakakani N Y Y Y N NA N N 0 875 6.83 0 0 8453 1.67 5277 27.7 34262 1.24 100 0 0 0 0 25 5 200 0 0 5 0 14 18 0 0 0
7 Doti Khatiwada N Y Y Y N NA N N 0 581 3.21 0 0 11866 0.76 1769 8.6 12165 0.78 0 0 0 0 40 40 2 40 0 0 5 8 14 0 0 0 0
8 Doti Mahadevsthan N Y Y Y N NA N N 0 2114 12.16 0 0 6875 2.75 3485 14.86 5956 0.37 248 0.37 300 0 0.03 485 485 1 20 0 0 4 1 11 100 0 0 0
9 Doti Dahakalikasthan N Y Y Y N NA N N 0 2054 11.53 4000 1.6 12001 2.15 2555 9.28 26136 1.64 332 0.18 0 0 20 20 6 120 0 0 10 1 21 0 0 0 0
10 Doti Kalikasthan N Y Y Y N NA N N 0 1805 10.79 1375 0.55 34156 2.86 3785 15.36 31959 2.01 728 0.59 0 0 20 20 2 40 0 0 8 1 21 0 0 0 0
11 Doti Waglek N Y Y Y N NA N N 0 0 0 1000 0.4 3500 0.22 2098 10.43 3437 0.22 0 0 0 0 50 50 0 0 0 0 11 7 16 15 0 0 0
12 Achham Baijanath N Y Y Y N NA N N 0 0 0 0 0 0 0 4072 17 0 0 1220 0 0 0 0 0 0 0 0 0 2 2 20 0 0 0 0
13 Achham Bhageshwor N Y Y Y N NA N N 0 0 0 0 0 0 0 2662 19.5 0 0 0 0 0 0 300 600 11 600.8 0 0 4 0 14 0 0 0 0
14 Achham Dunni N Y Y Y N NA N N 0 1139 6.51 0 0 0 0 2157 5.01 10440 1.34 0 0 0 0 320 640 7 580 0 0 3 0 13 0 0 0 0
15 Achham Jupu N Y Y Y N NA N N 0 200 2 0 0 0 0 4570 25.51 0 0 400 1 0 0 0 0 0 0 0 0 3 0 17 0 0 0 0
16 Achham Markhu N Y Y Y N NA N N 0 1672 8.34 0 0 2500 1 1946 7 4222 0.33 200 0 0 0 550 1100 9 979 0 0 4 1 6 0 0 0 0
17 Achham Oligau N Y Y Y N NA N N 0 0 0 0 0 0 0 4574 30.25 0 0 0 0 0 0 0 0 0 0 0 0 3 0 9 0 0 0 0
18 Achham Patalkot N Y Y Y N NA N N 0 1468 9.56 0 0 0 0 860 3.41 0 0 0 0 0 0 0 0 0 0 0 0 5 0 32 0 0 0 0
19 Achham Ridikot N Y Y Y N NA N N 0 0 0 0 0 0 0 1760 15.38 0 0 0 0 0 0 0 0 0 0 0 0 3 2 10 0 0 0 0
20 Achham Sokot N Y Y Y N NA N N 0 1452 5.88 0 0 0 0 2184 16.5 0 0 0 0 0 0 300 300 10 931.2 0 0 3 2 9 0 0 0 0
21 Achham Timmalsen N Y Y Y N NA N N 0 400 4 0 0 0 0 4535 21.5 15625 1 0 0 0 0 0 0 0 0 0 0 9 2 13 0 0 0 0
22 Achham Bannatoli N Y Y Y N NA N N 0 749 6.92 0 0 0 0 3896 23.26 0 0 0 0 0 0 0 0 0 0 0 0 5 0 17 0 0 0 0
23 Achham Mastamandu N Y Y Y N NA N N 0 343 1.8 0 0 0 0 2696 16.65 7500 0.48 0 0 0 0 70 85 0 0 0 0 5 2 13 0 0 0 0
24 Achham Nandegada N Y Y Y N NA N N 0 1565 5.06 0 0 0 0 1280 4.6 0 0 132 0.33 0 0 75 150 2 80 0 0 7 1 12 0 0 0 0
25 Achham Nawathana N Y Y Y N NA N N 0 84 0.3 0 0 0 0 732 5.53 0 0 0 0 0 0 0 0 4 160 0 0 10 0 16 0 0 0 0
26 Achham Siddheshwor N Y Y Y N NA N N 0 200 2 0 0 0 0 1300 13 0 0 0 0 0 0 0 0 0 0 0 0 0 2 9 0 0 0 0
27 Achham Bindabasani N Y Y Y N NA N N 0 423 1.99 0 0 0 0 1280 4.53 0 0 256 0.64 0 0 300 600 1 40 0 0 7 1 9 0 0 0 0
28 Achham Hatikot N Y Y Y N NA N N 0 466 2.32 0 0 0 0 1498 9.15 0 0 382 3.58 0 0 120 340 4 160 0 0 10 0 5 0 0 0 0
29 Achham Budhakot N Y Y Y N NA N N 0 847 8.53 0 0 1563 0.1 685 5.99 6376 1.18 0 0 0 0 60 120 8 160 0 0 9 0 2 0 0 0 0
30 Achham Gajara N Y Y Y N NA N N 0 262 0.94 0 0 0 0 1830 9.4 0 0 0 0 0 0 160 160 5 400 0 0 9 0 10 0 0 0 0
31 Bajura Barhabis N Y Y Y N NA N N 0 0 0 0 0 148 0.13 2204 9.84 0 0 400 1 0 0 80 160 1 12 0 0 6 0 27 0 0 0 0
32 Bajura Jayabageshwari N Y Y Y N NA N N 0 0 0 750 0.25 3593 0.75 2107 9.5 20153 1.38 400 1 0 0 80 160 3 60 0 0 2 0 9 0 0 0 0
33 Bajura Kaanda N Y Y Y N NA N N 0 0 0 0 0 7813 0.5 1318 3.05 31251 2 400 1 0 0 120 240 3 60 0 0 2 0 9 0 0 0 0
34 Bajura Dogadi N Y Y Y N NA N N 0 0 0 0 0 0 0 312 1.12 15312 0.97 280 0.7 0 0 80 160 4 120 0 0 3 1 28 0 0 0 0
35 Bajura Brahmatola N Y Y Y N NA N N 0 0 0 0 0 7924 0.59 894 3.21 0 0 240 0.6 400 0 80 80 1 40 0 0 9 2 9 0 0 0 0
36 Bajura Gudukhati N Y Y Y N NA N N 0 0 0 0 0 222 0.18 610 2.18 31872 1.99 200 0.5 0 0 50 100 3 60 0 0 7 1 4 0 0 0 0
37 Bajura Kuldevmandau N Y Y Y N NA N N 0 0 0 0 0 22222 1.68 923 4.79 85621 5.38 0 0 400 0 80 160 4 120 0 0 3 3 10 0 0 0 0
38 Baitadi Dhungad N Y Y Y N NA N N 0 0 0 0 0 0 0 3878 19.08 0 0 0 0 0 0 213 426 0 0 0 0 4 2 18 0 0 0 0
39 Baitadi Shivling N Y Y Y N NA N N 0 0 0 0 0 0 0 5599 21.45 0 0 0 0 0 0 237 475 0 0 0 0 1 0 12 0 0 0 0
Annex 1 b: Status of Environmental Safeguard during Implementation Stage
Batch II
Batch I
SN SNName of
SPs/Address
Location
of Quarry
& Burrow
Pit area
within 100
m (Y/N)
Quarry
Site
Manage
ment
(Y/N/NA
)
Excess
Spoil is
manag
ed
(Y/N)
Excava
ted
Top
Soil is
used
(Y/N)
Waste
generati
on (Y/N)
Use of
Safety
Gears
(Y/N)
Grazing
practice
in
catchme
nt
protecti
on area
(Y/N)
Alternati
ve
Animal
Grazing
Practice
(Y/N)
Cut tree
(Nos)
Winter
Plantation
(Nos)
Winter
Plantation
(Ha)
Forestry
Species
(Nos)
Forestry
Species
(Ha)
Fodder
Trees
Planted-
Survived
(Nos)
Fodder
trees/grass
plantation
(Ha)
Fruits plant
planted-
Survived
(Nos)
FRUIT
plantation
(Ha)
Grass
Species
Number
Shrubs/Gra
ss
Cultivation
Area (Ha)*
Bamboo
Speces
Number
Bamboo
Species
ha
Live
Fencing
(m)
Brush
Layering
Lngth (m)
Area of brush
layering/Bioe
ngineering
work (Ha)
Recharg
e Pit No
Recharge
Pit Ha
Recharge
Pond N
Recharge
Pond H
Conservati
on Pond N
Conserva
tion Pond
H
Irrigatio
n pond
(Nos)
Cattle
pond
(Nos)
Water
Source
Protectio
n (Nos)
Landslide
Stabilizati
on (ha)
Bamboo
Checkda
m (M)
Nos of
grievances
document
ed
No of
grievance
s
resolved
No of
grievances
under
processing
40 Baitadi Thalakada N Y Y Y N NA N N 0 0 0 0 0 0 0 5860 23.03 0 0 0 0 0 0 180 360 0 0 0 0 5 0 12 0 0 0 0
0 22385 142.09 7425 2.92 145072 20.13 98686 483.69 446909 29.01 8545 15.06 1300 222 0.27 4555 7541 105 5183 8 160 218 48 564 0 133 0 0 0
1 Doti Mudhegau N Y Y Y N NA N N 0 0 0 6324 3 3062 0.66 703 5.15 7812 0.5 240 0.6 0 0 0 0 0 0 0 0 1 0 6 0 0 0 0
2 Doti Mudabhara N Y Y Y N NA N N 0 0 0 4125 2 4587 1.08 276 0.99 13374 0.86 125 0.31 150 0 10 10 0 0 0 0 5 1 12 0 0 0 0
3 Doti Kapalleki N Y Y Y N NA N N 0 0 0 3299 1 11025 4.41 731 3.75 0 0 0 0 0 0 0 0 0 0 0 0 4 1 9 0 0 0 0
4 Doti Ranagau N Y Y Y N NA N N 0 0 0 2063 1 33219 6.33 763 6.3 31641 2.03 120 0.3 0 0 0 0 0 0 0 0 3 1 5 0 0 0 0
5 Doti Durgamandau N Y Y Y N NA N N 0 748 5 7150 3 16062 3.8 277 1 10937 0.7 40 0.1 0 0 18 18 0 0 0 0 1 0 8 0 0 0 0
6 Doti Basudevi N Y Y Y N NA N N 0 0 0 0 0 52728 9.93 674 4.67 33201 2.12 160 0.4 0 0 0 0 0 0 0 0 3 1 8 0 0 0 0
7 Doti Chawara Chautara N Y Y Y N NA N N 0 0 0 2750 1 14468 1.85 569 2.69 16406 1.05 80 0.2 162 0 5 38 0 0 0 0 3 2 2 0 0 0 0
8 Doti Dhirkhamandau N Y Y Y N NA N N 0 0 0 1100 0 2925 0.51 0 0 7432 0.48 40 0.1 0 0 0 0 1 15 0 0 1 1 8 0 0 0 0
9 Doti Gaguda N Y Y Y N NA N N 0 0 0 0 0 9296 1.75 1111 5.12 9764 0.62 0 0 0 0 7 68 3 68 0 0 2 0 6 0 0 0 0
10 Doti Tikhatar N Y Y Y N NA N N 0 0 0 0 0 8718 2.17 555 2.96 8592 0.55 80 0.2 0 0 4 36 1 15 0 0 1 0 7 20 0 0 0
11 Doti Satphari N Y Y Y N NA N N 0 0 0 0 0 5212 2.08 285 1.25 5860 0.38 0 0 0 0 0 0 1 20 0 0 1 0 7 0 0 0 0
12 Doti D.S. Municipality N Y Y Y N NA N N 0 0 0 21175 8 72112 11.91 2305 13.06 55074 3.52 120 0 0 0 119 119 0 0 0 0 1 0 19 0 0 0 0
13 Doti Kalena N Y Y Y N NA N N 0 0 0 4125 2 13561 5.42 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10 0 10 0 0 0 0
14 Achham Lungra N Y Y Y N NA N N 0 139 1 0 0 26673 8.18 1373 7 7419 0.47 0 0 0 0 0 0 0 0 0 0 8 1 3 0 0 0 0
15 Achham Chandika N Y Y Y N NA N N 0 0 0 0 0 23126 6.1 2246 14 9371 0.6 0 0 0 0 0 0 0 0 0 0 5 0 5 0 0 0 0
16 Achham Mangalsen N Y Y Y N NA N N 0 139 1 0 0 2500 1 4958 30 50778 3.25 0 0 0 0 660 1320 0 0 0 0 6 2 13 0 0 0 0
17 Achham Batulasen N Y Y Y N NA N N 0 0 0 0 0 10000 4 2185 8.5 31248 2 0 0 0 0 360 720 1 50 0 0 8 4 14 0 0 0 0
18 Achham Kalika N Y Y Y N NA N N 0 0 0 0 0 11000 4.4 2807 16.5 55469 3.55 0 0 0 0 0 0 0 0 0 0 1 1 2 0 0 0 0
19 Achham Bardadevi N Y Y Y N NA N N 0 139 1 0 0 0 0 2557 14.64 69533 4.45 0 0 0 0 0 0 0 0 0 0 4 1 8 0 0 0 0
20 Achham Janalikot N Y Y Y N NA N N 0 462 1 21313 9 12264 3.33 1970 12.37 1552 0.1 0 0 0 0 0 0 0 0 0 0 4 1 6 0 0 0 0
21 Achham Payal N Y Y Y N NA N N 0 278 1 0 0 36313 8.33 3260 23.7 17577 1.12 0 0 0 0 0 0 0 0 0 0 7 2 8 0 0 0 0
22 Achham Malatikot N Y Y Y N NA N N 0 0 0 0 0 27751 5.85 1668 6 45313 2.9 0 0 0 0 100 200 0 0 1 60 7 0 9 600 0 0 0
23 Achham Kalagau N Y Y Y N NA N N 0 0 0 5000 2 19218 3.75 3056 15.47 58596 3.75 0 0 500 0 260 260 1 70 0 0 8 0 8 0 0 0 0
24 Achham Caphamandau N Y Y Y N NA N N 0 2100 21 0 0 10000 4 4114 18 31252 2 0 0 500 0 450 900 0 0 0 0 3 1 3 0 0 0 0
25 Achham Santada N Y Y Y N NA N N 0 698 6 0 0 6628 2.65 556 2 28124 1.8 0 0 500 0 0 0 3 144 0 0 5 0 5 0 0 0 0
26 Achham Thanti N Y Y Y N NA N N 0 1250 11 0 0 21225 4.29 403 2.25 22300 1.5 0 0 0 0 0 0 0 0 0 0 6 0 0 0 0 0 0
27 Achham Babala N Y Y Y N NA N N 0 1150 12 8250 3 28250 4.8 0 0 12000 1 0 0 0 0 0 0 0 0 0 0 6 0 4 0 0 0 0
28 Achham Jalapadevi N Y Y Y N NA N N 0 278 1 0 0 0 0 1620 15.75 0 0 0 0 0 0 0 0 1 40 0 0 1 0 3 0 0 0 0
29 Achham Kushkot N Y Y Y N NA N N 0 0 0 4500 2 20500 5.2 1162 4.5 12625 1 280 1 0 0 0 0 0 0 0 0 8 0 6 0 0 0 0
30 Achham Khodashadevi N Y Y Y N NA N N 0 0 0 5500 2 22625 3.8 1112 4 22300 1.5 300 3 0 0 24 48 0 0 0 0 4 0 9 0 0 0 0
31 Achham Ghughurukot N Y Y Y N NA N N 0 500 5 4000 2 10250 1.6 278 1 3600 0.25 0 0 0 0 0 0 0 0 0 0 9 0 10 0 0 0 0
32 Achham Sutar N Y Y Y N NA N N 0 0 0 0 0 5500 2.2 2780 10 30000 2 0 0 0 0 0 0 5 600 0 0 5 0 14 0 0 0 0
33 Bajura Atichaur N Y Y Y N NA N N 0 0 0 3250 1 4610 1.1 695 2.5 20000 1.5 0 0 1690 0 390 780 1 70 0 0 1 0 2 0 0 0 0
34 Bajura Manakot N Y Y Y N NA N N 0 0 0 8200 3 23534 3.52 1112 4 15240 1 0 0 0 0 0 0 0 0 0 0 5 0 5 0 0 0 0
35 Bajura Martadi N Y Y Y N NA N N 0 0 0 5000 2 16000 4.5 556 2 5000 0.5 0 0 0 0 0 0 0 0 0 0 5 0 7 0 0 0 0
36 Bajura Budiganga N Y Y Y N NA N N 0 0 0 11000 4 34291 9.16 1073 4.5 13666 1 100 3 0 0 36 72 0 0 0 0 5 0 7 0 0 0 0
37 Bajura Kailashmandau N Y Y Y N NA N N 0 0 0 9600 4 19297 5.82 834 3 5997 0.5 0 0 0 0 50 50 1 120 0 0 4 4 10 0 0 0 0
38 Bajura Tollidewal N Y Y Y N NA N N 0 0 0 2570 1 7765 1.95 1251 5 3515 0.25 0 0 0 0 12 24 0 0 0 0 8 0 6 0 0 0 0
39 Bajura Jugada N Y Y Y N NA N N 0 0 0 5500 2 50060 6.9 834 2.5 78125 5 0 0 0 0 120 240 1 180 0 0 3 0 8 0 0 0 0
40 Bajura Dahakot N Y Y Y N NA N N 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 0 2 0 0 0 0
0 7881 66 145794 58 696355 158.33 52709 276.12 850693 55.8 1685 9.21 3502 0 0 2625 4903 20 1392 1 60 174 24 284 0 620 0 0 0
0 55078 369 455823 181.96 2188353 387.58 261882 1235.03 1893039 122.93 27773 67.91 11974 2469 0.459 11230 17492 157 7195 21 864 498 90 1279 6 1965 0 0 0
Note: Y: Yes, N:No, NA: Not Applicable, Nos: Number, Ha: Hectare, M: Meter
Total (All Batch)
Batch IV
Batch III
i
Annex 2: Compliance status with Loan and Grant Covenants (As of June, 2020)
Reference Covenants Compliance Date Status/Remarks
Para 2, Schedule
4
Environment
The Recipient shall ensure, or cause the EA and implementing agencies to ensure, that the
preparation, design, construction, implementation, operation and decommissioning of the Project
and all Project facilities comply with (a) all applicable laws and regulations of the Recipient relating
to environment, health, and safety; (b) the Environmental Safeguards; (c) the EARF; and (d) all
measures and requirements set forth in the IEEs, and any corrective or preventative actions set
forth in a Safeguards Monitoring Report.
Throughout the project.
Being complied. It is
considered both
planning and
implementation stage.
Para 3, Schedule
4
Involuntary Resettlement and Indigenous People:
The Recipient shall ensure, or cause the EA and implementing agencies to ensure, that the Project
does not have any Indigenous Peoples Safeguards or Involuntary Resettlement Safeguards impacts,
all within the meaning of ADB’s Safeguard Policy Statement (2009). Any sub-project which requires
involuntary resettlement or has Indigenous Peoples Safeguards impact shall be dropped. In the event
that the sub-projects do have any such impact, the Recipient shall take all steps required to ensure
that the Project complies with the applicable laws and regulations of the Recipient, and with ADB’s Safeguard Policy Statement.
Throughout the project
Being complied. It is
considered in planning
stage.
Para 4, Schedule
4
Voluntary Land Donation
The Recipient shall ensure that all voluntary donation of land by beneficiaries is implemented in
accordance with the procedures laid out in the Voluntary Land Donation Framework after free,
prior and informed consultation and consent of the affected persons.
Throughout the project Being complied. During
Planning Stage.
Para 5, Schedule
4
Human and Financial Resources to Implement Safeguards Requirements
The Recipient shall make available, or cause the EA and implementing agencies to make available, Throughout the project Being complied.
ii
Reference Covenants Compliance Date Status/Remarks
necessary budgetary and human resources to fully implement the EARF, any IEE or EMP, and any
additional documents to be prepared in accordance with the EARF.
Para 6, Schedule
4
Safeguards – Related Provisions in Bidding Documents and Works Contracts
The Recipient shall ensure, or cause the EA and implementing agencies to ensure, that all bidding
documents and contracts for Works contain provisions that require contractors to:
(a) comply with the measures and requirements relevant to the contractor set forth in the IEE,
the EMP, and any corrective or preventative actions set out in a Safeguards Monitoring
Report;
(b) make available a budget for all such environmental and social measures;
(c) provide the Recipient with a written notice of any unanticipated environmental,
resettlement or indigenous peoples risks or impacts that arise during construction,
implementation or operation of the Project that were not considered in the IEE or the
EMP;
(d) adequately record the condition of roads, agricultural land and other infrastructure prior
to starting to transport materials and construction; and
(e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-
project condition upon the completion of construction.
Throughout the project Being complied.
Para 7, Schedule
4
Safeguards Monitoring and Reporting
The Recipient shall (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose
relevant information from such reports to affected persons promptly upon submission; (b) if any
unanticipated environmental and/or social risks and impacts arise during construction,
implementation or operation of the Project that were not considered in the IEE or the EMP,
promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the
Throughout the project Being complied.
iii
Reference Covenants Compliance Date Status/Remarks
event and proposed corrective action plan; and (c) report any actual or potential breach of
compliance with the measures and requirements set forth in the EMP promptly after becoming
aware of the breach.
Para 17, Schedule
4
Grievance Redress Mechanism
As soon as possible during the implementation, the EA shall constitute a special committee in each
Project district to receive and resolve complaints and grievances or act upon reports from
stakeholders on misuse of funds and other irregularities. The committees shall (a) make public the
existence of the grievance mechanism, (b) review and address grievances of stakeholders of the
Project, in relation to either the Project, any of the service providers, or any person responsible
for carrying out any aspect of the Project; and (c) proactively and constructively respond to them.
Throughout the project
Being complied/ No
district wise special
committee was formed
due to the restructuring
of the local level. Ward
of Rural/municipality
along with Community
Development Groups
are taking care of such
grievances
iv
Annex-3: Photographs of sample civil and implementation works
Recharge pit in Badimalika RM, Martadi Tap-stands in Trishakti High School Barabis SP, Bajura
Cattle pond in Bajhakakani SP, Doti Water source development wail, Durgamndu SP, Doti
Water Collection chamber & Irrigation pond in Basudevi SP, Doti Irrigation pond in paharpani, Shikharpur SP, Baitadi
v
Reservoir tank Kund CMA, Kadamandu SP, Doti Reservoir tank ChipkeCMA, Jijodhamandu SP, Doti
Recharge pit in Bhauni CMA, Siddheshwor SP, Baitadi Gully control at Chaddi khola CMA, Sangau SP, Doti
Catchment restoration Thulaban CMA, Nawadurga SP, Dadeldhura Okhar plantation, Ghodigada CM, A Nandegada SP, Achham
Seedling for distribution to CMA, Nawadurga SP, Dadeldhura Source protection Garkha CMA, Mastamandu SP, Dadeldhura
vi
Hedge plantation Dharapani CMA, Banlek SP, Doti Brush layering Nuwakot CMS, Sanagau SP, Doti
Gully control Dharapani CMA, Banlek SP, Doti
Conservation Pond, Jalapadevi, Sanfebagar
Monitoring SPs of Jalpadevi Achham Failure of irrigation Pond, Toli, Bajura