Enigineering Economic Report by Ashakoor Comsats Atd

  • Upload
    sobi

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    1/23

    INTRODUCTION

    As a part of the educational experience at COMSATS, CIIT organizes and conducts differenttypes of national and international academic activities. In this connection CIIT,ABBOTTABAD 0is holding its fifth high-Tech national level event consisting of seminars,

    symposia and exhibit ions under the umbrella of Techno Moot 2012. Like the previousyears, we hope that this year too, all the participants would benefit and enjoy thismult idimensional gathering of people from different sciences and technologies.

    TECHNOMOOT

    TechnoMoot2012 include the following events.

    All Pakistan Project Competit ion,EMCOT organized by Department of ElectricalEngineering

    Symposium on Computational Complexities, Innovations and Solutions, CCISorganized by Department of Mathematics

    Conference of Software Enterprises CSEorganized by Comsats IT Center

    VisionICT organized by Department of Computer Science

    Managing Innovation, Leadership, Entrepreneurship and Strategies, MILESorganized by Department of Management Sciences

    Science for Development S-Dev (organized for the fi rst time by Department ofEnvironmental Sciences in collaboration with the Departments of DevelopmentalStudies, & Pharmacy.)

    These seven events organized to benefit students, learners and practitioners alike will be held

    simultaneously these two days, in the various departments on campus.

    EMCOT 2012

    EMCOT 2012 is one of the research potential engineers in the field of Electrical Systems, Micro-Controllers and Telecommunications. This year, Electrical Department COMSATS Abbottabad

    campus has organized 8th event of EMCOT in the month of May 2012. Efforts have been made

    to extend the projects in education sector to industrial production level

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    2/23

    2

    Scope

    EMCOT intend to provide the students of Comsats as well as all other participating universities aplatform to interact with other members of their community as well as the industry.

    The scope of EMCOT is to develop an environment of academic where institutes can exchange

    their expertise in their respective fields. The program for this years EMCOT includes along withthe project competition, a number of seminars, a panel discussion and talks by eminent scientists

    and academicians on cutting edge Electrical and Electronic Engineering technologies.

    Objectives of the EMCOT

    Objective of EMCOT is listed below

    To provide plateform to all students for sharing knowledge and information.

    To builtconfidence,motivation among the students.

    To learn advanced techniquesStudent project exhibition and competition.

    Symposia on latest advancement in ELECTRICAL ENGINEERING.

    Deliverables

    Financial management committeeSend mails to all the committees

    Get acknowledge of E-mailsReceive response from all committeesPrepaid ini tial finance list from previous estimationEstimated demand by individual committeeSum of the total budgetFinalize the listSend budget to HOD to approvalSend the budget li st to direct for final approval and receive cash

    Poster and Invi tation Card Commit teePrepaid rough design for invitation card and postersFinalize the design by Heartz society

    Release the estimated cost from financial management headGive order to prepared posters and invitation cardReceive Printed cards and postersAfter print ing check fault in them

    Invitation and registration committeeSend invitation card to different universit ies and industr iesConfirmation of sent cards and postersPrepare E-mail format

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    3/23

    Approve the E-mail formatSend E-mailsGet acknowledge of E-mailsCall for confirmation to all the universit ies and industr iesMake a list for interested participants

    Prepare the list of online registrationReceive project purposed by participantMake a list of accepted projectsInform to that participant those are acceptable

    Millstones

    Financial management (18-4-12 to11-5-12)

    Financial estimation Total cost (2.5lac)

    Arrange of cash

    Budget approved

    Posters and invitation (8-4-12 to 2-05-12) Total cost (9050 Rs)

    Preparation of broachers ,posters, invitation cardsand banners

    Script for opening and closing ceremonies

    Invitations and registration (18-4-12 to 14-5-12) Total cost (2400 Rs)

    Sending invitations, letters, posters and broachers to different universities andindustries

    Registration of participants

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    4/23

    4

    LIMITATIONS OF EMCOT

    Human Resources

    Prescribed Time and Days

    Limited Financial Resources

    Maximum Project Stalls Boarding and Loading of Guest and Part icipants

    Area

    1) Human Resources: Required man power for arrangement of events related toEMCOT.

    2) Prescribed Time and Days: Within limited days, event has to be organized andshould successfully be completed.

    3) Limited Financial Resources: Overall financial expenses that are available inorder to arrange the whole event.

    4) Maximum Project Stalls: Arrangement of limited space for the display of themaximum projects.

    5) Boarding and Loading of Guest and Participants: Arrangement of a limitedspace for guests and part icipants coming from for away, who are invi ted toparticipate in the event.

    6) Area: Arrangement of limited area or space, where event has to be organized.

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    5/23

    TECHNICAL REQUIREMENTS

    Proper Space

    Backup Power Supply

    Time Management

    Financial Resources Technical Team

    1) Proper Space: Arrangement of proper space like hall or auditorium, where eventhas to be organized.

    2) Backup Power Supply: Arrangement of backup power supply in case of loadshedding like generators or UPS etc.

    3) Time Management: Specification of t ime in which, event has to be organized andshould successfully be completed.

    4) Financial Resources: Overall financial expenses that are available in order toarrange the whole event.

    5) Technical Team: Technical team also required to manage all the proceeding duringthe event.

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    6/23

    Activities

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    7/23

    Network Diagram

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    8/23

    Gantt chart

    In Gantt chart the bar chart includes a timescale band across the top that denotes units of time.

    The bars on the chart graphically represent the tasks in the table in terms of start and finish dates,duration, and status (for example, whether work on the task has started or not). Other elements

    on the chart, such as link lines, represent relationships between tasks. The Gantt chart is apopular and widely understood representation of project information throughout the projectmanagement world.

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    9/23

    WBS (WORK BREAKDOWN STRUCTURE)

    A Work Breakdown Structure (WBS) chart is a way of organizing a project into varying levels

    of detail using a hierarchical diagram. The traditional Work Breakdown Structure chart displaysvarying levels of detail starting with the highest or broadest at the top.

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    10/23

    1

    RESPONSIBILITY MARTIX

    It defines the tasks to be accomplished and who is responsible for which particular task and it

    also provide the information about people who are assisting a person in any task.

    Codin

    g

    DR

    IMDA

    D

    Aya

    z

    Ali

    Sha

    h

    UmairAas

    hiq

    Haid

    er Ali

    Aam

    ir

    Isla

    m

    AbidIq

    bal

    Hertz

    Socie

    ty

    Aiz

    az

    Ali

    AtiqaKiy

    ani

    SajidAq

    eel

    Khurra

    m Aziz

    Asmat

    ali

    1.0.0.

    0

    * + + + + + + + + + + +

    1.0.0.0

    .1

    * + +

    1.0.0.0.1.

    1 * + +1.0.0.0.1.

    2+ +

    1.0.0.0.1.

    3+ +

    1.0.0.0.1.

    4+ +

    1.0.0.0.1.

    5+ +

    1.0.0.0.1.

    6+ +

    1.0.0.0.1.

    7+ +

    1.0.0.0

    .2

    + * +

    1.0.0.0.2.

    1+ +

    1.0.0.0.2.

    2+ +

    1.0.0.0.2.

    3+ +

    1.0.0.0.2.

    4+ +

    1.0.0.0.2.

    5+ +

    1.0.0.0.3

    * + +

    1.0.0.0.3.

    1+ +

    1.0.0.0.3.

    2+ +

    1.0.0.0.3.

    3+ +

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    11/23

    1

    1.0.0.0.3.

    4+ +

    1.0.0.0.3.

    5+ +

    1.0.0.0.3.6 + +

    1.0.0.0.3.

    7+ +

    * =Head + =Assistant

    Risk Management

    Identification

    Delay in Arrangement of cash

    Short of money

    Printing Errors

    Load shedding

    Conformation of VIPs in Script dialogue

    Late invitation received

    Crash of online reception and registration system

    Risk Register

    Risk Impact Likelihood Detection When

    Delay in

    Arrangement of

    cash

    5 1 1 Planning

    Short of money 4 1 1 Execution

    Printing Errors 3 1 2 Execution

    Load shedding 5 4 1 Execution

    Conformation of

    VIPs in Script

    dialogue

    4 1 4 execution

    Late invitation

    received

    5 3 3 Planning

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    12/23

    1

    Risk Severity Matrix

    A Risk is the amount of harm that can be expected to occur during a given time period due to

    specific harm event.

    Risk response development

    In case of delay and shortage of money we wi ll arrange extra cash.

    To avoid print ing error we will arrange a person to continuously monitor theprinting.

    We wi ll properly acknowledge the invitation. Power backup should be available for continuous supply of electricity.

    Lists of guests and participants should be available in hard form also.

    Failure Mode and effect analysis

    Short ofmoney

    LoadShedding

    Delay inArrangement

    Of money

    Conformation

    of VIPs

    Printing

    errors

    Late

    invitation

    receive

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    13/23

    1

    Load Chart

    Financial management

    Invitation and Registration

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    14/23

    1

    Poster and Invitation Card

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    15/23

    1

    Earned Value management System

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    16/23

    1

    Planned Value Graph

    0 5 10 15 20 25 300

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    DAYS

    commulativecost

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    17/23

    1

    Status Report for PERIOD 10

    Task %completion Earned Value Planned value Actual value

    2 100% 40 40 50

    3 100% 20 20 25

    4 - - - -

    5 - - - -

    6 - - - -

    7 - - - -

    8 100% 100 100 90

    9 50% 20 20 25

    10 - - - -

    11 - - - -

    12 - - - -

    13 - - - -

    14 - - - -

    15 - - - -

    16 - - - -

    17 - - - -

    18 - - - -

    19 - - - -

    20 - - - -

    21 - - - -

    22 100% 3000 3000 3200

    23 100% 500 500 400

    24 - - - -

    25 - - - -

    26 - - - -

    27 - - - -

    28 100% 2000 2000 1500

    29 66.6% 100 100 50

    5780 5780 5340

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    18/23

    1

    CPI = EV/ ACCPI=5780/ 5340=1.0823

    SPI=EV/ PV

    SPI=5780/ 5780=1EAC=ETC+AC

    ETC=BAC-EV/ CPIETC=15480-5780/ 1.0823=8962.39EAC=14302

    TCPI=15480-5780/ 15480-5340=0.9566

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    19/23

    1

    Status Report for PERIOD 20

    Task %completion Earned Value Planned value Actual value

    2 - - - -

    3 - - - -

    4 - - - -

    5 - - - -

    6 - - - -

    7 - - - -

    8 - - - -

    9 100% 40 40 45

    10 100% 20 20 15

    11 100% 90 90 100

    12 - - - -

    13 - - - -

    14 - - - -

    15 - - - -

    16 - - - -

    17 - - - -

    18 - - - -

    19 - - - -

    20 - - - -

    21 - - - -

    22 - - - -

    23 - - - -

    24 - - - -

    25 - - - -

    26 - - - -

    27 - - - -

    28 - - - -

    29 100% 150 150 125

    30 100% 100 100 105

    31 100% 200 200 215

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    20/23

    2

    32 600 600 445

    CPI = EV/ ACCPI=600/ 605=0.9917

    SPI=EV/ PVSPI=600/ 600=1

    EAC=ETC+ACETC=BAC-EV/ CPI

    ETC=15480-600/ 0.9917=15004EAC=15609TCPI=15480-600/ 15480-605=1.0003

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    21/23

    2

    Status Report for PERIOD 30

    Task %completion Earned Value Planned value Actual value

    2 - - - -

    3 - - - -

    4 - - - -

    5 - - - -

    6 - - - -

    7 - - - -

    8 - - - -

    9 - - - -

    10 - - - -

    11 - - - -

    12 - - - -

    13 - - - -

    14 100% 500 500 490

    15 100% 2000 2000 1500

    16 - - - -

    17 - - - -

    18 100% 5000 5000 4500

    19 100% 500 500 450

    20 100% 1000 1000 1500

    21 - - - -

    22 - - - -

    23 - - - -

    24 - - - -

    25 - - - -

    26 - - - -

    27 - - - -

    28 - - - -

    29 - - - -

    30 - - - -

    31 - - - -

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    22/23

    2

    32 100% 2000 2000 1500

    11000 11000 9940

    CPI = EV/ ACCPI=11000/ 9940=1.106

    SPI=EV/ PVSPI=11000/ 11000=1EAC=ETC+AC

    ETC=BAC-EV/ CPIETC=15480-11000/ 1.106=4050.63

    EAC=13990TCPI=15480-11000/ 15480-9940=0.8086

  • 7/31/2019 Enigineering Economic Report by Ashakoor Comsats Atd

    23/23

    Control Graph

    Ashakoor

    Comsats Atd

    [email protected]