Mylan Engineering Guidelines
Mylan Engineering needs to:
– Provide a consistent approach to the Management of Capital Projects.
– Provide a similar product irrespective of location or assigned Engineer.
Engineering Guidelines
– to facilitate a consistency of approach and output
– provide staff with a toolbox to assist them in the preparation, execution
and reporting of projects.
– support and are supported by Good Engineering Practices and
Corporate Policies and Procedures.
– do not replace requirements contained in Corporate Policies and
Procedures
Guidelines apply to:
– All Capital Project Requests (CPR) that include monies for facilities,
utilities, or equipment when "total project" costs are in excess of U.S.
$50k.
3
Mylan Engineering Guidelines
Procedure
PCG-00
PCG-01
PCG-02
PCG-03
PCG-04
PCG-05
PCG-06
Title
Introduction & Contents
Project Initiation – Global Engineering Review & Approval
Project Scoping – Conceptual Studies & Basis of Design
Development Guideline
Cost Management, Forecasting and Invoice Approval
Project Change Orders
Project Scope Change Process
Capital Project Reporting
4
Additional Project Controls
Mylan Engineering Guidelines
Project Initiation – Global Engineering Review & Approval
• All Capital Project Requests (CPR) that include monies for facilities, utilities, or
equipment when "total project" costs are in excess of U.S. $50k. These CPRs must
be approved by Mylan Global Engineering at the initial planning stage of the project.
PCG-01
Based on the larger capital investment, additional project controls are required for
projects that fall under this Guideline.
Global Engineering Review & Approval (Signature / e-mail) > $50k
CPR Submission Supporting Data Checklist > $50k
Capital Project Cost Estimate Form > $250k
5
Mylan Engineering Guidelines
Global Engineering Review & Approval (Signature / e-mail)
• Review to occur as part of annual budget process (Capital Project Pre-Approval
Form) and during formal Capital Project Request (CPR) submission.
• Approval is to be maintained as part of the complete CPR documentation.
CPR Submission Supporting Data Checklist
• Help to facilitate the review process
• Required to be completed as support for the project and included with the Capital
Project Pre-Approval Form or Capital Project Request (CPR) at time of submission
for review by Mylan Global Engineering.
• As projects can vary greatly, the supporting information provided should support the
overall project narrative.
Capital Project Cost Estimate Form
• The Cost Estimate should give the necessary resolution to support the “Amount
Requested”
• Standardizes format
6
Mylan Engineering Guidelines
Project Scoping – Conceptual Studies & Basis of Design
Development Guideline PCG-02
Conceptual Studies & BOD Development
• Poor scope definition in an engineering design project increases the risk of
increased project time and costs.
• Document defines the minimum engineering deliverables necessary to support
Conceptual Studies and Basis of Design (BOD) Development
• Utilized to help ensure that the design objective meets the project objectives, and to
allow for key design decisions to be made early in the design process.
7
Mylan Engineering Guidelines
Cost Management, Forecasting and Invoice Approval
This guideline establishes accounting and financial record keeping and control reporting
requirements covering capital projects.
PCG-03
Standard templates to use.
8
Mylan Engineering Guidelines
Project Change Orders PCG-04
Project Scope Change Process PCG-05
This guideline establishes accounting and financial record keeping and control reporting
requirements regarding change orders to an original scope of work of a contact that
occur during project execution.
• Applies to changes to specification & design intent that are proposed from the time
of BOD Approval to the completion of Performance Qualification
• For a change to be in the context of this guideline, it must be a rather a fundamental,
far reaching change to an Approved Design
• Used to identifying significant changes and assessing their effect on the project so
that the Project Team may decide to adopt or to reject a change, knowing the
implications of the decision.
• Allows for audit trail to be maintained
9
Mylan Engineering Guidelines
Capital Project Reporting PCG-06
• Guideline details the specific requirements in updating and presenting project
information on a monthly basis.
• Standardizes a monthly report that shall be generated - a one-page summary under
the three headings of Scope, Cost and Schedule.