  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005 i

    Amendment History

    Amendment Date Original issue February 2005 Plans A(BS)101M,106M,124M,131M,134S June 2009 New clause 5.19 added – Road Names November 2009 OSD map revised December 2009 OSD in append D relocated to append B December 2009 Pedestrian refuge guideline added to Append C February 2010 Standard Council Plan A(BS)143M added to append I February 2010 Section 10.1 of app’d D- list of programmes March 2010 New Clause (e) to positive covenants OSD September 2010 Path paving Policy updated October 2010 New plan A(BS)M 152 added October 2010 Section 5.18 amended to include reference to Boom gates and Council Plan A(BS)152M October 2010 Various amendments to reflect changes to Councils internal structure October 2010 Section 3.1 amended to reflect latest versions of acceptable design manuals October 2010 Section 10.1 appnd D list of progm amended November 2012 Pedestrian refuge policy deleted November 2012 OSD map updated November 2012 Various external reference manuals updated Ie Austroad publications

    November 2012

    Standard Plan A(BS) 113M updated November 2012 Standard Plan A(BS) 114M deleted November 2012 Amended Table 3.2 Road Design ParameterCertified stockpile definition (Glossary)

    February 2017June 2017

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    ii

    Blacktown City Council

    ENGINEERING GUIDE FOR DEVELOPMENT

    2005

    FOREWORD This Guide, and its accompanying document, Council's Work Specification - Civil, have been prepared to provide engineering guidelines for the subdivision and development of land within the Blacktown City Council area.

    The aim of the Guide is to facilitate the efficient processing of engineering plan submissions, and to ensure that infrastructure associated with any development is designed and constructed to be safe, serviceable, economical to maintain and meets community expectations.

    Applicants should be aware that each development is required to be treated on its merits, and that approval is dependant on the overall impact of the development and not solely on compliance with minimum engineering standards.

    Nothing in this Guide is to be construed as limiting, in any way, Council's rights to impose differing conditions when approving development proposals, nor limiting the discretion of Council's Co-ordinator Engineering Approvals or his nominated representative to vary any necessary engineering requirements in respect of a particular development, having regard to good engineering practice.

    Council wishes to acknowledge the assistance freely given by other Councils, Consultants and Contractors who suggested matters that required updating, new processes and products that may be adopted or provided assistance in this latest revision to ensure that this document represents current "best practice".

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    iii

    BLACKTOWN CITY COUNCIL GLOSSARY

    1:5 (V:H) Slope of 1 vertical to 5 horizontal.

    AC Asphaltic Concrete.

    ACRS Australian Certification Authority for Reinforcing Steel.

    Accredited Person qualified to issue certificates and operate as a Principal Certifying Certifier Authority (PCA) under the Environmental Planning and Assessment Act

    1979.

    Applicant Any person/s, company or entity representing the Applicant for the purpose of constructing the Works. This may also include Council.

    AR&R (1998) Australian Rainfall and Run-off (1998).

    ARI

    AS

    Certified

    Average Recurrence Interval.

    Australian Standards published by the Standards Association of Australia and being current at the time of application.

    A stockpile that has been certified by a NATA registered laboratory as complying with Council's specification (for relevant material type). Stockpile

    Co-ordinator Council's Co-ordinator Engineering Approvals of Council's Development Services Unit.

    Council Blacktown City Council as represented by its employees.

    Council Person approving or inspecting works on behalf of Council. Engineer

    DC or Notice of Determination giving Subdivision or Development Consent. Consent

    Development Person carrying out the day to day inspections on behalf of Council. Supervisor

    Documents All expressed and implied Specifications, Standards, Drawings and Correspondence, which are related to the works and referred to by Council or issued by Council.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005 v

    Engineer or Person who is a practising Engineer registered on the Institution of Engineers, Registered Australia, National Professional Engineers Register (NPER) in the relevant field Engineer of work. EP&A Act Environmental Planning and Assessment Act 1979, as amended. EPA Environmental Protection Authority. FRC pipe Fibre Reinforced Cement pipe. Guide Blacktown City Council's Engineering Guide for Development. Maintenance Period of a minimum of Twelve (12) months after the issue of the Period Subdivision Certificate (release of the Plan of Subdivision) or Development

    Completion, or such time as Council deems reasonable for the Final Certificate of Completion.

    NATA National Association of Testing Authorities, Australia. NATA A laboratory accredited by NATA to undertake the specific test referred to in Registered the body of the text. Laboratory OH&S Occupational Health & Safety. OSD On-site Stormwater Detention. PSD Permissible Site Discharge. RCP Reinforced Concrete Pipe. RHS Rectangular Hollow Section. RMS Roads & Maritime Services (Formerly RTA) RTA Roads & Traffic Authority, New South Wales ( now RMS) Site Area of land being developed under the Subdivision or Development Approval. SQID Stormwater Quality Improvement Device. SSR Site Storage Requirement. Supervisor The person appointed by the Applicant to supervise the construction Works and

    to represent the Applicant.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005 vi

    Surveyor Registered Surveyor. UCS Unconfined Compressive Strength. UPVC Unplasticised Polyvinyl Chloride (referring to pipe). VCP Vitrified Clay Pipe. WAE Works as Executed Plan. Works The development of land as described by the Drawings and Specifications (the

    Documents) as proposed by the Applicant and as cited and approved by Council "For Construction" including all the area of the land being developed.

    WSUD Water Sensitive Urban Design.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    vi

    TABLE OF CONTENTS

    SUMMARY

    1. GENERAL PROCEDURES 2. ENGINEERING DRAWINGS 3. ROAD DESIGN 4. DRAINAGE DESIGN 5. MISCELLANEOUS REQUIREMENTS 6. APPENDICES A. CHECKLIST FOR ENGINEERING PLANS B. ON-SITE DETENTION GENERAL GUIDELINES & CHECKLIST C. COUNCIL POLICIES AND GUIDELINES

    • PATH PAVING POLICY • PEDESTRIAN REFUGE GUIDELINE

    D. DRAINAGE DESIGN MANUAL E. BOND DOCUMENTS, FORMAT & INSTRUCTIONS F. STANDARD RECITAL FOR TERMS OF EASEMENTS, COVENANTS &

    RESTRICTIONS G. EXAMPLE OF A LOT FILL PLAN H. EXAMPLE EASEMENT CERTIFICATE I. STANDARD DRAWINGS

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    vii

    ENGINEERING GUIDE FOR DEVELOPMENT - 2004

    TABLE OF CONTENTS CONTENTS PAGE NO. FOREWORD ..................................................................................................... i GLOSSARY ....................................................................................................... ii 1 GENERAL SPECIFICATION OF WORKS

    1.1 General ........................................................................................................ 1 - 1 1.2 Aim .............................................................................................................. 1 - 1 1.3 Engineering Plans, Inspections & Accredited Certifiers ............................. 1 - 1 1.4 Overview of Engineering Process for the Applicant ................................... 1 - 2 1.5 Engineering Survey & Bench Marks .......................................................... 1 - 5 1.6 Engineering Drawings ................................................................................. 1 - 6 1.7 Persons Qualified ........................................................................................ 1 - 6 1.8 Consultation ................................................................................................ 1 - 6 1.9 Inspection of Works .................................................................................... 1 - 6 1.10 Tree Preservation ......................................................................................... 1 - 7 1.11 Street Trees .................................................................................................. 1 - 8 1.12 Erosion & Sediment Control ....................................................................... 1 - 8 1.13 Road Safety Audit & OH&S Requirements ................................................ 1 - 8 1.14 Bonds ........................................................................................................... 1 - 9 1.15 Contributions/Monetary Payments .............................................................. 1 - 10 1.16 Works-As-Executed (W.A.E.) Plans ........................................................... 1 - 10 1.17 Certificates .................................................................................................. 1 - 11 1.18 Written Consents ......................................................................................... 1 - 12 1.19 Street Lighting ............................................................................................. 1 - 12

    2 ENGINEERING DRAWINGS

    2.1 Scope ........................................................................................................... 2 - 1 2.2 Aim .............................................................................................................. 2 - 1 2.3 General Requirements ................................................................................. 2 - 1 2.4 Roads & Drainage Drawings ....................................................................... 2 - 1 2.5 On-site Stormwater Detection Drawings .................................................... 2 - 2 2.6 Title Blocks ................................................................................................. 2 - 2 2.7 Title Sheet/Layout Plan ............................................................................... 2 - 2 2.8 Detail Plan ................................................................................................... 2 - 3 2.9 Road Long Section(s) .................................................................................. 2 - 5

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    viii

    CONTENTS PAGE NO.

    2.10 Road Cross Section(s) ................................................................................. 2 - 5 2.11 Typical Road Cross Section(s) .................................................................... 2 - 6 2.12 Kerb Return, Cul-de-Sac & Splay Corner Details ...................................... 2 - 6 2.13 Traffic Calming Devices, Median Islands & Other .................................... 2 - 7

    Miscellaneous Details 2.14 Pathways ...................................................................................................... 2 - 7 2.15 Drainage Catchment Plan ............................................................................ 2 - 8 2.16 Drainage Calculations ................................................................................. 2 - 8 2.17 Drainage Longitudinal Section(s) ............................................................... 2 - 9 2.18 Other Drainage Details ................................................................................ 2 - 9 2.19 Easement Widths ......................................................................................... 2 - 11 2.20 Overland Flow Paths ................................................................................... 2 - 11 2.21 Retaining Walls ........................................................................................... 2 - 12 2.22 Erosion & Sediment Control Measures ....................................................... 2 - 12 2.23 Traffic Management Measures .................................................................... 2 - 13 2.24 Adjoining Owners Permission .................................................................... 2 - 14 2.25 Works-As-Executed Plans for Engineering Works ..................................... 2 - 14 2.26 Fill Plans ...................................................................................................... 2 - 17 2.27 Sheet Sizes ................................................................................................... 2 - 17 2.28 Scales ........................................................................................................... 2 - 18 2.29 Dimensions .................................................................................................. 2 - 18

    3 ROAD DESIGNS

    3.1 Scope ........................................................................................................... 3 - 1 3.2 Aim .............................................................................................................. 3 - 1 3.3 Planning Standards ...................................................................................... 3 - 1 3.4 Half Width Roads ........................................................................................ 3 - 3 3.5 Construction Specification .......................................................................... 3 - 3 3.6 Pavement Design ......................................................................................... 3 - 3 3.7 Pavement Surfacing ..................................................................................... 3 - 5 3.8 Geometric Design - General Principles (including designing for salinity) .......... 3 - 5 3.9 Design Speed ............................................................................................... 3 - 6 3.10 Sight Distance ............................................................................................. 3 - 7 3.11 Horizontal Alignment .................................................................................. 3 - 8 3.12 Transitions & Widening on Curves ............................................................. 3 - 8 3.13 Longitudinal Gradients ................................................................................ 3 - 8 3.14 Vertical Curves ............................................................................................ 3 - 9 3.15 Super-Elevation ........................................................................................... 3 - 10 3.16 Carriageway Crossfall ................................................................................. 3 - 10 3.17 Kerb & Gutter .............................................................................................. 3 - 11 3.18 Footpath Crossfall ....................................................................................... 3 - 11 3.19 Berms .......................................................................................................... 3 - 11 3.20 Batters .......................................................................................................... 3 - 11

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005 ix

    CONTENTS PAGE NO.

    3.21 Intersections ................................................................................................ 3 - 12 3.22 Kerb Returns ............................................................................................... 3 - 12 3.23 Cul-de-sac Head Kerb Guttering ................................................................. 3 - 13 3.24 Roundabouts ................................................................................................ 3 - 14 3.25 Traffic Calming Devices ............................................................................. 3 - 14

    4 DRAINAGE DESIGN

    4.1 Scope ........................................................................................................... 4 - 1 4.2 Aim .............................................................................................................. 4 - 1 4.3 General Requirements ................................................................................. 4 - 1 4.4 Trunk Drainage Designs .............................................................................. 4 - 1 4.5 Extent of Works .......................................................................................... 4 - 1 4.6 Adjoining Owners Consent/Creation of Drainage Easements .................... 4 - 2 4.7 Interallotment Drainage ............................................................................... 4 - 2 4.8 Subsoil Drainage ......................................................................................... 4 - 2 4.9 Flood Liable Land ....................................................................................... 4 - 3 4.10 Pit Design .................................................................................................... 4 - 3 4.11 Water Sensitive Urban Design (WSUD) ..................................................... 4 - 3

    5 MISCELLANEOUS REQURIEMENTS

    5.1 Scope ........................................................................................................... 5 - 1 5.2 Aim .............................................................................................................. 5 - 1 5.3 Kerbs, Laybacks & Kerb Ramps ................................................................. 5 - 1 5.4 Path Paving .................................................................................................. 5 - 1 5.5 Battleaxe Handles ........................................................................................ 5 - 2 5.6 Lot Filling .................................................................................................... 5 - 2 5.7 Conduits/Ducts ............................................................................................ 5 - 3 5.8 Safety Notation ............................................................................................ 5 - 3 5.9 Temporary Roads ........................................................................................ 5 - 3 5.10 Street Furniture ............................................................................................ 5 - 4 5.11 Debris Disposal ........................................................................................... 5 - 4 5.12 Insurance ..................................................................................................... 5 - 4 5.13 Traffic Control for Works in Public Roads ................................................. 5 - 4 5.14 Soil & Water Management .......................................................................... 5 - 6 5.15 Landscaping of Roundabouts & Median Strips .......................................... 5 - 7 5.16 Bridges & Culverts ...................................................................................... 5 - 9 5.17 Safety Barriers for Roads & Bridges ........................................................... 5 - 9 5.18 Fencing & Access Points Adjacent to Public Reserves, Drainage

    Reserves and Channels ................................................................................ 5 – 9 5.19 Road Names..................................................................................................5 – 9

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT -February 2005

    x

    6 APPENDICES

    A. Checklist for Engineering Plans .................................................................. A - 1 B. On-site Detention General Guidelines & Checklist .................................... B - 1 C. Councils Policies and Guidelines ................................................................ C-1 Path paving policy Pedestrian Refuge Guideline D. Drainage Design Manual ............................................................................. D -1 E. Bond Documents, Format & Instructions ................................................... E - 1 F. Standard Recital for Terms of Easements, Covenants & Restrictions ........ F - 1 G. Example of a Lot Fill Plan………………………………………………...G - 1 H. Example Easement Certificate…………………………………………….H - 1 I Standard Drawings ...................................................................................... I - 1

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 1

    1. GENERAL PROCEDURES 1.1 Scope This section of the Engineering Guide sets out Council's general procedures

    and practices in respect of engineering requirements for subdivision and development of land within the Council area.

    1.2 Aim To provide an Applicant with an outline of Council's engineering procedures

    for subdivisions and developments. 1.3 Engineering Plans, Inspections & Accredited Certifiers In this Guide, whenever the term "Engineering Plan" is used, this is deemed to

    also be a reference to engineering plans associated with Construction Certificates issued by Council or Private Accredited Certifiers under the EP&A Act 1979, and Engineering Approvals issued by Council under the Roads Act 1993 and Local Government Act 1993.

    Private Accredited Certifiers may issue Construction and Compliance

    Certificates for subdivision and development works in accordance with the requirements of the EP&A Act 1979. Therefore any reference made in this Guide to approvals or inspections by Council’s Engineers or Development Supervisors for works under the EP&A Act 1979 shall also be deemed to be a reference to certificates issued and inspections carried out by Private Accredited Certifiers under the EP&A Act 1979.

    Private Accredited Certifiers do not have any authority to issue Engineering

    Approvals or carry out inspections for works on Public Roads under the Roads Act 1993.

    It should also be noted that Construction Certificates cannot be issued for

    works on sites that are not part of the "subject land" for which the Development Consent has been issued.

    An example is interallotment drainage through adjacent lots that are not

    included in the "subject land". In this case, a separate Section 68 Local Government Act 1993 Approval would be required for the drainage works. This form of approval can only be issued by Council.

    Private Accredited Certifiers have no authority to vary the requirements of this

    Guide. They must comply with all of the Guide’s requirements prior to issuing any Construction or Compliance Certificates under the EP&A Act 1979.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 2

    1.4 Overview of Engineering Process for the Applicant This section of the Guide sets out the suggested steps an Applicant should

    follow once a Notice of Determination giving Development Consent to a development has been issued by Council. All other steps required prior to issue of consent can be found in Blacktown Development Control Plan 1992.

    A. Read Notice of Determination (Development Consent): Where you are unsure of the meaning or extent of any condition,

    contact the Council and seek clarification. (Development Consent No./File No. will help in this instance.)

    Note: Construction Certificates cannot be issued until all Pre-

    Construction Certificate requirements/conditions of the Development Consent have been satisfied.

    B. Engage an Engineering Consultant/Project Manager: Satisfy yourself that the consultant has the required expertise and do

    not decide on your consultant simply on the basis of fees. A higher fee may result in substantial savings in approval time/construction costs due to the consultant's expertise.

    C. Give the consultant a copy of the whole of the Notice of

    Determination: Any approved plans or other documents should also be given to the

    consultant so he/she can fully understand the project. D. Let the consultant do the work: Once the consultant has been engaged, Council's officers will have

    only one contact who is co-ordinating the progress of your development. Time delays often arise where inexperienced Applicants try to share the project management role.

    E. Engineering plans are prepared by the consultant:.

    The consultant is to arrange survey and engineering designs that will fulfil the conditions of consent. These plans, when approved, will be used by the contractor to construct the works.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 3

    F. Lodge Engineering Plans with Council for approval and pay assessment and inspection fees:

    Lodge Engineering Plans, together with any other documents

    /calculations/information and/or any clearances from government authorities required to satisfy the conditions of consent. Council's Engineer will provide a quote for the engineering fees. Once this is accepted, Council's Engineer will assess the Engineering Plans to ensure compliance with conditions of consent and other Council requirements.

    G. Engineering plans returned to consultant for amendment (if

    required): The Consultant will be advised if any amendments are required to the

    Engineering Plans, and if any other outstanding items are required prior to the release of approved Engineering Plans.

    H. Engineering plans relodged with Council: The Consultant should have carried out all the amendments required by

    Council. If the consultant needs clarification of any requirements, Council's Engineers are available for discussion. The Consultant must also ensure that Council's "Red Mark Up" Plan (showing required corrections) is returned to Council with the amended plans. This will expedite their assessment.

    I. Engineering plans approved: When Council is satisfied that the engineering plans will enable work

    to be constructed with a minimum of field supervision the plans are approved and issued in accordance with the Consent conditions.

    J. Construction of Works: The Consultant/Applicant will engage a contractor to carry out the

    works in accordance with the approved plans. Council's Engineer or Development Supervisor will inspect the work to ensure the contractor carries the work out in accordance with the approved plans and with Council's "Works Specification - Civil".

    K. Lodge Works-As-Executed Plan: Together with any Hydraulic (OSD), Structural or Compliance

    Certificates, prior to requesting the final inspection.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 4

    L. Preliminary final inspection: When the Applicant considers that the works to be complete, Council's

    Engineer/Supervisor will inspect the work and any defects will be brought to the Applicant's attention for rectification.

    M. Final inspection: When all the defects, identified in the Preliminary Final Inspection, are

    rectified the Applicant shall request a Final Inspection. Council's Engineer/Development Supervisor will reinspect the work to confirm that all the defects have been rectified.

    N. Check Notice of Determination Before requesting the issue of a Subdivision Certificate (in the case of

    subdivisions) or in other cases prior to the issue of an Occupation Certificate for the development, the development consent must be checked in detail. The Consultant/Applicant must ensure all conditions have been satisfied including, but not limited to:

    * Compliance with all engineering conditions required by the

    Development Consent, * Payment of fees and contributions, * Lodgement of completed Deed of Agreement for bonded

    works, * Lodgement of certificates required by the Works Specification, * Lodgement of a Works-As-Executed Plan, and * Lodgement of Hydraulic & Structural certificates. O. Issue of Subdivision Certificate/Occupation Certificate: When all engineering conditions of consent have been satisfied and the

    plan of subdivision and accompanying legal documents are correct, Council's Engineer for the project will recommend release of the plan of subdivision. The plan will only be released by Council if all conditions of consent have been satisfied and/or securities have been established for outstanding works.

    P. Defects Liability/Maintenance Period: (a) Subdivisions: Upon the issue of a Subdivision Certificate the

    constructed civil engineering work will enter the Maintenance Period. During this period any defect which becomes evident will be the responsibility of the Applicant to rectify. The

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 5

    Maintenance Period lasts for at least 12 months from the issue of the Subdivision Certificate. At the end of the Maintenance Period, after any defects have been rectified, the Bond will be released and Council will issue an "Acceptance of Works" Certificate.

    (b) All Other Development: Upon a clearance at the Final

    Inspection (Step M) the constructed work will come under a Maintenance Period of at least 12 months. At the end of this period and upon rectification of any defects that become evident during that period, Council will issue an "Acceptance of Works" Certificate.

    Q. Completion of Project: When all bonded works have been satisfactorily completed Council

    will, upon request, release all securities held over the works. In the case of Path Paving Bonds in subdivisions, 2 years or more can elapse between the "Acceptance of Works" and the release of the bond. Council provides the Applicant with the option of making a monetary payment for the works rather than be burdened with a long-term bond in accordance with Council's Path Paving Policy (January 2001). In this event, Council will use the Monies to construct the path paving when building activities are finalised and when damage is less likely.

    This monetary payment is based on the costs set out in Council's

    Goods and Services Pricing Schedule. These costs include a provision for the delay in construction and are updated every year.

    1.5 Engineering Survey & Bench Marks The engineering survey shall be carried out using the ISG co-ordinate

    reference system and all levels shall be on Australian Height Datum (A.H.D.). The Co-ordinator's approval shall be obtained if another datum is to be adopted.

    The survey shall accurately show the landform to facilitate the best possible

    design and construction of road works and drainage consistent with minimum interference to the existing amenity of the area.

    Bench Marks shall be established at intervals not greater than 600 metres and

    are to be placed where they will not be disturbed. This requirement may be waived by the Co-ordinator where State Survey Marks exist. One copy of each locality sketch shall be submitted to Council at the same time as the final Plan of Subdivision (Subdivision Certificate).

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 6

    1.6 Engineering Drawings Engineering Drawings shall be submitted in triplicate, with a covering letter,

    by the Consultant. One set of approved plans will be returned to the Consultant with an approval letter. It is suggested that one (1) set of plans be submitted for an initial check by Council's Engineers, followed by the submission of the full set upon completion of any amendments required by Council.

    The preparation of engineering drawings for developments and subdivisions

    shall be carried out in accordance with Section 2 - "Engineering Drawings", of this Guide.

    The civil engineering drawings will be checked by Council's Engineers for

    compliance with these guidelines. It is the responsibility of the Consultant to ensure that the designs, calculations and specifications comply with Consent Conditions, this Guide, relevant Australian Standards and other Council Codes. Approval of the drawings does not relieve the Applicant from rectifying any errors or omissions which become evident during construction or the liability period.

    The Applicant is required to comply with Council's current standards and if

    work has not substantially commenced within two (2) years of the date of the endorsed approval, the Co-ordinator may require that revised engineering drawings, calculations and specifications be submitted for a renewed approval.

    1.7 Persons Qualified Unless stated otherwise in this Guide, Council requires that design plans be

    prepared to Council's standards by a person either holding qualifications acceptable for Corporate Membership of the Institution of Engineers Australia or approved by the Co-ordinator and/or who has proven experience in the preparation of plans and specifications for land development.

    1.8 Consultation Designers are encouraged to consult with Council and other relevant

    authorities during the preparation of design plans. 1.9 Inspection of Works All road and drainage works carried out by the Applicant that will become part

    of Council's infrastructure, are to be inspected by Council's Engineers and Development Supervisors in accordance with Council's Works Specification - Civil.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 7

    In addition to all engineering works associated with land subdivisions, Council's Engineers and Development Supervisors will also approve and carry out inspections for road and drainage works on Public Roads, On-site Stormwater Detention Systems, Interallotment Stormwater Drainage Lines, WSUD features, Stormwater Quality Improvement Devices, Stormwater flow paths and channels, and Community Title/ Private Access Roads.

    A separate application shall be submitted to Council in respect of footway and

    gutter crossings and inspections shall be arranged with Council's Maintenance Section.

    1.10 Tree Preservation Applicants are advised that NO trees shall be removed without Council's

    permission. The Applicant shall provide a tree survey plan detailing the trees to be retained and clearly defining any trees proposed for removal.

    The following Tree Preservation Order applies to the City: Blacktown City Council Tree Preservation Policy is covered by Clause 25

    of the Blacktown Local Environmental Plan 1988. "Tree Preservation 25. (1) A person shall not ringbark, cut down, lop, top, remove, injure

    or wilfully destroy any tree, or cause any tree to be ringbarked, but down, topped, lopped, removed, injured or wilfully destroyed, except with the consent of the Council.

    (2) In any proceedings for an offence arising under this Clause, it

    shall be sufficient defence to prove that the tree ringbarked, cut down, topped, lopped, removed, injured or wilfully destroyed, was dying or dead or had become dangerous.

    (3) This clause does not apply to trees in State forest or on land

    reserved as a timber reserve within the meaning of the Forestry Act 1916, or to trees required to be lopped in accordance with Regulation 38 or 29 of the Overhead Line Construction and Maintenance Regulations 1962, or to any trees which are under the control or management of Sydney Water.

    (4) This clause does not operate so as to require a consent to be

    given pursuant to this clause for the carrying out of development at a plant nursery if the development could be lawfully carried out at the plant nursery in the absence of this clause."

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 8

    Council may require Applicants to lodge a Tree Bond to ensure trees are not damaged or removed during the construction of works.

    Engineering Plans must bear the following note: Prior to the commencement of any earthworks, and after the road centrelines

    have been pegged and/or permanently marked, the site must be inspected by Council's representative and the Applicant's representative to identify and appropriately mark:

    (a) The trees to be retained. (b) All trees to be left undisturbed and cordoned off. All trees to be retained are to be protected by paraweb fencing, firmly staked

    four (4) metres from the trunk of the tree. This fencing is to be erected prior to the commencement of any site works and is to be maintained in position for the duration of the works. The area within the drip line of the tree should not be used for the stockpiling of new or demolition material, nor for vehicular or pedestrian convenience or uses that would compact the soil in this area.

    1.11 Street Trees Where the Applicant proposes to plant street trees in lieu of the Section 94

    Tree Contribution, or proposes to landscape roundabouts and medians, works must be carried out in accordance with the requirements set out in Council's "Tree Planting Study". The Applicant must obtain written agreement from Council prior to proceeding with these works.

    1.12 Erosion and Sediment Control All developments, where the site is disturbed, shall provide Erosion and

    Sedimentation Control in accordance with the requirements of the NSW Department of Environment and Conservation, and Council.

    Design plans shall be in accordance with the NSW Department of

    Environment and Conservation Guidelines, Landcom's "Managing Urban Stormwater - Soil and Construction - Volume 1" 4th Edition (2004), and Section 5.14 of this Guide.

    1.13 Road Safety Audit and OH&S Requirements Consultants preparing Engineering Plans must carry out a road safety audit of

    the site, drawings and associated documents to ensure that all the requirements as set out in Austroad's "Road Safety Audit" Manual, Second Edition 2002, have been satisfied.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 9

    It is the responsibility of the Consultant/Designer to ensure that they have

    addressed all relevant Occupational Health & Safety concerns, including but not limited to Traffic Management Plans for works on Public Roads, and Confined Spaces Act requirements for SQIDs and OSD storages.

    1.14 Bonds 1.14.1 General

    Council's Development procedures provide for the lodgement of bonds where it is impractical to complete certain aspects of the infrastructure work or where it is necessary to defer construction until building activities have been substantially completed. All bonds must be in accordance with Council's Standard format (see Appendix "E").

    Bond amounts will be provided upon request. Upon written request from the Applicant and satisfactory completion of the Maintenance Period, or the works (whichever is the case), the Bond or any amount remaining will be released by Council.

    1.14.2 Path Paving

    Path paving construction in accordance with Council's Path Paving Policy (see Appendix "C") shall be deferred for a period following practical completion of the road works.

    Two options are available to the Applicant:-

    * Bond the Works, by lodging an appropriate security with a

    Deed of Agreement. * Monetary Payment, where Council will use the monies for

    construction of paths at a later, appropriate time.

    1.14.3 Maintenance

    Prior to the issue of a Subdivision Certificate (for subdivisions) or at practical completion of works (for other developments), a Bank Guarantee or Cash Security, to the amount of 5% (with a minimum amount of $5,000) of the value of the whole of the works to be constructed, must be lodged with Council. This is to provide for the satisfactory performance of works and the replacement of any failed or unsatisfactory work and any repairs required, inclusive of the maintenance of any traffic control facilities.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 10

    The bond will be held by the Council for a period of at least 12 months from the date of issue of the Subdivision Certificate/release of the Plan of Subdivision or the date of completion of the works, whichever is the latter. During this time the Applicant is responsible for maintenance of the works. Any failure on his behalf may lead to call-up of all or part of the security to enable remedial works to be undertaken by Council.

    1.15 Contributions/Monetary Payments Contributions and/or monetary payments for certain outstanding items must be

    lodged prior to the issue of the Subdivision Certificate, or upon practical completion of ½ width road works associated with developments as detailed in the Consent.

    1.15.1 A.C. Sealing

    Subdividers are required to lodge a cash payment to cover the cost of the final 25mm layer of Asphaltic Concrete (A.C.) following installation of services by the various authorities. Such payment is assessed by Council after submission of Work-As-Executed plans and is based on Council's current construction rates.

    1.15.2 Street Trees A cash contribution in accordance with Section 94 (EP&A Act) Contributions Plan No.10 is required in respect of each new lot towards Council's provision of street trees at a suitable time in the development of the area.

    1.15.3 Path Paving

    As detailed in Council's Path Paving Policy (Appendix C), a cash contribution may be lodged as an alternative to the bonding of these works.

    1.16 Works-As-Executed (W.A.E.) Plans

    Following the completion of engineering works of a subdivision or development, a "Work-As-Executed" plan is required to be prepared by a Registered Surveyor or "Persons Qualified" (See Section 1.7) and forwarded to Council prior to the final inspection.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 11

    The WAE plans must show the matters listed below and as detailed in Section 2.25 - Engineering Drawings, of this Guide: * all works have been completed generally in accordance with the

    approved plans and specification, * any departure from the approved plans, * any additional/deleted work, * the location of conduits, subsoil lines, stub mains and interallotment

    drainage lines, * pipeline long sections showing the constructed invert levels of each

    pipe at each pit and pipe dimensions, * details of overland flow provisions, * site regrading areas by new contours, and * all other details which have a bearing on the extent of works and their

    acceptance by Council.

    1.17 Certificates and Slope Junction Plans Prior to issue of a Subdivision Certificate, Occupation Certificate or upon

    completion of works, the following Certificates and Plans must be lodged:

    1.17.1 Compaction Certificates

    The final submission requires lodgement of the road pavement compaction certificates for all stages of the road pavement construction, lot filling and lot classification which have been prepared by a N.A.T.A. laboratory.

    A lot fill diagram, an example of which can be found in Appendix "G", must be provided where lots have been filled. The diagram will apply to all lots that have been filled in excess of 250mm. Two (2) copies shall be provided.

    1.17.2 Easement Certificates

    The final submission requires lodgement of the Surveyor's Certificate in the form shown in Appendix "H" of this Guide. This is to certify that all pipes and drainage structures are located within the proposed drainage easements.

    1.17.3 Material Compliance Certificates

    Material Compliance Certificates for all road pavement materials will be required to be submitted prior to issue of the Subdivision Certificate or upon completion of the works.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 12

    1.17.4 Engineer's Certificate

    Where structural work has been undertaken on a project a certificate from a Registered Engineer must be lodged certifying the adequacy of the structure for the imposed loads.

    For OSD systems, a Hydraulic Certificate from "Persons Qualified"

    (See Section 1.7) shall be lodged with Council certifying that the system will function hydraulically as per design requirements.

    1.17.5 Slope Junction Plan (Interallotment Drainage)

    A slope junction plan indicating location, depth and off-sets of all slope junctions shall be prepared by the project engineer/surveyor and submitted to Council. Two (2) copies shall be provided.

    1.18 Written Consents

    Where work has been carried out on adjoining properties, or a claim

    made by an affected property owner, a written clearance that all outstanding claims have been met, must be lodged with the final document submission.

    1.19 Street Lighting

    1.19.1 General

    Council requires all new lighting levels to be in accordance with AS/NZ 1158 in its various parts and to comply with all the requirements of Integral Energy's document "General terms and Conditions for the Connection of Public Lighting Assets".

    1.19.2 Arterial and Sub-Arterial Roads

    The lighting of arterial and sub-arterial (Traffic Route Lighting) roads

    must comply with AS/NZS 1158.Part1.1 – Vehicular Traffic (Category V) Lighting – Performance and Installation Design Requirements 1997, using the appropriate lighting categories.

    1.19.3 Residential Roads and Public Places

    The Lighting of residential roads and public places must comply with AS/NZS 1158 Residential Street Lighting Part 3.1: Pedestrian Area (category P) Lighting – Performance and Installation Design Requirements 1999, using the appropriate lighting categories.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 13

    1.19.4 Approval of Proposed Schemes The appropriate levels of street lighting for any proposed scheme will

    be identified by Council's Manager Transport Management Services. To facilitate this, plans of the proposed scheme showing the limits of all proposed works, all traffic management facilities and devices, pedestrian facilities and all other relevant information must be submitted to Council's Manager Transport Management Services who will assess the proposal to ensure compliance with Council's Street Lighting Policy and the relevant part of AS/NZ 1158.

    The appropriate street lighting categories within each proposal will be

    forwarded to the applicant by way of a Design Brief Checklist to enable a street lighting design for the proposed works to be prepared for Council's approval and acceptance.

    To further assist the designer, designs should also be prepared in

    accordance with Section 6 - Public Lighting Assets of Integral Energy's document "SPJ 4004 Network Connections - Contestable Works - General Terms and Conditions" which is available via Integral Energy's internet site at www.integral.com.au.

    All street lighting schemes must be prepared by an accredited Level 3

    service provider and submitted to Council for its approval prior to a Construction Approval being granted by Integral Energy. Upon satisfactory completion of the works a 'Notification of Arrangement" will be issued by Integral Energy.

    1.19.5 Subdivision Schemes

    (i) For residential roads in areas having underground reticulation

    of electricity, the basic lighting category should normally be P4. The type of street lighting to be used to achieve the P4 Category is 2 x 14 Watt T5 Street light to be mounted on dedicated lighting columns at about 55m spacings.

    (ii) For sub-arterial or principal roads which connect arterial or

    main roads to areas of development within a region, or which carry traffic directly from one part of a region to another part, the minimum lighting requirement should be either V5 or P3 and in accordance with the standard.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    1 - 14

    (iii) In pathways the standard lamp used in pathways shall be an 80W HP Mercury lamp.

    1.19.6 Traffic Management Devices

    Lighting for traffic management devices shall be provided in accordance with AS/NZS 1158 and as determined by Council's City Assets Directorate

    1.19.7 Central Median and Traffic Islands

    Where street lighting is to be provided within the central medium island or within other traffic islands located within the carriageway, barrier kerb must be provided for the islands.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 1

    2. ENGINEERING DRAWINGS 2.1 Scope This section of the Engineering Guide sets out Council's general requirements

    for the preparation of Engineering Drawings. 2.2 Aim To provide comprehensive details to facilitate the assessment of plans and

    construction of works in a safe, efficient and effective manner. Also to ensure that Engineering Drawings provide sufficient information in a

    consistent format to allow Council to maintain a permanent record of subdivision and development works.

    2.3 General Requirements All engineering drawings are to ensure that all relevant conditions of consent

    have been addressed by the details shown. Drawings are to be submitted on standard size drawing sheets, stapled and bound.

    Three (3) full sets of the Engineering Drawings are to be submitted. One set,

    endorsed with Council's approval, will be returned to the Consultant. 2.4 Road and Drainage Drawings Plans for Road and Drainage works shall be presented to Council generally in

    the following format: * Title Sheet, * Detail Plan(s), * Road Longitudinal Section(s), * Road Cross Sections, * Typical Road Cross Section(s), * Kerb Return Details, * Traffic Calming Devices, Pathways and Other Miscellaneous Road

    Details, * Permanent Traffic Warning and Regulatory Details (i.e. Linemarking,

    Stop/Give Way Signs, Curve Signs etc.) * Drainage Catchment Plan, * Drainage Calculations, * Drainage Longitudinal Section(s), * Other Drainage Details, * Erosion and Sediment Control Measures, and

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 2

    * Traffic Control Measures. 2.5 On-site Stormwater Detention Drawings Engineering Drawings showing on-site stormwater detention details for

    developments shall generally include the following: * Catchment Plan showing contours, area of site affected and area of site

    not collected, * Drainage design summary in format of that shown in the Upper

    Parramatta River Catchment Trust's On-site Stormwater Detention Handbook,

    * Calculations to confirm volumes, pipe sizes, size of overland flowpaths and overflow weirs,

    * Detail Plan and sections (see Section 2.18), * Design Levels for top water/overflow; inverts of all drainage pits,

    pipelines and storage areas; overflow weir; centreline of orifice; surface of all drainage pits; and surfaces designed to detail and direct stormwater, and

    * Dimensions of storage areas, drainage pits, overflow weirs, maximum head, high early discharge head and depth of storage.

    2.6 Title Blocks All Engineering Drawings submitted to Council for approval are to have a title

    block showing the following: * Applicant's Name, * Consultant's Name, Address, Phone No. and Contact Name, * Drawing Number, Sheet Number and Amendment Number, * Schedule showing Date and Nature of Amendments, * Site Address, including Lot and Deposited Plan (DP) Number, * Council's File Reference, * Stage Number, * Drawing Title, * Scale with Scale Bar, and * Signature of Authorised Person (See Section 1.7 of this Guide). 2.7 Title Sheet/Layout Plan The location of the Development shall be identified by Lot, DP, street name

    and suburb and by clearly marking the site on a Locality Plan. A layout plan shall be provided showing the layout of roads, road numbers,

    allotment layout (with lot numbers as per the approved plan of subdivision)

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 3

    and Bench Marks (to A.H.D.). The original nature and value of the datum used to establish the bench marks is to be indicated, eg Permanent Mark or State Survey Mark and number. Where the plan shows layouts for part or future stages, a bold and clearly defined stage border is to be shown. For small developments, where all of these details can be shown on the detail plan, the layout plan may be omitted.

    The title sheet should also include construction notes and an index of the

    sheets provided in the set of drawings. Council's File number shall be shown in letters 25mm high in the top right

    corner of the sheet, eg, CC-04-1000. 2.8 Detail Plan Detail plans should include the following:

    * Scale 1:500 or 1:200 for small sites (with Scale Bar),

    * North point,

    * Lot details including boundaries, numbers, easements and any road widenings,

    * Existing contours (at least two across each lot) extending beyond the

    boundary of the site for a distance sufficient to show any constraints, with a minimum distance of 10 metres,

    * Existing natural features including: native vegetation, trees, ditches,

    dams, mounds, creeks, etc. These details are not to be limited to the proposed subdivision but shall include any features which have an impact on the development,

    * Existing constructed features including: fences, kerb and gutter, pipes,

    pits, road pavements, buildings, road furniture, adjacent subdivisions, etc. These details are not to be limited to the site and are to include any feature which has an impact on the Development,

    * Existing services: sewer, water, telephone, gas mains, electricity, etc.,

    including all associated pits, poles and other structures, must be shown on plan and plotted on Longitudinal Sections,

    * Road centrelines showing chainages, bearings and intersection points,

    * Extent of proposed works (using shading to aid in clarity) including:

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 4

    - road names, - carriageway and footway widths, - chainages, - tangent points, - kerb type, - path paving, cycleways, pram ramps, - berms, - batters, - cut and fill areas clearly indicated by shading, clearly

    identifying depths, - location of laybacks (one to each frontage of corner lots 1m

    from prolongation of common property boundaries) for roads with Standard barrier kerb,

    - street signs to Council plan A(BS)113M, - kerb return numbers, - dimensions, - pit numbers (1), (2), etc, - pit chainages, - pipelines identification numbers, - pipe sizes, - pipe type and class, - drainage lead-in and tail-out works, - flood extents for 100 year ARI, - floodway warning signs to Council plan A(BS)114S, - curve information including tangent point chainages, radii, arc

    and chord lengths, super elevation (if applicable), * Termination of works shall be matched in smoothly with existing

    works and/or be suitably treated with: guide posts, line marking, scour protection, etc. Limit of works shall be clearly identified,

    * Vehicular Footway crossings (Council Plan A(BS)102S) shall be

    provided where the distance from the kerb to the property boundary is 5.5m or more, or as otherwise detailed in the Development Consent,

    * Reciprocal rights-of-way shall be provided with a concrete access strip

    in accordance with Council plan A(BS)110S,

    * Longitudinal sections, cross-sections at every 15 metres and detailed typical cross-sections are required for each road including temporary roads,

    * Plans shall show road names NOT road numbers. Road names should

    be selected in conjunction with Council's Land Information Officer. If

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 5

    road names are not approved initially, road names must be shown on Work-As-Executed drawings, and

    * Pit schedule in tabular form to be shown on the plan sheet indicating pit numbers, type of pit, invert levels, surface levels chainages,

    2.9 Road Long Section(s) Road long section(s) shall be "boxed" and include the following details: * Road name,

    * Design level and chainage at least every 15 metres, * Existing level and chainage at least every 15 metres, * Grade (%) between each vertical curve, * Length of each vertical curve, * Chainage of each intersection point, * Level of each I.P., * Tangent chainages, * Centreline intersection chainages, * Chainage and level of each crest and sag, * Chainage and levels at grade intersection points and vertical curve

    tangent points, * Extended levels and grading to depict future works and/or match to

    existing roads, (minimum extension 30m) * Minimum longitudinal gradings of roads shall preferably be 1.0%.

    Grades less than 1.0% will only be considered where it is demonstrated that no other options are viable, see table 3.6, and

    * Existing services shall be shown along with size and level on all longitudinal sections where they affect proposed works.

    2.10 Road Cross Section(s) A cross section for each centreline chainage (typically 15.0 metre intervals),

    with additional cross sections as required shall be "boxed" and include the following:

    * Road name, * Centreline Chainage, * Existing surface levels, extending beyond any proposed batters, * Design surface levels, * Offset distances to centreline, * Cross-falls, batter slopes and dimensions, where these differ to that

    shown on the typical section, * Batters shall have a maximum slope of 1:5 (V:H), * ½ width road works still require full width design cross sections, and

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 6

    * Existing services shall be shown along with size and level on all cross sections where they affect proposed works.

    2.11 Typical Road Cross Section(s) A typical cross section shall be provided for each road as additional detail on

    at least one cross section on each sheet of road cross sections OR alternatively, may be provided separately as a set of typical cross sections. Where typical cross sections are provided separately to the road cross sections, general details shall comply with Section 2.10. The additional detail for a typical road cross section should include the following:

    * Road reserve width (existing and proposed), * Road width between face of kerbs, or where no kerb is constructed

    pavement and shoulder widths, * Location and width of any proposed concrete footpaving or cycle

    paths, * Kerb and gutter type, * Grades/Slopes of pavements, footpaths and batters, with offsets to

    changes of grade, * 3% crossfall on carriageway, * 4% crossfall on footway with 0.5m berms inside lots, * Concrete path paving 1.2 metres wide 0.90 metres from property

    boundaries where required in accordance with Council's Path Paving Policy, and to have a crossfall of 2.5%, and

    * Pavement thicknesses, designed in accordance with Council's specification by a N.A.T.A. registered geotechnical consultant.

    2.12 Kerb Return Cul-de-Sac and Splay Corner Details Plans showing kerb returns at intersections, junctions and turning heads should

    include the following:

    * General design of returns shall be by dividing return into quarters between tangent points and using two vertical curves to achieve smooth profile,

    * Each quarter and tangent point shall be consecutively lettered on plan

    and longitudinal section,

    * Longitudinal section shall show:

    - design top of kerb,

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 7

    - kerb chainage, - road chainage, - high and low points,

    * Splay corner and kerb return radii shall be: - Residential roads - 5m x 5m splay corners with 8.5m kerb

    return radii, - Industrial roads - 8m x 8m splay corners with 12m kerb return

    radii, - splays are not to be used for installation of services or

    landscape works that may impeded sight distances.

    * Cul-de-sac kerb radii shall be:

    - Residential - 8.5m (12.0m at property boundary), - Industrial - 13.5m (17.0m at property boundary),

    * All intersection and cul-de-sac detail plans shall be contoured, and

    * A minimum kerb frontage of 3.5m must be provided for each lot. This

    width is measured between radial lines from the kerb return centre point to the allotment front corners.

    Cul-de-sac head details shall be provided generally in accordance with the

    abovementioned requirements.

    2.13 Traffic Calming Devices, Median Islands and Other Miscellaneous Road Details

    Plans showing traffic calming devices should show design levels, design

    contours, signposting and line marking. Median islands and other miscellaneous road details should be shown clearly on typical sections.

    2.14 Pathways * Pathways are generally required to provide for safe, convenient,

    pedestrian access and cater for overland flows of discharges from the 100 year ARI event between streets, or from streets to recreational and/or community facilities.

    * Pathways shall be a minimum of 4m wide, or as otherwise directed,

    with full width concrete paving, cross-fall generally of 2.5% and kerbs shall be provided where required,

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 8

    * If pathways are designed as overland flowpaths they shall have a minimum width of : (i) up to 2ha catchment area, 4m width (ii) up to 6ha catchment area, 6m widhth (iii) over 6ha catchment area, 10m width

    * Longitudinal sections shall be provided, * Pathways are to be straight, * Their grading shall not be steeper than 1 in 12 (8.3%). * Vehicular barriers in accordance with Council plan A(BS)105S and

    A(BS)137S shall be provided for each pathway, and * The footway area between the road kerb and gutter, and the pathway,

    may be shaped with a reverse cross-fall (ie, graded from kerb down to pathway) to direct overflows from the road into the pathway.

    2.15 Drainage Catchment Plan A plan showing all internal and external catchments affecting the development

    and their breakdown into sub-catchments should include the following: * Road Names, * Existing and proposed property and road boundaries, * All catchments/sub-catchments labelled according to the drainage

    calculation sheet, * Catchment/Sub-catchment boundaries indicated by a bold line, * Proposed/Existing contours at a suitable interval, * Direction of waterflow along the flow paths of the longest times of

    concentration, * Any features that may affect catchment boundaries, * Drainage lines and pit numbers, * Areas of all catchments/sub-catchments, and

    * Proposed roads, pathways, pits and pipes. 2.16 Drainage Calculations A drainage report shall be presented generally in the form shown in

    "Australian Rainfall and Runoff" (1998) and shall be included on the A1 sheets as part of the set of engineering plans and before the Longitudinal Sections. It will also provide any information required by Section 4 - Drainage Design and Appendix "D" of this Guide.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 9

    2.17 Drainage Longitudinal Section(s) 2.17.1 A longitudinal section of each drainage pipeline is to be shown

    including the following information on each:

    * pipe flows and capacities, * pit numbers, * drainage line numbers, * pipe chainage, * road chainage, * existing and finished surface levels, * design invert levels, * hydraulic level, * datum R.L., * pipe size, type and class, * pipe grade (%), (minimum grade 1.0%), * hydraulic grade line plot, * water surface levels in receiving waters for design ARI, * tail-out, * lead in, * pipeline junctions, and * details of utility services to be shown along with the level

    where they cross pipelines. 2.17.2 Longitudinal sections shall be designed for interallotment drainage

    lines. Where more than 5 lots shall be served, a hydraulic analysis is required to ensure lots are not affected by surcharge.

    2.18 Other Drainage Details 2.18.1 Designs shall satisfy the requirements of Section 4 - Drainage Designs,

    and Appendix "D" of this Guide. 2.18.2 Details of the following are to be provided on a drainage detail plan

    where not shown on the road works detail plan: * Details of pipe junction, * Full details, including reinforcing, of non-standard structures, * Invert levels, surface levels and locations of all drainage

    structures, * Pipe details, * Length of lintels (by clear opening size), and * Extent of lead-in and tail-out works.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 10

    2.18.3 Each industrial lot shall be provided with a pit draining to the drainage system via interallotment drainage lines. The minimum pipe size shall be 375mm diameter. Drainage lines should be located in the setback area where possible or rear of site, as may be required. An easement in accordance with Section 2.19 of this guide shall also be provided.

    2.18.4 The schedule of drainage structures shall show: * pit number, * description of structure, and * road chainage of structure. 2.18.5 Sag pits shall have a minimum internal lintel opening commensurate

    with the inflow requirement. 2.18.6 Rubber ring jointed pipes shall be used for construction of pipelines: (a) for pipelines up to and including 1800mm diameter. 2.18.7 Where open drains are designed additional details shall be provided

    including the following: * Cross sections (usually 15.0 metre intervals), and * Details of drop structures, energy dissipators, etc. (plan and

    sectional views). * All natural creeks are to be retained and any works must

    comply with the requirements of DIPNR in addition to the requirements set out in Section 4 and Appendixes B and D of this guide.

    2.18.8 Where detention basins are required, full construction details shall be

    provided including the following: * Plan view, * Sectional views, * Details of basin wall construction, * Details of outlet structures, including energy dissipators, * Extent of storage, * Maximum storage level, and * Extent and nature of landscaping.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 11

    2.19 Easement Widths 2.19.1 Where easements are required the following minimum widths apply:

    2.19.1.1 Residential Interallotment Drainage:

    - Pipes up to 300mm - 1.0m - Pipes 375mm - 1.5 to 2.0m

    2.19.1.2 Industrial/Commercial Interallotment drainage, and Council Drainage

    Pipes. These pipes shall generally be located in pathway systems.

    - Pipes 375mm to 750mm - 2.5m - Pipes 825mm to 1200mm - 3.0m - Pipes 1350mm to 1800mm - 3.5m

    2.19.2 Easement width for other pipe sizes and multiple pipes will be

    determined by Council.

    2.19.3 ALL drainage structures MUST be contained within the relevant easement. Easements may be widened to ensure this occurs.

    2.20 Overland Flow Paths 2.20.1 Subdivisions Any overland stormwater flow from the 100 year ARI event must be

    discharged via a road or pathway system. Easements will not be acceptable except under exceptional circumstances, or where upstream catchment area is < 2. ha.

    2.20.2 Site Developments For site developments, eg, medium density development, an overland

    flowpath shall be provided through the site to cater for the 100 yr ARI event flows from the upstream catchment. These flows must be safely conveyed through the site to Council's road and/or drainage system.

    2.20.3 Restrictions/Positive Covenants Restrictions and positive covenants shall be provided over all

    constructed overland flowpaths. The wording shall be in accordance with Appendix F "Standard Recital for Terms of Easements, Covenants and Restrictions" of this Guide.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 12

    2.21 Retaining Walls Retaining walls adjacent to roads, pathways and public reserves shall be

    constructed in reinforced concrete or masonry with an attractive finish. They shall not be constructed from any timber products.

    The Applicant must provide full engineering details of the proposed structure,

    including elevation, typical cross-section and structural certification. The design of the retaining wall must be prepared by a Registered Engineer. A certificate of structural adequacy from a Registered Engineer for the

    finished product shall also be submitted to Council on completion of the works.

    2.22 Erosion and Sediment Control Measures A plan prepared in accordance with the requirements of Section 5.14 shall be

    provided showing relevant site characteristics and design criteria of erosion and sediment controls and should include but not be limited to the following:

    * Existing and design contours, * Existing site drainage and vegetation, * Limit of clearing, grading and filling, * Grades/Slopes of site, * Critical natural areas (natural watercourses, swamps, cliffs, etc), * Location of topsoil stockpiles, roads and all impervious surfaces, * Distance to nearest natural watercourse or drainage line, * Catchment area boundaries, * Sediment basin calculations, * Erosion and sediment controls, including diversions, * Construction/Revegetation notes, and * Outline of program for maintenance of erosion and sediment controls. 2.23 Traffic Management Measures 2.23.1 Traffic Control A plan prepared in accordance with the requirements of Section 5.13

    shall be provided showing traffic control measures for each stage of a proposed development and should include but not be limited to the following:

    * Diversion of pedestrian traffic, * Delineation of temporary traffic paths,

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 13

    * Position of warning devices, * After hours traffic arrangements, including emergency contact

    names and telephone numbers and * Instructions for the installation, operation, between stage

    rearrangements, and removal of traffic control devices, safety barriers, temporary pavement markets, etc.

    2.23.2 Traffic Regulation (Permanent)

    A plan shall be prepared and submitted to Council for approval showing all permanent traffic regulatory and warning devices including but not limited to linemarking (edge lines, centre lines, and holding lines), painted lane arrows, school zone signs and pavement markings, curve warning signs, keep left signs, parking restrictions, speed limit signs, bus zones, and any other warning signs as required by the development consent or relevant Australian Standard.

    2.24 Adjoining Owners Permission Where ancillary works are necessary on adjoining private properties the

    applicant must submit the written consent of the owner to such work, either on the plans or by letter, prior to approval of engineering plans.

    2.25 Works-As-Executed Plans for Engineering Works 2.25.1 General (a) In order to have a permanent record of construction which

    incorporates amendments, completed site regarding, etc. Works-As-Executed Plans shall be lodged for Council's records, with W.A.E. figures (where there is a variation from the design) shown boxed, in red colour, on plan and longitudinal sections.

    (b) Works-As-Executed Plans must be submitted to Council prior

    to final inspection by the Development Supervisor. (c) Subdivision Certificate (Plan of Subdivision) will not be

    processed until the Works-As-Executed Plans have been received and verified.

    (d) The Works-As-Executed Plans must be certified by a

    Registered Surveyor or Engineer responsible for the preparation of the Works-As-Executed Plan.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 14

    (e) The Surveyor responsible for the Plan of Subdivision, or where easements are registered, covering the subdivision/development, shall supply a signed certificate stating that all pipes and associated structures are located wholly within the respective easements (see Appendix "H" for example of Easement Certificate).

    (f) The following certificate shall be appended to each sheet of the

    plans and signed by the Registered Surveyor or Engineer: "I hereby certify that engineering works shown on this plan

    have been constructed generally in accordance with Construction Certificate issued by ……. OR the plans and specification approved by Blacktown City Council."

    Name ………………………….. Signature ……………………… Capacity ………………………. Date ………………………….…

    2.25.2 Information To Be Shown

    2.25.2.1 Kerb & Gutter

    (i) Footway widths, gutter invert/nominal kerb line to property boundary.

    (ii) All T.P.’s.

    (iii) Centre of curves.

    (iv) Beginning and end of construction.

    (v) Intermediate points on long straights no more that

    100m intervals, where variation exceeds 10% from the approved width.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 15

    2.25.2.2 Gutter invert levels

    (i) All T.P.'s. (ii) Crest Points.

    (iii) Sag Points.

    (iv) End of straight grades.

    (v) As required on flat grades.

    (vi) Location of all Vehicular Crossings to be shown.

    2.25.2.3 Stormwater Drainage

    (i) Invert levels of all pipelines at entrance and exit of all pits and headwalls.

    (ii) Pipe sizes at entrance and exit of all pits. (iii)Two connections from lot corner peg shall be given to

    locate slope junction of all interallotment drainage lines. (iv) The depth from finished surface level to invert of slope

    junction of all interallotment drainage lines.

    (v) The information required in Sections 2.25.2.3(iii) and (iv) shall also be shown on the Slope Junction Plan required by Section 1.17.5 of this Guide.

    (vi) The location of all pipes within lot boundaries shown by

    dimensions to nearest boundaries. (vii)The location of all pits and pipes within street

    alignments where the location varies by more than 0.5m from the approved design.

    2.25.2.4 Site Regrading

    Where any lot is the subject of site regrading, the following is required:

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 16

    (i) Finished surface levels recorded by spot levels of the regrading area.

    (ii) For minor regrading (i.e. cut or fill < 0.5m deep) Spot

    levels observed and recorded on plans at:

    ■ Allotment corners,

    ■ Centre of front and rear boundaries, and

    ■ 12 metres from front alignment on side boundaries and centre of lot.

    (iii)Major site regrading (i.e. cut or fill over 0.5m in depth)

    recorded by new contours. (iv) A Fill Plan, as per requirements of Section 2.26 of this

    Guide.

    2.25.2.5 Design Variations Where design details have been varied prior to or during

    constructions, Works as Executed plans shall show the details of such variations or amendments.

    2.25.2.6 Flood Prone Areas

    Spot levels are required on all lots as per Section

    2.25.2.4(ii).

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 17

    2.26 Fill Plans A plan showing filling, where any part of a subdivision has had the surface

    level raised by the placement of any fill, other than nominal topsoiling, is to be provided showing a minimum of that area of the subdivision that has been filled plus a reasonable surrounding area to enable the filled section to be located and should include the following:

    * Road numbers and road names, * Road reserve boundaries, * Allotment layout, including easements and lots numbered in

    accordance with the final plan of subdivision, * Extent of fill (using maximum intervals of 0.5m), * Fill area hatched, and hatching shown in a legend as filled area, * Stripped and finished levels, * Contours, and * Certification of the plan by a Registered Surveyor or Engineer. 2.27 Sheet Sizes Sheet sizes should not be mixed within the same drawing set and shall be

    limited to the following: * A1 - 841mm x 594mm - Earthworks, Road and Drainage Works, OSD

    Works, Erosion and Sediment Control, and Traffic Control Details, etc, and

    * A2 - 594mm x 420mm - Minor Engineering Details.+ + Minor Engineering Works may consist of connection to a street gully

    pit or existing interallotment pit and interallotment drainage for a 2 lot subdivision.

  • BLACKTOWN CITY COUNCIL ENGINEERING GUIDE FOR DEVELOPMENT – 2005

    ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    2 - 18

    2.28 Scales The following scales shall be used for the following plans and sections, unless

    varied by the Co-ordinator: * Engineering Detail Plan 1:1000, 1:500 or 1:200, * Road Longitudinal Section 1:100 (vertical) to 1:500 (horizontal), * Road Cross Section 1:100 Natural or 1:100 (vertical) to

    1:200 (horizontal), * Intersection Details 1:250, 1:200 or 1:100, * Layout Plan 1:500, 1:1000, 1:2000 or 1:4000, * Catchment Plan 1:500, 1:1000, 1:2000 or 1:4000 (for

    external catchment), * Locality Plan 1:500, 1:1000, 1:2000 or 1:4000, * Kerb Return Plan 1:200, * Kerb Return Longitudinal 1:100 (vertical) to 1:200 Section (horizontal), and * Details 1:10, 1:20, 1:50 or 1:100 as required. 2.29 Dimensions Linear dimensions on all engineering plans shall be in metres, with the

    exception of detail plans which may be in millimetres. Methods of dimensioning will be in accordance with the current Australian Standard.

    Chainage shall be expressed to the nearest 0.01m, levels shall be reduced to

    Australian Height Datum (AHD) and expressed to the nearest 0.005m (except Bench Marks, PM's and SSM's which will be expressed to the nearest 0.001m).

  • ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    3 - 1

    3. ROAD DESIGN 3.1 Scope This section of the manual sets out Council's requirements for the design of

    urban and rural roads. It is in no way a comprehensive design manual and it is intended to be read in conjunction with and as a supplement to:

    * AUSTROADS (2009) - Guide to Traffic Management * AUSTROADS (2009) – Guide to Road Design- suite of design

    manuals- as amended * AUSTROADS (2012) – Guide to Pavement Technology – Part 2

    Pavement structural Design * ARRB, Transport Research (1995) Sealed Local Roads Manual -

    Guidelines to Good Practice for the Construction, Maintenance and Rehabilitation of Pavements,

    * AMCORD - A National Resource Document for Residential Development,

    * Department of Housing Road Manual, and * Council's relevant Development Control Plans. 3.2 Aim The design and construction of a road system that provides the following: * a high level of safety for all users, * acceptable levels of amenity and protection from the impact of traffic, * a reasonable level of convenience for all users, and * economy of construction and maintenance. 3.3 Planning Standards The road hierarchy has been developed to cater for various functions that need

    to be performed by roads within Council's road network. The road hierarchy and relevant road widths are listed in table 3.1 of this Guide and are also embodied in Council's Blacktown Development Control Plan 2006 (Part A).

    New road layouts and widths must conform to that shown in Table 3.1 and any

    other relevant Development Control Plans. The precise location of any proposed roads are subject to the detailed site assessment carried out during the subdivision application process. In areas not covered by a Development Control Plan the layout and width will be determined by Council on their merits.

    Kerb return and cul-de-sac details are contained within Section 2-12 of this guide.

  • ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    3 - 2

    Table 3.1: Road Hierarchy and Widths Road Type

    Carriageway (in metres)

    Footway each side (in metres)

    Total Road Reserve (in metres)

    Number of Lanes

    SUB-ARTERIAL within Zone No. 5(c)

    12.5 separated by 4m

    median

    4.25

    Generally 25

    4 travel lanes and no parking

    INDUSTRIAL Collector within new industrial areas Other Industrial

    15.5

    13.5

    3.75

    3.5

    23

    20.5

    2 travel lanes and 2 parking lanes 2 travel lanes and 2 parking lanes

    RESIDENTIAL

    Collector (1) loop roads serving activity centres such as large open space areas, shops, etc.

    11

    3.5

    18

    2 travel lanes and 2 parking lanes

    Local Street minor loop roads and cul-de-sac serving more than 30 dwellings including corner lots

    9

    3.5

    16

    2 travel lanes and 2 parking lanes

    Cul-de-sac serving a maximum of 30 dwellings/dwelling units (not lots), no residues, super lots, or medium density sites at the end of culs-de-sac.

    7.5

    3.5

    14.5

    2 travel lanes parking permitted

    Access Streets Development one side only Development both sides

    5.5 only for short lengths (maximum of 8 dwellings or 80m) to link culs-de-sac

    As above

    3.5 on residential side 1.0 other opposite side

    3.5

    10

    12.5

    1 travel and with permitted parking As above

    Private/Community Title Roads Up to 5 dwellings Up to 15 dwellings

    4.5

    5.0

    1.5 minimum *

    1.5 minimum *

    7.5

    8.0

    single travel As above

    Temporary Road

    7

    3.0 & 1.0

    11

    2 travel lanes

    Pathways

    4.0 - 10.0 m depending on function.

    (access/drainage/servicing)

    Pedestrians &/or cycles only

    * The 1.5m buffer strips are to provide for services and landscaping. Fencing will not be permitted inside the buffer strips.

  • ENGINEERING GUIDE FOR DEVELOPMENT - February 2005

    3 - 3

    3.4 Half Width Roads

    Council does not encourage the construction of half width roads, however in certain circumstances this may be permitted. A minimum 4.5m width pavement must be fully constructed.

    Where half widths roads are approved, the applicant is required to provide sufficient details regarding the extent of works to ensure operational effectiveness and safety. This will involve a full design together with sufficient details to ensure adequate transitions to the standard road pavements inclusive of full width cross sections.

    3.5 Construction Specification

    Council's Works Specification - Civil complements this Guide and shall be referred to for all construction details.

    3.6 Pavement Design

    A formal pavement design shall be prepared by a registered N.A.T.A.

    laboratory based on sampling and testing of the subgrade materials from the site. Details of the pavement design, results of subgrade testing (including 4 day soaked CBR's) are to be submitted to Council for approval prior to commencement of pavement construction. The design shall be based on Traffic Loading Criteria specified in the Consent for the proposed works, which is based on the Design Traffic Loadings shown in Table 3.2.

    The structural design of the pavement must be in accordance with the following procedures and shall have a con