Upload
buiminh
View
216
Download
1
Embed Size (px)
Citation preview
Energy Efficiency Projects for
Aeration Systems:• A Case Study of the Fox River
Water Reclamation District
James Kerrigan, P.E. – Fox River Water Reclamation DistrictRyan Christopher, P.E. – Greeley and HansenLaurissa Cubbage, P.E. – Greeley and Hansen
Presentation Topics
• Overview of Energy Usage at WRF
• Overview of the Fox River Water Reclamation District
• West WRF High Efficiency Aeration Improvements
• Albin D. Pagorski WRF Aeration System Improvements
• Grant Funding Availability
• Summary
Overview of Energy Usage at WRF
Source: Zahreddine, Phil, USEPA. “Innovative Energy Conservation Measures at Wastewater Treatment Facilities.” Power Point Presentation.
AERATION
54.1%
Fox River Water Reclamation District
• Provides wastewater treatment services to
over 180,000 residents in service area (City
of Elgin, Village of South Elgin)
• FRWRD treats average of 26 MGD across 3
WRFs– North
– West
– Albin D. Pagorski
West Water Reclamation Facility
• Online in 2004
• Design average flow 5.0
mgd
• Current average flow 3.1
mgd
• Designed for expansion
up to 25 mgd
West WRF – Aeration System
Background
• 3 Existing Multi-Stage Centrifugal Blowers– Blowers were oversized for
low flow situations
– Excess air was sent to off-line aeration tank
• Infrastructure Available for Denitrification– Tanks setup for
denitrification
– Equipment purchase required (mixers and recycle pump)
West WRF – Aeration Blower
Technology Evaluation
• Comparison Between Turbo Blowers and Existing Equipment – Energy efficiency
– Operation and maintenance costs
– Capital costs
– Payback period
• Option 1 – New Turbo Blower, continue to send excess air to aeration tank
• Option 2 – New Turbo Blower, no excess air
• Option 3 – New Turbo Blower, no excess air and install denitrification
Air Flow Frequency
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
20.00%
Air Flow Frequencies
Option 3
Option 2
Option 1
Evaluation Recommendation
• Recommended Option 3
– Install One 150 hp Turbo Blower and install pump
and mixers to operate denitrification
• Total Construction Cost = $177,000
• $30k in annual energy savings
• $153,318 grant was awarded from two
agencies• 87% of construction cost for project came from grants
• Payback reduced to under 1 year with grant funding
West Plant Blower Power Reduction
New Blower Online
Old Blower Operation
– Approx. 40% Reduction in Power Usage
BNR Online
Albin D. Pagorski WRF
Aeration System Improvements
• Albin D. Pagorski WRF
– Daily average flow 16.0 mgd
– Design average flow 25.0 mgd
– Peak flow 50 mgd
• Existing blowers were past
useful life and have become
maintenance intensive
• No D.O. Controls, labor
intensive process
• New industrial load to plant
with high BOD concentration
ADP Aeration System Efficiency
Evaluation
• Comparison between existing equipment
and new equipment– Energy efficiency
– Operation and maintenance costs
– Capital costs
– Payback period
• Option 1 – New Turbo Blowers
• Option 2 – New Turbo Blowers with new diffusers
• Option 3 – New Turbo Blower, with new diffusers and
D.O. controls
Air Flow Frequency
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
20.00%
Air Flow Frequencies
New DO and Diffusers
New Diffusers Only
Existing Aeration System
ADP Aeration System Improvements
• Updated Plant Basis of Design
– Analyzed plant firm capacity, resulting reduction • 27,000 scfm to 20,800 scfm
• Evaluated blower combinations
• New DO Control System
– Pressure Based Dual Loop Control
• Sequencing
– Minimizing WRF interruption
Blower Combination – Selected
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
22,000
24,000
26,000
28,000
30,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Air
Flo
w,
scfm
Percentile Frequency
Neuros 300 HP Option at Design Flow (25 mgd) with Fresh Express Peak Flow (0.80 mgd)
(Dirunal Variations Shown by Dashed Lines)
DAILY AVERAGE FLOW
DAILY MAXIMUM FLOW, 40% ABOVE AVERAGE
DAILY MINIMUM FLOW, 50% BELOW AVERAGE
1-300HP
2-300HP
BLOWER RANGE300HP: 2,353 to 5,369 scfm
MinimumFlow Envelope
Firm Capacity
3-300HP
4-300HPMaximum Flow Envelope
ADP ASI – Project Update
• $2.4 million construction cost
– 5 Turbo Blowers with associated electrical upgrades
– Dissolved oxygen control system
• Fine bubble diffusers (under separate contract)
• Substantial Completion April 2015
• Final Completion May 2015
• Grant Funding
Grant Funding
• Both projects received grant funding through ICECF and DCEO
– West WRF• $45k from ICECF
• $108k from DCEO
– ADP Aeration System Improvements• $208k from ICECF
• $612k from DCEO
– (Diffuser replacement required to receive full funding)
• Total Grant Funding
– $973k awarded to both projects
Summary
• Aeration system efficiency improvements can greatly reduce operational costs
• Grant funding is available to push projects that fight for funding with more conventional projects
• FRWRD Projected Annual Energy cost savings
– Total = $167,400
• Simple Payback
– Under 10 years
Lessons learned
• Blower Manufacturer Differences
– Controls of blowers, valve operation
– Selected blower more cost effective even with slightly lower efficiency
• Integration Needs Careful Consideration
• Design to Include Staging of Demolition
• Staff Training
• Flow Meters
• New Check Valves