1
Instrucon Planning strategy and project management advice in support of a planning applicaon to develop an Energy Centre at Ipswich Hospital as part of a carbon footprint reducon iniave being progressed by the Hospital Trust Client Ipswich Hospital NHS Trust Project Details Planning permission for an Energy Centre was required to support the Hospital Trusts iniave to reduce its carbon footprint. The Energy Centre would be capable of generang approximately 80% of the Hospitals electricity requirements from used cooking oil, a non-toxic low carbon bio-degradable fuel source. Planning permission was granted in 2013 and the Energy Centre is due to be constructed in 2015. LPPs Role Project management of planning applicaon process including coordinaon of specialist technical inputs covering Architectural drawings, Visual Impact Analysis, Acousc and Air Quality assessments and an Environmental Report. Pre-applicaon discussions with the LPA including scoping of the form of the planning applicaon Organising a community engagement exercise Preparaon and submission of planning applicaon and liaison with LPA and consultees Securing planning consent with no pre- commencement condions www.lppartnership.co.uk For further informaon please contact John Lawson tel 01206 835150 or email [email protected] Energy Centre, Ipswich Hospital CHARTERED TOWN PLANNERS

Energy Centre, Ipswich Hospital - Lawson Planning Partnership · 2018. 7. 27. · Instruction LPP Planning strategy and project management advice in support of a planning application

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Energy Centre, Ipswich Hospital - Lawson Planning Partnership · 2018. 7. 27. · Instruction LPP Planning strategy and project management advice in support of a planning application

Instruction

Planning strategy and project management advice in support of a planning application to develop an Energy Centre at Ipswich Hospital as part of a carbon footprint reduction initiative being progressed by the Hospital Trust

Client

Ipswich Hospital NHS Trust

Project Details

Planning permission for an Energy Centre was required to support the Hospital Trust’s initiative to reduce its carbon footprint. The Energy Centre would be capable of generating approximately 80% of the Hospital’s electricity requirements from used cooking oil, a non-toxic low carbon bio-degradable fuel source. Planning permission was granted in 2013 and the Energy Centre is due to be constructed in 2015.

LPP’s Role

• Project management of planning application process including coordination of specialist technical inputs covering Architectural drawings, Visual Impact Analysis, Acoustic and Air Quality assessments and an Environmental Report.

• Pre-application discussions with the LPA including scoping of the form of the planning application

• Organising a community engagement exercise

• Preparation and submission of planning application and liaison with LPA and consultees

• Securing planning consent with no pre-commencement conditions

www.lppartnership.co.uk

For further information please contact John Lawson tel 01206 835150 or email [email protected]