Hindustan Steelworks Construction Limited Statement showing Quarterly Progress of Original Works for the Quarter en (Civil works only) Civil work costing Rs.1.00 crore and above. Electrical work costing Rs.15.00 lakhs and above Horticulturer work costing Rs.2.00 lakhs and above Sl.No. Name of work Estimated cost in Lacs Tendered cost in Lacs %age above/below such of rates applicable i.e.receipts Agt.No/LOI No. Name of Agency Date of commenc ement Time of completion Physical progress of work in %age Name of Engineer Incharge Remarks 1 Construction of office Bldg. for sub-regional office at Hubli for EPFO Pkg-I 459.77 459.7 -0.10% HSCL/BNG/EPFO/Hub li/09/LOI/134 dt.4.12.09 Annanmar Construction 4.12.09 3.6.11 completed Sri Nagoor,Dy. Mgr. 2 Construction of office Bldg. for sub-regional office at Hubli for EPFO Pkg-II 277.24 276.92 -0.11% HSCL/BNG/EPFO/Hub li/09/LOI/136 dt.21.12.09 Annanmar Construction 21.12.09 20.6.11 completed Sri Nagoor,Dy. Mgr. 3 Construction of school Bldg. for KVS at bagalkot 353 455.83 29% HSCL/BNG/AGM/LOI/ Bagalkot/2010/139 dt.20.4.10 Everest Construction 20.4.10 19.7.11 61.43% Vinod Kumar APE (c) 4 Construction of staff Qtrs & Dev.works for KV at bagalkot 167.75 215.02 28% HSCL/BNG/AGM/LOI/ Bagalkot/2010/140 dt.20.4.10 Everest Construction 20.4.10 19.7.11 11.16% Vinod Kumar APE (c) 5 Construction of ESIC Medical College 500 bedded hospital and allied works at Gulberga 71192.91 71115.8 0% LOI/AGT/No.243/ESIC/ HSCL/2010/11 dt.11.5.10 Nagaarjuna Construction 18.5.10 31.12.2012 52.66% V K TyagiED 6 Construction of Fishery harbour at Yanam in the Union Territory of Punduchery 1923.49 1817.7 -5.50% HSCL/GLB/Yanam/LOI /2011/1 dt.18.2.11 AMR Construction Ltd. 17.2.11 16.5.12 19.81% Sri Nagoor,Dy. Mgr. 7 Renovation of existing ESIC 100 bedded hospital at Hubli 2206 2202.69 -0.15% HSCL/Head(M&C)/122- Mktg/2011-4386 dt.21.2.11 Jampana Construction (P) Ltd. 1.1.2011 31.12.2011 42% A.Gurudtt Mnager (C) 8 Renovation of existing ESIC 100 bedded hospital at Dawangeri 2219.77 2216.44 -0.15% HSCL/Head(M&C)/122- Mktg/2011-4386 dt.21.2.11 Jampana Construction (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.( C) 9 Renovation of existing ESIC 100 bedded hospital at Mysore 2188 2184.46 -0.15% HSCL/Head(M&C)/122- Mktg/2011-4386 dt.21.2.11 Jampana Construction (P) Ltd. 1.1.2011 31.12.2011 48% J.T.Roa Asst. Manager (C) 10 Construction of ESIC Nursing College/Hostel and 1000 seater Auditorium at Indira Nagar attached to Medical College,Rajaji Nagar,Bangalore 6478.53 6465.22 -0.20% HSCL/Head(M&C)/122- Mktg/2011- 4333dt.2.2.11 Phadnis Infrastructure Ltd. 1.12.10 30.11.2011 21.11% Sukumaran APE (C) Bangalore ending-June'2012 D:\uploadedFiles\MqvEMlTOz5tq_ZRkiA5_YRSA3jqOM_ZrADuSR87sN_ZnaO4_I\QPR of June 2012.xls

ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated cost

in Lacs

Tendered

cost in

Lacs

%age

above/below

such of rates

applicable

i.e.receipts Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of office Bldg.

for sub-regional office at

Hubli for EPFO Pkg-I 459.77 459.7 -0.10%

HSCL/BNG/EPFO/Hub

li/09/LOI/134

dt.4.12.09

Annanmar

Construction 4.12.09 3.6.11 completed

Sri

Nagoor,Dy.

Mgr.

2

Construction of office Bldg.

for sub-regional office at

Hubli for EPFO Pkg-II 277.24 276.92 -0.11%

HSCL/BNG/EPFO/Hub

li/09/LOI/136

dt.21.12.09

Annanmar

Construction 21.12.09 20.6.11 completed

Sri

Nagoor,Dy.

Mgr.

3

Construction of school

Bldg. for KVS at bagalkot 353 455.83 29%

HSCL/BNG/AGM/LOI/

Bagalkot/2010/139

dt.20.4.10

Everest

Construction 20.4.10 19.7.11 61.43%

Vinod

Kumar APE

(c)

4

Construction of staff Qtrs &

Dev.works for KV at

bagalkot 167.75 215.02 28%

HSCL/BNG/AGM/LOI/

Bagalkot/2010/140

dt.20.4.10

Everest

Construction 20.4.10 19.7.11 11.16%

Vinod

Kumar APE

(c)

5

Construction of ESIC

Medical College 500

bedded hospital and allied

works at Gulberga 71192.91 71115.8 0%

LOI/AGT/No.243/ESIC/

HSCL/2010/11

dt.11.5.10

Nagaarjuna

Construction 18.5.10 31.12.2012 52.66%

V K

TyagiED

6

Construction of Fishery

harbour at Yanam in the

Union Territory of

Punduchery 1923.49 1817.7 -5.50%

HSCL/GLB/Yanam/LOI

/2011/1 dt.18.2.11

AMR

Construction

Ltd. 17.2.11 16.5.12 19.81%

Sri

Nagoor,Dy.

Mgr.

7

Renovation of existing

ESIC 100 bedded hospital

at Hubli 2206 2202.69 -0.15%

HSCL/Head(M&C)/122-

Mktg/2011-4386

dt.21.2.11

Jampana

Construction

(P) Ltd. 1.1.2011 31.12.2011 42%

A.Gurudtt

Mnager (C)

8

Renovation of existing

ESIC 100 bedded hospital

at Dawangeri 2219.77 2216.44 -0.15%

HSCL/Head(M&C)/122-

Mktg/2011-4386

dt.21.2.11

Jampana

Construction

(P) Ltd. 1.1.2011 31.12.2011 44%

A P

Shukla,Mgr.(

C)

9

Renovation of existing

ESIC 100 bedded hospital

at Mysore 2188 2184.46 -0.15%

HSCL/Head(M&C)/122-

Mktg/2011-4386

dt.21.2.11

Jampana

Construction

(P) Ltd. 1.1.2011 31.12.2011 48%

J.T.Roa

Asst.

Manager (C)

10

Construction of ESIC

Nursing College/Hostel and

1000 seater Auditorium at

Indira Nagar attached to

Medical College,Rajaji

Nagar,Bangalore 6478.53 6465.22 -0.20%

HSCL/Head(M&C)/122-

Mktg/2011-

4333dt.2.2.11

Phadnis

Infrastructure

Ltd. 1.12.10 30.11.2011 21.11%

Sukumaran

APE (C)

Bangalore

ending-June'2012

D:\uploadedFiles\MqvEMlTOz5tq_ZRkiA5_YRSA3jqOM_ZrADuSR87sN_ZnaO4_I\QPR of June 2012.xls

Page 2: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending June'12 (Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

BHUBANESWAR

1

Construction of JNV

Complex at

sankrushnapur,bhadr

ak,Orissa 963.39 890.79 8%

HSCL/BBSR/CP

M/30/2007-

444&445

dt.15.6.07

Triveni Civil

tech (p) Ltd. 14.11.07 30.06.2012 99.93%

S S

Aich,DM©

Approval

of RRPF

for Rs.

1093.11

Lakhs

received

on

02.11.201

0 From

NVS/New

Delhi

2

Construction of JNV

Complex atPallijhar

dist.Boudh 912.58 843.81 8%

HSCL/BBSR/Agt

/JNV/Boudh/29/2

008-16

dt.29.12.08

Triveni Civil

tech (p) Ltd. 10.10.08 30.09.2012 99.50%

S S

.Aich,Mana

ger(C)

Work in

Progress

3

Construction of North

Stand of State Sports

Academy,Kalinga

Stadium 609.93 577.27 5.35%

HSCL/BBSR/

Agt.I DCO/

North/Stand/200

8-18 dt.30.10.08

Y B Constn.(P)

Ltd. 13.6.08 30.07.2012 67.87%

S K

Bakshi,Mgr

. (C)

Work in

Progress

clearance

just

received

by client

IDCO

4

Construction Ph-A

work of JNV at

Angul,Dist.Angul. 1446.6 1335.61 8.00%

HSCL/BBSR/Agt

./JNV/Angul(ph-

A)/35/2010-20

dt.24.8.10

Triveni Civil

tech (p) Ltd. 15.3.10 30.09.2012 82.05%

S S

Aich,DM©

Work in

Progress

5

Construction of phase-

B Building of JNV,Dist

Bhadrak 635.97 588.04 8%

LOI No.

HSCL/BBSR/AG

M/Bhadrak (ph-

B)/30/2010-757

dt.30.12.10

Triveni Civil

tech (p) Ltd. 3.12.10 30.09.2012 89.31%

S S

Aich,Dy.M

gr(C)

Work in

progress

Page 3: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

6

Renovation of civil &

Electrical portion of

main building at

Institute of Minerals &

materials

technology.BBSR 220 268.19 9.77%

HSCL/BBSR/AG

M/IMMT(renovati

on)/2010/688

dt.6.12.2010

Triveni Civil

tech (p) Ltd. 22.12.10 31.7.11 100%

S K

Bakshi,Mgr

. (C)

work in

progress

7

Construction of office

cum training centre at

plot No.L-3,jayadev

Vihar,BBSR for SIDBI 635.29 839.49 9%

HSCL/BBSR/Agt

./SIDBI-

BBSR/09/2011-

23 dt.9.4.2011

M/s Y B

Construction

(P) Ltd./BBSR 28.4.2011 30.09.2012 47.00%

S S

Aich,Mngr(

C)

Work in

progress

8

Construction of

External Devolopment

works of national Law

University, Cuttack,

Odisha 817.3 890 8.10%

LOI No.

HSCL/BBSR/GM

/NLUO(part)/201

2-294

dt,12/19.06.2012

M/s Y B

Construction

(P) Ltd./BBSR 28.05.12 12 months 24.38%

S S

Aich,Mngr(

C)

Work in

Progress

Page 4: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Civil works OnlyCivil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and aboveHorticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable

Agt.No/LOI

No.

Name of

Agency

Date of

commencem

ent

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

BHILAI

1

Civil & Strl works (Pkg-V) for

installation of 700 ASU-4 at

OP-II BSP/Bhilai 450.83 400.33 -11.20%

GM/BH/TC/20

1/OT/173/08/1

434 dt.8.3.08 S.K.Jain 25.2.08 30.06.2012 76.40%

R L

Sharma,Ma

nager

2

Dismantaling & relocation

works(works PKg-118-B) for

enabling works of & MT

expasion of BSP,Bhilai,Part-

I-Civil 492.34 361.02 -26.61%

GM/BH/TC/20

1/OT/177/08/1

435dt.8.3.08 S.K.Jain 25.2.08 31.01.2012 113.03%

S V

singh,Mana

ger Completed

3

Strl. Work for universal Rail

mill (URM) (PKG-052B)

under 7 MT expansion of

BSP 1082.56 995.96 -8%

HSCL/BH/TC/

201/LT(642)10

M/s S.K.Jain

Constn.(P)

Ltd. 17.2.11 17.7.12 90%

S B

yadav,DM(

S&A)

4

Civil work for relocation of

plant spare(PKG-116A) for

7MT expansion of

Bhilai,Balance work-sanitary

works,Dismantling

works,water supply system 237.63 225.56 -5.08%

ED/BH/TC/20

1/OT(180)/08

Five Star

Construction 11.6.08 30.9.11 completed

S B yadav

,DM(A&S)

5

Strl.work for setting up of

Bar & Rod Mill (Pkg-051B-!)

at BSP,Bhilai 1195.59 1147.77 (-)04%

HSCL/BH/TC/

201/LT(640)/1

1

M/SMCK

Kutty & Co. 17.2.11 17.7.12 70.03%

S C

Rai,DM(Mill

s)

6 Cold repair of battery No.4 389.97 357.15 -8.60%

HSCL/BH/TC/

201/OT(195)/0

9 M/s WICC 20.6.09 31.3.11 completed

J S

Pathaniya,

DM(CO)

7

Civil & dismantling work for

relocation of mech.repair

shop and quenching car

repair shop in CO & CCD 224.16 208.02 -7.20%

HSCL/BH/TC/

201/OT/206/1

0 M/s WICC 9.7.09 30.06.2012 80% -do-

Complete

fronts are

not made

available

by client

Quarterly progress report for original works for quarter ending-June-12

Page 5: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

8

Road work and Road

culvert(Pkg.100-2) for BSP 1250.77 1137.83 -9.03%

HSCL/BH/TC/

201/OT(206)/1

0

M/S BSBK(P)

Ltd. 2.6.10 30.06.2012 61% RL Sharma

9

Civil work of Bar & Rod Mill

of bhilai Steel Plant

(Pkg.051A) at Bhilai 6660.66 6244.23 -6.25%

HSCL/BH/TC/

201/OT(209)/1

1

M/s BSBK (P)

Ltd. 5.5.11 31.8.12 33.33%

R L

Sharma,sr.

Mgr(C)

10

Civil work of Universal Rail

Mill of Bhilai Steel

Plant(Pkg.052A) at Bhilai 4305.29 4154.6 -3.50%

HSCL/BH/TC/

201/OT(208)/1

1

M/a Amar

Insfrastructure

Ltd. 28.4.11 08.08.2012 9.45%

I.Tembhare

Mgr ( C )

Bhilai

11

Strl.work for universal Rail

Mill (URM)(PKG-052b)

under 7 MT expansion of

BSP part -II 1082.56 999.74 -7.65%

HSCL/BH/TC/

201/LT(644)/1

0

M/s S.K.Jain

Construction 17.7.11 10.7.12 28.17%

S B

yadav.DM

12

Civil work forsetting up of

basic oxygen Furnace

(BOPF) & constinuous

casting shop PKG-033A)

under 7 MT expansion of

BSP part-I 5562.69 5338.33 -4.03%

HSCL/BH/TC/

201/OT(210)/1

1

M/s BSBK (P)

Ltd. 30.5.11 9.10.12 19.77%

P.K.Tamrak

ar Dy.Mgr

(C) Bhilai

13

Civil work for setting up of

basic oxygen Furnace

(BOPF) & constinuous

casting shop PKG-033A)

under 7 MT expansion of

BSP part-II 3338.36 3104.68 -5%

HSCL/BH/TC/

201/OT(216)/1

1 Jaya projects 11.7.11 20.9.12 10.30%

P.K.Tamrak

ar Dy.Mgr

(C) Bhilai

14

Desilting of 05 lakhs cum of

iron ore slime at Hitkasa

tailing Dam & Transportation

to the dumping area at Dalli

mech,mine(phase-II) 739.05 675.78 -8.56%

HSCL/BH/TC/

201/LT(684/11

Shiv Shakti

Enterprises 1.10.11 31.8.12 94.03%

A.Ahmed,A

GM

15

Construction of CPU

regeneration bldg. of

expansion Power

Plant,NSPCL,Bhilai 119.1 106.57 -10.57%

HSCL/BH/TC/

201/LT(645)/1

1

Five Star

Construction

Co./Bhilai 1.8.11 30.06.2012 56.25%

J S

pathariya,

Mgr(CO)

16

Hot Repair of partial/full wall

of battery 1 to 8 120.31 109.49 -9%

HSCL/BH/TC/

OPRn.//202(ii)

/11

Rosy

Enterprises 12.11.11 17.11.12 81.45%

J S

pathariya,

Mgr(CO)

On HSCL's

approved

rate

17

Civil work of Universal Rail

Mill of Bhilai Steel Plant(Pkg-

052A) at Bhilai 2581.32 2490.26 -3.52%

HSCL/BH/TC/

201/OT(217)/1

1 Jaya Projects 13.10.11 08.10.2012 16.69%

I.

Tembhare

Mgr (C)

Bhali

Page 6: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

18

Civil work for setting up of

basisc oxygen

furnace(BOPF) & continuous

casting shop(CC)

(Pkg.033A) under 7 MT

expansion of BSP 233.65 214.31 -8.28%

HSCL/BH/WO

/proj/11-12/13

Five Star

Construction

Co./Bhilai 7.3.11 9.10.2012 134.28%

P.K.Tamrak

ar Dy. Mgr

(C) Bhilai

On HSCL's

approved

rate.

Scope in

creased.

19

Civil works of Universal rail

Mill of Bhilai

Steel(Pkg.052A) at bhilai 206.78 187.84 -9.16%

HSCL/BH/WO

/Proj/11-12/15 Dhiraj Traders 24.2.11 08.08.12 61.41%

I.

Tembhare

Mgr (C)

Bhali

20

Civil work of universal Rail

Mill of BSP(PKG.052A) at

Bhilai 236.98 215.27 -9.16%

HSCL/BH/WO

/Proj/11-12/16

Five Star

Construction

Co./Bhilai 1.7.11 08.08.12 Completed

I.

Tembhare

Mgr (C)

Bhali

21

Civil work of Universal rail

Mill of BSP(Pkg.052A) at

Bhilai 136.98 124.27 -9.16%

HSCL/BH/WO

/Proj/11-12/17

Kadam

Builders 12.9.11 08.08.12 37.23%

I.

Tembhare

Mgr (C)

Bhali

22

Civil work of universal Rail

Mill of BSP (Pkg.052A) at

Bhiali 205.54 186.72 -9.16%

HSCL/BH/WO

/Proj/11-12/18

Amarnath

Dwiedi 20.2.11 08.08.12 91.95%

I.

Tembhare

Mgr (C)

Bhali

On HSCL's

approved

rate.

23

structural work (Pkg.1) for

Installation of Hot Metal De-

sulphurisation Unit at SMS-ii

of BsP,Bhilai 147.2

HSCL

115.50

Input

13.82

Tatal

129.32 (-)12.15%

GM/Bh/TC/20

1/LT(603)/05-

293

M/s Westeon

Enginners Pvt

. Ltd. Bhilai 20.09.05 30.06.07 90%

S B yadav

,DM(A&S)

Work

comleted,

clearence

from BSP

for

dismaintai

ng of tower

crane is

awaited-

permission

yet not

given by

BSP.

24

Replacement of NB 1200

mm mixed gas pipe line

from Mixing Station to

Normalizating furnace, at

Bhilai Steel Plant 171.24 154.08 (-) 10.02%

HSCL/BH/TC/

2/01/OT(221)/

12/

M/s S.k.Jain

Construction

Pvt Ltd, Bhilai 25.02.12 05.11.21

J.S.Pathani

ya Mgr

(CO) Bhilai

Work

space not

made

available

by BSP

Page 7: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

25

Civil work of installation of

addl. Roller table in welding

line no 204 in Rail & Strl. Mill 105.1 87.26 (-)16.97%

HSCL/BH/WO

/oprn/11-

12/3704

M/s Five Star

Construction

Co. Bhilai 13.01.11 30.06.12 83.72%

R.l Sharma

Sr. Mgr ( C)

Bhilai Completed

26

Cleaning of High silt

deposits and associated

jobs of out lets no

6,14,15,16,17,18,19 & 20 of

BSP 204.26 169.62 (-) 16.96%

HSCL/BH/WO

/Oprn./11-

12/3615

M/s S.k.Jain

Construction

Pvt Ltd, Bhilai 24.01.12 30.06.2012 100%

R.l Sharma

Sr. Mgr ( C)

Bhilai Completed

27

Civil work of Universal Rail

Mill of Bhilai Steel ( Pkg. 052

A ) at Bhilai 318.93 282.7 (-) 6.96%

HSCL/BH/WO

/Proj./12-13/01

M/s Five Star

Construction

Co. Bhilai 15.03.12 08.08.12 29.41%

I.

Tembhare

Mgr (C)

Bhali

Overall

margin of

rate

structural

28

structural work for Universal

Rail Mill (URM) (Pkg-052B)

under 7 MT Expansion of

BSP. Part III 541.28 495.27 (-) 8.50%

HSCL/BH/TC/

201/WOT(298

)/12

M/s s.k.Jain

Construction

Pvt Ltd, Bhilai 21.05.12 09.08.2012 5.54%

s B yadav

,DM(A&S)

Page 8: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending-December1112-Jun

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Constrution of

permanaent ash Pond for

BTPS-B-BTPS_A of DVC

at Bokaro Thermal

Powwer Plant 484.31 455.26 6.10%

LOI No.OT-05/2008-

TCD-1701

BKB Transport

(P) Ltd. 26.9.08 25.1.10 129.04% CTM-II

Qty

deviated

2

E/W in

cutting,filling,compaction,t

urfing,constn. Of minor

bridges and other

associated works 3955.78 3752 5.15%

LOI No.TCD-79

dt.22.1.09

Ratna Shirdi

saiJV 22.1.09 10.2.10 75.30% CTM-II

3

E/W in

cutting,filling,compactionb

lanketing,turfing,constn.

Of minor bridges and

other associated works

between Koderma to

hazaribagh in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xiv ch.km63.00

to km 66.00 144.72 135.67 6.25%

LOI No.TCD-932

dt.6.8.09

Srinivasa

Infrastructure 6.8.09 7.9.10 82.05% CTM-II

4

E/W in

cutting,filling,compactionb

lanketing,turfing,constn.

Of minor bridges and

other associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xxx

Ch.KM119.300 1686.1 576 6.50%

LOI NO.OT-07/2007-

2011/TCD-868A

dt.25.3.11

Suraj

Construction 31.5.11 24.50% Site Engr.

BOKARO

Page 9: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

5

E/W in

cutting,filling,compaction,t

urfing,construction of

minor bridges and other

associated works

between hazaribagh to

barkakhana in connection

with construction of a new

BG Rail line Koderma to

Ranchi for the reach

xxvii,chKM 109.50 to

110.50KM 1409.37 1336.79 5.15%

LOI No.TCD-134

dt.9.2.10

Shirdi sai

Construction 24.3.2011 61% Site Engr.

6

E/W in

cutting,filling,blanketing

work,constn. Of minor

bridges protection work

and Misc works from

KM169.374 to KM176.600

of barkakhana-Ranchi

section New BG Rail 1516.69 1418.87 6.45%

LOI No.TCD-1994

dt.2.12.08

Suraj

Construction 2.12.08 3.3.10 87.02% CTM

7

Civil & strl.Pkg of 300

TPH boiler cum 36 MW

BPTG unit No.9 project of

BPSCL 382.28 356.48 6.75%

LOI No.TCD-522

dt.13.4.09

Jai Bharat

Constn. 16.4.09 30.9.10 99% CTM

8

Civil & strl.Pkg of 300

TPH boiler cum 36 MW

BPTG unit No.8 project of

BPSCL 354.11 330.22 6.75%

LOI No.TCD-523

dt.13.4.09

Jai Bharat

Constn. 16.4.09 30.9.10 90% CTM

9

processing & handling of

LD Slag 333 298.86 10.25%

HSCL/ED/TC/TW/OT-

07(2010)2011-TCD-

1246 dt.16.5.11

Abinash

Construction 8.10.11 100% AGM

10

Civil & strl.Pkg of 300

TPH boiler cum 36 MW

BPTG unit No.9 project of

BPSCL 382.15 342.07 10.48%

LOI No.TCD-515

dt.13.4.09

R & P

Construction 16.4.09 30.9.10 99% CTM

11

Civil & strl.Pkg of 300

TPH boiler cum 36 MW

BPTG unit No.9 project of

BPSCL 407.87 317.06 22.27%

LOI No.TCD-659

dt.20.5.09 Bagu Constn. 23.6.09 30.9.10 98% Sr.Mgr.

12

Civil & Strl,PKG for Boiler-

9 project of BPCL 181.38 162.98 10.14%

LOI No.TCD-1230

dt.10.11.09 Brahamdeo pd. 10.11.09 30.9.10 99% CTM

Page 10: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

13

E/W in

cutting,filling,compaction,t

urfing,constn. Of minor

bridges and other

associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xxv

ch.104.100km to

108.00km 1891.48 1792.87 5.21%

LOI No.TCD-1428

dt.31.12.09

Shrdi Sai

Constn. 23.8.11 75.00% Site Engr.

14

E/W in

cutting,filling,compaction,t

urfing,constn. Of minor

bridges and other

associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xxi

ch.97.200km to98. 800km 2336.88 2217.94 5.09%

LOI No.TCD-

133dt.9.2.10

Shirdi Sai

Constn. 15.9.11 32.06% Site Engr.

15

E/W in

cutting,filling,compaction,t

urfing,constn. Of minor

bridges and other

associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xxii

ch.99.800km to101.

200km 1017.97 965.03 5.20%

LOI No.TCD-

75dt.20.1.10

Shirdi Sai

Constn. 23.2.11 79.00% Site Engr.

Page 11: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

16

E/W in

cutting,filling,compaction,t

urfing,constn. Of minor

bridges and other

associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi for

the reach xxvii

ch.109.50km to110. 50km 1409.37 1336.79 5.15%

LOI No.TCD-

134dt.9.2.10

Shirdi Sai

Constn. 24.3.11 60.90% Site Engr.

17

Construction of railway

formation including

cutting,filling,controlled

blasting of

rock,compaction,blanketin

g, minor bridges RUBs

etc and other associated

works in connection

withdoubling work

between Chandrapura-

bhandaridah and

Chandrapura-rajbera

section on Gomoh-

Barkakhana section of

ECR 1046.85 982.99 6.10%

LOI No.TCD-

491dt.27.4.10

Mithila saran

Singh 22.3.11 36.00% Site Engr.

18

Construction for welfare&

canteen bldg. in CRM

complex(PH-I) 685.24 644.13 6%

LOA

NO.HSCL/ED/TW/O

T-03(a)/2011-TCD-

1928 dt.4.8.11

R & P

Construction 13.9.11 10.12.12 Nil CTM-I

19

Disposal of

muck/debris/slag/skull etc

from SMS-II 252.79 232.56 8%

LOI No.

HSCL/ED/TC/TW/LT-

07/2011-TCE-2044

dt.18.8.11

Shiv Shakti

Enterprises 26.8.11 15.1.12 85% CTM-I

20

E/W in

cutting,filling,compaction,

blanketingturfing,constn.

of minor bridges and

other associated works

between Hazaribagh to

barkakhana in connection

with construction of New

BG Rail line from

Koderma to Ranchi 549.2 510.75 7%

LOI No.TCD-

895dt.23.7.10

Niklang

Nirankar

Drilling 12.11.11 38% Site Engr.

Page 12: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

21

Construction of HL Bridge

over River in 4th KM of

NH 23 358.5 331.61 7.50%

LOI No-TCD-1587

dt.13.12.10

Bokaro

Construction

Co. 5.11.11 23.00% CTM-I

22

Construction of

infrastructure facilities

around proposed New

SMS-II of Bokaro Steel

Plant 600.61 552.56 8%

LOI No-TCD-

1603dt.16.12.10

Abinash

Construction 28.5.11 14% AGM

23

Disposal of

muck/debris/slag/skull/ste

el scrap etc from SMS-I

on regular basis 194.35 178.8 8%

LOI

NO.HSCL/ED/TC/T

W/LT-06/2011-TCD-

2043 dt.19.8.11

R N Singh &

Co. 23.8.11 15.1.12 59% CTM-I

24

Electricals for illumination

and Airconditions system

with associated earthing

lighting protection & area

lighting part of welfare &

canteen Bldg.in CRM

complex(PKG-II) 322.75 296.93 8%

LOA

NO.HSCL/ED/TW/O

T-03/2011-TCD-2089

dt.25.8.11

Arun

Electricals 10.12.12 Nil CTM-I

25

Construction of Boundary

wall for enclosing 300

acre of land beyond slag

dump-2 165.52 152.28 8%

LOI

No.HSCL/ED/TW/LT-

5®/2011-TCD-2246

dt.13.9.11

B K B

Transport (P)

Ltd. 31.12/11 Nil AGM

26

Civil work for expansion &

modernisation of ware

house (PH-I) 989.99 589.05 8%

LOI

NO.ED/TC/TW/OT-

01/2011-TCD-1559

dt.17.6.11

hanuman

Enterprises 24.2.12 45.08% Sr.PE

317.18 8%

LOI

NO.ED/TC/TW/OT-

01/2011-TCD-1560

dt.17.6.11

Laxmi

Enterprises 24.2.12 45.08% Sr.PE

27

Design & construction of

two lane ROB comprising

of RCC superstructures

over hot metal tracks

including reinforced earth

structure and approach

roads including all allied

works on devisible

turnkey basis 722.58 677.73 6.21%

LOA

No.HSCL/ED/TC/TW

/OT-02/2011-TCD-

1277 dt.18.5.11

Sneha

marketing &

management

services 2.3.11 1.6.12 9% GM(Mod)

Page 13: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

28

Hiring of equipment

removal of OB including

blast drilling,excavation,

loading & transportation

by tipping trucks of all

kinds of soil,rock broken

rocks,hard

rock,extraneous materials

including mixed soil,

mixed hard soil,clay soil

pebbles,stone and will be

dubped

yard,transportation after

weighment to CSC

behara dump yard,kedla

washery & NR siding. 7717.14 7158.21 7.24$

LOA

No.HSCL/RD/TC/TW

/OT/04/2011/TCD-

2399 dt.8.10.11

R N Singh &

Co. 29.10.16 1.16% AGM(TC)

Page 14: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Chennai

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1 KV Dharampuri PKG-I 586 548 7%

HSCL/CHI/GMK/KV/

Dharam/Pkg-

I/09/3479 dt.5.10.09

Gayatri

Construction 5.10.09 5.4.11 100%

S.Dharam

seelan,Sr.

Site Engr.

Work

completed

and

handed

over to

KVS

Dharmapu

r on

15.03.201

2

2 KV Dharampuri PKG-II 302 268 -7%

HSCL/CHI/GMK/KV/

Dharam/Pkg-

II/09/3480 dt.5.10.09

Harrine

Associates 5.10.09 5.4.11 100% -do- -do-

3 KV No.1,OFT Trichy 322 292 -7%

HSCL/CHI/GM/KV

No.1 OFT/10

dt.15.7.10

Harrine

Associates 30.6.10 31.12.11 100% -do-

work

completed

and

handed

over to

KVS

Trichy on

31.03.201

2

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Hindustan Steelworks Construction Limited

Page 15: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

4 K V No.2,pondicherry 362 329 -7%

HSCL/CHI/GM/KV

No.2/pondy/10/4435

dt.15.12.10

Gayatri

Constructions 22.9.10 21.9.11 73% -do-

Due to

non

availability

of fund

progress

hampered

. Work in

Progress

5

Pondicherry University-

Gallary for various play

field 292.82 276 -5%

HSCL/CHI/GM/Addl.

(gallery)/11

dt.2.2.2011

Gayatri

Constructions 15.12.10 30.01.2012 100% -do-

Work

completed

and

handed

over to

P.U.

Page 16: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending June'12

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

DEOGHAR

1

Construction of Staff Qtrs

at

JNV/Luckeesarai,phase-

A,Group-C 145.06 175.11 05%above

HSCL/Deoghar/DG

M/2009-252

dt.18.12.09

Chandra

Shekhar

Kapri 7.11.09 31.10.12 100%

R Jha, Site

Supervisor

2

Construction of KD at

JNV/Luckeesarai,Phase-

A,Group-D 107.44 130.66 05%above

HSCL/Deoghar/DG

M/2009-253

dt.18.12.09

Jai Baba

Construction 7.11.09 31.10.12 100%

R Jha, Site

Supervisor

3

Construction of SB at

JNV/Luckeesarai,phase-

A,Group-E 247.42 300.91 05%above

HSCL/Deoghar/DG

M/2009-238

dt.9.12.09

Ganga

Construction 7.11.09 31.10.12 100%

R Jha, Site

Supervisor

4

Development work at

JNV/Luckeesarai,Phase-

A,Group-F 151.51 169.5 05%above

HSCL/Deoghar/DG

M/2009-248

dt.15.12.09

Ashok

Kumar 11.11.09 31.10.12 92%

R Jha, Site

Supervisor7

5

Construction of type-III(8

Nos) Type-II(2 Nos),Type-

I (2 Nos and GH(1 No)

qtr.at

JNV,Luckeesarai,Phase-

B,Group-B. 110.82 164.46 05%above

HSCL/deoghar unit

Head/2010-

606dt.18.9.10

Upendra

yadav 23.9.10 31.10.12 90%

R Jha, Site

Supervisor

6

Construction of 0.5 Nos

Girls Dormitory with 2

nos warden residence at

JNV,luckeesarai,Phase-

B,group-B 127.33 186.55 05%above

HSCL/deoghar unit

Head/2010-

588dt.8.9.10

Ashok

Kumar 1.11.10 31.10.12 98%

R Jha, Site

Supervisor

Due to

noncompl

etion to

approach

road by

State

Governme

nt, the

Princepal

is not

willing to

take over

the

building.

So,Lucke

esarai,pha

se-A &

Phase-B

work is

stopped.

Page 17: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

7

Construction of 0.5 Nos

Boys Dormitory with 2

nos warden residence at

JNV,luckeesarai,Phase-

B,group-C 127.33 186.55 05%above

HSCL/deoghar unit

Head/2010-

589dt.8.9.10

Chanda

shekhar

kapri 1.11.10 31.10.12 98%

R.Jha,Site

Supervisor

8

Construction of 0.50 unit

addl.dormitory with

warden residence at

JNV,hazaribagh(Jharkha

nd) 106.65 144.4 05%above

Sailendra

pd.Singh 2.11.2010 31.10.12 70%

J Prasad

,Jr.Engr.

9

Construction of 0.50 unit

addl.dormitory with

warden residence at

JNV,Dhanbad 106.65 144.4 05%above

HSCL/deoghar unit

Head/2010-

590dt.8.9.10

Junaid

Enterprise 4.10.10 31.10.11 completed

J Prasad

,Jr.Engr.

10

Construction of 0.50 unit

addl.dormitory with

warden residence at

JNV,deoghar 106.65 156.44 05%above

HSCL/deoghar unit

Head/2010-

655Adt.27.10.2010

Ganga

Construction 1.11.10 31.3.12 85%

R B Mahto,

Supervisor

11

Construction of 0.50 unit

addl.Dormitory with

warden residence at

JNV/Koderma/Jharkhand 106.65 144.4 5%

HSCL/Deoghar/unit

head/2010-743

dt.27.12.10

Ganga

Construction 2.12.10 31.8.12 95%

J Prasad

,Jr.Engr.

12

Construction of JNV

Purulia,Phase-B 324.72 464.47 5%

HSCL/Deoghar unit

Head/2010-725

dt.13.12.10

N.Islam &

Co. 25.11.10 23.11.11 completed

N.Dutta,Site

Engr.

13

Construction of addl.

Dormitory at

JNV/Birbhum 110.98 164.99 5%above

HSCL/Deoghar/Unit

Head/2011-328

dt.15.11.11

N.I.Infra

Engg.(P)

Ltd. 16.11.11 31.10.11 70.00%

N.Dutta,Site

Engr.

14

Construction of Additional

Dormitory at JNV

Bhagalpur(Bihar 161.7 234.9 05%above

HSCL/Deoghar/unit

Head/2012-479 dt

12.03.2012

M/s Ashok

Kumar 6.03.2012 4.12.2012 27%

R Jha, Site

Supervisor

Due to

noncompl

etion to

approach

road by

State

Governme

nt, the

Princepal

is not

willing to

take over

the

building.

So,Lucke

esarai,pha

se-A &

Phase-B

work is

stopped.

Page 18: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending June'12

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No.Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No. Name of Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Fab.& Erec.works of Pkg-

119 of NINL/Duburi 1238.87 1350.03

11.98%

below

CPM/HSCL/BBSR-

Duburi/08-09

dt.1.10.08 Patra fab.(P) Ltd. 27.4.07 31.3.10 76%

jalilSah,Sr.

Mgr.

2

Erection work with sheeting

& painting work of PKg.119

of NINL /Duburi 247.38 371.06

19.73%

above

CPM/HSCL/BBSR-

Duburi/08-02

dt.25.10.08 Rukmani Engg.works13.8.08 31.3.10 96%

RD

Tembhare,

Mgr(M)

3

Strl.Steel fab. and sheeting

works in BOF,GCP & CCP

area inside NINL Pemises 161.58 192.28

19%

above

HSCL/Dub/Head(M

&C)/2010-03

dt.1.3.10 R K Engg. 29.5.09 31.3.10 66%

Jalil Shah,

Mgr.

4

Balance strl.steel erection

works in BOF,GCP & CCP

area at NINL 161.17 222 31.18%

HSCL/DUB/DGM/L

OI/LT-10/10-3684

dt.4.12.10 R K Engg. 12.7.10 12.1.11 30%

RD

Tembhare,

Mgr(M)

5

Balance strl.steel erection

works in BOF,GCP & CCP

area at NINL 160.21 160.21 Nil

HSCL/DUB/DGM/L

OI/ P-119(B)/11-

3697 dt.23.3.11

Bhawani Enclaves

(P) ltd. 18.11.10 17.5.11 32%

V.Raja

Mgr(M)

DUBURI

Page 19: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending June'12

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Durgapur

Sl.No. Name of work

Estimated

cost in Lacs

Tendered

cost in Lacs

%age

above/belo

w such of

rates

applicable

i.e.receipts

Agt.No/LOI

No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress of

work in

%age

Name of

Engineer

Incharge

1

Construction of Workshop

sheds and extension of

work shop sheds,store

Godowns,Roads,Office

Bldg. etc in connection with

augumentation work of 200

locos per year at

Chittaranjan Locomotive

Works, including all earth

work,foundation

etc.complete excluding

electrical works at CLW

Chittaranjan

2424.17 2424.17

CE/B/21/201

0-11 dtd

26.8.10

M/S Happy

Hi-Rise

Infra

Ventures

(P) Ltd,

Hyd. & M/s

M.S

Constructio

n

9.6.2010 24 months 25.12%

A.K

Bandopadhy

ay, P.E,

HSCL/Durga

pur

Page 20: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Hazipur

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of kitchen

& dining,principal

residence type-III Qtrs

(8Nos),Type-II Qtrs(4

Nos),Type-I Qtrs (4

Nos) under phase-A at

JNV,Seohar. 208 192.13

7.63%

below

HSCL/DGM/sasara

m/2006-15

dt.6.1.07 A K Constn. 26.12.06 Dec,12 96% S D singh

Slow

progress

due to

land disput

& fund

2

Construction of

dormitories (D/S) RCC

framed structure for

264 boys,192 girls & 4

Nos warden Qtrs(D/S)

load Strs under phase-

A at JNV/madhubani 398.51 398.51 0%

HSCL/DGM/hajipur

/2007-108

dt.20.4.07 D K Constn. 7-Apr Dec,12 58% S D Singh

Slow

Progress

due to

fund

3

Constn. Of school

(S/S) RCC framed Strs

& dormitories (D/S) for

192 boys with 4 Nos

warden Qtrs under

phase-A at

JNV/Rohtas 357.62 355.43 0.61%

HSCL/DGM/hajipur

/2007-148

dt.16.6.07 Suraj Constn. 7-May July, 12 99% S D Singh

Completed

Handing

over is

under

Progess.

Statement showing Quarterly Progress of Original Works for the Quarter ending-June12

Hindustan Steelworks Construction Limited

Page 21: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

4

Constn.of 0.5 unit,96

girls dormitory with 2

Nos warden

residence,kitchen &

dining(S/S) RCC

framed Strs,Principal

residence,Type-I Qtrs

(4 Nos) type-II Qtrs(4

Nos) type-III Qtrs 8

Nos at JNV/Rohtas 260.72 250.88 3.77%

HSCL/DGM/hajipur

/2007-149

dt.16.6.07 S S constn. 7-May July, 12 99% S D singh

Completed

Handing

over is

under

Progess.

5

External Dev.works at

JNV/Seohar 138.88 138.88 0%

HSCL/DGM/hajipur

/2008-129 dt.8.5.08

satyendra

Kr.Singh 8-Apr Dec,12 94% S D Singh

Slow

Progress

due to

land

dispute &

harvesting.

6

External Dev.works at

JNV/patna 109.39 109.39 0%

HSCL/CPM/hajipur/

2008-208

dt.21.8.08 AK Constn. 8-Oct Completed 99% SD Singh

Slow

progress

due to

obstruction

of old bldg

& trees

7

External dev.works at

JNV/Rohtas 145.58 145.58 0%

LOA

No.HSCL/CPM/Haz

ipur/2008-231

dt.26.9.08

Jai Electrical

centre 8-Oct July, 12 99% SDsingh

Work held

up due to

land

dispute &

Local

Problem

Page 22: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

8

Construction of 0.5 unit

boys dormitory with 2

Nos warden

residence,0.5 unit girls

dormitory with 2 Nos

warden residence type-

III(8 nos) type-II Qtrs(2

Nos) type-I Qtrs (2

Nos) & G.H (1 No )

including dev. Works

under Phase-B at

JNV/Gopalgunj(bihar) 493.7 493.7 0%

HSCL/CPM/Hazipu

r/2009-271

dt.24.11.09

Sadanand

Gupta 9-Nov May,12 97% SD Singh

9

Construction of 0.5 unit

boys dormitory with 2

Nos warden

residence,0.5 unit girls

dormitory with 2 nos

warden residence,type-

III qtrs (8 nos) type-II

qtrs (2 nos) type-I qtrs

(2nos) and GH (1 No)

including Dev. Works

under Phase-B

atJNV/Seohar(Bihar) 494.06 404.06 0%

LOA

No.HSCL/CPM/Haz

ipur/2009-281

dt.4.12.09

Satyendra

Kr.Singh dec,09 Dec,12 78% SD Singh

Slow

progress

due to

harvesting.

10

External development

work at

JNV/Madhubani(Bihar) 218.3 218.3 0%

HSCL/CPM/Hazipu

r/2010-41 dt.3.1.10 ss constn. 10-Feb April'12 68% SD Singh

Page 23: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending Jun-12

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

HYDERABAD

1

Construction of external

works i.e. compound wall

etc.JNV-II Gulbarga Pkg

III 221.94 289.59 30.48%

AGM/HSCL/HY

D/JN/V-

II/19/2689 R R Associates 4.2.11 3.4.12 80.00%

K.Srikant

APE

2

Construction of school

bldg.and staff qtrs for

JNV Gulbarga Pkg-I

works 339.15 472.77 39.39%

HSCL/HYD/NVS

/51/124

dt.26.2.11

SLV Bldrs &

developers 4.2.11 3.4.12 88.04%

K.Srikant

APE

3

Construction of 1 unit

dormitory for boys, o.5

unit of girls dormitory and

kitchen, dining etc.for

JNV II Gulbarga Pkg-II 352.87 498.26 41.20%

HSCL/HYD/NVS

/52/125

dt.28.2.11 R R Associates 4.2.11 3.4.12 97%

K.Srikant

APE

4

Construction of external

works i.e. compound wall

etc JNV II prakashan Dist

AP Pkg-III 276.54 341.06 23.30%

HSCL/HYD/NVS

/50/123

dt.28.2.11

SLV Builders&

developers 4.2.11 3.4.12 88%

B Reddy

APE.

5

Construction of 1 unit

dormitory for boys, o.5

unit of girls dormitory and

kitchen, dining etc.for

JNV II Prakashan Dist AP

Pkg-II 351.77 456.48 29.76%

HSCL/HYD/NVS

/49/122

dt.28.2.11

SLV Builders&

developers 4.2.11 3.4.12 90%

B Reddy

APE.

6

Construction of school

bldg.and staff qtrs for

JNV-II prakasan Dist AP

Pkg-I 349.6 448.99 28.42%

HSCL/HYD/NVS

/48/122

dt.28.2.11 R R Associates 4.2.11 3.4.12 90%

B Reddy

APE.

Page 24: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

7

Construction of addl.

Classrooms at KV 2

Golkonda 122.09 123.31 1.90%

HSCL/GLB/KV/

Golkonda/2/672

dt.6.8.11

Chakri

construction 6.8.11 5.7.12 53%

Vijay

Kumar

Bijalani,A

PE

8

Construction of A type

school bldg. for KV at

kadapa 414.5 568.72 37.21%

HSCL/HYD/KVS

/47/100

dt.23.11.09

Laxmi

Construction 8.10.09 7.12.11 82%

Santish

patil,APE

Applied

for EOT

up to

28.02.201

3

9

Construction of 9 units of

SQ, compound

wall,development

works,elect.works for

KVS at KV,kadapa 164.15 209.1 27.38%

HSCL/HYD/KVS

/48/101

dt.23.11.09

Laxmi

Construction 8.10.09 7.12.11 83.25%

Santish

patil,APE

Applied

for EOT

up to

28.02.201

3

10

Construction of Para

medical & allied health

science institute at

Gulbarga,karnataka for

ESIC 30080.39 30080.39 At par

HSCL/Head(M&

C)/122-

Mktg/2011-4529

dt.13.10.11 NCC Limited 10.7.11 9.1.13 14.26%

D.Mishra

DGM

Page 25: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No. Name of Agency

Date of

commenc

ement

Time of

completi

on

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

S G Area civil works

Pkg.for Kahalgaon

STPP,stage-II,phase-I

(2x500MW) CS-4230-323-

9-CS-LOA=4230

dt.31.7.03 4799.91 629.74 9.50%

GGM/EZ/122/Coor

dn./03-1078

dt.24.11.03

Shankar Stone

works jan.04 Feb.07 90.16% V Singh

contract

has been

terminate

d by

NTPC

629.74 9.50%

GGM/EZ/122/Coor

dn./03-1079

dt.24.11.03 SKCPL -do- -do- 73.56% V Singh

contract

has been

terminate

d by

NTPC

2

Main Plant civil works

Pkg. for Kahalgaon

STPP,stage-II,Phase-II

(1x500mw)CS-4231-322-9-

CS-LOA-4283 dt.3.2.04 4921.27 605.31 6.79%

GGM/EZ/122/Cord

n./04-1454

dt.19.8.04 Satyendra Kumar 19.8.04 2.9.05 92.74% V Singh

contract

has been

terminate

d by

NTPC

3

Ash Dyke Pkg.for

KHSTPP-stage-II

(3x500mw)CS-4230-331-9-

CS-LOA-4302 dt.22.3.04 790.09 650 7.66%

HSCL/GM/TC/KLG

N works/2004-TCD-

601 dt.8.7.04

Banwori lal

Agarwal 10.4.04 30.6.08 91.95% V Singh

KAHALGAON

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 26: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and aboveHorticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimat

ed cost

in Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable

i.e.receipt

s Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of culture

centre at yangang,South

Sikkim 4675 3955 4.00%

GM(P)/RMDD-

Sikkim/yangang/06

/150 dt.5.5.06 Indus Buildwell 17.4.06 31.12.10 completed

P.K.Thakur,

Mgr.

2

Extended services for

Pilgrimage-cum-culture

centre,Solophok,namchi,ga

ngtok 2332 2215 5%

HSCL.Kol/Sikkim/I

BL/LOI/08-4502

dt.29.8.08 Indus Buildwell

Being

grannted upto

31.12.10 100%

P.K.Thakur,

Mgr.

Work

complete

d handing

over in

progress

3

Construction of upper three

floors (1st,2nd&3rd) of

Library Bldg.at

IACS,Jadavpur/Kol. 645 603.01 7%

CPM/HSCL/IACS/

2009/32 dt.27.3.09

P B Nigam

Udyog(P0 Ltd. 17.3.09 18 months 93%

M K

Sharma,Dy

Manager©

Work in

progress

Extension

of time

granted

upto

31.01.13

4

Construction of Pilgrimage-

cum-culture

centre,Solophok,Namchi,S

outh Sikkim 3472 3330 4.10%

DGM(P) RM &DD-

Sikkim/05/483

dt.15.1.05 Indus Buildwell 13.02.05

Being

grannted upto

31.12.10 100% P K Thakur

Work

complete

d handing

over in

progress

5 Addl.work at Solophok 1699 2069 5%

DGM(P) RM &DD-

Sikkim/05/483

dt.15.1.05 Indus Buildwell 13.2.05

Being

grannted upto

31.12.10 100% P K Thakur

Work

complete

d handing

over in

progress

6

Construction of

multipurpose cyclone

shelter in south 24

parganas,WB under

PMNRF at Sagar Block 299.39 477.14 7%

HSCL/Head(M&C)/

NDMA/2011/4707

dated 18.7.11

M/s Amiya

Commerce &

Constn.Co.(P)

Ltd. 06.06.11 18 months 32%

P K

Dasgupta,Sr

.Engineer(C) in Progress

Kolkata Project

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 27: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

7

Construction of

multipurpose cyclone

shelter in south 24

parganas,WB under

PMNRF at Namkhana

Block 296.95 469.96 7%

HSCL/Head(M&C)/

NDMA/2011/4839d

ated 31.8.11

M/s Amiya

Commerce &

Constn.Co.(P)

Ltd. 29.07.11 18 months 18%

P K

Dasgupta,Sr

.Engineer(C) in Progress

8

Addl.facility works at

solophok 1308 1243 5%

HSCL/Kolkata/Sikk

im/IBL/LOI/2010-

5474 dt.25.1.10 Indus Buildwell Jan.10 31.12.10 100% P K Thakur

Work

complete

d handing

over in

progress

9

Construction of

multipurpose cyclone

shelter in south 24

parganas,WB under

PMNRF at basanti & Kultali

Blocks 188.18 292.67 7%

HSCL/AGM/Kol/Pr

oj/NDMA/2011/09/

749dated 11.11.11

Roy

Construction 26.09.11 15 months 40%

P K

Dasgupta,Sr

.Engineer(C) in Progress

10

Construction of pile,Pile

cap,Retaining wall,Bore

well etc for b+G+4 INSDAG

Bldg.at Nonadanga,Kol. 182 281.43 5%

HSCL/AGM/Kol/Pr

oj./INSDAG/2011-

12/809 dt.28.12.11

Roy

Construction 24.11.11 6 months 67%

M K

Sharma,Dy

Manager©

in progrss

EOT upto

31.08.201

2

11

Construction work of 04

Nos class rooms along with

Dev.of play ground & Toilet

block in school at

CST,Ravangla 50.6 104.22 7%

HSCL/AGM/Kol/Pr

oj./Ravangla/2011-

13/810 dt.28.12.11

Roy

Construction 14.11.11 15 months 65%

P K

Thakur,Man

ager(Proj) in progress

12

Construction of Cultural

Centre Additional work at

Yangang. 338 321 4.65%

GM(P)/RMDD-

Sikkim/yangang/06

/150 dt.5.5.06 Indus Buildwell 17.4.06 31.12.10 50%

P.K.Thakur,

Mgr.

in

progress

13

Construction of School

Building Complex at JNV

South 24 Parganas II 522.43 870.11 5.00%

AGM/HSCL/JNV-

Canning/2012/265

dt.13.07.12

M/s Sadanand

Gupta 16.05.12 12 months 4%

Sri S.K

Chakraborty

in

progress

14

Construction of Boys'

Dormitory at JNV south 24

parganas II 384.24 637.4 5.00%

AGM/HSCL/JNV-

Canning/2012/266

dt.13.07.12

M/s Sadanand

Gupta 16.04.12 12 months 5%

Sri S.K

Chakraborty

in

progress

15

Construction of

Multipurpose Cyclone

Shalter in South 24

Parganas. WB under

PMNRF at Achintynagar of

Patharpratima Block 01

nos 93.68 148.04 7.00%

HSCL/Head(M&C)/

NDMA/2012/14/59

dt 23.02.2012

M/s laxmi

Narayan

Agarwal 10.10.11 15 months 34%

Sri P.K.

dasgupta Sr

Engineer (C)

in

progress

Page 28: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

16

Construction of

Multipurpose Cyclone

Shalter in South 24

Parganas. WB under

PMNRF at Laxmi

Janardhanpur of

Patharpratima Block 157.55 264 7.00%

HSCL/Head(M&C)/

NDMA/2012/5501

dt 11/16.05.12

M/s basu

Enterprise 03.04.12 15 months 11%

Sri P.K.

dasgupta Sr

Engineer (C)

in

progress

17

Construction of

Multipurpose Cyclone

Shalter in South 24

Parganas. WB under

PMNRF at Kuimuri of

Patharpratima Block 151.93 257.93 7.00%

HSCL/Head(M&C)/

NDMA/2012/5492

dt 09.05.12

M/s Atlantic

Projects 03.04.12 15 months 15%

Sri P.K.

dasgupta Sr

Engineer (C)

In

progress

18

Construction of

Multipurpose Cyclone

Shalter in South 24

Parganas. WB under

PMNRF at Muriganga II of

Sagar Block 151.63 251.65 7.00%

HSCL/Head(M&C)/

NDMA/Muriganga-

11/2012/5537 dtd

01.06.12

M/s Amiya

Commerce &

Constn.Co.(P)

Ltd. 03.04.12 15 months 2%

Sri P.K.

dasgupta Sr

Engineer (C)

in

Progress

19

Fabrication Erection

grouting etc of steel

structure for th

Construction of B+G+4

storied INSDAG Building at

Anandapur Kolkata 417.08 462.91 5.00%

Head (M&C)/ 122-

Mktg/HSCL/Insdag

/2012-5436 dt

23.04.12

M/s Vrinda

engineers (pvt)

Ltd 05.03.12 6 months 20%

Sri M.K

Sharma Dy

Mgr (C)

In

Progress

Page 29: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of School

Bldg.& dormitories works

at JNV,Deria 339.72 650.5 97%

HSCL/LKO/CPM/L

OI/JNV/09-1142

dt.10.10.09 J N Sharma 1.9.09 In progress 99.00%

H.T Azmi

(G.M)

2

Construction of Kitchen &

Dining,Principal residence

& Staff Qtrs at JNV,deoria 124.44 206.69 62%

HSCL/LKO/CPM/L

OI/JNV/08-321

dt.15.9.08 J N Sharma 1.10.08 In progress 99.00%

H.T Azmi

(G.M)

3

C/o residential flats at

SIDBI,Lucknow 595 660.86 13%

HSCL/LKO/A

Mgr(IC)/SIDBI/201

0-256 dt.1.11.10

R K

Construction 1.11.10 In progress 45%

H.T Azmi

(G.M)

4

Construction 9of girls

hostel,capital repairs

works and boundary wall

at Dr.HS Gaur

University,sagar 667.03 892.12 37% DSR

HSCL/GM/UP/SU/L

OI/2011-684

M/s Raghu

Infra(P) Ltd. 20.10.11 in progress 11.99% S.Banerjee

5

Construction of Abdul gani

Khan Stadium and

part(Approx) boundary

wall at Dr.HS Gaur

University,sagar 609.33 814.47 37% DSR

HSCL/GM/LKO/SU/

LOI/2011-677

Kandarp

Construction

(I) PVT Ltd. 14.10.11 In progress 7.85% S.Banerjee

6

Construction of external

Dev.works in NVS,Deoria 80 190.48 (36%) 54%

HSCL/LKO/A.Mgr(I

)c)/NVS/Contract0r/

2010-284

dt.1.12.10

Subhash

Singh 1.12.10 In progress 39.90%

H.T Azmi

(G.M)

7

Supply, Transportation &

Distribution of 4 Nos. of

Solar Lantern in U.P. 120 104 -15.38%

HSCL/GM/LKO/LOI-

761,dt:22.11.11

M/s Insta

Power 22.11.11 In progress 44.23%

H.T Azmi

(G.M)

LUCKNOW

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 30: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

8

Construction of

communication Centre at

Mou Gorepur, Distt;

Barabanki (U.P.) 107.25 105.1 -2.04%

HSCL/GM/UP/MST

C/CSR/2012-1109,

dt: 14.06.2012

M/s. DGM

Infra Pvt. Ltd 01.01.12 In progress 7.26%

H.T Azmi

(G.M)

Page 31: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in Lacs

%age

above/belo

w such of

rates Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress of

work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of

Residential quarter at

Balaghat

Mine,Beldongri

Mine,Chilka Mine and

Ukwa Mine of MOIL (A

B C & D type)

including internal and

external

electrification,sanitary

arrangements,Sewera

ge disposal

system,compound

wall,Gates,developme

nt works etc.&

infrastructure

amenities like

road,drain,electrificatio

n, water supply etc. 1842 1986.58 7.54%

HSCL/PH(WR)/NGP/

MOIL/PPS/F-

227/2011-101

dt.23.2.2011

M/s Prithipal

Singh &

Co.,Nagpur 1.2.11 30.5.12 65%

1) Shri

A.R.Agwal,A

M (C)

2.Shri

S.K.Job AM

(C)

3.

M.C.Sulakhe,

Pro.Eng

4.Ved Vrat

Puri,APE

NAGPUR

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 32: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

2

Construction of

residential quarter

atGumgaon Mine &

kandri Mine of MOIL

(A & C type) including

internal & external

electrification,sanitary

arrangements,sewerag

e disposal

system,compound

wall,gates,

development works

etc & infrastructure

amenities like

road,drain,electrificatio

n,water supply etc. 333 353.75 9.02%

HSCL/PH(WR)/NGP/

MOIL/PI/F-228/2011-

102 dt.23.2.2011

M/s Prime

Infrastructure 28.1.11 31.05.2012 70%

Shri A R

Agwan,AM©

3

Addition and

modification of Guest

house at balaghat

Mine of MOIL 138 149.15 7.63%

HSCL/PH(WR)/NGP/

MOIL/PPS/F-

229/2011-103

dt.23.2.11

M/s Prithipal

Singh &

Co.,Nagpur 4.2.11 31.08.2012 38.00%

Ved Vrat

Puri,APE

Balance

works site

not

handed

over by

client till

date

1 ICMR Site 1527 910.12 3.50%

HSCL/GM/BPL/F-

124/2006/1027

dt.14.4.06

M/s SAAGAR

Infrastructure

Ltd. 14.4.06 15 months 67% S.K. Charde

work

delayed

due to

non

finalizatio

n of

services

drawings

& agency

MUMBAI

Page 33: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

2

Balance construction

work of

concrets,Monkey

Carrols and road

works including other

related services for

ICMR at plot No.80-

1A,sasunavghar(Maljip

ada),Taluka-Vasai,Dist-

Thane(Maharastra) 1500 1434 3.50%

HSCL/mumbai/NIRR

H/NCPBR/Project(Ph-

I)-CC,MC &

RW/42/2010-W07

dt.17.9.10

GM Bijilani

Construction

(P) Ltd. 9.9.10 12 months 39%

kedar

pandey,Engr.

work in

Preogress

3

Laying of City Gas

Pipe Line at Bandra

Mira Rod, Mumbai-

Mahanagarn gas

limited (MGL) 982 982

5.11% on

direct cost

HSCL/Mumbai/GM/

(WR)/51-54/LOI-

11/2011-2171 dated;

08.11.2011

M/s Future

projects 26.09.11 24 months 17.005

Gyanendra

Singh

work in

Preogress

4

Quarantine Building,

ICMR Works at

Sasunavghar, thane 538 538

3.5% on

direct cost

HSCL/NCPBR/LE-

39/WO-11/2011

dated: 18.11.2011

M/s Sterling

and Wilson

Limited 28.11.11 6 months 4.60%

kedar

pandey,Engr.

work in

Preogress

Page 34: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

C/o Bldg.for JNV phase A

Saharanpur 827.8 765.44 9%

HSCL/AGM/ND/

JNV/2006-97

dt.20.1.06

Techno

Construction

Co 2.3.06 31.03.2012 99%

Shri

J.S.Ansari

,AGM

Partially

handedov

er balance

work in

progress

REPE of

Rs.

959.05

has

submitted

to NVS

2

balance work of

Rejuvenation of

cafeteria,Museum shop &

main gate and other allied

area in NHHM craft

measum Pragati maidan 140.26 128.68

DSR

item+64%

MR9%

HSCL/GM/ND/C

raft

measum/2010-

1060-441

dt.10.10.11

SP

Construction 10.10.11 9.6.12 95%

Shri J.U

Ansari(

AGM) &

Shri B.R.

Divya

Manager

(C)

work in

progress

3

Construction of handloom

Maktg.complex at janpath -- 3514.31

Item rate

tender

LOI

HSCL/GM/ND/h

andlooms/2009-

664 dt.20.8.09

joycon

Infrastructure

Ltd. 26.8.09 31.03.2012 98%

Shri J.U

Ansari(

AGM) &

Shri B.R.

Divya

Manager

(C)

work in

progress

4

C/o addl. Dor. Without

warden residence for 96

boys & 48 girls at JNV

Dist.Jind 189.19 170.07 80%

LOI

HSCL/GM/ND/J

NV/Jind/2009-

366 dt.14..5.09

Sutej Singh

Yadav 29.8.09 31.01.2012 99%

J U

Ansari,AG

M

work in

progress

5

C/o addl. Dor. For 24 boys

& 48 girls at JNV,Jhajjar 108.18 100.03 88%

HSCL/GM/ND/jN

V/Jhajjar/2010/1

29 dt.6.2.10 -do- 15.2.10 31.03.2012 98% -do-

work in

progress

Re RPE

for Rs

154.93

lacs has

been

submitted

to NVS

NEW DELHI

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 35: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

6

C/o regional office for

NHDC Ltd. at

Panipat(haryana) 119.41 115.49 27%

HSCL/GM/ND/N

HDC-

panipat/2010-

1076 dt.16.11.10

Tameerat

group 20.11.10 28.02.2012 98%

J U

Ansari,AG

M

Add. Work

in

Progress

7

Rejuvenation of cafeteria

museaum

shop,Toilets,maingate in

crafts measeum phase-A 115.53 135.67 9%

HSCL/GM/ND/C

raft

Meseaum/2010-

1060 dt.10.11.10

S P

Construction 19.10.10 31.010.2011 100%

J U

Ansari,AG

M & Shri

B.R.Divya

Manager

(C)

Complete

d

8

moderation of STC at

CISO,Chandigarh 1642 1486.91 9.60%

HSCL/GM/ND/C

ISO/2011-261

dt.26.3.11

Jaycon

Infrastructure 8.4.11 7.7.12 30%

Shri

gagan

Preet

Singh, Sr.

Site

Engg/Miss

Vidhuti

sinha,

Engineer

(T)

work in

progress

9

rennovation & expansion

work at Rajachari

College,Raja garden 105.4 16%

HSCL/GM/ND/R

ajdhani

college/2011-70

dt.31.5.11

Tameerat

group 11.4.11 31.01.2012 98%

J U

Ansari,AG

M

work in

progress

10

Rennovation of ESIC

Dispensary at mayapuri 123.75 35%

HSCL/GM/ND/E

SIC/Mayapuri/20

11-190

dt.10.4.11

Mohit buildtech

(P) Ltd. 1.4.11 30.06.2012 30%

J U

Ansari,AG

M

work in

progress

11

Furnishing of AICTE office

at 10th floor,Chandralok

Bldg.janpath,New Delhi 143.35 133.72

DSR+49%

MR at per

HSCL/GM/ND/AI

CTE/LOI/2011/5

50 dt.8.1.11

NCI global

infratech 24.10.11 15.1.12 100%

J U

Ansari,AG

M & Shri

B.R.Divya

Manager

(C)

Complete

d

Page 36: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Super speciality 150 bedded

Hospital at ECR/Patna 2249 2136.55 5%

LOI/2007-P-117

dt.5..3.07

Adya Raj

Developers

(P) Ltd. 5.3.07 31.12.10 100%

RD

Sutrakar,A

GM

2

Construction of shed at

ECR/Samastipur 2100 1995 55

LOI/2007-P-167

dt.2..4.07

Samiur

rahman Khan 10.10.07 30.6.10 100%

RD

Sutrakar,A

GM

3 Earth work at WP,ECR 762.07 722.82 5.15%

LOI/2007-P-47

dt.16.1.10

Dushad

Construction

(P) Ltd. 18.1.10 30.9.10 95%

A

Sengupta,

Sr.Tech.

Superviso

r

4 Road work at WP,ECR 920.17 873.24 5.10%

LOI/2007-P-48

dt.16.1.10 -do- -do- -do- 100%

RD

Sutrakar,A

GM

5

left Embrassement work at

Jhanjharpur 1477.7 1329.93 10%

LOI/2007-P-11

dt.6.2.10

Sashi

galvanising

(P) Ltd. 16.2.10 31.5.10 100%

A.Kumar,

AGM

6

Right Embrassement work at

Jhanjharpur 1724.63 1552.17 10%

LOI/2007-P-119

dt.6.2.10 -do- -do- -do- 100% -do-

7 Road work at RWD,Buxer 749.93 695.56 7.25%

LOI/2007-P-334

dt19.6.10 -do- 20.6.10 3.8.11 61% -do-

8 Bakhtiyarpur Flyover of ECR 552.89 525.24 5%

LOI/2007-P-461

dt22.7.09

Adya Raj

Developers

(P) Ltd. 15.7.10 31.12.10 50% -do-

9

Bagmati Extension scheme-

execution 79,800 72,500 10%

HSCL/MOU/Bag

mati/01

dt.8.10.05

Avantika-

Ghra(JV) 15.6.06 31.3.13 56%

V.Singh,

Sr.PM

10

Bagmati Extension scheme-

Survey & DPR 1,248 1.72%

HSCL/MOU/Bag

mati/02

dt.8.10.05

Coolroc

technologies

Ltd. 15.6.06 31.3.13 56%

V.Singh,

Sr.PM

PATNA

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 37: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

11

Bagmati extension scheme-

supervision 2,684 3.70%

HSCL/MOU/Bag

mati/03

dt.8.10.07

Coolroc

technologies

Ltd. 15.6.06 31.3.13 56%

V.Singh,

Sr.PM

12

tropical Disease: Research

centre at RMRI 3,535.00 3,399.00 4%

HSCL/CPM/Pat/

RMRI/08-P-83

dt.14.7.08

Nandlakl &

Co. 20.4.08 31.3.12 60%

V.Singh,

Sr.PM

Page 38: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

1

Construction of community

Health Centre at Leshligunj

,Dist-palamu

314 294.84 -6.10%

HSCL/RNC/TC

/LOA/2008-123

dt.18.2.08

sadanand

Gupta18.2.08 20 months 100%

B N

Singh,PH

Work

complete

on

available

site &

handed

over. No

scope for

further

work.

2

Construction of Community

Health Centre atbaghmara

,Dist-Dhanbad

317 298.41 -6%AGT No.832

dt.5.5.08

Ganvir's Spares

and Constn.18.4.08 20 months 95% -do-

Inadequat

e fund

allotment

3

Construction of community

health centre at Gola Dist-

hazaribagh

317 298.38 -6.10%LOA No.282

dt.3.4.08

Aman

Enterprises5.4.08 20 months 98% -do-

4

Construction of community

health centre at Kairo Dist-

Deoghar

328 308.77 -6%LOA No.292

dt.5.4.08

Singh Sons

Archcon (P) Ltd.8.4.08 20 months 100% -do-

5

Construction of community

health centre at Maharama

Dist-Godda

328 308.32 -6%LOA No.661

dt.27.5.08

Ranchi

Developers Ltd.27.5.08 20 months 32% -do-

Due to

Stoppage

of work.

6

Construction of community

health centre at JainagarDist-

Koderma

317 297.98 -6%LOA No.662

dt.27.5.08Anamica Engg. 30.5.08 20 months 94% -do-

7

Construction of community

health centre at

SatgawanDist-Koderma

317 297.91 -6.02%LOA No.691

dt.5.6.08

Jai baba

Constn.6.6.08 20 months 95% -do-

RANCHI

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending-June12

Page 39: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

8

Construction of community

health centre at DevipurDist-

Deoghar

328 308.32 -6%LOA No.692

dt.5.6.08S K constn. 6.6.08 20 months 86% -do-

9

Construction of community

health centre at Chainpur

Dist-palamu

314 295 -6.05%LOA No.728

dt.14.6.08RNT Constn. 15.6.08 20 months 45% -do-

Fund

Problem

10

Construction of community

health centre at

pathalgawan, Dist-Godda

328 307.99 -6.00%LOA No.828

dt.26.7.08

Ranchi

Developers Ltd.11.8.08 18 months 40% -do-

Due to

Stoppage

of work.

11

Construction of community

health centre at

Sunderpahari, Dist-Godda

328 308.29 -6%LOA No.972

dt.18.9.08Dinesh Sharma 22.9.08 20 months 65% -do-

12Construction of Sadar

Hospital at Koderma485 455.9 -6%

LOA No.754

dt.30.6.08Singh Bros. 24.10.08 20 months 42% -do-

Fund

Problem

13

Construction of community

health centre at Borio, Dist-

sahibgunj

328 305.04 5%

HSCL/RNC/TC

/LOA/2009-181

dt.13.3.09

Rai Electricals 25.3.09 9-Dec 50% -do-Land

problem

14

Construction of community

health centre at Maheshpur,

Dist-Pakur

328 305.04 -7%

HSCL/RNC/TC

/LOA/2009-120

dt.20.2.09

Crescent

Construction9-Feb 9-Dec 87% -do-

15

Construction of 192 bedded

Boys Dorm.& 8 nos type-III

Qtrs at JNV/Sahibgunj

223.53 321.33 0.50%

LOA

No.HSCL/RNC/

TC/LOA/2009-

83 dt.14.3.09

H K Singh 9-Mar 18 months 99%

S.K.

Sinha

AGM

Finishing

work in

Progress.

16

Construction of School

Bldg.,Kitchen,dining,Principa

l residence & 4 nos Type-II

Qtrs at JNV/Sahibgunj

253.28 365.43 0.50%

LOA

No.HSCL/RNC/

TC/LOA/2009-

184 dt.14.3.09

Ashyina Constn 9-Mar 18 months 99% -do- -do-

17

Construction of 192 bedded

Boys Dorm. 96 bedded girls

dorm.,B/wall fencing & type

IV Qtrs under phase-A at

JNV/Jashpur& 8 nos type-III

Qtrs at JNV/Sahibgunj

361.79 489.76 5%LOA-651

dt.8.10.09Ashyina Constn 9-Oct 15 months 97% -do-

18

Construction of SB,KD & T-

III Qtrs,8 nos phase-A at

JNV/Jashpur

262.09 353.24 5%LOA-652

dt.9.10.09

Aman

Enterprises9-Oct 15 months 96% -do-

19

C/o SB,KD &T-III Qtrs,8

Nos,Phase-A at

JNV/Jashpur

89.85 152.86 5%LOA No.469

dt.8.10.09Ashyina Constn 9-Oct 15 months 40% -do-

Due to

site

Problem

Page 40: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

20

C/o 96 bedded boys

Dormitory under phase-B at

JNV/Sahibgunj

150.73 150.73 5%LOA.No.155

dt.16.2.10

Junaid

Enterprises10-Feb 10 months 95%

S.K.

Sinha

AGM

21

C/o 96 bedded Girls

Dormitory under phase-B at

JNV/Sahibgunj

150.65 150.65 5%LOA.No.169

dt.18.2.10Bahadur & Sons 10-Feb 10 months 97% -do-

22

C/o 96 bedded boys

Dormitory with 2 nos W/R

under phase-B at

JNV/Simdega

130.72 130.66 5%LOA.No.167

dt.18.2.10

Sadanand

Gupta10-Feb 12 months completed -do-

23

C/o 96 bedded Girls

Dormitory with 2 nos W/R

and GHunder phase-B at

JNV/Simdega

131.64 131.07 5%LOA.No.168

dt.18.2.10

Bhusan

Constn.Co.10-Feb 12 months completed

G D

Yadav

24

C/o Community Health

centre at Barharwa Dist

sahibgunj

328 308.32 -6.00%LOA.No.690

dt.5.6.08

Raja

Enterprises

Constn.Co.(P)

Ltd.

No. Land 20 months 24%B N Singh

PH

Land

problem

25

C/o Community Health

centre at harihar gunj Dist

Palamu

314 295.16 -6%LOA.No.693

dt.5.6.08

Abhay

Enterprises20 months -- -do-

26

C/o 96 bedded boys,96

bedded Girls Dormitory,type-

I,Qtrs.2 No.Type-II Qtrs-2 no

and dev.work under phase-B

at JNV/West Singhbhum

367.85 367.85 5%LOA No.148

dt.11.2.10Ashyina Constn 10-Feb 10 months 100%

S.K.

Sinha

AGM

27

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chhaterpue &

hazaribagh,Dist Palamu

2638.05 2638.05 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-002 dt

19.4.10

Chandi

Enterprises20.3.10

18 months + 5

years

Maintenance

82%

G S

Prasad,P

H(

PMGSY)

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

Page 41: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

28

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Hussainabad

&Bishrampur,Dist Palamu

1762.3 1762.3 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-003 dt

24.4.10

Abhay

Enterprises20.2.10

18 months + 5

years

Maintenance

68% -do-

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

29

Construction of Road & its

maintenance of 5 years

under PMGSY in

blockDaltongunj satbarwa

&Chainpur,Dist Palamu

1074.53 966.89 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-001 dt

15.4.10

Reasonable

Constn(P) Ltd.20.3.10

18 months +5

years

Maintenance

44% -do-

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

30

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Panki & Leshligunj,Dist

Palamu

1320.38 1319.72 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-007 dt

24.5.10

Indian Electrical

services6.4.10

18 months + 5

years

Maintenance

42% -do- -do-

31

Construction of Road & its

maintenance of 5 years

under PMGSY in

blockSimaria

Tandwa,lewalong &Gidhorj

Dist Chatra

2699.37 2699.37 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-004 dt

24.4.10

Gupta &

co.Developers

(p) Ltd.

20.3.10

18 months + 5

years

Maintenance

64% -do-

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

Fprest

problem

Page 42: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

32

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Itkhori,Chatra

sadar,Huntergunj,Partappur

& Kundaj Dist Chatra

2372.56 2372.56 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-005 dt

7.5.10

-do- 7.4.10

18 months +5

years

Maintenance

34% -do-

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

Fprest

problem

33

Construction of Road & its

maintenance of 5 years

under PMGSY in block

patan Dist-Palamu

899.63 805.7 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-008

dt11.6.10

Niraj

Enterprises1.6.10

18 months +5

years

Maintenance

67% -do-

Due to

Naxal

problem.

Acute

shortage

of

bitumen.

Crusher

Strike.

34

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Manatu Dist-Palamu

966.32 966.32 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-006

dt19.5.10

H.H.Enterprises 25.4.10

18 months + 5

years

Maintenance

72% -do- -do-

35Construction of CHC at

Taljalhari,Dist Sahibgunj328 305.04 7%

HSCL/RNC/TC

/CHC/LOA/201

0-828 dt.9.8.10

Anamica Engg. 10.8.10 20 months 29%B N Singh

PH

DRR

under

approval

36

Construction of 96 bedded

Girls dorm. & 4 Nos Type-I

Qtr. At JNV/Sahibgunj

106.71 153.58 5%

HSCL/RNC/TC

/LOA/2009-

185dt.14.3.09

Amman

Enterprises9-Mar 18 months 99%

S.K.

Sinha

AGM

Finishing

work in

Progress.

37

C/o SB,KD & T-III Qtrs,8

Nos Phase-A at

JNV/Jashpur

262.09 353.24 5%LOA-652

dt.8.10.09

Amman

Enterprises9-Oct 15 months 90%

GD

Yadav,Sr.

Site Engr.

38

C/o 96 bedded Girls

dorm.,Type-I & II Qtrs,Phase-

B at JNV/pakur

336.63 336.63 5%LOA-655

dt.9.10.09

Junaid

Enterprises9-Oct 10 months completed

AK

Pandey

,DGM

39C/o Development at JNV

Sahibgunj under phase-A83.67 124.49 5%

HSCL/RNC/TC

/AGT/2010-961

dt.23.9.10

Ashyina Constn 8 months 60% -do-

Page 43: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

40C/o Development at JNV

Bankura under phase-A77.66 111.02 5%

HSCL/RNC/TC

/AGT/2010-

959dt.23.9.10

Aman

Enterprises

01.10.201

28 months 87% -do-

Due to

Non

approval

of

41

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chas,dist.-Bokaro

461.56 421.05 10%

HSCL/RNC/TC

/AGT/2010-

12dt.7.8.10

Subhas Singh

Choudhary10.7.10

18 months +5

years

Maintenance

45% -do-

Due to

actual

shoetage

of

bitumen.

Crusher

strike

42

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chas,dist.-Bokaro

417.79 385.47 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

11dt.7.8.10

Malti

Enterprises10.7.10 18 months 80% -do-

43

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chas,dist.-Bokaro

439.2 373.34 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

16dt.7.8.10

AP Bariyar &

sons1.7.10

18 months +

5years

maintenance

42% -do-

Due to

shortage

of

bitumen.

Crusher

strike.

44

Construction of Road & its

maintenance of 5 years

under PMGSY in

blockBermo & Nawadih,dist.-

Bokaro

480.92 441.97 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

712dt.12.7.10

Shiv Shail

Construction15.7.10

18 months +

5years

maintenance

85% -do-

45

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Gomia,dist.-Bokaro

485.3 481.49 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

733dt.17.7.10

sadanand

Gupta20.7.10

18 months +

5years

maintenance

10% -do-

Work

started

delayed

due to

Forest

problem.

46

Construction of Road & its

maintenance of 5 years

under PMGSY in block

jaridih,dist.-Bokaro

312.65 299.88 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

15dt.30.8.10

Dubey

Construction15.7.10

18 months +

5years

maintenance

96% -do-

Page 44: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

47

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Kasmar,dist.-Bokaro

434.84 430.46 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

14dt.17.8.10

Ashutosh

Construction15.7.10

18 months +

5years

maintenance

70% -do-

Due to

actual

shortage

of

bitumen.

Crusher

strike

48

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Kasmar,dist.-Bokaro

305.37 259.57 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

10dt.30.7.10

Maa

Chhinamastika

Construction

10.7.10

18 months +

5years

maintenance

75% -do- -do-

49

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Nawadhi,dist.-Bokaro

497.31 497.31 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

13dt.7.8.10

Malti

Enterprises22.7.10

18 months +

5years

maintenance

80% -do-

50

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Petarwar,dist.-Bokaro

503.27 427.85 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

17dt.2.9.10

AP Bariyar &

sons2.7.10

18 months +

5years

maintenance

63% -do-

Due to

actual

shortage

of bitumen

Crusher

strike.

51

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chandankayari,dist.-Bokaro

492.86 414.33 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

803dt.4.8.10

Sachin Kr.Singh 10.8.10

18 months +

5years

maintenance

27% -do- -do-

52

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chandankayari,dist.-Bokaro

455.43 419.25 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

09dt.29.7.10

Md.nasim

Ansari10.7.10

18 months +

5years

maintenance

90% -do-

53

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chandankayari,dist.-Bokaro

255.13 216.87 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

18dt.26.9.10

Sachin Kr.Singh 10.7.10

18 months +

5years

maintenance

50% -do-

Due to

actual

shortage

of bitumen

Crusher

strike.

Page 45: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

54

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chas,dist.-Bokaro

350.96 287.78 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

985dt.28.9.10

Sk Enterprises 29.9.10

18 months +

5years

maintenance

70% -do- -do-

55

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Gomia,dist.-Bokaro

348.85 348.81 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

983dt.28.9.10

Sanjay

Construction29.9.10

18 months +

5years

maintenance

15% -do-

Due to

actual

shortage

of bitumen

Crusher

strike.

Forest

Problem

56

Construction of Road & its

maintenance of 5 years

under PMGSY in block

bishnugarh,dist.-Hazaribagh

500.22 452.15 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

879dt.23.8.10

Nirmata

Engg.Constn.

(P) Ltd.

25.8.10

18 months +

5years

maintenance

85% -do-

57

Construction of Road & its

maintenance of 5 years

under PMGSY in block

bishnugarh,dist.-Hazaribagh

323.73 293.6 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

892dt.28.8.10

Ram tahal

Saran30.8.10

18 months +

5years

maintenance

90% -do-

58

Construction of Road & its

maintenance of 5 years

under PMGSY in

blockmandu & Gola,dist.-

Ramgarh

317.96 267.09 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

984dt.28.9.10

Suraj Lal singh 29.9.10

18 months +

5years

maintenance

55% -do-

Due to

shortage

of

bitumen.

Crusher

strike.

59

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Chchu,Barkakhana,Barhi &

Couparandist.-Bokaro

355.3 351.07 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

905dt.3.9.10

Siddartha

Constn.5.9.10

18 months +

5years

maintenance

50% -do-

Due to

shortage

of

bitumen.

Crusher

strike.

60

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Ichakatakamasandi &

Padma dist.-Hazaribagh

433.57 385.84 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

880dt23.8.10

SK Enterprises 25.8.10

18 months +

5years

maintenance

35% -do-

Due to

shortage

of

bitumen.

Crusher

strike.

Page 46: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

61

Construction of Road & its

maintenance of 5 years

under PMGSY in block

Ramgarh & patratu dist.-

Ramgarh

210.07 188.96 10%

HSCL/RNC/TC

/AGT/PMGSY/

2010-

963dt24.9.10

Torpedo

Construction25.9.10

18 months +

5years

maintenance

50% -do-

Due to

shortage

of

bitumen.

Crusher

strike.

62

C/o Road & its 5 yrs routine

maintenance under PMGSY

in block chandankiyari,

Chas, Peyerwar & Kasmar

Distt-Bokara.

731.65 689.61 10%

No.

HSCL/RNC/TC

/PMGSY/AGT./

2012-31

dt./12.03.2012

M/s Shiv Shail

Construction

Pvt.Ltd

18 months 18% -do-

63

C/o Road & its 5 years

routine maintenance under

PMGSY in block Gomia &

Nawadih

329.57 329.49 10%

Agt.

NoHSCL/RNC/

TC/PMGSY/AG

T./2012-32

dt.31.03.2012

M/s Malti

Enterprises18 months 15% -do-

64

C/o phase- B (Balance) 0.50

Boys Dormitory at JNV/

Simdega .

with Cl

154.49149.93 5%

LoA No.

HSCL/RNC/TC

/JNV/2012-

318B dt.12th

March 2012

M/s Sadanand

Gupta

13th

March

2012

6months 35%

S.K.

Sinha

AGM

65

C/o Phase-B (Balance) 0.50

unit Boys Dormitory at JNV/

East Singhbhum

with Cl

126.70126.7 5%

LOA No.

HSCL/RNC/TC

/JNV/LOA/2012-

321 B dt. 20th

march 2012

M/s Bahadur &

Sons

30th

March

2012

6 months 25%

S.K.

Sinha

AGM

66

C/o Boys Dorm, Guest

House & Devolopment under

Phase- B At JNV/Bankura.

219.67 219.67 5%

LOA No.

HSCL/RNC/TC

/LOA/2012-496

dt. 19th April

2012

M/s Aman

Enterprises 12 months

S.K.

Sinha

AGM

Due to

non

receipt of

drawings.

67

C/o 0.5 Girls Dorm 7 Type-III

Qtrs. under phase-B at

JNV/Bankura.

253.09 253.09 5%

LOA No.

HSCL/RNC/TC

/LOA/2012-497

dt. 19th April

2012

M/s Junaid

Enterprises

25th June

201212 months

S.K.

Sinha

AGM

late

receipt of

Drawings.

Page 47: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

68

C/o 0.5 unit Boys Dorm.

With two nos. warden

residence under Phase -B

(Balance) at JNV/Pakur

178.471 178.46 5%

LOA.No.

HSCL/RNC/TC

/ LOA/2012-

608 dt. 10/11th

May 2012

M/s Junaid

Enterprises

20th may

201206 months 5%

S.K.

Sinha

AGM

Page 48: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Frist Raising of

Ashdyke (Lagoon-C)

for Rourkela CPP-

II(2x60) MW,NSPCL

LOI NO-

NSPCI/CS/1009724/A

L-11047 Dtd

27.10.2011

395.57lakhs

(Receipt

from Client)

371.55

Lakhs

6.07%

(below)

1)HSCL/RKL/MKTG

/NSPCL/L-C/2011-

611

Dtd

2)HSCL/RKL/MKTG

/NSPCL/L-

C/2011/610

M/s Jaya

Projects ltd

70%

M/s Sanjit Ku

Naik

30%

26/11/11

As per

Client

Actual

start of

work

26.12.11 25.11.12

Rs70.20

Lakhs

C.L.Shrist

ava

AGM

Front not

available

due to

technical

reason of

client

2

Construction of New

Telephone Exchange

Building under 4.2 MT

Expansion at RSP

RSP,Rourkela (PKG

072A) A/T

No.PA/Proj/385(072A)/

99036/605-

R/11049284 dtd

22.12.2012

143.31

lakhs

Including

Taxes

(Receipt

from Client)

125.04

Lakhs

Excluding

Air

Conditioni

ng work

and

service

tax

(+)6.6%

Excluding

Air

Conditioni

ng work

(Below)

HSCL/RKL/MKTG/R

SP/Tel/T-

224/2012/82 dtd

21.01.2012

M/s Rai

Electricals

17.11.11

As per

Client 16.09.2012

Rs7.23

Lakhs

C.L.Shrist

ava

AGM

Constn.of

colum is

in

Progress

3

BOF shop platfrom,

Bunkers, pipe

supporting structure

and other facilities in

BOF & CPP Area RSP

2701.73

lakhs

(Including

service tax

& OVAT)

(Receipt

from Client

1138.92

lakhs

(50% of

work

awarded)

Excluding

ST &

OVAT)

5.25%

(Below)

HSCL/RKL/MKTG/R

SP/BOF/T-

223/2012/232 dtd

05.03.2012

M/s Four

Pillars

Communicati

on Pvt Ltd.

17.01.12

As per

Client 16.09.2012 NIL

C.L.Shrist

ava

AGM

Work of

M/s Four

Pillars

com Pvt

Ltd was

terminate

d on

25.04.12

ROURKELA

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 49: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Do- Do-

484.78

lakhs

(50% of

work

excluding

cost of

Materials)

Sl No 1&

2 of BOQ

1.29%

(Below)

LOA No:

HSCL/RKT/TC/RSP/

BOF/T-

223/2012/568 dtd

21.05.2012

M/s MCK

Kutty &

Company

21.05.201

2 for the

date of

LOA

issued to

agency 16.09.2012

Rs 2.30

Lakhs

C.L.Shrist

ava

AGM

fabrication

stared in

the month

of June'

4

Bay Extension &

Enabling works for

Additional Heat

Treatment facilities at

SPP,package (02)

RSP,Rourkela A/T No;

P4/Proj/257/09403(Pk

g-02)/12049013

dtd6.3.2012

560.43.Lakh

s (Including

taxes

466.01

lakhs

7.52%

(Below)

LOA No.

1)

HSCL/RKL/TC/BAY/

EXTN/RSP/T-

217/2012/345 dtd

30.03.20112

2)

HSCL/RKL/TC/BAY/

EXTN/RSP/T-

217/2012346

dtd30.03.2012

3)

HSCL/RKL/TC/BAY/

EXTN/RSP/T-

217/2012 F1+F47

Dtd 30.03.20128

1)M/s Ponia

Enterprises(S

trl & Elet)

2) M/s

jethson

Building, Pvt

ltd (piling

Work)

3)M/s R.C.G

Construction

(Civil Work)

29.02.201

2

29.02.201

2

29.02.201

2

28.08.2012

28.08.2012

28.08.2012

Work Not

Started

C.L.Shrist

ava

AGM

Work not

started

due to

non

avalibility

of site

clearance

from RSP

Page 50: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/belo

w such of

rates

applicable

i.e.receipts Agt.No/LOI No. Name of Agency

Date of

commencem

ent

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

SG Area civil works

for sipat Thermal

power project stage-

I for NTPC Sipat

PKG.-I Civil work 1900 2882.41 (-)4.30%

GM/BH/TC/201/

LT(584)/04/1370

dt.27.10.04 BSBK(P) Ltd. 30.9.04

Extn up to

31 3.12 93.00%

S K

Mishra,AM(C

)

2

SG Area civil works

for sipat Thermal

power project stage-

I for NTPC Sipat

PKG.-I Structural

work 4400 3349.42 (-) 2%

GM/HSCL/BH/1

435 dt.27.3.06

Sunil Hi tech

Engr.Ltd. 2.12.05

Extn up to

31.3.12 97%

NK

Vasishnava,

DM(M)

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

SIPAT

Page 51: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

Hindustan Steelworks Construction Limited

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates Agt.No/LOI No. Name of Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Construction of 150

bedded district hospital at

Tepania,Udaipur in South

Tripura Dist. 2312.98 1914.47 5.74%

HSCL/Hed(Mktg)/Tep

ania-udiapur/150

BDH/2007-01 M P Khaitan 8.5.07 7.11.08 87%

SK

THAKUR,

Site

Encharge

2

Construction of 150

bedded district hospital at

bhagban nagar,

Kailashar in North Tripurs

Dist. 2394.17 1214.75 7.48%

HSCL/Hed(Mktg)/Bag

hbannagar_kailashar/

North Dist./150

BDH/2007-02

P B Nirman

Udyog (P) Ltd. 8.5.07 7.11.08 80% -do-

3

Construction of 150

bedded District hospital at

kulai Dhalai Dist. 2356.95 1215.17 7.45%

HSCL/Head(Mktg)/Ku

lai/Dhalai Dist/150

BDH/2007-03

Sikaria Infra

projects (P) Ltd. 8.5.07 7.11.08 75% -do-

4

Construction and

maintenance of rural

roads under PMGSY,

phase-iv at Dhalai

Dist,NIT-2 1327.33 1370.83 10%

HSCL/Tripura/PMGS

Y-24A/works/2006-

224(1) dt.24.11.06

BGM

Consotium(p)

Ltd. 9.12.06 8.12.07 96.96%

S K

Mondal

5

Construction &

Maintenance of Rural

roads under PMGSY

phase-V at Dhalai

Dist.NIT-10 809.69 801.59 10%

HSCL/Tripura/PMGS

Y-25A/works/2007-

300 dt.25.7.07

RKMinerals &

Trading (P) Ltd. 9.8.07 8.8.08 95.84% S.N Baral

6

Construction &

Maintenance of Rural

roads under PMGSY

phase-V at Dhalai

Dist.NIT-12 439.46 617.36 10%

HSCL/Tripura/PMGS

Y/NIT-12/2007-641

dt.5.11.07 Manoj Ghosh 20.11.07 19.11.08 94.00% S.N Baral

7

Construction &

Maintenance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-15 1211.51 1250.88 10%

DGM/HSCL/Tripura/P

MGSY/NIT-15/2007-

576 dt.13.10.07

Shree Goutam

Construction co.

Ltd. 28.10.07 27.10.08 100.00% D P Singh

8

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-16 763.09 890.25 10%

AGM/HSCL/Tripura/P

MGSY/NIT-16/2007-

700 dt.13.12.07 J C Corporation 28.12.07 27.12.08 100.00% D P Singh

TRIPURA

Statement showing Quarterly Progress of Original Works for the Quarter ending-June'12

Page 52: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

9

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-17 1189.84 1285.99 10%

AGM/HSCL/Tripura/P

MGSY/NIT-17/2007-

699 dt.13.12.07 J C Corporation 28.12.07 27.12.08 98.60% D P Singh

10

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-18 915.98 931.41 10%

DGM/HSCL/Tripura/P

MGSY/NIT-18/2007-

582 dt.13.10.07 Ratan sarkar 28.10.07 27.10.08 100.00% D P Singh

11

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-20 393.72 401.29 10%

AGM?HSCL/Tripura/

PMGSY/NIT-20/2007-

710 dt.14.12.07 Utpal datta 29.12.07 28.12.08 98.03% D P Singh

12

Construction &

maintenance of rural

roads under PMGSY

phase-VI at Dhalai

Dist.NIT57 586.48 614.28 10%

HSCL/Tripura/PMGS

Y/NIT-57/2011/1393

dt.14.11.11

Shekhar

Ch.Poddar 29.11.11 28.5.13 32.83%

S K

Mondal

13

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-22 1230.14 1128.63 10%

DGM/HSCL/tripura/P

MGSY/NIT-22/2007-

498 dt.22.9.07 Nimai kar 7.10.07 6.10.08 100.00% D P Singh

14

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-25 805.89 894.7 10%

DGM/HSCL/tripura/P

MGSY/NIT-25/2007-

496 dt.22.9.07 Nimai kar 7.10.07 6.10.08 100.00% D P Singh

15

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-26 410.06 440.17 10%

DGM/HSCL/tripura/P

MGSY/NIT-26/2007-

521 dt.28.9.07 CSP Enterprise 13.10.07 12.10.08 20.94% D P Singh

Propritor

of the

agency

has diede

works has

been re-

assigned

to M/s

kalyani

Debnath

16

Construction

&maintenance of Rural

roads under PMGSY

phase-VII at North

Tripura,NIT-52 2221.88 2348.79 10%

HSCL/Tripura/PMGS

Y/NIT-52/2011/129

dt.28.2.2011 Dilip Kr.Kar 15.3.11 14.9.12 77% D P Singh

Page 53: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

17

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at North tripura

dist.NIT-29 1630.31 1744.03 10%

PM/HSCL/tripura/PM

GSY/NIT-29/2008-

1103 dt.7.5.08 CSP Enterprise 22.5.08 21.5.09 40.30% D P Singh

propritor

of the

agency

has diede

works has

been re-

assigned

to M/s

kalyani

Debnath

18

Construction

&maintemnance of Rural

roads under PMGSY

phase-VII at

Dhalaidist.NIT-55 1386.45 1509.57 10%

HSCL/Tripura/PMGS

Y/NIT-%%/2011/430

dated 11.5.11 Prabir kanti Roy 26.5.11 25.11.12 40.00% S.N Baral

19

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at Dhalai

dist.NIT-36 2229.88 2016.91 10%

HSCL/tripura/PMGSY

/NIT-36/2008-1082

dt.2.5.08 Dilip Kr.Kar 17.5.08 16.5.09 100.00% S.N Baral

20

Construction

&maintemnance of Rural

roads under PMGSY

phase-V at Dhalai

dist.NIT-33 1451.86 1305.68 10%

PM/HSCL/Agartala/P

MGSY/NIT-33/2008-

1571 dt.1.9.08 Dilip Kr.Kar 16.9.08 15.9.09 92.16%

S.K.

Mondal

21

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at Dhalai

dist.NIT-34 1366.8 1413.43 10%

HSCL/tripura/PMGSY

/NIT-34/2008-1654

dt.20.9.08 Manoj Ghosh 5.10.08 4.4.10 62.27%

S.K.

Mondal

22

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-37 4271.01 4505.91 10%

Head(Mktg)/HSCL/Tri

pura/PMGSY/NIT-

37/2008/4530

dt.21.8.08

Evershine vanijya

& Exports (p) Ltd. 5.9.08 4.9.09 79.45% DP Singh

work

order

cancelled

and

balance

work

awarded

to New

agency

23

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-28 1398.02 1404.88 10%

PM/HSCL/tripura/PM

GSY/NIT-28/2008-

1418 dt.15.7.08 Kalyani debnath 1.8.08 30.1.10 95.71% DP Singh

Page 54: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

24

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-30 2670.97 2993.95 10%

PM/HSCL/tripura/PM

GSY/NIT-28/2008-

3010 dt.17.12.08 Ratan Sarkar 1.1.09 30.6.10 88.65% DP Singh

25

Up gradation

&maintemnance of Rural

roads under PMGSY

phase-VI at Dhalai

dist.NIT-38 2490.23 2672.03 10%

Head(Mktg)/HSCL/Tri

pura/PMGSY/NIT-

38/2008/453a

dt.21.8.08

Evershine vanijya

& Exports (p) Ltd. 5.9.08 4.9.09 49.72% S.N Baral

Work

order

cancelled

and

balance

work

awarded

to New

agency

26

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-32 1456.61 1602.27 10%

HSCL/Tripura/PMGS

Y/NIT-32/2008/1958

dt.6.12.08

R & K Minerals &

Trading Co. 21.12.08 20.6.10 79.02% DP Singh

27

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-59 1526.14 1676.47 10%

HSCL/Tripura/PMGS

Y/NIT59/2011/1480

dt.1.12.11 kalyani Debnath 16.12.11 15.6.13 48.77% DP Singh

28

Construction

&maintemnance of Rural

roads under PMGSY

phase-VI at North tripura

dist.NIT-39 416.49 538.88 10%

HSCL/Tripura/PMGS

Y/NIT-39/2010/4015

dt.17.2.10

Das

Constructiobn 4.3.10 3.9.11 100.00% DP Singh

29

construction of 100

bedded sub-divisional

hospital at

Teliamura,West tripura 1809.13 1644.66 10%

HSCL

Head(M&C)/TRI/LOI/

2011/4849/G-3533

dt.6.9.11

P B Nirman

Udyog (P) Ltd. 9-Oct 11-Apr 41.51%

S K

THAKUR

30

Construction of accident

& Trauma centre, stff Qtr.

Misc.work at Dhalai dist

hospital at Kulai 585.43

Sikaria Infra

proj.(p) Ltd. 1.11.09 31.3.11 25.11%

S K

THAKUR

31

Construction of South dist

Polytechnic at

Fulkumari,Udaipur,South

Tripura 1468.6 1372.3 6.55%

GM/Tripura/F-

90/LOI/2010/4264

dt.14.5.2010

P B Nirman

Udyog (P) Ltd. 1.6.10 19.8.12 70.00%

S K

THAKUR

32

Accident & trauma Center

at Dhalai District Hospital

at kulai 149

Sikaria Infra

proj.(p) Ltd. 1.11.09 31.03.11 53.81%

S.K.

Thakur

Contract

with

agency

not yet

finalized

as file is

lying in

PWD for

approval

of

difference

in

tendered

cost &

estimated

cost

Page 55: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

33

Staff quarter & other

Misc. works at dhalai

District Hospital at Kulai 436.43

Sikaria Infra

proj.(p) Ltd. 1.11.09 31.03.11 7.79%

S.K.

Thakur

34

Construction of staff

quarter 7 development of

site at North district

hospital at Khailashahar 721.6 687.179 5.01%

GM/HSCL/Tripura/Kai

lashahar/Staff

Qtr./2012/2155,dt.28.

04.2012

Amma

Construction

India Pvt Ltd 08.05.12 27.06.13 4.85%

S.K.

Thakur

35

construction and

maintenance of rural road

under PMGSY Phase-V

at Dhalai District,Nit-2 1563.931 1597.792 10%

HSCL/Tripura/PMGS

Y-25A/works/2007-

299,dated 25.07.2007 Sri Mintu Pal 09.08.07 08.08.08 93.93%

S.K.

Mondol

36

Construction and

maintenance of rural road

under PMGSY Phase-VI

at Dhalai District,NIT-61 98.86 104.85 10%

HSCL/Tripura/PMGS

Y-NIT-61/2012/1646,

dated 03.01.12

Gias Uddin

Choudhary 03.01.12 08.07.13 88.69% S.N Baral

37

Construction and

maintenance of rural road

under PMGSY Phase-VI

at Dhalai District,NIT-62 2340.94 2507.7 10%

HSCL/Tripura/PMGS

Y-NIT-

62/2012/1660,dated:0

6.01.12 Dilip Kumar Kar 06.01.12 21.07.13 46.35%

shri

D.P.Singh

& Shri

S.N. Baral

38

Construction and

maintenance of rural road

under PMGSY Phase-VIII

at Dhalai District,NIT-63 1308.81 1465.85 10%

HSCL/Tripura/PMGS

Y/NIT-

63/2012/2033,dated

29.03.2012

Amma

Construction

India Pvt Ltd 29.03.12 12.10.13 42.74%

Shri

D.P.Singh

& Shri

S.K.

Mondal

39

Construction and

maintenance of rural road

under PMGSY Phase-VIII

at Dhalai District,NIT-69 666.901 622.42 10%

HSCL/Tripura/PMGS

Y/NIT-

69/2012/1766,dated

25.01.2012 Dilip Kumar Kar 25.01.12 09.08.13 48.52%

S.K.

Mondol

40

Construction and

maintenance of rural road

under PMGSY Phase-VIII

at Dhalai District,NIT-71 1584.342 1814.06 10%

HSCL/Tripura/PMGS

Y/NIT-

71/2012/2035,dated

29.03.2012 Mintu pal 29.03.12 12.010.13 19.57

S.K.

Mondol

41

Construction and

maintenance of rural road

under PMGSY Phase-VIII

at Dhalai District,NIT-72 1612.422 1846.2 10%

HSCL/Tripura/PMGS

Y/NIT-

72/2012/2015,dated

24.03.2012 Nimai kar 24.03.12 07.10.13 10.94%

S.K.

Mondol

Contract

with

agency

not yet

finalized

as file is

lying in

PWD for

approval

of

difference

in

tendered

cost &

estimated

cost

Page 56: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/belo

w such of

rates

applicable

i.e.receipts

Agt.No/LOI

No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

1

Library & seminar hall

SVDV/BHU 1.73 1.73 343 dt.14.3.09

Ganvir's

Spares &

Construction 14.3.09 31.10.11 90%

B N Sharma,

AGM

2

2nd floor balance work

commerce faculty/BHU 1.72 1.72

248

dt.7.12.09

Ganvir's

Spares &

Construction 7.12.09 15.6.11 85% do-

3

Exhibition Hall & lecture

hall,Visual Arts/BHU 1.73 1.73 10 dt.11.5.09

Prachi

Construction 11.5.09 30.6.11 80% -do-

4

Conference hall,lecture

hall faculty of

commerce/BHU 1.83 1.83

246

dt.7.12.09

Ganvir's

Spares &

Construction 7.12.09 7.12.10 15% -do-

5

Construction of centre for

Interdisciplinary Life

Science,BHU 4.08 4.08 68 dt.20.6.11

Anand

Enterprises 21.6.11 30.7.12 80% -do-

6

Extension of Gandhi

Smirti mahila Chtrawas

adjacent to old hostel part-

A/BHU 3.42 3.42 27 dt3.5.10 R K Associates 3.5.10 25.03.2012 85% -do-

EOT

Applied

7

Extension of Gandhi

Smiriti mahila Chtrawas

adjacent to old hostel part-

B/BHU 1.21 1.21

385

dt.29.3.10 R K Associates 29.3.10 29.9.11 25% -do-

8

Construction of

community centre bldg at

Jodhpur

colony,BHU(phase-I) 2.17 2.17 69 dt.20.6.11

vaisali

Construction 21.6.11 20.6.12 95% -do-

EOT

Applied

9

Construction of class

room (G+2) kendriya

Vidalaya/BHU 2.18 2.18 30 dt.11.5.10

Radha

machinary

works 11.5.10 10.5.13 70% -do-

Hindustan Steelworks Construction Limited

Quarterly progress of original works for the month of June 12

VARANASI

Page 57: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

10

Construction of faculty of

Chambers with corridor

Electrical

Engineering/BHU 1.08 1.08

382

dt.26.3.10

Radha

machinary

works 26.3.10 26.1.11 95% -do-

11

Construction of

interconnection bldg.

structure between plant

breeding & horticulturer

bldg.(g+2)/BHU 1.2 1.2 76dt.24.6.10

Jai Bajrang

Enterprises 24.6.10 30.06.2012 98% -do-

12

Construction of lecture

theatre,IMS/BHU 5.15 5.15

331

dt.24.2.10

Vaishali

Construction 24.2.10 23.2.12 80% -do-

13

Construction of 3rd floor

& balance finishing work

of

lecture,Theatre,IMS,BHU 1.53 1.53

128

dt.17.10.11

Vaishali

Construction 18.10.11 17.3.12 100% -do-

Work

complete

d

14

Bio-technology

dept.extension of

dept.bldg adjacent to

existing deptt bldg.(g+3)

floor/BHU 1.64 1.64

371dt.20.3.1

0

Anand

Enterprises 20.3.10 19.3.11 70% -do-

15

Extension of existing

Zoology dept .bldg.by

construction of (g+1) floor

overe xisting cycle stand

area with provision of two

another floors 2.18 2.18 31dt10.5.10 R K Associates 10.5.10 10.8.11 25% -do-

16

Construction of

employees health centre-I

(New Bldg.) Jodhpur

colony,BHU 1.08 1.08

155

dt.21.11.11

Vaishali

Construction 22.11.11 21.11.12 90% -do-

17

Construction of New

Guest House (G+1) in the

back of lakshman Das

Guest House , BHU 1.9 1.9

214/ dt

03.02.2012

M/s Anand

Enterprises

04.02.201

2 15.07.2012 3%

Owner

issue

material

i.e. Tor

steel is

shortage

in BHU

store

Page 58: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Civil works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No.Name of work

Estimated

cost in Lacs

Tendered

cost in

Lacs

%age

above/below

such of rates

applicable

i.e.receipts Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

VIZAG

1

Strl.Steel work for raw

material handling system

(zone-I)(area-2) coal

handling system 151.17 134.69 10.90%

01/M/06-07/738

dt.16.7.07

Jyoti

Erectors 9.12.06 31.1.12 160%

G N

Das,AGM

2

Strl.Steel work for wire

rod Mill-2 281.01 264.21 7.95%

HV/TC/804/2009-

840/355

dt.18.8.09

Kalathil

Bros. 28.5.09 29.2.12 98% U P pandey

111.42 105 7.95%

HV/TC/805/2009-

841/131

dt.4.8.09

Sencon

System 28.5.09 30.11.11 100%

U P

pandey,CTM

236.93 224.41 7.95%

HV/TC/807/2009-

843/131

dt.7.8.09

Raj Mohan

Enterprise 2.6.09 30.11.11 99% U P pandey

3

Civil Engg. Work of Coal

handling Plant Ph-II

facilities Coke oven

battery No.4 846 818.98

3.19%

margin on

Receipt

01/C-2008-

09/749 dt1.11.08

Gayatri

Project &

Aruna

Constructio

n 29.5.08 30.9.12 97.00%

G N

Das,AGM

4

Technilogical Assistance

in Batteries of CO & CCP 338.21 321.3 5%

HV/TC/818/2010

/856 dt.21.12.10

Kalathil

Bros. 1.12.10 30.11.11 100.00%

G N

Das,AGM

5

Strl.Steel work for BF-3

Granulated slg conveyor 619.81 588.2

5.10%

margin on

Receipt

HV/TC/816/2010-

854 dt.24.8.10

Happy

Hirise

Infra.Ventur

es 24.8.10 23.07.2012 99.00%

CL

srivastava,Sr

.Mgr.

Quarterly progress of original works for the month of June'12

Hindustan Steelworks Construction Limited

Page 59: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Electrical works only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No. Name of work

Estimated

cost in

Lacs

Tendered

cost in

Lacs

%age

above/bel

ow such

of rates

applicable Agt.No/LOI No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress

of work in

%age

Name of

Engineer

Incharge Remarks

BHILAI

1

Electrical works for

relocation of Plant spare

store (Pkg No.116-A) for

7 MT expansion of

BSP,Bhilai,Part-II

(Elec.Store) 72.07 68.76 -4.58%

ED/BH/TC/201/OT

(185)/08 RA Singh 7.2.08 31.3.11 completed

S B

yadav,DM

(C)2

RANCHI

1

Ex Electirification at

JNV/Bankura Under

phaseA 22.65 32.48 5%

LOA

No.HSCL/RNC/TC/

LOA/2010-962

dt.23.9.10

Rai

Electrification 1.10.2010 8 months completed

A K

pandey,D

GM

2

Ex electrification

development at

JNV/Sahibgunj Under

Phase-A 30.56 37.42 5%

LOA

No.HSCL/RNC/TC/

LOA/2010-907

dt.22.10.10

krishna

Construction 1.10.2010 8 months completed

A K

pandey,D

GM

1

levelling and grading

including earth work Plain

& reinforced cement

concrete roads.MS

embedment work etc at

2.500MW units Anpara-D

TPS of UPRUVNL at

anpara 22.59 22.59 5.30%

HSCL/CPM/BHEL/

Anpara/2009/780

dt.15.4.09

K N

International

Ltd. 15.4.09 8 months 65%

S K

Choubey,

PM

1

Internal electrical for

medical Linac laboratory

bldg.(PH_II) at SAMEER 105 105 7.70%

HSCL/CPM/NGP/F-

170/2008-743

dt.5.11.08

Gautam Trading

Co. 15.11.08 5 months 15%

A K

Kanwar

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending-June 12

Anpara

Nagpur

Page 60: ending-June'2012 Physical progress Name of · (P) Ltd. 1.1.2011 31.12.2011 44% A P Shukla,Mgr.(C) 9 Renovation of existing

(Horticulturer work only)

Civil work costing Rs.1.00 crore and above.

Electrical work costing Rs.15.00 lakhs and above

Horticulturer work costing Rs.2.00 lakhs and above

Sl.No.

Name of

work

Estima

ted

cost in

Lacs

Tendere

d cost in

Lacs

%age

above/below

such of rates

applicable

i.e.receipts

Agt.No/LOI

No.

Name of

Agency

Date of

commenc

ement

Time of

completion

Physical

progress of

work in

%age

Name of

Engineer

Incharge Remarks

Hindustan Steelworks Construction Limited

Statement showing Quarterly Progress of Original Works for the Quarter ending-June 12

NIL