    Environmental

    Compliance

    Certificate

  • 8/11/2019 Encie Ecc Report

    2/22

    ECC is a certificate issued by DENR/EnvironmentalManagement Board EMB after a positive review of theECC application. This certifies that based on the

    application of the proponent, the proposed project orundertaking will not cause a significant negativeimpact on the Philippines environment. The ECC'scontain specific measures and conditions that must be

    met by the project proponent before and during theoperation of the project. In some cases, conditions arelisted to be pre-formed during the projectsabandonment phase to lessen identified potentialenvironmental impacts.

  • 8/11/2019 Encie Ecc Report

    3/22

    The ECC's also certify that the proponent hascomplied with all the requirements of the

    Environmental Impact Statement (EIS)System and has committed to implement itsapproved Environmental Management Planin the Philippines.

  • 8/11/2019 Encie Ecc Report

    4/22

    Must Document Requirements:

    Environmental Impact Statement (EIS) Report Accountability Statement from EIS Consultant

    and Project Proponent DA Certificate of Viability for Conversion (if in

    agricultural land and conversion is necessary) Land Title/Proof of Land Jurisdiction/Ownership PAWB Endorsement (if within protected area) SEC Registration

  • 8/11/2019 Encie Ecc Report

    5/22

    NWRB Water Use Permit/Certificate of WaterAvailability

    Review Fund Electronic File of the EIS Environmental Tract Record (for expansion

    projects)

    Photocopy of TCT/OCT/CLT Zoning/Certificate of Locational Viability Barangay or Municipal of City Council

    Resolution/Proof of consultation with LGUs

  • 8/11/2019 Encie Ecc Report

    6/22

    Category A1 (for new co-located projects)

    Requirements:

    -Programmatic Environmental PerformanceReport and Management

    Plan (new co-located project)

  • 8/11/2019 Encie Ecc Report

    7/22

    Category A2(for expansion projects)

    Requirements: -Programmatic Environmental Performance

    Report and Management Plan (co-located projects) Environmental Performance Report and

    Management Plan (single project)

  • 8/11/2019 Encie Ecc Report

    8/22

    Category A3 (for existing projects withoutECC)

    Requirements: -Programmatic Environmental Performance

    Report and Management Plan (co-located projects) -Environmental Performance Report &

    Management Plan (single project)

  • 8/11/2019 Encie Ecc Report

    9/22

    Category B.

    Projects that are not categorized as ECPs, butwhich may cause negative environmentalimpacts because they are located inEnvironmentally Critical Areas (ECA's)

  • 8/11/2019 Encie Ecc Report

    10/22

    Category C. Projects intended to directlyenhance environmental quality or address

    existing environmental problems not fallingunder Category A or B.

    Category D. Projects unlikely to cause adverseenvironmental impacts.

  • 8/11/2019 Encie Ecc Report

    11/22

    1. Proponent consults EMB (EIAD) re: his project.

    (screening)

    2. EIAD schedules scoping meeting.2.1. Assigns case handler2.2. Determines and notifies members of EIARC2.3. Meets proponent, case handler and

    members of EIRC for project scoping orrequirements checklist2.4. Second level scoping Public consultation

  • 8/11/2019 Encie Ecc Report

    12/22

    3. Proponent conducts EIA and prepares EISbased on the scoping or requirements

    checklist and second level scoping.

    3.1. Deposits EIA review fund with NRDC3.2. EIAD Case Handler determinescompleteness of documents.

  • 8/11/2019 Encie Ecc Report

    13/22

    4. Proponent pays filing and processing fee with EMBCashier.4.1. Proponent submits complete, procedurally screenedEIS together with supporting documents to EMB record

    and forwards to EIAD.4.2. EIAD schedules RC meeting

    .5. EIARC meets to review EIS (Several meetings).

    5.1. May request for additional information (up to 2 times)

    5.2. Conducts site inspection5.3. Conducts public hearing5.4. Prepares and submit final report andrecommendation to EMB Director thru EIA Division Chief

  • 8/11/2019 Encie Ecc Report

    14/22

    6. EMB Director reviews final report andrecommendation.6.1. If not OK, returns it to EIARC thru EIADC

    6.2. If OK;6.2.1. Signs / Approves ECC or6.2.2. Recommends ECC to the Secretary

    7. Secretary either approves or denies ECC within

    15 days.

    Note: Processing time will be 120 working days

  • 8/11/2019 Encie Ecc Report

    15/22

    A. Application for ECC1. Category A-1 (Co-located Projects)

    total : P10,000.000

    Procedural Screening Fee -1,500.00 Database Management Fee -3,000.00 Processing Fee - 5,500.00

  • 8/11/2019 Encie Ecc Report

    16/22

    2. Category A-1(Single project), Category A-3(Co-located Project)

    total: P 6,000.00

    Procedural Screening Fee 600.00 Database Management Fee 2,000.00 Processing Fee 3,400.00

  • 8/11/2019 Encie Ecc Report

    17/22

    3. Category A-2, and B-1Total: P4,000.00

    Procedural Screening Fee 300.00 Database Management Fee 1,000.00 Processing Fee 2,700.00

  • 8/11/2019 Encie Ecc Report

    18/22

    4. Category B-2 and B-3

    Total: P3,000.00

    Procedural Screening Fee 300.00 Database Management Fee 1,000.00 Processing Fee 1,800.00

  • 8/11/2019 Encie Ecc Report

    19/22

    B. Certification of Non-Coverage1. Category D P 100.002. Category C 600.00

    C. Post ECC Processing Services1. Request for minor ECC Amendment P 300.00/

    application(Article II, sec. 3-B item 2.1)

    2. Request for major ECC AmendmentP1,200.00/application

    (Article II, sec. 3-B item 2.2)

  • 8/11/2019 Encie Ecc Report

    20/22

    D. Other Services1. Request for miscellaneous certifications P

    50.00/certification2. Request for certified true/photocopy25.00/document

  • 8/11/2019 Encie Ecc Report

    21/22

    DENR-Department of Environment and NationalResources

    ECC- Environmental Compliance Certificate

    EIS- Environmental Impact StatementEMB-Environmental Management BureauPAWB-Protected Areas and Wildlife BureauNWRB-National Water Resources BoardEIAD-Environmental Impact Assessment DivisionEIARC-Environmental Impact Assessment Review

    CommitteeEIA-Environmental Impact AssessmentNRDCNatural Resources Development Corporation