EN-HE Group meeting19th June 2015
I. Rühl / EN-HE
EN-HE Group meeting 2
Agenda
19.06.2015
• General issues I. Rühl 10min
• Presentation F. Daclin 10min
• Presentation A. Lambert 10min
• LS2, LIU, IT-4074 C. Bertone 20min
• HL-LHC B. Feral10min
• HM activities H. Lourenco 20min
• LM activities D. Lafarge 20min
• (FCC I. Rühl 10min)
• BBQ at PA6
EN-HE Group meeting 3
Agenda – General issues I. Rühl
19.06.2015
• LS1• EN-HE organization• Supply and service contracts• Space management• Consolidation• Divers
EN-HE Group meeting 4
General issues – LS1
19.06.2015
• Very very good feedback during LS1day(s)• Very good, professional and flexible transport
and handling service• Very good equipment availability and reliability
Sepp HerbergerNach dem Spiel ist vor dem Spiel!
After LS1 is before LS2
19.06.2015 EN-HE Group meeting 5
Handling Engineering GroupI. Rühl
Deputy Group LeaderC. Bertone
Heavy Handling
C. Bertone
Handling Maintenance
H. Lourenco
CranesG. RocheJ.-P. GranchelliR. RinaldesiO. BöttcherA. Kertesz (F)
Industrial trucksJ.-M. ChevalleyB. Feral
Maintenance MethodsC. BalJ. Sylvestre (F)
Team ‘Handling’S. PelletierP. BruneroF. DaclinE. DugueS. FumeyY. SeraphinP. Vallet
Team ‘Projects’J.-L. GrenardJ.-B. Bonnamy (VIA)L. Favre-Reguillon (TS)
Team ‘Transport’T. MazzarinoR. Brun
Lift Maintenance
D. Lafarge
A. CalderoneJ-P. LappeN. PerezG. Jdaini (TS)
Group Administrator – JM. Soudan
Secretariat (50%) – A. Lambert
General issuesEN-HE Organization Chart
Departures• F. Girard-Madoux (03/2015)• A. Kertesz (05/2015)• J. Sylvestre (05/2015)
New LD contracts• F. Daclin (01.01.2015)• A. Lambert (01.03.2015)
New arrivals• Jean-Baptiste BONNAMY (VIA)• Loic FAVRE-REGUILLON (TS)• Ghizlane JDAINI (TS)• M. Czech (F; 01.09.2015)
EN-HE Group meeting 6
General issues – Supply & service contracts
19.06.2015
• IT-3980 Supply of EOT cranes ≤ 10t• Contract proposal approved by FC June• Contract started in July 2014 – BONFANTI / IT
• IT-3981 Supply of EOT cranes > 10t• Contract proposal approved by FC June• Contract started in July 2014 - BONFANTI / IT
• IT-3972 Maintenance of industrial trucks• Contract proposal approved by FC September• Contract started in January 2015 – MECSA / CH
• IT-3976 Maintenance of cranes• Contract proposal approved by FC September• Contract started in January 2015 – REEL, AltéAd / FR
EN-HE Group meeting 7
General issues – Supply & service contracts
19.06.2015
• IT-4056 Replacement and maintenance of LHC lifts• Contract approved by FC March 2015• Contract started in April 2015 – VESTNER / DE• First lift to be replaced – ALICE in WS 2015/2016
• IT-4074 Transport and handling services• IT released in April 2015• Contract proposal to be approved by FC Sept. 2015• New contract to start either in October 2015 or in January 2016
• IT-4123 Crane rail supply and consolidation works• MS released in May 2015• IT to be released by July 2015• Contract proposal to be approved by FC December 2015• New contract to start in January 2016
EN-HE Group meeting 8
General issues – Supply & service contracts
19.06.2015
• IT-xxxx Access to height / EOT crane access / Life-lines consolidation works• MS to released before end of 2015• IT to be released by March 2016• Contract proposal to be approved by FC June 2016• New contract to start in July 2016
EN-HE Group meeting 919.06.2015
• Bldg. 7 – Adding 2nd floor (~120m2)• Office space for EN-HE-HH section• Free office space in bldg. 57/1 for HSE
(requestor)
General issues - Space
InfrastructureProjectProposalRF. Ortega / GS
EN-HE Group meeting 10
General issues - Space
• Bldg. 867 bis - 900 m2 (60 x 15 m) + PR 40t
• Maintenance, training and storage of LHC and SPS transport and handling equipment (i.e. MAFI tunnel transport vehicles for LHC cryo-magnets)
• + similar storage area on Meyrin side• Storage of transport and handling
equipment that cannot be stored in the experimental areas anymore
19.06.2015
EN-HE Group meeting 11
General issues - Consolidation
19.06.2015
• See presentations by D. Lafarge and H. Lourenco• CERN consolidation program / budget will be cut by XX% as from
2016 onwards ….
EN-HE Group meeting 12
General issues – New contract policy
19.06.2015
• Proposal: Change from 5 years LD contract duration to• 5 + 3 years – APPROVED
• BUT CONTRACT EXTENSIONS ARE NOT AUTOMATIC• Rules, regulations, procedures, ratio applies
General issues - CERN Career Structure
PerformanceMARS Advancement
Promotions
Career Path Structure
Salary grid
BenchmarkJobs
EN-HE Group meeting 14
Conclusion
19.06.2015
• Projects/Studies/Activities vs. MTP• Need more input to assess manpower
requirements• Consolidation - All set up but budget cuts ...• Pushing for 900m2 in 867bis• After LS1 is before LS2/LIU is before LS3/HL-LHC is before …!
EN-HE Group meeting 1519.06.2015