Upload
others
View
21
Download
0
Embed Size (px)
Citation preview
Emergency Action Plan
Gordon Road Bardon Detention Basin
Referable Dam ID: # 2608
Version: 1.3
Dam Owner: Brisbane City Council
September 2019
RM Ref: CA18/164487
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 2 of 71
Emergency Actions – Quick Reference Summary
Dam Hazard and
Document Reference
Activation Stage
Alert Lean Forward Stand Up Stand Down
Decision Authority Flood Officer
Event Response Coordinator
Dam Owner
Event Response Coordinator
Dam Owner
Event Response Coordinator Event Response Coordinator
Activation trigger for dam hazards (See section 6)
Dam Crest Flood Failure
See section 6.4
Warning issued by BoM for
rainfall greater than 100mm
and possible flash flooding
WL at or above 72.6 m AHD
and rising.
Further rain is predicted
WL at or above 75 m AHD and
rising.
Evidence of seepage or other
damage to integrity of dam.
WL fallen below dam crest: (76
m AHD) and dropping
predictably
AFC Overtopping Failure
See section 6.5
Warning issued by BoM for
rainfall greater than 100mm
and possible flash flooding
WL at or above 72.6 m AHD
and rising.
Further rain is predicted
WL at or above 75 m AHD and
rising.
Further rain predicted.
WL fallen below dam crest (76
m AHD) and dropping
predictably.
Earthquake
See section 6.6
Earthquake greater than 5.5
Modified Mercalli (MM)
reported
Inspection confirms cracking,
movement or other damage to
integrity of dam and heavy
rainfall event is predicted.
Heavy rain continuing.
Water levels rising and
inspection indicates seepage,
erosion or movement is
substantial
Risk assessment has
determined that failure risk has
reduced
High Energy Impact/
Terrorist Activity
See section 6.7
Impact/activity reported Inspection confirms cracking,
movement or other damage to
integrity of dam and heavy
rainfall event is predicted.
Heavy rain continuing.
Water levels rising and
inspection indicates seepage,
erosion or movement is
substantial
Risk assessment has
determined that failure risk has
reduced
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 3 of 71
Revision Status
Rev No. Issue Date Revision Description
0.72 March 2018 Original Draft – For review by Council staff and LDMG
1.0 July 2018 Version 1 issued to DDC, LDMG & CEO for endorsement prior to
lodgement with DSR
1.1 August 2018 Amended to ensure consistency with LDMP after consultation with
LDMG and DMO.
1.2 November 2018 Revised after consultation with DNRME re roles and responsibilities
and local government notice by CEO Brisbane City Council.
1.3 September 2019 Updated contact details for key personnel in Appendix C.
1/10/2019
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 4 of 71
Distribution Control Sheet (Controlled Hard Copies)
Copy Position Organization/Location
1 Manager, Natural Environment Water and
Sustainability (NEWS),
Level 7, Brisbane Square, Brisbane, QLD
4000
2 Unit Manager, Flood Management, City
Projects Office
Level 1, Green Square Close, South Tower,
Fortitude Valley, QLD 4006
3 Manager, Asset Services, Level 10, Brisbane Square, Brisbane, QLD
4000
4 Regional Manager, West Region Regional Business Centre, 681 Fairfield Rd.
Yeerongpilly, QLD 4105
5 Manager, Disaster Management Level 23, Brisbane Square, Brisbane, QLD
4000
6 Coordinator, Disaster Management Level 23, Brisbane Square, Brisbane, QLD
4000
7 Senior Operations Officer, Disaster
Management
Level 23, Brisbane Square, Brisbane, QLD
4000
8 CEO, Brisbane City Council Level 23, Brisbane Square, Brisbane, QLD
4000
9 Local Disaster Management Group
(LDMG)
Level 23, Brisbane Square, Brisbane, QLD
4000
10 District Disaster Management Group
(DDMG)
Queensland Police, Brisbane
11 Emergency Management Coordinator Queensland Fire and Emergency Services
12 Dam Safety Regulator Department of Natural Resources Mines and
Energy, George Street, Brisbane, QLD 4000
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 5 of 71
Common Abbreviations and Definitions
The following abbreviations and definitions are common in EAPs and disaster management documents.
Note: Some Brisbane City Council specific abbreviations and definitions are noted (BCC) in parenthesis.
Other definitions associated with the regulation of referable dams in Queensland are listed in Appendix E.
The Act The Water Supply (Safety and Reliability) Act 2008
AEP Annual Exceedance Probability
AFC The Acceptable flood capacity (of a referable dam)
AHD Australian Height Datum
ANCOLD Australian National Committee on Large Dams
BoM Bureau of Meteorology
BCC Brisbane City Council
CEO Chief Executive Officer (BCC)
CPO City Projects Office (BCC)
DCF Dam crest flood – design flood event which just overtops the crest
DDMG District Disaster Management Group
DDC District Disaster Coordinator
DEWS Former Qld Dep’t of Energy and Water Supply responsible for dam safety – see DNRME
DM Disaster Management (BCC)
DM Act Disaster Management Act 2003
DMDO Disaster Management Duty Officer (BCC)
DMSPF Disaster management strategic policy framework
DNRME Department of Natural Resources, Mines and Energy
DOMM Detailed Operations and Maintenance Manual for a referable dam
DSR Dam Safety Regulator – See Appendix E
EA Emergency Alert messaging service operated by QFES through the SDCC
EER Emergency Event Report
EHSOT Emergency Human Services Operational Team (BCC)
EMAF The emergency management assurance framework
ERC Event Response Coordinator
EWA Early Warning Alert messaging service operated on behalf of BCC
FIC Flood Information Centre – (BCC)
FIS Failure Impact Statement – See also Appendix E
FSL Full supply level
GRBDB Gordon Road Bardon Detention Basin – (BCC)
GS Gauging station
GIS Geographic Information System
IC Incident Controller
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 6 of 71
LDC Local Disaster Coordinator
LDCC Local Disaster Coordination Centre
LDMG Local Disaster Management Group
LDMP Local Disaster Management Plan
ML Mega litre
m AHD metres elevation above Australian Height Datum
MDM Manager, Disaster Management (BCC)
MNEWS Manager, Natural Environment, Water and Sustainability (BCC)
NEWS Natural Environment, Water and Sustainability Group (BCC)
PAR Population at Risk
PMPDF Maximum realistic design flood resulting from probable maximum precipitation event
PPRR Prevention, preparedness, response and recovery
QDMA Queensland disaster management arrangements
QDSMG Queensland dam safety management guideline
QFCoI Queensland Floods Commission of Inquiry
QFES Queensland Fire and Emergency Services
QPS Queensland Police Service
RL Reduced level (relative to fixed height datum, usually AHD)
RIMTs Regional Incident Management Teams
RPEQ A Registered Professional Engineer. Queensland
SDCC State Disaster Coordination Centre
SDMG State Disaster Management Group
SES State Emergency Service
SITREP Situation Reports
SOP Standing Operating Procedure
IGEM The Office of the Inspector-General Emergency Management
Notes:
Source: Department of Natural Resources, Mines and Energy Emergency Action Plan for Referable Dam Guideline 2017
BCC specific references annotated (BCC)
Some additional definitions applicable to the licence are included with a copy of the licence conditions in Appendix F
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 7 of 71
Table of Contents
Emergency Actions – Quick Reference Summary ........................................................................................ 2
Approval and Authorisation ........................................................................... Error! Bookmark not defined.
Revision Status .............................................................................................................................................. 3
Distribution Control Sheet (Controlled Hard Copies) ..................................................................................... 4
Common Abbreviations and Definitions ........................................................................................................ 5
Table of Contents .......................................................................................................................................... 7
List of Appendices ......................................................................................................................................... 8
List of Tables ................................................................................................................................................. 9
List of Figures ................................................................................................................................................ 9
1.0 Dam Information .............................................................................................................................. 10
1.1 Introduction .................................................................................................................................. 10
1.2 Development of an Emergency Action Plan ................................................................................ 10
1.3 Objective of the Emergency Action Plan ..................................................................................... 11
1.4 Updating the Emergency Action Plan .......................................................................................... 11
1.5 DNRME Referable Dam Data Summary Sheet ........................................................................... 11
1.6 Dam Location, Access and Evacuation Routes .......................................................................... 12
2.0 Gordon Road Bardon Detention Basin – Performance and Operation ........................................... 14
2.1 Design and As-Constructed Dam Performance Data .................................................................. 14
2.2 Dam Inflow/Outflow and Water Levels for Design Flood Events ................................................. 15
2.3 Storage-Discharge Details ........................................................................................................... 16
3.0 Dam Safety Management ................................................................................................................ 19
3.1 The Emergency Management Framework .................................................................................. 19
3.2 Maintenance and Management of the Detention Basin .............................................................. 19
3.3 Water Level Measurement and Rainfall Records ........................................................................ 19
3.4 Emergency Events ....................................................................................................................... 20
3.5 Relationship to Other Plans ......................................................................................................... 20
4.0 Key Roles and Responsibilities ....................................................................................................... 21
5.0 Warning and Communication Plan .................................................................................................. 24
5.1 Purpose of the Communication Plan ........................................................................................... 24
5.2 Limitations Associated with PAR Notifications ............................................................................ 24
5.3 Notification to External Agencies ................................................................................................. 24
5.4 Notification to Population at Risk (PAR) ...................................................................................... 24
6.0 Assessment of Dam Hazards and Emergency Situations ............................................................... 29
6.1 Dam Hazards ............................................................................................................................... 29
6.2 Gordon Road Bardon Detention Basin – Failure Impact Assessment (FIA) ............................... 29
6.3 Possible Flood–related Failure Mechanisms Considered for the Gordon Road Detention Basin29
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 8 of 71
6.3.1 Sudden Collapse Due to Seepage Under the Basin ............................................................... 30
6.3.2 Erosion and Undermining of the Foundation ........................................................................... 30
6.3.3 Cracking and Development of Uncontrolled Seepage ............................................................ 30
6.4 Situation 1 – Dam Crest Flood (1 in 50 AEP) with Structural Failure .......................................... 30
6.5 Situation 2 -- Dam Crest Overtopping With Structural Failure ..................................................... 36
6.6 Situation 3 - Damage to the Basin as a Result of Earthquake .................................................... 41
6.7 Situation 4 – Terrorist or High Energy Impact ............................................................................. 41
7.0 Activation of the EAP ....................................................................................................................... 42
7.1 Emergency Management to Identify and Minimise Risk ............................................................. 42
7.2 Stages of Emergency Services Activation ................................................................................... 42
7.3 Initiation of an Emergency ........................................................................................................... 43
7.4 Notifications on Activation of the EAP ......................................................................................... 44
7.5 Emergency Situation - Alert Triggers ........................................................................................... 44
7.6 Pre-approved Wording of the Agreed Notification and Warning Messages ................................ 47
8.0 Emergency Event Report (EER) ...................................................................................................... 48
9.0 Dam Event Public Warning and Education Protocol ....................................................................... 49
9.1 Public Education .......................................................................................................................... 49
9.2 Staff Training and Exercises ........................................................................................................ 49
List of Appendices
APPENDIX A – Population at Risk and Inundation Mapping ...................................................................... 50
APPENDIX B – Summary of EAP Activation and Alert Triggers ................................................................. 57
APPENDIX C – Contact Lists for PAR and Key Council Officers ............................................................... 58
APPENDIX D – Modified Mercalli Earthquake Intensity Scale – Damage Guide ....................................... 62
APPENDIX E - Definitions/Glossary ............................................................................................................ 63
APPENDIX F – DNRME License Conditions .............................................................................................. 66
APPENDIX G – DRAWINGS - Gordon Road Bardon Detention Basin – General Layout .......................... 69
APPENDIX H – Reference Documents ....................................................................................................... 71
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 9 of 71
List of Tables
Table 1 – DNRME Referable Dam Data Summary Sheet .......................................................................... 11
Table 2 - BCC Dam Design and As-constructed Data Summary ................................................................ 14
Table 3 - Stage/Storage and Discharge Data for the Gordon Road Bardon Detention Basin .................... 16
Table 4 – Inflow / Outflow and Dam Water Levels for Design Floods, Including Extreme Event ............... 17
Table 5 – Key Roles and General Responsibilities ..................................................................................... 21
Table 6 – Contact Details for Notification of Relevant External Agencies ................................................... 27
Table 7 - Situation 1 – Dam Crest Flood EAP Response (Possible Structural Failure) .............................. 32
Table 8 - Situation 2 – Dam Crest Overtopping EAP Response ................................................................. 37
Table 9 – EAP Escalation Levels ................................................................................................................ 43
Table 10 – Summary of Pre-approved Emergency Communication Messaging to the PAR ...................... 47
List of Figures
Figure 1 – Location Map .............................................................................................................................. 13
Figure 2 – Gordon Road Detention Basin Catchment ................................................................................. 13
Figure 3 – Gordon Road Detention Basin Stage – Storage Curve ............................................................. 18
Figure 4 – Gordon Road Detention Basin Stage – Discharge Relationship ............................................... 18
Figure 5 – Agreed Internal and External Communication Flow ................................................................... 26
Figure 6 – Inflow, Outflow and Peak Water Levels in GRBDB for 1 in 50 AEP Event ................................ 45
Figure 7 – Catchment Rainfall and Peak Water Levels in GRBDB for 1 in 50 AEP Event. ........................ 45
Figure 8 – Gordon Road Bardon Detention Basin - Emergency Situation Alert Triggers ........................... 46
Figure 9 – Dam Event Public Warning and Notification Protocol ................................................................ 49
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 10 of 71
1.0 Dam Information
1.1 Introduction
Gordon Road Bardon Detention Basin (GRBDB) is located in the suburb of Bardon in Brisbane. The original
structure consisted of an earth-fill embankment with a large culvert opening through the main embankment
of the basin, which permitted floodwater to flow downstream through a defined open earth channel. The
open channel finishes upstream of 54 Gordon Road where it drains into an 1800 mm diameter circular
culvert near the properties at risk.
The basin was reconstructed in 2017/2018 to provide enhanced stormwater detention and flood mitigation
functions. The newly re-constructed detention basin includes works of raising the crest level and reducing
the size of its outlet to restrict outflow so it matches the capacity of the downstream stormwater pipe. Figure
1 shows the location of the basin and Figure 2 the contributing catchment.
The basin is to be kept safe, and be maintained and operated in accordance with the attached Dam Safety
Schedule and current versions of the following guidelines issued in Queensland under the Water Supply
(Safety and Reliability) Act 2008 and the Water Legislation (Dam Safety) Amendment Act 2017, including:
• Queensland Dam Safety Management Guidelines
• Guidelines for Failure Impact Assessment (FIA) of Water Dams
• Guidelines on Acceptable Flood Capacity (AFC) for Dams
The current Dam Safety Regulator in the State of Queensland is the Chief Executive, Department of
Natural Resources, Mines and Energy (DNRME) or the Department’s Delegate Officers.
1.2 Development of an Emergency Action Plan
The approved FIA has been carried out based on the design of the enhanced GRBDB under the provisions
of the Water Supply (Safety and Reliability) Act 2008.
The FIA identified the GRBDB as a Category -1 Referable Dam (2 or more persons at risk).
DNRME has issued a licence and a set of draft licence conditions based on their assessment of the FIA and
classified the basin as a referable dam.
Further information on guidelines associated with these dams are available in the website
www.dnrme.qld.gov.au.
Both the Act and the licence conditions issued pursuant to the Act require the dam owner (BCC) to develop
an EAP and have that plan endorsed and approved by the Dam Safety Regulator.
The EAP is a tool for the dam owner, relevant disaster management groups, local government and
emergency management agencies to effectively coordinate the management of risk and consequences of
a dam hazard /emergency event.
In preparing the EAP, the following has been considered:
• Identification of dam hazard, hazard events and dam emergency events;
• Identification of people who may be affected/harmed as a result of dam hazard;
• State processes to be followed to minimise risk of harm to people/property if such an event happens;
• Identification of relevant entities, roles and responsibilities of all parties during planning, activation
and testing for an event;
• Identification of who (in priority order), when and how the notification and warning messages are to
be delivered to persons who may be at risk and whose properties are at risk;
• The types of notification/messages to be delivered and who will deliver those;
• Ensure training is provided to the staff and relevant officer involved in handling EAP;
• Testing the effectiveness of the EAP in an exercise.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 11 of 71
1.3 Objective of the Emergency Action Plan
This document is intended to guide responsible personnel through identifying and responding to hazardous
conditions associated with the Gordon Road Detention Basin. Emergencies are dynamic events which
evolve rapidly, usually under adverse weather conditions, and this plan does not cover all possible
combinations of events.
Emergency response personnel should maintain situational awareness at all times, and exercise their best
judgment in their response. The safety of the public and all emergency response personnel should not be
compromised in implementing this plan.
1.4 Updating the Emergency Action Plan
The Emergency Action Plan (EAP) will be reviewed for adequacy every five years or alternate timeframe as
advised in writing from the Department of Natural Resources Mines and Energy.
Telephone contact details will be updated annually or as required with changes to State and Local
Government contact details.
Following any update to the Plan, it will be distributed as per the Distribution Control Sheet.
1.5 DNRME Referable Dam Data Summary Sheet
Note: The following summary information is provided in accordance with the dam licence conditions. It is
based on design drawings submitted with the Failure Impact Statement for assessment by the Dam Safety
Regulator. A copy of the licence conditions is included in Appendix F.
Table 1 – DNRME Referable Dam Data Summary Sheet
Category Assessment
Dam Name Gordon Road Bardon Detention Basin
Referable Dam ID: #2608
Failure Impact Rating 1
Population at Risk1 (PAR) 34.8 ( DCF - 1 in 50 AEP Flood Failure)
Date Assessment accepted 18 May 2017
Hazard Category (ANCOLD) High C1
Acceptable Flood Capacity (AFC): 1 in 34,800 AEP
Current Dam Crest Flood Capacity (DCF): 1 in 50 AEP
Timing of Minimum AFC Upgrade/s: N/A
Location
Coordinates 27°27’31.53” S, 152°57’58.96” E
Property description (Primary Location) Lot 1324 S31983
Lot 699 S31294
Lot 701 S31294
1 For the purposes of this EAP, PAR is the total population at risk if a dam failure event was to occur, including transient populations as well as those at residences and businesses.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 12 of 71
Category Assessment
Lot 12 RP45087
Local Authority Brisbane City Council
Basic Characteristics of the Dam
Purpose Flood Detention
Embankment
Construction Type Reinforced concrete wall with rock protection facing
Total Length 70 m
Maximum Embankment Height 4.8 m
Storage Capacity 17.7 ML
Surface Area 1.1 Ha
Catchment area 51.1 Ha
Full Supply Level No permanent storage available
Dam Crest Level 76.0 m AHD
Spillway
Description Nil
Control level -
Discharge Capacity 7.3 m3/s (1.2 m x 1.2 m box culvert at toe – Invert
Level ; 71.38 m AHD)
1 High C – This Consequence Category is based on the maximum PAR of 34.8 estimated in the Gordon
Road Bardon Detention Basin Failure Impact Assessment dated 28 February 2017 and utilising the Minor
to Medium ‘Severity of Damage and Loss’ in accordance with DNRME Guidelines on Acceptable Flood
Capacity for Water Dams dated August 2016.
1.6 Dam Location, Access and Evacuation Routes
General access to the Gordon Road Detention Basin is via the unsealed service track at the western end of
Gordon Road. The access track is unsealed and potentially unusable in wet weather. It is deemed unsafe
to try to access the dam during a flood event.
Gordon Road is accessed from Simpson’s Road, Bardon. Local roads in this area are winding and flood
prone, with a high likelihood that residents would be cut off and isolated by road closures at many locations.
It is therefore likely that an event large enough to trigger a Level 3 activation of the EAP will be sufficient to
ensure the community is isolated by local floodwater for a couple of hours until floodwaters recede.
Due to the short response time between the start of rainfall and the onset of flooding sufficient to trigger a
Level 2 alert, access to the dam and evacuations of the Population at Risk downstream of the dam will not
be possible. The population at risk (PAR) will therefore need to be flood resilient and remain in place until
after a flooding event is over.
The only viable means of evacuation for the PAR will be to evacuate to a safe refuge in place, at least 1.2
m above the floor.
This means taking refuge in a safe place in a flood proof structure (house) above the highest possible flood
level.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 13 of 71
Figure 1 – Location Map
Figure 2 – Gordon Road Detention Basin Catchment
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 14 of 71
2.0 Gordon Road Bardon Detention Basin – Performance and Operation
2.1 Design and As-Constructed Dam Performance Data
The following data has been compiled from surveyed as-constructed details and may differ slightly from the
data sheet details held by DNRME which was based on the preliminary design data.
Table 2 - BCC Dam Design and As-constructed Data Summary
Description Data
Name of Dam Gordon Road Bardon Detention Basin
Location UBD Ref: 158/G6
Lat: 27.450 S; Long: 152.970 E
Lot on plan Lot 1324 on S31983
Referable Dam Register No: #2608
Dam Owner Manager, Natural Environment Water and Sustainability
(NEWS), Brisbane City Council
Owners Contact number 07 3403 8888
Owners Site Contact No site based personnel.
Emergency Contact Name Regional Manager, West
Emergency contact Regional Business Centre,
Ground level, 681, Fairfield Road
Yeerongpilly
07 3403 8888
Watercourse: Tributary of Ithaca Creek
Original construction Circa 1980
Construction upgrade completed 25 January 2018
Type of dam Reinforced concrete cantilever wall with rock armouring and
gabion protection of downstream watercourse.
Purpose of dam Urban stormwater detention basin
Dam height 4.8m
Width of dam crest 3.5m
Side slopes 2H : 1V (both US and DS faces are rock protected)
Dam length at crest 70m (Approximately)
Dam crest level 76.0 m AHD
Full supply level (FSL) No permanent storage available.
Storage capacity at dam crest level 18.7 ML
Surface area at dam crest level 0.75 Ha
Spillway type and width
Design width of crest-overtopping
Dam Overflow (at 76.00 m AHD crest level),
Approximately 40m
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 15 of 71
Description Data
Outlet works: 1.2m wide x 1.2m high RCBC
Outlet works: U/S & D/S invert levels 71.38 & 71.03 m AHD – culvert barrel length 19.2 m
Discharge capacity 7.3 m3/s at 76m AHD (in 1 in 50 AEP flood)
Dam Crest Flood 1 in 50 AEP flood
Acceptable Flood Capacity 1 in 34800 AEP flood
Catchment area (contributing) Approx. 52 Ha
PMF Design Flood Approx. 62 m3/s
Population at risk (PAR) Approx. 35
2.2 Dam Inflow/Outflow and Water Levels for Design Flood Events
Gordon Road Detention Basin is located on a tributary of Ithaca Creek, in the greater catchment of Breakfast
Creek. The contributing catchment area is approximately 52 hectares. Discharge from the basin is through
a reinforced concrete box culvert of 1200mm x 1200mm at the toe of the basin wall. The culvert upstream
and downstream invert levels are 71.38 and 71.03 m AHD. The length of the discharge culvert is 19.2 m.
Maximum culvert discharge capacity is approximately 7.3 m3/s with basin water level at the dam crest level
of 76m AHD. Storage capacity of the basin at dam crest level is 18.7 ML.
During detailed design, ARUP (2015) assessed the Acceptable Flood Capacity of the basin using a
TUFLOW-2D hydraulic model of the proposed upgrade. A 2m model grid was adopted extending from the
basin to the residential development downstream. Hydrological information regarding design inflow data
was obtained from the WBNM hydrology model developed by Council.
As designed, the upgraded basin can hold runoff up to a 1 in 50 (2%) AEP event. The critical storm duration
is 60minutes (102mm of rainfall in an hour) and a Dam Crest Flood results from this event. Design flood
events rarer than a 1 in 50 AEP event would overtop the dam crest.
The Acceptable Flood Capacity event was identified as the 1 in 34800 AEP flood event. This event would
result in a flood level of approximately 76.58 m AHD and was used as the extreme event for design of the
detention basin wall.
Inflow and outflow hydrographs for the detention basin, including water level variation with time for a wide
range of design flood events are included in the Dam Data Book.
The inflow and outflow hydrograph for the 1 in 50 AEP event is reported in Figure 6.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 16 of 71
2.3 Storage-Discharge Details
A stage-storage plot for GRBDB is presented in Figure 3. Stage-storage and spillway discharge data is
included in Table 3 and dam characteristics against various AEP events in Table 4.
Table 3 - Stage/Storage and Discharge Data for the Gordon Road Bardon Detention Basin
Dam Level Basin Storage Discharge Comments
(m AHD) (m3) (m3/s)
71.38 28 0.0 Outlet culvert-invert
71.50 50 0.1
71.75 205 0.5
72.00 409 1.0
72.25 843 1.7
72.50 1277 2.4
72.75 1949 3.1 LEAN FORWARD – Trigger Level 1
Outlet culvert running full 1 in 10
AEP
73.00 2621 3.6
73.25 3488 4.2
73.50 4355 4.7
73.75 5466 5.2
74.00 6576 5.6
74.25 7848 5.9
74.50 9120 6.2
74.75 10529 6.5
75.00 11938 6.8 STAND UP - Trigger Level 2
1 m below Dam Crest –
75.25 13523 7.1
75.50 15108 7.3 See Note:
75.75 16936 7.6*
76.00 18764 7.9* Basin wall crest – 1 in 50 AEP flood
76.25 20773 16.2 1 in 200 AEP flood
76.35 21577 21.9 STAND UP – Trigger Level 3
1 in 500 AEP flood
76.40 21980 25.3 1 in 1000 AEP flood level
76.46 22460 31.0 1 in 2000 AEP flood level
76.50 22783 31.0 Water level above design flood
76.58 22783 36.9 1 in 34,800 AEP flood
76.75 24965 50.2
76.88 Approx. 26000 62.1 PMF
77.00 27147 72.9 Water level above PMF
Note: * Outflows above 7.3 m3/s are pressurised culvert flows with no allowance for blockage.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 17 of 71
Table 4 – Inflow / Outflow and Dam Water Levels for Design Floods, Including Extreme Event Event
ARI
Event
AEP
Rainfall
Depth
(WBNM)
Peak Inflow
Peak
Outflow
Peak
Water
Level
Time to
peak
(Years)
(Critical storm
duration
minutes)
(%) (mm) (m3/s) (m3/s) (m AHD) (minutes)
20 (90min) 5 62 11.2 7.1 75.25 86
50 (60min) 2 102 14.4 7.3 75.97 74
100 (60min) 1 113 17.1 12.7 76.15 60
200 (60min) 0.5 130 19.7 16.5 76.25 58
500 (60min) 0.2 150 23.9 21.9 76.35 50
1000
(60min)
0.1 165 26.9 25.3 76.4 49
2000
(60min)
0.05 180 30.1 28.9 76.46 47
34800
(60min)
2.87x10-3 243 37.2 36.9 76.58 45
PMF
(60min)
1x10-5
380 62.1 62 76.88 40
The AFC event was identified as the 1 in 34,800 AEP flood event. This event would result in a flood level of
approximately 76.6 m AHD and was used as the dam overtopping flood event to assess failure impacts
downstream.
A plot of the spillway-rating curve is shown in Figure 4.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 18 of 71
Figure 3 – Gordon Road Detention Basin Stage – Storage Curve
Figure 4 – Gordon Road Detention Basin Stage – Discharge Relationship
70
71
72
73
74
75
76
77
78
79
80
81
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0
m A
HD
Storage-ML
Gordon Road Basin- Storage/Elevation Plot
Storage-elevation
70
71
72
73
74
75
76
77
78
79
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00
Ba
sin
Ele
va
tio
n -
m A
HD
Culvert Discharge and Overflow - m3/s
Gordon Road Basin-Rating Curve
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 19 of 71
3.0 Dam Safety Management
3.1 The Emergency Management Framework
This Emergency Action Plan (EAP) is a tool used to define the communication protocols and procedures
that should be followed to manage incidents in the Gordon Road, Bardon Detention Basin catchment.
Very heavy rainfall and extensive flooding can occur in the catchment of Ithaca and Breakfast Creek
resulting in significant stream rises and flash flooding in the upper reaches of the creek systems. When such
flood emergency develops that affects the Gordon Road Detention Basin, close co-operation needs to be
maintained with the Local Disaster Management Group.
The Detention Basin does not overtop until the rainfall event equates to a 1 in 50 (2%) AEP event, a very
major event. When that happens, the Local Disaster Management Group and emergency management
personnel may already be activated with flooding all over the area. A failure in the dam embankment will
surcharge those flood levels, potentially worsening the flooding downstream to the junction of Ithaca Creek.
Modelling associated with the preparation of the Dam Failure Impact Analysis shows that for a flood up to a
1 in 500 AEP magnitude (approx. 350 mm above the Dam Crest Flood), while there will be downstream
flood impacts, the PAR identified in the worst case dam failure modelling will not be at risk. At this water
level, the discharge is well within the structural safety limits allowed for in design and no failure of the
structure is anticipated.
Nevertheless, assuming is possible, Council considers that water levels rising within 1 m of overtopping the
Dam Crest will require Stand Up status. The 1 in 500 AEP (i.e. 76.35 m AHD) water level is considered to
be the trigger level for taking action to issue automated EA messaging to PAR as described in this EAP.
The 52 Ha creek catchment above the detention basin is relatively steep, and so the time for the Local
Disaster Management Group and emergency management personnel to react will be short – less than an
hour. This coupled with the lack of safe evacuation routes will make responding to an emergency event
associated with the basin a challenge for all emergency personnel.
3.2 Maintenance and Management of the Detention Basin
Gordon Road Bardon Detention Basin (GRBDB) is owned by Council and the responsible officer is the
Manager, NEWS.
Day-to-day management of the Basin is carried out under the overall responsibility of the Dam Asset
Manager (Regional Manager West).
Regular inspections and asset maintenance is carried out by the Dam Asset Manager as required, in
accordance with the GRBDB Asset Maintenance and Management Plan (Detailed Operating and
Maintenance Manual).
The Asset Maintenance and Management Plan (Detailed Operating and Maintenance Manual) of the
GRBDB sets out procedures to follow and provides guidance on actions required to maintain the basin
ensuring the operation of the basin is in accordance with the design parameters and the licence conditions.
3.3 Water Level Measurement and Rainfall Records
To assist with the monitoring and alerting requirements of managing the basin, a stream height gauge is
located near the right bank of the basin wall (looking downstream) which is connected to Council’s telemetry
network. This gauge provides continuous 24 hour-7days per week monitoring of water levels in the basin to
enable automatic alert messaging to the PAR.
There are two ALERT rainfall gauges in close proximity to the basin providing continuous live reporting of
nearby catchment rainfall to Council’s telemetry network.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 20 of 71
• The nearest gauge (I_R512) is located 2km south-west of the basin wall in the suburb of Mount
Coot-tha in the Ithaca Creek catchment;
• The second gauge (TWR 279) is located 2.73 km south-east of the basin wall in the Toowong
Creek catchment.
Both gauges have a 1 mm resolution and report instantaneously. Rainfall accumulations are monitored
continuously in Council’s FloodWise Information System. Because of the short catchment response time
between rainfall and the onset of flooding, a series of automatic alerting protocols have been set up to
enable notifications to the PAR in accordance with this EAP. The automatic rainfall and water level alert
triggers and messaging are summarised in Table 10.
A limitation with this system is that there may be a slight delay of up to five to ten minutes for the system to
update the latest rainfall data. Any alerts to the PAR need to take this delay into account.
3.4 Emergency Events
The flood hazards resulting from the release of water via the dam spillway and/or controlled release from
the low flow culvert is managed by Council under normal daily operations in response to flooding incidents
and by on-call personnel after hours.
The emergency events catered for in this document include:
• dam crest flood breach failure (1 in 50 AEP event) inundation downstream of the detention basin;
and,
• dam overtopping collapse associated with the acceptable flood capacity event (1 in 34,800 AEP
event).
Other non-flooding related conditions which may influence the safety of the basin are covered in Section 6.
3.5 Relationship to Other Plans
This plan is subordinate to the Brisbane District Disaster Management Plan.
Information presented here is intended to assist with the management of a flooding emergency in the
catchment of Gordon Road and the upper reaches of Ithaca Creek that may be affected by the condition of
the Gordon Road Detention Basin.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 21 of 71
4.0 Key Roles and Responsibilities
In managing a dam hazard event, close collaboration between the Dam Owner and internal as well as
external stakeholders is required. All parties who have a role in the implementation of the EAP are required
to agree on their respective roles and responsibilities.
Table 5 lists the personnel and agencies which have designated roles and responsibilities in the
implementation and management of the EAP response. Notification arrangements and contact details for
external agencies are discussed in Section 5 and contact details for key Council officers provided in
Appendix C2.
Table 5 – Key Roles and General Responsibilities
Role/Position EAP Dam Release Hazard Responsibility
EAP Non-emergency Response Planning and Non-urgent Responsibility
Dam Owner
(Manager NEWS)
Notify priority stakeholders about the
situation.
Respond in accordance with the approved
EAP in all dam relevant incidents.
Activate the EAP and maintain an incident
log (including visual inspection of the dam
and any notifications that have been
made).
Provide timely and accurate notifications
to all relevant parties mentioned in the
notification list in a relevant dam hazard
event or emergency event.
Report all incidents and failures in writing
to the chief executive within forty-eight
(48) hours of becoming aware of the
incident or failure.
Prepare Emergency Event Report (EER)
and submit to the chief executive within 30
business days after the end of the
emergency event.
Develop an emergency action plan in
consultation and collaboration with local
government and disaster management group/s
who may be affected by a dam hazard identified
in the plan.
Provide a copy of the EAP to each disaster
management group who may be affected by a
dam hazard identified in the plan.
Submit the EAP to the chief executive for
assessment.
Maintain and update documents annually
(before 1 October each year)
Distribute current approved EAP to all parties
listed in the distribution list.
Ensure adequate funds and resources available
to manage the dam.
Ensure the Population at Risk (PAR) have an
appropriate evacuation plan in the event of a
dam failure.
Ensure the Population at Risk (PAR) have an
understanding of the purpose of the warning
and notifications in the event of a dam
emergency or dam hazard.
Ensure appropriate training for all personnel
with responsibilities under the EAP.
Undertake periodic testing of EAP to ensure
telephone numbers are correct and the
notification priority list is logical. Make
appropriate dam safety related decisions based
on advice from a consulting engineer where
appropriate.
Authorise any immediate expenditure so that
urgent repair work will not be delayed.
The dam owner is responsible for conducting a
safety evaluation of the dam and to identify any
deficiency in the dam’s safety. Where
deficiencies exist, the dam owner is required to
take appropriate steps to minimise the potential
risk of dam failure from these deficiencies.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 22 of 71
Role/Position EAP Dam Release Hazard Responsibility
EAP Non-emergency Response Planning and Non-urgent Responsibility
Dam Asset Manager
(Regional Manager,
West)
Undertake inspections in response to developing dam hazard event.
Coordinate relevant repairs if time permits and if safe to do so.
Monitor events on site when safe to do so.
Coordinate day-to-day asset management functions including inspections, maintenance and repairs to ensure dam is safe and fit for purpose
Event Response
Coordinator
(Depending of the scale
and phase of the event
this role is filled by:
• Disaster
Management Duty
Officer;
• Manager, Disaster
Management; or
Incident Controller, Local
Disaster Coordination
Centre)
Coordinate Council’s response to the hazard event.
Review the emergency information received and advise the LDMG of the developing hazard situation.
Issue Alert/advice to the emergency response groups and requirements for mobilisation of emergency resources and actions.
Liaise with the Dam Owner in implementing EAP actions and the local disaster management plan and check the requirements
Issue Emergency Alert messages via the SDCC Watch Desk
Mobilise and convene the Local Disaster Management Group (LDMG) and assign resources required to manage the event
Mobilise disaster response from internal and external organisations in accordance with the Qld Disaster Management Arrangements.
Mobilise State assistance if the situation escalates beyond control of local community.
Establish LDCC and organise resources.
Organise LDMG and manage functions.
Maintain a log of all communications and data records
Ensure that the GRBDB EAP has been prepared in consultation with other response agencies and is in accordance with the Qld. Disaster Management Guidelines.
Flood Officer
(FIC Duty or Technical
Officer)
Monitor BoM weather forecasts, flood warnings, recorded rainfall and dam water levels
Advise Dam Owner and Event Response Coordinator (ERC) of the developing hazard conditions
In case of a developing emergency event, Identify the trigger levels and follow up on the automated FloodWise alerts to Dam owner or representative
Update the Dam Owner and ERC as required
Maintain a log of all communications and data records
Monitor BoM weather forecasts, warnings, Flood-wise gauge readings and dam water level readings
Be aware of and report to ERC any emerging situation that could trigger a dam emergency event.
Corporate
Communication
(Duty Officer)
Liaison with relevant emergency management entities including LDMG
Follow up with repeat public messaging in authorised media channels and on social media.
Assist Dam Owner with Public Education and Awareness communication
Ensure a high level of participation in Council’s OPT-IN messaging service.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 23 of 71
Role/Position EAP Dam Release Hazard Responsibility
EAP Non-emergency Response Planning and Non-urgent Responsibility
Local Disaster
Coordinator (LDC)
(BCC Chief Executive
Officer)
Exercise Delegated Responsibility in case of an emergency event related to the dam as per the Qld. Disaster Management Act.
Exercise primary responsibility for disaster management with in boundaries as per the Queensland Disaster Management Act
Contact Centre Receives calls coming into Brisbane City Council via the Contact Centre
Works with Contact Centre team and the Corporate Communication Team to update scripting on the situation
Receives calls coming into Brisbane City Council via the 24 hour Contact Centre
Field Services Disaster
Response Officer
Coordinate Field Services resourcing e.g. water over road signs, road closure signs and earthmoving equipment as required
Activate Regional Incident Management Teams as required
Coordination of Field Services resources to support disaster operations
Brisbane Metropolitan
Transport
Management Centre
Advise Translink about potential impacts to public transport
Liaise with the FIC and DM on potential and actual road closures
24 hour monitoring and reporting of incidents on the road network.
Advise Translink about potential impacts to public transport
LDMG Set priorities for the LDCC Provide input/feedback on the EAP
SDCC
Coordination of state level operational response during disaster operations
Issue authorised preconfigured Emergency Alert Warnings in accordance with the EAP
Maintain a 24/7 watch desk
QLD Police Initiate appropriate emergency actions to protect PAR
First response and initial evacuation
Public safety
QFES Coordinate swift water rescue if required
Carry out general rescue and recovery, including confined space rescue and recovery in the event of structural collapse of buildings, bridges, etc.
Public safety
DNRME
Dam Safety Regulator
Liaise with SDCC re dam safety emergency requirements
Administer Dam safety licencing & regulations.
Review and approve EAPs.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 24 of 71
5.0 Warning and Communication Plan
5.1 Purpose of the Communication Plan
There are high community expectations that all dam owners will provide timely warnings and notifications
of a dam hazard event or emergency event. For this reason, the Act requires the Dam Owner to state within
the EAP when and how PAR and relevant entities (internal and external) will be contacted in the event of a
dam emergency (including priority order).
Possible hazards identified with GRBDB which may require notifications and warning are outlined in more
detail in Section 6.
The purpose of emergency warnings is to inform the PAR of an impending or current threat and promote an
appropriate responsive action.
Depending on the location of the dam and the number of PAR that may need to be notified of warning it
may be appropriate that the warning is issued via a personalised phone call or personal visit.
5.2 Limitations Associated with PAR Notifications
The primary purpose of issuing public notifications during an emergency event is to enable a suitable, safe
and timely action from the PAR.
It has already been identified that the rainfall event likely to cause water levels to rise above the nominated
trigger levels will be greater than a 1 in 20 AEP rainfall event. During such events, access to local roads and
to the PAR will be severely constrained and the safest action may well be to “shelter in place” because safe
evacuations may not be possible. Messaging to the PAR has been carefully constructed around this central
idea.
Note: In the event of forecasted intense storm events, it may not be possible to tell when or where the
rain will fall until it starts to rain. As the response time of the catchment is so short, the time to issue
warnings is limited and it is essential that the alerting procedure be highly automated.
Notwithstanding the time constraints on issuing warnings, provision exists for early alerts to be activated
based on rainfall and rate-of-rise triggers.
In managing a dam hazard event in accordance with the response protocols identified, the safety of
emergency services personnel is of paramount importance.
5.3 Notification to External Agencies
The communications flow chart as given in Figure 5 describes the agreed information flow surrounding the
management of a dam hazard or hazard event. This flow chart has been developed in consultation with
other internal units and external agencies.
Note that due to the rapid response of the catchment, a dam hazard event may develop a short period after
the commencement of rainfall in the catchment. For this reason, many of the actions listed on the flow chart
will need to occur concurrently.
Contact details and notification requirements for relevant external agencies and roles associated with the
implementation of the EAP are provided in Table 6.
5.4 Notification to Population at Risk (PAR)
The Dam Owner is responsible for the continuous monitoring of the status of the dam in accordance with
the EAP, and provision of timely and accurate notifications to all relevant parties in the event of an
emergency event at GRBDB.
Modes of communication may include:
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 25 of 71
• Personalised calls or door knocks if practical and appropriate;
• Mass notification and warning messages via voice messages to land lines and SMS to mobile
phones. Dam owners are required to prepare and submit polygons and pre-formatted wording to
the State Disaster Coordination Centre (SDCC);
• Media news coverage (i.e. radio and television), if time permits;
• Social media (i.e. websites, Facebook, Twitter);
• Sirens or other direct means.
The PAR is encouraged to register to receive notifications by phone (landline or mobile) or by SMS
via the Brisbane City Council Early Warning Alert (EWA) Service.
Note: During extreme rainfall situations, severe degradation of mobile phone and SMS services
may be experienced. Fostering an aware, self-reliant community is desirable to ensure
maximum effectiveness and safety.
If time permits, targeted telephone-based emergency warnings may be issued to the PAR within the
geographical area likely to be affected via the national Emergency Alert (EA) system.
The area likely to be affected by the possible emergency event is shown in Appendix A, Figure A-6. This
area was determined to be the area covered by the PMF dam failure flood outline expanded to the nearest
road crest.
Contact details for potentially impacted downstream properties are listed in Appendix C1.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 26 of 71
Figure 5 – Agreed Internal and External Communication Flow
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 27 of 71
Table 6 – Contact Details for Notification of Relevant External Agencies
Person/Agency Name Contact Details Notification Requirement
(What this role needs to know)
Contact
priority
Contacted by
Local Disaster
Management
Group
Coordinated through Disaster Management
Manager Disaster Management
Disaster Management Duty Officer
LEAN FORWARD: Confirmation of a decision to activate the EAP
STAND UP: Advice on the severity of the situation and the likely
response required
1 Event Response
Coordinator
District Disaster
Management
Group /
Queensland
Police Service
District Disaster Management Group
Executive Officer
LEAN FORWARD: Advice on the severity of the event and status
of the dam.
STAND UP: Advice on the severity of the situation and the need
for a response including the likelihood of the need for evacuations
2 Event Response
Coordinator
Queensland Fire
and Emergency
Services (QFES)
Emergency
Management
Coordinator
Contact via SDCC
Watch Desk
STAND UP: Advice on the severity of the situation and the
likelihood of the need for rescue and swift water rescue
STAND DOWN: Request recovery operations if necessary
3 Event Response
Coordinator
SDCC Watch Desk Duty Officer 24 hours
LEAN FORWARD: Advise the EAP has been activated
Notify Emergency Management Coordinator
STAND UP: Request issue of pre-approved emergency
notices/warnings via sms and voice messaging to downstream
residents
4 Event Response
Coordinator
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 28 of 71
Brisbane Metropolitan Transport Management Centre (BMTMC)
Shift Leader/
Duty Officer
STAND UP: Advice on the situation and request that all
notification services are utilised to advise the public of impacts to
the road network
5 Event Response
Coordinator
Dam Safety Regulator (DSR), DNRME
STAND UP: Advice of details of activation of EAP to ‘Stand-up’
level of activation.
Informed of any changes in dam status as emergency situation
develops.
Notify any incidents or failures in accordance with safety conditions
applied to the dam.
6 Dam Owner
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 29 of 71
6.0 Assessment of Dam Hazards and Emergency Situations
6.1 Dam Hazards
For the purpose of this document:
Dam Hazards as defined by the Water Supply (Safety and Reliability) Act 2008 include hazard situations
arising from either the controlled release of water from the dam, or failure of the dam, where failure includes
collapse of the dam and/or the uncontrolled release of water from the dam.
An uncontrolled release from the Dam (Basin) can be associated with natural flooding and caused by
water that has flowed naturally into the Dam (Basin), filling it and making it overflow. An uncontrolled release
need not be associated with a failure of the Dam (Basin) structure.
A Dam (Basin) structural failure/collapse is associated with an uncontrolled release of water from the
Dam caused by a failure of the Dam structure. In such an event, the flood impacts downstream of the Dam
(Basin) may be worsened by the natural flooding.
A Sunny Day Failure of the Dam (Basin) structure is one that occurs when no natural flooding is occurring.
Emergency Events as defined by the Water Supply (Safety and Reliability) Act 2008 include any event
where persons or property may be harmed because of the event and a coordinated response involving 2 or
more relevant entities are likely to be required. For the purpose of this EAP an emergency event is taken to
be when the operational state of LEAN FORWARD is reached based on the triggers defined in this EAP.
Dam Safety Emergency Event triggers are associated with the potential for a Dam (Basin) structural failure.
6.2 Gordon Road Bardon Detention Basin – Failure Impact Assessment (FIA)
During the design of the basin, a Preliminary Failure Impact Study was prepared (ARUP, 2015) in
accordance with Queensland government guidelines (DEWS, 2012). Possible failure mechanisms and risks
to the PAR downstream of the basin were investigated.
ARUP identified and investigated two possible breach scenarios, a large breach and a confined breach.
Both of these resulted from an overtopping failure triggered by water level reaching EL 76.00 m AHD. The
design 1 in 50 AEP flood was identified as the Dam Crest Flood Event while the 1 in 34800 AEP event was
identified as the Acceptable Flood Capacity event.
A licence for a referable dam was issued in February 2018 setting out the approved conditions to be met by
the Dam Owner in operating and managing the dam. A copy of the licence conditions is included in
Appendix F.
6.3 Possible Flood–related Failure Mechanisms Considered for the Gordon Road
Detention Basin
Possible failure cases for GRBDB are:
• Breach failure from a Dam Crest Flood (1 in 50 AEP – approx. 102 mm rainfall in an hour);
• Dam collapse due to overtopping in an extreme event (up to 1 in 34,800 AEP event or between 102
to 243mm rainfall in 1 hour)
Sunny Day Failure is not identified as a possible threat to the community as the dam does not contain a
permanent storage component other than a small wetland in the base of the basin.
Other potential failure mechanisms considered include:
• Damage or collapse of the dam as a result of earthquake/tremors or high impact events (including
terrorist activity);
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 30 of 71
• Sudden collapse due to associated structural failures, either seepage under the basin wall leading
to foundation failure, sliding, overturning or structural failure;
• Erosion and undermining of the foundation;
• Long-term damage to the basin wall including cracking /deformation /sliding due to other reasons.
6.3.1 Sudden Collapse Due to Seepage Under the Basin
Sudden collapse from seepage under the basin is not considered a possibility for this structure, as there is
no permanent storage in the basin. Even with the basin full, there is insufficient head to cause seepage
through a foundation which is primarily on rock. Any evidence of seepage through bedrock joints should be
detected during annual maintenance inspections and could be grout injected to remove it in the future. Any
increase in outflow due to seepage is not considered a threat and would be unlikely to cause serious damage
to the downstream community.
6.3.2 Erosion and Undermining of the Foundation
This failure mechanism has not been investigated in detail as the basin is founded on competent rock. There
will be no permanently stored water in the basin to provide the required hydraulic head to initiate seepage
through the foundation. Evidence of wet areas in the downstream channel and banks or any evidence of
slumping or movement of the structure (which may initiate cracking of the concrete parapet), should be
reported and investigated. Prompt repairs and remedial works will ensure the ongoing integrity of the
structure.
6.3.3 Cracking and Development of Uncontrolled Seepage
Any evidence of cracking of the concrete weir or parapet walls should be investigated thoroughly and repairs
made as soon as possible. Cracking of the parapet walls may be difficult to detect and the rock protection
work may have to be partially removed to facilitate this. Inspections should carefully examine any differential
movement of the weir slab as it may indicate an underlying problem with the wall that cannot be readily
seen. However, as there is no permanent storage, it is unlikely that cracking could develop into a sudden
failure in the limited time the basin is holding water.
6.4 Situation 1 – Dam Crest Flood (1 in 50 AEP) with Structural Failure
A Dam Crest Flood is likely to result from a 1 in 50 AEP rainfall event, equivalent to the runoff from 102mm
rainfall in an hour. In the preliminary FIA, the failure mechanism considered was a breach from dam crest
level to the toe level at 71.75 m AHD.
Two breach shapes were tested. One was a larger breach having a width of 51m at the dam crest reducing
to 4m at the toe. The other was a confined breach in trapezoidal shape having 12.5m width at the crest and
reducing to 4m width at the toe.
The confined breach resulted in a total discharge (including culvert flow) of 19.3 m3/s from failure during a
dam crest flood. The amount of material removed to form the breach was 495 m3.
In both design scenarios, commencement of the breach occurs when the basin fills. Breach development
takes 22 to 27 minutes giving peak basin outflows (including culvert flow) within 1.25 hours of the start of
the design rainfall event.
GRBDB is located in a remote location and it will not be possible to attend the site during a rainfall event,
therefore the only way Council can confirm the integrity of the dam wall is to infer it from the water level
record.
A water level drop of more than 1 m in 6 minutes should alert officers to the possibility that the structural
integrity of the wall has been compromised. Unfortunately, by the time Council receives and alert of this
nature, the resulting flood flow will have reached and potentially impacted the downstream properties.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 31 of 71
A breach event is expected to impact up to 15 houses which may be directly impacted with depths of flooding
of up to 300mm.
Potential inundation and impact areas for this event have been mapped and are presented in Appendix A,
Figure A2. The FIA for GRBDB also undertook sensitivity analysis using the 1 in 500 AEP event. Inundation
extents for this event are presented in Figure A3.
Actions in response to the Dam Crest Flood failure scenario are provided in Table 7.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 32 of 71
Table 7 - Situation 1 – Dam Crest Flood EAP Response (Possible Structural Failure)
EAP Phase Alert Lean Forward Stand Up Stand Down
Trigger ID Monitor Trigger 1 Trigger 2 Trigger 3 Trigger 4
Event Data
Water Level Status Warning issued by BoM for rainfall greater than 100mm and possible flash flooding
WL at or above 72.6 m
AHD and rising
(1 in 10 AEP)
WL at or above 75.0 m AHD (i.e. 1 m below crest) and rising
(1 in 20 AEP)
WL at 76.35 m AHD
(1 in 500 AEP)
WL <72.6 m AHD and
dropping predictably
Rainfall Status 40 mm in 30 minutes
1 in 20 AEP rain
70 mm in 30 min
1 in 50 AEP rain
100 mm in 60 min
1 in 100 AEP rain
150 mm in 60m
1 in 500 AEP rain
No rain for last two hours
Dam Status Catchment runoff beginning to enter basin
Observed structural issues with dam such as seepage, cracking or evidence of erosion or movement
WL above culvert obvert and rising
Basin expected to overflow within 20 to 30 mins
If no structural issues dam failure not expected.
If structural issues, anticipate possible failure. Use Dam Crest Flood extents (Figure A2) to estimate impacts
Dam is overflowing with 350 mm over crest.
Refer Situation 2
WL below triggers
Response Actions
Internal Alerts Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
None
Population at Risk messaging
BoM preliminary advice only
BoM Flash Flood and severe storm warnings only
Pre-worded EWA
Media and social media messaging
Pre-worded EWA and Warning EA with SEWS
Media and social media messaging
Media and social media messaging
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 33 of 71
EAP Phase Alert Lean Forward Stand Up Stand Down
Dam Owner Activate EAP Advise CEO of Stand-up
Advise CEO, Councillors and Lord Mayor and DNRME of event status
Advise CEO, Councillors and Lord Mayor and DNRME of event status
Authorise relevant inspections and repairs as necessary
Prepare EER and submit to DSR
Dam Asset Manager Coordinate relevant pre-event inspections and repairs if time permits and it is safe to do so.
Advise ERC of status
Remove resources from site once it is unsafe to continue.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Coordinate relevant inspections and repairs as necessary when safe to do so.
Event Response Coordinator
Liaise with Flood Officer and Dam Asset Manager
Liaise with QPS and SES and Dam Asset Manager re status of dam
Advise Dam Owner, internal and relevant external parties of event status
Advise Dam Owner, internal and relevant external parties of event status
Implement appropriate Disaster Response Plan including PAR warnings
Advise Dam Owner, internal and relevant external parties of event status
Flood Officer Monitor rainfall and dam WL
Monitor rainfall and dam WL
Advise ERC of Lean Forward
Actively monitor rainfall, inflows, outflows and dam WL
Ensure PAR messaging has been sent
Advise ERC of Stand Up trigger
Actively monitor rainfall, inflows, outflows and dam WL
Ensure PAR messaging has been sent
Report likely impacts to ERC
Monitor rainfall and dam WL
Advise ERC of Stand Down trigger
Report on potential impacts
BMTMC Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
closures and incidents on
the road network
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
closures and incidents on
the road network
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
closures and incidents on
the road network
Liaise with the FIC and DM
on potential and actual
road closures;
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
Provide up to date public
messaging through the
131940 hotline and website,
variable message signs (VMS)
messages and radio
broadcasts on road closures
and incidents on the road
network;
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 34 of 71
EAP Phase Alert Lean Forward Stand Up Stand Down
radio broadcasts on road
closures and incidents on
the road network;
Advise Translink about
potential impacts to public
transport
Advise Translink about
potential impacts to public
transport;
Contact Centre Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into
Brisbane City Council via the
Contact Centre
Field Services Proactive coordination of field resources as required
Coordinate field resources as required for recovery
SDCC 24/7 Duty Officer Monitor developing situation
Monitor developing situation
Issue pre-worded Emergency Alert voice and text warnings with SEWS
Coordinate relevant resources as needed.
QPS Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Assist with recovery phase as needed when safe to do so.
QFES Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Assist with rescue and recovery phase as needed when safe to do so.
DNRME Receive advice from ERC
Monitor developing situation
Monitor situation and liaise with Dam Owner
Review EER
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 35 of 71
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 36 of 71
6.5 Situation 2 -- Dam Crest Overtopping With Structural Failure
Any outflow events rarer than 1 in 50 AEP will cause uncontrolled discharges, which are likely to exceed the
capacity of the downstream drainage system, have the potential to cause property damage and pose a risk
to the safety of the PAR. The preliminary FIA investigation work undertaken by ARUP (2015) routed the 1
in 100 AEP (116mm rain in 1 hour) and the 1 in 500 AEP (150mm rain in 1 hour) design events through the
dam. These events overtopped the dam.
As designed, uncontrolled outflows from the basin may occur due to overtopping in events rarer than 1 in
50 AEP. All overtopping flows greater than the 1 in 50 AEP event will pass through the basin without any
mitigation. Water levels at the upstream end of the piped drainage system are expected to peak within five
to ten minutes of overtopping.
It should be noted that the duration of overflows and the volume of the hydrograph for floods exceeding the
dam crest flood are typically short and for flows up to the 1 in 500 AEP event, are not expected to cause
significant downstream impacts provided the basin wall remains in place.
The 1 in 34,800 AEP rainfall event (approximately 243 mm in 1 hour) was nominated as the Acceptable
Flood Capacity (AFC) event. This results in a design water level of 76.6 m AHD at the basin crest with
overtopping occurring approximately 45 min from the start of the storm. The basin wall has been designed
and constructed to withstand a flood of this magnitude. The annual chance of a flood greater than that
magnitude occurring is less than 0.003%.
Note: A 1-hour PMP (Probable Maximum Precipitation) storm event (approximately 380 mm in 1 hour) in
the basin catchment will also fill and overtop the dam. The PMF (Probable Maximum Flood), assumed to
result from the PMP rainfall is estimated to reach a peak basin water level of 76.88 m AHD. The
corresponding design discharge from the PMF would be in the order of 62 m3/sec.
Failure of the basin wall at the AFC has been assessed. The potential inundation and impact areas for this
event have been mapped and are presented in Appendix A Figure A4
Actions in response to the AFC overtopping failure scenario are provided in Table 8.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 37 of 71
Table 8 - Situation 2 – Dam Crest Overtopping EAP Response
EAP Phase Alert Lean Forward Stand Up Stand Down
Trigger ID Monitor Trigger 1 Trigger 2 Trigger 3 Trigger 4
Event Data
Water Level Status Warning issued by BoM for rainfall greater than 100mm and possible flash flooding
WL at or above 72.6 m
AHD and rising
(1 in 10 AEP)
WL at or above 75.0 m AHD (i.e. 1 m below crest) and rising
(1 in 20 AEP)
WL at 76.35 m AHD
(1 in 500 AEP)
WL <72.6 m AHD and
dropping predictably
Rainfall Status 40 mm in 30 minutes
1 in 20 AEP rain
70 mm in 30 min
1 in 50 AEP rain
100 mm in 60 min
1 in 100 AEP rain
150 mm in 60m
1 in 500 AEP rain
No rain for last two hours
Dam Status Catchment runoff beginning to enter basin
WL above culvert obvert and rising
Basin expected to overflow
If no structural issues dam failure not expected.
If structural issues, anticipate possible failure. Use Dam Crest Flood extents (Fig A2 and A4) to estimate impacts
Dam is overflowing with 350 mm over crest
WL below triggers
Response Actions
Internal Alerts Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
Automated rain and WL trigger alerts to Flood Officer and ERC
None
Population at Risk messaging
BoM preliminary advice only
BoM Flash Flood and severe storm warnings only
Pre-worded EWA
Media and social media messaging
Pre-worded EWA and Warning EA with SEWS
Media and social media messaging
Media and social media messaging
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 38 of 71
EAP Phase Alert Lean Forward Stand Up Stand Down
Dam Owner Activate EAP Advise CEO of Stand-up
Advise CEO, Councillors and Lord Mayor and DNRME of event status
Advise CEO, Councillors and Lord Mayor and DNRME of event status
Authorise relevant inspections and repairs as necessary
Prepare EER and submit to DSR
Dam Asset Manager Coordinate relevant pre-event inspections and repairs if time permits and it is safe to do so.
Advise ERC of status
Remove resources from site once it is unsafe to continue.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Coordinate relevant inspections and repairs as necessary when safe to do so.
Event Response Coordinator
Liaise with Flood Officer Liaise with QPS and SES and Asset Manager re status of dam
Advise Dam Owner, internal and relevant external parties of event status
Advise Dam Owner, internal and relevant external parties of event status.
Implement appropriate Disaster Response Plan including PAR warnings
Advise Dam Owner, internal and relevant external parties of event status
Flood Officer Monitor rainfall and dam WL
Monitor rainfall and dam WL
Advise ERC of Lean Forward
Actively monitor rainfall, inflows, outflows and dam WL
Ensure PAR messaging has been sent
Advise ERC of Stand Up
Actively monitor rainfall, inflows, outflows and dam WL
Ensure PAR messaging has been sent
Advise ERC of Activation
Report likely impacts
Monitor rainfall and dam WL
Advise ERC of Stand Down
Report on potential impacts
BMTMC Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
Liaise with the FIC and DM
on potential and actual
road closures;
Provide up to date public
messaging through the
131940 hotline and
Provide up to date public
messaging through the
131940 hotline and
website, variable message
signs (VMS) messages and
radio broadcasts on road
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 39 of 71
EAP Phase Alert Lean Forward Stand Up Stand Down
closures and incidents on
the road network
closures and incidents on
the road network
closures and incidents on
the road network
website, variable message
signs (VMS) messages and
radio broadcasts on road
closures and incidents on
the road network;
Advise Translink about
potential impacts to public
transport
closures and incidents on
the road network;
Advise Translink about
potential impacts to public
transport;
Contact Centre Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Receives calls coming into Brisbane City Council via the Contact Centre
Field Services Proactive coordination of field resources as required
Coordinate field resources as required
SDCC 24/7 Duty Officer Monitor developing situation
Monitor developing situation
Issue pre-worded Emergency Alert voice and text warnings with SEWS
Coordinate relevant resources as needed.
QPS Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Assist with recovery phase as needed when safe to do so.
QFES Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Receive advice from ERC
Monitor developing situation
Ready resources for deployment when safe to do so.
Assist with rescue and recovery phase as needed when safe to do so.
DNRME Receive advice from ERC
Monitor developing situation
Monitor situation and liaise with Dam Owner
Review EER
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 40 of 71
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 41 of 71
6.6 Situation 3 - Damage to the Basin as a Result of Earthquake
While South East Queensland does not have a history of moderate or major earthquakes, they are possible,
albeit rare occurrences. An earthquake equal to or stronger than magnitude 5.5 may cause slight damage
to the concrete structure. However, it is unlikely that the basin wall will sustain sufficient damage in an
earthquake of up to magnitude 6.0 to result in a serious leakage problem or to trigger a sudden collapse.
Even if there was serious damage to the basin wall from an earthquake, the dam needs to be full at the time
of the event to pose any risk at all.
The maximum amount of damage likely to occur from a mild-moderate tremor would be cracking or
differential movement of the concrete parapet walls (particularly at the abutment cut/fill line, or where the
retaining wall changes direction). Such damage is unlikely to occur while the basin is full. Therefore, the
possibility of this failure mechanism occurring can be mitigated by regular inspections.
Nevertheless, given the time it may take to enact repairs following any earthquake damage, vigilance around
the monitoring of any adverse rainfall events is to be maintained. The worst case scenario from such a
situation is best described by the Dam Crest Flood breach failure – refer Situation 1.
The following steps are recommended to be undertaken following an earthquake event.
• Undertake an inspection of the structural concrete work within thirty days of any earth tremors of
less than 5.5 magnitude;
• Undertake immediate inspection of the structural concrete work within five working days of any earth
tremors greater than 5.5 magnitude;
• Carry out any maintenance or repairs necessary as a matter of priority in accordance with the
Detailed Operations and Management Manual.
6.7 Situation 4 – Terrorist or High Energy Impact
Any identified sabotage or vandalism should be treated seriously and the following actions are
recommended:
• Immediately report the incident to Queensland Police Service by calling 000
• Report the incident to National Security Hotline by calling 1800 123 400.
• Take photographs of the damage or incident site
• If possible and safe to do so, record and photograph unusual vehicle details including registration,
description, time, date etc.
• Barricaded the area to enable the incident site to be inspected and investigated
• Conduct a dam safety inspection
Such an event would only represent a risk to the downstream community should a significant rainfall event
occur whilst the basin is in a damaged state. The worst-case scenario from such a situation is best described
by the Dam Crest Flood breach failure – refer Situation 1.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 42 of 71
7.0 Activation of the EAP
7.1 Emergency Management to Identify and Minimise Risk
Whenever a severe weather event is forecast by the Bureau of Meteorology (BoM) or any situation develops
within the catchment which might require a heightened response, close monitoring of BoM advice and
Council’s flood information systems are to be undertaken by authorised and trained BCC Flood Information
Centre (FIC) personnel. They are to be alert to potential hazard developments and maintain vigilance during
large and extreme rainfall events with reference to the hydraulic functioning of the basin.
Regular maintenance of the basin wall and inspection of relevant areas prior to such warnings as
scheduled/planned would help to assure that there is no structural impediment to the design function of the
basin wall during a storm event.
Analysis of runoff patterns has demonstrated that water level in the basin could rise rapidly to the crest level
if 102mm of rainfall falls within one hour (1 in 50 AEP-1hour duration design storm event). In this design
scenario, basin water levels are expected to peak approximately within 60-75 minutes from the start of the
storm.
If one hourly rainfall is more intense and likely to exceed 100mm in one hour, water levels are likely to peak
in less than an hour and will almost definitely overtop the dam wall. Therefore, the effective warning time
available to issue warnings and alert notifications during intense storm events is limited.
The effectiveness of actions taken during and after an event will depend largely on how effective the pre-
event community education has been. Ongoing community awareness and education programs aimed at
increasing awareness of possible hazards in the surroundings, identifying safe refuge locations, and safe
evacuation routes in accordance with Council’s adopted Dam Event Public Warning and Education Protocol
are essential. Such programs can enhance community resilience and ensure the PAR can become self-
reliant and proactive during and after a dam hazard event.
7.2 Stages of Emergency Services Activation
The EAP should be activated when there is a developing dam hazard event or when an emergency event
is occurring at the dam and there is a potential to place people and property at risk.
Full activation may not be possible or even required for minor incidents such as cracking, small slips, sink
holes if they occur near the basin wall. Such events are likely to be detected during routine inspections and
are unlikely to coincide with elevated water levels in the basin.
However, these incidents need investigation, repair and adequate monitoring to prevent further
deterioration. Refer to the Detail Operation and Management Manual for details.
Activation of the EAP in response to a Dam Hazard Event will follow the following sequence as the event
develops:
• Alert
• Lean Forward
• Stand Up
• Stand Down
The stages are summarised in Table 9.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 43 of 71
Table 9 – EAP Escalation Levels
Level Conditions
Alert ▪ A heightened level of vigilance due to the possibility of a major event in the
GRBDB catchment.
▪ Preventative action is recommended at this stage and residents in the
evacuation area already experience overland flooding in their streets with
anything over a 1 in 10 AEP (10%) rainfall event.
▪ Duration of this level is dependent on the rate of development of the
potential failure condition.
▪ During the alert level, agreement on the need for and frequency of
situational reports should be discussed with the ERC.
▪ No further action may be required. However, the situation may need to be
monitored by someone capable of assessing the potential of the threat
Lean Forward ▪ A heightened level of situational awareness of a potential dam hazard event.
▪ Commence moving into a state of operational readiness. Disaster coordination
centres are placed on standby, prepared but not activated. Information is
received that the area may be impacted by an emerging dam hazard event.
▪ At this stage, the relevant agencies, are requested to Lean Forward and
confirm contact details. The Local Disaster Coordination Centre (LDCC) is
checked for operational readiness.
Stand Up ▪ The operational state following Lean Forward whereby resources are ready
to be mobilised, personnel are activated and operational activities
commenced. Disaster coordination centres are activated. Information is
received to confirm that the impact of a disaster situation within the area is
imminent.
▪ Relevant members are requested to Stand Up. The LDCC should be now
operating on a 24-hour basis. There should be ongoing liaison between the
LDMG, DDMG and QDMC (if activated), including release of situation reports
(SITREPs), as required by the reporting requirements of the Local Disaster
Management Plan.
Stand Down ▪ Transition from responding to an event back to normal core business and/or
recovery operations. There is no longer a requirement to respond to the event
and the threat of a disaster has passed.
▪ When the requirements of disaster operations have been completed to the
stage that the LDCC are no longer required to be activated, they may be stood
down.
7.3 Initiation of an Emergency
Key members of the Brisbane City Council, including the Flood Duty Officer and Council’s Disaster
Operations staff receive advance warnings from the Bureau of Meteorology of impending extreme weather
events.
It is acknowledged that due to the flash flood nature of this catchment, advance warning of significant rain
producing weather systems cannot be guaranteed. In the event that the BoM predicts high rainfall totals and
advance warning is received of likely flash flood producing rain in the catchment, the Flood Officer is to
inform the Event Response Coordinator (initially the Manager, Disaster Management or the Disaster
Management Duty Officer). If the LDCC is not yet stood up, the Manager, Disaster Management or the
Disaster Management Duty Officer may initially fill the role of the LDCC Incident Controller.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 44 of 71
During this period and until the situation has stabilised and the threat passed, key operational staff are to
remain in a state of heightened awareness of developing weather conditions and act in accordance with the
requirements set down in the EAP.
Persons that become aware of a structural deficiency associated with the basin, either during a rainfall event
or at any other time during an impending flood emergency or other non-flood related issues are to contact
the Council Customer Service Centre or After Hours Emergency Centre on 07 3403 8888 and direct their
enquiry to the Regional Manager, West.
7.4 Notifications on Activation of the EAP
In the case of an emergency situation, the Dam Owner after advising the ERC, will make a decision (in
consultation) to activate the Emergency Action Plan and request the ERC:
o Notify the Local Disaster Coordinator; then
o Notify District Disaster Management Group;
o Notify the Local Disaster Management Group – Brisbane City Council;
o Notify Queensland Fire and Emergency Services;
o Notify Queensland Police Service;
o Notify the Corporate Communications and the Contact Centre if public information and warnings are
required;
o Notify the Brisbane Metropolitan Transport Management Centre about actual and potential road
closures;
o Notify other persons/organisations listed in the Relevant Agencies Listing Table. Refer Table 6 and
Figure 5.
7.5 Emergency Situation - Alert Triggers
The water level triggers presented in Figure 8 are incorporated into Council’s Alert protocols in accordance
with the pre-approved messages in Section 7.6 of this EAP.
For reference, the design 1 in 50 AEP:60 minute inflow and outflow hydrographs, and cumulative rainfall
and predicted water levels are also shown in Figure 6 and Figure 7, respectively.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 45 of 71
Figure 6 – Inflow, Outflow and Peak Water Levels in GRBDB for 1 in 50 AEP Event
Figure 7 – Catchment Rainfall and Peak Water Levels in GRBDB for 1 in 50 AEP Event.
71.00
72.00
73.00
74.00
75.00
76.00
77.00
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
0 50 100 150 200 250
1 in
Infl
ow
& O
utf
low
(m
3/s
)
Time(mins)
1 in 50 AEP - 60min Inflow, Outflow & Water Level
Inflow-q50 60m Outflow Stage
71.00
72.00
73.00
74.00
75.00
76.00
77.00
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0 50 100 150 200 250m
AH
D
Rai
nfa
ll(m
m)
Time(m)
1 in 50 AEP - 60min - Rainfall & Water Level
50y 60m rain Stage
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 46 of 71
Figure 8 – Gordon Road Bardon Detention Basin - Emergency Situation Alert Triggers
77
76
75
74
73
72
71
70
Gordon Road Bardon - Detention Basin
Culvert sill level= 71.38 mAHD
Water level = above 72.6 mAHD
Water level= 75 mAHD - 1m below Basin crest
Lean Forward - Monitor water levels - Trigger-1 : Internal messaging
STANDUP -Trigger 2 - External messaging
Basin crest76.0 mAHD
Basin base= 70.5m AHD
Culvert outlet = 71.03 mAHD
Culvert obvert level = 72.58 mAHD
Water level = 76.35 mAHD - 350mm over Basin crest Trigger 3 - Emergency Actions- As in EAP
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 47 of 71
7.6 Pre-approved Wording of the Agreed Notification and Warning Messages
A notification provides appropriate information and advice on a heightened risk to enable those potentially
involved to make informed decisions about preparedness and safety.
A warning is the dissemination of an urgent message signalling an imminent hazard event, or emergency
event and provides advice on protective measures.
The warning messages involve more than notifying people about the technical nature of a release of water
from the dam. The message includes telling people if, when, and potentially even how, they need to act to
protect life or property.
Warning messages inform those at risk, or whose property is at risk, of an impending escalation of an emergency event and aims to prompt an appropriate response or action from those persons. The required action is contained in the warning message, for example, ‘seek further information’, ‘take shelter’, ‘evacuate’ or ‘activate your personal emergency plan’.
The pre-approved wording of notification and warning messages to be issued under this EAP are presented in Table 10.
Table 10 – Summary of Pre-approved Emergency Communication Messaging to the PAR
Dam
warning type
Trigger Level 1 Trigger Level 2 Trigger Level 3
Gordon
Road
Detention
Basin
Water Level rising
> RL72.6 (above
box culvert
obvert)
Water Level 1 m below basin
crest – RL 75.0 m AHD
Water over basin crest - > RL 76.35 m AHD
(350 mm above crest) – water level now
exceeding the 1 in 500 AEP flood.
EWA
Messaging
*No Public
Messaging at this
stage.
Internal Heads-up
alert to FIC Duty
Officer generated
by FloodWise.
Consult EAP to
check triggers
Phone Voice Message:
{104 characters}
Gordon Road Bardon - heavy rain
– flash flooding possible in next 20-
30 minutes. Stay out of flood water
SMS – Twitter Text: {104
characters}
Gordon Road Bardon - heavy rain
– flash flooding possible in next 20-
30 minutes. Stay out of flood water
Phone Voice Message: {87 characters}
Gordon Road Bardon – dam now spilling – flash
flooding likely. Stay out of flood water
SMS – Twitter Text: {87 characters}
Gordon Road Bardon – dam now spilling – flash
flooding likely. Stay out of flood water
EA
Messaging
NA NA Voice Warning (Priority 1): {348 characters}
Emergency Emergency. This is a dam failure
warning from Queensland Fire and Emergency
Services. Gordon Road Detention Basin is at
imminent risk of failure. Move immediately to high
ground away from Gordon Road. You should warn
neighbours. For more information listen to local
radio or visit w w w dot Brisbane dot q l d dot gov
dot a u
SMS Warning (Priority 1): {157 characters}
Warning.GordonRoadDetentionBasin imminent
failure risk. Move immediately from GordonRoad
to high ground. Warn others. Radio or
www.brisbane.qld.gov.au
Note: The Standard Emergency Warning Signal (SEWS) will be activated when a priority 1 EA message is sent.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 48 of 71
8.0 Emergency Event Report (EER)
The dam owner is required to prepare an emergency event report (EER) and submit it to the chief executive
(dam safety regulator) within 30 business days (or another period agreed in writing with the chief executive)
at the conclusion of an emergency event which has resulted in the activation of the EAP, where:
• a person or property has been or may have been harmed because of the event; and
• any of the following applies -
(i) a coordinated response involving two or more relevant entities;
(ii) an event arose because of disaster situation declared under the Disaster Management Act;
(iii) an entity performing functions under the State Disaster Management Plan, required the dam
owner to provide information about the event,
An emergency event ends when the dam hazard that triggered the event, no longer presents a material risk
to persons or property.
The EER should provide a timeline of events, including monitoring and inspection data (rainfall, storage
level, seepage, etc.), which were used to make EAP activation decisions.
The EER should also outline responsibilities associated with emergency communications between the dam
owner, governments (local and state), disaster management groups (local and district) and the PAR and the
wider community (if relevant).
The EER should include photographs of the event.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 49 of 71
9.0 Dam Event Public Warning and Education Protocol
Figure 9 – Dam Event Public Warning and Notification Protocol
9.1 Public Education
Council’s Public Warning and Education Protocol (Figure 9) shows Council’s adopted protocol to ensure
regular community education programs are in place to keep the PAR fully aware of issues related to the
safety and management of the basin.
To facilitate public education, the following programs have been put in place:
• Signage will be erected in the area near Gordon Road Detention Basin to advise the PAR to contact
Council if they have any concerns about the dam;
• The PAR will receive a letter from Council on an annual basis advising them about the dam and
inviting them to subscribe to the Early Warning Alert service to receive alerts if the dam is at risk of
over topping;
• In the event that the dam is at risk of over topping an early warning alert message will be sent to
subscribers;
• In an extreme event (such as a 1 in 500 AEP rain event), a pre-worded Emergency Alert will be sent
to the PAR and people in the vicinity of the dam. See draft alerting polygon, Appendix A – Figure
A.5);
• The pre-prepared message and alert polygon will be saved at the State Disaster Management
Centre for use during an emergency event. A summary of the pre-worded alert messages is
included in Section 6.8 and summarised in Table 9.
9.2 Staff Training and Exercises
Regular joint exercises will be held involving Council officers and other authorities involved in implementing
the EAP to test and strengthen the EAP procedures described herein.
The EAP will reviewed and updated to incorporate learnings from the training and to reflect changes in best
management practices.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 50 of 71
APPENDIX A – Population at Risk and Inundation Mapping
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 51 of 71
Figure A1 – Gordon Road Bardon Detention Basin – Catchment Plan
Blank Page
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 52 of 71
Figure A2 – Gordon Road Bardon Detention Basin – Inundation for 1 in 50 AEP Dam Crest Flood Failure
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 53 of 71
Figure A3 – Gordon Road Bardon Detention Basin – Inundation Extent for 1 in 500 AEP Dam Crest Flood Failure
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 54 of 71
Figure A4 – Gordon Road Bardon Detention Basin – Inundation Extent for 1 in 34,800 AEP Dam Overtopping Flood with Structural Failure
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 55 of 71
Figure A5 – Gordon Road Bardon Detention Basin – Flood Depth in 1 in 34,800 AEP Dam Overtopping Flood Failure
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 56 of 71
Figure A6 – Gordon Road Bardon Detention Basin – Emergency Messaging Polygon
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 57 of 71
APPENDIX B – Summary of EAP Activation and Alert Triggers
77
76
75
74
73
72
71
70
Gordon Road Bardon - Detention Basin
Culvert sill level= 71.38 mAHD
Water level = above 72.6 mAHD
Water level= 75 mAHD - 1m below Basin crest
Lean Forward - Monitor water levels - Trigger-1 : Internal messaging
STANDUP -Trigger 2 - External messaging
Basin crest76.0 mAHD
Basin base= 70.5m AHD
Culvert outlet = 71.03 mAHD
Culvert obvert level = 72.58 mAHD
Water level = 76.35 mAHD - 350mm over Basin crest Trigger 3 - Emergency Actions- As in EAP
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 58 of 71
APPENDIX C – Contact Lists for PAR and Key Council Officers
Appendix C has been redacted
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 62 of 71
APPENDIX D – Modified Mercalli Earthquake Intensity Scale – Damage
Guide
Earthquake Magnitude
Typical Maximum Modified Mercalli Intensity
1.0 – 3.0 I
3.0 – 3.9 II – III
4.0 – 4.9 IV – V
5.0 – 5.9 VI – VII Prioritise repairs with resource availability but generally within 60 days.
6.0 – 6.9 VII – IX – URGENT REPAIRS May be needed to concrete structures around spillway pipes.
7.0 and higher VIII or higher
Abbreviated Modified Mercalli Intensity Scale
I Not felt except by a very few under especially favourable conditions.
II Felt only by a few persons at rest, especially on upper floors of buildings.
III Felt quite noticeably by persons indoors, especially on upper floors of buildings. Many people do not recognize it as an earthquake. Standing motor cars may rock slightly. Vibrations similar to the passing of a truck. Duration estimated.
IV Felt indoors by many, outdoors by few during the day. At night, some awakened. Dishes, windows, doors disturbed; walls make cracking sound. Sensation like heavy truck striking building. Standing motor cars rocked noticeably.
V Felt by nearly everyone; many awakened. Some dishes, windows broken. Unstable objects overturned. Pendulum clocks may stop.
VI Felt by all, many frightened. Some heavy furniture moved; a few instances of fallen plaster. Damage slight.
VII Damage negligible in buildings of good design and construction; slight to moderate in well-built ordinary structures; considerable damage in poorly built or badly designed structures; some chimneys broken.
VIII Damage slight in specially designed structures; considerable damage in ordinary substantial buildings with partial collapse. Damage great in poorly built structures. Fall of chimneys, factory stacks, columns, monuments, walls. Heavy furniture overturned.
IX Damage considerable in specially designed structures; well-designed frame structures thrown out of plumb. Damage great in substantial buildings, with partial collapse. Buildings shifted off foundations.
X Some well-built wooden structures destroyed; most masonry and frame structures destroyed with foundations. Rails bent.
XI Few, if any (masonry) structures remain standing. Bridges destroyed. Rails bent greatly.
XII Damage total. Lines of sight and level are distorted. Objects thrown into the air.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 63 of 71
APPENDIX E - Definitions/Glossary
Reference: https://www.dews.qld.gov.au/__data/assets/pdf_file/0018/84015/eap-guideline.pdf
The Act Water Supply (Safety and Reliability) Act 2008
(EAP) Activation
Is defined as actions undertaken by the dam owner as per the EAP in response to a dam
event if:
1. persons or property may be harmed, because of the event
2. a coordinated response involving two or more of the following relevant entities is likely
to be required to respond to the event:
• each local group (LDMG) and district group (DDMG) for the emergency action plan
• each local government whose local government area may be affected if a dam
hazard event or emergency event were to happen for the dam
• the DNRME chief executive
• another entity the dam owner considers appropriate i.e. QPS, QFES.
Alert
The first stage of emergency response whereby a heightened level of vigilance is maintained
due to the possibility of an emergency event occurring. Action is required to ensure the
situation is monitored by someone capable of assessing the potential of the threat.
Approved emergency
action plan
An emergency action plan that is approved under s 352I(1)(a) or taken to be an approved
emergency action plan under s 352Q(2).
(Refer s 352A of the Act.)
Approval period (for
an EAP)
The period of approval for the EAP can be for a period of no more than five years and must
be stated in the approved EAP (refer s 352K(2)).
Chief Executive
In this guideline, unless otherwise specifically given a different meaning, references to the
‘chief executive’ or the Dam Safety Regulator are to be interpreted as references to the
Director-General of the Department of Natural Resources, Mines and Energy or the Director-
General’s delegate.
Correspondence to the Director-General’s delegate can be sent to:
Chief Executive
Department of Natural Resources, Mines and Energy
Water Supply Division
PO Box 15216, City East QLD 4002
or via email to: [email protected]
Controlled document Having an EAP issued as a ‘controlled document’ means that specified copies of a document
are kept up to date in a controlled manner using a system that distributes updated
versions/pages of the document as they are issued and retrieves superseded versions/pages
of the document as they become redundant. In this way, only the current version of the
document is used during any event.
A controlled document requires the following metadata to be recorded in the document and
securely archived:
• contents, versions and dates of versions
• name and role of the person approving each version and details of any prior
consultation undertaken
• names and roles of persons issued with copies.
Dam hazard Dam hazard, for a dam, means a reasonably foreseeable situation or condition that may:
a) cause or contribute to the failure of the dam, if the failure may cause harm to
persons or property
or
b) require an automatic or controlled release of water from the dam, if the release of
the water may cause harm to persons or property.
(Refer s 352A of the Act.)
Dam hazard event An event arising from a dam hazard if persons or property may be harmed because of the
event and
a) a coordinated response involving 2 or more of the relevant entities
b) mentioned in paragraphs (b) to (d) of the definition relevant entity is unlikely to be
required to respond to the event
c) the event is not an emergency event.
(Refer s 352A of the Act.)
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 64 of 71
Dam Safety Team Group of engineers and professionals working in the administering state government agency
District group
DDMG
District disaster
management group
The district group for an emergency action plan, means a district group established under the
Disaster Management Act 2003 (DM Act), s 22 whose disaster district under that Act could,
under the plan, be affected by a dam hazard.
District disaster management group/s established under the DM Act, comprise
representatives from regionally based Queensland Government agencies, which provide and
coordinate whole-of-government support and resource gap assistance to disaster-stricken
communities. The district group/s perform a 'middle management' function within the disaster
management arrangements by coordinating the provision of functional agency resources
when requested by local group/s on behalf of local government/s.
Disaster management
plan (DMP)
A local or District Disaster Management Group’s disaster management plan under the DM
Act.
Disaster risk
assessment
The process used to determine risk management priorities by evaluating and comparing the
level of risk against predetermined standards, target risk levels or other criteria (Council of
Australian Governments (COAG), Natural Disasters in Australia: Reforming mitigation, relief
and recovery arrangements: 2002).
Incorporates the processes of risk identification, risk analysis and risk evaluation (refer to ISO
Guide 73:2009 Risk management - Vocabulary).
Dam Safety Regulator
(DSR)
Refer to the ‘chief executive’ above.
Emergency alert
(EA)
The emergency alert (EA) system is a national telephone warning system administered in
Queensland by the Queensland Fire and Emergency Service.
The EA system provides emergency authorities with a rapid mass notification service to
deliver preformatted messages via landline and mobile telephones within a defined
geographic area.
Emergency
event
An event arising from a dam hazard if persons or property may be harmed because of the
event, and any of the following apply:
i. A coordinated response where two or more of the relevant entities, mentioned in
paragraphs (b) to (d) of the definition relevant entity, are likely to be required to
respond to the event.
ii. The event may arise because of a disaster situation declared under the DM Act.
iii. An entity performing functions under the State disaster management plan may,
under that plan, require the owner of the dam to give the entity information about
the event.
(Refer s 352A of the Act)
Emergency event
interim report
An interim report on the performance of the dam and the functioning of the EAP during an
emergency event, which is submitted to the chief executive prior to the end of the event at the
request of the chief executive.
(Refer s 352U(2)(a) of the Act)
Emergency event
report (EER)
A report on the performance of the dam and the functioning of the EAP during an emergency
event, which is presented to the chief executive following the end of the event.
(‘End’ of an emergency event means when the dam hazard giving rise to the event is no
longer a risk to persons or property.)
(Refer s 352T(2) of the Act)
Failure (of a referable
dam)
Means — (a) the physical collapse of all or part of the dam; or (b) the uncontrolled release of
any of the dam’s contents.
Failure impact
assessment
(FIA)
It is a process used under the Act to determine the number of people whose safety could be
at risk should the dam fail.
The FIA must be certified by a Registered Professional Engineer Queensland (RPEQ) in
accordance with the Act.
Failure impact rating
(FIR)
A failure impact rating is a measure of the population at risk should the dam fail. There are
two categories for referable dams:
• category 1: 2 to 100 people at risk if the dam were to fail;
• category 2: more than 100 people at risk if the dam were to fail.
Flood mitigation
manual
A manual of the operational procedures for flood mitigation for a dam that complies with s
371D of the Water Supply (Safety and Reliability) Act 2008
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 65 of 71
Hazard A source of potential harm, or a situation with a potential to cause loss (Emergency
Management Australia, 2004).
Lean forward The stage of emergency response prior to ‘stand-up’ whereby a heightened level of
situational awareness of a disaster event (either current or impending) is maintained and a
state of operational readiness is developed. Personnel at dam are on standby, ready to
activate the EAP.
Local disaster
coordinator
An officer appointed under the DM Act who is responsible for the coordination of disaster
operations for the local disaster management group.
Local disaster
management group
Local disaster management groups are established to support local government disaster
management activities. The local group is supported by the relevant district group if and when
disaster management activities exceed the capacity of a local group. The functions of the
local group include (but are not limited to):
• developing, regularly reviewing and assessing effective disaster management
• assisting local government for its area to prepare a local disaster management
plan
• ensuring the community is aware of ways of mitigating the adverse effects of an
event, and preparing for, responding to and recovery from a disaster
• identifying and coordinating the use of resources that may be used for disaster
operations
• managing disaster operations in the area under policies and procedures decided
by the State group
• ensuring disaster management and disaster operations in the area are
consistent with the State group’s strategic policy framework for disaster
management for the State.
Notice A statement provided to the dam owner from the local government and/or the disaster
management group on the outcomes of the assessment and review of the EAP.
Notice response A statement of reply from the dam owner to the local government and/or disaster
management group on the information provided within the notice of assessment.
Early warning
notification system
Non-government, commercial subscription based warning/alert system that provides SMS,
landline, email, and social media alert messages. Members of the public are required to
register to receive the notification service.
Population at risk
(PAR)
The number of people calculated under the failure impact assessment guideline, whose
safety will be at risk if the dam, or the proposed dam after its construction, fails. For the
purposes of this EAP, PAR is the total population at risk if a dam failure event was to occur,
including transient populations as well as those at residences and businesses.
Probable maximum
precipitation (PMP)
The theoretical greatest depth of precipitation for a given duration that is physically possible
over a particular drainage basin.
Probable maximum
flood (PMF)
The flood resulting from PMP, snowmelt, coupled with the worst flood-producing catchment
conditions that can be realistically expected in the prevailing meteorological conditions.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 66 of 71
APPENDIX F – DNRME License Conditions
The following conditions were issued by DNRME and are attached to the licence for the dam:
Condition DS 1 - Documentation
1. Any documentation prepared in order to comply with these conditions must be stored securely until
such time as the dam is decommissioned.
2. The documentation must be made available to Dam Safety Regulator for inspection within five (5)
business days of a written request for access being received by the dam owner.
3. On change of ownership of the dam, these conditions and all documentation prepared and stored
in compliance with these conditions must be transferred to the new owner.
Condition DS 2 - Incidents and Failures
1. In addition to the requirements detailed within the approved Emergency Action Plan (EAP), the dam
owner must report all incidents and failures as defined in the Queensland Dam Safety Management
Guidelines to the Dam Safety Regulator within two (2) calendar days of becoming aware of the
incident.
2. The Dam Owner must provide a report on the incident including any remedial actions to the Dam
Safety Regulator within twenty (20) business days of the incident or failure.
Condition DS 3 - Design
1. Design Report/s and any identified design and construction documentation must be referenced in the
Data Book.
Condition DS 4 - Construction
1. Any construction works must be carried out in accordance with current engineering best practice to
ensure that the dam remains generally in accordance with the documentation included in the Data
Book.
2. Proposed construction works require a design report to be submitted to the Dam Safety Regulator
at least twenty (20) business days before the commencement of construction works.
Condition DS 5 - As Constructed
1. All construction works must produce as-constructed drawings certified by a Registered Professional
Engineer (RPEQ) for inclusion in the Data Book in accordance with the Dam Safety Management
Guidelines.
2. These drawings must be provided to dam safety regulator within sixty (60) business days of practical
completion of construction of the dam.
Condition DS6 - Spillway Adequacy
N/A
Condition DS 7 - Data Book
1. The dam owner must prepare a data book within sixty (60) business days of practical completion of
construction of the dam.
2. The dam owner must maintain a data book in accordance with the current published version of the
Queensland Dam Safety Management Guidelines.
3. The data book must be reviewed and if necessary updated each calendar year. A written notification
confirming that the Data Book has been reviewed and if necessary updated must be submitted to
the dam safety regulator by 1 July each calendar year thereafter.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 67 of 71
Condition DS 8 - Standing Operating Procedures (SOPs)
1. The dam owner must prepare standing operating procedures (SOPs) within sixty (60) business days
of practical completion of construction of the dam.
2. The Dam Owner must maintain SOPs in accordance with the current published version of the
Queensland Dam Safety Management Guidelines.
3. The dam owner must ensure the SOPs are reviewed and if necessary updated each calendar year.
A written notification confirming that SOPs have been reviewed and if necessary updated must be
submitted to the dam safety regulator by 1 July of each calendar year thereafter.
Condition DS 9 - Detailed Operating and Maintenance Manual (DOMM)
1. The dam owner must prepare detailed operation and maintenance manual within sixty (60) business
days of practical completion of construction of the dam.
2. The dam owner must maintain detailed operation and maintenance manuals in accordance with the
current published version of the Queensland Dam Safety Management Guidelines.
3. The dam owner must ensure the manuals are reviewed and if necessary updated each calendar year.
A written notification confirming that the manuals have been reviewed and if necessary updated must
be submitted to the dam safety regulator by 1 July each calendar year thereafter.
Condition DS 10 - Periodic Inspections
Not applicable.
Condition DS 11 - Comprehensive Inspections
1. The dam owner must carry out a comprehensive inspection of the dam in accordance with the
current published version of the Queensland Dam Safety Management Guidelines. The inspection
is due on or before 25 January 2023.
2. The dam safety regulator must be advised in writing at least five (5) business days prior to the date
of the inspection and may elect to observe any or all procedures involved in the inspection process.
3. A Comprehensive Inspection Report must be submitted to the dam safety regulator within sixty (60)
business days after completion of the inspection.
4. Further comprehensive inspections are to be carried out at five (5) year intervals. When a
comprehensive inspection falls in the same year that a safety review is required, this inspection
shall be undertaken as part of the safety review.
Condition DS 12 - Safety Review
1. The dam owner must carry out a safety review in accordance with the current published version of
the Queensland Dam Safety Management Guidelines. The safety review is due on or before 25
January 2038.
2. The dam safety regulator must be advised in writing at least five (5) business days prior to the date
of inspection and may elect to observe any or all procedures undertaken in the inspection process.
3. A Safety Review Report must be submitted to the dam safety regulator within sixty (60) business
days after completion of the review.
4. Further safety reviews are to be carried out at twenty (20) year intervals, but may be required by
the dam safety regulator at more regular intervals.
Condition DS 13 - Special Inspections
1. When directed by the dam safety regulator, a special inspection must be carried out in accordance
with the current published version of the Queensland Dam Safety Management Guidelines. The
cost of this inspection is the responsibility of the dam owner.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 68 of 71
Condition DS 14 - Decommissioning
1. The dam must not be taken out of service (decommissioned) without a decommissioning plan that
has been prepared in accordance with the current published version of the Queensland Dam Safety
Management Guidelines and accepted by the dam safety regulator.
2. Following acceptance of the plan, the dam safety regulator must be advised within twenty (20)
business days of completion of the decommissioning.
Definitions
AFC’—acceptable flood capacity—the overall flood discharge capacity required of a dam determined in
accordance with these guidelines including freeboard as relevant, which is required to pass the critical
duration storm event without causing failure of the dam.
‘Dam’ means:
(a) works that include a barrier, whether permanent or temporary, that does or could impound water; and
(b) the storage area created by the works.
(c) an embankment or other structure that controls the flow of water and is incidental to works mentioned in
item (1)(a).
‘Dam Safety Regulator’ is the chief executive, or their delegate, of the Department or Agency administering the Water Supply (Safety and Reliability) Act 2008 or, if that Act is repealed, such later legislation as addresses dam safety.
‘FSL’ - for a dam, means the level of the water surface of the dam when the water storage is at maximum
operating level and the dam is not affected by flood.
‘Owner of a dam’ is the owner of land on which the referable dam is constructed, or is to be constructed.
‘PAR’ is the number of persons, calculated using FIA guidelines, whose safety will be at risk if the dam, or
the proposed dam after its construction, fails. Persons are considered to be at risk if they are within the
failure impact zone.
‘Practical completion of construction’. For the purpose of these conditions, the dam construction shall reach the stage of “practical completion of construction” when:
1. the dam embankment is capable of storage to full capacity; and 2. the inlet/outlet works are operational (minor components may not necessarily be installed).
‘Registered Professional Engineer of Queensland’: A professional engineer registered under the Professional Engineers Act 2002 in Queensland.
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 69 of 71
APPENDIX G – DRAWINGS - Gordon Road Bardon Detention Basin – General Layout
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 70 of 71
Gordon Road Bardon Detention Basin – Embankment Sections
CA18/164487 Gordon Road Bardon Detention Basin Emergency Action Plan Page 71 of 71
APPENDIX H – Reference Documents
The following list of all design documents, as constructed plans, Failure Impact Statement and other
reference documents will be included in the Dam Data Book.
Design & Flood Modelling:
G:\BI\CD\Proj11\110209_Gordon_Rd_Relief_Drainage\FloodManagement\Calculations\Hydrology\WBNM
\CW_Enquiry
G:\BI\CD\Proj11\110209_Gordon_Rd_Relief_Drainage\cad\3-received\from-ARUP\20150615-GRDB
Preliminary Design Report 15 June 2015A\ GRDB_Preliminary Design Report_15June15 DAS.pdf
CA16/484711 DGE - Report - Detailed Design Appendix D Failure Impact Assessment - GRBDB_FIA
CA18/69146 DGE - GRDB - Impact of amended culvert levels - ARUP Response 23 Jan 2018
Development Permit:
CA17/607889 PLN - Approval - DA - Development Permit for Operational Work (Referable Dam) - Gordon
Road Referable Dam - 7 July 2017
CA17/459418 : DGE - Letter - Gordon Rd Detention Basin - DEWS Notice
Asset Management Plan
CA16/484554 DGE - Report - Asset Maintenance Management Plan GRBDB_AMMP
As-Constructed Drawings:
CA18/185680 Construction - Civil - North - Sch 72 - Detention Basin Gordon Road Drawings - As
Con_Form 16_Geotech & Structural Engineers Cert - 28 Feb 2018
CA18/59734 Construction - Civil - North - Sch 72 - Detention Basin Gordon Road QA - Lots Confirming
Doval 22 Jan 2018
B17065-LTR-S-0001.pdf (not registered in RM) – RPEQ Structural Certification of Construction Works –
email attachment from Chris Wilson 26/02/2018
Mapping:
G:\BI\CD\Proj18\180614_Gordon_Rd_Detention_Basin\ArcGIS\Gordon_Rd_Detention_Basin_Map_Dam_
Crest.pdf
G:\BI\CD\Proj18\180614_Gordon_Rd_Detention_Basin\ArcGIS\Gordon_Rd_Basin_50yr_60m_Dam_Brea
k_S1.pdf
G:\BI\CD\Proj18\180614_Gordon_Rd_Detention_Basin\ArcGIS\Gordon_Rd_Detention_Basin_Maps_Q34
800_S1.pdf
Draft EAP