Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Supcrlund Records Center S i l t : £)'"2i!»«H n.*t
G'lhbK:
EMCAG Meeting
August 22, 2001
EE/CA Preview
And
Site Update
Objectives for Aug EMCAG Meeting
• Present overview of EE/CA o Schedule o Cleanup Options Summary o Format o Highlight key issues
• Regulations that will impact cleanup
• TP 3 preservation • Notification of Impacts to
Wetlands, Floodplains, and Historic Properties
• Truck Traffic
• Site Status o Recent TP 3 assessment o Residential well sampling o Fish and surface water/sediment
sampling o RI/FS Work Plan o(NHPA) 106 process
Schedule for the Engineering Evaluation and Cost Analysis (EE/CA)
• EE/CA is currently under internal review and editing
• Expect to release draft EE/CA to EMCAG for comment by end of September 2001
• Request comments within 30 days, October EMCAG
• Final EE/CA by end of November 2001
Proposed Plan release and 30 day comment period either December 2001 or January 2002
Cleanup Option Summary
All cleanup options include these baseline items:
• Preservation of a portion of TP3 (up to 100%, exact amount to be determined)
• Diversion of surface water away from TP1 and TP2 • Collection of storm water runoff and drainage from TP3 and
treatment with passive systems • Collection of drainage from toe of TP1 and treatment with passive
systems • Stabilization of the steep slope areas of TP1 and TP2 and
backfilling/stabilization of decant pipe
Cleanup Option 2B (multi-barrier cap)
• Consolidation of TP2 into the footprint of TP1 • Re-shaping the slope of TP1 to reduce "steepness" and increase
stability • Placement of an infiltration barrier (double barrier cap) over
consolidated TP1 • Placement of soil and drainage layer to protect the infiltration
barrier and promote vegetation (grass)
Cleanup Option 2C (multi-barrier cap)
• Placement of a reinforcing material on the steep slopes of TP1 and TP2 to maintain the current profile (rip rap, gabions, or concrete)
• Consolidation of a small portion of TP-2 onto TP-1 • Minor re-shaping of TP-1 and TP-2 • Placement of an infiltration barrier (double barrier cap - as in 2B)
overTPl andTP2 • Placement of soil and drainage layer to protect the infiltration
barrier and promote vegetation (grass)
Cleanup Option Summary
Cleanup Option 3B (42 inch ET soil cover)
• Placement of a reinforcing material on the steep slopes of TP1 and TP2 to maintain the current profile (rip rap, gabions, or concrete)
• Consolidation of a small portion of TP-2 onto TP-1 • Minor re-shaping of TP-1 /TP-2 • Placement of a 42 inch thick soil cover over TP1 and TP2 that will
reduce infiltration due to evaporation and plant use (not an infiltration barrier)
Cleanup Option 3C (minimal soil coven 6 inches)
• Placement of a reinforcing material on the steep slopes of TP1 and TP2 to maintain the current profile (rip rap, gabions, or concrete)
• Consolidation of a small portion of TP-2 onto TP-1 • Minor re-shaping of TP-1 /TP-2 • Placement of the least amount of soil over the surface ofTPl and
TP2 that will support long-termvegetation* assumed to be 6 inches (not an infiltration barrier)
Cleanup Option 3D (hardpan barrier layer)
• Placement of a reinforcing material on the steep slopes of TP1 and TP2 to maintain the current profile (rip rap, gabions, or concrete)
• Consolidation of a small portion of TP-2 onto TP-1 • Minor re-shaping of TP-1 /TP-2 • Placement of lime and/or crushed limestone into the tailings to
form a chemical cap to encapsulate areas of TP1 and TP2 • Placement of 18 inches of soil to promote a long-term vegetative
cover • Placement of a drainage net beneath the soil to prevent ponding of
water above the "induced" hardpan
c o o a:
o IO CO
. IO CO
•Tto CD
•fl10 CD
o o o
£
to 0_
0
CM
CD CM
CM
CD CM
^ CD CD LO
OO CO
CM CM CO 0 T—
CO
c g "a. O
0
S CO
T
00$ co co CM
oo CD CM f*^ O
co oo co en a> '
OO
8 CO CO CM
£ CM CO t>~
10
o> to CD
CO CM CO co co CM
co o co CD o CD
§ CM to OO
oo CM co CO co CM
T—
CO ao o T~
CD
CM O to
co
CO CO CM
S CO IO CO
to V* V* t* **
W <* ** tO to to to to to to
CD CM
o s
CD ao
CD
$
co oo co
CD 00
CM
00
to 03
CD CO
•t CO oo
CD co
IO r-CM
CO f^CO
CD CO
to to CO
"CD C .g "a.
co -a
ao o co
CM CO CD
OO O co
O co
toh-CD
CO o co
oo CD
CM to ao
00 o co
CD CM O to
oo o CO
o oo
— CDin £
O to to tO
<* <& V* <* CA- to to «0
*~ <* V* to to
D. 0 CO ^"
0
o> co £P CM
co ^
n eo<*>
CO o CM
en eo 10
IO ^«en
co o CM
TCO
CO eo
co CM
CM
on CD CO eo
CO 0 CM
CM
IO t
O COtr Q.
c
Q.
O
<*>h
~ ^™
•to
eo en eo
<»
en en
„
^ Sr
<»
n CM en
if*
IO r-co
-
*CM
to
o o
^
CM IO eo
»
^f
™
to
CO
~
CM s ~
CM
to
CD CM CO
«0
QL co QL1- 11-
d.i- a.1— 1
QLH
co a. K 1 H
QL 1-
co QLK1 K
QLK
co QL K
"5\
CD CD 00 CM
2 JO
CO
c .g a. O
CO 10" CO
^
CD CD o" co
co" T—
s 10"
CM"
0 ^_r CO
o"
CD T— CN CD CM"
m oO
Q.
"o Q ^~ O CD CM i
«•«
O O
CM C .g ^vL^
O
o 10_ fs^
CD o" £
0 IO CM co" s CM" s
CM IO v
co 10 CD_ i
**
to T— CD to r-co CD" to
to CM CD co" CO
CM" v~
< a. CM"
T3
Q
1 a. C0 O
"ms 'o. c^ ^™
c o !S
O
eo IO en* o CM at it*
i IO o I0_ T"
<f>
n ^^ ^fTCM
O
**
CO eof CM
°l •-•"
40
« CO, irT a> CO CD" to
QL
S o a. 2=
!i t <D > O
(3D > CC CCQ O *o. :> S X <B
CO 3 3 _j uu D: C t 3 ffl 0 CD O Q •»- CM" co co F CM CM CO co CO
E 5 3 oJ * < O Q- Q. Q(O z o o o
Format of the EE/CA
• EE/CA is an official EPA regulatory document developed to allow for public comment regarding development of the cleanup action for a non-time-critical removal action (NTCRA)
• Specific format and content is required for EE/CA
The EE/CA is a key document in the administrative record and basis for any legal reviews
Less user-friendly for general public than Alternatives Analysis Report (AAR)
Format of the EE/CA
Content of the EE/CA
• Chapter 1: Introduction o Summarizes purpose of
document
o Summarizes site characteristics and extent of contamination (Site Conditions Report, February 2001)
o Presents risk basis for NTCRA (Summary of Preliminary Ecological and Human Health Risk Evaluations, July 2001)
Format of the EE/CA
Chapter 2: Removal Action (NTCRA) Scope and Objectives
o Statutory limits/exemptions
o NTCRA justification
o NTCRA objectives
o Applicable or Relevant and Appropriate Requirements (ARARs)
• Legal requirements for action • Only specified for on-site
portion of cleanup • ARARs can be waived under
certain conditions
Format of the EE/CA
Chapter 3: Development of Removal Action Alternatives
o Statutory and Policy Considerations
o Assessment of Response Actions and Descriptions of Alternatives (similar to AAR, outcome is consensus cleanup alternatives identified through EMCAG comments on AAR)
10
Chapter 4: Analysis of Removal Action Alternatives
o EE/CA evaluation criteria are Effectiveness, Implementability, and Cost
o Effectiveness includes: • Overall protection of human health and
the environment • Compliance with ARARs and other
criteria • Long-term effectiveness • Reduction in toxicity, mobility, or
volume of contaminants through treatment
o Implementability includes: • Technical feasibility • Administrative feasibility • Availability of services and materials • State and Community Acceptance
o Cost • Capital • Post-Removal Site Control (operation
and maintenance)
Format of the EE/C
Chapter 5: Comparative Analysis of Removal Action Alternatives
• Compares the five cleanup alternatives in terms of effectiveness, implementability, and cost
• Provides the setting for EPA identification of a preferred option in Proposed Plan (issued with final EE/CA)
• EE/CA will not include a recommended option; that will be in the Proposed Plan
12
Key Issues in EE/CA
Several key issues have been identified to date:
• Certain regulations will control the acceptability and design of the cleanup alternatives
o National Historic Preservation Act (NHPA)
• Requires EPA to avoid impact, if possible, and minimize adverse effects if not
• Mitigation of adverse effects to be detailed in MOA
• Human health and environmental risks are basis for adverse effect
• Alternatives will comply with NHPA
13
Key Issues in EE/CA
o EPA and Vermont surface water discharge regulations (NPDES)
• Any discharge from the passive treatment systems must meet VTWQS (numerical) and EPA ambient water quality criteria at point of compliance (Copperas Brook)
• Passive systems will be designed to meet this requirement
14
Key Issues in EE/CA
o EPA and Vermont Wetlands and Floodplain Regulations
• There will be impacts to wetlands and floodplains within the area from the North Cut to just below TP 1
• These impacts are unavoidable
• Passive treatment systems and channel design will mitigate these impacts
• Additional mitigation may be necessary
15
Key Issues in EE/CA
o VT Solid Waste Regulations (may apply since mining waste is included in scope of regulations, however, mining waste is also subject to an exemption)
• Design requirements for closure specified in regulations
• Cover over waste material • Grading requirements (5%) • Certain cover designs
• TP 3 will not meet these requirements, if applicable
• Closure grade is also an issue for all cleanup alternatives (truck traffic for additional fill)
• Cover design for Cleanup Alternative 3C does not meet the cover requirements
• Cover design for Cleanup Alternative 3D may not meet these requirements
16
Key Issues in EE/CA
TP 3 Preservation o All of TP 3 will be preserved unless:
• design investigations reveal that slopes are unstable or some material represents human health threat; or
• VTANR will not accept maintenance responsibility
o Three preservation options will be presented in EE/CA
o All of run-off from TP 3 will be collected and treated in passive treatment systems
o VTANR acceptance of TP 3 is conditioned upon further review of cost information
o SHPO opinion will also be requested with respect to TP 3 preservation
17
Truck Traffic o Estimated truck counts and potential
traffic routes will be presented in EE/CA
o Truck routes and numbers will not be known until contract is awarded and all design and road issues are resolved
o Design will focus on finding on-site or nearby sources of construction materials, such as topsoil and common borrow
18
Update of Site Status
Sampling
o Residential well sampling will re-start September
o Monthly for remainder of year
o Fish sampling and additional fish abundance surveys to be performed by EPA and ANR in early September 2001
o Surface water and sediment sampling will occur with fish sampling
19
Update of Site Status
Remedial Investigation and Feasibility Study (RI/FS) Work Plan is being completed
o RI/FS Work Plan should be ready for EMCAG review in October 2001
NHPA 106 process o EPA is ready to begin consultation
meetings to discuss mitigation of potential adverse effect
o May be best to wait until future land use issues are better defined
o MOA needs to be completed soon after Action Memorandum (February 2002)
o EMCAG input requested
20
Update of Site Status
Recent (8/10/2001) TP 3 Assessment o A recent site visit was conducted to
gain a better understanding of TP 3 o New map has been developed based
on this visit o Map will be included in EE/CA
21
TP-3 Mapping and Assessment
TP-3 was examined in detail to develop a better understanding of the remaining historic features and the nature of environmental issues
Reconnaissance Activities:
• Historic features located and identified • Sequence of events/deposits • Copperas vs. copper production wastes • Environmental concerns identified • Acid-generation potential, as a function of
sulfide concentrations
22
TP-3 Mapping and Assessment (cont)
Initial Conclusions:
Historic features include: • Copperas production remains from early to
mid/late 1800's: -"Heap leach" piles -Stone foundations -Wooden structures — copperas liquor holding pond and troughs?
• Later (1880's and 1890's) copper production remains (from Tyson operations):
-Shafts and manway -Waste sulfide piles superimposed over Copperas works -"Upper" adit -"Cobbing" shed
23
TP-3 Mapping and Assessment (cont)
Environmental/Design Assessment:
• Portions of TP-3 contain high concentrations of "fresh" metal sulfides (pyrrhotite and chalcopyrite)
• The sulfide minerals are actively decaying through oxidation at the ground surface, releasing metals and generating acid-conditions in the runoff water
• Secondary "salts" of iron and copper sulfate form routinely during summer months - significant contribution to metals loading and acid generation
• Copperas leach piles lack fresh sulfides, but still contain some metals and acid-generation-potential
• Greatest acid-generation-potential is from hand-cobbed ore/waste located in upper portion of TP-3
• Low acid-generation-potential rock remains in southern and northern portions of TP-3
Design Data Needs: Detailed sampling over entire TP-3 area to map and quantify acid generation and metals contribution potential
24
o o .a
Figure 1-1 - Location Map - Elizabeth Mine, South Stratford, VT Ito
CDCD
o o o
o o o uf
o —'
Figure ES-1 Site Location Map and Extent of Contamination
o oFigure 1-20 - Lines of Evidence of Ecological Impacts,
Elizabeth Mine, South Stratford, VT
w s
JS D- at n> 5 3 & 3 LU <U W 5 CO TO W
J l l Q D B
o —'
60m
Elizabeth Mine and Vicinity One-Half Meter Topographic Contours
1ripnds Incc'or.
60m
Elizabeth Mine and Vicinity One-Half Meter Topographic Contours
|- ] L
Originals in color.
w C5
=r.
I33ft ll':; .iV V'*"$&£•«;
.•i'l'ii*.
Jl'ii'-Mw'.'ij.•t*Lr'. X'i'.
cro
5' o
en r
2.o"
o i -o-s r - * IS. i~r 2S *
0)
"c o o
o o cc
O ^ in CD
m CO
•* in CO
^i in CO
CD CM
i CO
I
u
1—
CO CL
" CM
en CM
CNJ
en CM
o en
T—
inff\ CU CO
CM CM CD O
CL CJ5 if)
CO c o "o. O
o £ CO
•"3"
te
oo CM CO CO CO CM
«>
CO CO CM fS.
o
«*
co CO CO en en
<»
CO
CO CO CM
te
jr; CM CO N
<«•
m en in CO
<&
CO
CO CO CM
te-
CO o CO en o en
<*
CO s CMin co
w
00 CM CO CO CO CM
W
T— CD co CD ^
w-
I CM O
*»
CO
CO CO CM
<»
en CD in CO
<e
§
CD
>
CD CO
£CL o CO
0 CO oc CL
CM
.0 a. O
T_
.0
Q.O
o en CO
••3
«9
O
CO
•"3
^
en CO ••3-
§CO
if>
CO
CM J"
^
en CM
CM co
**
T™
co en oo
~
CO CO CO
1
te-
CO CO CO en
^
^
en CO
§CO
«3
CO o CM
CM
^
^
CM
CO
O co
*&
o> coin CO
en
^
te en S CO
«>
in en in CD
<»
COi co o CO
<e-
CD 0 CM
CM ••3
«
co
00 en
** T"
00
o o
»
CO CO
CMin CO
««•
CD
CMin co
«»
en 00••a
§CO
•e/>
CO o CM
CM
^
«»
in CM
CO
T—
•ee-
CM en en COt-. CM
«
1 0in
<»
CO
CM Oin
«»
en co
§CO
«e-
CD o CM ••a-CM
«»
inin co o co
«»
in CD CM en
«»
T—1
CL 1-
co CLh
_ "Q
1-CL 1-
co a.i
_
"o1Q.h-
CO CL 1-
"co o QL
1
CO CL H
1_L
^ H
CL CO CL1
~m o
CO
J2
CO c .0 a. 0
cn
in" CO _.
T-
cn en en o CO 1 * CO
00
00 m" "*** CM
CM
O_
CO T
O
1 CVJ
CM"
(0 « o o o (0DC Q.•o CO
a. CO O "5 CO
CO
0 o CM
«-• CO 0 O "co 'Q. co O
Q.*3 » C C
S' _ {
CM C o "5. O
° c _o "5. O
P> \ >
O
r-CD o" <»
CO
55 O)CO CM en"
COCM
oin CM co" en CM" •5
co o •r-
m" o
Z
O CM
CMin co"in T-
«•
( CO
f T—CM o"
m CO
m en in" CO en" €«•
CD CO
CM" en t--"
O CO
in CM en co" CO
CM" •w-
CO
co in" en CD_
5
QCO
«d.
CO
CL s0 tB CL =:
•S I
^ I §CD > O> (0 C as o £ m x IP _j UJ DC » CM «
§ c c o o
ts :? •? Q. Q. Q. O O O