Federal Energy Regulatory CommissionDocket Sheet
Docket P-2808 (ALL Subdockets)Applicant(s)/Docket:KEI (Maine) Power Management (III) LLC
Sub Docket: 000
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (USA) Power Management Inc.
Filed Date: 1/23/2013
Accession No: 20130123-5046
Description: Submission to NYRO of KEI (USA) Power Management Inc. 2012 Minimum Flow Requirement Letter under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/1/2013
Accession No: 20130301-5312
Description: Submission to NYRO of KEI (USA) Power Management Inc. 2011 DSSMR Submittals under P-3562, et. al..,
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/1/2013
Accession No: 20130301-5313
Description: Submission to NYRO of KEI (USA) Power Management Inc. 2011 DSSMR Submittals under P-3562, et. al..,
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/1/2013
Accession No: 20130301-5328
Description: Submission to NYRO of KEI (USA) Power Management Inc. 2012 DSSMR Submittals under P-2808, et. al..,
Source: eLibrary
Page 1 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/1/2013
Accession No: 20130301-5329
Description: Submission to NYRO of KEI (USA) Power Management Inc. 2012 DSSMR Submittals under P-2808, et. al..,
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 9/25/2013
Accession No: 20130925-3027
Description: Letter to KEI (Maine) Power Management (III), LLC providing advance notice of license expiration re the Lower Barker Mill Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 10/22/2013
Accession No: 20131022-5026
Description: Submission to NYRO of KEI (USA) Power Management Inc. Acknowledgement of Receipt of Annual Letter under P-2808 et. al.,
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 1/2/2014
Accession No: 20140102-3026
Description: Letter to KEI (Maine) Power Management (III), LLC responding to their request for an exemption from filing the FERC Form No. 80, filed on 4/25/11, for the Lower Barker Mill Hydro Project under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 1/2/2014
Accession No: 20140102-3075
Description: Letter to Mr. Jean Roy re the Revised Form 80 for the Barker's Mill Hydroelectric Project under P-2808.
Source: eLibrary
Page 2 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 1/12/2014
Accession No: 20150202-0202
Description: Letter order accepting KEI (USA) Power Management Inc. request for an extension of time to provide flashboard designs and details of flashboard trips in the past 5 years for the Upper and Lower Barker Dams Project under P-2808 et al.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 2/21/2014
Accession No: 20140221-5061
Description: Supplemental Information / Request of KEI (Maine) Power Management (III) LLC under P-2808. Cover Letter to FERC re Newspaper Notice for PAD.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/12/2014
Accession No: 20140312-5135
Description: Request of KEI (USA) Power Management Inc. under P-2808, et. al.., Extension of Time Request to submit 2013 DSSMRs
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 4/30/2014
Accession No: 20140430-5437
Description: KEI (Maine) Power Management (III) LLC JAM FERC Cover Letter and Notice under P-2808
Source: eLibrary
Filed By: American Whitewater
Filed Date: 7/3/2014
Accession No: 20140703-5071
Description: Comment of American Whitewater on the PAD and Study Requests for the Lower Barker Project on the Little Androscoggin River (FERC No. P-2808).
Source: eLibrary
Page 3 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 7/10/2014
Accession No: 20140710-5053
Description: National Marine Fisheries Service's Comments and Study Requests for the Lower Barkers PAD and Study Request comment letter under P-2808.
Source: eLibrary
Filed By: Kleinschmidt Associates
Filed Date: 7/23/2014
Accession No: 20140723-5129
Description: Lower Barker Joint Agency Meeting Transcript under P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 7/25/2014
Accession No: 20140818-0184
Description: Letter requesting KEI (USA) Power Management Inc to provide a plan and schedule to address the comments w/in 30 days re the Dam Safety Inspection for the Barker Mill Lower Project et al under P-2808 et al.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 10/1/2014
Accession No: 20141015-0271
Description: Letter order accepting KEI (USA) Power Management Inc's 5/15/14 filing of the Dam Safety Surveillance & Monitoring Reports for the Barker Mill Lower Project under P-2808 et al.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 10/8/2014
Accession No: 20141017-0182
Description: Letter to KEI (USA) Power Management Inc. re the follow-up to the Dam Safety Inspection for the Barker Mill Lower Project under P-2808.
Source: eLibrary
Page 4 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 10/8/2014
Accession No: 20150520-0170
Description: Letter requesting KEI (USA) Power Management Inc. to provide within 30 days a plan and schedule to perform the inspection for the Barker Mill Lower Dam Project under P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 10/9/2014
Accession No: 20141017-0184
Description: Letter requesting KEI (USA) Power Management Inc to provide w/in 30 days the flashboard designs for the Upper and Lower Baker Mill Dams based on the 7/9/14 dam safety inspection under P-2808 et al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 10/14/2014
Accession No: 20141014-5346
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, Request for Extension of Time for DSI Follow-up Questions.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 11/5/2014
Accession No: 20141105-5068
Description: Dam Safety Inspection Report by NYRO for KEI (USA) Power Management Inc. for the Barker Mill Lower Station Project for the period May 27, 2011 to September 18, 2014 under P-2808-000.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 11/5/2014
Accession No: 20141105-5069
Description:
Page 5 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Dam Safety Inspection Report by NYRO for KEI (USA) Power Management Inc. for the Barker Mill Lower Station Project for the period May 27, 2011 to September 18, 2014 under P-2808-000.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/12/2014
Accession No: 20141112-5136
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al.., Dam Safety Follow-up EOT Request.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/12/2014
Accession No: 20141112-5358
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, Additional Dam Safety Inspection EOT Request
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 11/12/2014
Accession No: 20141118-0168
Description: Letter order accepting KEI (USA) Power Management Inc.'s 10/14/14 filing of the request to submit the plan and schedule by 11/30/14 for the Barker Mill Lower Project et al under P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 12/3/2014
Accession No: 20141231-0183
Description: Letter order accepting KEI Power Management Inc's 11/12/1 request for an extension of time to submit the plan and schedule to perform a detailed inspection for the Barker Mill Lower Project under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/4/2014
Page 6 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Accession No: 20141204-5125
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, 2014 Annual Hazard Review and Gate Certification Letter, 2014 Annual Minimum Flow Letter
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/18/2014
Accession No: 20141218-5305
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al., DSI Follow-up Response, Flashboards EOT Request
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/18/2014
Accession No: 20141218-5306
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al., DSI Follow-up Response, Flashboards EOT Request
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 1/12/2015
Accession No: 20150112-5234
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-5613-000, et. al.., Updated DSSMP including the revised DSSMR checklists
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 1/12/2015
Accession No: 20150112-5235
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-5613-000, et. al.., Updated DSSMP including the revised DSSMR checklists
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Page 7 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed Date: 2/2/2015
Accession No: 20150202-0181
Description: Letter to KEI(USA) Power Management Inc re the low hazard confirmation certification of spillway gate operation, and minimum flow certification for the American Tissue Project et al under P-2809 et al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/3/2015
Accession No: 20150303-5098
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, et. al., Annual Letter Acknowledgement
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 4/1/2015
Accession No: 20150401-5500
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al., 2014 DSSMRs
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 4/1/2015
Accession No: 20150401-5501
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al., 2014 DSSMRs
Source: eLibrary
Filed By: American Whitewater
Filed Date: 4/23/2015
Accession No: 20150423-5128
Description: Comment of American Whitewater on the Proposed Study Plan for KEI (Maine)'s Lower Barker Hydroelectric Project on the Little Androscoggin River (P-2808).
Source: eLibrary
Page 8 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 4/28/2015
Accession No: 20150428-5468
Description: Form of KEI (USA) Power Management Inc. Licensee/Exemptee Contact and Service List Information Forms Submittal under P-2808, et. al.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 4/28/2015
Accession No: 20150505-0366
Description: Letter requesting KEI (USA) Power Management Inc to provide within 30 days the follow-up on plan and schedule for detailed inspection and stability evaluation for the Barker Mill Lower Project under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 5/6/2015
Accession No: 20150506-5218
Description: Comments of NOAA Fisheries Service, Northeast Region under P-2808, Proposed Study PLan for FERC
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 5/7/2015
Accession No: 20150507-5022
Description: P-2808 Comments on KEI (Maine) Power Mgm't. Proposed Study Plan for Lower Barker
Source: eLibrary
Filed By: KEI (USA) POWER MANAGEMENT, INC
Filed Date: 5/20/2015
Accession No: 20150520-0157
Description: KEI (USA) Power Management Inc submits response to the 7/25/14 letter in regards to the July 2014 FERC Inspection of the Lower Barker Hydroelectric Project et al under P-2808 et al.
Source: eLibrary
Page 9 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 5/27/2015
Accession No: 20150527-5054
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Reply to Follow up Plan and Schedule for Detailed Inspection and Stability Evaluation
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 6/5/2015
Accession No: 20150605-5232
Description: Report of KEI (Maine) Power Management (III) LLC under P-2808, P-2808 FERC CvrLtr - Proposed Study Plan Lower Barker
Source: eLibrary
Filed By: KEI(MAINE) POWER MANAGEMENT, INC. KEI (USA) POWER MANAGEMENT, INC
Filed Date: 6/12/2015
Accession No: 20150626-0179
Description: KEI (Maine) Power Management (III) LLC submits the Dam Safety Surveillance and Monitoring Report for the period of 1/1/2014 to 12/31/2014 regarding the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 9/8/2015
Accession No: 20150916-0196
Description: Letter to KEI Power Management Inc. regarding the 2014 Dam Safety Surveillance and Monitoring Reports for the Lower Barker Project et al under P-2808 et al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/10/2015
Accession No: 20151110-5070
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Penstock Rehabilitation, Owners Cofferdam Approval.
Source: eLibrary
Page 10 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/10/2015
Accession No: 20151110-5071
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Penstock Rehabilitation, Owners Cofferdam Approval.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/12/2015
Accession No: 20151112-5085
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al.., Dam Safety Inspection Follow-up Response Letter
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 11/12/2015
Accession No: 20151112-5086
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, et. al.., Dam Safety Inspection Follow-up Response Letter
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 11/25/2015
Accession No: 20151125-3011
Description: Notice of License Expiration and Request for Information Regarding Process Selection.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 12/2/2015
Accession No: 20151202-3003
Description: Errata letter rescinding Advanced Notice of License Expiration letter issued November 25, 2015 under P-619 et al.
Source: eLibrary
Page 11 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/10/2015
Accession No: 20151210-5102
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-3023, et. al., Downstream Hazard Review Letters for the Year 2015
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/28/2015
Accession No: 20151228-5057
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. Annual Gate Certification Letters for 2015 under P-11472, et. al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/28/2015
Accession No: 20151228-5058
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. Annual Gate Certification Letters for 2015 under P-11472, et. al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/10/2016
Accession No: 20160310-5057
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, Dam Inspection Report Letter with Responses to the Dam Inspection Report by Independent Consultant, report also enclosed.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/10/2016
Accession No: 20160310-5058
Description:
Page 12 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808-000, Dam Inspection Report Letter with Responses to the Dam Inspection Report by Independent Consultant, report also enclosed.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/24/2016
Accession No: 20160324-5123
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. Dam Safety Surveillance and Monitoring Reports under P-2808, et. al.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/24/2016
Accession No: 20160324-5124
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. Dam Safety Surveillance and Monitoring Reports under P-2808, et. al.
Source: eLibrary
Issued By: KEI (USA) POWER MANAGEMENT, INC NEW YORK REGIONAL OFFICE
Filed Date: 4/21/2016
Accession No: 20160516-0230
Description: Letter order accepting KEI (USA) Power Management, Inc's 3/24/16 filing of the 2015 Dam Safety Surveillance and Monitoring Reports for the Mechanics Falls Project et al under P-11482 et al.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 7/13/2016
Accession No: 20160725-0286
Description: Letter order accepting KEI (USA) Power Management, Inc.'s 3/10/16 submittal of a Dam Inspection Report for the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc. KEI (USA) Power Management Inc.
Filed Date: 11/28/2016
Page 13 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Accession No: 20161128-5204 NOTE: This document is not part of this docket/sub docket.
Filed Date: 12/12/2016
Accession No: 20161223-0153
Description: Letter requesting KEI (USA) Power Management, Inc. to provide a plan and schedule within 45 days to perform maintenance measures at the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/19/2016
Accession No: 20161219-5299
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Downstream Hazard Review
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/20/2016
Accession No: 20161220-5059
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Dam Safety Inspection Responses
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/20/2016
Accession No: 20161220-5060
Description: Project Safety-Related Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Dam Safety Inspection Responses
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/29/2016
Accession No: 20161229-5053
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-11472, et. al.., 2016 Gate Certifications
Page 14 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/29/2016
Accession No: 20161229-5054
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-11472, et. al.., 2016 Gate Certifications
Source: eLibrary
Filed By: American Whitewater
Filed Date: 1/17/2017
Accession No: 20170117-5150
Description: Comment of American Whitewater on the DLA and Final Study Report for the Lower Barker Hydroelectric Project on the Little Androscoggin River P-2808.
Source: eLibrary
Filed By: Maine Department of Inland Fisheries and Wildlife
Filed Date: 1/23/2017
Accession No: 20170123-5126
Description: Comments on DLA by the Maine Department of Inland Fisheries and Wildlife under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 1/23/2017
Accession No: 20170123-5259
Description: Comments of NOAA Fisheries Service, Northeast Region on KEI (Maine)Power Mgm't (III) LLC on the Draft License Application for the Lower Barker Hydro Project, P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 2/23/2017
Accession No: 20170322-0207
Description: Letter requesting KEI (USA) Power Management Inc. to provide the emergency contact lists for the Mechanics Falls Project under P-11482 et al.
Page 15 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 3/9/2017
Accession No: 20170322-0288
Description: Letter requesting KEI (USA) Power Management, Inc to provide a response within 45 days re the Consultant Dam Inspection Report for the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region
Filed Date: 3/20/2017
Accession No: 20170320-5096 NOTE: This document is not part of this docket/sub docket.
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/24/2017
Accession No: 20170324-5032
Description: KEI (USA) Power Management Inc. Change of Address for Contact of KEI (USA) under P-2808, et. al..,
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 4/10/2017
Accession No: 20170517-0174
Description: KEI (USA) Power Management Inc. submits a response to the Consultant's Dam Inspection Report recommendations re the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: NEW YORK REGIONAL OFFICE
Filed Date: 4/27/2017
Accession No: 20170511-0184
Description: Letter order accepting KEI (USA) Power Management Inc's 4/4/17 filing of the plan and schedule for repairs at the Lower Barker Project under P-2808.
eLibrary
Page 16 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Source:
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 5/1/2017
Accession No: 20170501-5163
Description: KEI (Maine) Power Management (III) LLC Response in re Proposed Replacement of Turbine under P-2808
Source: eLibrary
Filed By: City of Auburn, Maine
Filed Date: 5/5/2017
Accession No: 20170505-5172
Description: City of Auburn, Maine under P-2808 to remind licensee that the City is a stakeholder in the licensing process and wishes to reiterate that recreation and notice of the flow study is important to the community.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 7/17/2017
Accession No: 20170811-0178
Description: KEI (Maine) Power Management (III) LLC submits a Dam Safety Surveillance and Monitoring Report re the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 7/31/2017
Accession No: 20170731-5253
Description: Motion to Intervene of NOAA Fisheries Service, Northeast Region under P-2808-000 Barker Mill's
Source: eLibrary
Filed By: City of Auburn, Maine
Filed Date: 8/2/2017
Accession No: 20170802-5095
Page 17 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: City of Auburn, Maine Whitewater Flow Study comments and request that Licensee mitigate project impacts to recreation within and adjacent to the project area under P-2808
Source: eLibrary
Filed By: American Whitewater
Filed Date: 8/8/2017
Accession No: 20170808-5098
Description: Comment of American Whitewater on the Draft Whitewater Boating Study for the Lower Barker Project on the Little Androscoggin River (P-2808).
Source: eLibrary
Filed By: City of Auburn, Maine
Filed Date: 8/22/2017
Accession No: 20170822-5013
Description: Motion to Intervene of City of Auburn, Maine under P-2808-000. The City of Auburn seeks intervener status in this License Application Process in order to advocate for safe and appropriate recreational opportunities within the project boundary.
Source: eLibrary
Filed By: ANDROSCOGGIN LAND TRUST INC.
Filed Date: 8/29/2017
Accession No: 20170829-5073
Description: Motion to Intervene of ANDROSCOGGIN LAND TRUST INC. under P-2808.
Source: eLibrary
Filed By: American Whitewater
Filed Date: 9/13/2017
Accession No: 20170913-5055
Description: American Whitewater scoping comment under P-2808.
Source: eLibrary
Filed By: City of Auburn, ME
Filed Date: 9/29/2017
20170929-5191
Page 18 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Accession No:
Description: Barker Mill Dam Scoping document 1 comments and Androscoggin Greenway Plan
Source: eLibrary
Filed By: Maine Department of Marine Resources STATE OF MAINE EPA
Filed Date: 10/2/2017
Accession No: 20171002-5031
Description: Comprehensive Plans of Maine Department of Marine Resources under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 10/31/2017
Accession No: 20171031-5361
Description: Report / Form of KEI (Maine) Power Management (III) LLC under P-2808-000. P-2808 Lower Barker Whitewater Flow Study Report
Source: eLibrary
Sub Docket: 002
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (USA) Power Management Inc.
Filed Date: 1/23/2013
Accession No: 20130123-5141
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, Annual Hazard Communication and Gate Certification Letter for 2012
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 12/20/2013
Accession No: 20131220-5157
Description: Submission to NYRO of KEI (USA) Power Management Inc. under P-2808, 2013 Annual Hazard Communication, Gate Certification and Minimum Flow Letters
Source: eLibrary
Page 19 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Sub Docket: 014
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (USA) Power Management Inc. KEI (USA) Power Management Inc.
Filed Date: 11/28/2016
Accession No: 20161128-5204
Description: Request of KEI (USA) Power Management Inc. for Proposed Replacement of Turbine Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 2/6/2017
Accession No: 20170206-3011
Description: Letter to KEI (Maine) Power Management, Inc. re their proposed turbine replacement for the Lower Baker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region
Filed Date: 3/20/2017
Accession No: 20170320-5096
Description: Comments of NOAA Fisheries Service, Northeast Region on KEI (Maine)Power Management LLC Proposed Turbine Replacement for the Lower Barker Hydroelectric Project P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region
Filed Date: 3/20/2017
Accession No: 20170320-5096 NOTE: This document is not part of this docket/sub docket.
Issued By: ENERGY PROJECTS, OFFICE OF ENERGY PROJECTS, OFFICE OF
Filed Date: 3/31/2017
Accession No: 20170331-3020
Description: Letter requiringKEI (USA) Power Management Inc. to cease construction and requesting additional information within 30 days for the Lower Barker Project under P-2808.
Source: eLibrary
Page 20 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Issued By: ENERGY PROJECTS, OFFICE OF ENERGY PROJECTS, OFFICE OF
Filed Date: 5/25/2017
Accession No: 20170525-3077
Description: Letter requiring KEI (USA) Power Management Inc. to cease construction and re-file, within 30 days, section 2.2.2 of application for the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 6/26/2017
Accession No: 20170626-5149
Description: Supplemental Information / Request of KEI (Maine) Power Management (III) LLC under P-2808 and P-2808. Lower Barker - Proposed Turbine Additional Information
Source: eLibrary
Sub Docket: 015
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/31/2015
Accession No: 20150331-5319
Description: Form 80 of KEI (USA) Power Management Inc. under P-2808.
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 3/31/2015
Accession No: 20150331-5434
Description: Supplemental Information of KEI (USA) Power Management Inc. under P-2808-015, Estimation Memo and signed FERC Form 80
Source: eLibrary
Filed By: City of Auburn, ME City of Auburn, ME
Filed Date: 5/10/2016
Accession No: 20160510-5051
Page 21 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: Request for notice of recreational flow study for community involvement in recreational opportunity. Supplemental Information / Request of City of Auburn, ME under P-2808-016, et. al..
Source: eLibrary
Sub Docket: 016
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 1/31/2014
Accession No: 20140131-5541
Description: KEI (Maine) Power Management (III) LLC NOI/PAD for the Lower Barker Hydroelectric under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 1/31/2014
Accession No: 20140131-5542
Description: KEI (Maine) Power Management (III) LLC NOI/PAD for the Lower Barker Hydroelectric under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 2/14/2014
Accession No: 20140214-3006
Description: Letter inviting Passamaquoddy Tribe of Indian Township to participate in the relicensing process for the Lower Barker Hydroelectric Project, and requesting a response by March 17, 2014 under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 2/14/2014
Accession No: 20140214-3007
Description: Letter inviting Penobscot Indian Nation to participate in the project consultation re the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Page 22 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed Date: 2/14/2014
Accession No: 20140214-3008
Description: Letter inviting Passamaquoddy Tribe at Pleasant Point to participate in the relicensing process for the Lower Barker Hydroelectric Project, and requesting a response by March 17, 2014 under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 2/14/2014
Accession No: 20140214-3009
Description: Letter inviting Houlton Band of Maliseet Indians to participate in the relicensing process for the Lower Barker Hydroelectric Project, and requesting a response by March 17, 2014 under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 2/14/2014
Accession No: 20140214-3010
Description: Letter inviting Aroostook Band of Micmacs to participate in the relicening process for the Lower Barker Hydroelectric Project, and requesting a response by March 17, 2014 under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 3/19/2014
Accession No: 20140319-3038
Description: Letter order granting KEI (Maine) Power Management (III) LLC's 1/31/14 request to use the Traditional Licensing Process for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: SECRETARY OF THE COMMISSION, FERC
Filed Date: 3/19/2014
Accession No: 20140319-3052
Description: Notice of intent to file license application, filing of pre-application document, and approving use of the Traditional Licensing Process re KEI (Maine) Power Management (III) LLC's Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Page 23 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: Maine Department of Inland Fisheries and Wildlife
Filed Date: 5/5/2014
Accession No: 20140505-5086
Description: Comments of Maine Department of Inland Fisheries and Wildlife under P-2808.
Source: eLibrary
Filed By: Maine Department of Inland Fisheries and Wildlife
Filed Date: 6/17/2014
Accession No: 20140617-5108
Description: Maine Department of Inland Fisheries and Wildlife Study request under P-2808.
Source: eLibrary
Filed By: Maine Department of Marine Resources
Filed Date: 7/9/2014
Accession No: 20140709-5032
Description: Comment of Maine Department of Marine Resources under P-2808
Source: eLibrary
Filed By: Maine Department of Environmental Protection
Filed Date: 7/16/2014
Accession No: 20140716-5082
Description: TLP Comments or Study Request of Maine Department of Environmental Protection under P-2808.
Source: eLibrary
Filed By: City of Auburn, Maine
Filed Date: 7/16/2014
Accession No: 20140716-5115
Description: PAD Comments and Study Request of City of Auburn, Maine under P-2808.
Source: eLibrary
Filed By: U.S. Fish and Wildlife Service/MEFO
Page 24 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed Date: 7/18/2014
Accession No: 20140718-5039
Description: Comments and Study Requests of U.S. Fish and Wildlife Service/MEFO under P-2808.
Source: eLibrary
Filed By: Individual No Affiliation
Filed Date: 5/1/2015
Accession No: 20150501-5007
Description: Comment of Risa Shimoda in Docket(s)/Project(s) P-2808-016 Submission Date: 4/30/2015
Source: eLibrary
Filed By: Maine Department of Inland Fisheries and Wildlife
Filed Date: 5/6/2015
Accession No: 20150506-5068
Description: Comment of Maine Department of Inland Fisheries and Wildlife under P-2808.
Source: eLibrary
Filed By: Maine Department of Environmental Protection
Filed Date: 5/6/2015
Accession No: 20150506-5122
Description: Proposed Study Plan comments of Maine Department of Environmental Protection under P-2808.
Source: eLibrary
Filed By: City of Auburn, Maine
Filed Date: 5/6/2015
Accession No: 20150506-5212
Description: Comment of City of Auburn, Maine under P-2808, Barker Mill Dam Draft Study Plan Comments.
Source: eLibrary
Filed By: City of Auburn, ME City of Auburn, ME
Filed Date: 5/10/2016
Page 25 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Accession No: 20160510-5051
Description: Request for notice of recreational flow study for community involvement in recreational opportunity. Supplemental Information / Request of City of Auburn, ME under P-2808-016, et. al..
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 6/10/2016
Accession No: 20160610-5222
Description: Supplemental Information of KEI (Maine) Power Management (III) LLC under P-2808-016. 20160610_Barker_Auburn_Response_letter
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 10/24/2016
Accession No: 20161024-5055
Description: KEI (Maine) Power Management (III) LLC Draft License Application for the Lower Barker Hydroelectric Project under P-2808
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 10/24/2016
Accession No: 20161024-5056
Description: KEI (Maine) Power Management (III) LLC Draft License Application for the Lower Barker Hydroelectric Project under P-2808
Source: eLibrary
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 1/5/2017
Accession No: 20170105-3076
Description: Letter to KEI (Maine) Power Management, Inc. providing comments on the draft license application for the Lower Baker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: City of Auburn, Maine
Page 26 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed Date: 1/23/2017
Accession No: 20170123-5036
Description: Comments regarding DLA for P2808/ Relicense in City of Auburn, Maine under P-2808.
Source: eLibrary
Filed By: US Fish and Wildlife Service - Maine Field Office
Filed Date: 1/23/2017
Accession No: 20170123-5042
Description: Comment of US Fish and Wildlife Service - Maine Field Office under P-2808.
Source: eLibrary
Filed By: Maine Department of Marine Resources
Filed Date: 1/23/2017
Accession No: 20170123-5057
Description: Comments of Maine Department of Marine Resources re the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: Maine Department of Environmental Protection
Filed Date: 1/23/2017
Accession No: 20170123-5099
Description: Maine Department of Environmental Protection Draft License Application and Final Study Report Comments for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 1/30/2017
Accession No: 20170130-5361 NOTE: This document is not part of this docket/sub docket.
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 1/30/2017
Accession No: 20170130-5362 NOTE: This document is not part of this docket/sub docket.
Page 27 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Sub Docket: 017
Docket Description: Lower Barker Hydroelectric Project
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 1/30/2017
Accession No: 20170130-5361
Description: Power Management (III) LLC submits the Final License Application for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 1/30/2017
Accession No: 20170130-5362
Description: Power Management (III) LLC submits the Final License Application for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: SECRETARY OF THE COMMISSION, FERC
Filed Date: 2/3/2017
Accession No: 20170203-3014
Description: Notice of Application Tendered for Filing with the Commission and Soliciting Additional Study Requests etc re KEI (Maine) Power Management (III) LLC under P-2808.
Source: eLibrary
Issued By: SECRETARY OF THE COMMISSION, FERC
Filed Date: 2/15/2017
Accession No: 20170215-3029
Description: Errata to the 2/3/17 Commission issued Notice of Application Tendered for Filing with the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing etc re KEI (Maine) Power Management (III) LLC under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 3/9/2017
Accession No: 20170309-5225
Page 28 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: Final Application Document Proof of Publication of KEI (Maine) Power Management (III) LLC under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 3/13/2017
Accession No: 20170313-3006
Description: Letter to KEI (Maine) Power Management (III) LLC re the deficiency of license application and additional Information request for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region
Filed Date: 3/20/2017
Accession No: 20170320-5096
Description: Comments of NOAA Fisheries Service, Northeast Region on KEI (Maine)Power Management LLC Proposed Turbine Replacement for the Lower Barker Hydroelectric Project P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region NOAA Fisheries Service, Northeast Region
Filed Date: 3/20/2017
Accession No: 20170320-5096 NOTE: This document is not part of this docket/sub docket.
Filed By: Maine Department of Environmental Protection
Filed Date: 3/21/2017
Accession No: 20170321-5153
Description: Additional Study Request of Maine Department of Environmental Protection under P-2808.
Source: eLibrary
Filed By: US Fish and Wildlife Service - Maine Field Office
Filed Date: 3/29/2017
Accession No: 20170329-5129
Page 29 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: Comment of US Fish and Wildlife Service - Maine Field Office under P-2808, Lower Barker.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF ENERGY PROJECTS, OFFICE OF
Filed Date: 3/31/2017
Accession No: 20170331-3020
Description: Letter requiringKEI (USA) Power Management Inc. to cease construction and requesting additional information within 30 days for the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: National Park Service NER
Filed Date: 3/31/2017
Accession No: 20170331-5129
Description: Final Amendment Comments of Kevin Mendik, of National Park Service NER under P-2808.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 3/31/2017
Accession No: 20170331-5201
Description: NOAA Fisheries Service, Northeast Region Requested Study and Comments on Final License Application for the Lower Barker Project (P-2808) KEI (Maine) Power Management (III) LLC
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 4/13/2017
Accession No: 20170413-3012
Description: Letter to Maine Department of Environmental Protection et al providing a response to the 3/21/17 and 3/31/17 filings of additional study requests on the Lower Barker Hydro Project under P-2808.
Source: eLibrary
Filed By: Atlantic Salmon Federation
Filed Date: 4/24/2017
Accession No: 20170424-5177
Page 30 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: Comment of Atlantic Salmon Federation under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF ENERGY PROJECTS, OFFICE OF
Filed Date: 5/25/2017
Accession No: 20170525-3077
Description: Letter requiring KEI (USA) Power Management Inc. to cease construction and re-file, within 30 days, section 2.2.2 of application for the Lower Barker Project under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 6/12/2017
Accession No: 20170612-5120
Description: KEI (Maine) Power Management (III) LLC under P-2808-017. Lower Barker - License Deficiency and Additional Information
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 6/12/2017
Accession No: 20170612-5121
Description: KEI (Maine) Power Management (III) LLC under P-2808-017. Lower Barker - License Deficiency and Additional Information
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 6/12/2017
Accession No: 20170612-5122
Description: KEI (Maine) Power Management (III) LLC under P-2808-017. Lower Barker - License Deficiency and Additional Information
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC KEI (Maine) Power Management (III) LLC
Filed Date: 6/26/2017
Accession No: 20170626-5149
Page 31 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Description: Supplemental Information / Request of KEI (Maine) Power Management (III) LLC under P-2808 and P-2808. Lower Barker - Proposed Turbine Additional Information
Source: eLibrary
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 6/29/2017
Accession No: 20170629-3016
Description: Letter providing Scoping Document 1 for Barker's Mill Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: SECRETARY OF THE COMMISSION, FERC
Filed Date: 6/29/2017
Accession No: 20170629-3019
Description: Notice of Scoping Meetings and Environmental Site Review and Soliciting Scoping Comments re KEI (Maine) Power Management (III) LLC under P-2808.
Source: eLibrary
Comments Due Date:
9/29/2017
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 6/30/2017
Accession No: 20170630-3015
Description: Letter informing KEI (Maine) Power Management (III) LLC that the license application has been accepted by the Commission for filing as of January 30, 2017 for the Lower Barker Hydroelectric Project under P-2808.
Source: eLibrary
Issued By: SECRETARY OF THE COMMISSION, FERC
Filed Date: 6/30/2017
Accession No: 20170630-3016
Description: Notice of Application Accepted for Filing and Soliciting Motions to Intervene & Protests re KEI (Maine) Power Management (III) LLC under P-2808.
Source: eLibrary
Page 32 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: KEI (USA) Power Management Inc.
Filed Date: 8/1/2017
Accession No: 20170801-5191
Description: Supplemental Information of KEI (USA) Power Management Inc. under P-2808, Stability and Stress Analyses Report
Source: eLibrary
Filed By: KEI (USA) Power Management Inc.
Filed Date: 8/1/2017
Accession No: 20170801-5192
Description: Supplemental Information of KEI (USA) Power Management Inc. under P-2808, Stability and Stress Analyses Report
Source: eLibrary
Filed By: Maine Department of Inland Fisheries and Wildlife
Filed Date: 8/7/2017
Accession No: 20170807-5148
Description: Notice of Intervention of the Maine Department of Inland Fisheries and Wildlife under P-2808.
Source: eLibrary
Filed By: American Whitewater
Filed Date: 8/28/2017
Accession No: 20170828-5091
Description: Motion to Intervene and Comment of American Whitewater under P-2808.
Source: eLibrary
Filed By: United States Department of Interior
Filed Date: 8/29/2017
Accession No: 20170829-5031
Description: Motion/Notice of Intervention of United States Department of Interior under P-2808. (Erroneously filed)
Source: eLibrary
Page 33 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: United States Department of Interior
Filed Date: 8/29/2017
Accession No: 20170829-5048
Description: Notice of Intervention of United States Department of Interior under P-2808.
Source: eLibrary
Filed By: KEI (Maine) Power Management (III) LLC
Filed Date: 8/29/2017
Accession No: 20170829-5086
Description: KEI (Maine) Power Management (III) LLC under P-2808-017. MSHPO response letter 20170829
Source: eLibrary
Issued By: FEDERAL ENERGY REGULATORY COMMISSION
Filed Date: 9/20/2017
Accession No: 20170920-4001
Description: Transcript of the 08/29/2017 meeting held in Auburn, Maine re the KEI Power Management LLC under P-2808-017.
Source: eLibrary
Issued By: FEDERAL ENERGY REGULATORY COMMISSION
Filed Date: 9/20/2017
Accession No: 20170920-4002
Description: Transcript of the 08/30/2017 meeting held in Auburn, Maine re the KEI Power Management LLC under P-2808-017.
Source: eLibrary
Filed By: NOAA Fisheries Service, Northeast Region
Filed Date: 9/27/2017
Accession No: 20170927-5101
Description: Comment of NOAA Fisheries Service, Northeast Region for the Barker's Mill Hydro under P-2808.
Source: eLibrary
Page 34 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Filed By: US Fish and Wildlife Service - Maine Field Office
Filed Date: 9/28/2017
Accession No: 20170928-5099
Description: Comment of US Fish and Wildlife Service - Maine Field Office under P-2808-017.Comments on the Barker's Mill SD1.
Source: eLibrary
Filed By: Atlantic Salmon Federation
Filed Date: 9/29/2017
Accession No: 20170929-5084
Description: Comment of Atlantic Salmon Federation et al. under P-2808.
Source: eLibrary
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 10/3/2017
Accession No: 20171003-3012
Description: Letter requesting KEI (Maine) Power Management (III) LLC to provide the final report of the whitewater flow study analysis, along with any proposed boating flow releases or other proposed measures within 30 days etc under P-2808.
Source: eLibrary
Issued By: ENERGY PROJECTS, OFFICE OF
Filed Date: 10/19/2017
Accession No: 20171019-3014
Description: Letter providing Scoping Document 2 for the Barker's Mill Hydroelectric Project under P-2808
Source: eLibrary
Issued By: OFFICE OF ENERGY PROJECTS
Filed Date: 10/26/2017
Accession No: 20171026-3002
Description: Letter to Maine Department of Marine Resources regarding treatment of the Interstate Fishery Management Plan et al as Comprehensive Plans under ZZ09-5 et al.
Source: eLibrary
Page 35 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp
Page 36 of 36eLibrary - Docket Sheet
11/1/2017https://elibrary.ferc.gov/idmws/docket_sheet.asp