Upload
dothuan
View
218
Download
1
Embed Size (px)
Citation preview
Presentation Outline
• Subsurface Oxidation Events
� The Basics
• Case Study
� Thermal Imaging Basics
� Identify Additional Areas
� Confirm the Extent
� Mitigate the Issue
� Confirm Effectiveness
• Regulatory Concerns
• Cost
• Closing
• Questions
Subsurface Oxidation EventsThe Basics
• Not the same thing as an Elevated Temperature Landfill
(ETLs)
� ETLs typically have an exothermic chemical reaction occurring over a
large area
� ETLs are normally very deep with initial reaction occurring at depth
� ETLs associated with specific waste streams that the landfill accepted
• Subsurface Oxidation Events
� Typically occur in shallow areas
� Typically can be identified by Carbon Monoxide production
Subsurface Oxidation EventsThe Basics
• Defining Elevated Subsurface Temperature
� 100°F to 120°F
– Expected Temperature Range
� 120°F to 131°F
– Somewhat warm but within
regulatory constraints
� 131°F to 145°F
– Elevated but typically allowable as
Alternative
– Additional monitoring typical
� < 145°F
– Concerning
– Trigger for EST 4 letter word starting with “F” FIRE
Case StudyInitial Request
• Site contacted Tetra Tech that an area recently excavated
was exhibiting signs of Elevated Subsurface Temperature
� Smell of burning
� Slight smoking
� Area has historically had similar incidents in the last 2-3 years
• Tetra Tech was asked to:
� Identify any additional Areas of Concern
� Define the extent of the Areas of Concern
� Mitigate the Elevated Subsurface Temperature Areas of Concern
� Confirm effectiveness through follow up monitoring
Case StudyThermal Imaging Basics
• Some basics about thermal imaging
� It is not as expensive as it once was in the past
� If aerial thermal imaging is used it must be verified with ground-based follow up
� Uses variances in surface temperatures to provide visual differences
� Can be skewed by surface fluctuations (grass versus dirt, for example)
� The temperature scale is displayed based on the view of the camer
Case StudyThermal Imaging Basics
Variances between the temperatures in the pictures are
used for the colors in the image
Case StudyIdentify Additional Areas
Original Area of Concern
Thermal Signature #1
Below Grade Header Line
Excavator Location
Case StudyConfirm the Extent
Original Area of Concern
Thermal Signature #1
Thermal Signature #2
Thermal Signature #3
1
2
3
45
67
8
Case StudyConfirm the Extent
• Temporary Monitoring Probes were installed using an
excavator
6 – 8’
1’
1” Diameter Black Iron Pipe (10’ Long)
1” Diameter Threaded Cap
1” Diameter Threaded Cap
1/4” Perforations
Case StudyConfirm the Extent
• Temporary Monitoring Probes had the following performed
prior to mitigation activities for confirmation of Elevated
Subsurface Temperatures:
� Methane
� Carbon Dioxide
� Oxygen
� Balance
� Temperature
� Carbon Monoxide
Case StudyConfirm the Extent
Original Area of Concern
Thermal Signature #1
Thermal Signature #2
Thermal Signature #3
1
2
3
45
67
8
Case StudyMitigating the Issue
• After confirming the two (2) Areas of Concern, mitigation
strategies were analyzed
• A multi-faceted approach was selected:
• Application of additional
soil to surface
• Wetting of the surface
• Compaction of the soil
surface
• Injection of liquid
carbon dioxide
Case Study Mitigating the Issue
• Liquid CO2 Fun Facts
� Delivery typically occurs between –60°F to 0°F and a pressure of 100
to 600 PSI
� Serious health hazard for inhalation, cryogenic injury and severe
frostbite
� Approximately 8.5 ft3 of gas is created for each pound of liquid CO2
� Sudden change in temperature or pressure will cause dry ice snow to
form
� Rapid discharge of liquid CO2 through a line will cause a build-up of
static electricity
Liquid CO2 Injection is dangerous!!!
Case Study Confirm Effectiveness
• Additional monitoring after the injection of liquid CO2 was performed to confirm the effectiveness of the mitigation measures
• Monitoring included:
� Methane
� Carbon Dioxide
� Oxygen
� Balance
� Temperature
� Carbon Monoxide
• Monitoring was performed regularly for a period of one month
Case Study Confirm Effectiveness
• Gas monitoring indicated Carbon Dioxide concentrations
greater than 94% by volume in some nearby Temporary
Monitoring Points
• Carbon Monoxide concentrations were found to decrease
over 60% within 24 hours of the injection
• Temperatures reduced over 16% over a 20 day period
• Continued monitoring has not indicated any evidence of the
elevated subsurface temperature event
Regulatory ConcernInforming the Agencies
• Notification was provided to the regulator in this event
• There was no exceedance of regulatory limits that caused
the event
• Go through specifically the regulatory requirements
associated with the incident that is being addressed:
� Is the regulator already aware of the issue?
� Is the issue being addressed because of a regulatory issue?
� Will the regulator be required to be notified?
� Is there anything in site permit that calls out the activities?
CostThe Bottom Line
• Initial thermal Investigation:
� Drone Pilot $175/hr for 8 hours
� Drone Spotter $155/hr for 8 hours
� Video Processing $125/hr for 4 hours
� Drone $100/hr for 8 hours$4,000
CostThe Bottom Line
• Monitoring Well Installation and Monitoring:
� Construction Crew $2500/day for 1 day
� Monitoring Technician $110/hr for 8 hours
� Materials $450/well for 8 wells $7,000
CostThe Bottom Line
• Liquid CO2 Injection Wells Installation:
� Construction Crew $2500/day for 1 day
� Supervisor $175/hr for 8 hours
� Materials $1,500/well for 5 wells$12,000
CostThe Bottom Line
• Liquid CO2 Injection:
� Supervisor $175/hr for 16 hours
� Technician $110/hr for 16 hours
� Liquid CO2 $8,000/tanker for 2 tankers (20 tons each)
$21,000
CostThe Bottom Line
• Follow-Up Monitoring:
� Monitoring Technician $110/hr for 24 hours (over 1 month)
� Office Staff $120/hr for 10 hours
$4,000
CostThe Bottom Line
Initial Thermal Investigation: $4,000
Monitoring Well Installation and Monitoring: $7,000
Liquid CO2 Injection Well Installation: $12,000
Liquid CO2 Injection: $21,000
Follow-Up Monitoring: $4,000
Subtotal: $48,000
Equipment Allocation: 5.0 % ($2,400)
Contingency: 10 % ($4,800)
Total Cost:Total Cost:Total Cost:Total Cost: $56,000$56,000$56,000$56,000
Cost Per Acre:Cost Per Acre:Cost Per Acre:Cost Per Acre: $46,000$46,000$46,000$46,000
Compare to the on-going monitoring and mitigation activities associated with the
traditional approach
Closing Summary
• Thermal imaging has the potential to identify areas of elevated subsurface temperatures
� Limited to shallow areas
� Requires experience to interpret results
• Liquid CO2 Injection was successful in mitigating the subsurface elevated temperature areas at this particular landfill
� Can be dangerous
� Needs to be designed and operated properly
� Has multiple benefits for this application
• More testing is required to fully evaluate the processes effectiveness but preliminary results were exceptional