18
1 LCLS EIR, 10/9/07 D. Schultz Electron Beam Systems ETC and Methodology Electron Beam Systems Definition of terms Schedule Overview Start-Up Test Plan E-Beams Costs Risk Analysis David Schultz E-Beams Systems Manager

Electron Beam Systems ETC and Methodology

Embed Size (px)

DESCRIPTION

Electron Beam Systems ETC and Methodology. Electron Beam Systems Definition of terms Schedule Overview Start-Up Test Plan E-Beams Costs Risk Analysis. David Schultz E-Beams Systems Manager. E-Beams Systems layout. Sector 21. Sector 20. Laser lab. BC1. LX. L1. Injector. - PowerPoint PPT Presentation

Citation preview

Page 1: Electron Beam Systems ETC and Methodology

1LCLS EIR, 10/9/07D. Schultz

Electron Beam SystemsETC and Methodology

Electron Beam Systems Definition of terms

Schedule Overview Start-Up Test PlanE-Beams CostsRisk Analysis

David Schultz

E-Beams Systems Manager

Page 2: Electron Beam Systems ETC and Methodology

2LCLS EIR, 10/9/07D. Schultz

BC1

LXL1

Laser lab

Sector 20

Sector 21E-Beams Systems layout

Injector Injector Commissioning complete

Page 3: Electron Beam Systems ETC and Methodology

3LCLS EIR, 10/9/07D. Schultz

The electron gun in the InjectorLaser beam

transport

Electron gun

Page 4: Electron Beam Systems ETC and Methodology

4LCLS EIR, 10/9/07D. Schultz

SLAC linac tunnelSLAC linac tunnel research yardresearch yard

Linac-0L =6 m

Linac-1L 9 m

Linac-2L 330 m

Linac-3L 550 m

BC1L 6 m

BC2L 22 m

LTU L =275 m

undulatorL =130 m

6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV

Linac-XL =0.6 m

...existinglinac

rfgun

X

E-Beams Systems layout

L2/BC2/L3Injector/BC1

Comm

issio

ned

Now In

stal

ling

Page 5: Electron Beam Systems ETC and Methodology

5LCLS EIR, 10/9/07D. Schultz

Beam Transport Hall Transport the electron beam to the Undulator

E-Beams Systems layout

SLAC Linac LCLS uses the last 1/3 of the existing Linac.

Controls Beamline and diagnostics control for e-beams systems.

Undulator Hall Underground tunnel housing the undulator.

Electron Beam Dump Underground facility for the beam dump.

Near and Far Halls – Areas for x-ray experiments

Page 6: Electron Beam Systems ETC and Methodology

6LCLS EIR, 10/9/07D. Schultz

Injector WBS 1.02, 2.02Jose Chan, Control Account Manager

Laser/Gun/L0/Spectrometer

– Installed and commissioned

Create electrons, accelerate, analyze beam quality

E-Beams Systems WBS structure

Laser HeaterAccelerator R&D activity

Page 7: Electron Beam Systems ETC and Methodology

7LCLS EIR, 10/9/07D. Schultz

Linac WBS 1.03, 2.03Jose Chan, CAML1/Lx/BC1 – Installed and commissioned

Accelerate the beam, initial beam bunch compression

L2/BC2/L3Full beam acceleration, second compression of bunch

E-Beams Systems WBS structure

LTUTransport electron beam from Linac to Undulator

Electron dumpSafely dispose of the electron beam

Page 8: Electron Beam Systems ETC and Methodology

8LCLS EIR, 10/9/07D. Schultz

Undulator WBS 1.04, 2.04Generate x-rays as the high power electron beam passes through.

Undulator Systems at ANL, Geoff Pile, CAMFabricate components and supports for the Undulator system

Undulator Integration at SLAC, Rodd Pope, CAMTune, fiducialize, assemble, and install the Undulator system

E-Beams Systems WBS structure

Page 9: Electron Beam Systems ETC and Methodology

9LCLS EIR, 10/9/07D. Schultz

Accelerator Controls WBS 1.02.02, 2.02.02,

1.03.02, 2.03.02, 1.04.02, 2.04.02

Hamid Shoaee, CAMControlling hardware, cable plant and software for Injector, Linac and Undulator Systems

Commissioning WBS 2.01.01, 2.02.17, 2.03.07, 2.04.06

David Schultz, CAMLOE manpower for LCLS personnel and maintenance groups during the electron beam commissioning process.

E-Beams Systems WBS structure

Page 10: Electron Beam Systems ETC and Methodology

10LCLS EIR, 10/9/07D. Schultz

System engineering resource loaded schedule is controlled through P3.Design process:

Interface Control Documents specify which group has responsibility for each system.Physics Requirements Documents are written by the LCLS Physics group specifying subsystem needs.Engineering group holds Design Reviews, and writes Engineering Specification Documents to detail how the PRD is to be satisfied.

Physicists and Engineers sign-off on component assembly and testing prior to installation.

System Design Management

Page 11: Electron Beam Systems ETC and Methodology

11LCLS EIR, 10/9/07D. Schultz

E-Beams Systems Level 3 Milestones

L3 milestones sufficient and properly distributed to monitor performance.

Page 12: Electron Beam Systems ETC and Methodology

12LCLS EIR, 10/9/07D. Schultz

E-Beams Systems Level 3 Milestones

Page 13: Electron Beam Systems ETC and Methodology

13LCLS EIR, 10/9/07D. Schultz

LCLS Installation and Commissioning Time-Line

SS OO NN DD JJ FF MM AA MM JJ JJ AA SS OO NN DD JJ FF MM AA MM JJ JJ

Linac/BC2 Install

Linac/BC2 Commissioni

ng

LTU/Und/Dump Install

20072007 20082008

CF Early Occupancy

LTU/Und Commissionin

g

Flux milestone

AA SS OO NN DD

20092009 20102010PPS

X-ray tunnel/FEH Install

CD-4(7/30/10)

PPS

FEE/NEH Commissioning

Tunnel/FEH Commissioning

JJ FF MM AA MM

FEE/NEH Install

FEH X-rays milestone

Page 14: Electron Beam Systems ETC and Methodology

14LCLS EIR, 10/9/07D. Schultz

LCLS Safety Assessment Document is due 7/2008

LCLS Accelerator Readiness Review is needed 10/2008

Systems installed, checked out, signed off by responsible parties.

Safety officers’ sign offs on approvals and installations.

Safety specific systems (Personnel Protection) certified.

Maintenance groups have procedures and training in place.

Procedures in place for Operations, and Operators trained.

Beam Authorization Sheet prepared.

Detailed commissioning schedule and performance goals are produced by the LCLS Physics group.

Approval to begin commissioning given by the Director’s office

Start Up Test Planning

Page 15: Electron Beam Systems ETC and Methodology

15LCLS EIR, 10/9/07D. Schultz

As installation is approaching, systems are well defined.Installation costs

Based on experience in 2006 Injector installation. Hardware install estimate done top-down and bottom-up.

Based on experience on undulator prototype at ANL.Cable plant install estimated using R.S. Means.

Fabrication/procurementCosts based on quotes and experience with prototypes at SLAC and ANL.

Engineering and CommissioningTimetable for completion well understood.

E-Beams Systems Cost Estimation

Page 16: Electron Beam Systems ETC and Methodology

16LCLS EIR, 10/9/07D. Schultz

Risk Assessment

Design maturity and cost/schedule exposure are used in the contingency analysis for all DCE activities.Major risks are identified as Risk Registry entries, and assessed and maintained by the System Manager.The Senior Management team reviews the Registry monthly.

Summary of E-Beams Systems entries:Linac (2)

Risk: Linac diagnostics may need to be enhanced to have sufficient sensitivity for FEL commissioning.

Mitigation: The upcoming BC2 commissioning will determine if an upgrade is warranted.

Page 17: Electron Beam Systems ETC and Methodology

17LCLS EIR, 10/9/07D. Schultz

Risk registry

Summary of entries (cont.):Undulator (3)

The assembly of the Undulator Girders is a pacing item for Undulator commissioning. Several components from ANL are close to being the limiting factor

Risk: Any rework or modification of parts at SLAC will delay girder assembly.

Mitigation: We have multiple weekly video meetings with ANL and quarterly Undulator collaboration meetings to ensure coordination.Integration engineers at ANL and at SLAC have been established to coordinate the receipt and assembly.

Page 18: Electron Beam Systems ETC and Methodology

18LCLS EIR, 10/9/07D. Schultz

Electron Beams Systems are approaching final installation.Systems are well defined,

Based on Project documentation.Resource loaded schedule in P3.Costs have a solid basis.

The start up test plan is based on the successful turn-on of the LCLS Injector.Identified risks are being controlled.

Summary