Electrical Integration. CM38 Steve Griffiths & Ian Mullacrane. Contents. Decay Solenoid Power Supply replacement QD System Upgrade Rack Room 2 Infrastructure AC Electrical Distribution UPS System Cooling Channel Control racks Cooling Channel Power Supply racks FC and SS QD Systems - PowerPoint PPT Presentation
Citation preview
Electrical Integration
CM38Steve Griffiths & Ian Mullacrane
S A Griffiths & I D Mullacrane CM38 Feb 2014
Contents
• Decay Solenoid• Power Supply replacement• QD System Upgrade
• Rack Room 2• Infrastructure• AC Electrical Distribution• UPS System• Cooling Channel Control racks• Cooling Channel Power Supply racks• FC and SS QD Systems
• Compressor and Vacuum rack• Diffuser and Tracker Control rack
2
S A Griffiths & I D Mullacrane CM38 Feb 2014
Decay Solenoid Power Supply & QD System Upgrade
3Existing PSI Power Supply & QD System
in MICE Hall
• Existing Power Supply is electrically noisy and unreliable. Causing QD system to trip at currents below 150A.
• New Power Supply from FuG was procured and delivered in Sept 2013.
• Failure of a Solenoid - current lead has delayed the installation.
• Power Supply installation and commissioning is planned for April 2014.
• A new DL QD system has been installed and final commissioning is planned for March 2014.
• The DL QD system has been operated with existing Power Supply up to 150A.
• A Quench Data Logger system will be constructed to monitor the Solenoid during initial operations.
S A Griffiths & I D Mullacrane CM38 Feb 2014
Decay Solenoid Power Supply Replacement
4
FuG - Superconducting Magnet Power Supply - 10V, 1000A
FuG - Superconducting Magnet Power Supply - 8V, 1000A
Discharge Resistors
Rectifier & SmoothingCapacitors
Transistor Bank forOutput Regulation
Main DC contactor
S A Griffiths & I D Mullacrane CM38 Feb 2014
Quench Detection System Upgrade
5
• Existing system contains obsolete components.
• Combines the reliable PSI philosophy with a modern modular design.
• Tripping points are set at 20mV for most of the voltage taps except for channel 4 which is set at 40mV.
• The Voltage taps from the magnet are arranged in sets of three with overlap along the length of the solenoid.
• Not all of the voltage taps are used.
DL Quench Detection System
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – Step IV Equipment Layout
6
• Room infrastructure progressing well, handover planned for cable management installation in March 2014.
Proposed extended MCR?
• Allocation and position of racks and equipment for Step IV agreed and finalised.• QD & QP system for SS – layout / position to be confirmed.
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – Infrastructure
7
New Door Access
Cable Managementfrom Hall
Cable Managementunder stairs
Cable Access into RR2
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – AC Electrical Distribution
8
Main AC Supply for Critical Loads via UPS
Main AC Supply forGeneral Distribution
Lighting replaced and main AC feeder installed
208V Transformer
S A Griffiths & I D Mullacrane CM38 Feb 2014
AC Distribution for RR2 up to Step VI
9
AC Distribution separated into Critical systems and General distribution
All Critical systems are fed via the 30KVA UPS with 1 hour autonomy.
General distribution includes DC magnet power supplies, A/C conditioning and lighting.
Critical systems includes instrumentation, controls system and cooling water for SS energy absorbers
208V Transformer
Main Hall Board
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – UPS Inverter and Batteries
10
UPS for Critical Loads
Riello UPS – Sentry unit3 Phase - Double Conversion Technology
As the total load will be significantly lower than 30KVA the autonomy will be >1hour
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – Cooling Channel Racks Step IV
11
FC & SS Power Supplies,
Instrumentation and Control
RacksRacks allocated up to Step VI
S A Griffiths & I D Mullacrane CM38 Feb 2014
Cooling Channel Rack Configuration
12
• All 7 Cooling Channel Control & PSU racks to be located in RR2 are designed and assembled as far as possible.
• RR2 installation is scheduled for May 2014.
Cooling Channel Control Rack
Spectrometer #1&2 Control & Instrumentation
Rack
FC Control & Instrumentation
Rack
FC Power Supply Rack
Spectrometer #1 Power Supply
Rack
Spectrometer #2 Power Supply
Rack
Spectrometer #1&2 Discharge
Circuit Rack
Blister Front Back
Focus Coil & Spectrometer Solenoid Control Racks
13
Cooling Channel Control Racks - Step IV
• These 3 racks have been designed, assembled and partially commissioned.• Awaiting procurement / delivery of instrumentation to fully populate.
Racks allocated for Step V & VI
Spare
Focus Coil & Spectrometer Solenoid Control Racks
14
Racks viewed from rear
Cooling Channel Control – VME crates, CANBUS modules, ADC, DAC and serial interfaces.
FC & SS Control - He level gauges, temperature indicators / controllers, pressure indicators and interfacing.
Focus Coil & Spectrometer Solenoid PSU Racks
15
Cooling Channel PSU Racks - Step IV Racks allocated for Step V & VI
• These 4 racks are all designed.• Assembly is completed apart from SS#2 PSU rack.
Focus Coil & Spectrometer Solenoid PSU Racks
16
• Assembly and commissioning can only be completed after procurement / delivery of instrumentation (SS#2 PSU rack requires DC contactors).
• Racks are partially commissioned.
FC PSU Rack-Front FC PSU Rack-Rear SS PSU Rack-Rear SS PSU Rack-Front
Spectrometer Solenoid Energy Absorber Rack
17
• Upstream SS energy absorber have been upgraded and thermally tested.• Cooling water circuits have been modified and flow indication added.• Downstream SS energy absorbers will be delivered once Solenoid training
complete. (May 2014)
Energy Absorber Rack-Rear with and without DC Cables
Items Required
S A Griffiths & I D Mullacrane CM38 Feb 2014
Instrumentation required for FC & SS Racks
18
• Racks will be populated once testing of the Spectrometer Solenoids is complete. Availability of FC instrumentation depends on training schedule.
• There are still power supplies and instrumentation to be procured for Step IV for both FC and SS.
• A list is being compiled of the remaining items for the SS, funding needs to be agreed for these and DC magnet / controls cables.
Control & Instrumentation racks operational at WANG and RAL R9
S A Griffiths & I D Mullacrane CM38 Feb 2014
Rack Room 2 – QD & QP Systems
19
3 Racks allocated for the QD & QP systems for FC,
SS & RFCC
SS QD & QP System
FC QD & QP System
All Step IV systems fully installed and commissionedby Nov 2014
S A Griffiths & I D Mullacrane CM38 Feb 2014
Quench Detection & Protection Racks
20
SS QD / QPSystem rack
FC QD / QPSystem rack
RFCC QD / QPSystem rack
• The location of the FC QD systems is agreed. (for all 3 focus coils)
• Tests are being conducted to ensure reliable operation with 36m voltage tap cable lengths.
• Two FC QD systems are assembled and tested.
• One system is currently being used for training the FCs.
• The location for SS QD systems is being discussed.
• A second SS QD system is to be assembled, tested and installed before Nov 2014.
• Integration of the data logging for both systems needs to be finalised.
Diffuser and Tracker Control Rack
21
• The rack design is being developed with the work package managers.• The rack will be assembled ready for population with equipment by
Summer 2014.
Cooling Chanel Control Racks for Step IV
S A Griffiths & I D Mullacrane CM38 Feb 2014
Compressor & Vacuum Control Rack
22
• The control system requirements for the compressors are agreed and the rack physically assembled.
• The vacuum control and instrumentation have been reviewed and equipment ordered.
• Control philosophy needs to be finalised with Vacuum specialists
S A Griffiths & I D Mullacrane CM38 Feb 2014
Summary
• Project Plan for Step IV Electrical & Controls is fully developed and linked to the master plan.
• Resource priorities are focused on the Step IV milestones and this may affect other work packages such as RF systems.
• Electrical & Control requirements for Step IV are progressing well.
• Installation & commissioning is dependent on key milestones such as installation of South PRY, FC and downstream SS.
• Peak resource loading will occur between July and November 2014 and will need to be carefully co-ordinated.
23
Questions?CM38