Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
EIA/EMP REPORT
w.r.t.
“MODIFICATION & EXPANSION OF GROUP
HOUSING COLONY PROJECT”
At`
VILLAGE –DHANWAPUR, SECTOR-104,
GURUGRAM, HARYANA
For
M/s JUVENTUS ESTATE LTD.
September, 2018
Schedule: 8 (b), Category: B
QCI Certificate no. NABET/EIA/1619/RA 0064
Prepared By
GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD.
(Accredited by QCI/NABET, Approved by MoEFCC, GoI, ISO 9001:2008 Certified Co.)
F-374-375, Sector-63, Noida, U.P.
Ph.: 0120- 4044630, Telefax: 0120- 2406519
Email: [email protected], [email protected]
Website: http://www.grc-india.com
GRC INDIA TRAINING & ANALYTICAL LABORATORY
(Accredited by NABL, Recognized by MoEFCC, GoI)
A unit of GRC India
TABLE OF CONTENT
Table
No.
Description Page No.
CHAPTER 1 INTRODUCTION 1-9
1.1 Preamble 1
1.2 General Information on Project 1
1.3 Environmental Clearance Process 2
1.4 Validity of Environmental Clearance 2
1.5 Post Environmental Clearance Monitoring 2-3
1.6 Transferability of Environmental Clearance 3
1.7 Generic Structure of Environment Impact Assessment 3-4
1.8 Project proponent 5
1.9 Brief Description of Project 5-6
1.10 Applicable Legal Requirements 6
1.11 Need of EIA Study 6
1.12 Scope of EIA study 6-7
1.13 Study Methodology 7-8
1.14 EIA methodology 8-9
CHAPTER 2 PROJECT DESCRIPTION 10-32
2.0 Introduction 10
2.1 Project Location and Site Surroundings 10-11
2.2 Brief Project Features 11-12
2.3 Population detail 12-13
2.4 Power Requirement 14
2.5 Parking 14-15
2.6 Water supply 15-21
2.7 sewage treatment plant 21-24
2.8 Rain Water Harvesting 24-27
2.9 Solid Waste Management 27-31
2.10 Landscape 31
2.11 Fire Fighting System 31
CHAPTER 3 DESCRIPTION OF THE ENVIRONMENT 32-69
3.1 Introduction 32
3.2 Study period 32
3.3 Study area 32
3.4 Baseline monitoring of environmental component 32-58
3.5 Socio Economic Impact Assessment 58-69
CHAPTER 4 ANTICIPATED ENVIRONMENTAL IMPACTS
&MITIGATION MEASURES
70-92
4.1 Introduction 70
4.2 Impact Matrix 71-72
4.3 Pollution sources 73-74
4.4 Impact identification 74-76
4.5 Assessment of Environmental Impacts During Development and
Construction Phase
76-85
4.6 Assessment of the environmental impacts during post Operation phase 85-92
CHAPTER 5 ANALYSIS OF ALTERNATIVE 93-100
5.1 Introduction 93
5.2 Building Materials 93-95
5.3 Natural Hazard Prone areas 95
5.4 Green Building 96-98
5.5 Community Issues
98
5.6 Energy conservation 98-99
5.7 Transportation 100
CHAPTER 6 ENVIRONMENTAL MONITORING PROGRAM 101-105
6.1 Introduction 101
6.2 Performance indictors 101-104
6.3 Data Management 105
6.4 Reporting Schedules 105
CHAPTER 7 ADDITIONAL STUDIES 106-115
7.0 Introduction 106
7.1 Risk assessment And Disaster Management Plan 106-110
7.2 Response In Case of earthquake 110-111
7.3 Response For LPG leakage 111
7.4 Response In case of fire 111-112
7.5 Resource conservation 113-114
7.6 Resettlement And rehabilitation 114
7.7 Corporate Social Responsibility 115
CHAPTER 8 PROJECT BENEFITS 116
8.1 General 116
8.2 Physical infrastructure 116
8.3 Social Infrastructure 116
8.4 Economic Benefits 116
CHAPTER 9 ENVIRONMENTAL MANAGEMENT PLAN 117-161
9.1 Introduction 117-118
9.2 Environmental Management Strategies 118-154
9.3 Overall mitigation measures and EMP 154-161
CHAPTER 10 SUMMARY AND CONCLUSION 162-167
10.1 Project background 162
10.2 Project site & Connectivity 162-166
10.3 EMP 166-167
CHAPTER 11 DISCLOSURE OF CONSULTANTS ENGAGED 168-170
11.1 Accreditation from quality council of India QCI 168-170
CHAPTER 12 CORPORATE ENVIRONMENTAL
RESPONSIBILITY
171-173
12.1 Procedure for Environmental Compliance 171-172
12.2 Organizational Structure for Environmental Compliance 172-173
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 1
CHAPTER 1: INTRODUCTION
1.1 PREAMBLE
EIA is a technical exercise to establish baseline environmental condition to predict
environmental impact, assess their significance and provide recommendations for their
mitigation. The impact assessment covers both construction and operation phase of the
development. The report covers areas such as noise, air quality, ecology, water quality,
hydrology, local architecture, landscape & visual character, sustainability and socio-economics.
Early identification and characterization of critical environmental impacts allow the public and
the Government to form a view about the environmental acceptability of a developmental project
and what conditions should apply to mitigate or reduce those risks and impacts. The report
describes how the project has been improved through the EIA process.
This report has been prepared as per the EIA Notification, 2006 and amendments; ToR
prescribed by SEAC, Haryana and Technical Guidance Manual for Building Construction,
Townships and Area Development projects.
1.2 GENERAL INFORMATION ON PROJECT
M/s. Juventus Estate Ltd. has proposed Modification & Expansion of existing Group Housing
Colony project located at Village Dhanwapur , Sector-104, Gurugram, Haryana.
The project was earlier granted Environment Clearance by SEIAA, Haryana vide letter no.
SEIAA/HR/2014/923 dated 11/07/2014 for Plot area = 1,16,009.63 m2
(28.66665 acre) and
Built-up area 3,75,674.82 sqm. A copy of the earlier EC letter is enclosed as Annexure – I.
The project has undergone some revision in planning, due to which the built-up area will reduce
to 3,61,332 sqm. As a result of additional license issued to the project by DTCP, Haryana, the
plot area increases from 1,16,009.63 m2 to 1,37,685.79 m
2 (34.022 Acre) for which this EC is
being sought.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 2
1.3 ENVIRONMENTAL CLEARANCE PROCESS
As per EIA Notification, 2006 and amendments, all building construction and area development
projects covering an area ≥ 50 ha / built up area greater than 1, 50,000 m2 are appraised as 8 (b),
Category B and are required to obtain prior environmental clearance from respective
SEIAA/SEAC. The application for environmental clearance comprises submission of Form I,
Form IA, and Conceptual Plan. Following the appraisal of the project to the satisfaction of the
SEAC (Haryana), environmental clearance will be granted.
As per the EIA notification, M/s. Juventus Estate Ltd, submitted an EC application to State Level
Environment Impact Assessment Authority (SEIAA), Haryana which comprised of Form I, Form
IA Conceptual Plan and proposed Terms of Reference (ToR).
Thereafter, the case was placed before State Expert Appraisal Committee (SEAC), Haryana
during 158th
meeting held on 27th
Sept., 2017 wherein Terms of Reference was recommended for
the project by committee.
A copy of the ToR Letter is enclosed as Annexure-II. Point-wise compliance to the ToR
conditions is enclosed as Annexure-III.
Since the tenure of SEIAA/SECA, Haryana has expired in Aug., 18, the EIA/EMP report of
project is being submitted to MoEFCC in purview of EIA Notification, 2006 for appraisal and
grant of EC.
1.4 VALIDITY OF ENVIRONMENTAL CLEARANCE
As per the provisions of the EIA Notification, 2006 & amendments, the environmental clearance
granted is for a period of seven years. This may be extended by a maximum of ten years,
provided an application is submitted to the regulatory authority within one month before validity
period with updated Form I, Form IA and Conceptual Plan.
1.5 POST ENVIRONMENTAL CLEARANCE MONITORING
On award of Environmental Clearance, M/s. Juventus Estate Ltd. will be required to advertise
the receipt of EC in at least two local newspapers.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 3
The project management will submit the half-yearly compliance report in respect of the
stipulated prior environmental clearance terms and condition in hard and soft copies to the
regulatory authorities concerned on 1st June and 1
st December of each calendar year.
1.6 TRANSFERABILITY OF ENVIRONMENTAL CLEARANCE
A prior environmental clearance granted for a specific project or activity to an applicant may be
transferred during its validity to another legal person entitled to undertake the project or activity
on application by the transferor or the transferee with a written “no objection” by the transferor,
to, and by the regulatory authority concerned, on the same terms and conditions under which the
prior environmental clearance was initially granted, and for the same validity period.
1.7 GENERIC STRUCTURE OF ENVIRONMENT IMPACT ASSESSMENT
The environmental impact assessment has been carried out to assess the impact of the project on
various environmental components. The methodologies and findings of the study are detailed in
this report along with other relevant information under the different chapters as under:
Introduction- provides background information about the project falls in the category as defined
in EIA Notification, 2006 and amendment, based on area statement and the developers along
with the legal environmental requirements of the project. The scope and EIA methodology
adopted in preparation of EIA report have also been described in this chapter.
Project Description– briefly discusses the project features while elaborating on components
bearing environmental consequences.
Description of the Environment– Discusses the baseline data of environmental attributes such
as air, water, soil, noise and socioeconomic environment of the area based on primary and
secondary data collection at the site. Study of existing environment at the site and in the study
area comprising base-line and environmental quality after receive of new development during
construction & operation of the project.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 4
Anticipated Environmental Impacts & Mitigation Measures – Predicts the environmental
impacts of the various components of the project during construction and operation phases to
highlight concern areas requiring mitigation measures. Accordingly, it also suggests controls and
mitigation measures to offset/ minimize the adverse impact while optimizing the positive
benefits from the project.
Analysis of Alternatives – Explores the alternative sites and plans that have been considered for
the project and evaluates the different scenarios in the environmental context.
Environmental Monitoring Programme – Outlines a monitoring programme for the different
environmental components during the construction and operation phase for evaluation of the
environmental status of the region against the project development.
Additional Studies – Discusses any study that has been carried out for the purpose of better
understanding of the environmental impacts of the project. It also highlights any pertinent
findings from the study that will aid decision-making.
Project Benefits – Describes the positive impacts of the project.
Environmental Management Plan – Organizes the suggested mitigation measures to aid
implementation through formulation of performance indicators, reporting structure and
pronounced implementation period.
Summary & Conclusion – Summarizes the important report findings and concludes on the
environmental sustainability of the project.
Disclosure of Consultants engaged – gives the names of the technical team involved in the
report preparation with accreditation of consultant from the Quality Council of India.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 5
1.8 PROFILE OF PROJECT PROPONENT
M/s. Juventus Estate Ltd. has nominated Mr. Tarun Arora as the authorized signatory to
represent the company before SEIAA/SEAC/EAC for Environmental Clearance of the project.
The contact details of project proponent are as follows:
Mr. Tarun Arora,
Authorised Signatory,
M/s. Juventus Estate Ltd.,
Indiabulls House, 448-451, Udhyog Vihar,
Phase, Gurugram, 121001,
Haryana
M: 9810778498
1.9 BRIEF DESCRIPTION OF PROJECT
1.9.1 Project Background
The project site is located at Village Dhanwapur, Sector-104, District Gurugram, Haryana with
Plot area = 1,37,685.79m2 (34.022 acre). The estimated built up area of the project post revision
& expansion will be 3,61,332 m2.
The geographical coordinates of project site are 28°29'06.35”N, 77°00'09.97"E.
There is neither any litigation (s) pending against the project and / nor any directions or order
passed by any court of law/any statutory body.
1.9.2 Site Description
The site has good road connectivity through Dwarka Expressway road, which is 200 m away in
West direction from project site.
The connecting links to the project site are NH-8 which is 5.41 km in SE direction of the project
site.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 6
Gurgaon Railway Station is approx. 1.2 km, NE from the project site & Indira Gandhi
International Airport is 12 km, NE from project site.
1.10 APPLICABLE LEGAL FRAMEWORK
The project falls under item 8(b), Category B, as per the EIA Notification 2006 and
amendments. The total estimated built-up area of the project (post revision & expansion) is
3,61,332 m2.
The project proponent is required to comply with the provisions of Environment Protection Act,
1986; Air (Prevention & Control of Pollution) Act 1981; Water (Prevention & Control of
Pollution) Act 1974 and Hazardous Waste Management Rules, 2016.
1.11 NEED OF THE EIA STUDY
The project activities must co-exist in harmony with its surrounding environment, to reduce the
environmental impact, which is likely to arise during various project activities. To safeguard the
environment from adverse effects of developmental activities, the MoEFCC has issued
guidelines to optimize the use of natural resources and protect environment for sustainable
development.
As per the MoEFCC notification dated 14.09.2006, EIA study is required to be carried out for
the projects having either plot area of 50 ha and or built up area greater than 1,50,000 m2. Since,
the estimated built-up area of the project (post modification & expansion) is 3,61,332 m2, an
EIA/EMP report has been prepared and submitted herewith for Environmental Clearance for the
project.
1.12 SCOPE OF STUDY
The scope of the EIA study is:-
• Compilation of baseline environmental and social scenario of the study area
within a radius of 10 km around the project site based on field studies covering one season
(December, 2016 to February, 2017), and secondary data;
• Identification, prediction and evaluation of potential environmental impacts
expected during the construction and operation phase of the project;
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 7
• Preparation of mitigation measures, Environmental Management Plan (EMP) and
Monitoring Programme for implementation of suggested mitigation measures.
1.13 STUDY METHODOLOGY
The approach followed for conducting the EIA study is in accordance with the applicable
regulatory framework. The main stages are described below:
Stage -I
• Review of design and operational information of the project from various plans, drawing and
identification of sources of major potential impacts.
•
Stage -II
• An initial review of the project site and status of the physical environment around the project
site vicinity;
• Understanding regarding project design and operation as well as macro environmental
aspects. The major issues needed to be addressed with due care were identified and monitoring
plan for the environmental baseline was prepared;
• Baseline environmental assessment was conducted within the study area of 10 km radius
around the project site;
• Intense monitoring and primary field data collection of environmental components viz.
Micro-Meteorological Condition, Ambient Air Quality, Water (Surface and Ground water) use
and its Quality, Soil Quality, Noise Level, Traffic Volume etc.;
• Survey study was carried out in the study area to assess the status of flora & fauna and socio-
economic profile of the study area; and
• Information was also collected through Secondary sources like Department of Census, Local
and City Offices, National Institutions (Survey of India, National Information Centre etc.),
District Head Quarters and other Government Offices etc. as well relevant Published Literatures.
Stage –III
• Compilation of the Baseline Environmental Study of the Area.
Stage –IV
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 8
• Assessment of Environmental Impact by predicting the scale and extent of
changes associated with the project and their subsequent effects on the environment against the
environmental baseline condition, and evaluating the significance of such impacts against
accepted criteria.
Stage -V
• Identification and preparation of measures to mitigate significant impacts
(evaluated from the impact prediction process) by proposing applicable alternatives and control
measures; and
• Finally, development of appropriate Environmental Management and
Monitoring Plan to audit and ensure that the proposed mitigation measures are in place and
effective.
1.14 EIA METHODOLOGY
The project may have impact on environment attributes such as air, water, noise level, soil
quality, hydrology and drainage pattern and meteorology of surrounding environment due to on-
going project. In assessing the environmental impact, collection, collation and interpretation of
baseline data is of prime importance. The objective of EIA is to predict and address potential
environmental problems/concerns at an early stage of project planning and design as the
infrastructure development has adverse impact on environment. EIA/EMP assists in the decision
making process by identifying the key impacts/ issues as a results of the activities and
formulating mitigation measures, leading to an improvement in environmental quality.
In order to achieve these objectives, the following procedures have been adopted for the study:-
• Collection, collation and analysis of regional and local environmental status for
various environmental attributes (like topography, geology, ambient air quality, meteorology,
water quality, noise level, soil characteristics and land use, transport, settlement status and socio
economic aspects etc.) to assess base-line status of the project.
• Identification of environmental impacts leads to assessment of impact on the
base-line status which will decide the feasibility of the project and suggests mitigation measures
to control pollution with respect to standards applicable for the area.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 9
• Evaluation of impacts leading to preparation of environmental management and
monitoring plan.
• Addition study will cover disaster management plan during construction and
operation phase of the project.
• Environment Monitoring Plan and annual budget – one time and recurring cost of
EMP will be discussed.
This report is based on scientific principles and professional judgment with resultant subjective
interpretation. Professional judgments expressed herein are based on the available data and
information.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 10
CHAPTER 2: PROJECT DESCRIPTION
2.0 INTRODUCTION
M/s. Juventus Estate Ltd., has proposed Modification & Expansion of Group Housing Colony
project at Village Dhanwapur , Sector-104, Gurugram, Haryana.
The project was earlier granted Environment Clearance by SEIAA, Haryana vide letter no.
SEIAA/HR/2014/923 dated 11/07/2014 for Plot area = 1,16,009.63 m2
(28.66665 acre) and
Built-up area = 3,75,674.82 sqm. A copy of the earlier EC letter is enclosed as Annexure – I.
The project has undergone some revision in planning, due to which the built-up area will reduce
to 3,61,332 sqm. As a result of additional license issued to the project by DTCP, Haryana, the
plot area increases from 1,16,009.63 m2 to 1,37,685.79 m
2 (34.022 Acre)
Project comprises of:
• Residential Units (Main units, EWS units, Servant units)
• Commercial Facilities
• Community Facility
• Schools
• Dispensary
• PROJECT LOCATION AND SITE SURROUNDINGS
2.1.1 Location
The Group Housing Colony project is located at Village Dhanwapur, Sector-104, Distt.
Gurugram, Haryana'
Geographical coordinates of project site are 28029
’06.35”N & 77
000’09.97”E.
Google earth image & SoI toposheet showing project site alongwith 500 m, 2 km, 5 km and 10
km radius maps are attached as Annexures - IX (A), IX(B) , IX(C) & IX(D).
2.1.2 Connectivity and Infrastructure
The site has good road connectivity through the Dwarka Expressway road, which is 200 m away
in West direction from project site.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 11
The connecting links to the project site are NH-8 which is 5.41 km in SE direction of the project
site.
Gurgaon Railway Station is approx. 1.2 km, NE from the project site & Indira Gandhi
International Airport is 12 km in NE direction.
2.2 BRIEF PROJECT DETAILS
The total plot area (post modification & modification) is 1,37,685.79 m2
(34.022 acre). The
detailed area statement is given below in Table 2.1 and break-up of built-up area is provided in
Table 2.2:
Table 2.1: Detailed Area Statement (Post Modification& Expansion)
S.
No.
Particulars Value as per
earlier EC
(m2)
Modification/Expansion
(m2)
Total
(Post
Modification &
Expansion)
(m2)
1. Total Plot Area 1,16,009.63 21,676.16 1,37,685.79
Site area as per
zoning
1,37,428.411
Plot area in intense
zone (32.522 acre)
1,31,613.2744
Plot area in
transition zone
(1.437 acres)
58,15.33
Net Plot area 1,26,055.128
2. Permissible
Ground Coverage
40,603.37
(@35%)
14,470.946 55,074.316
(@40%)
3. Proposed Ground
Coverage
28,242.13
(@24.34 %)
- 15,775.28 13,591.98
(@9.89%)
4. Permissible FAR
• Permissible
FAR in Intense
Zone @3
• Permissible
FAR in Transition
Zone @2.5
2,03,016.86
(@ 1.75)
2,56,709.346 4,09,378.13
(@ 3.0)
3,94,839.8232
14,538.31
5. Proposed FAR 2,03,016.8 22,167.269 2,25,184.069
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 12
• Total FAR under
Phase 1
• Total FAR under
in Phase 2
• Total FAR under
Phase 3
(@ 1.75) (@163.885%)
97,832.36
1,27,351.71
Nil
6. Non-FAR Area 1,72,658.02 -36,510.09 1,36,147.93
7. Built-up Area 3,75,674.82 -14,342.82 3,61,332
8. Landscape Area 35,724.15
(@ 30%)
6,683.07 37,816.538
(@ 30% of net
plot area)
9. Basement area 1,22,133.94 - 16,465.94 1,05,668
• Basement 1
• Basement 2
• Basement 3
56,338.58
53,043.28
12,752.08
-11935.59
-8539.28
4009.92
44403
44504
16,762
10. Maximum Height
of the Building (m)
129.151 -1.151 128
Table 2.2: Built-up Area Details
S.
No.
Particulars Value as per
earlier EC
(m2)
Modification/Expansion
(m2)
Total (Post
Modification
&
Expansion)
(m2)
1. FAR Area 2,03,016.8 22,167.269 2,25,184.069
2. Non-FAR Area 1,72,658.02 -36,510.02 1,36,148
Built-up Area 3,75,674.82 -14,342.82 3,61,332
2.3 POPULATION DETAILS
The residential population of the project will be 12,461 persons, floating population including
staff and visitors will be 796 and 2132 respectively. So, the total population for the project is
14,910 persons.
The comparative population details are given below in the Table 2.3:
Table 2.3: Comparative Population Details
S. No. Particulars Value as per EC
Accorded
Modification/Expansion Total
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 13
1 Population 7228 7682 14,910
The detailed population calculations are given below in the following Table 2.4:
Table 2.4: Population Break up (Post Modification & Expansion)
S. No. Unit Type No. of DUs PPU Total Population
1. Residential Facilities:
• Main Dwelling Units 810 +1107 =1917 5 9585
• EWS Units 181+220 = 401 5 2005
• Units with Servant room 86+110 =196 2 392
• Staff @5% of main units 479
Sub-Total 12,461
2. Community
Building(5474.3 sqm):
• Staff
• Visitors
@ 1person/10 m2
547
109
438
3. Convenient Shopping
(682.38sqm):
• Staff
• Visitors
@ 1person/3 sqm
227
45
182
4. Schools (3861.603 sqm)
• Staff
@ 1person/4 sqm
(10%)
96
5. Dispensary (1334 sqm)
• Staff
• Visitors
@ 1person/4 sqm
333
67
266
6. Visitors @10% of residential
population
1246
GRAND TOTAL 14,910
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 14
2.4 POWER SUPPLY
2.4.1 Power Requirement
The power will be supplied by Dakshin Haryana Bijli Vitran Nigam. The total connected load for
the project post modification & expansion will be approx. 15,255 KW which shall be supplied by
3 transformers of total 11,402 kVA (6 x 2000) capacity.
2.4.2 Power back-up
There is provision of 4 no. of DG sets of total 9684 kVA (6x1500 + 2x 1010) capacity for power
back up. The DG sets will be equipped with acoustic enclosure to minimize noise generation and
adequate stack height for proper dispersion.
2.5 PARKING
Adequate provision will be made for car/vehicle parking within the project site. Details are as
provided below:
PARKING REQUIRED
As per MoEFCC Norms:
1 ECS / 100 sqm FAR area for residential = 197721.79/ 100 = 1978ECS
1 ECS / 50 sqm FAR area for Community = 5474.54/ 50 = 110 ECS
1 ECS / 50 sqm FAR area for Convenient shopping = 682.38/ 50 = 14 ECS
1 ECS / 50 sqm FAR area for Schools = 3861.603/ 50 = 78 ECS
1ECS/100 sqm FAR for EWS Housing = 9711.75/100 = 98 ECS
Total parking required as per MoEFCC norms = 1978 + 110+ 14 + 78 + 98
= 2278 ECS
As per bye-laws:
For Residential projects
0.5 ECS per DU of carpet area < 100 sqm. (1373 DU’s) = 687 ECS
1 ECS per DU of carpet area >100 sqm. (529 DU’s) =529 ECS
1.5 ECS per DU of carpet area >150 sqm (15 DU’s) =23 ECS
Parking requirement for EWS @ 5% of residential parking = 62 ECS
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 15
Total parking required as per Bye-laws = 1301 ECS
PARKING PROPOSED
Area proposed for Open parking = 3354.566 m2
Area proposed for 1 ECS of Surface Parking = 23 m²
Parking proposed for open parking = 146 ECS
Area proposed for basement level 1 parking = 43399.954m2 (16005.086+27394.868)
Area proposed for 1 ECS of basement 1 parking = 32 m²
Parking proposed for basement 1 parking = 1357 ECS
Area proposed for basement level 2 parking = 43,522.085m2 (15920.205+27601.880)
Area proposed for 1 ECS of basement 2 parking = 32 m²
Parking proposed for basement 2 parking = 1360 ECS
Area proposed for basement level 3 parking = 15915.222m2
Area proposed for 1 ECS of basement 3 parking = 32 m²
Parking proposed for basement 3 parking = 498 ECS
Area proposed for Stilt parking = 991.982 m2
Area proposed for 1 ECS of Stilt parking = 28 m²
Parking proposed for Stilt parking = 35 ECS
TOTAL PROPOSED PARKING = 3395 ECS
2.6 WATER REQUIREMENT
The water will be provided by HUDA. The total water requirement is approx 1343KLD out of
which domestic water requirement is 1075 KLD. Total fresh water requirement will be approx.
804 KLD.
Comparative daily water demand calculation are shown below in Table 2.5.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 16
Table 2.5: Comparative daily water demand calculation
S.No. Particulars Value as
per earlier
EC (KLD)
Modification/Expansion
(KLD)
Post Modification &
Expansion (KLD)
1 Total water
requirement
1112 231 1343
2 Domestic Water 826 249 1075
3 Fresh Water 593 208 801
4 Waste Water 710 205 915
5 STP capacity 850 250 1100
The daily water requirement and waste water calculations are given below in Table 2.6 & 2.7
respectively:
Table 2.6: Daily Water Demand Calculation
(Post Modification & Expansion)
S.
No.
Description Occupancy
Rate of water demand
(lpcd)
Total Water demand (post
Modification & Expansion)
A. Domestic Water
Fresh Flushing Fresh Flushing Total • Main
Dwelling
Units
9585 @ 65 lpcd @ 21
lpcd
623 201 824
• EWS Units 2005 @ 65 lpcd @ 21
lpcd
130 42 172
• Units with
Servant room
392 @ 65 lpcd @ 21
lpcd
25 8 33
• Staff
(Schools,
Commercial,
Community
facilities,
796 @15 lpcd @15 lpcd 12 12 24
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 17
Dispensary,
etc) • Visitors
(Schools,
Commercial,
Community
facilities,
Dispensary,
etc)
2132 @ 5 lpcd @5 lpcd 11 11 22
801
KLD
274
KLD
1075
KLD
Total Domestic Water = 1075 KLD
B. Horticulture 37, 816.538 m2
7 l/sqm 265 KLD
C. Make up
Water for
Swimming
Pool
3 KLD
Grand Total (A+B+ C) = 1343 KLD
Table 2.7: Waste Water Calculations (Post Modification & Expansion)
Domestic Water 1075 KLD
• Fresh/Potable water 801 KLD
• Flushing water 274 KLD
Waste water [@80% fresh + 100% flushing] 641 +274= 915 KLD
STP capacity 1100 KL
The water balance diagrams are given in Figure 2.1, 2.2 & 2.3:
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 18
Figure 2.1: Water Balance Diagram (Summer Season)
@ 100% SULLAGE GENERATED =
(915 KLD + 72 KLD)
STP CAPACITY = 1100 KL
Treated effluent
FRESH WATER
(801 KLD)
FLUSHING
(274 KLD)
DISCHARGE TO
EXTERNAL SEWER
(284 KLD)
274 KLD
265 KLD
@ 80%
HORTICULTURE*
(265 KLD)
Wastewater
@ 9
0%
of
91
5 K
LD
= 8
23
KL
D
EVAPORATED WATER
(2 KLD)
(2 % of total untreated
water)
WET SLUDGE
(90 KLD)
(98% of total untreated
water)
@ 1
0%
of
91
5 K
LD
= 9
2 K
LD
@ 80%
72 KLD
90 KLD
2 KLD
*Considering horticulture water demand @7l/sqm
SWIMMING POOL
(3 KLD)
FRESH WATER
(801 + 3 =804 KLD)
3 KLD
284 KLD
Fresh water
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 19
Figure 2.2: Water Balance Diagram (Monsoon Season)
@ 100% SULLAGE GENERATED =
(915 KLD + 72 KLD)
STP CAPACITY = 1100 KL
Treated effluent
FRESH WATER
(801 KLD)
FLUSHING
(274 KLD)
DISCHARGE TO
EXTERNAL SEWER
(434 KLD)
274 KLD
114 KLD
@ 80%
HORTICULTURE*
(114 KLD)
Wastewater
@ 9
0%
of
91
5 K
LD
= 8
23
KL
D
EVAPORATED WATER
(2 KLD)
(2 % of total untreated
water)
WET SLUDGE
(90 KLD)
(98% of total
untreated water)
@ 1
0%
of
91
5 K
LD
= 9
2 K
LD
@ 80%
72 KLD
90 KLD
2 KLD
*Considering horticulture water demand @3l/sqm
SWIMMING POOL
(3 KLD)
FRESH WATER
(801 + 3 =804 KLD)
3 KLD
434 KLD
Fresh water
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 20
Figure 2.3: Water Balance Diagram (Winter Season)
Waste Water Generation & Treatment
It is expected that the total project will generate approx. 915 KLD of Waste water. The Waste water will
be treated in the STP provided within the complex generating 1100 KLD of treated water from STP
which will be recycled within the project but 284 KLD, 434 KLD,398 KLD will become surplus in
summer, Monsoon & Winter seasons which can be used for nearby construction activities/discharge to
external sewer.
@ 100% SULLAGE GENERATED =
(915 KLD + 72 KLD)
STP CAPACITY = 1100 KL
Treated effluent
FRESH WATER
(801 KLD)
FLUSHING
(274 KLD)
DISCHARGE TO
EXTERNAL SEWER
(398 KLD)
274 KLD
151 KLD
@ 80%
HORTICULTURE*
(151 KLD)
Wastewater
@ 9
0%
of
91
5 K
LD
= 8
23
KL
D
EVAPORATED
WATER
(2 KLD)
(2 % of total untreated
water)
WET SLUDGE
(90 KLD)
(98% of total
untreated water)
@ 1
0%
of
91
5 K
LD
= 9
2 K
LD
@ 80%
72 KLD
90 KLD
2 KLD
*Considering horticulture water demand @4l/sqm
SWIMMING POOL
(3 KLD)
FRESH WATER
(801 + 3 =804 KLD)
3 KLD
398 KLD
Fresh water
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 21
10% of the waste water that is to be treated is removed from the STP in form of sludge as well as
vapors.
Out of this 10%, approx. 98% of the untreated waste water is removed as wet sludge, which is then
dewatered by passing through a filter press and extracted water is added back to the collection chamber of
the STP. Somewhat around 40% of the moisture of the sludge is retained, and the sludge thus generated is
further processed by drying the same on a non-permeable bed, which upon drying can be used as manure
in the green area provided within the project site. The wet sludge is generally removed during the
processes of primary treatment, secondary treatment and tertiary treatment or scrubbed off of the
collection tank.
Remaining 2% of waste water is evaporated from the system during treatment process and thus cannot
be converted into sewage.
2.7 SEWAGE TREATMENT PLANT (MBBR TECHNOLOGY)
Sewerage System
An external sewage network will collect the sewage from all units, and flow by gravity to the
sewage treatment plant.
Following are the benefits of providing Sewage Treatment Plant:
• Reduced net daily water requirement.
• Reduced dependence on public utilities for fresh water supply and sewerage system.
• Sludge generated from the Sewage Treatment Plant shall be rich in organic content and
used as manure for horticultural purpose.
(a) Wastewater Details (Inlet)
(a) Daily load : 915 KLD
(b) Duration of flow to STP : 24 hours
(c) Temperature : Maximum 32oC
(d) pH : 6.5-8.5
(e) Colour : Mild
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 22
(f) T.S.S. (mg/l) : 250-400 mg/l
(g) BOD5 (mg/l) : 300-400 mg/l
(h) COD (mg/l) : 600-700 mg/l
(b) Treated effluent (Outlet)
(a) pH : 6.0 to 8.5
(b) B.O.D. : <20 mg/l
(c) C.O.D. : <100 mg/l
(d) Total Suspended Solids : <20mg/l
Treatment Technology
Moving bed biofilm reactor technology is based on the principle of attached growth process.
Raw sewage will be collected under gravity into the equalization tank after allowing to pass
through the bar screen. Screens will be provided in screen chambers and it will be manually
cleaned by going down to a platform. The bar screen, by removing coarse solids from the
sewage help in protecting the raw sewage pump.
Fully submersible centrifugal non clog sewage handling pump will be provided in the
collection cum equalization tank to pump the collected waste water to the next MBBR tanks.
Automatic level controller will be provided in the tank to turn the pump off at the low water
level in the tank and to start the pump when water level is high automatically. Air will be
introduced in this tank to prevent any potential foul smell problem & to provide the mixing of
wastewater to avoid the sedimentation of solids in this tank. Air Grid used for aeration
purpose shall be non-clog.
The sewage collected in equalization tank is pumped the moving bed bioreactor. There shall
be two nos. of bioreactors in series for the efficient working and removal of BODs for the
required retention time. The process inside the moving bed bioreactors consists of adding
small cylindrical-shaped polyethylene/polypropylene carrier elements in aerated basins to
support biofilm growth. The small cylinders are provided with a cross inside the cylinder and
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 23
longitudinal fins on the outside. The biofilm carriers are maintained in the reactor by the use
of a perforated plate with appropriate slot at the tank outlet. Air agitation or mixers are applied
in a manner to continuously circulate the packing. The packing may fill 25 to 50 percent of the
tank volume. Specific surface area of the packing is about 450-500m2/m
3 of bulk packing
volume. The waste water from first bioreactor flows by gravity through the perforated
plate/mesh to the next bioreactor kept in series. Inside the bioreactors, aerobic bacteria grow in
an attached growth from around the moving plastic media inside the reactors. The bacteria
have to reduce BOD & COD of waste water in the presence of oxygen provided through the
air grids located at the bottom of the reactors. The Process does not require any return
activated sludge flow or backwashing.
From the bio-reactors, the effluent passes by gravity into the clarifier (Tube Settling Tank).
Clarifier will be a hopper bottom sedimentation tank provided with appropriate size PVC tube
deck media. The suspended solids will settle at the bottom of the tank & clear supernatant will
overflow to filter feed tank through outlet launder. The collected sludge at bottom shall be
transferred through pumps to sludge holding tank.
The clear supernatant after clarifier will be collected in to filter feed tank. This tank will act as
housing tank for filter feed pumps. The clarified & dis-infected water will be then fed to
filtration unit.
Filtration unit consisting of Dual Media sand filter, activated carbon filter and ultra-filtration
system (optional) will remove the residual impurities such as odor/color, suspended solids,
BOD/COD. The treated water after the filtration unit will be collected in Irrigation cum
Flushing water storage tank from where it is transferred to flushing water tank at terrace &
Irrigation System.
Excess sludge from the bottom of the settling tank will be removed and transferred to sludge
holding tank. Air grid shall be provided in this tank to avoid conversion into anaerobic
conditions, thickening of sludge and keep sludge in homogenous condition. The digested &
thickened sludge shall be further thickened through Sludge Dewatering System (Filter press with
screw pump) and disposed-off periodically through closed tanker or can be reused as manure.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 24
Figure 2.4: Schematic Diagrams for STP Based on MBBR Technology
2.8 RAINWATER HARVESTING
The storm water collection system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run
off from roads shall flow towards the drains. Storm water from various plots/shall be connected
to adjacent drain by a pipe through catch basins. Therefore, it has been proposed to provide 35
rainwater harvesting pits at selected locations, which will catch the entire run-off from site.
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at
regular intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm
water storage tank. This water will be pumped out to the nearest external storm water
drain.
4) The peak hourly rainfall of 45 mm/hr shall be considered for designing the storm water
drainage system.
The recharge pit will have 4 m diameter and 2.5 m depth. Inside the recharge pit, a recharge bore
is constructed having adequate diameter and depth. The bottom of the recharge structure will be
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 25
kept 5 m above the confined aquifer level. At the bottom of the recharge well, a filter media is
provided to avoid choking of the recharge bore. Design specifications of the rain water
harvesting plan are as follows:
• Catchments/roofs would be accessible for regular cleaning.
• The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
• All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is
flushed off.
• No sewage or wastewater would be admitted into the system.
• No wastewater from areas likely to have oil, grease, or other pollutants has been
connected to the system.
Calculations for storm water load:
Net Plot Area = 1,26,055.128 m2
Roof-top area = Ground Coverage = 13,591.98 m2
Green Area = 37,816.538 m2
Paved Area = Plot Area – (Roof-top Area + Green Area)
= 1,26,055.128 – (13,591.98 + 37,816.538)
= 1,26,055.128 – 51,408.518
= 74,646.61m2
Roof-top area = 13,591.98 × 0.045 × 0.90
= 550.475m3/hr
Green Area = 37, 816.538 × 0.045 × 0.20
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 26
= 340.34 m3/hr
Paved Area = 74,646.61× 0.045 × 0.70
= 2351.368m3/hr
Total Runoff Load = 550.475 + 340.34 + 2351.368
= 3242.183m3/hr
Taking 20 minutes retention time, volume of storm water =3242.183/3 = 1080.72m3
Capacity of a Recharge pit = π r2h = 3.14 × 2 × 2 × 2.5 = 31.4 m
3
Hence No. of pits required = 1080.72/31.4= 34.41 pits
Total of 35 Rain Water Harvesting pits are proposed for artificial ground water recharge within
the project premises.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 27
Figure 2.5: Rain Water Harvesting Pit Design
2.9 SOLID WASTE MANAGEMENT
Solid waste would be generated both during the construction as well as operation phase. The
solid waste expected to be generated during the construction phase will comprise of excavated
materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed
to be followed for the management solid waste:
• Garbage Bins are proposed for storage of construction materials.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 28
Solid Waste
Construction
Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty
Cement
Bags
Used in re-filling,
raising site level Road making
Excavated
Soil
Top soil conserved for
landscaping, balance used
in re-filling
• The excavated material such as topsoil and stones will be stacked for reuse during later
stages of construction
• Excavated top soil will be stored in temporary constructed soil bank and will be reused
for landscaping of the commercial project.
• Remaining soil shall be utilized for refilling / road work / rising of site level at locations/
selling to outside agency for construction of roads etc.
Figure 2.6: Solid Waste Management Scheme (Construction Phase)
During the operation phase, approx. 6537.288 kg/day (@ 0.5 kg per capita per day for residents,
@ 0.15 kg per capita per day for the visitor, @ 0.25 kg per capita per day for the staff members
and landscape wastes @ 0.2 kg/acre/day).
Solid waste calculations are given below in Table 2.7:
Table 2.7: Solid Waste Claculations
S.
No.
Description Norms (kg/c/day) Total Waste (Post
Modification &
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 29
Expansion)
(kg/day)
1.) Domestic Solid waste
• Main Dwelling Units 9585@ 0.5 4792.5
• EWS Units 2005 @ 0. 5 1002.5
• Units with servants room 392 @ 0. 5 196
• Staff (Schools, Commercial,
Community facilities,
Dispensary etc)
796 @ 0.25
199
• Visitors (Schools,
Commercial, Community
facilities, Dispensary etc)
2132 @ 0.15
319.8
2.) Horticultural waste (9.34 acre) @ 0.2 kg/acre/day 1.868
3.) STP Sludge Waste water x 0.35
x B.O.D
difference/1000
25.62
TOTAL SOLID WASTE 6537.288 kg/day
(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment
Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)
• Collection and Segregation of waste
• Door to door collection system will be provided for collection of solid waste through
colored bins.
• An authorized local vendor will be hired fort management of solid waste.
• Litter bins will also be provided in open areas.
• Treatment of waste
Bio-Degradable waste
• Bio-degradable waste will be subjected to composting through Organic Waste Converter.
• STP sludge is proposed to be used for horticultural purpose.
• Horticultural Waste is proposed to be composted and used as manure.
Recyclable waste
• Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
• Recyclable waste like paper, plastic, metals etc. will be sold off to local approved
recyclers.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 30
• Disposal
Disposal of waste will be done through a local approved agency. Solid Waste Management
Scheme for Opeartion phase is depicted in the following figure:
Figure 2.7: Solid Waste Management Scheme (Operation Phase)
Organic Waste Converter:
Organic Waste Converter - 300 (Dim. 3m × 4m) is proposed to be used for composting waste
120kg/batch or 3000 kg/day & it requires electricity of about 13.5 HP.
No. of batches /day = 3000/120 = 25
No. of batches to convert 3922.372 kg/day = 3922.372 /120 =32.6 say 33 batches
Monthly per Capita Operation Cost:
The operating cost of OWC - 300 = 1, 80,000 INR/month
Cost/day = 1, 80,000/30
= 6000/-
1 batch/day cost = 6000/25
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 31
= 240 INR
Cost for 33 batch/day = 33 × 240/-
= 7920/-
Monthly operating cost = 30 × 7920
= INR 2, 37,600/- per month
2.10 LANDSCAPE
Total green area measures 37,816.538m2 i.e 30% of net plot area which includes Shelter belt,
Avenue plantation and lawn.
Evergreen tall and ornamental trees like Anthocephalus cadamba, Lagerstromeia indica,
Plumeria alba, Thuja occidentallis, Polyalthia longifolia are proposed to be planted inside the
premises.
2.11 FIRE FIGHTING SYSTEM
Following provisions will be made according to National Building Code, 2016;
• Fire-Water tanks;
• Firewater inlet and outlet connections will be provided to the water storage tanks;
• External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing
will be provided. This external fire ring will be separated from the Sprinkler Main Systems;
• All flow switches, test valves, drain pipes etc. will be provided as per NFPA
guidelines on the sprinkler system;
• All pump installation and arrangements will be in accordance with IRI guidelines
and NFPA-20;
• All pumps and accessories and electrical controllers will be as per UL/FM lists,
tested, approved and certified; and
• By-pass arrangements will to be provided (150 mm diameter nominal bore) with
NRV and gate valve and bulk flow meter on the discharge header of each pump to check the
duties of pumps.
• The fire extinguishers provided would be in conformance with Ozone Depleting
Substances (Regulation and Control) Rules, 2000.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 32
CHAPTER 3: DESCRIPTION OF ENVIRONMENT
3.1 INTRODUCTION
Information on the existing environmental status is essential for assessing the likely
environmental impacts of the project. In order to get an idea about the existing state of the
environment, various environmental attributes such as meteorology, air quality, water quality,
soil quality, noise level, ecology and socio-economic environment have been studied/ monitored.
3.2 STUDY PERIOD
Baseline environmental data generation for air, water, noise and soil quality monitoring around
the project site was conducted from December 2016 to February, 2017. Apart from field
monitoring, additional data was also collected from secondary sources like irrigation department,
India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of
India, State Ground Water Department, State Pollution Control Board, Census of India and Local
Forest Department, Non - Governmental Agencies, etc.
3.3 STUDY AREA
The present report covers baseline environmental data generated in the study area (10 Km radius
around the project site for land use and the sample selection for air, water, soil and noise
monitoring).
3.4 BASELINE MONITORING OF ENVIRONMENTAL COMPONENTS
In order to get an idea about the existing state of the environment, various environmental
attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology and
socio-economic environment have been studied/monitored.
3.4.1 Meteorology
Climate
The Gurgaon district receives most of the rainfall during June to September. The district is
characterized by a warm climate in March to June and later on there is a gradual decline in
temperature from October onwards to December. December and January are the coolest months
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 33
of the year in Gurgaon. March, April and May are the hot and dry months of the district. During
winter season the district records temperature between 5 to 21 °C while, during summer the
temperature ranges from 30° to 44° C.
Meteorological data was generated during the December 2016-February 2017. The following
parameters were recorded at hourly intervals continuously during monitoring period:
• Air Temperature
• Wind speed
• Wind Direction
Table - 3.1 gives summarized meteorological data for the monitoring period (March-May 2017).
Figure - 3.1 gives the wind-rose diagram for the monitoring period.
Table 3.1: Meteorological Data for December 2016-February 2017
Month Temperature in Kelvin
(K)
Wind Speed
(km/h)
Min Max Average Min Max Average
December 287 310 300.4 1 6.2 2.41
January 285 305 294.3 1 5.7 2.13
February 277 300 288.2 1 6.2 2.29
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 34
Figure 3.1: Wind rose for December 2016 to February 2017
3.4.2 Air Environment
The prime objective of the baseline study with respect to ambient air quality is to establish the
present air quality and its conformity to National Ambient Air Quality Standards. This data has
been further used during impact assessment to predict the final air quality. This section describes
the sampling locations, frequency of sampling and methodology adopted for monitoring ambient
air quality.
To quantify the impact of the project on the ambient air quality, it is necessary at first to evaluate
the existing ambient air quality of the area. The existing ambient air quality, in terms of
Particulate Matter – 10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide (SO2), Oxides of
Nitrogen (NO2), and Carbon Monoxide (CO), has been measured through a planned field
monitoring.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 35
To assess the ambient air quality level, 6 (six) monitoring stations were set up. Table - 3.2 gives
location of the ambient air quality monitoring stations and a map showing the ambient air quality
monitoring stations is attached as Annexure - VII.
Table 3.2: Location of Ambient Air Quality Monitoring Stations
Location Code Location Direction Distance (km)
AAQ1 Project site Center -
AAQ2 Sector 99 A SW 4.50 km
AAQ3 Garoli Khurd SSW 4.80 km
AAQ4 Basai Village S 2.70 km
AAQ5 Daya Vihar WSW 5.45 km
•
• 3.4.2.1 Monitoring Schedule
Ambient air quality monitoring was carried out twice a week with a frequency of 24 hours for 12
weeks.
3.4.2.2 Methods of Sampling and Analysis
The brief methodology of the parameter analyzed is as follows:
• Particulate Matter (PM2.5): (CPCB Method) Particulate Matter (PM2.5) was analyzed by
Fine particulate Sampler Enviro tech Model APM 550. PM 2.5 was collected on 47mm
diameter filter paper. The mass concentration of (PM2.5) fine particles in ambient air was
calculated as the total mass of collected particles divided by the volume of air sampled.
• Particulate Matter (PM10): Particulate Matter (PM10) was carried out by respirable dust
sampler enviro tech Model APM 460 BL. The cyclone of this instrument is used for
fractionating the dust into two fractions. PM 10 dust is accumulated on the filter paper
(8ʺ×10ʺ size) while coarse dust is collected in a cup placed under the cyclone.PM 10 was
calculated as per IS: 5182 (Part 23):2006. The mass of these particles was determined by
the difference in filter weight prior to and after sampling. The concentration of PM 10 in
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 36
the designated size range was calculated by dividing the weight gain of the filter by the
volume of air sampled.
• Sulphur dioxide (SO2): SO2 was monitored with the help of APM 411 assembly attached
with APM 460 BL using the impinge. It was absorbed by aspirating a measured air
sample through a solution of Potassium tetrachloromercurate (TCM). This procedure
resulted in the formation of a dichloro sulphite mercurate complex. The complex was
made to react with pararosaniline and methylsulphonic acid. The absorbance of the
solution was measured by means of spectrophotometer.
• Nitrogen Dioxides: NO2 was monitored with the help of APM 411 assembly attached
with APM 460 BL using the impinge. It was collected by bubbling air through a solution
of sodium hydroxide and sodium arsenite. The concentration of nitrite ion produced
during sampling was determined colorimetrically by reacting with the nitrite ion with
phosphoric acid, sulphanilamide and NEDA and absorbance of highly colored azo-dye
was measured at 540nm.
• Carbon Monoxide: It is measured using CO Analyser. This analyser is used to measure
CO in ambient air, in the range of 0-200 ppm (220 mg/m3) to a sensitivity of 0.05 ppm
(55µg/m3). The Serinus 30 combines the benefits of Microprocess control with Non-
Dispersive Infrared Spectrophotometry technology. CO concentration is automatically
corrected for gas temperature and pressure changes. CO was monitored on hourly basis
whereas other parameters were monitored on 24 hourly bases.
• 3.4.2.3 Results and Discussions
The results of AAQ are summarized in the tables below. The results when compared with
National Ambient Air Quality Standards (NAAQS) of Central Pollution Control Board
(CPCB) for "Industrial, Residential, Rural and Other Areas" show that the average values of
ambient air quality parameters are well within the stipulated limit.
Table 3.3 (b) Ambient Air Quality with respect to PM2.5
PM2.5 (µg/m3) For Dec 2016-Feb 17
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ
5
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 37
Min 94.2 94.1 92.6 87.5 89.6
Max 112.8 112.2 110.5 121.0 106.7
Average 104.1 103.0 101.4 110.3 98.4
98 Percentile 112.8 111.1 109.4 120.7 106.1
The values of PM2.5 in study area are presented in Table 3.3 (a). The seasonal minimum,
maximum, average values and 98 percentile of PM 2.5 were observed 87.5µg/m3,
121.0µg /m3, 110.3 µg/m
3 and 120.7µg/m
3 respectively at the project site. The seasonal
minimum, maximum and average values ranged between 87.5-94.2µg/m3, 106.7-121.0
µg/m3 and 98.4-110.3µg/m
3 respectively in the study area
Table 3.3 (c) Ambient Air Quality with respects to PM10
PM10 (µg/m3) For Dec 2016-Feb 17
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ
5
Min 176.7 178.5 175.8 188.6 157.0
Max 197.4 199.7 198.5 211.7 190.2
Average 190.2 190.7 189.5 200.4 172.7
98
Percentile 197.4 199.6 197.6 211.6 186.0
The values of PM10 in study area are presented in Table 3.3 (b). The seasonal minimum,
maximum, average values and 98 percentile of PM10 were observed 157.0 µg/m3, 211.7 µg /m
3,
200.4 µg/m3 and 211.6µg/m
3 respectively at the project site. The seasonal minimum, maximum
and average values ranged between 157.0-188.6µg/m3, 190.2-211.7µg/m
3 and 172.7-200.4µg/m
3
respectively in the study area.
Table 3.3 (e) Ambient Air Quality with respect to SO2
SO2 (µg/m3) For Dec 2016-Feb 17
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ
5
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 38
Min 8.0 11.1 9.6 10.6 8.9
Max 10.2 13.6 12.7 14.1 11.0
Average 9.2 12.3 11.2 12.6 9.9
98
Percentile 10.2 13.5 12.6 14.0 10.9
The values of SO2 in study area are presented in Table 3.3 (c). The seasonal minimum,
maximum, average values and 98 percentile of SO2 were observed 8.0µg/m3, 14.1µg /m
3, 12.6
µg/m3 and 14.0µg/m
3 respectively at the project site. The seasonal minimum, maximum and
average values ranged between 8.0-11.1µg/m3, 10.2-14.1µg/m
3 and 9.2-12.6µg/m
3 respectively
in the study area.
Table 3.3 (g) Ambient Air Quality with respect to NO2
NO2 (µg/m3) For Dec 2016-Feb 17
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ
5
Min 35.8 25.9 21.5 28.9 30.7
Max 45.4 34.4 28.5 40.7 38.4
Average 40.2 29.3 25.2 34.6 33.8
98 Percentile 44.4 33.7 28.4 40.2 38.4
• The values of NO2 in study area are presented in Table 3.3 (d). The seasonal minimum,
maximum, average values and 98 percentile of NO2 were observed 21.5 µg/m3, 45.4µg /m
3,
40.2 µg/m3 and 44.4µg/m
3 respectively at the project site. The seasonal minimum, maximum
and average values ranged between 21.5-35.8µg/m3, 28.5-45.4µg/m
3 and 25.2-40.2µg/m
3
respectively in the study area.
• Table 3.3 (i) Ambient Air Quality with respect to CO
CO (µg/m3) For Dec 2016-Feb 17
Location AAQ
1 AAQ
2 AAQ
3 AAQ
4 AAQ
5
Min 1270 1150 1170 1150 1110
Max 1690 1510 1580 1460 1540
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 39
Average 1458 1305 1383 1304 1351
98
Percentile 1644 1505 1580 1446 1540
• The values of CO in study area are presented in Table 3.3 (e). The seasonal minimum,
maximum, average values and 98 percentile of CO were observed 1110 µg/m3, 1690 µg/m
3,
1458µg/m3 and 1644 µg/m
3 respectively at the project site. The seasonal minimum,
maximum and average values ranged between 1110-1270 µg/m3, 1460-1690 µg/m
3 and
1304-1458µg/m3 respectively in the study area.
• 3.4.3 Noise Levels
Noise is one of the most undesirable and unwanted by-products of our modern life style. It may
not seem as insidious or harmful as air and water pollutants but it affects human health and well-
being and can contribute to deterioration of human well-being in general and can cause
neurological disturbances and physiological damage to the hearing mechanism in particular. It is
therefore, necessary to measure both the quality as well as the quantity of noise in and around the
site.
• 3.4.3.1 Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is
expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an additional
circuit (filters) is provided, which modifies the received signal in such a way that it replicates the
sound signal as received by the human ear and the magnitude of sound level in this scale is
denoted as dB (A). The sound levels are expressed in dB (A) scale for the purpose of comparison
of noise levels, which is universally accepted by the international community.
Noise levels were measured using an Integrating sound level meter manufactured by Pulsar
Instruments PLC, Model NO. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq.
Keeping the mode in Lp for few minutes and setting the corresponding range and the weighting
network in “A” weighting set the sound level meter was run for one hour time and Leq was
measured at all locations.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 40
The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels,
during 10.00 pm to 6.00 am at all the 4 locations, which covers residential areas, and silence area
within 6 km radius of the study area.
• 3.4.3.2 Sampling Locations
A preliminary survey was undertaken to identify the major noise generating sources in the area.
The noise survey was conducted to assess the background noise levels in different zones.
Gazettes Notification (S.O. 123(E)) of MoEFCC dated December 14, 2000 on ambient air
quality standards has different noise levels for different zones viz. project site, industrial, and
residential zones. Four sampling locations were selected for the sampling of noise levels. The
sampling locations are given in Table - 3.4 below. Map showing the noise monitoring stations is
attached as Annexure - VIII
Table 3.4 Noise Level Monitoring Stations in the Study Area
Location
Code Locations Type of Area
Direction Distance
NQ1 Project site Silence zone - -
NQ2 Basai Villege Residential Zone S 2.70
NQ3 Vee Kay industries Industrial Zone S 6.25
Ministry of Environment, Forests and Climate Change (MoEFCC) has notified the noise
standards vide gazette notification dated December 14, 2000 for different zones under the
Environment Protection Act (1986). These standards are given in Table - 3.5.
Table 3.5 Ambient Quality Standards in Respect of Noise
Area
Code Category of Area
Noise dB(A) Leq
Day time* Night time*
A Residential Zone 55 45
B Silence zone 50 40
C Industrial Zone 75 70
D Commercial Zone 65 55 Note:
• Daytime is from 6.00am to 10.00 pm and Night time is from 10.00 pm to 6.00 am.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 41
• Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions and
courts. Use of vehicle hours, loud speakers and bursting of crackers are banned in these zones.
3.4.3.3 Results and Discussion
The noise data compiled on noise levels during March – May 2016 is given in Table - 3.6. The
ambient noise level at the project site during the day was 56.8 dB (A) which is just above the
limit of residential area as ~55 dB (A) during night it is 41.7 dB(A) which is also within the
limit. For maintaining the noise level, plantation and traffic management during the operation
phase are suggested.
Table 3.6: Hourly Leq Noise Level in the study Area
NOISE QUALITY DATA JAN - 2017
S.No. LOCATION ZONE LIMIT as per CPCB
Guidelines Leq, dB(A) Observed value
Leq, dB(A)
DAY* NIGHT** DAY* NIGHT**
1 Project Site Residential
area 55 45 56.2 43.8
2 Basai Villege Residential
area
55 45 58.7 46.3
3 Vee Kay industries industrial
Area
75 65 69.5 56.1
* Day time (6.00AM TO 10.00PM)
** Night time (10.00PM TO 6.00AM)
3.4.4 WATER ENVIRONMENT
3.4.4.1 Water Quality
Water quality assessment is one of the essential components of EIA study. Such assessment
helps in evaluating the existing health of water body and suggesting appropriate mitigation
measures to minimize the potential impact from development projects.
The water quality at the site and other locations within the 10 km impact zone was monitored
during Dec 2016 - Feb 2017. The locations of the monitoring sites are given in Table 3.7 and the
result of the monitoring and analysis of surface water is presented in the Table 3.8 (a, b, c).
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 42
3.4.4.2 Sampling Frequency and Sampling Techniques
Parameters for analysis of water quality were selected based on the utility of the particular source
of water as per MoEF guidance. Hence quality of water was compared with IS: 10500: 1991
(Reaffirmed 1993 With Amendment NO -3 July 2010). As per the standard practice, one sample
from each station was taken each month in the study period. Sampling was done by standard
sampling technique as per the Standard Methods. Necessary precautions were taken for
preservation of samples. The sampling locations for surface water are given in Table-3.7.
Table 3.7: Location of water sampling sites
Location No. Location Name Distance & Direction from
project site
SW – 1 Najafgarh drain SW; 4 km
The water quality in the impact zone was assessed through physico- chemical and
bacteriological analysis of ground samples. The results have been compared with the
drinking water quality standards specified in IS: 10500.
3.4.4.2 Sampling Frequency and Sampling Techniques
Samples were studied at monthly intervals in the study period. Quality of ground water was
compared with IS: 10500: 1991 (Reaffirmed 1993 with Amendment No.3 July 2010) for
drinking purposes. Surface water quality was analyzed for parameters as mentioned in the
‘Annexure IV of CPCB guidelines’ and it was rated according to the CPCB Water Quality
Criteria (Designated Best Use). Water samples were collected in a 5 liter plastic jerry can and
500ml sterilized clean glass bottles for physio-chemical and bacteriological tests respectively.
GW sampling was done after flushing out the source (minimum 10 minutes) to get the fresh
ground water and grab sampling method was used. River water samples were collected about
10cm below the water surface. All sampling, preservative and sample handling techniques were
in accordance with APHA for Examination of Water & Wastewater/ IS: 3025 (Part-1)/ IS: 1622.
The samples were analyzed as per Indian standard /APHA latest edition. The water quality is
compared with CPCB water quality criteria mentioned in Table 3.8.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 43
The water quality in the impact zone was assessed through physico-chemical and bacteriological
analysis of ground samples. The results have been compared with the drinking water quality
standards specified in IS: 10500.
Table 3.8: Water Quality Criteria as per Central Pollution Control Board
Designated-best-use Class Criteria
Drinking water source
without conventional
treatment
but after disinfection
A
Total Coliform Organism MPN/100ml will be 50 or less
pH between 6.5 and 8.5 Dissolved Oxygen 6mg/l or
more
Biochemical Oxygen Demand 5 days 20°C 2mg/l or less
Outdoor bathing
(Organized)
B
Total Coliform Organism MPN/100ml will be 500 or
less
pH between 6.5 and 8.5; Dissolved Oxygen 5mg/l or
more
Biochemical Oxygen Demand 5 days 20°C 3mg/l or less
Drinking water source after
conventional treatment and
disinfection
C
Total Coliform Organism MPN/100ml will be 5000 or
less
pH between 6 to 9; Dissolved Oxygen 4mg/l or more
Biochemical Oxygen Demand 5 days 20°C 3mg/l or less
Propagation of Wild life and
Fisheries
D
pH between 6.5 to 8.5
Dissolved Oxygen 4mg/l or more
Free Ammonia (as N) 1.2 mg/l or less
Irrigation, Industrial
Cooling, Controlled Waste
disposal
E
pH between 6.0 to 8.5
Electrical Conductivity at 25°C micro mhos/cm
Max.2250
Sodium absorption Ratio Max. 26
Boron Max. 2mg/l
Below-
E Not Meeting A, B, C, D & E Criteria
Table 3.9(a) : SurfaceWater Quality in Study Area (December 2016)
Modification & Expansion of Group Housing Project, Village-Dhanwapur Sector-104,
Gurugram, Haryana
Dec-16
S. No.
Parameter Unit Najafgarh Drain
1 pH - 7.95
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 44
2 Dissolved Oxygen mg/l 2.0
3 BOD (3 Days at 27 °C) mg/l 159
4 Free Ammonia (as N) mg/l 1.7
5 Sodium Adsorption Ratio - 1.17
6 Boron mg/l 0.2
7 Conductivity µmhos/cm 1426
8 Temperature (°C) 19.2
9 Turbidity NTU 7.0
10 Magnessium Hardness ( as CaCO3) mg/l 81
11 Total Alkalinity (as CaCO3) mg/l 225
12 Chloride (as Cl) mg/l 189
13 sulphate (as SO4) mg/l 124
14 Nitrate (as NO3) mg/l 2.5
15 Fluoride (as F) mg/l 0.8
16 Sodium (as Na) mg/l 40
17 Potassium (as K) mg/l 19
18 TKN mg/l 2.8
19 Total Phosphorous (as P) mg/l 1.6
20 COD mg/l 525
21 Phenolic compounds (as C6H5OH) mg/l <0.001
22 Lead (as Pb) mg/l <0.01
23 Iron (as Fe) mg/l 0.36
24 Cadmium (as Cd) mg/l <0.001
25 Zinc (as Zn) mg/l 0.31
26 Arsenic (as As) mg/l <0.01
27 Mercury (as Hg) mg/l <0.001
28 Chromium (as Cr) mg/l <0.001
29 Nickel (as Ni) mg/l <0.01
30 TDS mg/l 856
Bacteriological parameter
1 Total Coliform MPN/100ml 9.6x106
2 Faecal Coliform MPN/100ml 1.2x106
Table 3.9(b) : Surface Water Quality in Study Area (January 2017)
Modification & Expansion of Group Housing Project, Village-Dhanwapur Sector-104,
Gurugram, Haryana
Jan-17
S.No. Parameter Unit Najafgarh Drain
1 pH - 8.09
2 Dissolved Oxygen mg/l 1.8
3 BOD (3 Days at 27 °C) mg/l 167
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 45
4 Free Ammonia (as N) mg/l 1.9
5 Sodium Adsorption Ratio - 1.08
6 Boron mg/l 0.19
7 Conductivity µmhos/cm 1410
8 Temperature (°C) 18.9
9 Turbidity NTU 5.0
10 Magnessium Hardness ( as CaCO3) mg/l 86
11 Total Alkalinity (as CaCO3) mg/l 230
12 Chloride (as Cl) mg/l 177
13 sulphate (as SO4) mg/l 128
14 Nitrate (as NO3) mg/l 2.8
15 Fluoride (as F) mg/l 0.7
16 Sodium (as Na) mg/l 38
17 Potassium (as K) mg/l 17
18 TKN mg/l 3
19 Total Phosphorous (as P) mg/l 1.5
20 COD mg/l 542
21 Phenolic compounds (as C6H5OH) mg/l <0.001
22 Lead (as Pb) mg/l <0.01
23 Iron (as Fe) mg/l 0.34
24 Cadmium (as Cd) mg/l <0.001
25 Zinc (as Zn) mg/l 0.3
26 Arsenic (as As) mg/l <0.01
27 Mercury (as Hg) mg/l <0.001
28 Chromium (as Cr) mg/l <0.001
29 Nickel (as Ni) mg/l <0.01
30 TDS mg/l 846
Bacteriological parameter
1 Total Coliform MPN/100ml 7.8x106
2 Faecal Coliform MPN/100ml 3.7x105
Table 3.9(c) : SurfaceWater Quality in Study Area (February 2017)
Modification & Expansion of Group Housing Project, Village-Dhanwapur
Sector-104, Gurugram, Haryana
Feb-17
S.No. Parameter Unit Najafgarh Drain
1 pH - 7.86
2 Dissolved Oxygen mg/l 2.2
3 BOD (3 Days at 27 °C) mg/l 163
4 Free Ammonia (as N) mg/l 1.7
5 Sodium Adsorption Ratio - 1.11
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 46
6 Boron mg/l 0.21
7 Conductivity µmhos/cm 1477
8 Temperature (°C) 19.5
9 Turbidity NTU 9.0
10 Magnessium Hardness ( as
CaCO3) mg/l 95
11 Total Alkalinity (as CaCO3) mg/l 237
12 Chloride (as Cl) mg/l 185
13 sulphate (as SO4) mg/l 137
14 Nitrate (as NO3) mg/l 2.5
15 Fluoride (as F) mg/l 0.5
16 Sodium (as Na) mg/l 41
17 Potassium (as K) mg/l 19
18 TKN mg/l 3.4
19 Total Phosphorous (as P) mg/l 1.7
20 COD mg/l 550
21 Phenolic compounds (as
C6H5OH)
mg/l <0.001
22 Lead (as Pb) mg/l <0.01
23 Iron (as Fe) mg/l 0.31
24 Cadmium (as Cd) mg/l <0.001
25 Zinc (as Zn) mg/l 0.25
26 Arsenic (as As) mg/l <0.01
27 Mercury (as Hg) mg/l <0.001
28 Chromium (as Cr) mg/l <0.001
29 Nickel (as Ni) mg/l <0.01
30 TDS mg/l 886
Bacteriological parameter
1 Total Coliform MPN/100ml 7.8x106
2 Faecal Coliform MPN/100ml 3.7x105
Results and Conclusion
The water quality in the impact zone was assessed through physico-chemical and bacteriological
analysis of ground water samples. The results have been compared with the drinking water
quality standards specified in IS: 10500. It was observed that all the physic chemical parameters
and heavy metals from ground water samples are below stipulated drinking water standards.
All the ground water samples analyzed can be considered fit for drinking purpose in the absence
of alternate sources
3.4.5 DRAINAGE
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 47
The drainage of the Gurgaon district is typical of the arid and semi-arid areas. It comprises of large
depressions and streams. The drainage is peculiarly complex owing to most of the streams
tending to converge towards inland depressions instead of flowing into Yamuna. The important
depressions in the level of the district in this region are Khalipur, Chandaini, Sangel-Ujina, Kotla
Dahar Jheels and Najafgarh Lake. Sahibi and Indrani are two important seasonal streams of the
district.
3.4.6 LAND ENVIRONMENT
Land is an important component of the life support system. Degradations of land due to
industrialization, urbanization and population growth is a matter of concern. Therefore, it is
necessary to establish the existing land use pattern to optimize the land use as well as minimize
degradation due to the developmental activities. Also it is necessary to the landform of the
project site and the quality of the soil as soil erosion further deteriorates the quality of the land.
The land use pattern of the area is mainly agriculture land, open scrub and settlement etc. The
land use of individual revenue units falling within 5 km radius established on the basis of data
from Directorate of Economics & Statistics (Ministry of Agriculture, Govt. of India) are
presented in table 3.10
(Land use statistics of Haryana 2005-06, Directorate of Economics & Statistics, Ministry of
Agriculture, Govt. of India)
Topography
The landform of the project site is fairly plain. The land environment is described by landuse /
landcover of the study area within 10 km radius and soil environment of the study area within 5
km radius.
Land use–description
The land use / land cover of the project site were done to identify the land use pattern and land
cover pattern of the study area. The study of land use in the area enables one to know about the
land that can be used for various development activities envisaged in post project scenario. It
also enables to envisage the scenario emerging due to the increase in demand for land with
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 48
increase in population and the impacts arising due to the interface with the various project
activities.
Objectives of the Study
The objectives of the present study are:
• To map the study area with respect to various land use/land cover change over the past 10
years.
• To identify the sensitive areas within 5 km radius around the project site.
Methodology
The land-use/land-cover pattern has been established based on the analysis of the data received
from satellite imagery by making land-use/land-cover map with the help of GIS technique. Also
the data based on Census of India, 2001 was referred and land-use study was done within 5 km
radius area with limited ground truth verifications. Ground and ancillary information have been
used to identify the sensitive places within 5 km radius of the project.
Land Use Pattern Classification and description
The classification of land use / land cover pattern of the study area is mainly dominated by the
types - agricultural land, water bodies, canals, settlements or cultural use, and etc. The
agricultural land covers the majority of the land which is about 69 % of the study area and
settlement the second highest pattern of the land use covering about 16 % of the total land within
10 km radius. The land use data are presented in Table 3.9 and also highlighted with a pie chart
at Figure 3.3. The Land use map is enclosed refer Annexure V (e).
Table 3.10: Land use/Land cover Pattern of the Study area
Land use Class Area (Ha)
Settlement 4828.24
Water bodies 293.35
Vegetation 45.92
Forest 197.93
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 49
Open Land 1374.93
Open Scrub 900.45
Agricultural Land 24934.79
Total 32575.79
Figure 3.2: Land Use Patten of the Project Site within 5 km
Topography:
Slope form: Contour plan shown that land is flat land with highest RL 99.53 and Lowest
RL 98.41. Project will not cause any change in natural slope.
Landform and Terrain analysis: According to the study of 10 km radius around the project in
topographical map of scale 1:50000, it was found that 69 % is Agriculture, 16 % is settlement, 9
% is Open land, 4 % area is Open Scrub, 2 % is Forest and traces of Water bodies. Complete
details are given in figure 3.3 above. Project site is a vacant land.
Settlement
Water bodies
Vegetation
Forest
Open Land
Open Scrub
Agricultural Land
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 50
3.4.7 Soil
Soil formation is influenced mainly by climate, geology, relief and other biotic interactions. To
assess the soil quality of the proposed area, following stations were selected. Soil profile and
quality was studied at 5 different locations.
The composite soil samples were collected from different location and were analyzed for characterization.
The locations of the monitoring sites are depicted in Table 3.10 (a) and the results of the monitoring and
analysis is presented in the Table 3.10 (c)
Table 3.11: Location of Soil sampling
Location Code Location Direction Distance (km)
SQ1 Project site Center -
SQ2 Sector 99 A NW 0.39 km
SQ3 Garoli Khurd WNW 3.62 km
SQ4 Basai Village W 3.18 km
SQ5 Daya Vihar SE 2.21 km
3.4.7.2 Methodology
The soil samples were collected in the January 2017 from 6 locations as given in Table above. At
each of these locations 3 sub-locations were identified randomly from where soil was collected
from up to 30 cm below the surface. The final 4 samples represent homogenously mixed soil
from these 3 sub-locations for each location. The samples were filled in polythene bags, labeled
in the field with number and site name and sent to laboratory for analysis. Table 3.12 gives the
idea of the frequency and methodology of selection of soil sampling stations and monitoring
process.
Table 3.12: Frequency and Methodology for Soil Sampling & Monitoring
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 51
Particulars Details
Frequency One grab sample from each station– once during the Study Period
Methodology Composite grab samples of the topsoil were collected from 3 depths,
and mixed to provide a representative sample for analysis. They were
stored in airtight Polythene Bags and analyzed at the laboratory
*Grab sample- a single sample or measurement taken at a specific time or over as a short
period as feasible.
Table 3.13: Soil Quality Data (January 2017)
Modification & Expansion of Group Housing Project, Village-Dhanwapur Sector-104,
Gurugram, Haryana
Soil Quality Data JAN. - 2017 S.No Parameter Unit SQ-1 SQ-2 SQ-3 SQ-4 SQ-5
Project
Site Sector
99 A Gorali
Khurd Basai
Village Daya
Vihar 1
Texture - Sandy
loam
Sandy
clay
loam Sandy
loam Sandy
clay loam Sandy
loam Sand % 66.5 58.7 64.1 57.6 62.3 Silt % 17.8 21.5 18.2 23.7 19.2 Clay % 15.7 19.8 17.7 18.7 18.5
2 pH (1:2) - 7.68 8.12 7.86 8.16 7.85
3 Electrical Conductivity
(1:2) µmhos/cm 328 426 389 499 430
4 Cation exchange
capacity meq/100
gm 14.0 15.7 15.0 16.8 15.3
5
Exchangeable
Potassium meq/100
gm 0.21 0.32 0.29 0.31 0.37
6 Exchangeable Sodium meq/100
gm 0.58 0.66 0.68 0.71 0.62
7
Exchangeable
Calcium meq/100
gm 9.8 10.7 9.9 11.3 9.5
8
Exchangeable
Magnesium meq/100
gm 3.4 4.0 4.1 4.5 4.8
9 Sodium Absorption
Ratio - 0.71 0.77 0.81 0.80 0.73 10 Water Holding Capacity % 25.7 26.4 25.3 26.1 27.4 11 Porosity % 37.5 35.8 39.7 36.5 37.8
12 Permeability cm/hrs 2.4 1.6 2.1 2.3 2.6
13
Total kjehdahl
Nitrogen % 0.041 0.043 0.047 0.039 0.046
14 Phosphorus(Olsen’s) mg/kg 8.5 9.7 7.9 9.9 8.7
15 Organic Matter % 0.32 0.31 0.34 0.35 0.38
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 52
3.4.7.3 Result:
Results are summarized in Table 3.10 (c); the result shows that texture of the core is Sandy
Loam. The results of buffer zone show that texture is sandy loam. pH ranges from 7.73-7.96. The
amount of exchangeable Potassium is between 33-59 mg/kg.
3.5 Biological Environment
3.5.0 Introduction
Biodiversity reflects the potential of a regional ecosystem. Biota of a particular area is
considered as indicators of the environment as they quickly respond not only to one
environmental factor but also an interactive group of factors. These communities influence and
react sensitively to changes in the balance of environmental stresses.
Biological diversity comprises the variability of genus, species and ecosystems and is very
crucial for maintaining the basic processes on which the life depends. On the basis of biological
physiology biodiversity broadly can be divided into two category i.e. the floral diversity and
faunal diversity. Conservation of the biodiversity is essential for the sustainable development as
it not only provides the food, fodder and medicine, but also contributes to improvement of
essential environmental attributes like air, water, soil, etc. Before starting any Environmental
Impact Assessment study, it is necessary to identify the baseline of relevant environmental
parameters which are likely to be affected as a result of the operation of the proposed project. A
similar approach has been adopted for conducting the study on Biological Environment for this
Project. Both terrestrial and aquatic ecosystems have been studied to understand the biological
environment near the project site.
The study was conducted in the project area to assess all possible consequences on the biological
environment. Flora and fauna surveys and data collection conducted for assessing the biological
diversity and its status over a period of time that forms an integral part of Impact Assessment
Techniques. The present study is highlighting the various issues pertaining to floristic diversity
and the faunal wealth in the core area i.e. Modification & Expansion of Group Housing Project
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 53
at Village –Dhanwapur, Sector- 104, Gurugram, Haryana and buffer zone i.e. area within 10 km
radius.
3.5.1 Methodology
Period of Sampling
The ecological survey has been conducted during Post monsoon season for the collection of
primary data of flora-fauna, vegetation, soil and other environmental observations. The details
are given as below:
Pre-monsoon : December, 2016 to February, 2017
Core zone : Project site
Buffer zone : 10 km radius around project site
3.5.2. Mode of Data Collection
Detailed survey was conducted to evaluate floral and faunal composition of the study area.
Primary data on floral and faunal composition was recorded during site visit and secondary data
was collected from the Forest Department and published relevant literature. Inventory of flora
and fauna has been prepared on the basis of collected data. The mode of data and parameters
considered during field investigations is given in Table 3.15.
Table 3.15: Mode of Data Collection & Parameters Considered During the Survey
Aspect Data Mode of Data Collection Parameters Monitored
Terrestrial
Ecology
Primary data
collection By field survey
Floral and Faunal
diversity
Secondary
data
collection
* Forest Department of Haryana,
*Official website of district
administration Gurgaon
Floral and Faunal
diversity, Types of
vegetation, forest type,
Importance etc.
3.5.3. Biological Component of Core Zone
3.5.3.1 Flora
The core zone comprises flat agricultural land where construction operation is proposed. Some
trees are growing in the proposed construction area such as Babool, Ber and Sisham along with
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 54
some seasonal grasses (Dabh, Doob, Munj, Parthenium, Madar and Sanwak) etc. Tress growing
in the core zone will be cut and compensatory plantation will be done. The project shall not lead
to any change in landuse.
3.5.3.2 Fauna
Core zone of the proposed construction project is located on flat land. During the field survey,
some common domesticated animals such as Cow and Goat etc. were observed along with Rock
lizard and Chameleon. Permanent habitat of mammals and avifauna in the core zone were not
observed. There is no any aquatic habitat in the core zone, so aquatic fauna also does not exist.
3.5.4 Biological Component of Buffer Zone
3.5.4.1 Flora
3.5.4.1.1Forests
Gurgaon district is not well enriched with forest as compare to others in Haryana. There is no
any RF and PF present in the buffer area except some dense patches of Babool. In the
development process, forests have denudated due to increasing population, urbanization, and
industrialization without much replenishment despite so many schemes under implementation.
On account of increasing biotic pressure on the forests, there has been ecological degradation.
The vegetation of the district comprises of tropical moist deciduous due to high temperature and
humidity. Sultanpur Bird Sanctuary is situated at the distance of 5.4 km in West direction to the
project site and it is maintained by the concerning authority. No any schedule-I animals are
found in within the 5 km buffer area of present project.
Vegetation in and Around Human Settlement
Vegetation pattern in villages and surrounding areas in the Gurgaon district are slightly different
from the rest of the areas. Most of the area of Gurgaon district is barren and agriculture land
without major vegetation. The common species grown near villages are mostly edible or useful
plants are Artocarpus integrifolia, Azadirachta indica, Delonix regia, Eucalyptus sp., Ficus
religiosa, Mangifera indica, Madhuca indica, Sizygium cumini and Tamarindus indica.
Terrestrial Flora of the Buffer Zone
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 55
Buffer zone of the present project is mainly agricultural land. The most common plant species
observed in the buffer zone of present proposed construction area are listed in Table 3.12.
Table 3.16: Vegetation of Buffer Zone
S. No. Scientific name Local name Family Plants
1 Acacia arabica Babul Leguminosae 2 Aegle marmelos Bel Rutaceae 3 Azadirachta indica Neem Meliaceae 4 Bassia latifolia Mahua Sapotaceae 5 Bombax malabaricum Semal Malvaceae 6 Butea frondosa Palas Leguminosae 7 Dalbergia latifolia Shisham Leguminosae 8 Eugenia jambolana Jamun Myrtaceae 9 Feronia elephantum Kaith Rutaceae 10 Gmelina arborea Gamari Verbenaceae 11 Mangifera indica Aam Anacardiaceae 12 Spondias mangifera Amra Anacardiaceae 13 Tamarindus indica Imli Leguminosae 14 Tectona grandis Sagon Verbenaceae 15 Terminalia arjuna Arjun Combretaceae 16 Terminalia belerica Bahera Combretaceae
Shrubs 1 Achyranthes aspera Apamarg Amarantaceae 2 Calotropis gigantea Aak Asclepiadaceae 3 Eugenia heyneana Kath Jamun Myrtaceae 4 Lantana camara Raimunia Verbenaceae 5 Woodfordia floribunda Dhawai Lythraceae 6 Zizyphus rugosa Churna Rhamnaceae 7 Zizyphus rotundifolia Jharberi Rhamnaceae
Grasses 1 Cynodon dactylon Doob Gramineae 2 Eragrostis tenella Bhurbhusi Gramineae 3 Heteropogon contortus Kusul Gramineae 4 Imperata cylindrica Chhir Gramineae 5 Saccharum munja Munj Gramineae
Source: GRC survey data supported by Department of Forest, Haryana.
3.5.4.1.4 Aquatic Flora of the Buffer Zone
There is no any perennial lentic and lotic water body present in the buffer area except Najafgarh
drain. So, aquatic flora and fauna are not observed during present survey.
3.5.4.2 Fauna of the Buffer Zone
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 56
The major part of the buffer zone of present project lies under agriculture field which restrict the
wildlife habitat significantly. There is no any wildlife sensitive corridor is present for the
movement of wildlife animals. A list of animals of the study area has been prepared on the basis
of present survey, inquiry from local people and from the available published literatures. The
animals thus recorded were cross checked with Wildlife Protection Act (1972) for their schedule.
3.5.4.2.1 Mammals
Domesticated mammal species like Cow, Goat, Buffalo etc. were noticed in the buffer zone.
During present survey and Inquiry from village people regarding wild animals reveals that Fruits
bat and Indian Fox etc. are often seen in the area. List of Mammal species present in the buffer
zone is given in Table 3.17.
Table 3.17: Mammal Species Found in Buffer Zone
S. No. Scientific name Common name Schedule Status
(WPA,1972)
IUCN
Status
1 Canis sp. Indian Pariah Dog II LC
2 Funambulus palmarum Three-striped Squirrel IV LC
3 Herpestes edwardsi Common Mongoose IV LC
4 Mus booduga Indian Field Mouse V LC
5 Rattus rattus Indian House Rat V LC
6 Suncus murinus Grey musk Shrew IV LC
7 Tatera indica Indian Gerbille IV LC
8 Vandeleuria oleracea Long-tailed Tree Mouse V LC
9 Vulpes bengalensis Indian Fox II LC
3.5.4.2 .2 Reptiles and Lizard
During the present survey period some of the reptiles and lizard species were recorded in the
buffer zone of the present proposed construction area while some information were also noted
down by verbal communication of the people living surroundings in the buffer area. A list of
reptiles and lizard species observed in the buffer area are given in Table 3.14.
Table 3.18: Reptiles and Lizard Species Present in Buffer Zone
S. No. Common name Scientific name Schedule Status
(WPA,1972 ) IUCN
Status
1 Common Krait Bungarus caeruleus IV NA
2 Banded Krait Bungarus fasciatus IV NA
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 57
3 Red Sand Boa Eryx johnii - NA
4 Indian Cobra Naja naja II LC
5 Rat Snake Ptyas mucosus II NA
Lizards
1 Rock Lizard Agama buberculatus - DD
2 Chameleon Chamelion calcarata II DD
3 Indian House
Gecko
Hemidactylus
flaviviridus - DD
3.5.4.2.3 Avian Fauna
During the present investigation it was observed that the various avian fauna are moving across
the proposed construction project area in the buffer zone. But, no fixed pattern in migratory
behavior is noticed. No bird’s habitats like nesting, breeding and forging patterns are noticed in
the core zone as well as buffer zone. A list of birds observed in the buffer zone of proposed
project is given in Table 3.19.
Table 3.19: Avian Fauna in the Buffer Zone
S. No Common Name Scientific Name Schedule
Status
(WPA,1972)
IUCN
Status
1 Common Myna Acridotheres tristis IV LC
2 Common Kingfisher Alcedo atthis IV LC
3 House Swift Apus nipalensis IV LC
4 Purple Sunbird Cinnyrisa siaticus IV LC
5 Rock Pigeon Columba livia IV LC
6 Jungle Crow Corvus macrorhynchos IV LC
7 House Crow Corvus splendens IV LC
8 Common Cuckoo Cuculus canorus IV LC
9 Indian Cuckoo Cuculus micropterus IV LC
10 Black Drongo Dicrurus macrocercus IV LC
11 Red Jungle fowl Gallus gallus IV LC
12 White Wagtail Motacilla alba IV LC
13 House Sparrow Passer domesticus IV LC
14 Jungle Bush Quail Perdicula asiatica IV LC
15 Grey Bushchat Saxico laferreus IV LC
16 Common Babbler Turdoides caudata IV LC
17 Common Hoopoe Upupa epops IV LC
3.5.5 Agricultural Land
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 58
Gurgaon region is characterized as low rainfall and dry with vast marginal lands. Agro-
climatically a number of crops can be grown in Gurgaon district but major portion of cultivable
land is occupied by wheat, paddy, sugarcane, bajra and arhar. The significant area shift towards
these crops reflects their respective profitability and ease with which these crops can be
cultivated as per land suitability.
3.5.6 Fishery
The Haryana State has very good water resources in the shape of rivers, canals, drains, natural
and manmade lakes, reservoirs, micro-water sheds and village ponds to enable promotion of
fisheries. But Gurgaon district is poor w.r.t. water resources and there is no major natural
resource available for fish production. Fish culture in Haryana is little difficult due to non-
availability of fishermen community and mostly vegetarian population. The fisheries sector has
been recognized as a powerful income and employment generator as it stimulates growth of a
number of subsidiary industries and is a source of low cost animal protein to the people
particularly to the economically weaker sections of the society and thereby it is an advantageous
position to ensure national food security. The average annual fish production in the state is 6000
kg/hectare.
3.6 SOCIO ECONOMIC ASSESSMENT
INTRODUCTION
Socio-Economic Impact Assessment (SEIAA) refers to the systematic analysis of various social
and economic characteristics of the human beings living in the geographical area/study area
around the proposed project location. SEIAA is carried out separately but concurrently with
Environment Impact Assessment (EIA). The study area consists of core and buffer area around
the project site. The SEIA focuses on the likely effects of the project on social and economic
well-being of the community. The impact(s) may be direct or indirect, positive or negative.
In this section of the EIA Report an attempt has been made to assess the Socio-Economic Impact
of the project.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 59
OBJECTIVES OF SEIA
The prime objective of the current study is to assess the likely impact of the proposed project on
socio-economic characteristics of people living in the study area. Further, it is to be established
whether the impact would be direct or indirect. Furthermore, it is to be examined whether the
said impact would be positive or negative. Lastly, it is to be comprehended if the impact is
positive how long it would sustain or if it is negative how soon the same could be eased.
SCOPE OF THE STUDY
The Scope of the study is as follows:
• To collect baseline data of the study area
• To comprehend socio-economic status of the people living in the study area.
• To assess the probable impact of the project on social and economic aspects in the study area.
• To evaluate the likely impact of the project on Quality of Life of the people living in the
study area.
• To ensure sustainability of the positive impact.
• To suggest mitigation measures and agency responsible for taking action in case of adverse
impact.
METHODOLOGY
For Socio-Economic Impact Assessment of the proposed project, GRC India carried out
systematic analysis of the various socio-economic characteristics, both in terms of quality and
quantity. Accordingly, both qualitative and quantitative data was collected from secondary
sources. The secondary data was collected from the published data/information of the Census
Authority. Records of the state and district administration were also referred to.
For collection of primary data, a sample survey was conducted in the study area. In each selected
habitation, a specified number of representative households were selected scientifically for
collection of information from the head of the household or any responsible member of the
family.
• Census-cum Sample Survey in the Core Area
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 60
As the likely project impact(s) will traverse a domino alley with greatest impacts in the core area which
diminish progressively when moving away from the core to the buffer of the study area, a Census-
cum-Sample Survey was conducted in the core area for the collection of socio-economic data. It is
treated as a census survey because all the habitations located in the core area were surveyed for
the collection of information. Further, in each habitation a household survey was conducted by
drawing representative samples from the habitations by adopting the sample survey approach as
collection of information from all the households in a habitation is time consuming and expensive.
• Sample Survey in the Buffer Area
In the buffer areas where the impact of the project progressively reduces with the distance from the
project area, two stage sample design was adopted. The first stage units were census
village(s)/towns(s) and ultimate stage units were households.
• Sample Size
The sample size at each level (village and household) was decided by using the formula = √
{(1.96 *σ)/Δ}; where = Sample size, 1.96 is the Table Value of Confidence Limit, σ = Standard
Deviation and Δ = Degree of Precision.
• Selection of First Stage Units (Villages/Towns)
In the study area the sample villages were selected from the list of Census villages/towns by
adopting the method of Probability Proportional to Size (PPS), the size being number of
households in a given village/town.
• Selection of Ultimate Stage Units (Households)
The sample households were selected from the list of households by adopting the method of
Circular Systematic Sampling. This method was adopted since the sampling frame i.e. the list of
households was readily available.
SURVEY INSTRUMENTS
The following Schedules/Questionnaires were developed for collection of primary data from the
households and villages/towns:
• Schedule/format for Village/Town Particulars
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 61
• Questionnaire for Household Details and project perception
Each of these data/information instruments has segment blocks and there are both open-ended
and close-ended questions
VARIOUS STEPS FOLLOWED TO PREPARE THE SEIA REPORT
Project Location and Study Area
The project site is located at Village Dhanwapur, Sector-104, District Gurugram, Haryana. The
project site has good connectivity with the road, rail and air network. The nearest railway station
is Gurgaon Railway Station about 1.2 km (NE) away from the project site. The nearest airport is
Indira Gandhi International Airport, at 12 km (NE) from the project site.
The study area of the project is spread across a 10 km radius around the project site. There are 81
identified habitations which are spread over in rural and urban parts of the study area. The
habitation in this area is largely agricultural. The land use pattern of this area shows area under
settlements of 18.99 % with the major segment being agriculture land with a share of 54.61 %.
Study of Project details
Literature Review & ToR-where
applicable
Study area identification and
important landmarks
Listing of Habitations located
in the study area
Collection of Secondary Data
Firming up of Approach & Methodology
Finalization of Questionnaire
/Schedules
Site Visit to collect primary
data/information
Data Entry, Collation and Generation of
Tables
Socioeconomic Baseline of study
area
Socioeconomic initiatives wrt
project
Review of PH input based on MoM
where applicable
Report Preparation
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 62
BASELINE DATA
The baseline data with respect to population and basic amenities & infrastructure available in the
study area is as under:
• Demographic Details
According to Census of India- 2011, the study area has total population of 13,92,596 which are
housed in 3,14,124 households with average household size of four. Of the total population, 54.9
per cent are males and remaining 45.1 per cent are females. The sex ratio of the study area has
been worked out to 821 females per 1,000 males.
The total child population of 0-6 age group has been worked out to 1,81,060 which comprise
around 13.0 per cent participation in the total population. The gender wise share in the
population of 0-6 age group is distributed with 54.5 per cent male and 45.5 per cent female. The
sex ratio of this age group has been worked out to 836 females per 1,000 males.
Further, the study area has Scheduled Caste population of 1,61,173 which comprise 11.6 per cent
of the overall population of the study area. Of this, participation of male and female population is
53.6 and 46.4 per cent respectively. The sex ratio of the Scheduled Caste population has been
worked out to 867 females per 1,000 males.
In the study area, total number of literates are 10, 45,925. Of the total literates, 58.0 per cent are
males and remaining 42.0 per cent are females.
The overall literacy rate has been worked out to 86.3 per cent. The male literacy rate is 91.1 per
cent as against women literacy rate of 80.5 per cent. This has created a gender gap of 10.6 per
cent in the literacy rate.
Total number of workers in the study area is 5, 15,786 which constitute 37.0 per cent of the total
population. Of the total workers, 82.0 per cent are males and remaining 18.0 per cent are females
which creates a gender gap of 64.0 per cent in work participation rate. Again, of the total workers
93.1 per cent are Main Workers and the remaining 6.9 per cent are Marginal Workers. Of the
total main workers, 83.3 per cent are males and the remaining 16.7 per cent are females.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 63
Similarly, of the total marginal workers, 64.4 per cent are males and the remaining 35.6 per cent
are females.
A tabulation of the salient features of the demographic profile along with the amenities and
social infrastructure of the study area is presented in the table below:
S.
No. Description Number
Percentage to
respective totals
1
Total Population- Gender wise 320580 100
Male 174031 54.28
Female 146549 45.72
Sex ratio (No. of females per 1000 males) 842.1 -
2
Total Population (0-6 years) - Gender wise 45942 100
Male 25627 55.78
Female 20315 44.22
Sex ratio (No. of females per 1000 males) 792.7 -
3
Total Population (Sector Wise) 320580 100
Rural 155245 48.42
Urban 165335 51.58
4
Total Population (0-6 years) – Sector wise 45942 100
Rural 24923 54.24
Urban
21819
45.76
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 64
5
Total no. of household 62278
Average House Hold size 5
Highest Household size Rural 8
Urban 6
Lowest Household size Rural 5
Urban 4
6
Total Population Schedule Caste Community 39,169 100
Rural 25,305 64.60
Urban 13,864 35.4
7
Total Literates 229021 100
Male 133935 58.48
Female 95086 41.52
8
Total Literates – Sector wise 229021 100
Rural 103673 45.26
Urban 125348 54.74
9
Over all Literacy Rate 83.4
Male 90.3
Female 75.3
Gender gap in literacy rate 14.9
10
Total Workers 109606 100
Male 88029 80.31
Female 21577 19.69
11 Total Workers- Sector wise 109606 100
Rural 55943 51.04
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 65
Urban 53663 48.96
12
Total Main Workers Gender wise 99018 100
Male 81748 82.55
Female 17270 17.45
13
Total Main Workers- Sector wise 99018 100
Rural 48025 82.55
Urban 50993 17.45
14
Total Marginal Workers Gender wise 10588 100
Male 6281 59.32
Female 4307 40.68
15
Total Marginal Workers- Sector wise 10588 100
Rural 7918 74.78
Urban 2670 25.22
16
Total Agricultural Workers 12994 100
Cultivators 10084 77.60
Agricultural Labours 2910 22.4
17
Total Agricultural Workers- Sector wise 12994 100
Cultivators Rural 9772 75.20
Urban 312 2.40
Agricultural Labors Rural 2664 20.50
Urban 246 1.90
18 Household Industrial Workers Gender wise 3,754 100
Male 2417 64.38
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 66
Female 1337 35.62
19
Household Industrial Workers- Sector wise
wisewiwisewiwise wise
wisesedcssSector wise
3,754 100
Rural 2145 57.13
Urban 1609 42.87
20
‘Other Workers’ Gender wise 92858 100
Male 77328 83.27
Female 15530 16.73
21
‘Other Workers’- Sector wise 92858 100
Rural 41362 44.54
Urban 51496 55.46
22 Area Sq. Km 314
23 Density/km2
24 Population Growth Decade
Source: Census of India- 2011
• Amenities & Social Infrastructure
Facility Number of
village
Number
INSTITUTIONAL EDUCATIONAL FACILITIES
Primary school 35 42
Middle school 21 22
Secondary school 0 0
Senior Secondary school 7 7
TOTAL 71
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 67
HEALTH FACILITIES
Primary Health Center 2 2
Primary Health Sub Center 14 14
TOTAL 16
Registered Medical
Practitioner
6 19
DRINKING WATER FACILITIES
Tap 38 40
Tank 38 76
Well 38 41
Tube Well 38 49
Hand Pump 37 45
TOTAL 251
POWER
Domestic 38 villages
Agricultural 38 villages
POST & TELEGRAPH
Post office 5 5
Land line Phones 28 1562
ROAD & TRANSPORT FACILITIES
Paved road 35 villages
Mud road 11 villages
Bus service 23 villages
Railway service 24 villages
BANK & FINANCIAL INSTITUTIONS
Commercial bank 6 8
Cooperative Bank 1 1
SOCIO-ECONOMIC IMPACT OF THE PROJECT
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 68
Impact on Demographic Composition
The proposed project is intended to encourage and support the creation, expansion of urban
development in the area in an environmental friendly manner. The project is therefore envisaged
to increase the population of 18,277 persons that include residents, staff & visitors. This potential
increase of population has been provisioned for by way of residential area in the land utilization
matrix by the project proponent. Whereas the people recruited for providing employment will be
largely met locally to the maximum extent, there is possibility of in-migration from outside the
study area. Accordingly, there may be some variation in the total population of the study area
including that of sex ratio, after the project is completed.
Employment Opportunities
The proposed project will provide employment opportunities both during the construction and
operational phases. The direct and indirect employment will be provided during the construction
and operation phase of the project at both skilled and unskilled levels to the local people on
priority basis. Socio-economic standard of people will improve due to increased employment
opportunities provided by this project. Besides, the local people will have both employment and
business opportunities. The socio-economic standard of the local people will be raised due to
these enhanced employment and business opportunities.
This will lead to better quality of life, improvement in the living conditions and will also set a
standard for future developments in the area. It is a positive impact of the project.
Impact on Health
Following provisions will be made at project site for health and saftey:
• Safe Working Environment: The project proponent shall ensure health and safety of all the
employees at work. All efforts will be made to provide and maintain a safe work
environment and ensure that the machinery and equipment in use is safe for employees.
• Provision of First Aid: In case of any accidents arising out of the proposed construction
works, timely and prompt first aid treatment is, often, the most important tool. Suitable first
aid arrangements shall be made at the site for rendering immediate first aid in case of any
injury. The first-aiders will be well trained in handling patients working in the project.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 69
• Regular Medical Examination: For all workers, medical examination will be made on
regular basis.
• Health Education: Adequate health education & information related to the work will be
provided to the workers so that their health & safety can be ensured.
• Tie-up with the nearest Hospital for Medical Assistance: To meet the medical needs of
the workers in case of accidents, tie-up with nearest hospitals will be made. Efforts will be
made to reserve a few beds in the said hospitals for the workers to meet any emergency. This
will ensure timely medical aid to the affected persons.
• Supply of Mask & Gloves: The workers exposed to dust will be provided with dust masks
to prevent them from getting affected by respiratory diseases. Gloves will be provided to
workers working with hand tools to ensure safety of their hands.
• Special Telephone Number: A special telephone number will be made available to the
workers in case of emergency so that they can dial the same in case of any accident.
CONCLUSION
The socio-economic standard of people living in the area will improve due to the project. This
will lead to better quality of life and will also set a standard for future development in the study
area. The infrastructure of area will improve including development of parks, play ground,
schools, etc. This will give a boost to the standard of living of local community.
The overall impact of the project is expected to be positive.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 70
CHAPTER 4: ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION
MEASURES
4.1 INTRODUCTION
This chapter discusses identification and appraisal of various environmental impacts due to
the proposed Project. Generally, the environmental impacts can be categorized as either
primary or secondary. The development, construction and functional phase of the project
comprise various activities, each of which may have some impact on environmental
parameter. Various impacts during the development, construction and operation phase on the
environmental parameters have been studied to estimate the impact on environment.
The project will be constructed and developed gradually in the time span of 3-4 years
(approx.).
For proper evaluation and assessment of the environmental impacts due to development,
construction and functional phase of project understanding to the various activities associated
with the project is essential. Various activities related to the project would be different, in
terms of nature during the development, construction and operational phase.
The impact identification and prediction process aims to:
Identify potential source or cause of impact throughout life of the project.
Characterize the potential impacts affecting a target or receptor (physical, human and
socio-economic).
Assess the potential of changing likely-hood of impact through Environmental
Management Plan (EMP)
Prediction of the impacts due to the development, construction and functional
activities encompass the developmental processes to be undertaken during construction and
functional phases.
For each category of environmental receptor (such as, ambient air quality, water quality,
soils, land, etc.,) the potential impacts of activities during development, construction and
functional phases have been identified. Pollution sources & its characteristics, potential
impacts and magnitude of the impacts have been assessed and discussed in detail in following
sub sections. In each case, cognizance has been taken to mitigation measures inherited in the
development, construction and functional phase.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 71
4.2 IMPACT MATRIX
Various activities from the Project are likely to have some impact on the environmental
constituents during its construction as well as operational phase. The impact assessment
matrix given in Table 4.1 reveals the impact associated with each activity of the project on
various environmental parameters during construction and function phase respectively before
any mitigation measures are implanted. To assess the severity of the impacts, they are
categorized as follows:
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 72
Table 4.1: Impact Assessment Matrix
Environmental
Parameters
Nature of Potential Impacts during Construction and Operation Phases
Local Regional Short
Term
Long
Term
Reversible Irreversible Adverse Beneficial No Impact Significant Insignificant
Topography √ √ √
Drainage √ √
Soil √ √ √
Water Resources √ √ √ √
Water Quality √ √
Land Use √
Air Quality √ √ √ √
Noise √ √ √ √
Flora √ √ √ √ √
Fauna √ √ √ √ √
Employment √ √ √ √ √
Aesthetic
√ √ √ √ √
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 73
4.3 POLLUTION SOURCES
Pollutants generated from the development project
during the construction and functional phases are solid, liquid and gaseous in nature. Also the
generation of pollution could be continuous, periodic or accidental. Sources of pollution and
their characteristics are given below in Table 4.2.
Table 4.2: Pollution Sources
S. No. Activity / Area Pollutant Sources Frequency
CONSTRUCTION PHASE
1. Site
preparation and
construction
activities
Air emission- SO2,
& NO2.
Dust from
construction
activities and
excavation.
Particulates matter,
NO2 and CO from
vehicle exhaust
Temporary during
construction phase
only.
Bulk of the
emissions is expected
from ground work
and leveling.
Earth/Solid waste
Solid waste from
construction activity
and excavation.
Periodic.
Hazardous waste
generation such as
used oil and paints.
From D.G. Sets and
painting of the
buildings.
Periodic and
temporary
Noise Noise generated
from construction
equipment and
machinery
Temporary lasting
the construction
phase.
2. Labour Camps Sewage Sewage generated
from temporary labor
camps on site.
Temporary-during
the initial
construction phase
Solid Waste Solid Waste
generated from
temporary labor
camps on site.
Temporary- during
the initial
phase
OPERATIONAL PHASE
1. Vehicular
movement
Air emissions and
noise
Vehicle exhaust
emissions
Continuous/ periodic
2. Diesel
generators
Air emissions SO2, NO2, PM, CO
from fuel burning
Occasional- during
power failure
Noise Noise due to running
of equipment
Occasional - during
power failure
Hazardous Waste Used Oil Generation Occasional- during
oil changes
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 74
S. No. Activity / Area Pollutant Sources Frequency
3. Maintenance /
House-
keeping
Sullage Floor washing
Sewage
Continuous
Solid waste Domestic and garden
wastes
Continuous
4. Vehicle
Parking
Oil spills Minor oil leaks
Parking space
Continuous
5. Storm water
drains
Rainwater Contamination
discharge from site-
mainly suspended
solids
During rainy season
4.4 IMPACT IDENTIFICATION
The areas of environmental concerns for which the impacts and their predictions are taken into
consideration are mainly:
Air Environment
Water Environment
Noise Environment
Land Environment
Biological Environment
Socio economic Environment
Aesthetics Environment
The impacts can be further categorized as positive impacts and negative impacts depending upon
their nature, potential and magnitude.
4.4.1 Environmental Aspects of Development, Construction & Operation
Generation, storage and disposal of construction waste;
Noise pollution due to plant, machinery, equipment and vehicle movement;
Air pollution due to plant, machinery, equipment and vehicle movement;
Generation and disposal of wastewater;
Impact on ecology;
Consumption of resources such as water, electricity, and diesel.
Physical change in landscape due to earth work excavation and related activities.
Soil erosion caused due to loss of vegetation and other construction activities.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 75
4.4.2 Environmental Aspects of Building Planning and Use
Impacts identified during operation of the Revision & Expansion of Project and their use
includes major concerns such as:
Disposal of domestic sewage generation
Disposal of solid wastes generated in the Revision & Expansion of Project from office,
shops, restaurant and horticulture.
Increase in noise levels due to transport
Consumption of water and impact on water resources
Impact of traffic on the road
Storm water during rains
Management and maintenance project
Environmental aspects of the project are not just limited to impact of sources of pollution but
also relate to energy conservation, water conservation and other issues, which are mentioned in
Table 4.3.
Table 4.3: Environment aspects of the Project
S. No. Area Aspect
I. Energy
conservation Solar Heating, Day Lighting, Design Natural Ventilation,
Thermal Transfer value of Building Material, Energy Efficient
Building Services and Equipment,
Public Area Lighting
Exterior Lighting
II. Water
conservation Reuse of Recycled Water from STP
Rainwater Harvesting
III. Internal Roads
and Accesses Pedestrian Access Ramps for Disabled persons Road painting
and Signage Speed Breakers
IV. Material Use Construction Materials Selection
Paint Selection
Use of Recycled Materials
Use of Timber
V. Aesthetics
during
functional Use
Playground for children
Service Roads for walking
Standby Power Supply
Provision for Garden
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 76
VI. Facilities for
Building
complex
servants
Rest Rooms with toilets for Security Persons.
4.5 ASSESSMENT OF ENVIRONMENTAL IMPACTS DURING DEVELOPMENT
AND CONSTRUCTION PHASE
4.5.1 Topography
Impact: Topography around the project site is almost plain. Therefore, existing topography and
physiography of the area will not be affected during construction and operation phase of the
project.
Mitigation Measure: It is further proposed to maintain 37,816.538 m2 area as green through
plantation of various local and aesthetic species to improve the vegetation covers of the area. It is
however proposed that apart from the proposed plantation greens, turfing with local species will
be carried out. Therefore, there is no significant impact on topography from the project.
4.5.2 Land Use Pattern
Impact: No significant impact is expected from the project which will be constructed after
obtaining all necessary permissions.
4.5.3 Land Environment
Impact: Soil would be excavated at project site for laying foundation of building. During the
disposal of redundant overburden, soil of filling area would be covered and lost permanently.
Mitigation: The soil is being excavating during construction and first temporarily stored in an
area earmarked and then will be used to fill up low lying area in and around the project site and
rest of the soil will be transported by road to fill up low lying areas elsewhere. Proper drainage
system will be provided to deal with the storm water in case of rain. The impact on soil during
construction phase will be marginal and reversible in the nature. It is proposed to remove
vegetative cover only from the specific site on which construction is to take place and allowing
minimal disturbance to the vegetation in adjacent areas. Land clearing activities only confined to
necessary areas. The top soil will be stripped from constructional areas and stockpiled for later
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 77
reuse in landscaping. The number, frequency and area of movement of heavy machinery will
also be restricted.
4.5.4 Water Environment
4.5.4.1 Surface Water Quality
Impact: The primary concerns relating to surface water quality associated with construction
activities are pointed out below:
Runoff related to unpaved and excavated areas during the rain.
Sediments transported to runoff from the construction site.
Run off related to area where lubricant, fuel other materials are stored, used and disposed,
off.
Surface water quality may be affected with the discharge of the runoff from the project site. The
impact to the surface water bodies could arise from the increased soil erosion from excavated site
only causing increase in the suspended particles and turbidity of runoff water from the site.
However, this impact will be temporary in the nature and would be observed in first rain only
and as soon as rain is over excavated soil at site would be stabilized. Therefore, the surface water
quality during rains will be impacted marginally for very short duration.
Mitigation Measures: During the construction phase, surface water quality is likely to be
affected due to soil erosion during first rain and generation of sullage mainly from construction
labour camp. However, this phenomenon will be temporary and restricted to close vicinity of
construction site. The impact on surface water quality can be minimized by adopting following
measures;
Excavation during dry season and proper management of excavated soils,
Clearing all debris from site as soon as construction is over.
By providing proper hutment and toilet facilities for construction labour,
Proper disposal of wastewater.
4.5.4.2 Ground water Quality
Impact: No hazardous chemical and material will be used in the development and construction
phase of the project. Debris and waste generated will be collected and disposed suitably.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 78
Therefore, possibility of contamination of ground water will be negligible. Hence, no impact is
anticipated on the ground water quality during the construction phase.
Mitigation: A well planned solid waste management plan will be followed during the
construction phase including timely collection, segregation and disposal as per legal
requirements.
4.5.4.3 Surface and Ground Water Hydrology
Surface Water Hydrology
Impact: The project site is outside flood plain. Runoff during rain takes way to natural drain and
in storm water drains laid in the area. During construction phase, there is no impact anticipated
on the drainage pattern of the project area.
Mitigation Measures: Project proponent will ensure no interception on water runoff flow routes
and drainage pattern of the area throughout the construction of the project by providing adequate
water channel.
Ground Water Hydrology
Impact: Water requirement during construction phase will be met from STP treated effluent of
HUDA/private water tankers. Water will be required for site preparation activities dust
settlement, consolidation, compaction and curing as well as building construction and drinking
water requirement. The requirement of construction water will not put sudden pressure on the
available ground water resources of area. Therefore, impact on ground water resources will be
insignificant during construction of the project.
Mitigation Measures: Although no significant impact is anticipated on the groundwater regime,
it is proposed to carry out the following to further minimize the demand on freshwater resources:
Curing water will be sprayed on concrete structures and free flow of water not allowed.
After liberal curing on the first day, all concrete structures will be painted with curing
chemical to save water to stop daily water curing hence save water.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 79
Concrete structures will be covered with thick cloth/gunny bags and then water sprayed
on them to avoid water rebound and ensure sustained and complete curing.
Ponds will be made using cement and sand mortar to avoid water flowing away from the
flat surface while curing.
Water ponding will be done on all sunken slabs. This will also highlight the importance
of having an impervious formwork.
4.5.5 Air Environment
Emissions Source: The potential sources of air emissions during the construction and
development phase of the project will be as follows:
Dust from earth works (during site clearance and preparation);
Emissions from power generator at site;
Emissions from the operation of construction equipment and machines;
Fugitive emissions from vehicles running to site;
Fugitive emissions during the unloading of material at the site;
Fugitive emissions during mixing of cement with other building materials during
development and construction activities;
Air emissions other than dust arise from combustion of hydrocarbons. The pollutants of
concerns are NO2, SO2, CO, particulate matter, etc.
Potential Impacts: Ambient air quality effects are normally assessed in relation to their
potential to cause;
Health deterioration and nuisance in local communities
Health deterioration amongst on-site workers
Assessment of the impacts from Dust Emissions: During the excavation of channels,
foundations, unloading of construction material, cement bags and mixing of cement with other
building materials such as brick and silica dust, wood dust, fugitive dust emissions may be
emitted at construction site. During construction, curtaining floors from all sides will be done to
prevent cement dust from becoming airborne. It may be noted that all the emissions will be in the
form of coarse particulate matter and settle down ultimately in closed vicinity of construction
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 80
site. Therefore, no significant impact is anticipated due to dust emission during development and
construction phase.
Assessment of the impact from Diesel Generators: Emissions from D.G. Set during
construction phase may cause some localized impact on ambient air quality for short duration, as
it will be operated during power failure only. It may be noted that the D.G. Set power will be
used to operate construction equipment only if required. Adequate height of stacks and acoustic
erective will be provided to the D.G. Set as per guidelines of CPCB to facilitate the dispersion of
flue gases into the atmosphere.
Mitigation Measures: It is proposed to provide adequate dust control systems in the form of
installation of batch plants, and loose material handling in covered sheds. Dust suppression
system is also to be provided where necessary. Provision for treatment of DG Flue Gas emissions
in a scrubber will be considered. It is further proposed to cover scaffolding, hosing down road
surfaces and cleaning of vehicles especially during the dry season. Avenue and curtain plantation
on the internal roads and peripheral plantation around the site will also be developed.
4.5.6 Noise Environment
During the construction phase of project, noise will be generated from the various sources. Some
major sources of noise generation at project site are listed here under:
Generation of noise during movement of vehicles carrying materials, loading &
unloading activities.
Generation of noise from excavation machines, concrete mixer and other construction
machines,
Generation of noise during the operation of D.G. Set
Generation of noise during concreting, hammering, etc.
All the above-mentioned sources of development and construction activities at Project would be
intermittent and experienced occasionally. It may also be noted that the most of the construction
activities would be carried out only during the daytime.
The expected noise levels from various activities are given hereunder:
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 81
From vehicles bringing materials to the site 70 dB (A)
D.G. Set 85 dB (A)
Excavation 80 dB (A)
Concrete Mixtures 80 dB (A)
Hammering 85 dB (A)
Resultant Noise Level:
The combined effect of above sources can be determined as per the following equation:
Lp (total) = 10 log (10(Lpl/10)
+ 10(Lp2/10)
+ 10(Lp3/10)
+……..) ……. (1)
Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in dB (A). The
resultant maximum noise level for the above sources as calculated using equation (1) is 89.3 dB
(A).
For an approximate estimation of dispersion of noise in the ambient air from the sources, a
standard mathematical model for sound wave propagation is used. The sound level generated by
noise source decrease with increasing distance from the source due to wave divergence. An
additional decrease in sound pressure level from the source is expected due to atmospheric effect
or its interaction with objects in the transmission path.
For hemispherical sound wave propagation through homogenous loss of free medium, noise
levels at various locations can be calculated due to different sources using model based on the
first principles as per the following, equation:
Lr2 = Lr1 - 20 log (r2) – 8 ………. ( 2 )
Also, Lr2 = Lr1 - 20 log (r2/ r1)
Where: Lr1 and Lr2 – Sound Pressure Level (SPLs) at points located at 1m from sources and at
distance of r2 from the source respectively in dB (A).
Assuming no environmental attenuation factors, noise modeling has been done, which shows
that noise level will be mingle with baseline noise level within short distance. Baseline noise
level at the project site has been given in Table 4.4.
Table 4.4: Noise Levels in the Study Area
Modification & Expansion of Group Housing Project at Village-Dhanwapur, Sec-99 A, Gurgaon,
Haryana.
NOISE QUALITY DATA JAN. - 2017
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 82
S.N
o.
LOCATION ZONE LIMIT as per CPCB
Guidelines Leq, dB(A)
Observed value Leq, dB(A)
DAY* NIGHT** DAY* NIGHT**
1 Project Site Residential
area
55 45 56.2 43.8
2 Basai Villege Residential
area
55 45 58.7 46.3
3 Vee Kay
industries
industrial
Area
75 65 69.5 56.1
* Day time (6.00AM TO 10.00PM)
** Night time (10.00PM TO 6.00AM)
The noise produced during development and construction phase will have temporary impacts on
the existing, ambient noise levels at project site but restricted to limited distance and only during
daytime. Therefore, the impact of noise levels on surrounding area will be insignificant during
the development and construction phase.
Mitigation: To minimize impacts of noise generation from construction activities, the workers
will be provided with ear muffs and other protection devices. D.G. Sets with proper acoustic
enclosure for controlling noise would be installed.
4.5.7 Terrestrial Ecology
Impact: There is no loss of forestland due to the construction of the project. No tree felling is
involved, as the site is devoid of vegetation.
Birds and other domesticated biodiversity observed near the project site are common and already
adapted to thrive in human - colonized habitats. The project will not have any major negative
ecological impact. There is no forest near the project site and therefore there will be no effect on
the ecology of the area.
Mitigation Measures: However, it is to develop extensive green areas in the project site to
improve the aesthetics of the area which will also help in reduction of air pollution, noise
pollution and provide suitable habitat for local birds and animal species.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 83
4.5.8 Economic Impacts
Impact: Relatively long-lived economic impacts of the development and construction phase are
likely to be experienced in local area for the duration of construction phase of 3-4 years as
workers make everyday purchases from local traders in nearby areas. This is likely to give a
short-lived stimulus to the traders that may disappear as soon as the construction is complete.
Noticeable, flow-on economic impacts will be experienced in other sectors of economy as a
result of purchase of construction materials and the payment of wages and salaries to the
personnel engaged in the development and construction of the project. Once the development
and construction will complete, there will be some long-term positive impact on the economic
structure of the area. People in the area will get direct and indirect employment opportunities
and other benefits due to the project. Therefore, an overall positive impact is anticipated on
economy of the area due to the proposed project.
4.5.9 Socio-Economic
During the development and construction of Modification and Expansion of Group Housing
Colony Project, about 800-850 skilled and semiskilled and unskilled workers will get direct
employment opportunity, which will have beneficial impact on the local people and improve
socio-economic condition of the area.
4.5.10 Construction Camp
Impact: During the development and construction phase, most of the laborers will be from local
areas as the project will be developed gradually in the time span of about 3-4 years. Therefore,
laborer camps will be constructed to accommodate the laborers at the project site. This may lead
to sanitation problems in the absence of adequate facilities.
Mitigation: Suitable measures will be taken at the construction camps to mitigate anticipated
impacts due to temporary accommodation of laborers such as provision of clean drinking water,
adequate toilet facilities, water and solid waste disposal system.
Other safety precautions to be maintained at work site including provision of PPEs, guarding of
dangerous machine parts, maintenance of equipment as hoists and lifts etc., and adequate
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 84
provision of different types of fire extinguishers will be made. All applicable rules and
regulations pertaining to workplace health and welfare of workers will be adhered to.
4.5.11 Solid Waste Management
Impact: The construction and demolition waste includes debris, concrete (often recycled and
reused at the site), steel and other metals, pallets, packaging and paper products, fluorescent
tubes, wood beams, joists, studs, baseboards, cabinets and cupboards, railings, brick, doors and
casings, interior windows, bathroom fixtures, light fixtures, ceiling grid and tile, furnishings,
replant trees, shrubs. All wastes generated during the construction phase will be collected and
segregated for disposal as per the standard practice.
During the development and construction phase, some amount of debris, cuttings of construction
materials may be observed at construction site. However, the quantity of these waste materials
would be very small and limited up to the construction site only. There will be no contamination
due to this waste as it will be collected time to time during construction phase and disposed
accordingly.
Mitigation Measures: After due waste segregation, recyclable wastes will be sold off to scrap
dealers and vendors, while inert wastes will be disposed-off in landfills. Hazardous wastes will
be disposed-off as per the provisions of the Hazardous Wastes (Management & Handling) Rules,
2016.
4.5.12 Transport Linkage and Traffic
Impact: During development and construction phase, construction labour and construction
materials bringing vehicles will approach the project site. Modification and Expansion of Group
Housing Colony Project is well connected to neighborhood, where public transport facility, like,
buses and minibuses are easily available in the area as transport linkage. During construction
phase, some impact is anticipated on the transport linkage of the area, however increase in traffic
will not adversely affect the local traffic pattern since the site is well connected via. wide roads
and present traffic load on these road is not significant.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 85
Mitigation: Through careful planning, the movement of the heavy vehicles will be scheduled to
reduce load on existing traffic such that the peak hours are avoided. It will also be ensured that
all the vehicles to the site will be provided with Parking space such that there is no waiting time
along the access roads.
4.6 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING OPERATION
PHASE
4.6.1 Land Environment
Impact: During the operation phase of the project, the soil may get polluted/ contaminated from
littering of various kinds of wastes generated within the site such as food items, paper, wood
pieces, paints, pesticides, oil & grease etc. However, as a result of the proposed solid waste
management plan, no significant impact is anticipated.
Mitigation Measures: To ensure against any chances of soil pollution, it is imperative to
establish a well-planned solid waste collection system covering all areas of the project site apart
from door to door for the residential units. An identified area will be designated for storage and
segregation of the wastes which will be treated/ disposed as per their characteristics.
4.6.2 Water environment
4.6.2.1 Surface water hydrology
Impact: During the operation phase, no water will be taken from surface water bodies in the
area. Further, adequate drainage will be provided at the project site to channelize the storm water
for rainwater harvesting.
The sewage effluents generated from the project will be collected through the sewer line network
provided in the project site for treatment in the Sewage Treatment Plant (STP), and the treated
water reused within the site thereafter. Therefore, impact on the surface water hydrology will be
insignificant during the operation phase.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 86
Mitigation: It is proposed to provide rainwater harvesting across the project site. The roof tops
of buildings will also be connected to the rainwater collection system. This will not only reduce
the pressure of storm water management system of the city but also recharge groundwater.
4.6.2.2 Ground water hydrology
Impact: During operation phase, the total water requirement of the Modification and Expansion
of Group Housing Colony Project is approx. 1343 KLD out of which domestic water
requirement is 1075KLD. The fresh water demand will be approx. 801 KLD. The water
requirement will be met from HUDA. Therefore, no impact is anticipated on ground water
resources due to project.
To enhance the ground water level around the project site the rain water harvesting will be
proposed. The rainwater harvesting will recharge groundwater aquifers from the open areas as
well as roof top of the buildings. Treated water from the site will be recycled for landscaping,
flushing and to water body.
Water meters conforming to ISO standards will be installed at the inlet point of water uptake and
at the discharge point to monitor the daily water consumption. To further lower the water
consumption, options of Low flow flushing systems, sensor based fixtures, waterless urinals, and
tap aerators etc. will be explored.
4.6.2.3 Surface Water Quality
Impact: The sewage effluents generated from the Modification and Expansion of Group
Housing Colony Project will be collected through the sewer line network provided in
Modification and Expansion of Group Housing Colony Project, and treated in onsite STP of 3
onsite STPs of total capacity 1100KL that will generate 823 KLD of treated effluent which will
be reused for flushing & horticulture.
It is expected that the project after Modification & Expansion will generate approx. 915 KLD of
sullage. Surplus treated effluent will be discharged to external sewer line.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 87
Mitigation Measures: As no impact is anticipated on the surface water bodies of the region, no
mitigation measures are suggested.
4.6.2.4 Ground Water Quality
Impact: The storm water from the site will be collected for recharging groundwater resources
after adequate treatment of the storm water through oil, grease traps and filtration. The
wastewater from the site is proposed to be used for landscaping only after adequate treatment in
Sewage Treatment plant. Hence, no adverse impact is anticipated on the groundwater quality
form the project.
Mitigation Measures: The project site will be maintained well. Solid waste management
practices will be adopted and followed to prevent groundwater pollution from rain water
harvesting.
4.6.3 Air Environment
Prediction of Impacts
Vehicular emissions and DG sets emission will be major sources of air pollution from building
construction projects. Ground Level Concentration of pollutants (as added by the project) will
depend upon the following:
Emission of pollutants from additional traffic on the roads due to the project.
Meteorological conditions.
Emission sources from D.G. Sets.
PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic
movement and DG sets. Assuming that under cross wind condition perpendicular to the road, the
dispersion of vehicular emissions would be confined within limited distance from the road and
concentration will decrease with the increase in distance from road. It was anticipated that the
contribution of vehicular emissions from the exhaust in ambient air quality will be marginal as
Pollution under Control (PUC) Certified vehicles and branded make operated vehicle with low
sulphur diesel will be used. Ground Level Concentration (GLC) of pollutants is found to be well
within the stipulated National Ambient Air Quality Standards due to traffic movement and
vehicles used inside the premises. DG sets will be main source of Air Pollution in the project.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 88
CPCB/ MoEF & CC approved USEPA dispersion model -ISCST3 was used for prediction of
impacts caused by DG sets. Stack & emission data was used as per design value provided by
standard make and stipulated standards. Other primary data used as input for model were hourly
meteorological data of Wind speed, direction, temperature, cloud amount and mixing height.
Mixing height used in the model was taken from secondary data source “Atlas of Hourly Mixing
Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD, Delhi”. Hourly
meteorological monitored at site during study period data was compared with long term data
available from the nearest India Meteorological station or any other authorized source/Govt.
agencies.
In this project, total 4 no. of D.G. set of total capacity 9684kVA (6 x 1500 + 2 x 1010) have been
proposed, for back up of electricity supply during power failure.
This will cause emission of PM, SO2, NO2 and CO in the Ambient Air Quality. In the project
D.G. sets will be used only during power failure and low sulphur diesel will be used as fuel to
minimize SO2 emission. Therefore, incremental load in the ambient air environment will be very
low as given in the report. An adequate stack height of D.G. sets will be provided as per the
stipulated guidelines of Central Pollution Control Board (CPCB)/ National Building Code
Manual to facilitate proper dispersion of pollutants and to minimize the impact on Ambient Air
Quality under the influence of local meteorology.
Meteorology – Hourly Meteorological data of wind speed & direction, temperature, cloud
amount and rainfall were monitored at site for 3 month for the dispersion model. Wind rose
(Figure - 4.1) was prepared in sixteen directions as per standards. It was observed that westerly
and southwesterly was prevalent wind during the study period.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 89
Figure 4.1: Wind Rose Diagram (December, 2016 to February, 2017)
Model details and Frame work of Computation:
The predictions for air quality during operation phase were carried using CPCB/MoEF & CC
approved “USEPA, Industrial Source Complex (Version - ISCST3)” Dispersion model
developed by the US Environmental Protection Agency (USEPA) for prediction of pollutants
dispersion from single or multiple point sources using emission and hourly meteorological data
of the study period. Assumption used in the model was as follows:
The plume rise is limited to that of the mixing layer as published by IMD in the
Catalogue of Atlas of Mixing Heights in India for the site
Stack down-wash is not considered.
Flat terrain is used for computations;
It is assumed that the pollutants do not undergo any Physico-chemical transformation.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 90
Chemical and scavenging process occurred in the atmosphere in the pollutants released at
the stack exit is not considered.
Prediction is based on single/multiple point sources, pollution released at stack exit and
dispersed on the ground under influence of local meteorological conditions during the season.
ISCST3 dispersion model was used to predict GLC caused by a single point source at each
receptor of 40 m x 40 m of grid network covering total area of 2000 m x 2000m around the
proposed source with stack & emission values and 1-hourly meteorological data. It was
observed that SO2, NO2, Co and PM were significant pollutants released from the fuel of the
D.G. sets. Emission of PM, CO and SO2 were found insignificant with low values compared to
NO2.
Mitigation Measures: The project proponent will develop a green belt inside the premises of the
project site and along the internal road, which will work as barrier for the movement of
pollutants and help in pollution control.
4.6.4 Noise Environment
Impact: The main sources of noise from the project are running of D.G. Sets and vehicular
traffic. D.G. Sets will provide emergency electricity supply during power failure. This will be
intermittent and for short durations. The vehicles playing within the site will be mainly of the
residents and are hence not expected to cause unnecessary noise. Hence, during this phase, no
major impact on noise environment is anticipated.
Mitigation Measures: D.G. Sets will be fitted in acoustic enclosures to control the noise
generated within 25 dB (A) insertion loss or for meeting the ambient noise standard whichever is
on higher side as per E (P) Act, GSR 371 (E) and its amendments. Adequate personnel protective
equipment (PPE) will be provided. The traffic noise will diminish within a short distance from
the source of origin. Honking within the site will be discouraged. Proposed green belt plantation
will further restrict the noise.
4.6.5 Terrestrial Ecology
Impact: The project proposes 37,816.538 m2 (30 % of plot area) of green area that will be
planted with local species with aesthetic appeal that will attract local bird and insect species. As
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 91
against the existing barren stretch of land, the project will add to the greenery and beauty of the
region.
Mitigation Measures: Various kinds of plantation such as curtain, avenue, ornamental
plantation and lawns will be started during the construction phase itself and maintained during
the operation phase. Open space and Parks will be fenced through the grasses and ornamental
plants. Local and low water demanding plants that will also be effective as sinks for various
pollutants and attract birds will be grown in the site that will contribute in positive to the local
ecology.
4.6.6 Socio-economic Impact
Impact: During operational phase of the project, approx. 13000 persons will get employment
opportunities. As an estimate, during operation phase, more than 300 persons will get marginal
employment opportunities. This will help in improving the quality of life of economically
weaker sections of the local area.
Mitigation Measures: To further improve the socio-economic conditions of the area, it may be
proposed to employ mainly local people as workers. Much of the maintenance arrangements may
also be made with local companies and purchase of new parts from the local market.
4.6.7 Transport Linkage and Traffic
Impact: The vehicle from the project site will increase car and two wheeler traffic load along the
road during peak hours. However, since present load is lean, increase in traffic load may not lead
to traffic congestion problem.
Mitigation Measures: As per the planning, entry and exit will occur through service road.
Internal roads have been designed as per NBC and local regulations for smooth traffic
circulation.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 92
4.6.8 Energy Resources
Impact: During the operation phase of the project, electric supply will be provided from D.G set
and Dakshin Haryana Bijli Vitran Nigam.
Mitigation Measures: To promote energy conservation, it is proposed to provide the buildings
with low energy consuming fixtures and maximize availability of natural light.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 93
CHAPTER 5: ANALYSIS OF ALTERNATIVES
5.1 INTRODUCTION
This chapter discusses the assessment of various options that may be available for different
components of the project in terms of environmental suitability. Lately, there are a number of
options available for the use of building materials, means of energy conservation and methods of
transportation. The various applicable options are thus evaluated for their suitability to project
and environment.
5.2 BUILDING MATERIALS
The choice of building materials plays an important role in terms of energy efficiency of the
building. The manufacture of building materials should also be assessed to ensure the use of
environment friendly and recycled/ recyclable construction material.
5.2.1 Wall
Conventionally, sun burnt clay bricks are cemented in construction of walls. The strength of
these construction materials cannot be compromised which will otherwise pose a threat to the life
and property of the occupants. However, presently, materials with similar properties are easily
available that are made of waste products, thereby reducing the waste burden and conserving
natural resources. Thus, the project proposes the use of the following for walls:
Brick and block products with waste and recycled contents such as fly ash (15 to 35%), blast
furnace slag (20 to 25%), sewage sludge, waste wood fibre etc.
Fly ash based lightweight aerated concrete blocks – flyash being a waste product of thermal
power plant poses the challenge of disposal. Hazardous in powder form, it is rendered harmless
when moulded as bricks. Fly ash-based lightweight aerated concrete blocks are manufactured for
walling and roofing purposes by mixing fly ash, quick lime, or cement and gypsum with a
foaming agent like aluminum powder
Fal-G products – are manufactured by use of two waste products being fly ash, calcined
gypsum (a byproduct of phosphogypsum or natural gypsum) along with lime.
Perforated bricks
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 94
Materials proposed for use in the wall openings such as doors and windows include:
Precast thin lintels, use of Ferrocement-sunshade cum lintel etc.
Renewable timber
Steel manufactured from recycled content
Aluminum manufactured from verified recycled content
Saw dust based doors and window frames
Ferrocement shutters, PVC doors and windows, Rice husk boards, Natural fibre- reinforced
Polymer composite door panels
The finishing for the openings will be by the use of Fly ash, Ceramic tiles, Terrazzo floors.
5.2.2 Roof
The conventional material used for roofing is RCC, as it is suitable for longer spans. The
constituents of RCC, i.e. cement, sand, aggregate and steel are energy intensive materials and
high embodied energy content.
Alternately, it is proposed to use lightweight synthetic aggregates such as fly ash based
aggregates, which is suitable for manufacture of brick, blocks, and is good substitute for clinker
and natural aggregates. When pre-cast/aerated cellular concrete walling blocks and roofing slabs
are used in multi- storied structures, they reduce the weight, resulting in a more economical
design. They have high rating to fire resistance and provide better insulation and thus improved
energy efficiency. These are manufactured by the aerated cellular concrete manufacturing
process.
5.2.3 Superstructure
Structural frame of building comprises of footing, columns, beams and lintels, over which the
envelope of building is supported. A variety of metals are used in buildings. The major building
material used structurally is steel. Steel has a high-embodied energy and recyclable content, as
well as scrap value. Aluminum forms the second most common material used for roofing sheets,
window frames, and cladding systems, which has the highest recyclable content. Hence, bulk of
the metal needs for the building will be met by steel and aluminum.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 95
Problem with RCC. The choice of cement will be:
Use of fly ash and/or blast furnace slag concrete: The amount of cement used in
concrete can be reduced by replacing a portion of the cement with coal fly ash (waste material
from coal burning power plants) and/or GGBF (ground granulated blast furnace) slag in
conventional mixes.
Recycled aggregates: Recycled aggregates include crushed concrete, brick, glass, or
other masonry waste can also be used in conventional mixes
Lightweight concrete: Aluminum powder when added to lime reacts and form hydrogen
bubbles, and a lightweight cementation material is formed which could be used in conventional
mixes.
5.2.4 Roads and open spaces
Roads and open spaces consist of compound walls, grills, roads, sidewalks, parking lots, drains,
curbs, landscaped areas, street furniture, tree covers, and flowerbeds.
In line with environment friendly design it is proposed to provide:
Permeable paving- Permeable (porous) paving will be provided to control surface water
runoff by allowing storm water to infiltrate the soil and return to the ground water. The traffic
areas will however continue to be impermeable.
Gravel/crusher fines - Loose aggregate materials from masonry wastes will be used to
cover pedestrian surfaces.
Use of grass pavers on the road, parking and pedestrian areas to reduce the heat island
effect.
Use of steel in fencing, grills, tree covers, and benches and even in streetlights will be
replaced by bamboo in the parks and green landscaped areas.
5.3 NATURAL HAZARD PRONE AREAS
The project is located in high earthquake risk area (Seismic zone- IV). Special attention is thus
given to the structural design of foundation, elements of masonry, timber, plain concrete,
reinforced concrete, pre-stressed concrete, and structural steel. All applicable guidelines will also
be followed in this regard to ensure safety of the building and its residents.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 96
5.4 GREEN BUILDING
M/s. Juventus Estate Ltd proposes to design and construct the project in line with the
requirements of Green Building. Without compromising on the safety and comfort of the
occupants, care will be taken to achieve an energy efficient, water conscious project the benefits
of which will be enjoyed in monetary terms by the residents and other intangible benefits will
result for the society at large.
This will be achieved by:
a. Minimal disturbance to landscapes and site condition
The project aims to integrate the new development with the local existing surroundings. Efforts
are made to minimize on-site tree cutting by careful and detailed layout planning. Tree felling
will be undertaken only after receiving requisite permissions and under strict supervision. The
original landscape of the site has also been integrated with the design of the project such that
there is no alteration in the topography.
b. Resource Conservation and Environmental Friendly Building Materials
To reduce the ecological footprint of the development, use of recycled material for construction
and conserving natural resources is of primary importance. In this light, the use of recyclable
building materials has been proposed for various building materials. It is also proposed to reuse
building components, minimization of construction waste, etc.
The project proponent is also committed towards conservation of water. This includes use of
treated water, rainwater harvesting, provision of low water flow fixtures and raising awareness
on means of water conservation.
c. Efficient use of Water and Water Recycling
The need for water conservation in the face of impending water crisis cannot be overemphasized.
The project will follow a three pronged management for water resource viz. water resource
development, minimize use of water and recycle treated effluent within the site.
Rainwater harvesting across the entire project area is proposed to recharge groundwater. A
detailed storm water drainage system and water harvesting procedures are proposed to achieve
this.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 97
The water demand is proposed to be brought down by the use of water efficient fixtures,
implement best management practices for water conservation. An important means for achieving
this is spreading awareness to the occupants for water conservation.
To reduce the freshwater demand of the project, waste water from site will be treated in a STP
and treated effluent will be reused for landscaping, flushing and DG cooling.
d. Use of Energy Efficient design and Eco-Friendly Equipment
The project will be designed such that there is optimal solar energy utilization, especially natural
light availability. Shading will be provided on sides that will otherwise reduce the energy
efficiency of the building. Energy conservation will be one of the focuses during the planning,
development, construction and operation stages.
Use of Renewable Energy
The electrical supply is largely dependent on thermal power plants that are largely responsible
for accelerating the phenomenon of global warming and consumption of limited natural
resources. It is of paramount importance to shift focus on other renewable sources of energy to
achieve sustainable development in the energy sector. The area receives adequate hours and
intensity of sunlight for effective solar energy generation. Taking full cognizance of the
availability of natural sunlight and technology, the project proposes the use of solar energy to
reduce the power demand of the project.
Solar energy will be used for the purpose of heating of the water.
e. Indoor Air Quality for Human Safety and Comfort
To provide the occupants with a safe building is the primary responsibility of a developer. Indoor
pollution source that release gases or particles into the air are the primary cause of indoor air
quality problems in homes. Inadequate ventilation can increase indoor pollutant levels by not
bringing in enough outdoor air to dilute emissions from indoor sources and by not carrying
indoor air pollutants out of the home. High temperature and humidity levels can also increase
concentrations of some pollutants. Likewise, it is proposed to use all user safe building materials
such as:
i. The buildings will be painted with low VOC, ammonia free paints.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 98
ii. Asbestos will not be used.
iii. Adequate ventilation will be provided in each residential unit and floor
iv. Adequate openings for sunlight to enter the building, thereby reducing chances of microbial
growth.
v. All building maintenance and cleaning materials will be kept in an isolated and well
ventilated room with restricted entry.
f. Effective Controls and Management Systems
It is proposed to establish a Management System that will comprise modern equipment as well as
an efficient team of maintenance staff.
i. Each tower as well as common area will be provided with fire alarm as well as water
sprinklers. All essential services such as lifts and water supply will be provided with power
back up.
ii. A security system for the entire project will be provided comprising intercom facility,
closed circuit camera to the entrance and round-the-clock manning.
iii. Separate entry and exits are proposed. The staffs’ vehicle will be provided with
identification stickers while visitors’ vehicles will be monitored through security guards at
the entrance/exit.
The project proponent further proposes extensive green areas as avenues, parks and roadside
plantation. The plants serve to provide positive environmental impacts such as reduction in
overall energy use in buildings.
5.5 COMMUNITY ISSUES
All efforts will be made to ensure that the exiting neighborhood is not adversely affected by the
project.
5.6 ENERGY CONSERVATION
To achieve conservation of energy, appropriate design of a building is of paramount importance.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 99
Accordingly, it is proposed to incorporate the guidelines of Energy Conservation Building Code,
2017 in the building structure.
The concept of passive solar design emphasizes architectural design that minimize building
energy consumption by integrating conventional energy-efficient devices, such as mechanical
and electrical pumps, fans, lighting fixtures, and other equipment, with passive design elements,
such as building siting, an efficient envelope, appropriate amounts of fenestration, increased day
lighting design, and thermal mass. The basic idea of passive solar design is to allow daylight,
heat, and airflow into a building only when beneficial.
The project layout has been finalized after careful citing consideration various components of
Revision & Expansion of Mixed Use Development Project to optimize availability of natural
sunlight. Advanced Solar Passive Techniques are employed to achieve energy efficiency.
Glazed windows are proposed. To reduce heat losses during the night these windows are
often double-glazed and have insulating curtains.
Thermal storage wall is placed between the glazing and habitable space to prevent solar
radiation from directly entering the living space.
Passive cooling systems i.e. cooling directly from evaporation, convection radiation
without using any intermediate electrical devices.
Provisions for use of desert cooler (Indirect evaporative cooling which comprises water,
evaporative pads, a fan and a pump).
Effective measures have been incorporated to minimize the energy consumption in following
manners:
• Use of LED lamps instead of GLS lamps for Revision & Expansion of Mixed Use
Development Project.
• Use of LED instead of GLS lamps for Common area.
• T5 lamps are used instead of Normal Fluorescent lamps in Basements
• Using electronic ballast for Discharge Lamps
• Solar water heating systems will be provided as per HAREDA norms.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 100
5.7 TRANSPORTATION
A well planned road network is proposed within the project premises. Adequate parking will be
provided during construction phase to ensure that all heavy vehicles visiting the site are provided
parking space within the site. There will be no parking on the external roads. The movement of
the vehicles will also be scheduled such that the peak hours are avoided.
In the operation phase, entry and exits will be from separate gates to minimize disturbance to the
approach roads to project site
Adequate parking is proposed within the project site. Wide internal roads are proposed as per
norms. To achieve the speed limit, speed humps will be provided.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 101
CHAPTER 6: ENVIRONMENTAL MONITORING PROGRAM
6.1 INTRODUCTION
The purpose of monitoring programme is to ensure that the specified mitigation measures
defined in the EMP are complied with and leads to the desired benefits for the target area and
its population. To ensure the effective implementation of the EMP and gauge the efficiency
of the mitigation measures, monitoring will be undertaken both during the construction and
operation period of the project.
6.2 PERFORMANCE INDICATORS (PIs)
The physical, biological and social components are of particular significance to the project is
as listed below:
Air quality
Water quality
Noise levels
Solid Waste Management
Replantation success/survival rate
Of these, the following are selected as the Performance Indicators (PIs) and will be
monitored, since these are well known and comparative data series exist:
Air Quality
Noise levels
Water Quality
Flora
To ensure the effective implementation of the mitigation measures and environmental
management during construction and operation phase of project road, it is essential that an
effective Environmental Monitoring Plan be designed and followed as given in Table 6.1.
6.2.1 Ambient Air Quality (AAQ) Monitoring
Ambient air quality parameters recommended for monitoring with regard to constructional
activities are PM, CO, SO2, and NO2. Monitoring will be carried out twice a week for one
month in each season during construction phase in accordance to National Ambient Air
Quantity Standards. The locations with the pollution parameters to be monitored are detailed
out in the Environmental Monitoring Plan (Table 6.1).
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 102
6.2.2 Noise Level Monitoring
The measurement of noise levels will be carried out at all designated locations in accordance
to the ambient Noise Standards formulated by MoEFCC as given. Noise level will be
monitored on twenty-four hourly bases. Noise should be recorded at “A” weighted frequency
using a slow time response mode of the measuring instrument. The measurement location,
duration and the noise pollution parameters to be monitored are detailed in the Environmental
Monitoring Plan (Table 6.1).
6.2.3 Survival of Plantation
To ensure the proper maintenance and monitoring of the proposed plantation activities, a
regular survey of survival rate of the planted trees is proposed from the start of operation of
the project.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 103
Table 6.1: Environmental Monitoring Plan
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Ground Water
Quality
Construction
Stage
Drinking water
parameters
Drinking water standards
(IS 10500)
10 locations
including project site
Half yearly
Operation
Phase
Drinking water
parameters
Drinking water standards
(IS 10500)
Project site Once every year during the
dry season
Drinking water Construction
Stage
Drinking water
parameters
Drinking water standards
(IS 10500)
Supply water Half yearly
Operation
Phase
Drinking water
parameters
Drinking water standards
(IS 10500)
Supply water Half yearly
Treated
wastewater
Operation
Phase
pH, BOD, COD, TDS ,
TSS, DO,
General Standards for
discharge of effluents
Outlet of the Sewage
Treatment Plant (s)
Every three months during
the project life cycle
Air Construction
Phase
PM, SO2, NO2, CO National Ambient Air
Quality Standards
1) Project Site
2) Sector 99A
3) Garoli Khurd
4) Basai Village
5) Daya Vihar
Continuos 24-hourly, Half
Yearly
Operation
Phase
PM, SO2, NO2, CO, National Ambient Air
Quality Standards
Project Site Continuous 24-hourly,
HalfYearly
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 104
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Noise Construction
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
1) Project Site
2) Sector 99A
3) Garoli Khurd
4) Basai Village
5) Daya Vihar
One day hourly
measurement, Half Yearly
Operation
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
Project site One day hourly
measurement, Half yearly
Rainwater
harvesting
Operation
Phase
Inspection of storm water
drains and rainwater
harvesting pits
Design parameters Project site Prior to monsoon
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 105
6.3 DATA MANAGEMENT
The monitoring will be carried out through MoEFCC/ NABL approved laboratory. All results
will be maintained and submitted to the Regulatory authorities as per norms.
6.4 REPORTING SCHEDULES
The environment management cell will be responsible for timely conduct of the monitoring
activities. The results of the analysis will be intimated to the project head.
Any anomaly in test results will be investigated into and proper corrective actions will be
undertaken.
A complaint register will also be maintained to note any complaints from the staff and visitors in
the project or any other stakeholder. Corrective actions taken against the complaints will also be
noted.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 106
CHAPTER 7: ADDITIONAL STUDIES
7.0 INTRODUCTION
This chapter broadly looks at various aspects related to disaster management, resource
conservation and resettlement issues.
7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
The project will encompass the lives of a large number of people. It will also involve installation
of various structures and machineries that meet the comfort and needs of its residents but may
also pose serious threat in case of an accident. It is thus considered necessary to carry out a risk
assessment and disaster management plan for the project.
7.1.1 Risk Hazard & its control measures
It is attempted to plan and construct the buildings following all safety norms. However, it is not
always possible to totally eliminate such eventualities and random failures of equipment or
human errors. An essential part of major hazard control has therefore, to be concerned with
mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed
table showing activities during construction and operation phase along with mitigation measures
are given in Table 7.1.
Table 7.1: Activities during construction and operation along with mitigation measures
HAZARDS ASSOCIATED WITH
ACTIVITIES
(During Construction & Operation)
CONTROL/MITIGATION
MEASURES
Manual Handling
- Strains and sprains due to incorrect lifting
- too heavy loads
-Twisting - bending - repetitive movement - body
vibration.
- Exercise/warm up
- get help when needed
- control loads
- rest breaks/no exhaustion
- no rapid movement /twisting/ bending /
repetitive movement
- Good housekeeping.
Falls - Slips - Trips
- Falls on same level
- falls to surfaces below
- poor housekeeping
- slippery surfaces
- Good Housekeeping
- tidy workplace
- guardrails, handholds, harnesses, hole
cover, hoarding, no slippery floors/trip
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 107
- uneven surfaces
- poor access to work areas climbing on and off
plant
- unloading materials into excavations wind
- falling objects.
hazards
- clear/ safe access to work areas
- egress from work areas
- dust/water controlled
- PP
Fire
- Flammable liquids/Gases like LPG, Diesel
Storage area and combustible building materials
- poor housekeeping
- grinding sparks
- Open flames, absence of Fire hydrant network.
- Combustible/flammable materials
properly stored/used
- good housekeeping
- fire extinguishers made available & Fire
hydrant Network with reserve Fire water
(As per NFPA Code)
- Emergency Plan in case of Fire or collapse
of structure.
Absence of Personal Protective Equipment
- Lack of adequate footwear
- head protection
- hearing/eye protection
- respiratory protection
- gloves
-goggles.
- Head/face
- footwear
- hearing/eye
- skin
- respiratory protection provided
- training
- maintenance
Defective or wrong Hand Tools
- Wrong tool
- defective tool
- struck by flying debris
- caught in or on
- missing guards
- Right tool for the job
- proper use of tools
- good condition/ maintenance guards
- isolation/ proper demarcation of work
space
- eye/face protection
- flying debris controlled
Electricity
- Electrocution
- overhead/underground services
- any leads damaged or poorly insulated
- temporary repairs
-no testing and tagging
- circuits overloaded
- non use of protective devices.
- Leads good condition and earthed
- no temporary repairs
- no exposed wires
- good insulation
- no overloading
- use of protective devices
- testing and tagging
- no overhead/ underground services
Scaffolding
- Poor foundation
- lack of ladder access insufficient planking
- lack of guardrails and toe boards
- insufficient ties or other means
- all scaffolds incorrectly braced or stabilized
to prevent overturning.
- All scaffolds correctly braced and
stabilized
- 3:1 height to base ratio
- firm foundation, plumb and level
- ladder access provided and used
- proper platform (3 planks/675 mm)
- planks secured
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 108
- guardrails and toe boards
- 900mm to 1100mm high, within
200mm of working face, mid-rail.
Ladders
- Carrying loads
- not secured against dislodgement
- defective ladders
- not sufficient length
- wrong positions
- incorrectly placed (angles, in access ways,
vehicle movements.
- Secured against movement or footed
- ladders in good condition
- regularly inspected
- extend 1m above platform
- 4:1 angle
- out of access ways, vehicle
movements
- not carrying loads
- 3 points of contact
- no higher than 3rd
step down
- use for access only, not working
platforms
Excavations
- Trench collapse
- material falling in undetected underground
services
- falls
- hazardous atmosphere struck by traffic and
mobile plant.
- Soil stability known
- no water accumulation
- existing services known
- material 600mm from edge
- clear of suspended loads
- hardhats/PPE
- ladders
- public protection
– atmospheric testing
- traffic controls
- Emergency Plan.
Gas Cutting and Welding
- Fire
- welding flash, burns, fumes, electrocution
in wet conditions
- flashback in oxygen set, leaking cylinders,
acetylene cylinders lying down
- poorly maintained leads.
- Welding flash and burns controlled
with PPE and shields
- fumes controlled with ventilation
and PPE (in good condition and properly
positioned),Gas cylinders be kept upright &
secured position (properly tied)
- Combustible materials to be kept at
secured place to avoid fire & Fire
Extinguishers to be kept in fire prone area
with training to people for its use.
Noise
- Unknown noise levels
- known noise levels over 85 decibels
- Levels below 85 decibels
- Proper protection.
Falling Material
- Fall during carrying/Lifting materials-
dislodged tools and materials from overhead work
areas.
Materials to be secured
kept away from edge
toe boards
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 109
Use of hard hats.
Craneage& Lifts
- Display of carrying capacity i.e. load (No. Of
person), incorrectly slung, defective lifting
equipment, unsecured loads, craning in close
proximity to building people and plant
- falls
- falling materials.
- Periodic testing by competent authority
- correctly slung/secured loads, lifting
equipment good condition
- use of proper hand signals
- falls while unloading controlled.
Visitors Presence at site - Falls
- struck by dropped materials
- road accidents
- insufficient hoarding or fencing
- pedestrian access past site
- mechanical plant movement on and off site.
- Sufficient hoarding
- fencing and barricades
- safe pedestrian access past site
traffic management for loading and delivery
- construction separated from
occupied areas of projects.
7.1.2 Emergency Response Plan (ERP)
The overall objective of an Emergency Response Plan (ERP) is to make use of the combined
resources at the site and outside services to achieve the following:
1. To localize the emergency and if possible eliminate it;
2. To minimize the effects of the accident on people and property;
3. Effect the rescue and medical treatment of casualties;
4. Safeguard other people;
5. Evacuate people to safe areas;
6. Informing and collaborating with statutory authorities;
7. Initially contain and ultimately bring the incident under control;
8. Preserve relevant records and equipment for the subsequent enquiry into the cause and
circumstances of the emergency;
9. Investigating and taking steps to prevent reoccurrence
The ERP is therefore related to identification of sources from which hazards can arise and the
maximum credible loss scenario that can take place in the concerned area. The plan takes into
account the maximum credible loss scenario - actions that can successfully mitigate the effects of
losses/ emergency need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 110
Main hazards identified for the project include hazards pertaining to fires in buildings and fire in
diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in
the following section.
7.2 RESPONSE IN CASE OF EARTHQUAKE
Response Procedures for Occupants
If indoors:
1. Take cover under a piece of heavy furniture or against an inside wall and hold on.
2. Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to
leave the building because objects can fall on you.
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay
there until the shaking stops.
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses,
or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps
that might have been damaged by the quake.
After the earth quake
1. After the earthquake be prepared for aftershocks.
2. Although smaller than the main shock, aftershocks cause additional damage and may bring
weakened structures down. Aftershocks can occur in the first hours, days, weeks, or even
months after the quake.
Help injured or trapped persons.
1. Give first aid where appropriate. Do not move seriously injured persons unless they are in
immediate danger of further injury. Call for help.
2. Remember to help those who may require special assistance--infants, the elderly, and people
with disabilities.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 111
3. Stay out of damaged buildings.
4. Use the telephone only for emergency calls.
Response Procedure for Emergency Team
1. Formulate an Emergency Response Team for earthquake response.
Using the public address system, inform residents of response procedures discussed above.
2. Inform the necessary authorities for aid.
3. Ensure no person is stuck beneath any debris, in case of a structural failure.
4. Ensure that all occupants standing outside near the buildings are taken to open areas.
5. Ensure that the first aid ambulance and fire tender vehicles are summoned if necessary.
6. Inform the nearby hospitals if there are any injuries.
7. Check the utilities and storage tanks for any damage.
7.3 RESPONSE FOR LPG LEAKAGE
1. The affected area should be evacuated and cordoned off immediately
2. Initiate an Emergency Response Team for LPG leakage.
3. Shut down the main valves in the gas bank.
4. Ensure that only concerned personnel are present in the affected area and all other personnel
and visitors are moved to the nearest assembly points.
5. Rescue trapped personnel, also check if any personnel are unconscious in the area and
immediately move them outside and provide first aid. Ambulance should be summoned to take
injured personnel to the nearest hospital.
6. Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked
gas.
7. Source of leakage to be traced and isolated from all the other areas. And if required use
pedestal fans to bring down the gas concentration.
8. In case of a fire follow the instructions in case of fire.
7.4 RESPONSE IN CASE OF FIRE
1. Required response during in the event of a fire should be described in signs located in the
lobby.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 112
2. On sighting a fire, it should be immediately informed to the environment manager
giving the exact location and type of fire in detail.
3. Initiate the Emergency Response Team for fires.
4. If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher.
5. Guide the Emergency Response Team staff to the emergency assembly point.
6. The Emergency Response Team should immediately inform the nearest dispensary and
security force. If required a fire tender should be summoned.
7. The response team should immediately move to the point of fire and take all necessary steps to
stop the fire. If the fire is not controllable and spreads then the manager in charge should inform
the district authorities and call for external help.
8. The Emergency Response Team will provide immediate relief to the injured residents at the
scene of incident. Any injured persons should be evacuated on priority to the dispensary or one
of the nearest hospitals based on their condition.
Instructions for occupants
1. Get out of buildings as quickly and as safely as possible.
2. Use the stairs to escape. When evacuating, stay low to the ground.
3. If possible, cover mouth with a cloth to avoid inhaling smoke and gases.
4. Close doors in each room after escaping to delay the spread of the fire.
5. If in a room with a closed door.
6. If smoke is pouring in around the bottom of the door or if it feels hot, keep the door closed.
7. Open a window to escape or for fresh air while awaiting rescue.
8. If there is no smoke at the bottom or top and the door is not hot, then open the door slowly.
9. If there is too much smoke or fire in the hall, slam the door shut.
10. Stay out of damaged buildings.
11. Check that all wiring and utilities are safe.
A state of the art firefighting system is proposed for the project to prevent and control fire
outbreaks. The firefighting system will consist of portable fire extinguishers, hose reel, wet riser,
yard hydrant, automatic sprinkler system, and manual fire alarm system. The Modification &
Expansion of Group Housing Colony buildings will also be provided with automatic fire
detection and alarm system.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 113
7.5 RESOURCE CONSERVATION
The project will lead to utilization of various natural resources. As an environmentally
responsible corporate, the developer will endeavor to conserve these resources by judicious
management and recycling and strive to build up these resources where possible.
No withdrawal of groundwater: The water during operational phase will be sourced from
HUDA.
Reduced use of water: To further minimize the use of available freshwater, various low flow
fixtures may be provided such as Low flow flushing systems, sensor based fixtures, waterless
urinals, tap aerators. Awareness will also be spread amongst the residents on the following lines:
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Watering of lawn or garden during the coolest part of the day (early morning or late
evening, hours) when temperature and wind speed are lowest. This reduces losses due to
evaporation.
Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees. Once
fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for more
than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the water
and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning systems;
Equipping spring loaded shutoff nozzles on hoses;
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 114
Installation of float-controlled valve on the make-up line, closing filling line during
operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water.
Treatment and Recycling: The wastewater generated from the sites will be treated in on-site
Sewage Treatment Plant. This will enable the treated wastewater to be used for flushing and
landscaping thereby reducing the requirement of freshwater for these purposes.
Rainwater harvesting: The increased hard surface as a result of the project will increase the
runoff as compared to an otherwise barren land. It is proposed to harvest this rainwater runoff
that will recharge the groundwater resource while reducing the burden of storm water
management of the city and eventually natural water bodies. Apart from the open spaces, it is
proposed to harvest the roof top rainwater. The storm water will be treated through an oil and
grease trap and allowed to flow through layers of sand and gravel for filtration prior to reaching
the water table, to avoid any possibility of groundwater contamination.
Construction materials: The project will require various kinds of natural construction minerals
such as sand, gravel etc. It is proposed for prior estimation of required quantities of these
materials and procurement only as per requirement. This will also result in cost-efficiency.
Excavated soil from the project site will be used within the site to the extent feasible. Excess soil
will be made available to the nearby construction sites, as per demand or sold to local vendors.
Energy: To conserve the energy resources, good practices will be followed during the
construction phase such as turning off lights and equipments when not in use, ensuring fuel
efficiency of motors and vehicles through proper maintenance and minimal work at night. The
principles of energy conservation will also be embedded in the buildings through use of energy
efficient fixtures, maximum availability of natural light and use of solar energy for street
lighting.
7.6 RESETTLEMENT AND REHABILITATION
The project will not result in displacement of local population and hence does not require a
resettlement and rehabilitation study.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 115
7.7 CORPORATE SOCIAL RESPONSIBILITY
M/s. Juventus Estate Ltd continues to create world-class infrastructure and realizes its
responsibilities as a responsible Corporate and a change agent for accelerating the pace of social
and economic transformation across various segments to complement the efforts of government.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 116
CHAPTER 8: PROJECT BENEFITS
8.1. GENERAL
The Modification & Expansion of Group Housing Colony is located at Village Dhanwapur ,
Sector-104, Gurugram, Haryana on land measuring 34.022 acres.
The project offers environment friendly condominiums with amenities such as power backup,
food court, convenient shopping, including for economically weaker sections of the society and
service units.
8.2. PHYSICAL INFRASTRUCTURE
The project will help in meeting the growing commercial demand for people. It provides state-
of-the-art offices and modern terms of comfort and safety of its occupants. Care has been taken
to provide the occupants and visitors with necessary facilities as power, water supply, parking
spaces, and landscaping, wide internal roads that are safe and secure.
8.3. SOCIAL INFRASTRUCTURE
The project will result in an overall development of the region with construction/maintenance of
new/existing roads, power supply and water supply.
8.4. ECONOMIC BENEFITS
The project will have positive impact on the local economy. The construction phase will engage
a large number of construction workers including skilled, semi-skilled or unskilled.
During Operation phase too, several direct and indirect opportunities will be created which will
further stimulating the local economy. Public transport facilities are also likely to improve with
the development of the area.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 117
CHAPTER 9: ENVIRONMENTAL MANAGEMENT PLAN
9.1 INTRODUCTION
Identification and prediction of impacts further needs to suggest the mitigation measures which
would play a vital role in prevention of environmental degradation during construction and
operational phase of the project. This leads to preparation of Environmental Management Plan
(EMP), therefore EMP forms an imperative part of EIA process.
The Environmental Management plan is a site specific plan developed to ensure that the
project is implemented in an environmentally sustainable manner where all contractors and
subcontractors, including consultants if any, understand the potential environmental risks
arising from the project and take appropriate actions to minimize those risks. EMP also ensures
that the project implementation is carried out in accordance with the planned design and by
taking appropriate mitigates actions to reduce adverse environmental impacts during project’s
life cycle.
The project is being created certain inevitable impacts, mainly during construction phase,
although within permissible limits as mentioned in Chapter 4 and can be reduced significantly
with the help of effective implementation of a well-designed EMP. The potential
environmental impacts, which need to be regulated, are as mentioned below:
Air pollution due to the emission of particulate matter and gaseous pollutants from
operation of D.G. Sets during power failure and vehicular movement;
Noise pollution due to various noise generating equipment as well as vehicular movement;
Water resource management to ensure continuous water supply.
Wastewater generation from sanitary/domestic activities; and
Generation of municipal solid wastes from residences, maintenance of roads, parks,
common areas including constructional, electrical and plumbing wastes.
Energy conservation methods
Maintenance of Building Management Systems and emergency aids.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 118
To ensure better environment in & around the project site, effective EMP needs to be
developed separately for construction and operational phase.
9.2 ENVIRONMENTAL MANAGEMENT STRATEGIES
Strategy for environmental management in construction work is based on three-pronged
approach comprising of:
Pollution prevention.
Pollution control.
Protection of pollution recipients.
9.2.1 Topography and Physiography
During the development, construction and operation phase of the project, no significant impact
is anticipated on local or regional topography and Physiography, hence exhaustive
management plan is not required.
9.2.2 Soil
Development & Construction Phase
During the construction phase, various kinds of wastes are generated that is being disposed in
varied ways. The following measures are being taken to prevent soil contamination at site and
ensure waste management:
Vegetation and top soil management:
Remove vegetative cover only from the specific area on which construction is being
take place.
Plantation as proposed will be started at the earliest.
The top soil has been stripped from constructional areas and stockpiled for later reuse
in landscaping.
Promote use of organic fertilizers.
Construction of erosion prevention troughs, as deemed necessary.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 119
To prevent the erosion of excavated loose soil produced as a result of excavation, site
preparation activities and excavation work would be undertaken during dry season after
monsoon is over.
Construction Debris:
Fuel and oil is being stored in cement lined storage yard and handled carefully to
prevent soil contamination through leakage or spillage.
All metal, paper, plastic wastes, debris and cuttings have been collected from site as
soon as particular construction activity is over.
During construction of flexible pavement, bitumen wastes is being collected (if any)
and disposed in environmentally sound manner.
The number, frequency and area of movement of heavy machinery are also restricted.
Recycling of construction wastes into aggregates for use in the project site.
Used oil from DG Sets is being stored in HDPE drums in isolated covered facility and
disposed-off as per the Hazardous Wastes (Management & Handling) Rules, and its
amendments 2016.
Wastes from the labour camps will be collected and disposed as per the existing
practices in the site.
Operation Phase
To prevent soil contamination at site, the most important aspect is to manage the solid wastes
that will be generated during the operation phase. The Environmental Management Plan for
solid waste focuses on three major components during the life cycle of the waste management
system i.e. collection, transportation, and treatment or disposal.
Collection and segregation of wastes
Solid waste generated from project would be collected door to door and segregated into
decomposable, recyclable and inert wastes.
Decomposable wastes will be decomposed and converted to manure to be used for
horticulture.
Recyclable waste would be sold to vendors.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 120
Inert waste which comprises a very small amount of the total solid waste generated would
be temporarily stored within the project premises.
Waste bins would be placed at the strategic locations such as inter section of internal roads,
parks, common places, etc.
To minimize littering and odors, waste will be stored in well-designed containers/ bins that
will be located at strategic locations to minimize disturbance in traffic flow.
Care would be taken such that the collection vehicles are well maintained and generate
minimum noise and emissions. During transportation of the waste, vehicle will be covered to
avoid littering.
Disposal
Non-recyclable and non-biodegradable waste will be disposed through local approved agency.
The biodegradable waste will be converted to manure through Organic Waste Converter. SWM
Plan for Operation phase is shown below:
Figure 9.1 Solid Waste Management Flow Diagram (Operation Phase)
A local vendor will be hired for solid waste management during Operation Phase.
Solid Waste
Recyclable Non- Recyclable
Biodegradable Waste
Blue Bins
Organic waste Converter
Dark grey Bins
Final disposal through Govt. approved
agency
Non-Biodegradable Waste
Green Bins
Final disposal through a Govt. approved
agency to Manure
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 121
9.2.3 Hydrology
Ground Water
Development & Construction Phase
The water requirement during the construction phase will met from recycled water from STP
of HUDA. The following are also proposed to further reduce the demand of water:
Curing water will be sprayed on concrete structures and free flow of water not allowed.
After liberal curing on the first day, all concrete structures will be painted with curing
chemical to save water to stop daily water curing hence save water.
Concrete structures are being covered with thick cloth/gunny bags and then water
sprayed on them to avoid water rebound and ensure sustained and complete curing.
Pools have been made using cement and sand mortar to avoid water flowing away from
the flat surface while curing.
Water ponding has been done on all sunken slabs. This has also highlighted the
importance of having an impervious formwork.
Post Construction Phase
It is proposed to conserve groundwater resources through the combined means of water
resource development, minimized water consumption and reuse of treated sullage to reduce
freshwater demand.
Water Resource Development
The storm water collection system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall
run off from roads shall flow towards the drains. Storm water from various plots/shall be
connected to adjacent drain by a pipe through catch basins. Therefore, it has been calculated to
provide 34 rainwater harvesting pits at selected locations, which will catch the maximum run-
off from the site.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 122
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at
regular intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement
storm water storage tank. This water will be pumped out to the nearest external storm
water drain.
4) The peak hourly rainfall of 45 mm/hr shall be considered for designing the storm water
drainage system.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak
hourly rainfall has been considered as 45 mm/hr. The recharge pit of 4 m diameter and 3 m
depth is constructed for recharging the water. Inside the recharge pit, a recharge bore is
constructed having adequate diameter and depth. The bottom of the recharge structure will be
kept 5 m above this level. At the bottom of the recharge well, a filter media is provided to avoid
choking of the recharge bore. Design specifications of the rain water harvesting plan are as
follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic
bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is
flushed off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been
connected to the system.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 123
Calculations for storm water load (EC Accorded + Expansion/Modification):
Net Plot Area = 1, 26,055.128 m2
Roof-top area = Ground Coverage = 13,591.98 m2
Green Area = 37, 816.538 m2
Paved Area = Plot Area – (Roof-top Area + Green Area)
= 1, 26,055.128 – (13,591.98 + 37,816.538)
= 1, 26,055.128 – 51,408.518
= 74,646.61m2
Roof-top area = 13,591.98 × 0.045 × 0.90
= 550.475m3/hr
Green Area = 37, 816.538 × 0.045 × 0.20
= 340.34m3/hr
Paved Area = 74,646.61× 0.045 × 0.70
= 2351.368m3/hr
Total Runoff Load = 550.475 + 340.34 + 2351.368
= 3242.183m3/hr
Taking 20 minutes retention time, volume of storm water =3242.183/3 = 1080.72m3
Capacity of Recharge pit = π r2h = 3.14 × 2 × 2 × 2.5 = 31.4m3
Hence No. of pits required = 1080.72/31.4= 34.41 pits/ 35 pits
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 124
As 1 pit/acre is required so, total 35 rain water harvesting pits will be required for 34.0228 acre
land.
Total of 35 Rain Water Harvesting pits are being proposed for artificial rain water recharge
within the project premises.
Figure 5: Rain Water Harvesting Pit Design
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 145
Storm water management system
Since the storm water on site will be harvested for ground water recharge, proper management
of this resource is necessary to prevent contamination. Hence, regular inspection and cleaning
of storm drains will be carried out. Use of fertilizers and pesticides will be avoided prior to
and during monsoons. Clarifiers or oil/ water separators will also be installed.
Minimal Water Consumption
To reduce the water consumption, awareness along the following lines will be spread amongst
the management and maintenance team:
Installation of water meters conforming to ISO standards at inlet and outlet point
of water supply.
To further lower the water consumption, options of Low flow flushing systems,
sensor based fixtures, and tap aerators etc. will be explored.
Leak detection
Drip irrigation for shrubs and trees
Use of low-volume, low-angle sprinklers for lawn areas
The message of water conservation will be spread amongst the residents through awareness
campaigns and pamphlets. Following tips will be provided to the residents for conserving
water.
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Use of mug rather than running water for shaving;
Avoiding/minimizing use of shower/bath tub in bathroom;
Turning off faucets while soaping and rinsing clothes;
Using automatic washing machine only when it is fully loaded;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Watering of lawn or garden during the coolest part of the day (early morning or
late evening, hours) when temperature and wind speed are lowest. This reduces
losses due to evaporation.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 146
Planting of native and/or drought tolerant grasses, ground covers, shrubs and
trees. Once fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for
more than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the
water and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning
systems;
Equipping spring loaded shutoff nozzles on hoses;
Installation of float-controlled valve on the make-up line, closing filling line
during operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water.
Re-use of treated effluent
It is expected that the project will generate approx. 915 KLD of waste water. The waste water
will be treated in 3 onsite STPs of total capacity 1100 KLD that will generate 823 KLD of
treated effluent which will be reused for flushing & horticulture. Surplus treated effluent will
be discharged to external sewer.
Ground water Quality
Development and Construction Phase
To ensure against any groundwater pollution through leaching of soil, solid waste
management plan ensuring timely collection of wastes is being followed. The collected wastes
is being stored at designated area and disposed as per the standard procedures in line with the
statutory requirement.
Post Construction Phase
The ground water pollution can arise from improper waste handling or by recharge of
groundwater through contaminated storm water. A well planned solid waste management as
discussed in Chapter 2 is proposed for the operation phase that will ensure against any
chances of soil or groundwater pollution on this account.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 147
Storm water collects dirt and garbage along its flow. Contamination of this water with spilled
oil/ grease is especially of concern when recharging is proposed. Hence, preliminary treatment
for oil and grease and filtration through layers of sand and gravel is proposed prior to recharge
of the groundwater.
Landscaping water enters the soil and finally the groundwater. It is thus of utmost importance
that only clean water is used for horticulture purposes. The water from the households will
contain significant amounts of detergent and soap that is undesirable for plants, soil and in
groundwater. Hence, it is proposed to treat the waste water from the site up to tertiary level,
and be used for flushing, landscaping, etc. Regular monitoring of treated effluent will be
carried out to ensure that all parameters are within acceptable limit.
9.2.4 Air Quality
Development and Construction Phase
The construction phase of the project will last for about 3-4 years, causing marginal
impact on ambient air quality from constructional activities, unloading of construction
materials, cement, soil and vehicular movement etc. The main pollutant of concern is
PM 2.5 & PM10 (dust). Likewise, following mitigation measures is being adopted during
this phase to mitigate the impacts on ambient air:
Installation of batch plant at isolated place and providing cover shed around plants.
Loading and unloading of cement and other material in covered shed.
Providing dust suppression system in unloading area (as per requirement).
Developing avenue and curtain plantation on the internal roads and peripheral
plantation around the site to protect the movement of dust and other pollutants.
Cover scaffolding, hosing down road surfaces and cleaning of vehicles.
On-Road- Inspection for black smoke generating machinery.
Vehicles having pollution under control certificate is allowed to ply.
Use of covering sheets for trucks to prevent dust dispersion from the trucks.
Reducing the speed of a vehicle to 20 km/hr to reduce emissions on site.
All material storages is adequately covered and contained.
Training to the workers to reduce idling time of machines that otherwise tends to
produce hydrocarbons and carbon monoxide.
Best practices for maintenance and repair of all machineries and equipment.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 148
Operation Phase
During the operation phase, following measures will be adopted for air pollution control:
Adequate stack height for DG sets
Low sulphur diesel based DG sets
Traffic management to avoid congestion
Green belt plantation
DG Set: The running of DG sets will result in emission of various pollutants. To achieve
adequate natural dispersion, adequate stack height will be provided as per guidelines of
Central Pollution Control Board (CPCB).
Traffic management: Internal roads would be maintained in good conditions to control the
dust emissions and adequate width will be provided to avoid traffic congestion.
Plantation development: Plantation is an effective means for controlling air pollution due to
its dual action of acting as a barrier between the source of emission and receptors and also as a
sink for various pollutants.
It is proposed to develop the green area species effective in absorption of expected pollutants
at site, along the internal roads and on the periphery of the project. Suggested species for
plantation are:
Cassia fistula (Amaltas)
Delonix regia (Gulmohar)
Bauhinia variegate (Kachnar)
Thevetia peruviana (Kaner)
Dalbergia sissoo (Shisham)
9.2.5 Noise Levels
Development and Construction Phase
During the construction phase, some noise is being generated through the operation of
construction machines, excavators, DG set, etc. Following measures would be taken; into
consideration to mitigate the noise at construction site:
Use of well-maintained equipment fitted with silencers and providing noise shields
near the heavy construction operations
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 149
Acoustic enclosures would be provide to DG sets at the construction site,
Earmuff and other protection devices will be provided to laborers working in high
noise generating machines.
High noise activities will be carried out during daytime.
Operation Phase
The main sources of noise during this phase are the intermittent use of DG Sets and traffic.
The principles of noise emission control and screening are proposed for the two different
scenarios of noise generation.
Noise emission control
All the D.G. Sets will be provided with acoustic enclosures ensuring 25 dB (A) insertion loss
or for meeting the ambient noise standards whichever is higher as per CPCB norms. It will be
ensured that the manufacturer provides acoustic enclosures as an integral part with Diesel
Generator Sets.
Barriers
Trees having thick and fleshy leaves with flexible petioles having capacity to withstand
vibration are suitable. Heavier branches and trunk of the trees also deflect or refract the sound
waves. The following species are proposed to be used in a greenbelt especially surrounding
plotted colony and along the periphery of the project.
Antocephalous cadamba (Kadam)
Polyathia longifolia (Ashok)
Terminalia arjuna (Arjun)
9.2.6 Biological Environment
Development and construction phase
During the development, construction and operation phase, no tree has been cut and therefore
no impact is anticipated on terrestrial ecology. Site clearing has been carried out strictly as per
plan. Workers have advised against cutting, uprooting, coppicing of trees or small trees
present in and around the project site for cooking. Workers have also been discouraged from
wandering in nearby areas with plantation or dense vegetation.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 150
Further, green belt has been developed on the periphery and along the internal roads of project
site during the construction phase itself that will act as a curtain to restrict the movement of
pollutants from either side of the project and improve site aesthetics.
Operation phase
During the operation phase, green belt will be developed and maintained. Ornamental plant
species and grasses will be planted in open space within the premises. 37,816.538 m2 (30%) is
proposed to be maintained as green within the project site.
9.2.7 Demographic and Socio-Economic Environment
Development and Construction Phase
During the development and construction phase of the project, more than 800-850skilled,
semiskilled and unskilled workers got direct and indirect employment opportunities which
have beneficial impact on the socio-economic condition of the area.
Following suggestions are given to strengthen the beneficial impacts on the socio-economic
environment.
All the applicable guidelines under relevant acts and rules related to labor welfare and
safety is being implemented during the construction work activities.
Proper sanitary and drinking water facilities have been provided to workers living in
the construction camps within the project premises.
Workers have been provided with appropriate PPEs during work.
Guarding of dangerous machine parts, maintenance of equipment’s as hoists and lifts
is being ensured
Adequate provision of different types of fire extinguishers has been made.
Construction Camps has been provided with clean and safe drinking water and toilet
facilities. Domestic refuse generated at the construction camps is being disposed off on
a regular basis. First Aid Medical facilities have been proposed for the construction
workers.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 151
Operation Phase
The project envisages addressing the wider goal of environmental protection through a social
investment strategy for the communities around the project. The project seeks to increase the
benefits to the local population and contribute towards meeting community’s expectation of
benefits from the project.
Some of the concerns raised by local people relate directly to the project. Concerns and
aspirations not directly related to the project were also solicited so as to identify areas that
could be addressed through socially responsible initiatives and interventions. These were:
a) Demand for employment opportunities.
b) Infrastructure development
The proposed strategy envisages addressing the wider goal of sharing benefits with the local
community. The following activities would be undertaken.
Income Generation Opportunity for local community
The local people will be given preference, although they will be recruited on their individual
merit. Tender specification for operation services will include favorable employment
opportunities towards the local population. The main principles of employment are outlined
below:
Employment strategy will provide for preferential employment during operation
phase.
General recruitment procedures will be transparent, public and open to all.
Recruitment procedures will be publicized at locally prominent locations in advance.
There will be no discrimination on basis of gender, caste or other factors.
Contractors would be required to abide by the Indian labour laws regarding standards
on employee working conditions, minimum wages for workers, safety and welfare
measures. Following the appointment of the contractor, information on employment
will be available to the local community at the Panchayat office or other prominent
places like the school, frequently visited spots in the village etc. Information on the
following aspects would be provided- scale and duration of employment, type of
available work and demand projection.
Improved working conditions
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 152
The project would provide safe working conditions for the labor and other workers employed
at the facility during construction and operation phase. Conditions of employment would
address issues like minimum wages, medical care, etc.
9.2.8 Vehicle Parking and Traffic Management
Adequate provision will be made for car/vehicle parking at the project site. There will also
be adequate parking provisions for visitors so as not to disturb the traffic and allow smooth
movement at the site.
9.2.9 Energy Conservation
The Project will be designed in such a way that natural light is maximized indoor. The project
will be energy efficient through use of low energy consuming fixtures. Energy conservation
will be achieved through various means as given below.
Site Plan and building design
Maximum utilization of solar light will be done
Public areas will be cooled by natural ventilation as opposed to air-conditioning
Maximize the use of natural lighting through design
The orientation of the buildings will be done in such a way that maximum daylight is
available
The water bodies and green areas will be spaced, so that a significant reduction in the
temperature can take place.
Energy saving
Energy efficient lamps will be provided within the complex.
Constant monitoring of energy consumption and defining targets for energy
conservation
Adjusting the settings and illumination levels to ensure minimum energy used for
desired comfort levels
Awareness
Promoting resident awareness on energy conservation
Training staff on methods of energy conservation and to be vigilant to such
opportunities
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 153
9.2.10 Management and Maintenance System
Management and maintenance is an important issue for the project. During the construction
phase the project proponent will take care of the implementation of environmental
management plan.
They will review the effectiveness of implemented mitigation measures adopted by
contractors and sub-contractors from time to time. The buildings will be provided with water
sprinklers and fire alarms and there will be provision of adequate number of fire extinguishers
as per NBC norms. Power back up service will be provided for all emergency equipment and
machineries.
Operation, management and maintenance of the internal services laid inside the project will be
done by the project proponent.
Institutional Capacity Building
a. Reporting: For effective implementation of any system/ plan, a systematic reporting
system is essential. An Environmental Management Cell will be set up for implementation of
the proposed Management Plan. Reporting of the results of all the management and
monitoring plan will be submitted to the designated Project Head. The reports will be
reviewed and parameters exceeding their limits should be identified and the reason for the
same investigated. Any requisite mitigation plan will be taken up accordingly.
The Environment Management Cell will be a permanent organizational set up charged with
the task of ensuring its effective implementation of mitigation measures and conduct
environmental monitoring. The major duties and responsibilities of Environmental
Management Cell will be as given below:
To implement the environmental management plan
To assure regulatory compliance with all relevant rules and regulations
To ensure regular operation and maintenance of pollution control devices
To minimize environmental impact of operations as by strict adherence to the EMP
To initiate environmental monitoring as per approved schedule
b. Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 154
c. Maintain documentation of good environmental practices and applicable environmental
laws for a ready reference
d. Maintain environmental related record
e. Coordination with regulatory agencies, external consultants, laboratories, etc.
f. Maintenance of log of public complaints and the action taken.
Hierarchical Structure of Environmental Management Cell
EMP cell would be supervised by the Project Head.
Awareness and Training
Training and human resource development is an important link to achieve sustainable
operation of the facility and environment management. For successful functioning of the
project, relevant EMP would be communicated to residents and contractors.
Occupants must be made aware of the importance of waste segregation and disposal, water
and energy conservation. The awareness can be provided by periodic Integrated Society
meetings. They would be informed of their duties.
9.3 OVERALL MITIGATION MEASURES AND ENVIRONMENTAL
MANAGEMENT PLAN
Overall impact assessment of anticipated environmental impacts and mitigation measures &
environmental management plan to mitigate the potential impacts during the development &
construction and operation phase are summarized in Table 9.1.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 155
Table 9.1: Environmental Management Plan during Construction and Operation phase of the Project
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
1. Groundwater
Quality
Ground water
contamination
Construction Phase
Wastewater
generated from Labor
tents.
1. Mobile type toilets
will be provided
No significant
impact as majority
of laborers would
be locally deployed.
Operation Phase
Wastewater
treatment, sludge
disposal on land.
Waste water will be
treated in onsite
Sewage Treatment
Plant. Sludge will be
used for horticultural
purpose as manure.
No significant
negative impact on
ground water
quality envisaged.
In an unlikely event
of soil and ground
water
contamination,
remediation
measures will be
implemented.
2. Groundwater
Quantity
Ground Water
Depletion
Construction Phase
Ground water will
not be used for
construction activity.
Not Applicable
Not Applicable
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 156
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Water will be
supplied by HUDA.
Recycling of treated
effluent from STP to
reduce freshwater
requirement
Storm water
collection for Water
Harvesting.
Awareness
Campaign for reduced
water use by occupants.
No significant
impact on ground
water quantity
envisaged.
4. Air Quality
Dust
Emissions
Construction Phase
All heavy
construction
activities.
Dust suppression
through water
sprinkling using water
trucks, handheld sprays
and automatic sprinkler
systems.
Vehicles
transporting loose
construction material
should be covered.
Contractors will be
advised to provide dust
masks for the employed
labor.
Not significant
because dust
generation will be
temporary and will
settle fast due to
dust suppression
techniques used.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 157
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Emissions of
PM, SO2, NO2
and CO
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Rapid on site
construction
Improved
maintenance of
equipment.
Not significant
Regular monitoring
of emissions and
control measures to
reduce the emission
levels.
Operation Phase
Power back-up
through D.G. Set
Emissions from
vehicular traffic.
Use of low Sulphur
diesel.
Stack will be
provided with adequate
height as per CPCB
guideline.
Green belt to be
provided with specified
species to help reduce
PM level.
Not significant as
D.G. Set would be
used for power
back-up only.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 158
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
5. Noise
Environment
Noise
emissions
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Equipment should be
fitted with silencers,
where applicable and
maintained well.
Providing noise
shields near heavy
construction
operations.
Construction activity
will be limited mostly
to daytime hours only.
Use of Personal
Protective Equipment
(PPE) like earmuffs
and earplugs during
construction activities.
Operation Phase
Noise from
vehicular movement.
Noise from D.G.
sets operation.
Peripheral
plantations.
Providing Acoustic
Enclosures on D.G.
Sets.
Not significant
Short-term
exposure within
permissible limit.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 159
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
6. Land
Environment
Soil
contamination
Construction Phase
Disposal of
construction debris.
Construction debris
will be collected and
suitably used on site as
per construction waste
management plan.
Impact will be
local, as any waste
generated will be
reused for
construction
activities. Not
significant.
Operation Phase
Dumping of
municipal solid waste
on land.
Dumping of
hazardous solid waste
on land.
Handling of used
oil from D.G. Sets.
Solid waste from site
will be collected on a
daily basis and
disposed as municipal
wastes. The
segregation,
transportation and
disposal of waste will
be handled by a local
approved vendor.
Used oil generated
will be managed
through authorized
recyclers.
Not Significant
Negligible impact
7. Biological
Environment
(Flora and
Removal of
Flora and
Fauna on site.
Construction Phase
Site development
during construction.
The site comprises
of fallow land.
No negative impact
--
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 160
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Fauna)
Increase of
Green Cover
Operation Phase
Plantation along
the periphery of the
project.
Plantation of species
that is native to the
area, fast growing and
with good canopy
cover.
Beneficial impact
8. Socio -Economic
Environment
Population
displacement
and economic
impact
Construction Phase
No relocation is
involved.
Constructional
activities
Employment
opportunities.
No negative impact
Beneficial impact
--
Operation Phase
Site operation.
Project will provide
employment
opportunities.
Boost to local
market for increased
demand in goods of
daily need.
Beneficial impact
--
9. Traffic Pattern Increase of
Vehicular
traffic
Construction Phase
Heavy vehicular
movement during
construction.
Heavy vehicular
movement will be
restricted to daytime
only and adequate
parking facility will be
provided.
No negative impact
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 161
S.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through
EMP & Design Impact Evaluation
Remedial
Measures
Operation Phase
Increased traffic
from the project.
Vehicular movement
will be regulated inside
the project site
Adequate parking
space provided within
the complex.
No significant
impact
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 162
CHAPTER 10: SUMMARY AND CONCLUSION
10.1 PROJECT BACKGROUND
Modification & Expansion of Group Housing Colony Project is spread over an area of 1,
37,685.79 m2 (34.022 acre). The estimated Built-up area (post revision/expansion) is 3, 61,332
m2. Total green area measures 37,816.538m
2 (30%).
As per EIA Notification, 2006 and amendments thereto, all building and construction projects
covering an area of 50 ha and/ or built up area greater than 1, 50,000 m2
are designated as 8(b)
and are required to obtain prior environmental clearance from respective State Environmental
Impact Assessment Authority (SEIAA).
The EIA is conducted to establish the baseline environmental setting in the study area,
assessment of potential impacts on different environmental components, design of mitigation
measures so as to keep impacts within acceptable limits and strengthen the positive impacts.
The summary highlights the baseline environmental status, key environmental issues and their
likely impacts and also lists the major recommended mitigation measures to attenuate the
impacts. It describes the findings of the EIA study to aid in decision making and provides project
related information and environmental impacts.
10.2 PROJECT SITE AND SALIENT FEATURES
The area has good infrastructure facilities. The nearest railway station is Gurgaon Railway
Station about 1.2 km (NE) away from the project site. The nearest airport is Indira Gandhi
International Airport, at 12 km (NE) from the project site.
Table 5.1: Salient Features of the Project
Feature Detail
Project name Modification & Expansion of Group Housing Colony project
Location Village Dhanwapur, sector-104, Distt. Gurugram, Haryana
Type of project 8 (b), Category B
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 163
Feature Detail
Plot area Plot Area = 1,37,685.79m2
Built-up area 3,61,332 m2
Ground coverage 13,591.98 m2
Parking facilities 3395 ECS
Power requirement
& source
15,255 KW from Dakshin Haryana Bijli Vitaran Nigam
(DHBVN)
Power backup 4 no. of D.G sets of total capacity 9684 kVA
(6x1500 + 2x 1010)
Water requirement
& source
Fresh water: 801KLD (from HUDA)
Waste water generated : 915 KLD
Total water requirement: 1343 KLD
Sewage treatment &
disposal Sewage treatment facility: 3 onsite STPs of 1100 KL each.
Solid wastes
generation
6537.288 kg/day
Estimated
population
14,910
Green-area 37,816.m2 (30% of plot area)
10.2.0 ENVIRONMENTAL SETTING OF THE STUDY AREA
The baseline environmental status was assessed based on primary and secondary data collected
either through in-site field observation or obtained from agencies such as Irrigation Department,
India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of
India, State Ground Water Department, State Pollution Control Board, Census of India and Local
Forest Department, Non -Governmental Agencies. The baseline status established from analysis
of secondary and primary data and predicted impacts and management plan are discussed below.
10.2.1 Land Environment
The site falls under residential land use as per the development plan by Gurgaon Master Plan,
2031.
The construction phase of a project may pose threat of soil contamination and soil erosion.
Inadequate solid waste management may also cause soil contamination during operation phase.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 164
During construction phase, excavation related work avoided during the monsoons and site
clearing is being carried out for specific areas being developed. Recyclable and non-recyclable
wastes are disposed through a local approved agency. Municipal Solid Waste Management is
proposed as per Municipal Solid Wastes (Management and Handling) Rules, 2016.
10.2.2 Water environment
The water requirement during construction phase will be met from STP treated water of HUDA.
A combination of efficient water management to reduce water consumption, reuse of treated
wastewater to reduce freshwater demand and rainwater harvesting to replenish groundwater is
proposed to have a positive bearing on the water environment of the region.
The wastewater will be treated in 3 onsite STPs of Total 1100 KLD capacity generating 823KLD
of treated effluent for reuse in flushing,& horticulture.
10.2.3 Air Environment
During construction phase, the major air pollutant is particulate matter as impacts of other
emissions such as SO2, NO2, and CO is not be significant.
Monitored average PM2.5, PM10 level not exceeded NAAQS at all the ten locations. The levels of
PM2.5, PM10, NO2, SO2 and CO at all the five locations were within the standards prescribed by
NAAQS at all the five locations. Thus dust emissions from construction activities will require
comprehensive mitigation measures and best construction practices.
Adequate stack heights have been proposed for D.G. sets i.e. 6 m above the rooftop to provide
sufficient dispersion of pollutants. Water sprinklers will be used to suppress dust during
construction.
During the operation phase, green belt is proposed to restrict and absorb air pollutants.
10.2.4 Noise Environment
Noise levels were observed at four locations within the study area. Levels of background noise
monitored in exceed the limit at 55 dB (A) and 45 dB (A) for daytime and night time
respectively.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 165
The noise emitted from heavy-duty construction equipment’s during construction period being
high will require occupational preventive measures and temporary noise barriers for noise
attenuation. The construction period being about three to four year duration, will require
significant mitigation measures such as restricted loud noise activities to daytime and provision
of PPEs In the operation phase, noise pollution will be checked through acoustic enclosures of
DG Sets and green belt plantation.
10.2.5 Biological environment
The landscape area will be developed with native species that will attract local birds and insects,
reduce pollution and improve aesthetics and micro-climate of the region.
Total green area measures 37,816.538m2 (30% of plot area) which include area under tree
plantation and lawn.
Evergreen tall and ornamental trees like Acacia auriculiformis, Acacia delbata, Aegle marmelos,
Adina cordifolia and ornamental shrubs like Bambusa arundinacia, Bambusa vulgaris have been
proposed to be planted inside the premises.
10.2.6 Socio-economic environment
The Modification & Expansion of Group Housing Colony Project does not call for change in the
existing land use pattern. The project will generate employment opportunities for both skilled
and unskilled workers which will have a multiplying positive effect on the life and economy of
the local population.
Thus from socio-economic point of view the project is beneficial to the people.
10.2.7 Energy efficiency
Please refer Environment Management Plan for details.
10.2.8 Other
Resource Conservation: A concerted effort is made towards resource conservation by way of
using recycled building materials, fly-ash bricks, reduced water consumption and improving
energy efficiency of the building.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 166
Indoor Air Quality: Special attention is being given to maintaining indoor air quality through
use of low VOC paints, provision of adequate ventilation, proper storage of chemical and
cleaning materials.
Safety: A network of manned security gates, security men, closed circuit TV and intercom
facilities are proposed to ensure safety of the occupant. The buildings will also be provided with
adequate fire tenders, fire alarms and water sprinklers as per norms.
10.3 ENVIRONMENTAL MANAGEMENT PLAN
Adequate environmental management measures will be incorporated during the entire planning,
construction and operating stages of the project to minimize any adverse environmental impact
and assure sustainable development of the area.
For the effective and consistent functioning of the campus, an Environmental Management
System (EMS) will be established at the site including an Environmental Management cell for
implementation of the EMP and monitoring plan, training and awareness, audits and
maintenance of records.
The total estimated cost of Modification & Expansion of Group Housing Colony is INR 592.83
Crore which includes the cost of land as well as development.
Based on the environmental assessment, the associated potential adverse environmental impacts
can be mitigated to an acceptable level by adequate implementation of the measures as stated in
the EIA and the EMP. Some of the environment friendly features of the project are:
Use of solar energy for street lighting
Provision of green walls and green terraces
Use of CLC blocks (containing approx. 33% fly ash)
Use of steel manufactured from recycled content.
Provide permeable paving to control surface water runoff
Rainwater harvesting
Meet all requirements for buildings in moderate earthquake prone areas.
Provision of fire alarms and water sprinklers.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT
At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 167
Provision of welfare schemes to workers.
Extending educational and healthcare facilities to the local people.
Commitment to engaging local population for job opportunities.
Hence, it may be concluded that the project will have significant positive socio-economic impact
on the local community apart from meeting the housing needs of the society, without bearing any
significant adverse environmental impact.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 168
CHAPTER-11
DISCLOSURE OF CONSULTANTS ENGAGED
Project Name: Modification & Expansion of Group Housing Colony Project
Name and address of
the Consultant
GRC India (P) Ltd.
F-374,375, Sector: 63,
Noida, India
ISO 9001:2008 Certified,
QCI-NABET Accredited.
Technical Members
Involved
Ms. Kavita Chopra (FAA)
Mr. Saurabh Gola (Member)
Base line data GRC India Training and
Analytical Laboratory
F- 375, Sector: 63,
Noida, India
Recognized by MoEF&CC, GoI &
Accredited by NABL.
A unit of GRC India (P) Ltd.
Under the guidance of following EIA Coordinator & Functional Area Experts:
EIA Coordinator Mr. Rajesh Bhaskaran
FAE- AP Dr. Dhiraj Kr. Singh
FAE- WP Dr. Dhiraj Kr. Singh
FAE- SHW Dr. Dhiraj Kr. Singh
FAE- SE Mr. B N Chaudhari
FAE - LU Mr. B N Chaudhari
FAE- EB Dr. Dhiraj Kr. Singh
FAE- AQ Ms. Mudita Tomar Singh
FAE- GEO Prof. Tapan Majumder/Shahbaz Malik
FAE- HG Prof. Tapan Majumder
FAE - NV Mr. Sanjay Singh
FAE- RH Dr. Ravindra Kode
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 169
11.1 ACCREDITION/ FROM QUALITY COUNCIL OF INDIA, QCI AND LIST OF
COORDINATORS
Grass Roots Research & Creation India (P) Ltd., Noida is an EIA Consultant organization
accredited by Quality Council of India, NABET. GRC India is accredited vide NABET
Certificate No. – NABET/EIA/1619/RA 0064 and validity of accreditation is till Dec., 12.
2019. Certificate of Accreditation is attached for reference.
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 170
As per the recently published QCI NABET ‘List of Accredited Consultant Organizations/Rev. 68, August 06, 2018, under LIST ‘A’, Category ‘A’ Sl. No. 80. The list of accredited consultants is published on QCI NABET and MoEF&CC website as well. For reference, a snapshot of the list where GRC India’s name is listed on QCI website is shown below:
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 171
CHAPTER-12
CORPORATE ENVIRONMENTAL RESPONSIBILITY
12.1 PROCEDURE FOR ENVIRONMENTAL COMPLIANCE
M/s. Juventus Estate Ltd., has a standard operating procedure to identify and bring into focus any
infringement/ deviation/ violation of the environmental/ forest norms and conditions to its
management. The applicable regulations are given in the Table 12.1 below:
Table 12.1 Applicable regulatory Framework
S. No. Environmental Acts & Rules Compliance
1 The Environment (Protection)
Act, 1986 and EIA Notification
dated 14.09.2006
Obtaining Environmental Clearance (EC)
from State Environment Impact
Assessment Authority (SEIAA), Haryana
for modification of the project.
Submission of Six-monthly Report of
Compliance of Stipulated EC Conditions
to Regional office of
MoEFCC/SEIAA/other authority as
mentioned in EC order- Twice a year: 1st
June and 1st December.
Submission of Environmental Statement
(ES) in Form-V to State Pollution Control
Board (SPCB) - Once in a year by 30th
September.
2 The Environment (Protection)
Rules, 1986 Monitoring of stack emission and
compliance to Emission Limits for DG
sets
Monitoring of STP effluent and
compliance to Standards for Discharge of
Effluents
Monitoring of air quality and compliance
to National Ambient Air Quality
Standards
Monitoring of DG noise level and
compliance to Noise limits for DG sets
3 The Water (Prevention &
Control of Pollution) Act, 1974,
and The Air (Prevention &
Control of Pollution) Act, 1981
Obtaining Consent to Establish (NOC)
from HSPCB before establishing the
project
Obtaining Consent to Operate (CTO)
from HSPCB and its periodic renewal.
4 Noise Pollution (Regulation Monitoring of ambient noise quality and
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 172
S. No. Environmental Acts & Rules Compliance
and Control) Rules, 2000 compliance to Ambient Noise Standards
5 Hazardous Wastes
(Management, Handling &
Transboundary Movement)
Rules, 2008 and its amendment
Obtaining Authorization for storage &
disposal of hazardous waste (in Form-1)
from SPCB and its periodic renewal
Submission of Annual Return for
hazardous waste (in Form-4) to HSPCB-
Once in a year by 30th
June
Disposal of hazardous waste to authorized
recycler (once in every three months)
Maintaining records of disposal and
transportation
6 Water (Prevention and Control
of Pollution) Cess Act, 1977
and Water (Prevention and
Control of Pollution) Cess
Rules, 1978
Submission Monthly Returns for Water
Cess (Form-1) to HSPCB for extraction
of groundwater- Once a month before 5th
of current calendar month
Payment of Cess- when claimed by SPCB
7 Municipal Solid Wastes
(Management and Handling)
Rules, 2016
Segregation of solid waste into
biodegradable and non-biodegradable and
storage into separate color bins.
Disposal of waste through authorized
local vendors.
12.2 Proposed Organizational Structure for Environmental Compliance
M/s. Juventus Estate Ltd has an an in-house team for ensuring compliance with the conditions
of Environmental Clearance letter. The proposed organization structure for Environmental
Compliance is shown in following chart at Figure 12.1:
Expansion & Modification of Group Housing Colony, EIA/EMP REPORT At Village –Dhanwapur, Sector-104, Gurugram, Haryana
M/s Juventus Estate Ltd 173
Figure 12.1: Proposed Organizational Structure for Environmental Compliance
MD
Executive Director Executive Director
Legal Advisor Project Manager
General Manager
IT Head
Customer Care Head
Finance Head