EDUCATION FIRST
FACILITIES
COMMITTEE
THE FACILITY COMMITTEE WAS CREATED IN NOVEMBER 2012 TO
COMPLETE A THOROUGH STUDY OF DISTRICT FACILITIES. MEMBERS OF THE COMMITTEE INCLUDE RESIDENTS FROM
ALL PARTS OF THE DISTRICT. TEACHERS, PARENTS, FARMERS,
RANCHERS, AND A WIDE VARIETY OF PROFESSIONS ARE REPRESENTED.
FACILITIES
COMMITTEE
FACILITY COMMITTEE COMMENTS – READING
Positive:Small classroom environments.Lobby/concession area.Building layout, creates good flow.Great gym environment.Stage performance is large with good
storage. Great lighting throughout facilityTwo computer labs
FACILITY COMMITTEE COMMENTS – READING
Issues:Office layout is isolated, creates safety and
supervision concern.Condition of older bathrooms.Aged locker rooms.Longevity of gym floor, can’t be sanded again
if damaged.Not one level throughout facility. Location in relation to rest of district.Older windows & doors not energy efficient.
FACILITY COMMITTEE COMMENTS – AMERICUS
Positive:Size of elementary classrooms.Advantage of 2 hallways – provides
separation for middle & elementary levels.Versatility of rooms – more modern feel.One level – easier access to rooms.Football field/softball diamond/nice
concessions/evening lightingClassrooms technologies.
FACILITY COMMITTEE COMMENTS - AMERICUS
Issues:Settling of building/Grading on
outside/Flooding.Mold in basement.Limestone on outside of building wearing down.Window AC units very loud disrupting teach
lectures.Office location hard for visitors to locateSecurity concerns – hard to monitor visitors
with current office locationSize of lunchroom
FACILITY COMMITTEE COMMENTS - AMERICUS
Issues:Infrastructure cannot always support new
classroom technologies.Poor restroom facilities.Lack of gym seating for sporting events &
accessing the seating.Lack of track facilities.Small locker rooms.Variance of temperature from room to room.Storage space throughout facility.
FACILITY COMMITTEE COMMENTS - AMERICUS
Other Comments:25 students maximum per middle school
classroom. Increased enrollment decreases functionality.
Increasing class sizes except in kindergarten (2012-2013)
One elementary class with enrollment of 27.Disparity in K-5 enrollment Americus/Reading
ARCHITECT REVIEW - AMERICUS
Metal roofs showing signs of deterioration.Roof in fair condition, reaching end of life
span.Exterior cracking result of building
movement.Metal panel siding showing signs of rust &
fastener failure.Majority of windows single pane or seals
have failed.Restrooms don’t meet ADA standards &
guidelines.Window AC units unable to control humidity.Limited IT & electrical infrastructure.
ARCHITECT REVIEW - AMERICUS
Life Safety Issues:Fire separation.Non-rated fire doors.Non-compliant corridor doors.Secure vestibule.Mold & mildew growth.Air quality.Exit plan/path from the basement.
FACILITY COMMITTEE COMMENTS - NHHS
Positive:Lower number of structural issues. Better
drainage.Majority of classrooms are adequately sized.Freshmen lockers located in separate
hallway.Nice gym/seating for sporting events.Large kitchen space. Visibility of office in entryway.Classrooms technologies. However,
infrastructure does not always support them.
FACILITY COMMITTEE COMMENTS - NHHS
Issues:Mobile units built to be temporary. West unit in
poor condition.Lack of electrical units due to building
infrastructure.Concern with age & adequate number of work
stations in science room.Window AC units very loud disrupting teach
lectures.Shop building houses woodworking and welding –
concern for fire.Lack of ventilation in shop, science & art rooms
FACILITY COMMITTEE COMMENTS - NHHS
Issues:Infrastructure cannot always support new
classroom technologies.Floor in shop class, concern about students
slipping.Location of secretary’s office – cannot monitor
those entering & exiting.Aged roof on shop – concern with water leaks
damaging equipment.Lack of designated dining area for various
school functions.
FACILITY COMMITTEE COMMENTS - NHHS
Issues:No commons area.Efficiency of windows throughout the building
(i.e. water and wind blowing in)Baseball and softball fields off campus in two
different locations. Difficult for spectators to attend both.
Significant costs for football and track facilities.Lack of adequate facilities for fine arts.Location long distance for students to
drive/travel.
FACILITY COMMITTEE COMMENTS - NHHS
Other Comments:Lower student population equals less course
opportunities.Vocational opportunities for students in
welding classes. Grants available for welding equipment, but no room for additional equipment in current building.
Do not anticipate growth in student population with current structure of facilities and lack of ability to provide expanded course opportunities.
ARCHITECT REVIEW - NHHS
Building movement evident from exterior cracking.
Majority of windows single pane un-insulated.Concrete façade is spalling. (Face layer is
falling off)Metal roof on wood shop is rusting.Temporary classrooms structures show
significant weathering.Window AC units don’t provide adequate air
quality.Limited IT and electrical infrastructure.Limited quality teaching space.
ARCHITECT REVIEW - NHHS
Exposed & unprotected gas lines in science rooms.
Restrooms don’t meet ADA standard & guidelines.
Inaccessible public restrooms in Gym, locker room facilities, stage & elevated seating. Football field access.
Life safety include fire separation, secure vestibule, non-compliant corridors & storage areas.
Exterior includes press box, pavement replacement & repair, current track & field requirements.
HERINGTON SCHOOL VISIT
K-12 enrollment – 480New addition PreK-5th grade for 240 current
students up to 300.$14.9 million with no changes to high school.
Demolished old grade school built in 1955. Building itself was good, but interior was not. Renovation would cost 60-70% of new costs.
Geothermal heating/cooling. All rooms have their own exchanger in enclosed 2nd story.
Separate entrance for parents and busses. Visitors’ entrance limited through office.
HERINGTON SCHOOL VISIT
Common kitchen area with two access and serving areas to separate cafeteria rooms – elementary and middle/high school. Concession by kitchen. Receiving area off kitchen for deliveries.
Have 3 gymsBuilding set up for wireless.Speaker systems in classroom for equal
sound.
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
HERINGTON SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
Middle School has 490 students/built to house 700.
Built on 80 acres with practice track. 110,000 sq. ft. cost $21.5 million did not include land acquisition, off-site development, furnishings or design fees.
All electric with gas service only in kitchen.All classrooms have wireless Internet service.
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
BASEHOR-LINWOOD SCHOOL VISIT
Frequently Asked Questions
Why hasn’t the school district kept up with maintenance of buildings through the years?
• Each mill levied in USD #251 raises a minimal amount of funds. Capital Outlay Funding has been about $150,000 annually. To replace the roof at NHHS would be $750,000 or 5 years of capital outlay levies.
Frequently Asked Questions
If we remodel the current buildings, how long will it take and how will school continue to be held?
• HTK estimates that a remodeling project will take about 2 years. It would be a challenge to keep school in session during this time frame. One of the options would be to conduct school in an alternate location. No alternate locations have been identified.
Frequently Asked Questions
If we remodel, are there any requirements in conjunction with the American Disabilities Act (ADA)?
• Yes. For every $1 spent on remodeling, $.20 must be spent on ADA issues until the building and location are ADA accessible.
Frequently Asked Questions
If a new building is built, has a new location been identified?
• No definite location has been identified. However, HTK has identified several needs for a building site. Adequate water pressure and three-phase electrical service are a must. Natural gas availability would help keep utility costs down.
Frequently Asked Questions
What would happen to the existing buildings if a new K-12 was constructed?
• The committee has not addressed this question at this time. As with everything else, the final decision would be made by the Board of Education.
Frequently Asked Questions
Is there information available about the number of USD #251 students attending school in other school districts?
• Yes, information is available for the 2012-2013 school year. 120 North Lyon County students attended school outside the district. The breakdown of where these students attended school is:
Emporia – 67 students (56%)Osage City – 20 students (17%)Mission Valley – 15 students (12%)All others – 18 students (15%)
OPTIONS PROS REMODEL PRO:-Keep elementary schools in Reading & Americus-Less building costs NEW K-12 PRO:-All students in one location. Families no longer have students in Reading, Americus & NHHS.-Better able to manage elementary class sizes so teachers & students will have more comparable teaching & learning experience.-Able to manage jr. high & high school courses better to have more courses available for these two levels.-Consolidation savings could be used for introducing new programs/classes.
NHHS Americus Total Total Total
Estimated Total ProjectBuilding $18,000,000 $4,000,000 $22,000,000 $25,000,000
Outdoor Facilities 2,000,000 0 $2,000,000 5,000,000
Total Estimated Total Project 24,000,000$ 30,000,000$
Estimated Annual Savings Salaries & Benefits $0 518,400
Transportation $0 172,000
Bus Replacement $0 33,000
Bus Expenses $0 45,000
Utilities $16,000 51,000
Maintenance & Repair $100,000 100,000
Total Estimated Annual Savings $116,000 919,400$
Remodel Existing Buildings Construct New Building
USD #251Remodel vs Rebuild Analysis
History & Projection of USD #251 Mill Levy for Remodeling
2011-12 2012-13 2013-142014-15 (est) or 1st year const.
2015-16 (est) or 2nd year const.
2017-18 (est) or 1-2 yrs. in bldg.
State Mill Levy 20.000 20.000 20.000 20.000 20.000 20.000Supplemental (LOB) 26.230 24.290 12.696 11.050 11.050 11.050Capital Outlay 6.510 6.995 7.000 6.100 6.100 6.100Total School Mill Levy 52.740 51.285 39.696 37.150 37.150 37.15024 Million for 25 years in Mills 21.600 21.600 21.600Possible Mill Reduction from Annual Savings* (1.630)Total and Possible Total School Mill Levy 52.740 51.285 39.696 58.750 58.750 57.120Change in Mill Levy from 2011-2012 (1.455) (13.044) 6.010 6.010 4.380Other Pertinent Local Mill Levy Change:County mill reduction (approx) (7.300) (7.300) (7.300) (7.300)Possible Mill Levy Change from 2011-2012 (20.344) (1.290) (1.290) (2.920)
Valuation (Non Gen) $29,508,262.00 $32,077,706.00 $61,846,224.00 $71,000,000 (est) $71,000,000 (est) $71,000,000 (est)1 Mill generates (approx) $29,500.00 32,000.00 61,800.00 71000.00 71000.00 71000.00
Change in annual taxes from 2011-12 for School Levy Only for Remodeling$50,000 home 34.56 34.56 25.19$100,000 home 69.12 69.12 50.37$50,000 commercial property 75.13 75.13 54.75$100,000 commercial property 150.25 150.25 109.50Dry Crop land (160 acres) 55.10 55.10 40.16Grass Land (160 acres) 17.89 17.89 13.03
*The 1.63 mill reduction is a result of possible reduction in utilities and maintenance of buildings. No reduction has been made to capital outlay. Capital outlay is currently used to purchase school buses and building maintenance. There would be no changes in bus routes with this option. If there were remaining funds after bus purchases, then capital outlay funds could be accumulated for future maintenance needs. This cost projection allows for no other changes to programs, etc.
History & Projection of USD #251 Mill Levy for New Construction
2011-12 2012-13 2013-142014-15 (est) or 1st year const.
2015-16 (est) or 2nd year const.
2017-18 (est) or 1-2 yrs in bldg
State Mill Levy 20.000 20.000 20.000 20.000 20.000 20.000Supplemental (LOB) 26.230 24.290 12.696 11.050 11.050 11.050Capital Outlay 6.510 6.995 7.000 6.100 6.100 4.100Total School Mill Levy 52.740 51.285 39.696 37.150 37.150 35.15030 Million - 25 years = Mills 27.000 27.000 27.000Possible Mill Reduction from Annual Savings* (7.000)Total and Possible Total School Mill Levy 52.740 51.285 39.696 64.150 64.150 55.150Change in Mill Levy from 2011-2012 (1.455) (13.044) 11.410 11.410 2.410Other Pertinent Local Mill Levy Change:County mill reduction (approx) (7.300) (7.300) (7.300) (7.300)Total Possible Mill Levy Change from 2011-2012 (20.344) 4.110 4.110 (4.890)
Valuation (Non Gen) $29,508,262.00 $32,077,706.00 $61,846,224.00 $71,000,000 (est) $71,000,000 (est) $71,000,000 (est)1 Mill generates (approx) $29,500.00 32,000.00 61,800.00 71000.00 71000.00 71000.00
Change in annual taxes from 2011-12 for School Levy Only for New Construction$50,000 home 65.61 65.61 13.86$100,000 home 131.22 131.22 27.72$50,000 commercial property 142.63 142.63 30.13$100,000 commercial property 285.25 285.25 60.25Dry Crop land (160 acres) 104.61 104.61 22.09Grass Land (160 acres) 33.96 33.96 7.17
* The possible annual savings of $919,400 converts to 12.949 mills ($71,000 per mill). The school board would have three options for this savings: 1) Early payoff of the bonds used to build the new building; 2) Lower capital outlay levy and/or the LOB levy; and 3) Use the extra funds to add new programs, increase salaries, put aside for future maintenance, etc. This illustration has designated a reduction of 7 mills. Also, the capital outlay levy has been reduced 2 mills to 4.1 mills (fewer buses needed). In this scenario the possible remaining 3.949 mills (app. $280,000 annually) could be used to reduce debt, new programs, or reduce the mill levy further.
THANK YOU
FACILITIES COMMITTEE