Spacesaver® OP-0708 Rev. 10/07
INSTALLATION INSTRUCTIONS
CAUTION
Spacesaver Recommends:1. That Safety Glasses be worn during any cut-
ting and drilling operations and grinding.2. That safety gear such as Hard Hats, Safety
Shoes, etc. be worn when required.
SECTION IGeneral Information
SECTION IILocker Configurations
SECTION IIILocker Installation
SECTION IVPass thru
ED3 EVIDENCELOCKERSby Spacesaver®
920-563-6362E-mail: [email protected]: www.spacesaver.com
Spacesaver® OP-0708 Rev. 10/07 Page 2
CONTENTS
PAGE # SECTION I - GENERAL INFORMATION + TOOL REQ.3-4
SECTION II - DOOR CONFIGURATIONS5
SECTION III - ED3 LOCKER INSTALLATION6-8
SECTION IV - PASS-THRU9-14
Spacesaver® OP-0708 Rev. 10/07 Page 3
HARDWARE AND TOOL INFORMATION
Spacesaver Supplied Hardware, quality per locker:
QTY Type Use
(4) Appliance Leveling Screw Floor leveling bolts(Hex head)
(4) 5/16-18 x 1” Bolt Bolt lockers together(4) 5/16-18 Nut Bolt lockers together(8) 5/16 Washers Bolt lockers together
(12) #8 x 1/2” Self Tapping Screws Fastening for Trim Panels (if required)(4) 3/8 x 3” Sleeve Anchors Bolt locker to floor(1) Bag of “U” Shims Support under locker for sleeve anchors(1) Touch-up Paint Fix minor scratches from installation(1) Bag of 1/8” Rivets For trim pieces (if required)
Installation Tools Required
DollyBox Cutter-Utility Knife1/2” Wrench9/16” Wrench#2 Phillips ScrewdriverStandard Hammer3/8” dia PunchHammer drill3/8” concrete drill bitLaser LevelDrill with 1/8” drill bitRivet GunHex Drive for Levelers
Pass-thru
Spacesaver® OP-0708 Rev. 10/07 Page 4
General Information
Verify that the full quantity of DSM-Spacesaver boxes have beenreceived prior to opening boxes or beginning work. Check with youoffice for details.
Each locker box contains all of the required hardware for a standardinstallation of that locker.
The final perimeter wall trim set and hardware (if required) is shippedinside one locker box and is clearly identified on the outside of thebox. (Pass-thru)
Unless otherwise specified, the front trim set is designed for installa-tion when the locker bank front face is installed flush with the wallsurface. (Pass-thru)
The keys for the lockers may be shipped separately depending uponthe customer’s request.
Please contact Spacesaver’s Field Service Department for any ques-tions regarding the installation procedure. 1-800-457-8463
Spacesaver® OP-0708 Rev. 10/07 Page 5
SECTION II LOCKER CONFIGURATIONS
Spacesaver® OP-0708 Rev. 10/07 Page 6
Step 1
The leveling point holes and the anchorholes are located at the bottom of eachlocker under the floor pans. Use aPhillips screwdriver to remove the (2)screws per floor. Retain all hardware forre-use.
Note: Prior to leveling and anchoringlockers, it is necessary to install trimmounting plates and trim retainer strips(Pass-Thru Lockers). See section IV Pg. 9
Step 2
Take note that there is a notch in thefloor so it will pass by the bottom rivet.Floors must be removed from the front.
Step 3
Remove the floor panel from the front ofthe system. Lift up the front and careful-ly pull the panel upward. When it haspassed all Rivet locations, the floorpanel can be tilted and removed.
SECTION III ED3 LOCKER INSTALLATION
Front Door
Rivet Notch
Spacesaver® OP-0708 Rev. 10/07 Page 7
Step 4
Use a 9/16 wrench to remove the nutand washer. Remove the bolt securingthe locker to the skid.
Step 5
Carefully remove the locker from theskid. Install (4) appliance levelingscrews into the leveling locations, fromthe bottom of the base up. Make sure tothread the levelers till they are flush withhe bottom of the unit. Determine thehigh point in the floor using a laserlevel. Use this location as the startingpoint; slide each locker into place andbegin leveling. Adjust levelers with ahex head drive bit. Make final adjust-ments to bolts to ensure the locker islevel. Repeat this process on everylocker.
Step 6
Using the locker as a template, drill (4)3/8” dia anchor holes into the floor toaccept sleeve anchors for each locker.Remove lockers to vacuum and cleanfloor and wall openings (when applica-ble) to provide a clear clean surface toproperly level and install the lockers.
Note: Lockers come with holes for join-ing together. Take note of this when plac-ing lockers.
Leveler location
Spacesaver® OP-0708 Rev. 10/07 Page 8
Step 7
Prior to anchoring, make sure lockersare level and plumb. Pound (4) 3/8” x 3”sleeve anchors into the anchoring holesand each locker base.
Bolt lockers together by lining up theholes and using 5/16”-18x1” (u)nc bolts,nuts, and washers. Do not tighten till alllockers are leveled and anchored
Note: If this is a pass-thru system, skipto step 10-14 and install trim mountingplates and trim retainer strips prior toanchoring.
Step 8
Stack shims between floor and lockeraround the anchor. Bolt the lockers tothe floor using the sleeve anchors.Tighten with a 9/16” wrench.
Note: Ensure every locker corner is sup-ported and anchor locations shimmedprior to tightening anchors. If a corner isanchored to the floor without the propersupport, there is the risk that the cornerwill be drawn down to the floor twistingthe locker. This may cause the doors andthe lock mechanism to mis-align andcause problems with locker operation.
Step 9
Tighten all hardware connecting unitswith a 1/2” wrench. Reinstall the floorpans with the original (2) screws (perpanel) that were removed in step 1.Clean lockers; removing all metal filings,excess screws, and leftover materials.Use touch up spray paint to repair anyscratches.
Spacesaver® OP-0708 Rev. 10/07 Page 9
SECTION IV PASS THRU INSTALLATION
Step 10
Install trim mounting plates to the bot-tom outside face of each locker.
SS part #340674.001P
Trim Mounting Plate
Spacesaver® OP-0708 Rev. 10/07 Page 10
Step 11
Secure to the front side of the baseusing (2) 1/8” rivets in the predrilledholes. make sure the rivet goes thruboth the trim mounting plate, and thelocker base.
Step 12
Locate the side retainer strips. Therewill be 6 holddown retainer strips perbank of lockers; 3 strips on each side.
SS Part #401740.001
Step 13
Line the side retainer strips up flushwith the front edge of the locker. Theholes for this should be pre drilled. Inthe event that these are not drilled, usethe holes on the retainer strip as aguide and drill 2 holes per strip. Securethe retainer strip using (2) 1/8” rivets.
.
Retainer Strips
Spacesaver® OP-0708 Rev. 10/07 Page 11
Step 14
Secure top retainer strips by lining themup with the pre-drilled holes at the topof the locker. Use 1/8” rivets for secur-ing it.
Step 15
Install the side trim into the retainerstrips. Begin by taping the side trim intothe retainer strips around the perimeterof the locker bank.
Note: Pictured from behind to show howtrim sits in the retainer strip.
Step 16
Secure each side trim by riveting thruthe holes in the trim and the bottom trimmounting plate (kick plate area) thatwas installed in step #1.
Front Trim
Kick plate Area
Rivet Here
Spacesaver® OP-0708 Rev. 10/07 Page 12
Step 17
Take note of the difference in the endsof the 2 top trim pieces. the front trimpiece has a tab on it.
Note: To aid in appearance, the topretainer strips come as 1 vertical kit. Themaximum length is 72”. Other lengthsinclude 24” and 32”. You may receivemore than one top trim piece if severallockers will be ganged together.
Step 18
The tab on the front top trim piece fits inthe slot on the front side piece.
Top Front
Top Rear
Spacesaver® OP-0708 Rev. 10/07 Page 13
Step 19
The top trim piece will fit behind theside piece.
Step 20
Make sure these are locked togetherproperly before tapping them fully intothe retainer strips.
Step 21
Use holes in the door frame to securethe top trim in place with #8 x 1/2” selftapping screw thru the trim.
Spacesaver® OP-0708 Rev. 10/07 Page 14
Step 22
Rear trim pieces do not have the lock-ing tabs, and do not fit in retainer strips.These are riveted to the top and sidesof the locker.
Step 23
After Locker has been installed, pushthe rear side trim piece tight up to thewall. All holes will need to be drilled withan 1/8” drill bit so the trim piece can besecured to the locker. Use 1/8” rivets tosecure the rear side trim. Repeatprocess on other side.
Step 24
Line up the top trim piece with the sidepieces. Use a drill with an 1/8” drill bit toso the top piece can be secured. Use1/8” rivets to secure the top rear trimpiece.
Clean lockers; removing all metal filings,excess screws, and leftover materials.Use touch up spray paint to repair anyscratches.