1
Economic Impact of Partial String Failure in Multistring Energy Storage Systems Vanshika Fotedar, Sarmad Hanif, Jan Alam File Name // File Date // PNNL-SA-##### PROJECT OVERVIEW Pacific Northwest National Laboratory (PNNL) has been engaged with exhaustive energy storage system and performance testing for the past decade. With development of battery storage technology, the state of health and mechanics are being scrutinized in detail. Electric utilities, and large industrial/commercial electricity customers are integrating multi-MW scale energy storage systems (ESS) for various reasons including improvement of system reliability and renewable energy integration. These large scale ESSs are typically implemented using multiple strings where failure of one or more strings is not unusual. Large battery systems, which have multiple strings operational at the same time, present a unique technical challenge when it comes to tracking the system’s state of health and mechanics as a whole (Crawford et al. 2020). Each individual string varies in terms of its performance and can fail occasionally impacting the system performance and capacity. Shutting down an ESS entirely because it has had a partial string failure would lead to economic losses. In order to evaluate the accurate costs and benefits associated with a particular battery system, it is essential to incorporate the costs associated with battery string failure and, as a result, reduced capacity. TECHNO-ECONOMIC IMPACT OF PARTIAL STRING FAILURE ILLUSTRATIVE ESS CASE RESULTS AFTER PLANNING/ADJUSTMENT Consider a 3-string 0.75 MW/1.5MWh ESS– string 1 has a rating of 0.3 MW/0.6 MWh and string 2 and 3 are rated at 0.225MW/0.45MWh. Now, let’s assume that the forward reserve payment rate is cleared at $25/MW and the real-time reserve payment rate is cleared at $30/MW. Here, Failure-to-reserve penalty = 0.3 MW x $37.5/MW= $11.25 If two of the strings failed, one with the capacity rating of 0.3 MW/0.6 MWh and another with 0.225MW/0.45MWh rating, Failure-to-reserve penalty = 0.525 MW x $37.5/MW= $19.7 This indicates that the penalty linearly increases with the fall in battery capacity. If we know the probability of a battery string failing in a given period of time, we can calculate the expected penalty for a battery system over a defined period of time. The first order technical impact of partial string failure in an ESS is partial loss of battery capacity. If the ESS had service obligations to fulfil with it’s entire capacity, it can only partially address these obligations now. On the economics side, the impact can vary widely depending on the system, type of service being provided, market rules, penalties, and so on. Thus, the economic benefits may be evaluated on a case by case basis. In this work, we evaluate economic losses for an illustrative battery system, providing frequency regulation in ISO-NE market, due to partial string failure. If the battery system bids into the market despite the partial string failure, the real-time battery control duty cycles will need to be updated. This poster looks at how the economic losses are accrued and how the real-time adjustment in battery control duty cycles can reduce the economic impacts due to partial string failure. REVENUE LOSS: FREQUENCY REGULATION In order to calculate the loss of revenue from providing regulation reserve due to partial capacity loss, the cost and benefits associated with an ESS with no string failure could be compared with the costs and benefits associated with an ESS which has undergone string failure. The real time failure to reserve is when the battery’s real time delivered megawatts are less than the real time megawatt obligation. In this situation, the penalty paid by the resource is determined by the Forward Reserve Failure-to-Reserve Penalty Rate and the market participant’s (in this case, the ESS facility) Forward Reserve Failure-to-Reserve Megawatts. The following figure lays down the overall net forward reserve calculation under failure to deliver the contracted energy due to loss of capacity. Vanshika Fotedar Pacific Northwest National Laboratory 620 SW 12 th Ave 8 th Floor, Portland, OR 97205 (971) 940-7106 [email protected] This work is supported by Dr. Imre Gyuk, U.S. Department of Energy (DOE) Office of Electricity under contract No. 57558. PNNL is operated by Battelle Memorial Institute for the DOE under contract DE-AC05-76RL01830. PROJECT OBJECTIVES 1. Develop control strategies to maximize financial benefits with string failure 2. Evaluate the financial losses of partial ESS string failure and its impact on the final benefits 3. Understand market rules and repercussions of reduced battery performance 4. Validate system model results 5. Challenge in managing multiple use services within a single optimization engine EXPECTED LOSSES For a battery with three strings, i, j, and k, for which we know the probability distribution associated with each string failing, expected failure-to-reserve penalty can be evaluated using: − − = 6 × 6 + : × : + ; × ; + 6,: × 6,: + :,; × :,; + ;,: × ;,: + 6,:,; × 6,:,; Where Pi = Probability of failure of string i, Pi,j= Probability of failure of string i and j together Pi,j,k= Probability of failure of string i, j, and k together Similarly, Fi= failure-to-reserve penalty when string i fails Fi,j= failure-to-reserve penalty when string i and j fail Fi,j,k= failure-to-reserve penalty when string i,j, and k all fail together For the case described above, given probability distribution of string failure, the expected failure to reserve penalty for a single reserve event is calculated in the accompanying table. Failed string Reduction in Battery Capacity (MW) Probability of failure Failure-to-reserve penalty ($) using (a) 1 0.3 0.3 11.3 2 0.225 0.25 8.438 3 0.225 0.20 8.438 1,2 0.525 0.15 19.688 2,3 0.450 0.10 16.875 1,3 0.525 0.10 19.688 1,2,3 0.750 0.5 28.125 Expected Failure-to- Reserve Penalty 35.453 Assuming the ESS in this example placed half of its rated power (0.375 MW), on average, for providing reserves to the market, where the average settled reserve price was 10 $/MW, the annual earnings would amount to 10 * 24 * 0.365 * 365 = 32,850 $, where due to partial string failure the net revenue = 32,850-12,592 = 20,258, which is 38% less than the estimated revenue. ACKNOWLEDGEMENT Scenarios Planning/Real-Time Adjustment Capacity Payment ($) Mismatch Penalty ($) Revenue ($) S1 No/No 324 297 27 S2 No/Yes 320 105 215 S3 Yes/No 287 215 72 S4 Yes/Yes 297 57 240 Different ESS performance scenarios were tested to see the impact of planned duty cycle and real- time adjustment on the economic losses. In the associated table, Scenario S1 represents a case where the duty cycle is planned without considering string failure and no real time adjustments are made. The mismatch penalty ($) gives the penalty owing to mismatch between power requested and power provided. The other scenarios represent different combinations of considering planning and real time adjustment. The results in the table highlight the fact that considering potential string failures in the planning stage and performing real time adjustment enhanced revenue from regulation service. With both planning and real time adjustment, the revenue is enhanced by the highest amount ($27 to $240) as one would expect. CHALLENGES AND NEXT STEPS 1. Stakeholders from the industry will need to consider the planning and real-time adjustment upgrades in order to extract the highest economic benefits. 2. Most ESS use off-the-shelf control systems to determine duty cycles. It may not be easy to integrate duty cycle adjustment strategies with these control systems 3. Additional costs may be incurred owing to string failure and battery maintenance

Economic Impact of Partial String Failure in Multistring ......Economic Impact of Partial String Failure in Multistring Energy Storage Systems Vanshika Fotedar, Sarmad Hanif, Jan Alam

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Economic Impact of Partial String Failure in Multistring Energy Storage Systems Vanshika Fotedar, Sarmad Hanif, Jan Alam

    File

    Nam

    e //

    File

    Dat

    e //

    PN

    NL-

    SA-#

    ####

    PROJECT OVERVIEWPacific Northwest National Laboratory (PNNL) has been engaged with exhaustive energystorage system and performance testing for the past decade. With development of batterystorage technology, the state of health and mechanics are being scrutinized in detail. Electricutilities, and large industrial/commercial electricity customers are integrating multi-MW scaleenergy storage systems (ESS) for various reasons including improvement of systemreliability and renewable energy integration. These large scale ESSs are typicallyimplemented using multiple strings where failure of one or more strings is not unusual. Largebattery systems, which have multiple strings operational at the same time, present a uniquetechnical challenge when it comes to tracking the system’s state of health and mechanics asa whole (Crawford et al. 2020). Each individual string varies in terms of its performance andcan fail occasionally impacting the system performance and capacity. Shutting down an ESSentirely because it has had a partial string failure would lead to economic losses. In order toevaluate the accurate costs and benefits associated with a particular battery system, it isessential to incorporate the costs associated with battery string failure and, as a result,reduced capacity.

    TECHNO-ECONOMIC IMPACT OF PARTIAL STRING FAILURE

    ILLUSTRATIVE ESS CASE

    RESULTS AFTER PLANNING/ADJUSTMENT

    Consider a 3-string 0.75 MW/1.5MWh ESS– string 1 has a rating of 0.3 MW/0.6 MWh and string2 and 3 are rated at 0.225MW/0.45MWh. Now, let’s assume that the forward reserve paymentrate is cleared at $25/MW and the real-time reserve payment rate is cleared at $30/MW. Here,Failure-to-reserve penalty = 0.3 MW x $37.5/MW= $11.25If two of the strings failed, one with the capacity rating of 0.3 MW/0.6 MWh and another with0.225MW/0.45MWh rating,Failure-to-reserve penalty = 0.525 MW x $37.5/MW= $19.7This indicates that the penalty linearly increases with the fall in battery capacity.If we know the probability of a battery string failing in a given period of time, we can calculatethe expected penalty for a battery system over a defined period of time.

    The first order technical impact of partial string failure in an ESS is partial loss of batterycapacity. If the ESS had service obligations to fulfil with it’s entire capacity, it can only partiallyaddress these obligations now. On the economics side, the impact can vary widely dependingon the system, type of service being provided, market rules, penalties, and so on. Thus, theeconomic benefits may be evaluated on a case by case basis. In this work, we evaluateeconomic losses for an illustrative battery system, providing frequency regulation in ISO-NEmarket, due to partial string failure.

    If the battery system bids into the market despite the partial string failure, the real-timebattery control duty cycles will need to be updated. This poster looks at how the economiclosses are accrued and how the real-time adjustment in battery control duty cycles canreduce the economic impacts due to partial string failure.

    REVENUE LOSS: FREQUENCY REGULATIONIn order to calculate the loss of revenue from providing regulation reserve due to partial capacityloss, the cost and benefits associated with an ESS with no string failure could be compared withthe costs and benefits associated with an ESS which has undergone string failure. The real timefailure to reserve is when the battery’s real time delivered megawatts are less than the real timemegawatt obligation. In this situation, the penalty paid by the resource is determined by theForward Reserve Failure-to-Reserve Penalty Rate and the market participant’s (in this case, theESS facility) Forward Reserve Failure-to-Reserve Megawatts. The following figure lays down theoverall net forward reserve calculation under failure to deliver the contracted energy due to lossof capacity.

    Vanshika Fotedar Pacific Northwest National Laboratory620 SW 12th Ave8th Floor,Portland, OR 97205(971) 940-7106 [email protected]

    This work is supported by Dr. Imre Gyuk, U.S. Department of Energy (DOE) Office of Electricityunder contract No. 57558. PNNL is operated by Battelle Memorial Institute for the DOE undercontract DE-AC05-76RL01830.

    PROJECT OBJECTIVES 1. Develop control strategies to maximize financial

    benefits with string failure2. Evaluate the financial losses of partial ESS string

    failure and its impact on the final benefits3. Understand market rules and repercussions of

    reduced battery performance4. Validate system model results5. Challenge in managing multiple use services

    within a single optimization engine

    EXPECTED LOSSESFor a battery with three strings, i, j, and k, for which we know the probability distributionassociated with each string failing, expected failure-to-reserve penalty can be evaluated using:

    𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑓𝑎𝑖𝑙𝑢𝑟𝑒 − 𝑡𝑜 − 𝑟𝑒𝑠𝑒𝑟𝑣𝑒 𝑝𝑒𝑛𝑎𝑙𝑡𝑦= 𝑃6× 𝐹6 + 𝑃:× 𝐹: + 𝑃;× 𝐹; + 𝑃6,:× 𝐹6,: + 𝑃:,;× 𝐹:,; + 𝑃;,:× 𝐹;,: + 𝑃6,:,;× 𝐹6,:,;

    Where Pi = Probability of failure of string i, Pi,j= Probability of failure of string i and j together Pi,j,k= Probability of failure of string i, j, and k togetherSimilarly, Fi= failure-to-reserve penalty when string i failsFi,j= failure-to-reserve penalty when string i and j failFi,j,k= failure-to-reserve penalty when string i,j, and k all fail together

    For the case described above, given probability distribution of string failure, the expected failureto reserve penalty for a single reserve event is calculated in the accompanying table.

    Failed string Reduction in Battery Capacity (MW)

    Probability of failure Failure-to-reserve penalty ($) using (a)

    1 0.3 0.3 11.3

    2 0.225 0.25 8.438

    3 0.225 0.20 8.438

    1,2 0.525 0.15 19.688

    2,3 0.450 0.10 16.875

    1,3 0.525 0.10 19.688

    1,2,3 0.750 0.5 28.125Expected Failure-to-

    Reserve Penalty35.453

    Assuming the ESS in this example placed half of its rated power (0.375 MW), on average, for providing reserves to the market, where the average settled reserve price was 10 $/MW, the annual earnings would amount to 10 * 24 * 0.365 * 365 = 32,850 $, where due to partial string failure the net revenue = 32,850-12,592 = 20,258, which is 38% less than the estimated revenue.

    ACKNOWLEDGEMENT

    Scenarios Planning/Real-Time Adjustment

    Capacity Payment ($)

    Mismatch Penalty ($)

    Revenue ($)

    S1 No/No 324 297 27S2 No/Yes 320 105 215S3 Yes/No 287 215 72S4 Yes/Yes 297 57 240

    Different ESS performance scenarios were tested to see the impact of planned duty cycle and real-time adjustment on the economic losses. In the associated table, Scenario S1 represents a case where the duty cycle is planned without considering string failure and no real time adjustmentsare made. The mismatch penalty ($) gives the penalty owing to mismatch between powerrequested and power provided. The other scenarios represent different combinations ofconsidering planning and real time adjustment. The results in the table highlight the fact thatconsidering potential string failures in the planning stage and performing real time adjustmentenhanced revenue from regulation service. With both planning and real time adjustment, therevenue is enhanced by the highest amount ($27 to $240) as one would expect.

    CHALLENGES AND NEXT STEPS1. Stakeholders from the industry will need to

    consider the planning and real-time adjustment upgrades in order to extract the highest economic benefits.

    2. Most ESS use off-the-shelf control systems to determine duty cycles. It may not be easy to integrate duty cycle adjustment strategies with these control systems

    3. Additional costs may be incurred owing to string failure and battery maintenance