Project Coordination ActivitiesProject Coordination Activities

Meeting with Cape Cod National Meeting with Cape Cod National Seashore –Seashore – August 27 August 27

Cape Cod Commission Cape Cod Commission USDA Meeting – September 16USDA Meeting – September 16

Page 3: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Nauset Regional High School

Drill Site

Page 4: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Drill Site at NRHS

Page 5: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Mud System

Page 6: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Drill Cuttings - Aquifer Zone

Page 7: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Well Screen

Page 8: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Well Development

Page 9: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Nauset High SchoolHydrogeologic Conditions

Deep boring installed to 400’

Water table at 50’

Good material to 105’Silts and clays below

Installed well at 90’

Page 10: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District H District H

Page 11: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District HDistrict HHydrogeologic Conditions Summary Hydrogeologic Conditions Summary

Deep boring: 405’ bgsDeep boring: 405’ bgs DTW – 30’ bgsDTW – 30’ bgs Potentially productive zones:Potentially productive zones:

Shallow 106-116’ bgsShallow 106-116’ bgsIntermediate 207-217’ bgsIntermediate 207-217’ bgs

Freshwater/Saltwater Interface 343 feetFreshwater/Saltwater Interface 343 feet

Page 12: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District HWell Installations

Deep well: 346’Deep well: 346’

Intermediate well: 207’ Intermediate well: 207’

Shallow well: 116’Shallow well: 116’

Page 13: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District H

Well Development

Page 14: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District H

Well Development

Page 15: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District H Drill Log

Potentially productive aquifer zone (sand) 80-218’

Fresh Water/Salt water interface: 143’ bgs

Specific Capacity Shallow: 33 gpm/ft Intermediate: 5-10+ gpm/ft

Water quality: Shallow – excellentIntermediate – Waiting on data

Silt and Clay

Sand

Fresh WaterSalt Water

Page 16: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District HDistrict HHydrogeologic IssuesHydrogeologic Issues

Response of salt water transition zone Response of salt water transition zone with pumpingwith pumping

Proximity of vernal poolsProximity of vernal pools Groundwater/vernal pool interactionGroundwater/vernal pool interaction

Page 17: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District H Deep Test Well

19.00

19.25

19.50

19.75

8/27/09 8/28/09 8/29/09 8/30/09 8/31/09 9/1/09 9/2/09 9/3/09 9/4/09 9/5/09

Tidal influences on water level in deep test well

Page 18: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Vernal Pools

Single Family Residential> 80,000 sq. ft.

General Business

General Industrial

Single Family Residential 40,000-79,999 sq. ft.

Conservation/Passive Recreation

Page 19: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

District GDrill Site

•Drill site and 400’ buffer entirely within Town-owned land

• Currently installing deep boring

• Site has available land for more than one test site

Page 20: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Eastham Water Supply Investigations

Updated Schedule

8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29

Phase I Tasks

Task 1. Project and Regulatory Coordination

Task 2. Orleans Water Source Feasibility Study

Task 3. Site Survey

Task 4. Initial Site Investigations

Nauset Regional High School

District H

District G

Task 5. Groundwater Modeling

Task 6. Request for Site Exam

Nauset Regional High School

District H

District G

Task 7. Request Approval to Conduct Pump Test

NovemberOctober FebruaryDecember2009 2010

Project Task June JanuaryJuly August MarchSeptember

Page 21: Eastham Water System Water Supply Investigations Status Update Board of Selectmen September 21, 2009

Discussion