EAST MIDLANDS COUNCILSAN INTRODUCTION TO VIABILITY
October 2017
2CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Speakers: Donna Pickersgill BSc Hons, MSc, MRICSCBREAssociate Director - Regeneration and Development Advisory
Martin Vickery BSc Hons MRICSCBRE Director – Project and Cost Management
East Midlands CouncilsAN INTRODUCTION TO VIABILITY
3CBRE | DEVELOPMENT VIABILITY IN
PLANNING
WHY VIABILITY IS IMPORTANTLegislative Framework and GuidanceInforms land valuation and development proposalsNational Planning Policy Framework – greater emphasis on viability and deliverabilityGrowth and Infrastructure ActAffordable housing and S.106 contributions are negotiableHCA Atlas Financial Appraisal and Viability in the Planning Process 2012RICS Financial Viability in Planning 2012Harman -Viability Testing Local Plans 2012
4CBRE | DEVELOPMENT VIABILITY IN
PLANNING
RICS Professional Guidance 2012: Financial Viability in Planning 1st Edition 2012:‘A financial appraisal of a development to calculate either:
the residual Site Value (deducting all development costs, including an allowance for the developer’s profit/return from the scheme’s capital value); or
the residual development profit/return (deducting all development costs, including the Site Value/cost from the scheme’s total capital value)
Developer’s Profit is defined as: ‘the amount by which, on completion or partial completion of a development, the estimated value or price realised on sale of a developer’s interest exceeds (or is less than) the total outlay, including such figure for the land as is considered appropriate in the circumstances (including accrued interest).
DefinitionWHAT IS A DEVELOPMENT APPRAISAL?
5CBRE | DEVELOPMENT VIABILITY IN
PLANNING
WHY ARE THEY USEDDevelopment Appraisals
Feasibility Study – establishing development options in terms of mix and scheme content
Viability Study – viability in planning & argument for conversion/alteration/demolition of historic buildings
Establishing the ‘gap’ – HCA/public sector investment Residual Valuation – establishes the land value for
valuation purposes
6CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Identifying Residual Land ValueValue of Completed DevelopmentLess construction costs Less Developer’s Profit (fixed %)Less finance cost %Residual Site Value
DEVELOPMENT APPRAISAL
Identifying Developer’s ProfitValue of Completed DevelopmentLess construction costsLess fixed land cost Less finance cost %Developer’s Profit
7CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Argus Developer HCA Development Appraisal Tool (DAT) Affordable Housing Development Control
Toolkit (GLA) ProDev Bespoke Excel modelling
Available Tools DEVELOPMENT APPRAISAL
8CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Gross Development Value – of the completed development
– Residential sales value of floor space / number of units– Affordable housing (discounted from market housing values)– Commercial estimated values i.e. capitalised rents– Net of rent free periods, incentives– Ground rents– Other income e.g. car parking, short term income streams
Appraisal InputsDEVELOPMENT APPRAISAL
9CBRE | DEVELOPMENT VIABILITY IN
PLANNING
DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
10CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Total Development costs – Site acquisition costs (land value or existing use value)– Build costs (high level BCIS, QS cost plan)– Externals (residential)– Professional fees (overall cost or as a % of build cost)– Other construction costs (e.g. car parking, demolition, site
abnormals, infrastructure) – Contingency (% of build costs)– Sales / Marketing costs – Planning obligations (e.g. S106, S278) – Finance
Appraisal InputsDEVELOPMENT APPRAISAL
11CBRE | DEVELOPMENT VIABILITY IN
PLANNING
DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
12CBRE | DEVELOPMENT VIABILITY IN
PLANNING
DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
13CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Informs cash flow Includes pre-construction lead-in period, construction period and sales/letting
period Phasing
Development Programme DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
14CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Development Cash-flow DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
15CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Development Profit – financial return to developer – reported as % of GDV or % of TDC. – expected level of return variable as dependent on use (e.g. market
expectation on residential = 20% of GDV, commercial 15% to 20% of TDC)
– expected level dependent on risk
Residual Land Value – output where Developer’s profit is fixed as a cost
Appraisal Outputs DEVELOPMENT APPRAISAL
16CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Example of OutputsDEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
17CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Small changes can make large difference to the outputs Can run analysis based on increase / decrease in key inputs such as:
– Rental values – Yields– Build costs– Profit %
Sensitivity Testing DEVELOPMENT APPRAISAL
ARGUS® Developer screenshots reprinted with permission from ARGUS® Software, Inc.
18CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Formal report format Advice to local planning authorities, developers and landowners S106 Viability Study - supporting information to planning applications
informing S.106 contributions/affordable housing negotiations Listed Building/Conservation Areas – support planning applications for change
of use/alterations/demolition Affordable Housing Viability Study Local Plan Viability studies CIL Viability Studies Feasibility Studies
REPORTING
19CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Development Risk Unforeseen site abnormals such as
ground conditions, contamination Delayed programme, weather Title e.g. restrictive covenants Planning Ecology Raising development finance Cost overruns and cost inflation Lettings and sales/market conditions Risk register to clearly set out risk
items
RISK MANAGEMENT AND THE NECESSITY FOR PROFIT
Profit Developer’s expectations of
return related to risk Differing returns for different
uses – commercial/residential Residential 20% GDV Commercial 15%-20% on TDC Market conditions will affect
outturn profits/losses Reduced development
management fee where risk reduced
20CBRE | DEVELOPMENT VIABILITY IN
PLANNING
Commissioning parties Local planning authorities Landowners Promoters Developers Contractors Funding institutions Housing associations Grant bodies including public sector
PURPOSE OF DEVELOPMENT APPRAISALS AND STUDIES
Opportunities New build development Redevelopment schemes Brownfield and greenfield sites Refurbishment Conversion / change of use Overage Viability in planning Viability reviews for ongoing
developments Public support – gap funding
THANK YOUAny Questions?