Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
EAST COAST RAILWAY
Tender Notice No. DRM/Engg/KUR/15/2009
Date: 21.8.09
Name of work:
All repairs & maintenance of P. way zonal
works for a period upto 30/9/2010 from Km. 450.20 to Km. 457.20 between Retang -
Kaipadar station and Km.457.20 to Km. 498.89 on Khurda Road-Puri section under the jurisdiction of SE(P.Way)/ Khurda Road .
Tender Value:
Rs.3515000.00
Amount of Earnest money: Rs. 70300.00
Date of opening: 07.10.09
East Coast Railway
ANNEXURE-I
TENDER FORMS (FIRST SHEET)
Tender No……………………………………………….
Name of Work: P.Way zonal/SE(P.Way)/KUR
To
The President of India,
Acting through the DRM(Engg)/KUR
East Coast Railway.
1. I/We………………………………………………………………………………………. have read the various
conditions to tender attached here to and agree to abide by the said conditions. I
/We also agree to keep this tender open for acceptance for a period of
…………………………………….days from the date fixed for opening the same and in default
thereof, I / We will be liable for forfeiture of my / our “Earnest Money”. I / We offer
to do the work for E.Co.Railway, at the rates quoted in the attached schedule and
here by bind myself / ourselves to complete the work in all respects within
……………………………… months from the date of issue of letter of acceptance of the
tender.
2. I/We also here by agree to abide by the General Conditions of Contract corrected
up to printed / advance correction slip No. ………….. dated…………………. and to carry
out the work according to the Special Conditions of Contract and Specifications of
materials and works as laid down by Railway in the annexed Special Conditions /
Specifications and the E.Co. Railway General Conditions of Contract and Standard
Specifications part IV corrected up to printed / advance correction slip No………………….
dated ……………………….. General Conditions of Contract and Standard Specifications
corrected up to printed / advance correction slip No………………………….
dated………………….. for the present contract.,
3. A sum of Rs……………………………………………….. is herewith forwarded as Earnest
Money. The full value of the Earnest Money shall stand forfeited without prejudice to
any other right or remedies in case my / our Tender is accepted and if :-
(a) I/We do not execute the contract documents within seven days after rece4ipt of
notice issued by the Railway that such documents are ready, and
(b) I/We do not commence the work within fifteen days after receipt of orders to that
effect.
4. Until a formal agreement is prepared and executed, acceptance of this tender shall
constitute a binding contract between us subject to modifications, as may be
mutually agreed to between us and indicated in the letter of acceptance of my / our
offer for this work.
Signature of Witnesses: Signature of Tenderer(s)
1) Date:
2)
Address of the Tenderer(s)
EAST COAST RAILWAY
NOTICE INVITNG TENDER
Tender Notice No. DRM/Engg/KUR/15/09 Dt. 21.8.2009
For and On behalf of President of India, Divisional Railway manager (Engg),
East Coast Railway, Khurda Road, invites sealed Tenders in prescribed form for the
under mentioned works.
Sl.
No.
Description Amount
in Rs.
Amount of
earnest
money in
Rs.
Cost of
tender
Document
in Rs.
1. Development & maintenance of
lawns, gardens etc at Cuttack Station
under SSE(Works)/ Cuttack.
4,21,300/- 8,430/- 1000/-
2. Provision of R.C.C. Pale fencing at
L.C.s under ADEN-I/Cuttack’s
jurisdiction of Khurda Road Division.
16,30,400/- 32,610/- 2000/-
3. Provision of R.C.C. Pale fencing at
L.C.s under ADEN-II/Cuttack’s
jurisdiction of Khurda Road Division.
17,29,200/- 34,580/- 2000/-
4. Proposed placement of 10T capacity
truck for carrying Railway materials
under the jurisdiction of
ADEN/Settlement, Khurda Road.
18,14,400/- 36,290/- 2000/
5. Miscellaneous P.Way works such as
removal of kinky rails, defective rail/
welds, wheel burn rails, changing of
gauge face and other safety related
works at various locations under
ADEN/Sett/ Khurda Road jurisdiction of
Khurda Road Division.
19,18,700/- 38,370/- 2000/-
6. Deep screening and through packing of
points & crossings along with deep
screening of track circuiting zone in
yards, Bridge approaches, LC
approaches, SEJ locations and other
related works on Khurda Road – Puri
section of Khurda Road Division.
19,72,600/- 39,450/- 2000/-
7. Provision of guard rails under Road
Over Bridges and on viaduct under
Sr.DEN(North)’s section of Khurda
Road Division.
20,37,500/- 40,750/- 3000/-
8. Fabrication, transportation, supply
and fixation of new galvanized M.S
chequered plates with gurard rail
renewal and painting of steel channel
sleepers on Br. Nos.950DN
(10x150’G) and 951DN(1x150’G)
between Ganjam - Chatrapur
stations of Khurda Road Division.
21,08,400/- 42,170/- 3000/-
9. Construction of crew lobby cum crew
booking office at Angul station of
Khurda Road Division.
21,91,100/- 43,820/- 3000/-
10. All repairs & maintenance of P. way
zonal works for a period upto
30/9/2010 from Km. 450.20 to Km.
457.20 between Retang - Kaipadar
station and Km.457.20 to Km. 498.89
on Khurda Road-Puri section under the
jurisdiction of SE(P.Way)/ Khurda Road.
35,15,000/- 70,300/- 3000/
11. Proposed repairs to cess & trolley
refuges in patches and other
miscellaneous works from Km.421/5
to 450/3 (DN) on main line between
Barang – Khurda Road section under
the jurisdiction of Sr.DEN(Central)
section of Khurda Road Division.
52,87,300/- 1,05,750/- 5000/-
12. Construction of 8 units Ty-II Qrs in
replacement of Qrs. at Bhadrak,
Baudpur, Manjuri road & Baitarani
road (2 unit in each station) stations
of Khurda Road Division.
53,04,960/- 1,06,100/- 5000/-
13. Provision of precast R.C.C. pale
fencing at Chilika, Kalijai(PH),
Khalikote, Ganjam, Rambha and
Humma stations of Khurda Road
Division.
67,57,500/- 1,35,150/- 5000/-
14. Supply and delivery in stacks of 50
mm size of 15,000 Cum of hard
stone machine crushed ballast of
approved quality at Khurda Depot
and loading the same into any type
of Railway Wagon.
1,03,20,000/- 2,01,600/- 5000/-
15. Upgradation of Running Room at
Palasa in Khurda Road Division.
1,10,69,900/- 2,05,350/- 5000/-
The prescribed non-transferable Tender forms are obtainable on any
working day from the offices of the Assistant Divisional Engineers’ (a) Jajpur
Keonjhar Road, (b) Cuttack, (c) Brahmapur (d) Bhubaneswar and (e) Divl. Rly.
Manager (Engg)/Khurda Road & on remittance of cost of Tender forms (non-
refundable) either by Crossed DD drawn in favour of FA & CAO/East Coast
Railway/BBS on any Nationalized/Scheduled Bank payable at Bhubaneswar or in
the form of money receipt issued by Chief Cashier/East Coast Railway/
Bhubaneswar or Divl cashier/E.Co.Rly. Khurda Road or any station master of this
Railway in support of deposition of requisite money with him. If any Plan/ Drawing
is attached with Tender Form, Rs.200/- per Plan/Drawing will be levied extra. An
amount of Rs.500/- extra has to be paid for each Tender Form, if required by post. The last date and time of issue of Tender form Upto 12.00 Hours of 05.10.2009 The last date and time of receipt of tenders Upto 15.00 Hours of 05.10.2009
Date and time of opening of Tenders at 15.00 Hours of 07.10.2009
If the date of opening happens to be a BANDH or Holiday, the tender will be
opened at the same time on the following working day.
The tender documents will also be available in the
www.eastcoastrailway.gov.in and http://tenders.gov.in during the period from
21/9/09 to 05/10/09 and can be down loaded and used as tender documents
for submitting the offer. Separate Demand Draft towards the cost of tender
documents as mentioned at Col-5, shall have to be enclosed in addition to earnest
money while submitting the tender, other wise, the tender will be summarily
rejected. Railway Administration shall not be responsible for any delay/difficulties/
inaccessibility of the down loading facility for any reason whatsoever.
Tenders will also be accepted by post. However, Railway shall not be
responsible for any postal delay.
In case of any discrepancy between the tender documents down loaded from
internet and the master copy available in the office, the later shall prevail and will
be binding on the Tenderer(s). No claim on this account will be entertained.
The tenderers are required to observe the Web site to find out if any
correction slips issued subsequent to uploading of the Tender Notice and
Schedule.
ELIGIBILITY CRITERIA:-
For the above works (item Nos. 7 to 15) the tenderers should satisfy the
following eligibility criteria.
1. Tenderer should have completed at least one work of similar nature for a
minimum value of 35% of the advertised tender value of the work in the last three
financial years (i.e. Current year and three previous financial years). Tenderer has
to produce supporting documents/ certificates from the organization with whom
they have worked along with the tender offer.
Certificates from private individuals/Organisations for whom such
works are executed/ being executed shall not be accepted.
Note for Eligibility Criteria:
(i) Similar nature of works physically completed within the qualifying period, i.e.
the last 3 financial years and current financial year (even though the work might
have commenced before the qualifying period) should only be considered in
evaluating the eligibility criteria.
(ii) The total value of similar nature of works completed during the qualifying period
and not the payments received within qualifying period alone, should be
considered.
In case, final bill of similar nature of work has not been passed and final
measurements have not been recorded, the paid amount including statutory
deductions is to be considered. If final measurements have been recorded and
work has been completed with negative variation. Then also the paid amount
including statutory deductions is to be considered.
However, if final measurements have been recorded and work has been
completed with positive variation but variation has not been sanctioned, original
agreement value or last sanctioned agreement value whichever is lower should be
considered for judging eligibility.
(iii) In the case of composite works involving combination of different works, even
separate completed works of required value should be considered while evaluating
the eligibility criteria.
For example, in a tender for bridge works where similar nature of work has
been defined as bridge works with pile foundation and PSC superstructure, a
tenderer, who has completed one bridge work with pile foundation of value at least
equal to 35% of tender value and also has completed one bridge work with PSC
superstructure of value at least equal to 35% of tender value, should be considered
as having fulfilled the eligibility criterion of having completed single similar nature
of work.
2. Total contract amount received by the Tenderer during the last three financial
years and in the current financial year should be a minimum of 150% of Advertised
Tender value. The tenderer(s) has to produce the attested certificates from the
employer/client/audited balance sheet duly certified by chartered accountant etc.
along with the Tender offer.
3. Similar work for the above mentioned works is clarified as follows:
Item No.7&10:- Execution of any P.Way related works.
Item No.8:- Execution of fabrication & erection of steel structural works.
Item No.9,12&15:- Execution of Building works.
Item No.11:-Construction/repairs/maintenance of any Civil Engineering
Works.
Item No.13:- Execution of any civil Engineering works.
Item No.14:- Supply of Machine crushed hard stone ballast.
For item No. 14:
The tenderer must submit certificate from govt./Semi Govt./Public
Sector undertaking issued by an authority not lesser than the
Executive Engineer in following format.
Name of the Organization
Name of the Contractor / Firm for whom the certificate is issued.
Name of the work.
Agreement No. & Date
Date of Commencement
Date of completion as per the Agreement.
Actual date of completion.
Agreement Value.
Agreement value on completion of the work.
Cost of machine crushed stone aggregates supplied in the above work.
Signature with Seal of issuing Authority.
Tender offer received without ballast test report shall be summarily
rejected.
Each tenderer at the time of tendering shall submit the test reports of
impact value, abrasion value and water absorption value from GE, LAB of
E.Co. Railway Waltair or REC/Rourkela, REC/ Nagpur or Indian Institute of
Technology Kharagpur. GE, LAB (Construction) Bilaspur, or Jadevpur
University Calcutta or National Test House Alipur or CAO(Con) laboratory at
Chandrasekharpur. Test reports of any other Laboratory shall not be given
due cognizance.
i) In case the delay in submission of the test certificate is due to any of
the approved laboratories, as listed in the tender document, a
certificate from the laboratory concerned clearly indicating the date
on which the sample was received for testing and the date by which
the results would be made available has to be submitted, which will
suffice the requirement. The test certificate should clearly indicate
the name of the Quarry. However, the tenderer shall be obliged to
submit the test certificate to the Railway within 10 (Ten) days of
tender opening, failing which his tender shall be summarily rejected.
4. JV/MOUs will not be accepted for works costing below Rs.8
Crores.
5. PEMD is not applicable for these tenders, tenders submitted without earnest
money will be summarily rejected.
6. Tenderers should submit all documents relating to eligibility criteria as
mentioned above along with their offer, failing which their offer shall be summarily
rejected.
7. The Tenderer for carrying out any construction work in the state of Orissa
and/or Andhra Pradesh must get themselves registered from the Registering
Officer under Section-7 of the Building and Other Construction Workers Act, 1996
and rules made thereto by the Orissa and/or Andhra Pradesh State Govt. and
submit certificate of Registration issued from the Registering officer of Orissa
and/or Andhra Pradesh Govt. (Labour Deptt.). For enactment of this Act, the
tenderer shall be required to pay cess @1% of the cost construction work to be
deducted from each bill. Cost of material shall be outside the purview of cess, when
supplied under a separate schedule item.
Divisional Railway Manager (Engg)
E.Co.Railway, Khurda Road.
For & On Behalf of President of India.
Visit our Website at "eastcoastrailway.gov.in"
8. The tender should be accompanied by a deposit towards Earnest Money to be
made in cash in any of the following forms obtained in favour of Sr.Divisional
Finance Manager E.Co.Railway, Khurda Road or FA & CAO, E.co.Railway,
Chandrasekharpur, Bhubaneswar. i) Deposit Receipt, (ii)Pay order, (iii)Demand
Draft issued from State Bank of India, Nationalised Bank. (Guarantee Bonds will
not be accepted) for the amount specified as under: Rs.8,430/- (Eight Thousand
Four hundred Thirty) for Item No.1, Rs.32,610/- (Thirty Two Thousand Six
hundred Ten) for Item No.2, Rs.34,580/- (Thirty Four Thousand Five hundred
Eighty) for Item No.3, Rs.36,290/- (Thirty Six Thousand Two hundred Ninety) for
Item No.4, Rs.38,370/- (Thirty Eight Thousand Three hundred Seventy) for Item
No.5, Rs.39,450/- (Thirty Nine Thousand Four hundred Fifty) for Item No.6,
Rs.40,750/- (Forty Thousand Seven hundred Fifty) for Item No.7, Rs.42,170/-
(Forty Two Thousand One hundred Seventy) for Item No.8, Rs.43,820/- (Forty
Three Thousand Eighty hundred Twenty) for Item No.9, Rs.70,300/- (Seventy
Thousand Three hundred) for Item No.10, Rs.1,05,750/- (One Lakh Five
Thousand Seven hundred Fifty) for Item No.11, Rs.1,06,100/- (One Lakh Six
Thousand One hundred) for Item No.12, Rs.1,35,150/- (One Lakh Thirty Five
Thousand One hundred Fifty) for Item No.13, Rs.2,01,600/- (Two Lakh One
Thousand Six hundred) for Item No.14 and Rs.2,05,350/- (Two Lakh Five
Thousand Three hundred Fifty) for Item No.15 respectively.
9. The tender shall hold the offer open for a period of 90 days from the date
fixed for opening the same, it being understood that the tender documents have
been sold / issued to the tenderer and the tenderer is being permitted to tender in
consideration of the stipulation on his part that after submitting his tender, he will
not resile from his offer or modify terms and conditions thereof, in a manner not
acceptable to the Chief Engineer / Divisional Railway Manager / Sr.Divisional
Engineer /Divisional Engineer of the East Coast Railway.
Should the tenderer fail to observe or comply with the foregoing stipulation
the aforesaid amount specified as under: Rs.8,430/- (Eight Thousand Four
hundred Thirty) for Item No.1, Rs.32,610/- (Thirty Two Thousand Six hundred
Ten) for Item No.2, Rs.34,580/- (Thirty Four Thousand Five hundred Eighty) for
Item No.3, Rs.36,290/- (Thirty Six Thousand Two hundred Ninety) for Item No.4,
Rs.38,370/- (Thirty Eight Thousand Three hundred Seventy) for Item No.5,
Rs.39,450/- (Thirty Nine Thousand Four hundred Fifty) for Item No.6,
Rs.40,750/- (Forty Thousand Seven hundred Fifty) for Item No.7, Rs.42,170/-
(Forty Two Thousand One hundred Seventy) for Item No.8, Rs.43,820/- (Forty
Three Thousand Eighty hundred Twenty) for Item No.9, Rs.70,300/- (Seventy
Thousand Three hundred) for Item No.10, Rs.1,05,750/- (One Lakh Five
Thousand Seven hundred Fifty) for Item No.11, Rs.1,06,100/- (One Lakh Six
Thousand One hundred) for Item No.12, Rs.1,35,150/- (One Lakh Thirty Five
Thousand One hundred Fifty) for Item No.13, Rs.2,01,600/- (Two Lakh One
Thousand Six hundred) for Item No.14 and Rs.2,05,350/- (Two Lakh Five
Thousand Three hundred Fifty) for Item No.15 respectively shall be liable to be
forfeited to the Railways. Government securities, stock certificates, bearer bonds
promissory notes/cash certificates etc. will not be accepted.
10. Tender forms purchased from one office may be dropped in the tender boxes
at any of five offices mentioned in the item No.11 below.
11. The tender to be deposited in the box available at the Offices of
CE/E.Co.Rly/CSP/BBS & Assistant Divl. Engineers' /Cuttack, Bhubaneswar, Jajpur
Keonjhar Road & Brahmapur and the box will be sealed at 15.00 Hrs. on
05.10.2009 and the tender box will be opened at 15.00 Hrs. on 07.10.2009 in
the Divisional Railway Manger (Engg), E,Co.Railway, Khurda Road Office in
presence of the tenderers. In case the date of opening is declared as holiday the
tenders will be opened on the next working day at the same time and same place.
12. The Tender Notice is also available in the Website "website
eastcoastrailway.gov.in"
No.Engg/T/T.Notice/
Copy Forwarded to :
1. ADENs : JJKR, KDJR, CTC-I & II, BBS, DNKL, BAM, BALU & KUR.
2. SE(P.Way):BHC,JJKR,KDJR,DNKL,TLHR,GRKN,CTC,BRAG,KUR,KAPG,RBA,BAM &
SPT.
3. SE(Works): BHC, CTC, BBS, TLHR, MCS, HQ&WW/KUR, PUI, BALU, BAM & PSA
4.SE(Bridge): BHC, CTC, North & South/KUR for information and display on their
tender notice board.
5. Sr.DFM/KUR for information. He is requested to depute one Section Officer to
witness the opening of tender on 07.10.2009 at 15.00 hrs.
Divisional Railway Manager (Engg)
E.Co.Railway, Khurda Road.
For & On Behalf of President of India.
EAST COAST RAILWAY
RATE SHEET
Name of work:- All repairs & maintenance of P. way zonal works for a period
upto 30/9/2010 from Km. 450.20 to Km. 457.20 between Retang - Kaipadar
station and Km.457.20 to Km. 498.89 on Khurda Road-Puri section under the
jurisdiction of SE(P.Way)/ Khurda Road .
Rate sheet for works covered under Sch-A, B, C & D.
Approximate Tender value:-Rs. 3515000.00
Sl.
No Description of Item
Approx.
Basic value.
(Rs)
Rates quoted by the tenderer in
Figures & Words.
1 Execution of all works
as indicated in
schedule 'A' enclosed.
500000 ___________%__________________
__________________ Percent
(above/below the rates of SOR-1992,
VOl-I, S.E. Railway.
2 Execution of all works
as indicated in
schedule 'B' enclosed.
50000 ___________%__________________
__________________ Percent
(above/below the rates of SOR-1992,
VOl-I, S.E. Railway.
3 Execution of all works
as indicated in
schedule 'C' enclosed.
709975 ___________%__________________
______________________ Percent
(above/below the basic cost given
against each Item of schedule-C
4 Execution of all works
as indicated in
schedule 'D' enclosed.
602760 ___________%__________________
______________________ Percent
(above/below the basic cost given
against each Item of schedule-D
Note:-
1 The tendrer(s) are required to quote separate percentage above/below under
each of above schedule indicating above or below clearly.
2 The entire work should be completed in all respect within 30/9/2010
3 The basic cost item & quantities are approximate and for guidance to the
tenderer(s).This may vary as per the site condition and no claim what-so-ever
will be entertained.
Signature of Contractor(s)/Tendere(s)
EAST COAST RAILWAY
Name of Work: All repairs & maintenance of P. way zonal works for a period upto
30/9/2010 from Km. 450.20 to Km. 457.20 between Retang - Kaipadar station
and Km.457.20 to Km. 498.89 on Khurda Road-Puri section under the jurisdiction
of SE(P.Way)/ Khurda Road .
Schedule:-A
SOR
SL.
No. Name of the work
Approx
Basic Cost
(Rs)
Rate Unit Amount
(Rs)
1 Execution of all works covered
under section A to Z/B (except
T&W ) of SOR-1992, S.E. Railway,
Vol-I.
500000 As per
SOR-
1992,
As per
SOR-
1992,
500000
NOTE:- Most of the work under item No. 1 of Sch.’A’ will be covered by section ‘Z’
of SOR,1992. However, some of the works will be done under other sections of
SOR if required.
Total for schedule ‘A’ Rs. 500000
Schedule:-B
SOR (T&W)
SL.
No. Name of the work
Approx
Basic cost
(Rs)
Rate Unit Amount
(Rs)
1 Transportation of track fittings
diesel and other materials with
contractor’s over transport vehicles
and labour at nominated place as
directed etc. loading, un loading,
and stacking of materials with lead,
lift, freight, taxes royalty, Octroi
etc. under section “T & W” of SOR
1992.
50000 As per
SOR-
1992,
As per
SOR-
1992,
50000
Total for schedule ‘B’ Rs. 50000
EAST COAST RAILWAY
NAME OF WORK: All repairs & maintenance of P. way zonal works for a period
upto 30/9/2010 from Km. 450.20 to Km. 457.20 between Retang - Kaipadar
station and Km.457.20 to Km. 498.89 on Khurda Road-Puri section under the
jurisdiction of SE(P.Way)/ Khurda Road .
Schedule ‘C’
Notes:-Unless otherwise specified, the unit rates for the Items of Sch-C
shall include the cost of following.
a) All labour and materials, tools and plants, equipments, machinery etc.
b) All lead, lift, ascent, descent etc.
c) All handling, rehandling, loading, unloading, freight, consumable stores fuels,
lubricants, transportation, vehicles, diplorring and when & where required
and crossing one or more lines if necessary.
d) All taxes including octroi on materials, royalty and all incidental charges
complete.
SL.
No. Name of the work
Approx
Qty.
Rate
(Rs) Unit
Amount
(Rs)
1 Cleaning of shoulder ballast both on
fair way & cess side by taking the
entire ballast available beyond edge of
sleeper, screening with 20mm wire
basket and putting back clean ballast
on track, dressing & boxing of ballast
to correct profile as advised by
Engineer-In-Charge throwing of
released muck ( including released
muck of BCM if any) away from track
or spreading the released muck on
1500 12 Per
Track
Mtr
18000
cess to raise the cess wherever
required as directed by Engineer-In-
Charge, dressing of cess upto edge of
cess to correct slope including all lead,
lift etc.
2 Distressing of LWR/CWR track as per
LWR manual with/without of rail
tensor as directed by Engineer-In-
Charge or his authorised
representative at site including
removal of all fittings for free
movement of rails opening of level X-
ing etc. cutting CWR/LWR in panels of
any length as directed by Engineer-In-
Charge or his representative, greasing
of all pendrol clips with contractor’s
grease after duly cleaning the clip and
insert by contractor’s wire brush,
changing of rubber pads/ fittings
wherever required putting the rail on
roller at every fifteenth sleepers,
adjustment of gap at SEJ lubrication
of SEJ, with contractors grease/oil,
fixing of fittings correctly from centre
of panel towards both ends, cutting of
extra rails after distressing, insertion
of cut rails of required sizes and
welding of all joints, re fixing of creep
anchors, check rails, closing the level
crossing etc.
10000 18 Tr. Mtr 180000
NOTE:- The permanent repairs in the panel(if any to be done in advance by
welding of fish plated joints existing before distressing of panel. The rate does not
include cutting of rails, renewal of cut rail, drilling of holes if required) welding etc.
which will be paid separately as per section “Z” of SOR 1992 under schedule “A” &
sch-"C".
3 Re-coupment of reference board’s by
fabricating, erecting, at site as per
approved drawing. These board’s like
curve board, LWR, gang jurisdiction
boards etc. are to be made out of MS
plates, angles, channels by welding,
riveting, painting, lettering and
providing luminous strips as per
approved drawing.
500 30 Per
Kg.
15000
NOTE:- If the boards are not fixed at site the deptt. Rate will be reduced by 20%.
Separate payment under SOR 1992 will be made for foundation work, like digging
earth, concreting with contractor’s materials except cement which will be supplied
by the Railways.
4 Cutting of wooden chalks out of U/S
Railway wooden sleepers and making
grooves etc. complete in all respects
including fixing in position under the
welds of rails on track with Rly’s spike
and its packing.
300 20 Each 6000
NOTE:- All rates include transportation of wooden sleepers from the nearest
depot as per availability with lead, lift, inclusive of contractor’s materials required
at site complete.
5 Making check rails of 52 Kg/90-R rail
section at level crossing by
bending/cutting the ends to provide
flair, cutting the rail foot suitably,
drilling holes etc. as per Rly's Drg. No.
CE's 23844 or RDSO T-4148 and
fixing the same with Rly's bracket, bolt
10 4500 Per
L.C.
45000
etc. with contractor's gas etc.complete
as directed by Engineering
Representative at site (check rail for
one level crossing will mean two check
rails both for right and left rail).
6 Execution of various works such as pre
and post tamping operation and other
enabling works in connection with CSM
working.
This item includes:
15000 10 Per
Track
Mtr
150000
(i) Tidying of full cess width is to be done, removal of vegetation (upto 2"
girth) from roots completely and cutting of earth ridges (upto 150 mm)
wherever existing on cess for effective drainage. Heaping up of ballast in
tamping zone including collecting scattered, spilled ballast from cess, bank
slope and spreading in tamping zone.
(ii) Low cess (upto 150 mm) to be made up and high cess should be cut upto
a depth (upto 150 mm) and giving a cross slope of 1 in 30 to 1 in 40 sloping
away from toe of ballast and then dressing of cess neatly.
(iii) Slewing of sleeper laterally to bring them in central position with rail foot
i.e. gap between rail foot and inserts on both sides should be made equal.
(iv) Squaring of sleepers and adjustment of sleeper spacings wherever
required.
(v) Making elastic rail clips visible, removing extra ballast (if any) for visibility
of operators. Clearing of ballast for about half of rail height and removing
joggled fish plates in advance to ensure proper clamping by lifting lining
rollers of the tamper.
(vi) Removal of all obstructions, infringements such as embedded rail posts,
tie bars etc in a width of 2300 mm on either side of the centre of track to
avoid infringements.
(vii) Shifting, removal, handling of scattered P.Way materials lying in the
working zone from the full ballast section and keeping the same within a free
lead of 30 metre neatly stacked.
(viii) Attention to low joints and cleaning of pumping joints.
(ix) Compaction of shoulder and crib ballast boxing and profiling the ballast to
standard approved profile with contractor's own wooden/steel rammers,
labour etc. complete.
(x) The ballast profile should be dressed to the specified dimension with
suitable template. The top and bottom edge of the ballast section should be
neatly lined using hemp chords of 6 mm dia. Re-distribution of ballast within
a free lead of 100 meter to make the ballast section and ballast profile
uniform.
(xi) Removal of wooden blocks, clamp etc for smooth working of tamping
machine.
(xii) Cleaning and greasing of elastic rail clips on PSC sleepers with
contractor's own grease confirming to IS-408 and labour complete as per
para 1411(5)(b) of IRPWM.
(xiii) Recoupment of defficient fittings and proper driving of all fittings to
correct position. Face of central leg of pandrol clip should be flushed with the
end of inserts i.e. the end of the leg shoul not remain inside nor should it
project beyond the eye of insert.
(xiv) One round of slack packing after tamping, including through packing of
spots where machine tamping does not work like glued joints and fish plated
portions etc.
(xv) Removing the ballast from shoulder from one end of sleeper for
facilitating alignment correction and raking in ballast immediately after
correcting the alignment and packing the other end of sleeper to retain
packing of sleeper wherever required as per direction of Engineer in charge or
his authorised representative.
Note:
(i) In case of night working, the rate shall be payable at 1.1 times of the
accepted rates. The contractor has to make his own arrangements for lighting
such as generator, fuel, labour etc.
7 Greasing of Elastic rail clips on PSC 20000 2 Per 40000
sleepers with contractors own grease
confirming to IS:408, of reputed
make, and labour etc. complete as per
para 1411(5)(b) of IRPWM. Greasing
work includes cleaning of ERC, metal
liners, and contact surface of rail and
eyes of inserts, first with wire
brush/bottle wire brush and
subsequently with sand/emry paper
and then cleaning of the above
surfaces with soft brush and
subsequently application of grease
using soft brush. ERC should be
correctly driven so that leg of clip is
flush with the end face of the insert.
Over driving or under driving of the
ERC should not be done.
Sleeper
Supply of materials including all
lead, lift, loading, unloading etc
complete at SE(P.Way)/Stores or
as directed by Engineer in Charge.
8 i) Drill twist made of high speed of size
16 mm of Addision/IT make or
equivalent.
4 450 Each 1800
ii) Drill twist made of high speed of
size 31.50 to 32 mm dia of
Addision/IT make or equivalent.
6 2100 Each 12600
iii) Drill twist made of high speed of
size 26.5 to 28 mm dia of
Addision/IT make or equivalent.
5 1600 Each 8000
9 Supply of grease confirming to
IS:508/IS:408 grade-"O" of reputed
manufacturer.
1500 39.7
5
Kg 59625
10 Retro Reflective Engineering Grade
Sheeting in Strips of 50 mm width
Kiwalite (Japan) make or equivalent of
yellow/white/red colour.
100 50 Mtr 5000
11 Cleaning of side drains and disposing
of the dugged out earth away from the
toe of the cutting & catch water drain
with all lead and lift as per the
direction of Railways representative at
the site of work including crossing of
one or more Railway line, road,
compound wall etc. if required
complete.
1500 41.1
0
Mtr 61650
12 Fixing/repairing of ht. Gauge as per
Railway standard on level
crossing/Bridge approach (Rails to be
supplied by the Railway)
5 2500 Each 12500
13 Repairing of gate booms/lifting barrier
as per Railway standard on level
crossing approaches as per the
instruction of Engineer in charge.
2 2000 Each 4000
14 Supply of different type gases in the
working site as directed by Engineer
in Charge.
i) Oxyzen Gas 10 300 Per
cylinder
3000
ii) DA gases 4 300 Per
cylinder
1200
15 Drilling hole in standard PSC sleepers
on track at exact location for fixing
Guard rail using contractor's own DG
100 135 Per
hole
13500
set along with other equipments
complete in all respect.
16 Painting one coat with contractor's
superior quality ready mixed paint
(Shalimar or equivalent) in all shades
on rails or any steel member after
scrapping thoroughly & clean with
contractor's labour and material
including painting letters, digital
letters (numbering), line diagram (like
key diagram at LC) with properly
maintained geometric line as per
IRPWM on curve boards, reference
boards, points & Xing boards, LC
boards, gate lodges, SEJ reference
boards, LWR & CWR boards and at any
other indicators with contractor;s
equipments complete in all respect.
10000 0.20 Sqcm 2000
Note: If only lettering/painting is
required, then the rate will be 50% for
item No.16.
17 Supplying skilled/artisan staff
(Excluding Welder) like moulder,
chipper, lutter, aligner,
striker/hammerman & adequate Nos.
of semiskilled and unskilled labour and
supplying petrol @ 1.6 ltres/joint for
facilitating welding works on track by
shifting the joint sleepers up to 30 cm
(1’ 0”) on either side, providing
suitable gap of about 23 mm to 25
mm by pulling back of rail including
removing keys, spikes & other
fastenings as required and refixing the
same after welding, cleaning the rail
ends, fixing the Petrol Tank & heating
the rails, ends by railways/ approved
Contractors equipment and chipping
the excess materials if required,
bringing the shifted joint sleepers to
the specific specification as directed
including adjustment of required gaps
for welding aligning, leveling etc.
complete including Contractor’s own
files for filing after welding in running
track.
150 380 Per
Joint
57000
18 Supplying skilled/artisan staff
(Excluding Welder) like moulder,
chipper, lutter, aligner,
striker/hammerman & adequate Nos.
of semiskilled and unskilled labour and
supplying petrol @ 1.6 ltres/joint for
facilitating welding works on track by
shifting the joint sleepers up to 30 cm
(1’ 0”) on either side, providing
suitable gap of about 23 mm to 25
mm by pulling back of rail including
removing keys, spikes & other
fastenings as required and refixing the
same after welding, cleaning the rail
ends, fixing the Petrol Tank & heating
the rails, ends by railways/ approved
Contractors equipment and chipping
the excess materials if required,
50 282 Per
Joint
14100
bringing the shifted joint sleepers to
the specific specification as directed
including adjustment of required gaps
for welding aligning, leveling etc.
complete including Contractor’s own
files for filing after welding on cess.
TOTAL FOR SCHEDULE-C 709975
EAST COAST RAILWAY
NAME OF WORK All repairs & maintenance of P. way zonal works for a period
upto 30/9/2010 from Km. 450.20 to Km. 457.20 between Retang - Kaipadar
station and Km.457.20 to Km. 498.89 on Khurda Road-Puri section under the
jurisdiction of SE(P.Way)/ Khurda Road .
Schedule ‘D’
Notes:-Unless otherwise specified, the unit rates for the Items of Sch-D
shall include the cost of following.
a) All labour and materials, tools and plants, equipments, machinery etc.
b) All lead, lift, ascent, descent etc.
c) All handling, rehandling, loading, unloading, freight, consumable stores fuels,
lubricants, transportation, vehicles, diplorring and when & where required
and crossing one or more lines if necessary.
d) All taxes including octroi on materials, royalty and all incidental charges
complete.
SL.
No. Name of the work
Approx
Qty.
Rate
(Rs) Unit
Amount
(Rs)
1 Cleaning of jungle (light/heavy) from the
side of Railway track once in a month
during monsoon (June to September) and in
other seasons once in two months. jungle
cleaning will be done 8 times in a year
alongwith clearing the branches, leaves and
removing of debrises from the site with
contractor's material and equipment,
labour, tools & plants , lead, lift, ascent,
decent including all incidental charges etc.
complete as directed by Engineer-in -charge
of the work.
50000 560.
00
per
100S
qm
28000
0
NOTE:-
(a) Cleaning will be done 8 times in a year i.e.once in a month during monsoon
(June to September) and remaning perion once in two months.
(b) After each time of cleaning of Jungle, the concerned SE(P.Way) will recorded
the measurement within 7 days after completion of the work (certain patch)
and test checked by ADEN concerned.
(c) It is the responsible of contractor to remove and throw all remnants and
dry/dead grass etc outside the Rly premises and the surface is completely
clean. No extra payment will be made for this job.
(d) Mode of payment: The payment will be made @ Rs.70/-per 100 Sqm/per
each cleaning after duly certified by SE(P.Way) and test checked by ADEN
concerned.
2 Packing of PSC sleeper with extra lifting
above 25mm but below 75mm in track/bad
bank location.
This item includes recuipment of ballast in
crib portion taking from adjacent track
within 50 meter free lead and proper
dressing.
8300 22.50 Per
sleepe
r
186750
3 Profile of ballast in LWR track with making
up of ballast section as per ballast profile for
LWR as laid down in LWR mannual.
20000 5.32 Per Tr.
Mtr
106400
4 Painting one coat with anti corrosive paint
to weld collars (i.e. flash butt welds as well
as A.T. welds) on track/on cess on any rail
sections with high build epoxy paint (2
packs) of reputed manufacturer conforming
3000 9.87 per
joints
29610
to RDSO's Specification no. M&C/PCN-III/BB
on the welded area upto 10cm on either
side including on the underside of the rail
foot as per Railway's AT Weld manual
including lettering/numbering as directed
with contractor's labour, materials, tools &
plants, paints, brushes etc., including
crossing of Railway lines all lead, lift
transportation, taxes/charges leviable by
the Government etc. complete as per
direction of Engineer-in-charge.
Before painting old paint shall be removed
thoroughly by scrapping. All loose rusted
and dirt shall be removed thoroughly by
wire brushing. Grease and oil shall be
removed by use of appropriate solvent
confirming to IS Specification 1745-1976.
Use of detergent followed by water washing
should also be done to ensure removal of oil
and grease apart from the greasing
compound.
TOTAL FOR SCHEDULE-D 602760
Certificate of Familiarization
I/We hereby solemnly declare that I/We have visited the site of above work
and have familiarized myself/ourselves of the working conditions there in all respects
and in particular the following:-
· Topography of the area and existing road network (highways
& village - Pucca & Katcha) and availability of service roads.
· Soil conditions at the site of the work.
· Sources and availability of construction materials.
· Rates for construction materials.
· Availability of construction materials.
· Availability of local Labour both skilled and unskilled and the
prevailing labour rates.
· Availability of water & electricity.
· Availability of space for putting up.
· Labour camps, offices, store godown.
· Engineering yard etc.
Signature Of Tenderer(S)/Contractor(S)
INSTRUCTIONS TO TENDERER (S)
2.1. Documents Part of This Tender
Sl
No
Document Name Published
By
Referred In This
Document As
1
South Eastern Railway Schedule Of
Labour And Material Rates 1992
Vol.1 with Correction Slip issued up
to date of opening of tender.
South Eastern
Railway
SOR 1992
2
General Condition Of Contract And
Standard Specification (Vol.2)
2001 with Correction Slip issued up
to date of opening of tender.
South Eastern
Railway
GCC 2001
Note: The terms “Correction slip” as referred to in this tender document includes the
following terms also.
Addendum slip, Correction slip, Addendum slip and corrigendum slip which are
issued in consecutive serials.
2.2 Submission :
2.2.1 Tender must be enclosed in sealed cover superscribing thereon the name of
the work, as mentioned in the tender notice, Scheme No and must be
deposited in the Tender box in the office of the AEN/BAM, AEN/BBS,
AEN/JJKR, AEN/CTC & CE/CSP/BBS/E.Co.Railway on or before the specified
time. Tenderer(s) are requested to be present at the time of opening of
tender.
2.2.2 Tenders that are received after the date and time specified will not be
considered.
2.2.3 Tenders containing over writing, additions, alterations, erasures, obliteration
and other discrepancies may not be considered. The Tenderer(s) should
properly attest all corrections made by them.
2.2.4 The Tenderer(s) shall sign every page of the tender documents and submit all
of them.
2.2.5 The Tenderer(s) should quote rates both in figures and in words. Wherever
there is a difference between the rates quoted in figures and in words, the
rate quoted in words will be taken as correct.
2.2.6 (i) Tender to give consent in a mandate form (Annexure-A) for receipt of
payment through ECS/EFT.
(ii) Tenderer to provide the details of Bank A/C in line with RBI guide lines for
the same. These details will include Bank Name, Branch Name and address.
Account type Bank A/C No. and Bank & Branch Code as appearing on MICR
cheque issued by bank.
(iii) Tenderer to attach certificate from their bank certifying the correctness of
all above mentioned information ( as mentioned in para (ii) above.
(iv) In case of non-payment through ECS/EFT or where ECS/EFT facility is not
available, payment will be released through cheque.
2.3 Eligibility criteria:
With the intention of bringing good & experienced contractor in the tenders the
eligibility criteria in all tenders shall be as under.
2.3.1 As given in the table below for open tenders costing above Rs.20
lakhs.
(i)
Should have completed in
the last three financial
years (i.e current year
and three previous
financial years):
At least one similar single work, for a
minimum of 35% of Advertised Tender value
of work.
(ii) Total contract amount
received during the last
three financial years and
in the current financial
year.
Should be a minimum of 150% of Advertised
Tender value. The tenderer (S) are required to
produce along with the tender the attested
copies of certificates from the employer/client/
audited balance sheet duly certified by
chartered accountant etc. in support of the
financial turnover.
2.3.2 Document submission:-The following documents should be submitted
along with tender.
(a) List of personnel, organisation available on hand and proposed to be engaged
for the subject work.
(b) List of plant & Machinery available on hand (own) and proposed to be
inducted (own and hired to be given separately) for the subject work.
(c) List of works completed in the last three financial years giving description of
work, organisation for whom executed, approximate value of contract at the
time of award, date of award and date of scheduled completion of work.
Date of actual start, actual completion and final value of contract should
also be given.
(d) List of works on hand indicating description of work, contract value,
approximate value of balance work yet to be done and date of award.
Note:
1 In case of items (c) and (d) above, supportive documents/certificates from the
organisations with whom they worked/are working should be enclosed.
2 Certificate from Private Individuals/Organisations for whom such works
are executed/ being executed shall not be accepted.
2.4 Company Profile
2.4.1 Tenderer(s) should specifically and fully disclose in his/their respective
tender, their respective constitutions and submit attested Photostat copies
of documents like partnership deed, Articles and Memorandum of
Association, Certificate of Incorporation etc., if any in support of such
disclosures. If Tenderer(s) is/are a firm i.e. partnership business, it should
be stated whether the same is Registered under the Indian Partnership Act,
and the name and address of all the partners of the firm should be fully
disclosed. He/they shall submit the partner ship deed/any other appropriate
document, if any, to prove about the joint venture with any other party
having such machineries, base of quarries etc. along with the tender offer
and the details of document regarding the joint venture shall of the dates
back before the date of opening of tender. The Railway Administration shall
always have the liberty to demand production of the original of the said
documents and also to make such further and other enquiries regarding the
constitution of the Tenderer(s) as may be considered necessary.
2.5 Programme for completion of work
2.5.1 Tenderer(s) should submit a programme for completion of work in the time
frame stipulated in the tender.
2.5.2 Tenderer(s) should work out resource requirement (men, material &
machinery) on monthly basis for his/their programme and submit it to
Railways. Tenderer should also submit a monthwise statement of resources
(men, material & machinery) proposed to be deployed at site.
2.6 Earnest Money: The tenderer(s) shall be required to deposit earnest money
with the tender for the due performance with the stipulation to keep the
offer open till such date as specified in the tender, under the conditions of
tender.
The earnest money shall be % age of the estimated tender value as indicated in
the Tender Notice as per following table.
Value of the work (Tender
Value)
EMD
(i) For works estimated to cost upto Rs.
1 Crore
2 % of the estimated cost of the
work.
(ii) For works estimated to cost more
than Rs. 1 Crore
Rs. 2 Lakhs plus ½ % (half
percent) of the excess of
estimated cost of work beyond Rs.
1 Crore subject to a maximum of
Rs. 1 Crore.
The earnest money shall be rounded to the nearest Rs.10. This earnest money
shall be applicable for all modes of tendering.
2.6.1 The Tender must be accompanied by a sum, as mentioned on page 1 of his
tender, as Earnest Money.
(i) Earnest Money should be in cash or in the form of deposit receipts, pay orders
or demand drafts executed by State Bank of India or any of the Nationalized
Banks or by a Scheduled Bank.
(ii) Deposit receipts executed by the Scheduled Banks (other than the State Bank
of India and the Nationalized Banks) approved by the Reserve Bank of India
for this purpose. The Earnest money is to be endorsed in the name of Sr.
Divl. Finance Manager, East Coast Railway, Khurda Road.
2.6.2 Earnest Money other than in the form mentioned in clause 2.6.1 (i) & (ii)
will not be accepted.
2.6.3 The Tenderer(s) shall hold the offer open for a period 90 days from the
date of opening of the Tender. It is understood that the Tender Documents
have been sold/issued to the Tenderer(s) and the Tenderer(s) is/are being
permitted to the tender in consideration of the stipulation on his/their part
that after submitting his/their Tender he/they will not resile from his/their
offer or modify the terms and conditions thereof in a manner not acceptable
to the DRM(Engg), E.Co. Railway, Khurda Road. Should the Tenderer(s) fail
to observe or comply with the foregoing stipulations, Railway shall forfeit
the Earnest Money deposited with the tender.
2.6.4 The Earnest Money of the Unsuccessful Tenderer(s) will be returned to
the Unsuccessful Tenderer(s). However Railway shall not be responsible for
any loss or depreciation that may happen to Earnest Money while they are
in Railways possession, nor be liable to pay interest thereon.
2.6.5 The Earnest Money deposit of the Successful Tenderer(s) will be retained
towards part of the Security Deposit for the due and faithful fulfillment of
the Contract. The same shall however be forfeited if the successful
Contractor(s) fails to execute the Agreement Bond within 15 days after the
receipt of Orders to that effect towards penalty imposed under the condition
of Contract.
2.7 Security amount
Unless otherwise specified in the special conditions, if any, the Security
Deposit/rate of recovery / mode of recovery shall be as under:-
a) Security Deposit for each work should be 5% of the contract value,
b) The rate of recovery should be at the rate of 10% of the bill amount till the
full security deposit is recovered,
c) Security Deposits will be recovered only from the running bills of the
contract and no other mode of collecting SD such as SD in the form of
instruments like BG, FD, etc. shall be accepted towards Security Deposit.
Security Deposit shall be returned to the contractor after the expiry
of maintenance period and after passing the final bill based on No Claim
certificate. The Competent shall normally be the authority, who is
competent to sign the contract. If this Competent Authority is of the rank
lower than JA Grade, then a JA Grade Officer (concerned with the work)
should issue the certificate. The certificate, inter alia, should mention that
the work has been completed in all respects and that all the contractual
obligations have been fulfilled by the contractors and that there is no due
from the contractor to Railways against the contract concerned. Before
releasing the SD, contractor concerned should submit an unconditional and
unequivocal no claim certificate.
2.7.1 Performance Guarantee (P.G.)
The procedure for submitting Performance Guarantee is outlined below:-
a) The successful bidder may give Performance Guarantee amounting to 5% of
the contract value in any of the following forms:-
i)A deposit of Cash, (ii) Irrevocable Bank Guarantee (As per Annexure-B), (iii)
Government securities including State Loan Bonds at 5% below the market
value, (iv) Deposit Receipts, Pay Orders, Demand Drafts and Guarantee
Bonds. These forms of performance Guarantee could be either of the State
Bank of India or of any of the Nationalized Banks, (v) Guarantee Bonds
executed or Deposits Receipts tendered by all Scheduled Banks, (vi) A
Deposit in the Post Office Saving Bank, (vii) A Deposit in the National
Savings Certificates, (viii) Twelve years National Defence Certificates, (ix)
Ten years Defence Deposits, (x) National Defence Bonds and (xi) Unit Trust
Certificates at 5% below market value or at the face value whichever is less.
Also FDR in favour of FA&CAO (free from any encumbrance) may be
accepted.
“Bank Guarantees (BGs) to be submitted by Contractor(s)/
Supplier(s) should be sent directly to the concerned authorities by
the issuing Bank under Registered Post A.D.”
b) A Performance Guarantee shall be submitted by the successfully bidder after
the letter of acceptance has been issued, but before signing of the
agreement. The agreement should normally be signed within 15 days after
the issue of LOA and the Performance Guarantees shall also be submitted
within this time limit. This guarantee shall be initially valid up to the
stipulated date of completion plus 60 days beyond that. In case, the time
for completion of work gets extended, the contractor shall get the validity of
Performance Guarantee extended to cover such extended time for
completion of work plus 60 days.
c) The Performance Guarantee (PG) shall be released after the physical
completion of the work based on the ‘Completion Certificate’ issued by the
competent authority stating that the contractor has completed the work in
all respects satisfactorily. The security deposit, however, shall be released
only after the expiry of the maintenance period and after passing the final
bill based on ‘No Claim Certificate’.
d) Wherever the contract is rescinded, the security deposit shall be forfeited and
the Performance Guarantee shall be encased and the balance work shall be
got done independently without risk and cost of the failed contractor. The
failed contractor(s) can participate in the risk & cost tender as per the
stipulations made vide clause (f) of item No.2.7.1 below.
e) The Engineer shall not make a claim under the Performance Guarantee except
for amounts to which the President of India is entitled under the contract
(not withstanding and/or without prejudice to any other provisions in the
contract agreement) in the event of:
i Failure by the contractor to extend the validity of the Performance
Guarantee as described herein above, in which event the Engineer may
claim the full amount of the Performance Guarantee.
ii Failure by the contractor to pay President of India any amount due, either
as agreed by the contractor or determined under any of the
Clauses/Conditions of the notice to this effect by Engineer.
iii The contract being determined or rescinded under provision of the GCC the
Performance Guarantee shall be forfeited in full and shall be absolutely at
the disposal of the President of India.
f) i. The provision of Clause 62(y) of GCC should be the guiding principle for Risk and Cost Tenders.
ii. The failed contractor should be notified about the Risk and Cost Tender and in
case he applies for the Risk and Cost Tender, the tender forms shall be
issued to him.
In case the offer of the failed contractor is accepted:
a) He should furnish a Performance Guarantee at 10% of the contract value
before the agreement is executed.
b) The Security Deposit shall be recovered only from the running bills and no
Bank Guarantee in lieu of Security Deposit can be accepted.
c) In case, he fails to execute the work for the second time, the Performance
Guarantee would be encashed and he would be debarred from participating
in the subsequent tender for completing the balance work.
2.8 General :
2.8.1 Non-compliance with any of the conditions set forth in this tender
document, SOR 1992 and GCC 2001 is liable to result in the tender being
rejected.
2.8.2 The instructions to the Tenderer(s) shall be deemed to form a part of the
tender document.
2.8.3 SOR 1992 and GCC 2001 can be had on payment of an amount specified
for copy of each Volume on any working day during office hours, subject to
availability, in the office of DRM(Engg), E.Co. Railway, Khurda Road, Jatni
752050.
2.8.4 The Submission of a Tender by a Tenderer(s) shall be deemed to imply
that he has read, understood and abided by the conditions stated in tender
document, SOR 1992 & GCC 2001.
2.8.5 A Certificate should be attached along with the Tender papers that the
Tenderer(s) has/have purchased SOR 1992 and GCC 2001 and gone
through all the conditions of contract and specifications etc. embodied
therein.
2.8.6 If the Tenderer(s) deliberately give/gives wrong information in his/their
Tender or create/creates circumstances for the acceptance of his/their
Tender, Railways reserve the right to reject such tender at any stage.
2.8.7 The authority for the acceptance of the Tender will rest with the President
of India acting through DRM, E.Co. Railway, who does not bind himself to
accept the lowest or any other Tender nor does he undertake to assign
reason for declining to consider the Tender. No correspondence will be
entertained with the Tenderer(s) in respect of the rejection of any or all of
the Tenders. The Railways reserve the right to accept the Tender either for
the full quantity of work or part thereof or divide the works amongst more
than one Tenderer without assigning any reasons for any such actions.
2.8.8 Should a Tenderer(s) find discrepancies in or omission from the drawings
or any of the Tender Forms, or should be in doubt as to their meanings,
he/they should at once, notify the authority inviting Tender who may send a
written instructions to all Tenderer(s). It should be understood that every
endeavour has been made to avoid any error which can naturally affect the
basis of the Tender and the successful Tenderer(s) shall take upon
himself/themselves and provide for the risk of any error which may
subsequently be discovered and shall make no subsequent claim on account
thereof.
2.8.9 Tender documents in which Tenderer(s) submits Tender shall become the
property of the Railway and the Railway shall have no obligation to return
the same to the Tenderer(s).
2.8.10 Before submitting a Tender, the Tenderer(s) will be deemed to have
satisfied himself/themselves by actual inspection of the site and locality of
the work all conditions likely to be encountered during the execution of the
works. It is understood that Tenderers have taken into account all factors
and rates he/they enters/enter in the Tender Forms are adequate and all
inclusive, to accord with the provisions in Clause - 37 of the GCC 2001.
2.8.11 The successful Tenderer(s) shall execute an Agreement with the President
of India acting through the DRM(Engg), E.Co. Railway, Khurda Road for
carrying out the works according to specification laid down in the document.
2.8.12 The Agreement to be executed shall on the Agreement Form for the
works of the E.Co. Railway except as specifically varied by these Tender
Papers, as well as provisions contained in the Tender Documents shall form
part of the contract. All certificates submitted by Tenderer including
programme & completion of work shall for the part of agreement.
2.8.13 The Tenderer(s) whose tender is accepted shall appear at the office of the
DRM(Engg), E.Co. Railway,Khurda Road, in person; in case of a Firm or
Corporation, a duly authorised representative there of, to execute the
Contract documents within Fifteen days after notice that the contract has
been awarded to him/them. Failure to do so shall constitute breach of the
Agreement effected by the acceptance of the Tender in which case the
earnest money accompanying the Tender shall be forfeited by the Railway
as liquidated damages for such fault.
2.8.14 In case of non acceptance of a Tender by the Railway Administration for
any reason whatsoever, the Tenderer(s) cannot claim for the expenses
incurred by him in submitting the Tender for the work or for any other
account.
2.8.15 Non-compliance with any of the conditions set forth herein above is liable
to result in the Tender being rejected.
2.9 Death of Tenderer
2.9.1 If a Tenderer(s) expires after the submission of his Tender or after the
acceptance of his Tender, the Railway shall deem such Tender as cancelled.
If a Partner of a Firm expires after submission of their Tender or after the
acceptance of their Tender the Railway shall deem such Tender as cancelled
unless the Firm retains its character legally acceptable.
2.10 Price preference 2.10.1 No price preference will be allowed for public sector undertaking.
Signature of Tendere(s)/Contractor(s)
Annexure – A
Form No. E-5
Appendix-VIII
NATIONAL ELECTRONIC FUND TRANSFER/
ELECTRONIC CLEARANCE SERVICE (CREDIT CLEARING)
MODEL MANDATE FORM
( Investor / Customer’s Opinion to receive payment through Credit Clearing
Mechanism)
NAME OF THE SCHEME AND THE PERIODICITY OF PAYMENT
No:-
1) Investor / Customer’s Name :
2) Particulars of Bank Account :
a) Name of the Bank :
b) Name of the Branch :
Address :
Telephone No.
c) 9 Digit Code Number of the bank and
branch appearing on the MICR cheque
issued by the bank :
d) IFSC Code of the branch :
e) Type of the Account (Current/Savings/
Cash Credit with code 10/11/13) :
f) Ledger and Ledger Folio Number :
g) Account Number (appearing on the Cheque book) :
(In lieu of the bank certificate to be obtained as under, please attach a bank
cancelled cheque or photocopy of a cheque or front page of your savings bank
passbook issued by your bank for verification of the particulars).
3. Date of effect:
I hereby decide that the particulars given above are correct and complete. If
the transaction is delayed or not effected at all for reasons of incomplete or
incorrect information, I would not hold the user instruction responsible. I have
read the option invitation letter and agree to discharge the responsibility
expected of me as a participant under scheme.
Date: Signature of the
Investor/Customer
Certified that the particulars furnished above are correct as per our records.
Bank Stamp
Date._______________
Signature of the Authorised
Official of the Bank.
Annexure – II
REVISED MODEL FORM OF BANK GUARANTEE BOND
GUARANTEE BOND
In consideration of the President of India (hereinafter called the
Government) having agreed to exempt …………………………….. (hereinafter called
the said contractor (s) from the demand under the terms and conditions of an
agreement dated------------ made between ………………….. and ……………………. for
…………………………(hereinafter called “the said agreement”), of security deposit for
the due fulfillment by the said contractor(s) of the terms and condition
contained in the said agreement, on production of a Bank Guarantee for
Rs…….………………… (Rupees ……………………………………………………………… only).
1. We ……………………………………………….(hereinafter referred to as the Bank) (
indicate the name of the Bank) at the request of ………………………… (contractor(s)
do hereby undertake to pay to the Government an amount not exceeding
Rs……………………… against any loss or damage caused to or suffered or would be
caused to or suffered by the Government by reason of any breach by the said
contractor(s) of any of the terms or conditions contained in the said agreement.
2. We ………………………………(indicate the name of the Bank) do hereby
undertake to pay the amounts due and payable under this guarantee without any
demur merely on a demand from the Government stating that the amount/
claimed is due by way of loss or damage caused to or would be caused to or
suffered by the Government by reason of breach by the said contractor (s) of any
of the terms or conditions contained in the said agreement or by reason of the
contractor (s) failure to perform the said agreement. Any such demand made on
the Bank shall be conclusive as regards the amount due and payable by the Bank
under this guarantee. However our liability under this guarantee shall be
restricted to an amount not exceeding Rs.…………………………..
3. We under take to pay to the Government any money so demanded not
withstanding any dispute or disputes raised by the contractor(s) / supplier(s) in
any suit or proceeding pending before any court of Tribunal relating thereto our
liability under this present being absolute and unequivocal.
The payment so made by us under this bond shall be a valid discharge of our
liability for payment there under and the contractor (s) supplier (s) shall have no
claim against us for making such payment.
4. We ………………………………… (indicate the name of the bank) further agree
that the guarantee herein contained shall remain in full force and effect during
the period that would be taken for the performance of the said agreement and
that it shall continue to be enforceable till all the dues of the Government under
or by virtue of the said agreement have been fully paid and its claims satisfied or
discharged or till………………………office/ department) Ministry of
……………………….certified that the terms and conditions of the said Agreement
have been fully and properly carried out by the said contractor (s) and according
discharges this guarantee. Unless a demand or claim under this guarantee is
made on us in writing on or before the ………………….., we shall be discharged
from all liability under this guarantee thereafter.
5. We …………………………… (indicate the name of the bank) further agree
with the Government that the Government shall have the fullest liberty without
our consent and without affecting in any manner, our obligations hereunder to
vary any of the terms and conditions of the said agreement or to extend time of
performance by the said contractor(s) from time to time or to postpone for any
time or from time to time any of the powers exercisable by the Government
against the said contractor(s) and to forbear or enforce any of the terms and
conditions relating to the said agreement and we shall not be relieved from our
liability by reason of any such variation or extension being granted to the said
contractor(s) or for any forbearance, act or omission on the part of the
Government or any indulgence by the Government to the said contractor(s) or
any such matter or thing whatsoever which under the law relating to sureties
would, but for this provision, have effect of so relieving us.
6. This guarantee will not be discharged due to the change in the
constitution of the Bank or the contractor (s)/ supplier (s).
7. We……………………………..(indicate the name of the bank ) lastly undertake not
to revoke this guarantee during its currency except with the previous consent of
the Government in writing.
Date the ……Day of…………..……200
For _____________________
(indicate the name of the bank )
SPECIAL CONDITIONS OF CONTRACT (PART-I)
3.1 General :
3.1.1 The Special Conditions of Contract, Part-I, II & III Instructions to
Tenderer(s) and the stipulations made in the Schedules of quantities shall
govern the works under this contract, in addition to and /or in part
suppression of the SOR 1992 & GCC 2001.
3.2 Precedence Order :
3.2.1 When there is a conflict between the Instructions to Tenderers, Special
Conditions of Contract Parts –I, II & III and the stipulations contained in the
Schedules of quantities and Rate on the one hand and the SOR 1992 & GCC
2001 on the other, the former shall prevail.
3.2.2 Provision contained on Instruction to Tenders, Special Condition of Contract
Pt. I, II & III Schedule of quantities and rate get precedence over provisions
contained in IRS Code/IRC code/IS codes/codes owned by other institution.
3.2.3 In case of conflict between provision of IRS/IRC/IS specification the
precedence will be in same order. In case of ambiguity the decision of
Divisional Railway Manager shall be final & binding.
3.2.4 Any notes appearing in the Schedule Of Quantities and Rates will take
precedence over Special Conditions Of Contract Part I, II & III and also SOR
1992 & GCC 2001.
3.2.5 Any specifications/conditions stated by the Tenderer(s) in the covering
letter submitted by him along with the tender shall be deemed to be a part
of the contract only to such an extent as has been expressly accepted by
the Railway.
3.2.6 All measurements, methods of measurements, meaning and item of
specifications and interpretation of Special Conditions of Contract part I, II
& III made by the Engineer on behalf of the Railway shall be final and
binding and shall be considered as “Excepted matters” in terms of condition
No.63 of GCC 2001.
3.3 Agreement:
3.3.1 All expenses in drawing up the agreement and the cost of stamp duty, if
any shall be borne by the Contractor.
3.3.2 The tenderer(s) if he/they so desire(s) may quote his /their Bank Account
number and other details of their Bank for arranging payment through
electronic payment mechanism as soon as the system is made effective.
3.4 Passes:
3.4.1 No Railway pass of any kind for self/ agent/ labourers, for any purpose in
connection with this tender/contract will be issued to the Contractor.
3.5 Change of address
3.5.1 Any change in the address of the Contractor shall be forthwith intimated in
writing to the Railways. The Railway will not be responsible for any loss or
inconvenience suffered by the Contractor on account of his failure to comply
with this.
3.6 Dissolution of Contractor’s Firm:
3.6.1 If the Contractor’s firm is dissolved due to death or retirement of any partner
or for any reasons whatsoever before fully completing the whole work or
any part of it undertaken by the Principal agreement, the partners shall
remain jointly, severally and personally liable to complete the whole work to
the satisfaction of the Railway and to pay compensation for loss sustained if
any, by the Railway due to such dissolution. The General Manager of the
Railway shall decide the amount of such compensation and his decision in
the matter shall be final and binding on the Contractor(s).
3.7 Deployment of plant and machinery:
3.7.1 The deployment of plant and machinery including moving machines shall be
such as not to infringe or cause damage to Railway track or any other
Government or private properties. Operation of such equipment involving
infringement to moving dimensions prescribed in the Handbook of the
Schedule of Dimensions of the Railway shall not be undertaken without the
prior approval of the Engineer-in-charge. Contractor/s shall be wholly
responsible for any loss or damage resulting from violation of this clause.
3.8 Emergency work:
3.8.1 In the event of any accident or failure occurring in or about the work or
arising out of or in connection with the construction, completion or
maintenance of the works in which Administration will not be liable to pay
the Contractor any charges for rectification or repairs to any damage which
may have occurred from any cause whatsoever, to any part in the opinion
of the Engineer requires immediate attention, the Railway may bring its own
workmen or other agency to execute or partly execute the necessary work
or carry out repairs if the Engineer considers that the Contractor/s is/are
not in a position to do so in time and charge the cost thereof, as shall be
determined by the Engineer-in-charge of SE Railway to the Contractor.
3.9 Night work:
3.9.1 Contractor/s attention is drawn to clause 23 of the GCC 2001 that stipulates
that no work shall be carried out between sunset and sunrise without
previous permission by the Engineer.
3.9.2 If the Engineer is satisfied that the work is not likely to be completed in
time except by resorting to night work, he may order the Contractor/s to
carry out the works even at night without conferring any right on the
Contractor for claiming any extra payment for the same. The Contractor at
his own risk and cost shall make all arrangements in this connection.
3.10 Service Roads :
3.10.1 The Contractor(s) will be permitted to make use of the service roads already
existing in the possession of the Railway. All service roads required by the
contractor in or outside Railway boundary shall be constructed by the
Contractor at his own risk and cost and all these roads shall be maintained
by the Contractor at his own cost. The Railway reserves the right to make
use of the service roads as and when necessary without any additional
payment to the Contractor.
3.11 Water supply :
3.11.1 The Contractor/s shall be responsible for the arrangements to obtain potable
water supply necessary for the works. No arrangements will be made by
the Railway administration for supplying water to the Contractor either for
drinking purpose or execution of work. Rates quoted shall include the cost
of arranging potable water supply. Only potable water shall be permitted to
use in all types of concrete as well as for curing.
3.12 Electricity:
3.12.1 Any electric supply required at site for whatsoever purpose shall be
arranged by the Contractor/s. The Contractor/s shall be responsible for the
arrangements for obtaining electric supply at his own cost and rates quoted
shall include the cost of providing electric supply arrangements required for
the work.
3.12.2 If required by Contractor/s, thpe Railway Administration may give required
assistance in recommending to State Electricity Board for giving necessary
electric connection to the Contractor for execution of works.
3.13 Loss Of Work Orders:
3.13.1 If the original work order issued to the contractor is lost by him for any
reason whatsoever and the Contractor demands for supply of a duplicate of
the same, a penal levy of Rs.100/- (Hundred only) for each work order shall
be imposed on him for the issue of a duplicate copy.
3.14 Income Tax Deduction :
3.14.1 In respect of works, the contract value of, which is more than Rs.10, 000/-
each, a deduction of 2% on the gross payment from each of the
Contractor’s bills shall be made in terms of section 194(e) of the Income
Tax Act of 1961 & 1991. From time to time surcharge will also be deducted
along with I.T.
3.15 Employment of Graduate Engineers/Diploma Holders by Contractor:
3.15.1 Tenderer(s)/Contractors after award of the contract shall be required to
employ unemployed civil engineering graduates/diploma holders on monthly
salary and for the duration as indicated below.
Contract
Value.
No. Of Eng./ Diploma
Holders and Degree
holders.
Monthly Salary. Duration.
Engineers Less than
Rs. 15
Lakhs. Diploma holder - 1 Engg. Diploma holder.
Not Less Than Rs.
2000/-.
During Currency
of Contract
Engineers Above Rs.
15 Lakhs. Degree holder – 1 Engg. Degree holder not
Less Than Rs. 4000/-
During Currency
of Contract
3.15.2 In case Contractor fails to employ the Technical staff as aforesaid, he shall
be liable to pay a sum of Rs.4000/- (Rupees Four thousand only) for each
month of default in case of Graduate Engineer and Rs.2000/- (Rupees Two
thousand only) for each month of default in case of Diploma Holder to be
deducted from his ongoing on A/C bills.
3.15.3 The decision of the Engineer-in-Charge as to the period for which the
required Technical staff was not employed by the contractor and as to the
reasonableness of the amount to be deducted on this account shall be final
and binding on the contractor.
3.16 Procurement of Machinery by Contractor:
3.16.1 It should be clearly understood that it is entirely Contractor’s responsibility
and liability to find and procure all the machinery, tools and plant and their
spare parts that are required for the efficient and methodical execution of
the work. Delay in procurement of such items due to their non-availability
or import difficulties or any other causes, whatsoever, shall not be taken as
an excuse for slow progress or non-performance of the work.
3.17 Hire of Railway’s Plant & Machinery:
3.17.1 The Railway may at their discretion give on hire to the Contractor such plant
as compressors, Pneumatic equipment, concrete mixers and light
equipment, as considered necessary by the engineer. However it does not
guarantee hiring any such machinery and it shall not entertain any claim or
compensation due to Railways inability to supply such plant/machinery or
the condition of the railway’s plant/machinery supplied on hire be taken as
an excuse for slow progress or for non- performance of the work.
3.18 Hire charges on Plant & Machinery :
3.18.1The railway administration shall charge the contractor for the hire of
machinery and plant supplied to him. The rate of hire charge for the plant
and machinery given by the railway will be calculated on the basis of the
S.E Railway General Conditions of Contract and Standard Specifications -
1994 Volume - 2 together with correction slips issued upto date of tender
notice.
3.19 Statutory Certificate Etc. :
3.19.1 While the machine(s) is/are in the possession of the contractor(s), he/they
shall be responsible for seeing that any inspection certificate or license
required under any Government Act is obtained in due time. The contractor
shall also be responsible for seeing that all required precautions are
observed in using the plant as well, and he shall be responsible for any
accident that may occur from the use of the plant.
3.20 Access to Plant at Hirer’s Premises:
3.20.1 The Railway shall be given reasonable access to the plant and such facilities
as may be necessary to satisfy itself that the plant is being so used as to
avoid any unnecessary wear or loss or risk.
3.21 Right to Recall :
3.21.1 The Railway shall reserve to itself the right to recall any plant/machinery
without assigning any reasons by giving one month’s notice or at any time
without notice in the event of its being required by the Railway for an
unforeseen emergency. In either case, the Railway shall not be liable to
pay any compensation to hirer for the loss that may be caused by the
withdrawal of the plant.
3.22 Storage of Railway Materials :
3.22.1 The Contractor shall make his own arrangements at the site of work for the
safe storage and custody of Railway material issued to him. Such Railway
materials issued to the Contractor and stored at the site of work shall be
open for inspection by the Engineer-in-charge or his representative at all
times.
3.23 Maintenance Period:
3.23.1 The maintenance period in terms of Clause 47 and 48 of the GCC 2001 shall
be six months from the date of issue of completion certificate for all works
except earthwork & supply of ballast. For earth work the maintenance will
be 12 months from the date of issue of completion certificate.
3.24 Employment of Railway surplus labour by contractor :
3.24.1 The Tenderer(s)/Contractor(s) may be required to engage
surplus/retrenched casual labour of the E.Coast Railway if found suitable
upto the extent of twenty persons for each Lakh or part of the value of the
contract during the currency of the contract. The terms of the employment
between such labour and the Tenderer(s) may be on mutually agreed terms
subject to the statutory provisions contained in the labour regulations and
enactments. The Contractor(s) shall indemnify the Railway against any
claim arising out of employment of such labour and the Railway shall not be
a party to any disputes etc., arising out of the employment of such labour
by the Tenderer(s)/Contractor(s).
3.24.2 The Contractor shall engage local labour for skilled/ unskilled work as far as
practicable.
3.25 Antilarval work:
3.25.1 During execution of the works against this contract the Contractor(s) shall
be responsible for antilarval work at his/their own cost.
3.26 Non-itemised works:
3.26.1 Where item not covered by the schedules are to be executed, the rates for
such non-itemised works shall be negotiated before commencement of such
work or to be got executed through any other agency by the Railway at the
discretion of the Railway Administration.
3.27 Time is the essence of Contract :
3.27.1 Time is the essence of contract. All the works are required to be completed
in all respects as stipulated by the Railway within the completion date.
Progress shall be maintained strictly in accordance with the programme
given by the Contractor and accepted by the Engineer-in-charge from time
to time as per the programme chart as per (BAR/CPM/PERT chart) as will be
finalised.
3.28 Lead & Lift on Railways/Contractor’s Materials:
3.28.1 No lead and lift for the Contractors/Railways materials is payable for the
works executed under this contract unless otherwise specified.
3.29 Testing of cement concrete :
3.29.1 The rates for concrete works shall be deemed to include all charges for
testing of aggregates, sand, water and the concrete as required to be done
in accordance with specifications, including the cost of labour, materials,
equipment, moulds, transport etc. The Contractor shall prepare at his own
cost standard cubes of concrete according to the directions of the Engineer-
in-charge both for the Preliminary Tests and during work Tests. The charges
of testing shall be borne by the contractor.
3.29.2 The Contractor shall follow the Guidelines for Quality Control for Concrete as
per Indian Railways Standard Code of practice for plain, reinforced &
Prestressed concrete for Bridge Construction (Concrete Bridge Code)
Incorporating Correction slips Nos. 1 to 20 and in S.I. Units. as well as
Specification and Special Conditions of Contract.
3.29.3 The criteria for acceptance of concrete work shall be that the test results
carried out at 28 days age should be found satisfactory.
3.30 Cutting/uprooting of tress :
3.30.1 No extra rate shall be paid for cutting or uprooting tress upto 30 cm. depth
at one metre above ground level, grubbing root of trees or jungle clearance
involved in any work under this contract.
3.31 IS Codes/IRS Specifications:
3.31.1 Wherever any reference to Code, specification, Act etc. is made in this
document, it shall be taken as a reference to the latest version thereof,
including all amendments and corrections there to or otherwise specified.
3.31.2 The contractor shall not be entitled to any extra payment on any account for
compliance with the various provisions of IS specifications/IRS specifications
and Special Conditions of contract. The rates indicated in the schedule shall
be deemed to include all works required to be done in compliance with the
specifications.
3.32 Sales Tax or any other taxes :
3.32.1 The Contractor shall bear in full all taxes and royalties or levied by the State
Government and/or Central Government from time to time. This would be
entirely a matter between the contractor and State
3.31.2 Government/or Central Government. Railway will recover the taxes and
royalties through running account bills if the contractor fails to pay the
taxes and royalties to the government.
3.33 Tree Cutting :
3.33.1 If the section passes through forest land, the contractor or his labour is
prohibited to cut the trees for the purpose of fire wood or for any other
purpose. Cutting of trees as required under the items of works indicated in
the tender schedules may be carried out strictly as directed by the
Engineer-in-Charge of the work. Unauthorized felling of trees will result in
prosecution and imprisonment. It is the contractor’s responsibility to cause
no damage to the forest growth and the Contractor at his own cost shall
arrange any fuel required by the Contractor for his own use or for the use
by his labourers, or for the work. The Contractor shall take this aspect into
consideration while quoting the rates against the tender.
3.34 Approval of Samples of Material :
3.34.1 All materials to be used in the work by the Contractor shall be subject to
the prior approval of the Engineer-in-charge of the work. Contractor shall
submit samples of materials to be used to work and arrange for the
supplies, only after if Engineer has approved the samples.
3.35 Blasting:
3.35.1 Wherever a cutting passes through or near OHE transmission line only
controlled blasting is to be resorted to as per schedule.
3.35.2 The guide lines for blasting as provided in GCC 2001 should be followed
3.36 Place of issue of Railway materials
3.36.1 The materials required to be supplied by the Railway such as cement and
steel for the items where specified will be issued from the Railway store
depot of SE-Incharge of the work and the transportation of the materials to
sites as advised by SE-Incharge and the transportation of surplus materials
from the site of work to the concerned SE-Incharge Godown will be at
contractor’s cost.
3.37 Price variation. i) Price Variation Clause (PVC) shall be applicable for tenders of value
more than Rs.50 Lakh irrespective of the contract completion period and
PVC shall not be applicable to tenders of value less than Rs.50 Lakh.
3.38 Disaster/train accident/Natural calamities.
3.38.1 In the event of any disaster/ train accident/ Natural calamities, the
contractor(s) shall be asked to mobilize his/ their manpower/ vehicle/ tools
and machineries to the affected locations to meet the situation. In such a
case, the contractor(s) shall shift the required material as per the direction
of Engineer-in-charge and separate payment for this will be made as per the
prevailing SOR and for the activities if any executed beyond the scope of
the agreement will be paid separately at the rates finalised by the Railway
Administration as per the existing procedure for NS items.
3.38.2 The contractor shall train his/ their staff/ supervisor adequately on First-
Aid (shall submit a certificate in support of it) and see that they are capable
of encountering any adverse situation at the disastrous spot during
execution of the work. In the event of the Engineer being satisfied that the
contractor is not employing properly trained staff, the contractor shall at
once remove them and engage additional trained staff within seven days
and failure on the part of the contractor will entitle the Railway take
necessary action, in terms of agreemental condition and which may cause
termination of contract in the event of failure of the contractor to engage
competent men.
3.39 VARIATION IN CONTRACT QUANTITIES
In suppression of paras 5.3.6,5.3.7 and 5.3.9 of Annexure-I of Board’s letter
No. 94/CE-I/CT/4 dated 17.10.2002, the procedure as detailed below shall
be adopted for dealing with variation in quantities during execution of works
contracts:-
i) Individual NS items in contracts shall be operated with variation of plus or
minus 25% and payment would be made as per the agreement rate. For
this, no finance concurrence would be required.
ii) In case of increase in quantity of an individual item by more than 25% of
the agreement quantity is considered as unavoidable, the same shall be got
executed by floating afresh tender. If floating a fresh tender is considered
not practicable, negotiations may be held with the existing contractor for
arriving at reasonable rates for additional quantities in excess of 125% of
agreement quantity.
iii) The limit for varying quantities for minor value items shall be 100% (as
against 25% prescribed for other items). A minor value item for this
purpose is defined as an item whose original agreement value is less than
1% of the total original agreement value.
iv) No such quantity variation limit shall apply for foundation items.
v) As far as SOR items are concerned, the limit of 25% would apply to the
value of SOR schedule as a whole and not on individual SOR items.
However, in case on NS items, the limit of 25% would apply on the
individual items irrespective of the manner of quoting the rate (single
percentage rate or individual item rate).
vi) For the tenders accepted at the Zonal Railways level, the variation in quantities will be approved by the authority in whose powers the revised
value of the agreement lies.
vii) For tenders accepted by General Manager, variations upto 125% of the
original agreement value (even if the revised agreement value is beyond
GM’s competence to accept tenders) may be accepted by General Manager.
viii) For tenders accepted by Board Members and Railway Ministers, variations
upto 110% of the original agreement value may be accepted by General
Manager.
ix) The aspect of vitiation of tender with respect to variation in quantities should be checked and avoided.
3.40 First-Aid facilities “There shall be provided and maintained by the contractor
so as to be readily accessible during all working hours first-aid box equipped
with the prescribed contents at every place where contract labour is
employed by him”. 3.41 The Tenderer for carrying out any construction work in the state of Orissa and/or
Andhra Pradesh must get themselves registered from the Registering Officer under
Section-7 of the Building and Other Construction Workers Act, 1996 and rules made
thereto by the Orissa and/or Andhra Pradesh State Govt. and submit certificate of Registration issued from the Registering officer of Orissa and/or Andhra Pradesh Govt.
(Labour Deptt.). For enactment of this Act, the tenderer shall be required to pay cess
@1% of the cost construction work to be deducted from each bill. Cost of material shall be outside the purview of cess, when supplied under a separate schedule item.
Signature of Tendere(s)/Contractor(s)
SPECIAL CONDITIONS OF CONTRACT (PART-II)
4.1 GENERAL:
4.1.1 The contractor should appoint a qualified person as site supervisor and the
supervisor should have full knowledge of the track works and should be well
versed in the safety rules of Railways. The contractor is required to furnish
along with the tender the Bio Data of the persons he intends to appoint as his
representative at site for supervision of day to day works. Tenders without this
information are liable to be rejected. However, the site supervisor will be tested
for his knowledge in track works and safety rules by the Engineer-In-Charge
(Sr. DEN/DEN) and only after being certified by the Engineer-In-Charge he can
be allowed to supervise the works at site. The decision of the Engineer-In-
Charge regarding the suitability of a person to act as site supervisor shall be
final. However the contractor himself may supervise works if certified fit by
Engineer-In-Charge.
4.1.2 No work on track shall be undertaken until and unless the PWI-In-Charge or
his representative and contractors technical supervisor are present at site.
4.1.3 The contractor will observe all safety precautions during working on track and
in the vicinity of track. The contractors supervisor should be well versed in the
safety rules of Railways. No tools and equipment will be supplied by Railways.
The contractor should procure at his own cost and make available sufficient
track gauges, gauge cum levels, spanners, keying and spiking hammers.
Augurs crow bars. Tommy bars, claw bars grip gauges, cotter splitters,
beaters, ballast rakes, wire claws, forks, wire brushes, ballast screens, mortar
pans, screening baskets, shovels powrahs, rail thermometers, expansion
liners, slotted fish plates, rail closures combination fish plates, wooden blocks
and wedges and all tools and equipment necessary for efficient execution of
work including that for rail cutting and rail drilling and chamfering of holes.
The contractor will not be allowed to commence the work unless adequate
manpower, tools and equipment required for the work are made available by
him at site or work. The contractor’s men must know the use of safety
equipment including use of Detonators. Contractor has to supply and fix
luminous temporary engineering restriction boards conforming to the Annexure
8/3 and 8/4 of para 807 & 808 of Indian Railway Permanent Way Manual. The
detailed specification for temporary Engineering restriction boards will be
supplied to the contractor by PWI-In-Charge of the work.
4.1.4 The housing accommodation and watering arrangement for contractor’s labour
will have to be arranged by contractor strictly as per prevailing labour contract
Act.
4.1.5 No compensation what-so-ever towards any accident or injury sustained to
labourers will be paid by Railway.
4.1.6 Before commencement of work, joint inventory of existing materials in the
track is to be taken by PWI-In-Charge of work and contractor and entered in
the inventory register and jointly signed.
4.1.7 After handing over the specific section to the contractor, the maintenance of
the track including the length under speed restriction will be maintained and
guarded by the contractor till the works is over and the track is handed over
back to the PWI-In-Charge.
4.1.8 The P. way materials required for the work will be supplied to the contractor
free of cost from nominated place on voucher.
4.1.9 The contractor will be responsible for the safe custody of all released
materials and fittings till such time they are handed over to the PWI-In-Charge
of the work at nominated place by contractor’s means and acknowledgement
obtained.
4.1.10 In case the released P. way materials are left over at site after a days work,
the contractor has to employ Chowkidars day and night till the P. way
materials are handed over to PWI-In-Charge at nominated place.
4.1.11 Shifting of labour camp from place to place as the work advances will be
done by the contractor at his own cost.
4.1.12 In case, the zone under speed restriction exceeds the stipulated length and
time loss is more than permissible; the contractor will have to pool up
additional resources to accelerate the work. The loss caused to the Railways by
consuming extra time shall be recoverable at the rate specified under clause
(vi) of “ Safety Precautions” mentioned below.
4.1.13 The following registers and records will have to be maintained by Railway’s
representative at the site of work. The contractor has to supply these registers
and should sign the registers so maintained in token of the acceptance of the
entries made therein.
i) Register of Joint Inventory
ii) Note order register
iii) Register of materials laid in track
iv) Register of materials received back from contractor.
v) Register of daily progress and type of work
vi) Register of track parameters
vii)Drawings, sketches, pegs ( Reference levels, cross and longitudinal)
4.2 SAFETY PRECAUTIONS:
4.2.1 The contractor is responsible for completing the day’s work taken in hand in all
respect to the satisfaction of Railway’s representative irrespective of adverse
weather conditions and any other situation arising during the course of the
work. No extra payment will be made for making any additional arrangements
for this.
4.2.2 In case of sudden rain while the work is in progress, the labourers should not
leave the site of work keeping the track unsafe for passage of traffic. In case
the labourers leave the site of work. PWI -In-Charge of the work will take
appropriate action to make the track safe for passage of traffic & maintain the
same till the contractors labourer return to the site on the same day or the next
day. In all such events, the cost of labour and tools and plants etc. expended
for rectifying contractors unfinished work will be recovered from the
contractors dues. The recovery per man per day would be made at the rate of
Rs. 100/- ( Rupees One hundred only) per man-day.
4.2.3 The contractor will be held responsible for any deterioration of track geometry,
which results in unsafe condition for passage of train. The cost of detention to
trains as a result of unsafe condition of track as result of unsatisfactory work on
the part of contractor will be recovered from contractor’s dues.
4.2.4 The works should executed to the satisfaction of the PWI-In-Charge of the
work. The contractor will be primarily responsible for the safety of traffic not
withstanding the presence of Railway’s supervisor staff at site.
4.2.5 In the event of any accident at the work spot a departmental enquiry will be
held by the Railway. If it is established that the accident occurred wholly or
partially due to any act tant-amounting to negligence on the part of contractor,
he shall render himself liable for all damages and also prosecution as per law.
4.2.6 The contractor will maintain the track where renewal has been done by him till
the speed is relaxed to normal sectional speed. A joint programme has to be
made out by the contractor and the Assistant Engineer fixing the dates for
gradual relaxation of speed restrictions as per para 308 of Indian Railway
Permanent Way Manual. A penalty of Rs. 1,000/- per 100m length per day (
over and above the scheduled length under restriction) will be imposed on the
contractor for his failure to adhere the target for relaxation of speed restriction.
4.3 PREPARATORY WORKS:
Stage Check is a check to ensure adequate preparedness to undertake the
work and stage check should be exercised by over all PWI-In-Charge of the
section. Assistant Engineers should ensure that stage check has been carried
out by the over all In- Charge PWI before commencement of work
The following preparatory works must be carried out and verified by In-
Charge before commencement of relaying work:
4.3.1For Through Sleeper Renewal Work:
4.3.1.1 Unloading of sleepers from wagons should be carried as per exact
requirement for every 100M within an error margin of (+/-) 5%. However care
should be taken to balance the errors and the errors should not get
accumulated beyond a length of 200m. No payment for unloading of sleepers
will be admissible unless the wrongly unloaded sleepers are shifted to correct
location free of cost by the contractor. The PWI-In-Charge of the work shall
give the Telegraph Post wise requirement of sleepers in advance to the
contractor. No payment for shifting the sleepers which may become necessary
during the renewal work due to incorrect unloading will be admissible.
4.3.1.2 Joint Inventory of existing sleepers and rail sleeper fastenings and sleeper
fastenings should be recorded jointly by contractors representative and Rly’s
representative at site 100% check should be carried out by PWI-In-Charge of
the work and 20% test check should be carried out by the Assistant Engineer.
4.3.1.3 The exact position of rail joints after allowing for one expansion gap each is
marked accurately with contractor’s steel tape on base rail.
4.3.1.4 Position of new sleepers is then marked on the base rail with white paint and
transferred to opposite rail by means of a contractor’s T- square.
4.3.1.5 A speed restriction of 20 Kmph is imposed and contractor’s temporary
Engineering restriction boards are fixed at appropriate places. The contractor
shall arrange at his own cost required number of luminous temporary
Engineering Restriction Boards conforming to the Annexure 8/3 and 8/4 of
para 807 & 808 of Indian Railway Permanent Way Manual. The detailed
specification for temporary Engineering Restriction Boards will be supplied to
the contractor by PWI-In-Charge of the work. The contractor will arrange
Kerosene Oil for lighting of Boards during night.
4.3.1.6 Sufficient Tools, equipment and labour should be arranged in advance to
achieve a minimum daily progress of 150 sleepers.
4.3.1.7 The existing rail levels / formation levels shall be taken by contractor with
his theodolite/ Dumpy level and men under the supervision of PWI-In-Charge
of the work before commencement of the work . Intermediate level pegs should
be marked at 20m intervals and change points and semi permanent pegs
should be fixed at 100m interval either at the centre of track or on the cess as
directed by PWI-In-Charge of the work. The design of the pegs will be approved
by Sr.DEN/DEN-In-Charge of the work. Payment for fixing of pegs shall be
made as per schedule. The proposed rail levels after renewal should be got
approved by Divisional Engineer-In-Charge of the work and marked at the site.
The existing and proposed longitudinal section of the track should be available
at site.
4.3.1.8 In curves for speed restriction up to 50 Kmph, 50% of total cant will be
provided . Super elevation shall be raised in subsequent round of packing.
4.3.1.9 Re-alignment of curves and straight should be done before commencement
of renewal work.
4.3.2 For Through Rail Renewal Work:
4.3.2.1A speed restriction of 20 Kmph is imposed and contractor’s luminous
temporary Engineering restriction boards are fixed at appropriate places as
directed by PWI-In-Charge of the work.
4.3.2.2 Joint Inventory of existing rails and rail sleeper fastenings should be
recorded jointly by contractors representative and Rly’s representative at site.
100% check should be carried out by PWI over all In-Charge of the work and
20% test check should be carried out by the Assistant Engineer.
4.3.2.3 The rails to be renewed should be classified and paint marked on as per para
320 & 321 of Indian Railway Permanent Way Manual by Assistant Engineer
before commencement of renewal work.
4.3.2.4 Unloading of rails should be done under personnel supervision of the PWI-
In-Charge of the work. Ramps made of unserviceable rails should be used for
unloading and utmost care must be taken to avoid damage to rails.
4.3.2.5 All rails must be examined for any defect and bent / kinked rails must be
straightened by Jim crow in advance.
4.3.2.6 Pairing and butting of rails should be completed on the cess at the location
where renewal is planned . Utmost care is to be taken to ensure that no rail
infringes the track or is likely to infringe the track under vibration of running
trains.
4.3.2.7 Rails of same lengths should be used in pairs.
4.3.2.8 Two fish bolt holes must be drilled at either end of each rail/rail panel as per
the approved template. All the fish bolt holes must be chamfered by contractor
with his chamfering tool and only after obtaining a certificate from PWI-In-
Charge of the work to the effect that all the fish bolt holes have been drilled
and chamfered properly, the rails can be laid on track.
4.3.2.9 The rails meant to be used at level crossings and station yards should be
given a coat of coal tar before laying.
4.3.2.10 The location of rail joints in approach of level crossings, bridges. Points &
crossings & curves must be decided in advance by PWI-In-Charge of the work
and marked at site.
4.3.2.11 Sufficient tools equipment and skilled labour should be arranged in
advance to achieve a minimum progress of 500m in a traffic block period of 2
hours.
4.3.2.12 Closure rail pieces of 1”, 2”, 3”, 4”,5 “ & 6” lengths ( 4 pieces of each
size) should be prepared and kept ready at site.
4.3.2.13 The required length of cut rail for closing the days work should be
calculated and the cut rails should be kept ready. The work should be planned
in such a manner that the shortest length of rails to be used in track is not less
than 5.5 metres. The cut rails should not be laid opposite to each other.
4.3.2.14 Sufficient Nos. of fish bolts, fish plates washers, grease should be arranged
at site before commencement of renewal. The fishing surfaces of rails and fish
plates should greased before putting the fish plates in position. The required
quantity of grease of approved quantity as per specification IS: 408 should be
arranged by the contractor at his own cost.
4.3.2.15 Track protection equipment as per Annexure 8/1 and 8/2 of para 806(1)
and 806(2) of Indian Railway Permanent Way Manual should be arranged at
site. All required protection equipment except. Detonators should be arranged
by the contractor at his own cost. Detonators shall be available with the Rly’s
site supervisor. The PWI-In-Charge of the work should ensure availability of
protection equipment and trained staff at site for carrying out protection work.
4.3.2.16 The works will be executed under traffic block or caution order as required
and the same will be arranged by Railway. Speed Restriction/ Caution Indicator
Boards as required shall be fixed at appropriate places as per the direction of
Rly’s representative. The contractor shall arrange at his own cost required
number of luminous temporary Engineering Restriction Boards conforming to
the Annexure 8/3 and 8/4 of para 807 & 808 of Indian Railway Permanent way
Manual. The detailed specification for temporary Engineering Restriction Boards
will be supplied to the contractor by PWI-In-Charge of the work.
4.3.2.17 It must be ensured before start of rail renewal on curved track that all the
curve boards and rail posts indicating transition points as described in para 413
of Indian Railway Permanent Way Manual are available on the curves.
Deficiencies if any, shall be made good by the contractor at his own cost before
commencement of work.
4.3.3 FOR LIFTING OF TRACK.
4.3.3.1 Longitudinal levels should be taken by the contractor with his theodolite /
dumpy level and men and correct level pegs should be fixed at 20m intervals
before lifting is commenced.
4.3.3.2The proposed rail levels should be got approved by Sr. DEN/DEN-In-Charge
of the work and marked at the size. The existing and proposed longitudinal
section of the track should be available at site.
4.3.3.3 Lifting should commence from the down hill and carried out in the direction
of rising grade in case of single line. It should proceed in the opposite direction
to traffic in case of double line care being taken not to exceed the easement
gradient of 25mm in one rail length of 13M.
4.3.3.4 Before commencement of work, it must be ensured that there will be no
infringements of standard dimensions due to bridges and over head structures.
4.3.3.5 Sufficient equipment. Non-infringing track lifting jacks and labour should be
arranged by the contractor for giving a daily minimum progress of 200m. the
cumulative progress for a period of 10 days ( consecutive) should not be below
1500 metres . For any short fall recovery will be made at the rate of Rs.3/- per
metre.
4.3.3.6 A speed restriction of 20 Kmph should be imposed and temporary
Engineering Restriction Boards are fixed at appropriate places. The contractor
shall arrange at his own but required number of temporary Engineering
Restriction Boards conforming to the Annexure 8/3 & 8/4 of para 807 & 808 of
Indian Railway Permanent Way Manual. The detailed specification for temporary
Engineering Restriction Boards will be supplied to the contractor by PWI-In-
Charge of the work.
4.3.3.7 No lifting of track should be planned on old ballast bed without shallow
screening.
4.3.3.8 Lifting work must be preceded by shallow screening of ballast as per para
227 of Indian Railway Permanent Way Manual where deep screening is not
done.
4.3.4 Deep Screening of Ballast.
4.3.4.1 Existing rail levels and formation levels should be plotted and attached to
the schedule.
4.3.4.2 A longitudinal section of the track should be taken indicating the rail levels
at every 30 metres, as also at changes of grades, obligatory points like
culverts, bridges over line structures, tunnels, level crossings, signal gantries
and points and crossings.
4.3.4.3 In station yards, on run through lines, cross sections at every 50 metres
should be taken and plotted including platform levels, rail levels and clearance
to under side of over line structures.
4.3.4.4 On the basis of the longitudinal and cross sections the final levels will be
decided by the Engineer-In-Charge keeping in view the depth of ballast
cushion to be provided and the possibility of eliminating humps, sags and
unevenness in the existing longitudinal section. The reference pegs shall be
available at 30m intervals to determine longitudinal and cross levels.
4.3.4.5 The repairs to cess should be carried out to bring it to correct level.
4.3.4.6 The minimum daily progress of deep screening work ( for 150 mm depth)
shall be 100 metres. Monthly progress should be minimum 2000 metres failing
which recovery at the rate of Rs. 10/- per metre will be made. Penalty shall be
calculated with cumulative effect. If the contractor makes up the back log of a
month in the following month, the penalty may be waived by Sr. DEN/DEN -In-
Charge of the work and the decision of the Sr. DEN/DEN in this regard shall be
final and binding.
4.3.4.7 The rate for deep screening includes slowing of curves.
4.3.4.8 Sleeper renewal if planned , should be carried out in advance of Deep
Screening.
4.3.4.9 Sufficient No. of wooden blocks/ wedges must be arranged at site.
4.3.4.10 Sufficient No. of ballast screens of appropriate size for screening of ballast
should be available at site.
4.3.4.11 A speed restriction of 20 Kmph should be imposed and temporary
Engineering Restriction Boards are fixed at appropriate places. The contractor
shall arrange at his own cost required number of temporary Engineering
Restriction Boards conforming to the Annexure 8/3 & 8/4 of para 807 & 808 of
Indian Railway Permanent Way Manual. The detailed specification for temporary
Engineering Restriction Boards will be supplied to the contractor by PWI-In-
Charge.
4.3.4.12 Surplus screened muck shall be transported away from track free of cost
upto a lead of 100 metres, irrespective of the height.
4.3.5 Through Packing of Track:
4.3.5.1 Track readings should be jointly taken by the Railway’s representative at site
and contractor before commencement of work.
4.3.5.2 Inventory of all track fittings existing on the portion of the track proposed to
be through packed should be jointly recorded by the Railway’s representative
at site and contractor.
4.3.5.3 All track fittings required to recoup the deficiencies should be made available
at site. the contractor has to carry the fittings from nearest store Depot of the
PWI-In-Charge of the work free of cost.
4.3.5.4 Sufficient tools and equipment and labour should be arranged by the
contractor for giving a minimum daily progress of 200M.
4.4 QUALITY ASSURANCE:
The following minimum standard of track para metres must be achieved for release
of payments.
4.4.1 For Through Sleeper Renewal:
After completion of the work, the PWI-In-Charge of the work shall check the quality
of the work executed and no payment towards renewal of sleepers will be made
unless following minimum standard of execution is achieved.
a) All sleepers should be laid as per the correct spacing marks given on rails
conforming to provisions in para 244 of Indian Railway Permanent Way Manual.
b) All sleepers should be laid square to the track.
(c) One round of through packing is given to the newly laid sleepers.
(d) The percentage of loose sleepers when checked with the help of contractors flax
metre should not exceed 10%. At no location two consecutive sleepers shall be
loose.
(e) All complement of rail sleeper and sleeper fastenings have been provided as per
design.
(f) The track gauge should be within 5mm tight to 3mm slack for straight track
including curved track of redius 350M or more and up to 10mm slack for curves
track of radius less than 350m in case special sleeper for curves are provided.
These measurements are with reference to nominal track gauge of 1676 mm.
(g) Sleeper to sleeper variation in track gauge should not be more than 2mm.
(h No low joints should be allowed and high joints should not be more than 2mm
above the general rail level.
(i)Spacing of sleepers with respect to theoretical spacing should not vary more than
(+/-) 20mm.
(j) Cross level to be recorded on every 4 th sleeper should not be more than (+/-)
3mm on straight track.
(k) Proper designed super elevation should be provided on curved track to an
accuracy of 5mm measured on every 4th sleeper.
(l) Alignment
(i) On straight track on 20M chord +/- 2mm
(ii) Variation over theoretical versines
(a) On curves of radius more than 600M on 20M chord +/- 5mm
(b) On curves of radius less than 600M on 20M chord +/- 10mm
(m) Variation in longitudinal level with reference to approved longitudinal sections
should not be more than 50mm
(n) The released sleepers and fittings are properly accounted for and neatly stacked
sufficiently clear of track.
(o) All the missing/ defective curve boards. Transition indicator boards, Gradient
Posts, Kilometre Boards LWR boards, Level Crossing Boards etc. in the length
under renewal must be made good at contractor’s cost. Existing boards should
be repaired/painted the prescribed collars as directed by AEN-In-Charge of the
work.
(p) Side drains, ballast walls to be repaired.
4.4.2 For Through Rail Renewal Works:
After completion of the work, the PWI-In-Charge of the work shall check the quality
of the work executed and no payment towards renewal of rails will be made
unless following minimum standard of execution is achieved.
(a) Correct expansion gap is provided at joints.
For single rails gap at rail joints should be provided as per para 3 1 5 of Indian
Railway Permanent Way Manual which is reproduced below:
Rail Temperature Range Recommended initial laying gap for 1213M
rail length.
0 to 10o Celsius 10mm
10 to 25o Celsius 8mm
25 to 40o Celsius 6mm
40 to 55o Celsius 4mm
55 to 70o Celsius 2mm
Above 70o Celsius Zero
For SWP, gap at rail joints should be provided as per para 508 ( for zone III) of
Indian Railway Permanent Way Manual which is reproduced below:
Rail Temperature at the time of Installation in centigrade:
tm-22.5 to
tm-17.6
tm-17.5 to
tm-12.6
tm-12.5 to
tm-7.6
tm-7.5 to
tm-2.5
tm-2.4 to
tm-2.5
tm-2.6 to
tm-7.5
Initial Laying gap in mm …
12mm 10mm 8mm 6mm 4mm 2mm
The value of “tm” will be decided by the Divisional Engineer.
(b) Rail joints:
… Rail joints shall be laid square to track on straight track. In curved track, no joint
shall be out of square by more than half pitch of holes in fish plates.
… Mid staggering of rail joints should be done on curved track of radius less than
400M
… No fish plated rail joints are permitted within the level crossing portion and within
three metres on either side of level crossing for single rail track and within six
metres in case of SWR track.
… No fish plated rail joint should be provided within 3M of a bridge abutment.
…. No fish plated rail joint should be provided over small bridges of less than 6.1M .
for other spans, rail joints should preferably be provided at 1/3 rd span from
either end.
(c) No bent/ kinked rails should be laid in track.
(d) All four fish bolts should be provided at all rail joints after champhering of bolt
holes.
(e) The fishing surfaces of rails and fish plates should be greased at rail joints.
(f) The rail fastenings should be driven correctly in proper direction.
(g) The rails used at level crossings and station yards should be given a cost of coal
tar.
(h) The released rails and fastenings are properly accounted for classified and
stacked on the cess sufficiently clear of track.
(i) The gauge face of rails shall be applied a coat of grease graphite before putting
in track.
(j) On curves, all the stations numbers at 10m interval should be painted on the
inner web of the outer rail. The corresponding Versions and Super Elevations
should be painted on the inner web of the inner rail.
(k) All the joints, including welded joints should be numbered serially Km . wise.
4.4.3, For Lifting of Track:
After completion of the work, the PWI-In-Charge of the work shall check the quality
of the work executed and no payment towards lifting of track will be made
unless following minimum standard of execution is achieved.
(i) The work has been carried out satisfactorily to the satisfaction of PWI-In-Charge
of the work
(ii) One round of through packing should be given immediately after lifting of track
and the track parameters must confirm to the standards as mentioned for
through sleeper renewal work of the tender schedule.
(iii) The designed rail level is achieved.
(iv) Shallow screening of ballast has been carried out.
(v) The repairs to cess has been carried out bring it to proper level and width.
4.4.4.Deep Screening of Ballast:
After completion of the work, the PWI-In-Charge of the work shall check the
quality of the work executed and no payment towards deep screening of ballast
will be made unless following minimum standard of execution is achieved.
(i) The work has been carried out satisfactorily to the satisfaction of PWI-In-Charge
of the work and final longitudinal and cross levels of formation has been
achieved.
(ii) Proper cross slope of 1 in 40 must be ensured from centre of track towards cess
side in case of single line. In case of double line tracks at same level, the cross
slope shall be given from centre of formation.
(iii) In case of track in cuttings side drains should be cleaned and the bottom of side
drains should be at least 30cm. below the formation level.
(iv) In ballast walls where provided in cuttings all weep holes must be cleaned.
Provision of weep holes where none exist and rebuilding of ballast wads if
necessary must be completed.
(v) The spoil from deep screening and cleaning of side drains must be disposed off as
per direction of PWI-In-Charge of the work in such a way that it is not likely to
be washed back in to the drains.
(vi) One round of through packing should be given immediately after deep screening
and the track parameter’s must confirm to the standards as mentioned for
through sleeper renewal work of the tender schedule.
4.4.5 First through Packing:
After completion of the work, the PWI-In-Charge of the work shall check the
quality of the work executed and no payment towards deep screening of ballast
will be made unless following minimum standard of execution is achieved.
(i) The track parameters must confirm to the standard specified as per para 16 of
Indian Railway Permanent Way Manual.
(ii) There should not be any deficient fittings in the through packed track.
(iii) The cess and track should be cleared of all grass, plantations and muck upto a
depth of 1m along the slope of the formation in case of banks. The formation
top edge is clearly defined and uniform. In case of formation width being more
than standards, dog bellying shall be done to define the standard formation and
cross drains at 6 metre interval excavated to slope of 1 in 20 and a trapezoidal
cross section of 450mm top width and 300mm bottom width. The depth of the
cross drain will be decided by the PWI-In-Charge of the work
(iv) In case of cuttings, side drains must be cleaned. The weeds and plantations on
cuttings up to a height of 1m above rails should also be cleaned.
(v) The ballast in the cribs and shoulders should be profiled and rammed.
Signature of Tenderer(s)/Contractor
SPECIAL CONDITIONS OF CONTRACT (PART-III)
5.1 The work is to be executed with contractor’s own tools and plants, labour
etc. under the supervision and direction of the PWI-In-Charge of work. The
work on track will be started only after the presence of Railway’s
representative at site of work.
5.2 The services of the contractor may be required to assist the Railway
Administration in case of emergencies like derailments. The contractor
should make the assistance available within short notice from the Engineer-
In-Charge or his authorised representative.
5.3 The work is to be carried out under traffic block, if required that will be
arranged by the Railway. However, Railway will not be responsible for idling
men and materials due to non availability of blocks.
5.4 Security deposit will be refunded after successful completion of all works,
settlement of all dues, less debits, if any according to terms and conditions
of contract.
5.5 The rate quoted and accepted by the Railway shall be inclusive all charges
and taxes levied by the Union of India or State Government.
5.6 All the new rails are to be painted before renewal and the payment will be
made under suitable item of SOR 1992.
5.7 After rail renewal, the station No, E.Co. & versine are to be written on web
of rail at curves with contractors materials & labour, for which no extra
payment will be made.
5.8 The maximum value of each work order will be Rs. 2 lakh.
5.9 Normally the value of individual work order will not be less than
Rs.1,00,000/-.
5.10 The date of completion against each work order will be given on the merit
of the case and need not be the last date of completion of the contract
period and the entire work shall be completed in all respects within
30.09.2010.
5.11 In case, the contractor fails to take up or complete the work of any work
order, the Railway will have a right to terminate the contract and invite
fresh tenders as per existing procedure.
5.12 The tenderer(s) can see the Drawings mentioned in Tender schedule
available in Sr.DEN's Office in any of the working days.
5.13 Mainly the work is to be carried out under SE(P.Way)/ KUR. However,
Railway reserves the right to execute part of the work under the
jurisdiction of adjacent PWI's if required.
The above conditions are read, understood and accepted by me/us with the
rates offered by me /us above.
Signature of Tenderer (s)/ Contractor (s)