Upload
andryaas-mamuaya
View
217
Download
0
Embed Size (px)
Citation preview
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 1/26
THE VALUE OF EARNEDVALUE MANAGEMENT
PMI P ittsburgh Chapter Meeting
February 8, 2001
Marilyn McCauley
McManagement Group703-455-0602
703-455-0598 (f)
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 2/26
AGENDA
Twelve Reasons Why Programs FailProgram Management Principles
Earned Value Management’s Role in PMWhat is Earned Value Management
History of Earned Value ManagementThe Value of Earned Value Management
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 3/26
REASONS WHY PROGRAMS FAILJohn Gioia, Robbins Gioio, Inc., PM Network, November 1986
1. Understanding Program Complexity
2. Lack of Management Access and Internal Communication
3. Not Integrating the Key Elements of Project Management
4. No Measurable Controls
5. Requirements Creep
6. Ineffective Implementation Strategy
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 4/26
REASONS WHY PROGRAMS FAIL
7. A Software Tool is Not the Only Answer
8. Different Contractor and Customer Expectation
9. No Shared “Win-Win” Attitude
10. No Formal Project Management Education
11. Lack of Top Management Commitment and Sponsorship
12. Projects Not Viewed as a Business
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 5/26
REASONS WHY PROJECTS FAIL1995 Standish Group Report
1. Incomplete requirements2. Lack of user involvement
3. Lack of resources
4. Unrealistic expectations
5. Lack of executive support
6. Changing requirements and specifications
7. Lack of planning
8. Didn’t need it any longer
9. Lack of IT management
10. Technology illiteracy
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 6/26
PROGRAM MANAGEMENT PROCESSES
Initiating Recognizing that a project or phase should begin
and committing to do so
Planning Devising and maintaining a workable scheme to
accomplish the business need that the project was
undertaken to address
Executing Coordinating people and other resources to carry out
the plan
Controlling Ensuring that project objectives are met by monitoring
and measuring progress and taking corrective actionwhen necessary
Closing Formalizing acceptance of the project or phase and
bringing it to an orderly end
Source: A Guide to the Project Management Body of Know ledge
published by Project Management Institute
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 7/26
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 8/26
Earned Value Management
EVMS fits naturally into the
Project Management Cycle
Initiate
Close out
Control
Execute
Project mana
gement
cycle
Plan
program manager needs
develop a realistic plan ofthe work scope, thebudget, and the schedule
organize the work andthe teams
authorize work properly
control changes understand variances
corrective actions forecast of final cost and schedule
performance reporting
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 9/26
WHAT IS EARNED VALUEMANAGMENT
EVMS IS THE PRIMARY PROJECT MANAGEMENT
TOOL……
THAT INTEGRATES THE TECHNICAL, SCHEDULE, AND
COST OBJECTIVES OF THE CONTRACT OR WORK EFFORT
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 10/26
WHAT IS EARNED VALUE VALUE
A Way To MeasureHow much work should be done?
How much work was completed?
How much did the work cost?How much is the job supposed to cost?
What do we expect the job to cost
A Way To ManageThe best way known to integrate scope, schedules,
Resources and risk management
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 11/26
EVM PROCESSES
• PLAN - The supplier establishes a system to control management processes– An integrated baseline plan is established
- work is defined, scheduled, and resources areallocated
EXECUTE - Work and resources are driven down to lowest level for execution– Budgets are “earned” as work is completed =EARNED VALUE
CONTROL - The system is used to control changes to the baseline
– Status provided against baseline
- schedule and cost variances are isolated
- Problem assistance
- early warning
- corrective plans
- Early insight provided into final estimated cost
- Project manager uses EVMS data to manage and control
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 12/26
FIVE CORE PRINCIPLES
Organize the project team and the scope of work ,using a work breakdown structure. Each task should have a single WBSnumber and organizational code.
Schedule the tasks in a logical manner so that lower level
schedule elements support other elements and the top level milestones.
Allocate the total budget resources to time-phased control
accounts.
Establish objective means for measuring work accomplishment. Budget should be earned in the same way that it wasplanned.
Control the project by analyzing cost and performance variances,
assessing final costs, developing corrective actions, and controlling changes to the
integrated baseline.
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 13/26
1. DEFINE THE WORK AND ORGANIZE TEAMS
Planning is a 3 Step ProcessPlanning is a 3 Step Process
100
40
60
15
25
30
30
2. SCHEDULE THE WORK
3. ALLOCATE BUDGETS
$
CONTRACT BUDGET BASE
TIME
IN
TEGRATED BA
SELINE
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 14/26
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 15/26
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 16/26
Schedule Variance
BC WS
BC WP
of the work I scheduled to have done,how much did I budget for it to cost?
of the work I actually performed,how much did I budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000SV= -$1,000 (negative = behind schedule)
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV $ = BCWP - BCWS
example: SV = BCWP - BCWS = $1,000 - $2,000
SV= -$1,000 (negative = behind schedule)
BUDGET BASE
D
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 17/26
Cost Variance
BC WP
AC WP
of the work I actually performed,how much did I budget for it to cost?
of the work I actually performed,how much did it actually cost?
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400CV= -$1,400 (negative = cost overrun)
COST VARIANCE is the difference between budgeted costand actual cost
formula: CV $ = BCWP - ACWP
example: CV = BCWP - ACWP = $1,000 - $2,400CV= -$1,400 (negative = cost overrun)
PERFORMANCE BASED
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 18/26
Variance at
Completion (VAC)
B ACwhat the total job is supposed
to cost
E AC what the total job is expectedto cost
VARIANCE AT COMPLETION is the difference between what the totaljob is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
VARIANCE AT COMPLETION is the difference between what the total
job is supposed to cost and what the total job is now expected to cost.
FORMULA: VAC = BAC - EAC
Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 19/26
Estimate at Completion (EAC)
defined as actual cost to date + estimated cost of work remaining
supplier develops comprehensive EAC at least annually
• reported by WBS in cost performance report
customer should develop a range of independent EACs for comparison
should examine on monthly basis
consider the following in EAC generation
• performance to date
• impact of approved corrective action plans
• known/anticipated downstream problems
• best estimate of the cost to complete remaining work
WHAT WILL BE THE FINAL
COST?
ACWP + ETC = EAC
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 20/26
Common EAC Formulae:
EAC = BAC
CPI
=ACWPcum + Budgeted Cost of Work Remaining
CPI3
=ACWPcum + Budgeted Cost of Work Remaining
.8(CPI) +.2(SPI)
=
ACWPcum + Budgeted Cost of Work Remaining
CPI * SPI
One method: statistical formulae
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 21/26
THE VALUE OF EARNED VALUEMANAGEMENT
Early and accurate identification of trends andproblems
Accurate picture of project statusCost, schedule and technical
Basis for course correction
Supports mutual goals of supplier and customer
Bring project in on schedule and cost
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 22/26
Why do we need
EVMS?
Course corrections are easierwhen you have time to make
small adjustments
It’s too late when you’re thisclose to the iceberg!
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 23/26
EARNED VALUE EVOLUTION
Dept of Defense Instructions – late 1960’3Cost/Schedule Control Systems Criteria
Financial Management Subculture
Contractor “Validation” Procedures
Evolution in Late 1990’sValue reaffirmed
Industry Ownership
Principles in Federal Policy
Global Acceptance of EVM
Application to DoD In-House Activities
Enterprise-Wide Utilization
Commercial Use
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 24/26
ANSI/EIA-748-1998Earned Value Management Systems
INDUSTRY DEVELOPED GUIDELINES FOR EVALUATION OF SUPPLIER’S SYSTEM
32 Guidelines 1. Organization2. Planning and Budgeting
3. Accounting
4. Analysis
5. Revisions and Access to Data
Standard does not prescribe specific systems, software, orprocedures, only general guidelines
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 25/26
INTERNATIONAL USERS
AUSTRALIA
CANADA
JAPAN
SWEDEN
UNITED KINGDOM
8/7/2019 Earned_Value_Management
http://slidepdf.com/reader/full/earnedvaluemanagement 26/26
REFERENCES
INDUSTRY EVM STANDARD – ANSI/EIA-748-98
www.cpm-pmi.org
www.pmi.org
www.acq.osd.mil/pm
www.deskbook.osd.mil