Upload
trannguyet
View
213
Download
0
Embed Size (px)
Citation preview
Upgrade of the Big Gulch WWTP Oxidation Ditches for Energy Efficiency and Improved
Nitrogen Removal
Authors: Thomas E. Coleman, dTEC Systems
Thomas G. Bridges, Mukilteo Water & Wastewater District
Mukilteo Water & Wastewater District
Bend, Oregon October 24-27, 2010
Introduction
• In 2008 and 2009 the Mukilteo Water and Wastewater District undertook a two phased project to upgrade the Big Gulch WWTP oxidation ditches.
• The project goals included:Improve oxidation ditch loading capacity
Reduce aeration energy costs
Increase nitrogen removal efficiency
2
Olympus Terrace/Big Gulch WWTF HistoryThe original plant, built in 1970, included• coarse bar screening of influent wastewater• one 639,800‐gallon oxidation ditch with two 40 HP brush rotor aerators
• one 58‐foot diameter secondary clarifier, • two 36‐inch diameter screw pumps for RAS pumping
• chlorine injection equipment with no chlorine contact tanks
There were no provisions for handling waste activated sludge.
6
Olympus Terrace/Big Gulch WWTF Upgrades
The first upgrade was completed in 1984 with the addition of a 54‐foot diameter secondary clarifier
A major upgrade completed in 1989 included:•A new headworks with grit removal•A 1.07 million gallon oxidation ditch with four 30 HP brush rotor aerators•One 54‐foot diameter secondary clarifier, •Aerobic Digesters, sludge pumping facilities, and dewatering equipment•Chlorine contact tanks
In 1993 a submersible mixer was added to each ditchIn 2002 the plant converted from chlorine to UV disinfection
7
Design Criteria in the NPDES permit issued in November 2004
11
Average flow for the max. month: 2.61 MGD
BOD5 loading for max. month: 4492 lbs/day
TSS loading for max. month: 3605 lbs/day
This permit expired in November 2009 and has not yet been reissued.
Capacity Study and Engineering Report (Gray & Osborne, March 2008)
13
Influent Loading Trends at MWWD
0
2,000
4,000
6,000
8,000
10,000
1997 1999 2001 2003 2005 2007 2009
Load
ing
Rat
e (lb
s/da
y)
Average Annual BOD5 Average Annual TSSMaximum Monthly BOD5 Maximum Monthly TSS
Capacity Study and Engineering Report
• Intermittent soluble BOD loading spikes in 2006 *
• New sampler revealed TSS loadings much higher than previously measured
• Long‐term trend of increasing loading rates
14
Findings:
Intermittent soluble BOD and TSS loading spikes have continued to the present time (October 2010).
*
Capacity Study and Engineering Report
Report Recommendations:
• Loading source investigations in collection system
• Grit removal improvements
• Activated sludge aeration capacity expansion
• Aerobic digester aeration capacity expansion
15
Activated sludge aeration capacity expansion
1. Aeration system capacity determined to be a limiting factor in establishing the BOD design capacity.
2. Evaluation of aeration system capacity upgrade alternatives:
• Upgrade brush rotor aeration system
• Replace rotors with diffusers and PD blowers
• Replace rotors with diffusers and turbo blowers
16
Evaluation of aeration system capacity upgrade alternatives
The evaluation of aeration system alternatives considered capital and O&M costs.
Incentives payments available from the utility (Snohomish PUD) for improvements which reduce electrical energy consumption and demand.
Other operational factors also considered.
17
Energy Costs at a WWTPAeration accounts for 50-75% of the total energy cost at a municipal wastewater treatment plant.
AerationLightingPumpingHVACMisc.
18
Comparison of Aeration Alternatives
Oxidation Ditch “A” peak energy consumption
19
Parameter Aeration MethodBrush Rotors
Diffused Aeration with
PD Blower
Diffused Aeration with Turbo Blower
Actual Oxygen Demand (lb/day) 4,527 4,527 4,527 Standard Oxygen Demand (lb/day) 6,658 7,611 7,611 Diffuser Air Flow Rate (scfm) N/A 1,300 1,300 Max. Motor Power (hp) 115 60 50 Max. Motor Power (kW) 86 45 37 Power Savings at Max. Load vs. Brush Rotor (%) 48% 57%
Power Savings at Max. Load vs. PD Blower (%) 17%
Comparison of Aeration AlternativesOxidation Ditch “A” annual avg. energy consumption
20
Parameter Aeration MethodBrush Rotors
Diffused Aeration with
PD Blower
Diffused Aeration with Turbo
Blower
Actual Oxygen Demand (lb/day) 2,440 2,440 2,440 Diffuser Air Flow Rate (scfm) N/A 665 665 Average motor power req'd (hp) 58 28 21 Avg. Annual Power Consumption (kWH) 380,000 183,000 137,000 Annual Power Savings (kWh) 197,000 243,000 Annual Power Cost Savings ($) $13,800 $17,000 Annual Power Savings vs. brush rotor (%) 52% 64%Annual Power Savings vs. PD blower (%) 25%
Comparison of Aeration AlternativesOxidation Ditch “A” annual O&M costs
21
Item Quantity Unit Price AmountA. Brush Rotor Alternative
Power 380,000 kWH $0.07 $26,600 Repair and Maintenance 1 LS $2,300 $2,300 Total $28,900
B. Diffused Air with PD Blower AlternativePower 183,000 kWH $0.07 $12,800 Repair and Maintenance 1 LS $2,100 $2,100 Total $14,900
C. Diffused Air with Turbo Blower AlternativePower 137,000 kWH $0.07 $9,600 Repair and Maintenance 1 LS $1,800 $1,800 Total $11,400
Comparison of Aeration Alternatives
Oxidation Ditch “A” lifecycle cost comparison
22
Alternative Total Construction
Cost
Annual O&M Cost Estimate
20-year Net Present Value
Brush Rotor Alternative $261,000 $28,900 $808,000
Diffused Air with PD Blower Alternative $279,000 $14,900 $507,000
Diffused Air with Turbo Blower Alternative $321,000 $11,400 $490,000
Operational Considerations Brush Aerators
23
ProsSimple “In-House” Repair
Submersible Mixer Not Needed
ConsFixed Hydraulic Level
Damages Floc Structure
Lubrication Required
Create Aerosols
Energy inefficient
Difficult to Control D.O.
Noise
Operational Considerations Brush Rotor Aeration Pros and Cons
Operational Considerations Turbo Blower With Fine Bubble
Diffusers
24
ProsHydraulic Level can vary
No Shearing of Floc
No Lubrication Required
Minimal Maintenance
Minimal Aerosols
Energy Efficient
Good D.O. Control
Low Noise
ConsNeeds Submersible Mixer
Proprietary Blower Technology*
Diffuser Inspection/Repair Requires Dewatering of Basin
*(in the case of Turbo Blowers)
Diffused Aeration Pros and Cons
Comparison of Aeration Alternatives• Selected alternative: Diffused air with turbo blower
• Despite higher capital cost, energy efficiency resulted in a payback period of 4 years
• Lowest 20 year lifecycle costs (3% lower than PD blower)
• 65% energy savings compared to brush rotors
• 25% energy savings compared to PD blower
25
Turbo Blower Cutaway View
27
Image courtesy of K-Turbo Inc.
Impeller directly mounted on motor shaftHigh-speed permanent magnet motor (up to 24,000 rpm)
Turbo Blower – Air Foil Bearing
28
Image from:http://www.grc.nasa.gov/WWW/Oilfree/bearings.htm
Turbo Blower Features
• Reduced maintenance: no maintenance required for seals, lubrication, etc.
• Low power at motor start
• Can run unloaded at 1% of rated power
29
Phase I Project
Convert Oxidation Ditch “A” from brush rotor aeration to diffused aeration with a Turbo Blower
30
Electric utility rebate
• Snohomish County PUD No. 1 monitored electricity consumption before and after Ditch “A” project construction
• Rebate for construction costs equal of $0.17/kWH of annual electricity savings
• District received SNOPUD Incentive Rebate of $39,171 for Phase 1
36
Phase II ‐ Conversion of Ditch “B”
• Phase II of the project converted Oxidation Ditch “B” to diffused air with turbo blowers
• 35% reduction in annual energy consumption were estimated for the oxidation ditch system
37
Conversion of Ditch “B”
• Removal of four 30‐hp brush rotors (120 hp total)
• Installation of two additional 50‐hp turbo blowers (one duty, one standby)
• Installation of two new 6‐hp submersible mixers
• Equipment was pre‐purchased
• Construction completed in March 2010
39
dNOx® System for Improved Denitrification
Originally developed under an EPA Small Business Innovation Research (SBIR) Project at the Grand Coulee, WA WWTP.
Patent # 5,582,734 process for oxidation ditch control
Inventors: Coleman, Stensel, Denham, and Fleischman
WAS
Process Flow Schematic for Oxidation Ditch with Cyclic Aerobic/Anoxic Operation
WSEO funded mixer installations in the early 1990s.
The automated anoxic cycle control system was developed during the mid 1990s under an EPA SBIR research contract.
The GC/EC WWTP has consistently achieved energy savings, good total nitrogen removal, and SVI control for over 15 years.
46
dNOx® System Description
• Detects ORP inflection point = reliable detection of nitrate/nitrite depletion in activated sludge processes
• Provides automated aeration control for oxidation ditches and other wastewater treatment processes such as SBRs and Aerobic Digesters
2NH4+ + 3O2
→ 2NO2− +4H+ + 2H2
O (Eq. 1)
Ammonia Oxidizing Bacteria (AOB)
2NO2− + O2
→ 2NO3− (Equation 2)
Nitrite Oxidizing Bacteria (NOB)
NH4+ + 2O2
→ NO3− + 2H+ + H2
OOverall Reaction
Nitrification Fundamentals
48
~ 4.6 lb of O2 required per lb of NH3
-N oxidized
Denitrification
NO3 ̄ → NO2 ̄ → NO → N2 O → N2
C6 H12
O6 + 4.8NO3
- + 4.8H+ → 6CO2 + 2.4N2
+ 8.4H2 O
49
~ 2.9 lb of O2 equivalent per lb of NO3
-N reduced
dNOx® Process Control Algorithm
dNOx control system algorithms utilizes
IEC 61131‐3 Compliant Structured Text and Function block diagrams
The Structured Text uses a syntax similar to the Pascal programming language
52
dNOx® System Benefits• Energy savings
• Reliable effluent nitrogen as low as 5 mg/L
• Quick installation, very little maintenance
• Fully automatic nitrification/denitrification cycles control
• Compatible with multiple wastewater processes
• Improved sludge settling
• Selective pressure against filamentous bacteria growth
• Alkalinity recovery
Nitrogen removal at Big Gulch
During the first 6 months of operation using the dNOx system to control anoxic/aerobic cycling in the oxidation ditches, a number of operational strategies have been evaluated.
Currently the process has been optimized to consistently achieve less than 5 mg/L total inorganic nitrogen.
57
Next Phase of Improvements at the Big Gulch WWTF
The next phase of improvements at the Big Gulch WWTF will include the upgrade of screening and grit removal at the Headworks and increasing the aeration capacity of the Aerobic Digester.A Selector Basin is also being designed into the Headworks upgrade. Depending on the amount of nitrate being returned to the selector it could be anoxic or anaerobic. If anaerobic, we can expect EBPR to occur.
58
Process Flow Schematic of Heyburn, ID WWTP(Recently upgraded to meet new P limits for discharge to the
Snake River)
WAS
59
ConclusionsBlowers and diffused air may be advantageous for oxidation ditch operation:•Significant energy savings•Operational flexibility Turbo blowers may offer further energy savings in comparison with positive displacement blowers.
An ORP based control system optimizing aerobic/anoxic cycling in an oxidation ditch can achieve additional energy savings and improved total nitrogen removal.
61